Installation Guide:
First SolarSingle-Axis
Tracker
Global
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 2/42
REDACTED COPY
Table of Contents1 General Document Overview ...................................................................................................................... 4
1.1 Purpose ......................................................................................................................................... 4
1.2 Scope ............................................................................................................................................ 4
1.3 Notice ........................................................................................................................................... 5
1.4 Safety Symbols and Signal Words ................................................................................................. 6
1.5 Common Terms ............................................................................................................................ 7
1.6 Key Definitions .............................................................................................................................. 7
2 Tracker System Installation Overview......................................................................................................... 8
2.1 Tracker System Components Overview ........................................................................................ 8
2.2 Component Installation Sequence ............................................................................................. 10
2.3 Recommended Component On-Site Storage ............................................................................. 10
3 Tracker Assembly Installation ................................................................................................................... 11
3.1 Tracker Installation Drawings ..................................................................................................... 11
3.2 Tracker Assembly Images ........................................................................................................... 11
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 3/42
REDACTED COPY
5.1 Wire Management Drawings ...................................................................................................... 27
5.2 Controller to Actuator Cable Packaging...................................................................................... 27
5.3 Controller to Actuator Cable Labeling ........................................................................................ 28
5.4 Controller to Actuator Cable Connections to Tracker Controller ............................................... 29
6 Tracker Gateway Installation .................................................................................................................... 30
6.1 Tracker Gateway Physical Installation ........................................................................................ 30
6.2 Tracker Gateway Electrical Installation ...................................................................................... 31
6.3 Tracker Gateway Communication Installation ........................................................................... 31
7 Tracker Weather Station Installation ........................................................................................................ 32
7.1 Tracker Weather Station Physical Location ................................................................................ 32
7.2 Tracker Weather Station Electrical Installation .......................................................................... 34
7.3 Tracker Weather Station Communication Installation ............................................................... 34
8 Tracker Backup Power System Installation (optional) .............................................................................. 35
9 Commissioning .......................................................................................................................................... 36
10 Warranty Terms & Conditions .................................................................................................................. 37
11 Appendices................................................................................................................................................ 38
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 4/42
REDACTED COPY
1
General Document Overview
1.1 Purpose
This Installation Guide: First Solar Single-Axis Tracker (PD-6-202) is intended to provide information
concerning installation of First Solar’s single-axis tracker system in a photovoltaic power plant site. This
document may be used to plan installation of tracker system components, including developingresource estimates for installation of the tracker system components.
Failure to install, commission, operate and maintain First Solar’s tracker system in the manner described
below will void the applicable warranty (refer to the First Solar Single-Axis Tracker Warranty Terms And
Conditions (PD-5-120)).
1.2
Scope
This document is not intended to:
1.
Be a substitute for site specific drawings that details the installation.
2.
Provide details of the tracker system that may be required for permitting purposes.
3.
Suggest any unsafe installation practices.
4.
Provide guidance for designing a photovoltaic power plant incorporating the First Solar’s tracker
system. (See the Application Manual First Solar Single-Axis Tracker (PD-6-241) for design
guidance.)
5.
Provide guidance for commissioning the First Solar Tracker Product. (See the Commissioning
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 5/42
REDACTED COPY
1.3 Notice
Changes to certain Tracker System Components are common as First Solar continuously strives for
product improvements. All products within the same model classification remain functionally
equivalent and compatible with one another, even though there may be slight differences.
Modifications that do not impact product functionality may be made without notification.
First Solar reserves the right to make changes to design or specifications applicable to the First Solar
Single-Axis Tracker at any time without notice. Accordingly, the Buyer is responsible for verifying that
data sheets are current before placing orders or finalizing system permitting and/or design. Neither
First Solar nor its affiliates assume any responsibility for use of information furnished by First Solar or its
affiliates, nor for any infringements of patents or other rights of third parties that may result from the
use of such information. No license is granted by implication or otherwise under any patent or patent
rights of First Solar or its affiliates.
For information regarding First Solar and its products, please visit www.firstsolar.com. For technical
support, please contact [email protected].
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 6/42
REDACTED COPY
1.4
Safety Symbols and Signal Words
Indicates a safety hazard or unsafe practice.
Indicates an electrical shock hazard.
DANGER Indicates a hazardous situation that, if not avoided, will result in death
or serious injury.
WARNING Indicates a hazardous situation that, if not avoided, could result in
death or serious injury.
CAUTION Indicates a hazardous situation that, if not avoided, could result in
minor or moderate injury.
NOTICE Indicates information considered important, but not hazard-related
(e g messages relating to property damage)
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 7/42
REDACTED COPY
1.5
Common Terms
Terms Found In Site Drawings (colloquial) Equivalent Meaning (proper name)
actuator control cable controller to actuator cable
anemometer weather station
anemometer control panel weather station enclosure
battery backup power backup power system
cable wire, wiring
gateway controller gateway enclosure
gateway control panel gateway enclosure
gateway tracker control panel gateway enclosure
longitudinal retention plates longitudinal retainers
MIB module interface bracket
post pile
TIB table interface bracket
tracker anemometer tracker weather stationtracker control unit tracker controller
tracker main beam torque tube
Table 1.List of items that may be found in site design drawings and their corresponding correct definitions or equivalents.
1.6
Key Definitions
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 8/42
REDACTED COPY
2
Tracker System Installation Overview
2.1 Tracker System Components Overview
A high level overview of the Tracker System Components can be found in Figure 1. A description of the
Tracker System Components’ functions and typical quantities can be found in Table 2.
Figure 1. Diagram of Tracker System Components.
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 9/42
REDACTED COPY
Component Function Typical Quantity
Trackerassembly
Structure and mechanism that hold and point modules in thedirection of the sun (includes the actuator, table, bearings and
torque tube). Each tracker assembly holds 60 First Solar
modules.
270 to 360tracker assembliesper array. Example: 326
tracker assemblies in a 1.956
MWdc array (assuming 100 W
First Solar module)
tracker
controller
The system “brain”. The tracker controller positions trackers at
the appropriate angle based on local conditions (time, date,
wind, and user input), and provides status of trackers to the
gateway.
24 to 39tracker controllers per
array.
Tracker
gateway
The main communication hub to tracker controllers, weather
stations, backup power system, and SCADA system. The tracker
gateway aggregates data for tracker controllers of each array
and converts this data into information that is comprehensible
to the SCADA system. The tracker gateway will receive and
process information from the tracker weather stations and the
backup power systems.
1 to 3tracker gateways per
array.
Tracker
weatherstation
Collects weather information from the anemometer sensors
and broadcasts weather information over the network to thetracker gateways.
2 to 8 tracker weather stations
per project site.
(optional)
backup
power
system
(BPS)
The backup power system passes grid supplied power through
to trackers until a power outage occurs, at which time it
switches to battery backup. Included in the system are the
necessary inverters/charger and batteries. This system is
optional.
0 to 1 backup power system
per array.
Table 2. Overview of Tracker System Component function and typical quantity. See Application Manual First Solar Single-
Axis Tracker (PD-6-241)for more information about quantities.
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 10/42
REDACTED COPY
2.2
Component Installation SequenceInstallation of tracker assemblies involves following the general sequence of steps described in Section
3. Other system components (such as the tracker controllers, the tracker gateways, the backup power
systems, and the tracker weather stations) may all be installed in parallel to the tracker assemblies.
Once tracker assemblies are structurally complete, and the tracker controllers are installed, complete
installation of the controller to actuator cables is possible.
CAUTION Trackers shall not be considered commissioned and released for operation
until they are able to communicate with an active tracker weather station. Until that
time, trackers may generate power but must remain near or at a flat orientation
(±7.5°).Without an active tracker weather station, the trackers may not be able to
accommodate the design wind loads at extreme tilt angles.(See the Commissioning
Manual: First Solar Single-Axis Tracker (PD-6-234).)
2.3 Recommended Component On-Site Storage
First Solar recommends storing the following items indoors (prior to installation): node assembly
SD card
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 11/42
REDACTED COPY
3
Tracker Assembly Installation
3.1 Tracker Installation Drawings
Any drawing set for tracker assembly provided by First Solar will specify torques ranges for fasteners,
and tolerances for component locations, and will remain subject to updates. For the remainder of thisdocument, such drawing set will be referred to as the “Tracker Installation Drawings”. It is the Buyer’s
responsibility to obtain the most current drawing set for accurate information and ensure the most
current version is used.
3.2 Tracker Assembly Images
Figure 2 through Figure 10show photo images of the major tracker assembly components.
(Image Redacted)
Figure 2. Bearing assembly with view of adjustment capability. The torque tube fits into the square slot.
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 12/42
REDACTED COPY
(picture redacted)
Figure 3. Torque tube highlighted in red; pile highlighted in green; bearing assembly circled in yellow.
Figure 4. Torque tube interface bracket.
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 13/42
REDACTED COPY
(Image Redacted)
Figure 5. Actuator arm.
(Image Redacted)
Figure 6. Actuator highlighted in red, and lower actuator mount highlighted in green. The linear actuator is shown in full
extension. The lower actuator mount attaches to the pile and connects to the linear actuator’s trunnions.
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 14/42
REDACTED COPY
Figure 7. Torque tube and table interface brackets (TIBs); TIBs highlighted in red. TIBs and tables (Configuration A) are an
alternative to MIBs.
(Image Redacted)
Figure 8. Table highlighted in red. TIBs and Tables (Configuration A) are an alternative to MIBs.
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 15/42
REDACTED COPY
Figure 9. Module interface brackets (MIBs). MIBs (Configuration B) are an alternative to TIBs and tables.
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 16/42
REDACTED COPY
3.3
Tracker Assembly Installation Warning, Caution and NoticeStatements
WARNING Wear electrically rated PPE when working on interconnected
modules or other electrical system components.
WARNING Wear appropriate safety helmets and safety glasses (ANSI Z87.1-
2003) during installation of tracker assembly. Take appropriate precautions
when reaching overhead during torque tube installation.
CAUTION Installation is to be performed only by qualified personnel.
CAUTION First Solar’s Single-Axis Tracker should be installed according to
project site drawings.
CAUTIONDO NOT disassemble any of the bearing assemblies; assemblies are
pre-assembled and tightened to factory-specified torque, and are to be fixed
to vertical posts AS-IS. Lateral adjustments are acceptable where necessary.
CAUTIONDO NOT use bolts that have been previously tightened or pre-stressed bolts that are structurally compromised and will not retain their
strength if recycled.
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 17/42
REDACTED COPY
NOTICE
For maximum performance, the actuator will arrive pre-calibrated from the factory
and must be installed AS-IS to allow the First Solar’s Single-Axis Tracker to track the
sun within its specified range of motion. Install top actuator bolt first and bottom
mount last.
DO NOT remove the seal from the actuator shaft. DO NOT rotate the
actuator shaft.
DO NOT modify the actuator in any way.
Failure to comply with the above will result in voiding of the applicable
warranty, i.e., warranty provided pursuant to the First Solar Single-Axis
Tracker Warranty Terms And Conditions.
3.4 Tracker Assembly Installation Tips
Alignment of posts and bearings is a priority (slots allow precise install). Torque fasteners to proper specifications and orientation. (See relevant Tracker Installation
Drawings).
Lubricated nuts (indicated by blue or green colored wax) and non-lubricated nuts have different
torque specifications. (See relevant Tracker Installation Drawings).
The shorter of the two torque tubes must be paired with the actuator on any given tracker.
Each tracker has two torque tubes and four bearings. The two torque tubes must be situated in the
same orientation across the four bearings. If the orientation is clocked incorrectly, the tracker will
not operate correctly. See the Figure 11, section (a), for incorrect installation and Figure 11, section(b), for correct installation of torque tubes in bearings.
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 18/42
REDACTED COPY
3.5
Suggested Material Staging for Tracker AssemblyFigure 12shows suggested staging of materials for tracker assembly installation. In Figure 12, “Core”
refers to the lower actuator mount, actuator, bearing assembly, and actuator arm, collectively. “Drive”
refers to a path that may be taken by a skid steer or forklift in distributing components prior to
installation. The diagram only shows a portion of an array. The remainder of the array could follow a
similar staging pattern.
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 19/42
REDACTED COPY
3.6
Suggested Workflow for Tracker AssemblyFigure 13, Figure 14, and Figure 15 provide a suggested workflow for assembly of the tracker. As shown
in each figure, steps such as installation of the bearings with or without the lower mount can be done in
parallel. Figure 14 and Figure 15 contain details for installation of configurations A and B.
(Image Redacted)
Figure 13. Suggested workflow for tracker assembly.
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 20/42
REDACTED COPY
(Image Redacted)
Figure 14. Suggested workflow for tracker assembly. Configuration A uses TIBs and tables. Configuration B uses MIBs.
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 21/42
REDACTED COPY
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 22/42
REDACTED COPY
3.7 Specialized Tools for Tracker Assembly Installation
Several tools are useful and recommended to render tracker assembly installation more efficient and/or
safe. These tools are summarized in Table 3. Figure 16 through Figure 20provide some images of these
tools.
Tool Purpose
lower mount spacer Locates lower actuator mount relative to the bearing.
joystick Control of the actuator without a tracker controller.
MIB installation jig Spacing tool that enables proper positioning of MIBs on torque tube.
actuator arm installation tool Proper centering of actuator arm around the bearing assembly.
actuator replacement kit Enables safe replacement of an actuator.
Table 3. Summary of tools useful for tracker assembly
Figure 16. Lower mount spacer dimensions dictated by Tracker Assembly Prints. This tool is not provided by First Solar but
can be fabricated by construction team.
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 23/42
REDACTED COPY
Figure 18. MIB installation jig (if configuration B is implemented).
Figure 19. Actuator arm installation tool (if configuration B is implemented).
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 24/42
REDACTED COPY
4
Tracker Controller Installation
4.1 Tracker Controller Physical Installation
NOTICE
If distance between top of tracker controller enclosure and the top of the pile the
tracker enclosure is mounted on is less than 8 inches, it may interfere with thetracker and movement and damage the tracker assembly.
NOTICE
If tracker controller enclosure is mounted below the 100-year flood level, then the
controller could become partially submerged during storm conditions and be
damaged.
The First Solar tracker controller is intended to be mounted on an I-Beam at a minimum of 1 ft above
grade (or 1 ft above 100-year flood level, whichever is higher). The top of the First Solar tracker
controller must be a minimum of 8 inches from the top of the pile to clear the tracker assembly. Follow
NEC 110.26 guidelines for working space around the tracker. In general this is 30 inches wide, 78 inches
high and 36 inches to 48 inches deep (76 cm x 198 cm x 91 to 122 cm).
See Appendix A and Appendix B for the two possible mounting configurations of the tracker controller.
Figure 21 shows a fully installed tracker controller.
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 25/42
REDACTED COPY
4.2 Tracker Controller Electrical Installation
DANGER Tracker controller enclosure must be properly grounded to avoid death or
serious injury due to electric shock.
At the end of physical installation, the tracker controller shall be provided by Buyer with an approved
conduit and shall be permanently connected to a protected branch main supply that is properly
grounded.
The wiring to provide power to the tracker controller shall comply with the national regulations of the
countries in which the appliance is to be sold.
The electrical supply provided by Buyer shall be equipped with a disconnect device to disconnect all
ungrounded AC lines. Buyer should follow standard lockout/tagout procedures for all servicing.
The tracker controller may be shipped without a cutout for AC mains input. It is the electrician’s
responsibility to cut the appropriate sized hole for the conduit in use and to plug unused cutouts with a
NEMA 4 approved hole plug.
Conduit fittings provided by Buyer shall be installed in the end-use application per local electrical codes.
Buyer will install such conduit fittings in such a manner as to not compromise the NEMA 4 ingress
protection rating of the system.
The AC input terminal block contains two each of Black, White, and Green terminal blocks. Black is for
the live voltage, white is neutral and green is earth ground. The pairs of terminal blocks are jumpered
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 26/42
REDACTED COPY
5
Controller to Actuator Cables (CTAC) Installation
5.1 Wire Management Drawings
Any drawing set for the tracker assembly wire management provided by First Solar will include specific
wire management component location detail on the tracker assembly and will remain subject to
updates. For the remainder of this document, such drawing set will be referred to as the “Tracker Wire
Management Drawings”. It is the Buyer’s responsibility to obtain the most current drawing set for
accurate information and ensure the most current version is used.
5.2 Controller to Actuator Cable Packaging
The CTACs will be delivered to Buyer in kits containing up to 12 cables. The CTACs will connect thetracker controllers to the actuators. One tracker controller may control up to 12 actuators. Each tracker
assembly will have one actuator. Some tracker controllers will control fewer than 12 actuators. For
such cases, extra cables not used in the kits can be set aside as spares. In some instances, it may be
possible to use a longer cable to replace a shorter one. For example, a 90 foot long cable can be used as
a spare for a 60 foot long cable if the extra slack can be appropriately looped and attached properly.
Figure 22 shows the typical numbering scheme for actuators found in the site design drawings. The
specific numbering scheme is found in the site design drawings.
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 27/42
REDACTED COPY
5.3 Controller to Actuator Cable Labeling
The CTACs will be labeled on each end with part number and suffix. The suffix which is the last two
numbers on the label will provide information about the cable length. Multiplying the number by 15 will
provide the length of the cable (see Table 4). For example: the cable labeled 20-00528-07 will be 105
feet long (7 × 15 = 105).
length (ft.)
20-00528 -01 15
20-00528 -02 30
20-00528 -03 45
20-00528 -04 60
20-00528 -05 75
20-00528 -06 90
20-00528 -07 105
20-00528 -08 120
20-00528 -09 135
20-00528 -10 150
20-00528 -11 165
20-00528 -12 180
20-00528 -13 195
20-00528 -14 210
20-00528 -15 225
20-00528 -16 240
20-00528 -17 255
Cable part number label
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 28/42
REDACTED COPY
5.4 Controller to Actuator Cable Connections to Tracker Controller
The CTACs are connected to the tracker controller on the outside of the tracker controller (see Figure
21). Figure 23provides a closer view of where the controller to actuator cables connect to the tracker
controller. On the inside of the tracker controller enclosure, the surge suppressor board (the blurred
out portion of the image) has the actuator channels numbered from A0 to A11, with the first actuator
starting at A0 or “Actuator 1” as shown in Figure 23. The site specific prints may have actuators
numbered according to Figure 22and therefore should be connected according to Figure 23.
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 29/42
REDACTED COPY
6
Tracker Gateway Installation
6.1 Tracker Gateway Physical Installation
NOTICE
If tracker gateway is mounted below the 100-year flood level, then the tracker
gateway could become partially submerged during storm conditions and be damaged.
The tracker gateway is intended to be mounted on an I-Beam at a minimum of 1 ft above grade (or 1 ft
above 100-year flood level, whichever is higher) using provided mounting kit.
See Appendix C for mounting configuration.
Figure 24 shows a fully installed tracker gateway.
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 30/42
REDACTED COPY
6.2 Tracker Gateway Electrical Installation
DANGER Tracker gateway enclosure must be properly grounded to avoid death or
serious injury due to electric shock.
At the end of physical installation, the tracker gateway shall be provided by Buyer with an appropriately-
sized conduit and shall be permanently connected to a protected branch main supply that is properlygrounded.
The electrical supply wiring to the tracker gateway shall comply with the national regulations of the
countries in which the appliance is to be sold.
The electrical supply provided by Buyer shall be equipped with a disconnect device to disconnect all
ungrounded AC lines. Buyer should follow standard lockout/tagout procedures for all servicing.
The tracker gateway may be shipped without a cutout for AC mains input. It is the electrician’s
responsibility to cut the appropriate sized hole for the conduit in use and to plug unused cutouts with aNEMA 4 compliant hole plug.
Conduit fittings provided by Buyer shall be installed in the end-use application per local electrical codes.
Buyer will install such conduit fittings in such a manner as to not compromise the NEMA 4 ingress
protection rating of the system.
The AC input terminal block contains two each of black, white, and green terminal blocks. Black is for
the live voltage, white is neutral and green is earth ground. The pairs of terminal blocks are jumpered
together to facilitate continuing AC wiring to the next device on the circuit (if any).
6 3 T k G t C i ti I t ll ti
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 31/42
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 32/42
REDACTED COPY
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 33/42
REDACTED COPY
7.2 Tracker Weather Station Electrical Installation
DANGER Tracker weather station enclosure must be properly grounded to avoid
death or serious injury due to electric shock.
At the end of physical installation, the tracker weather station shall be provided by Buyer with an
appropriately-sized conduit and shall be permanently connected to a protected branch main supply that
is properly grounded.
The electrical supply wiring to the tracker weather station shall comply with the national regulations of
the countries in which the appliance is to be sold.
The electrical supply provided by Buyer shall be equipped with a disconnect device to disconnect all
ungrounded AC lines. Buyer should follow standard lockout/tagout procedures for all servicing.
The tracker weather station may be shipped without a cutout for AC mains input. It is the electrician’s
responsibility to cut the appropriately-sized hole for the conduit in use and to plug unused cutouts with
a NEMA 4 compliant hole plug.
Conduit fittings provided by Buyer shall be installed in the end-use application per local electrical codes.
Buyer will install such conduit fittings in such a manner as to not compromise the NEMA 4 ingress
protection rating of the system.
The AC input terminal block contains two each of black, white, and green terminal blocks. Black is for
the live voltage, white is neutral and green is earth ground. The pairs of terminal blocks are jumpered
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 34/42
REDACTED COPY
8
Tracker Backup Power System Installation (op-tional)
Details for installation of the Tracker Backup Power Systems can be found in the installation sections of
the User Guide: First Solar Single-Axis Tracker Backup Power System (PD-6-205).
Figure 26 shows a typical installation of the BPS. This system is optional.
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 35/42
REDACTED COPY
9
Commissioning
Detailed guidance for commissioning the tracker system is found in Commissioning Manual: First Solar
Single-Axis Tracker (PD-6-234). Commissioning activities with the Tracker System may begin prior to
module installation or delivery of grid power to the project site.
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 36/42
REDACTED COPY
10
Warranty Terms & Conditions
Please refer to, First Solar Single-Axis Tracker Warranty Terms and Conditions (PD-5-120) for warranty
terms, limitations, and product return policies.
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 37/42
REDACTED COPY
11
Appendices
Appendix A. Interface, Tracker Controller with Channel to Pile Flange 38
Appendix B. Interface, Tracker Controller with Channel to Pile 39
Appendix C. Kit, Interface, Gateway to Pile 40
Appendix D. Kit, Tower, Weather Station 41
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 38/42
www.firstsolar.com © Copyright 2014, First Solar, Inc. | PD-6-202 | REV 1.0 | Installation Guide: First Solar Single-Axis Tracker |Page 38 of 42
REDACTED COPY
Appendix A. Interface, Tracker Controller with Channel to Pile Flange
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 39/42
www.firstsolar.com © Copyright 2014, First Solar, Inc. | PD-6-202 | REV 1.0 | Installation Guide: First Solar Single-Axis Tracker |Page 39 of 42
REDACTED COPY
Appendix B. Interface, Tracker Controller with Channel to Pile
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 40/42
www.firstsolar.com © Copyright 2014, First Solar, Inc. | PD-6-202 | REV 1.0 | Installation Guide: First Solar Single-Axis Tracker |Page 40 of 42
REDACTED COPY
Appendix C. Kit, Interface, Gateway to Pile.
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 41/42
www.firstsolar.com © Copyright 2014, First Solar, Inc. | PD-6-202 | REV 1.0 | Installation Guide: First Solar Single-Axis Tracker |Page 41 of 42
REDACTED COPY
Appendix D. Kit, Tower, Weather Station
7/21/2019 PD-6-202 Installation Guide First Solar Single-Axis Tracker
http://slidepdf.com/reader/full/pd-6-202-installation-guide-first-solar-single-axis-tracker 42/42
REDACTED COPY
Appendix D. Kit, Tower, Weather Station (continued)