PCR EVALUATION NOTE FOR PUBLIC SECTOR OPERATIONS · of the Government of Ghana namely, the Ghana...
Transcript of PCR EVALUATION NOTE FOR PUBLIC SECTOR OPERATIONS · of the Government of Ghana namely, the Ghana...
1. BASIC INFORMATION
a. Basic project data
Project title: Export Marketing and Quality Awareness Project (EMQAP)
Project code: P-GH-AA0-027 Instrument number(s): 2100150010245
Project type: Lending Sector: Agriculture & Agro-industry
Country: Ghana Environmental categorization (1-3):2
Processing Milestones Key Events Disbursement and Closing date
Date approved: 13 July 2005 Cancelled amount: NIL Original disbursement deadline: 31 March 2012
Date signed: 29 July 2005 Supplementary financing: NIL Original closing date: 31
December 2011
Date of entry into force: 24
March 2006
Restructuring: Revised disbursement deadline: 31
March 2014
Date effective for 1st
disbursement: 31 May 2006
Extensions (specify dates): Once (from
31 December 2011 to 30 December 2013
Revised closing date: 30
December, 2013
Date of actual 1st: 8 December
2006
b. Financing sources
Financing source/ instrument
(MUA)
Approved amount
(MUA) :
Disbursed amount
(MUA) :
Percentage disbursed
(%):
Loan: 17.00 14.98 88.14
Government: 1.84 1.07 58.21
Other (ex. Co-financiers):
TOTAL: 18.84 16.06 85.22
Co-financiers and other external partners:
Execution and implementation agencies:
c. Responsible Bank staff
Position At approval At completion
Regional Director
Sector Director
Sector Manager
Task Manager
Alternate Task Manager
PCR Team Leader
PCR Team Members
d. Report data
PCR Date: 31 May 2014
PCR Mission Date: From: 7 April 2014 To:22 April 2014
PCR-EN Date:
Evaluator/consultant: Tesfaye Teklu Peer Reviewer/Task Manager:
PCR EVALUATION NOTE FOR PUBLIC SECTOR OPERATIONS
2. PROJECT DESCRIPTION
The African Development Bank approved financing the Export Marketing and Quality Awareness
Project (EMQAP in July 2005. The Government of Ghana and the Bank signed the loan agreement in
July 2005, and committed to implement it over a period of five years. The purpose of the project was to
increase incomes of horticulture crop farmers and exporters in four Regions (Central, Eastern, Greater
Accra and Volta), and thereby improve the export earnings of the country. EMQAP started operation in
May 2006 and completed in December 2011, after a nearly two-year extension.
a. Rationale and expected impacts:
Ghana has a comparative advantage in production of non-traditional horticulture crops. However,
several factors constrain the production and marketing of these crops. The thrust of the project was to
address these constraints through production and productivity enhancement; export market promotion
and infrastructure improvement; and capacity building, mainly through training in good agricultural
practices. The expected impacts of the project were to increase incomes of horticulture crop farmers and
exporters, and consequently improve their living conditions (i.e. reduce rural poverty).
b. Objectives/Expected Outcomes:
The sector goal of the project was to increase export earnings from non-traditional agricultural products.
The specific objective was to increase incomes of horticulture crop farmers and exporters in four
Regions (Central, Eastern, Greater Accra and Volta). The expected outcomes were increased
participation in horticulture crop production for export, adoption of improved agricultural practices and
technology, increased profitability from improvements in productivity and value addition, and improved
living conditions (i.e. reduced household poverty). The target beneficiaries were mainly members of the
associations for horticultural export crops (SPEG, VEPEAG and FAGE) who comprise nucleus farmers
and smallholder out-growers linked to the nucleus farmers.
c. Outputs and intended beneficiaries:
The following were the key outputs expected to contribute to the expected outcomes by component:
Component 1: Production and Productivity Enhancement (demonstration centers established, GAP
manual and guidelines published and distributed, and improved seeds and planting material produced
and disseminated).
Component 2: Export market promotion and infrastructure improvement (one study on local and
regional, feeder roads built, pack houses constructed, temperature controlled trucks procure; small dams
built, and one laboratory constructed).
Component 3: Capacity building (farmer groups formed, beneficiaries trained in good agricultural
practices (GAP), agricultural professional staff trained in GAP, export traders trained, and executives of
farmer groups and private sector trained in export documentation, financing and business management).
Component 4: Project management (project implementation unit strengthened through technical,
institutional and logistic support).
d. Principal activities/Components:
The project was designed to achieve its expected outputs, outcomes and project objectives through the
following components and associated activities:
Component 1: Production and Productivity Enhancement (establishment of demonstration centers;
production, publishing and distributing GAP manual; and production and dissemination of improved
seeds and planting material).
Component 2: Export market promotion and infrastructure improvement (study on local and regional
markets for horticultural crops undertaken; construction/maintenance of feeder roads; construction of
pack houses, construction of laboratory; and building small dams).
Component 3: Capacity building (sensitization and formation of farmer groups; training of farmers in
good agricultural practices (GAP); training of agricultural professional staff in GAP; training of export
traders; and training of executives of farmer groups and private sector in export documentation,
financing and business management).
Component 4: Project management (strengthening project implementation unit through technical,
institutional and logistic support).
3. PROJECT PERFORMANCE ASSESSMENT
RELEVANCE
a. Relevance of the project development objective:
EMQAP sought to contribute towards Ghana's economic growth and poverty reduction through
increased non-traditional agricultural products for both domestic and export markets. Its specific
objective was to increase incomes of horticulture crop farmers and exporters in four Regions (Central,
Eastern, Greater Accra and Volta).
The project objective remained consistent from appraisal to completion with the main policy documents
of the Government of Ghana namely, the Ghana Poverty Reduction Strategy (GPRS for XX ), the
Ghana Shared Growth and Development Agenda (GSGDA for 2010-2013), the Food and Agricultural
Sector Development Policy (FASDEP I and II) and the Medium Term Agricultural Sector Investment
Plan (METASIP for 2011-2015).
The alignment is evident, for example, in the following policy statements/guidelines:
Promote the development of selected traditional and exotic vegetables for exports
Identify successful lead firms with access to assured export markets and apply viable model(s) of
linkage with smallholders
Facilitate the training of out-grower farmers on all the processors required under GAP (Good
Agricultural practices) with emphasis on the harvesting and handling of horticultural crops and
exotic vegetables
Promote formation of viable farmer groups and Farmer-Based Organisations to enhance their
knowledge, skills, and access to resources along the value chain, and for stronger bargaining
power in marketing
Provide relevant technology, market infrastructure (cold chain), and financing to enable
operators to respond to the changing needs of markets
Develop standards and promote good agricultural practices along the value chain (including
hygiene, proper use of pesticides, grading, packaging, standardisation)
Encourage partnership between private sector and District Assemblies to develop trade in local
and regional markets
Build capacity and adequately resource relevant stakeholders for international trade negotiations
The project was also consistent with the Bank’s strategy as outlined in the existing Country Strategy
Paper as well as with the Bank’s Agriculture Sector Strategy (AgSS) 2010-2014 and Ten Year Strategy
(TYS) 2013-2022.
Beneficiaries (horticultural farmers) who were interviewed during the Project Results Assessment
(PRA) Mission also confirmed the relevance of the EMQAP objectives to their needs.
In agreement with the PCR, the PCREN rates the relevance of the EMQAP objective highly satisfactory
(4) -- it was aligned with Ghana’s development policies and strategies, the Bank’s sector strategies and
the beneficiary needs throughout of the project cycle.
b. Relevance of project design (from approval to completion):
The appraisal report establishes the rationale and the logic of the export marketing and quality
awareness project (EMQAP). Ghana has a comparative advantage in production of non-traditional
horticulture crops such as pineapple, papaya, mangoes, and vegetables. However, several factors
constrain the production and marketing of these crops (insufficient quantity and quality of production
inputs, limited applications of improved knowledge and technology, high cost of transport, and
undeveloped marketing and processing value chains). The thrust of EMQAP was to address these
constraints through three pillars, namely: (1) production and productivity enhancement; (2) export
market promotion and infrastructure improvement; and (3) capacity building, mainly sensitization and
training in good agricultural practices.
The project design involved intensive consultations with the operators in the industry, farm communities
and donors financing the sector. The Bank’s experience in implementing its projects and the experience
from other donor-funded projects in Ghana also influenced the design of the project. However, as
evident in the quality of entry and implementation effectiveness, there were design deficiencies related
to incomplete/incorrect assumptions (e.g. inadequate capacities to meet loan effectiveness conditions,
and incorrect assumption about the availability of water for irrigation for demonstration centers), and
inadequate risk assessment and hence lack of inbuilt appropriate mitigation measures in the project
design. The project responded to these inadequacies through restructuring and modifications during the
implementation phase.
Overall, the PCREN considers the design was relevant at appraisal but adjustments were required in
scope and key activities during the implementation phase, which were done satisfactorily (e.g.
discontinuation of the cassava component of the project, and discontinuation of farmer group formation
to avoid duplications). PCREN rates design relevance 3 (satisfactory), a downgrade to the PCR rating
of 4 (highly satisfactory).
EFFECTIVENESS
c. Effectiveness in delivering outputs:
The project achieved the following key outputs by component with ratings of their performance (relative
to targets set at appraisal):
Component 1: Production and Productivity Enhancement
Establishment of Demonstration Centres (DCs), 4 (100%).
Publication and distribution of guides and GAP manual, 43,000 (143%)
Production & Dissemination of improved seeds & planting material, variable by crop but
average performance rate was 104.6%
All four (4) demonstration centres programmed for establishment as centres for the dissemination of
Good Agricultural Practices were duly set up and fitted with requisite equipment and tools. A total of
43,000 production guides and manuals were developed and distributed to various actors of the industry
over the project implementation period to enhance horticultural technology dissemination to farmers. In
addition, 484,000 MD2 suckers and 364,000 smooth cayenne suckers were produced and distributed to
farmers in response to change in varietal demand in export markets.
Component 2: Export market promotion and infrastructure improvement
Study on local and regional markets for horticultural crops, 1 (100%)
Infrastructure –feeder roads, 181.45 km (44.5%)
Infrastructure –pack house, 1 (25%)
Infrastructure –demonstration centers, 4 (100%)
Infrastructure –small dams, 4 (100%)
Infrastructure –laboratory, 1 (100%)
Procurement of temperature controlled trucks, 2 (100%)
Under the Export Marketing and Infrastructure Improvement Component, a study on local and regional
markets for horticultural crops was successfully conducted, and the study identified a large potential
market for horticultural crops produced in Ghana. Following a downward revision of the original target
for feeder road rehabilitation from 407km to 207.10 km, 181.45km of roads was successfully
constructed. Only one of the four planned pack houses were constructed. Two trucks (One 20-tonner
and one 10-tonner temperature controlled trucks) were procured for SPEG (Sea-Freight Pineapple
Exporters of Ghana) and VEPEAG (Vegetable Producers and Exporters Association of Ghana). One
residue analysis laboratory was constructed for the Ghana Standards Board
Note the significant of the construction of pack house and acquisition of temperature controlled trucks
for enhancing cold chain infrastructure in the project’s catchment areas. Improved road infrastructure
coupled with the cold chain infrastructure are significant for improved value chain of high perishable
produce.
Component 3: Capacity building
Sensitization and mobilisation of farmers into groups, 30,000 (37.5%).
21,134 beneficiaries trained in good agricultural practices (260%), female (21%)
1471 agricultural extension agents and District Crop Officers (DCOs) were trained in GAP in
pineapple, mango, citrus and vegetable production (122%), female (20%)
130 export traders trained (11%), female (30%)
About 980 executives of farmer groups and private sector actors were trained in export
documentation, financing and business management, female (17%)
Under the Capacity Building component, the mobilisation of farmers into groups discontinued to avoid
redundancy with another Government of Ghana project. The targeted numbers of beneficiaries
earmarked for training exceed the appraisal targets except for the training of export trade services staff
which recorded only 10.8%. A total of 5333 horticultural farmers were sensitised on HIV/AIDS, whilst
a further 6200 farmers benefitted from sensitisation on malaria prevention.
Overall, the project took longer than the planned timeframe but largely achieved its planned outputs at
project closure albeit its notable under achievements in construction of feed road and pack houses for
budgetary reason. PCREN nevertheless rates 3 (satisfactory) in line with the PCR.
d. Effectiveness in delivering outcomes:
EMQAP was expected to contribute to the attainment of the sector goal of increasing export earnings
from non-traditional agricultural products by 50%. But the increase was modest (14.3%).
The PCR reported considerable increases in household incomes of horticulture crop farmers at project
closure (increase in annual household gross incomes of pineapple farmers, mango farmers, papaya
farmers, and bird’s eye chillies). The Project Results Assessment (PRA) confirms from case farmers
interviewed that farmers in the project catchment experienced increased incomes.
It is hard for the PCREN to establish the credence of the reported gains in income in absence of
adequately developed outcome monitoring M&E. In light of the substantial output performance, and the
emerging evidence of improved agricultural practices, utilization of improved inputs and reduction in
post-harvest loss; the PCREN concurs significant improvements in household income, particularly
pineapple and mango farmers.
PCREN rates the project’s outcome performance satisfactory (3) in line with the PCR
e. Project development outcome:
As per the rating methodology recommended in the Staff Guidance Note on project completion
reporting and rating, the PCREN rates the development objective of the project satisfactory (3) since
both the outcome and output performance are rated satisfactory. The project is very likely to achieve its
development objective – raise the incomes of horticulture farmers.
f. Beneficiaries:
Using evidence, the evaluator should provide an assessment of the relevance of the total number of
beneficiaries by categories and disaggregated by sex.
21, 134 beneficiaries trained in good agricultural practices, female (21%)
1471 staff trained, female (20%)
130 export traders trained, female (30%)
g. Unanticipated additional outcomes (positive or negative, not taken into consideration in the
project logical framework):
Quality evaluation and certification of locally produced food products.
Pesticide research work being done in academic and research institutions.
Recognition as a regional testing and training centre in pesticide residue analysis and participation in
African Union Project on Pesticide Residue Data Generation.
EFFICIENCY
h. Timeliness:
The project became effective for disbursement on 31 May 2006 and its implementation ended on 31
December 2013. That is, it took a period of 7 years and 7 months. The ratio of planned (5 years) and
actual implementation time (7.7) is 0.71. PCR rates 2 (unsatisfactory) and PCREN concurs.
i. Resource use efficiency:
As per the PCR, the ratio of the median percentage physical implementation and commitment rate is
1.06. In accordance to the IPR guidelines, this indicates a high efficiency in resource use for a given
budget. The PCR rates the resource use efficiency of the project 4 (the project delivered all or more than
expected with the available budget).
Is a point estimate of 1.06 good enough to conclude the project delivered all or more outputs than
expected with the available budget? This question is pertinent in the case of this project since there were
delays in delivery of outputs (suggesting higher implied cost). In addition, the static measure does not
account for rate of utilization of outputs (some of the outputs were not fully utilized). Furthermore,
some of the key output targets were not achieved (e.g. road network and construction of pack houses).
For example:
Construction of the physical infrastructure was completed only during project extension in years
6 and 7 instead of year 4 and 5 as programmed at appraisal with attendant cost escalations.
The major economic assets such as the state-of-the-art pack house and the two temperature
controlled trucks have been lying idle since the project completion. In addition, the
demonstration centres have ceased functioning and demonstration plots located in some of the
pineapple growing communities have been abandoned.
The PCREN rates the resource use efficiency 3 (i.e., the project largely delivered the outputs expected
within the available budget).
j. Cost-benefit analysis:
The Economic and Financial analysis at appraisal was based on assumption that project benefits would
accrue from: (1) quality improvements in horticultural produce; (2) increased exports of horticultural
produce from both small scale out growers and large commercial producers; (3) increased profit margin
due to reduction in costs associated with improved feeder roads, construction of processing and pack
house facilities as well as supply of refrigerated vehicles to facilitate transportation. The economic rate
of return (ERR) at appraisal was 24%.
The PCR noted that aggregate financial benefits from horticultural production, processing and
marketing when computed against the investment costs for the project activities generated an estimated
EIRR of 20.29% at project completion. Whilst the project had still a positive NPV, the ERR was lower
than projected at appraisal.
The PRA revisited the assumptions that informed the computations in the PCR. Because major
economic assets such as the state-of-the-art pack house, the two Temperature controlled trucks, and the
demonstration centres were not fully functional, it expressed its expectation of a lower ERR at
completion. The PRA rates the project moderately unsatisfactory.
The PCREN rates 3 (satisfactory), in line with the PCR.
k. Implementation progress:
PCR: Rated 2 solely on the timeliness of the project (time overran). Not demonstrated the PCR
evaluated the IP criteria. PCREN: had no access to relevant project documents to assess the
implementation performance of the project. PRA rates unsatisfactory
Evidence on some of the IP criteria shows the following:
Compliance with general and specific conditions set in the legal documents for loan
effectiveness: there were substantial delays (10 months between loan signature and
effectiveness) that contributed to delays in project implementation and a two-year extension.
Compliance with environmental and social safeguards: Judged low environmental risk project,
ESMP was developed and implemented.
Audit compliance: As per the Borrower’s project completion report, the project has met its
reporting obligations in respect of the submission of audit reports to the Bank. The audit reports
submitted for years between 2007 and 2012 were certified.
Procurement: The Borrower’s project completion report indicates the performance was
satisfactory, i.e. the Bank and the PCU acted promptly on most of the procurement documents
and there was conformance with procurement methods agreed at appraisal
M&E performance: As per the Borrower’s PCR, the project team met all the scheduled reporting
requirements for the period. The project (Borrower) submitted a total of 27 quarterly reports,
seven (7) annual reports, eight (8) annual work plans, budgets and procurement plans to Bank
within scheduled time frames.
Disbursement: As reported in the Borrower’s PCR, 80% of ADF loan funds were disbursed at
the closure of the project.
Budget commitment rate: 85.2%
Counter part funding: 58%
No co-finance funding
These IP performance scores suggest the overall project implementation effectiveness was satisfactory
(3) in line with the PCR..
SUSTAINABILITY
The satisfactory rating of DO in section 3C suggests the project was very likely to achieve its
development objective. Whether the benefits would continue after completion is the topic of assessing
sustainability. There are financial, institutional, technical and environmental risks that could limit the
sustenance of continued flow of benefits.
l. Financial sustainability:
There are at least three steps in evaluating financial sustainability of projects; (1) determining if there is
a recognition of threat to financial sustainability since the design phase, (2) identifying the specific
modality in place for sustainability, and (3) assessing the sufficiency of these modalities to ensure
continued flow of benefits associated with the projects after completion using the four-point rating scale
prescribed in the PCR guidelines.
Farmers have confirmed that income gains from growing the crops under EMPAQ using the
technologies and knowledge acquired are substantially higher than traditional practices. Some of the
farmers have already integrated the improved technologies and practices into their farming systems. The
incentives are sufficient for those already in the project to sustain their income gains.
But to sustain the adoption of improved agricultural practices and adaptation to emerging technology
and market trends it would be necessary for MOFA and its collaborating partners continue development
of horticultural technologies and delivery of adequate horticultural advisory services to famers. In
addition, it would be necessary to maintain the key assets (i.e., demonstration centers, pack house, cold
chains, and feeder road) to continue their operation.
However, as noted in the PCR, the project had not effected a cost recovery or revenue generation model
for use of these facilities and infrastructure at the time of the PCR mission. The public financing option
was not yet proven viable to consolidate and sustain the gains achieved by the project. As the PRA
findings show, the project’s key assets were not functional in the period after the project closure.
The PCREN questions the PCR rating of satisfactory (3) and its conclusion that “there is likelihood that
both the beneficiaries and the Government (DAs and Central Government) will continue financing
activities that will further stimulate the appropriation of project benefits (e.g., utilization of
infrastructure).” The PCREN rates financial sustainability 3 (unsatisfactory) since reliance on public
financing is not sufficient to ensure continued flow of benefits associated with the project after
completion.
m. Institutional sustainability and strengthening of capacities:
The following are some of the contributions of the project towards institutional sustainability and
strengthening capacities:
The mobilization and formation of farmer groups was notable for instituting participatory
management system. Members of these groups were positioned to enhance their knowledge,
skills, and access to resources along the value chain, and for stronger bargaining power in
marketing.
The project had carried out various types of training targeted to different groups; for example,
beneficiary farmers trained in good agricultural practice, agricultural extension agents and
district crop officers trained in good agricultural practices, and executives of farmer groups and
private sector actors trained in export documentation, financing and business management.
The project developed capacities to respond effectively to change in consumer preferences in
export commodities as demonstrated in the EMQAP capacity to respond effectively to change in
demand from Smooth Cayenne to MD2 variety of pineapples. In addition, the project developed
crop surveillance systems to ensure export horticulture crops are free from pest.
Although the country’s research capacity in horticultural crops was weak at the beginning, there
was some progress in developing the capacities of researchers to resolve emerging issues
Staff drawn from various Directorates of Ministry of Food and Agriculture and its partnering
implementation agencies gained experience in the implementation of EMQAP. Modalities were
developing to utilize the experience to further advance development of the horticultural industry
in the country.
EMQAP supported the construction of pesticide residue analysis laboratory for the Ghana
Standard Authority (GSA) for conducting pesticide residue analysis in horticulture crops in
support of the industry. The facility was recently identified by the African Union as one of the
most established laboratories in Africa
The PCR rates institutional sustainability highly satisfactory (4) because there was was no risk in
terms of the Executing Agency overseeing the appropriateness and adequacy of the technical
solutions. Such reasoning fails to adequately characterize the efforts built in institutional
sustainability. The PCREN recognizes the multiple initiatives and efforts, and judges the project’s
significant contribution to institutional sustainability and capacity strengthening (rated 3).
n. Ownership and sustainability of partnerships:
The primary stakeholders of the project were members of the associations for horticultural export crops
(SPEG, VEPEAG and FAGE) who comprise nucleus farmers and smallholder out-growers linked to the
nucleus farmers. These associations were among the groups consulted in the preparation and appraisal
of the project. The members benefited from the various activities of the project intended to improve
their horticulture crop productivity and profitability.
The project procured two temperature controlled trucks in 2010 for SPEG and VEPEAG for moving
highly perishable produce from pack houses to export points (airports and seaports). SPEG and
VEPEAG were expected to utilize funds generated from the operations of the temperature controlled
trucks for the maintenance of the trucks. However, the assets were not handed over to SPEG and
VEPEAG at the project closure. As the PRA missions reported, these key assets necessary for
functioning cold chain (i.e., the pack houses and temperature controlled trucks) were not fully utilized
and deteriorating after the project completion.
The PCREN rates the contribution of the project towards the realization of the key assets of the project
among the primary beneficiaries unsatisfactory, given their limited participation in the preparation and
appraisal of the project, and non-ownership of the key assets.
The PCREN rating of 2 (unsatisfactory) is in line with the PCR.
o. Environmental and social sustainability:
The project was classified as category II, implying that the activities had minor adverse environmental
impacts and those foreseeable could be mitigated during project implementation. The Environmental
and Social Management Plan (ESMP) was developed and implemented to mitigate adverse
environmental consequences with a high degree of success (PRA).
PCREN rates environmental sustainability satisfactory (3) and PCR rates 3 (highly satisfactory).
4. PERFORMANCE OF STAKEHOLDERS
a. Bank performance:
The Bank was responsive to the Borrower (Government of Ghana) request for ADF loan to support
growth in horticulture production and export marketing. The project identification, preparation and
appraisal involved consultations with relevant stakeholders including prospective beneficiaries. The
Bank also factored lessons from its previous experiences in the country. However, the quality at entry
was not satisfactory as evident in late and slow start-up of implementation due to delays in meeting
some of the conditions for effectiveness.
The Bank enforced fiduciary requirements and safe guards. The procurement processes were mostly
done within acceptable timeframe. The exceptions were the longer period for recruitment of consultant
for the design and supervision of residue laboratory, demonstration centre and pack house. The Bank
supported development of staff capacity for improved delivery of services to beneficiaries. It also
supported establishment of the project’s M&E system and this was instrumental in enabling the
Borrower to meet its reporting requirements on schedule. ADF loan disbursement was slow at the
beginning but attained 80% at project closure.
The Bank facilitated the implementation of the project through supervision missions. As per the country
PCR report, the Bank fielded fifteen (15) implementation support missions. These missions reviewed
status of project implementation, identified constraints facing the project and proposed solutions, and
agreed on prioritized list of activities that should be implemented for the attainment of project
objectives. The Bank showed some flexibility in addressing problems/issues as evident in modifications
of the scope of the project following the mid-term review. The establishment of the AfDB Field Office
in Ghana assisted in more speedy resolution of problems encountered by the project. However, there
were few implementation challenges that arose mainly from frequent change in task managers (14 Task
Managers during the project implementation period).
Overall, the performance of the Bank in quality-at-entry and implementation effectiveness is rated 3
(satisfactory)
b. Borrower performance:
The Borrower participated in the formulation of the project was in line with its long-term development
strategy and policy. It signed on to long-term loan agreement and committed to fulfill loan conditions
including provision of counterpart funds. However, the design of the projects was not adequately
developed in terms of aligning the size of the project to its readiness for implementation. The quality at
entry was not satisfactory as evident in late and slow start-up of project implementation due to delays in
meeting some of the conditions for effectiveness.
The Borrower performed reasonably well in complying generally with the Bank’s fiduciary
requirements by preparing and submitting annual audited project financial statements and adhering to
the Bank’s disbursement regulations. It ensured project’s compliance with environmental safeguards. In
addition, the Borrower monitored the performance of the project (i.e. input/output performance,
procurement performance, and financial performance including disbursement) and reported on schedule
to the Bank. In addition, the Borrower was responsive to supervision recommendations as evident in
adjustments following the mid-term review. However, the Borrower was not in compliance with
meeting its commitment to the level of counterpart funding. Moreover, there was no adequate exit
strategy for financial sustainability after project closure.
Overall, the performance of the borrowers in design and readiness as well as implementation was
satisfactory (rated 3).
c. Performance of other stakeholders:
Among the key other stakeholders were the various consultants and contractors. The performance of
these providers was assed in the country PCR in terms of quality of work performed, timeliness of
execution of contracts, and quality of management and financial soundness. Performance rating of the
various providers varied but the majority scored satisfactory. These were few contracts terminated due
to non-performance or inability to rectify identified defects.
The PCR rates the performance of other stakeholders satisfactory (3) in line with the PCR.
5. SUMMARY OF OVERALL PROJECT PERFORMANCE
a. Overall assessment:
The project is rated satisfactory in its relevance. It achieved most of its output targets. Few beneficiary-
focused surveys whose methodology could not be verified indicate improvements in household
horticulture productivity, quality and income in the catchment areas. There was reasonable expectation
that the project would achieve its development objectives. There was some weakness in the project’s
economic worthiness over the course of the project implementation, which might be related to weak
operational efficiency and underutilization of key assets of the project. There was no adequate exit
strategy for financial sustainability, but there was notable progress towards institutional sustainability
and strengthening capacity, and environmental sustainability is satisfactory.
The PCREN rates satisfactory (3) the overall performance of the project in design, implementation and
results.
b. Design, implementation and utilization of the M&E (appreciation of the evaluator):
Often the M&E system designed and implemented for monitoring project performance is basic; it
focuses on collecting, analyzing and reporting performance in project activities and outputs (I/O
monitoring), procurement, and financial management including audit reports. Missing is systematically
monitoring project’s outcomes, which are necessary to assess performance towards achieving the
project’s objectives.
The performance of the basic M&E system was satisfactory. The project met all the scheduled reporting
requirements by producing 27 quarterly reports and seven annual report. In addition, the Project
submitted audit reports to the Bank within scheduled time frames. Missing was properly designed
monitoring of the project’s outcomes such as change in profitability of horticulture production and
exports to the beneficiaries.
PCREN rates 3 (satisfactory) in line with the PCR.
6. EVALUATION OF KEY LESSONS LEARNED AND RECOMMENDATIONS
a. Lessons learned:
Inadequate time and resources devoted to project appraisal, which should be thorough, ensuring very wide
consultation and ownership.
Involvement of key government departments -- retention of the Department of Feeder Roads to supervise the
work of contractors was useful in ensuring quality and timeliness
b. Recommendations:
None for the PCR to adopt
7. COMMENTS ON PCR QUALITY AND TIMELINESS
The PCR was complete in coverage of the dimensions of evaluation (relevance, efficacy in output and outcome,
efficiency, sustainability, Borrower and Bank performance). Access to data/evidence was limited. Quality of
analysis in terms of rigor and objectivity was poor. There were notable inconsistencies between rating and
explanation.
Overall, the performance of the PCR is 2 (unsatisfactory).
8. SUMMARY OF THE EVALUATION This is a summary of both the PCR and IDEV ratings with justification for deviations/comments. Appropriate section of the PCR
Evaluation should be indicated in the last column in order to avoid detailed comments. The evaluator must provide a reasonable
explanation for each criterion the PCR rating is not validated by IDEV. Consequently, the overall rating of the project could be “equally
satisfactory”.
Criteria PCR PCREN Reason for disagreement/ Comments
RELEVANCE 4
Relevance of project development objective 4 4
Relevance of project design 4 3 The discussion in the PCR was not about the
design of the project, i.e. rationale for its
choice, its internal logic, the extent the
design was informed, assessment of its
realism, and adjustment in scope over the
whole project life cycle, and relevance ex
post. The PCR rating is unrelated to the text.
EFFECTIVENESS
Development objective (DO) 3 3
EFFICIENCY
Timeliness 2 2
Resource use efficiency 4 3
Cost-benefit analysis 3 3
Implementation progress (IP) 3 3 The PCR rates on a single metrics of time
overrun. The PCREN had limited access to
the relevant documents, and hence the IP
rating was based on some (not all) the
suggested IP criteria.
SUSTAINABILITY 3
Financial sustainability 3 2 The PCR is not addressing the issues of the
recognition of the extent of threat
Institutional sustainability and strengthening
of capacities
4 3 Considerable disconnect between the rating
and the text in the PCR
Ownership and sustainability of partnership 2 2
Environmental and social sustainability 3 3
OVERALL PROJECT COMPLETION
RATING
3.25
Bank performance: 3 3 The rating in the PCR was based on a
narrow set of issues as compared to the ones
suggested in the PCR guidelines. The
PCREN was not able to access the Bank’s
supervision reports and IPR.
Borrower performance: 3 3 The rating in the PCR was based on a
narrow set of issues as compared to the ones
suggested in the PCR guidelines. The
PCREN was not able to access the Bank’s
supervision reports and IPR.
Performance of other shareholders: 3 3 Referring mainly to consultants and
contractors
Overall PCR quality: 2
9. PRIORITY FOR FUTURE EVALUATIVE WORK: PROJECT FOR
PERFORMANCE EVALUTION REPORT, IMPACT EVALUTION,
COUNTRY/SECTOR REVIEWS OR THEMATIC EVALUATION STUDIES:
- Project is part of a series and suitable for cluster evaluation
- Project is a success story
- High priority for impact evaluation
- Performance evaluation is required to sector/country review
- High priority for thematic or special evaluation studies (Country)
- PPER is required because of incomplete validation rating
Major areas of focus for future evaluation work:
a) Performance evaluation is required for sector/ country review
b) Cluster evaluation (institutional support)
c) Sector evaluation (budgetary support or public finance management reforms)
Follow up action by IDEV: Identify same cluster or sector operations; organize appropriate work or consultation mission to
facilitate a), b) and/or c).
Division Manager clearance Director signing off
Data source for validation:
Task Manager/ Responsible bank staff interviewed/contacted (in person, by telephone or email)
Documents/ Database reports
Attachment:
PCR evaluation note validation sheet of performance ratings
List of references
Appendice 1
PROJECT COMPLETION REPORT EVALUATION NOTE Validation of PCR performance ratings
PCR rating scale:
Score Description 4 Very Good – Fully achieved with no shortcomings 3 Good – Mostly achieved despite a few shortcomings 2 Fair – Partially achieved. Shortcomings and achievements are roughly balanced 1 Poor – very limited achievement with extensive shortcomings
UTS Unable to score/rate NA Non Applicable
Criteria Sub-criteria PCR
work
score
IDEV
review Reasons for deviation/comments
RELEVANCE Relevance of the project
development objective
(DO) during
implementation
4 4
Relevance of project
design (from approval to
completion)
4 3
OVERALL RELEVANCE SCORE
EFFECTIVENESS* Effectiveness in delivering outcomes
Sector goal -- increase
in export earning at
project closure, 15%
Modest gain recorded at national level
Increase in household
income of horticulture
farmers
Recorded substantial improvements
Effectiveness in delivering output
Established 4
demonstration Centres.
100%
Published and
distributed 43,000
guides and GAP
manual.
143%
Production &
Dissemination of
improved seeds &
planting material,
variable by crop
104.6%
Criteria Sub-criteria PCR
work
score
IDEV
review Reasons for deviation/comments
One study on local and
regional markets for
horticultural crops
100%
181.45 km of feeder
roads, 181.45 km
44.5% The rate was XXX relative to the revised target level
One of the four pack
houses built
25.0%
4 demonstration centers
were established
100%
30,00 farmers sensitized
and mobilized into
groups
37.5% The activity was discontinued to avoid duplications
with another Government of Ghana project
(MiDA) 21,134 beneficiaries
trained in good
agricultural practices
260%
1471 staff trained 122%
130 export traders
trained
11%
Development objective (DO)
Development objective
rating
3
Beneficiaries
Beneficiary1
Beneficiary2
Unanticipated outcomes (positive or negative not considered in the project logical
framework) and their level of impact on the project (high, moderate, low)
Institutional
development
Gender
Environment & climate
change
Poverty reduction
Private sector
development
Regional integration
Other (specify)
EFFECTIVENESS OVERALL SCORE
Criteria Sub-criteria PCR
work
score
IDEV
review Reasons for deviation/comments
EFFICIENCY Timeliness (based on the
initial closing date)
Resource used
efficiency
Cost-benefit analysis
Implementation progress
(from the IPR)
Other (specify)
OVERALL EFFICIENCY SCORE
SUSTAINABILITY Financial sustainability
Institutional
sustainability and
strengthening of
capacities
Ownership and
sustainability of
partnerships
Environmental and
social sustainability
Criteria Sub-criteria PCR
Work
score
IDEV
review Reasons for deviation/comments
BANK
PERFORMANCE Proactive identification and
resolution of problems at different
stage of the project cycle
3
Use of previous lessons learned
from previous operations during
design and implementation
3
Promotion of stakeholder
participation to strengthen
ownership
2
Enforcement of safeguard and
fiduciary requirements
3
Design and implementation of
Monitoring & Evaluation system
3
Quality of Bank supervision (mix
of skills in supervisory teams, etc)
3
Timeliness of responses to
requests
3
OVERALL BANK PERFORMANCE SCORE
BORROWER
PERFORMANCE
Quality of preparation and
implementation
3
Compliance with covenants,
agreements and safeguards
3
Criteria Sub-criteria PCR
work
score
IDEV
review Reasons for deviation/comments
Provision of timely counterpart
funding 2
Responsiveness to supervision
recommendations
3
Measures taken to establish basis
for project sustainability
2
Timeliness of preparing requests 3
OVERALL BORROWER PERFORMANCE SCORE 3
PERFORMANCE
OF OTHER
STAKEHOLDERS
Timeliness of disbursements by
co-financiers NA
Functioning of collaborative
agreements
NA
Quality of policy dialogue with
co-financiers (for PBOs only) NA
Quality of work by service
providers 3
Responsiveness to client demands ?
OVERALL PERFORMANCE OF OTHER
STAKEHOLDERS
DESIGN, IMPLEMENTAION AND UTILIZATION OF MONITIRING AND
EVALUATION (M&E)
Criteria Sub-criteria IDEV
Score Comments
M&E DESIGN M&E system is in place, clear,
appropriate and realistic
Monitoring indicators and
monitoring plan were duly
approved
Existence of disaggregated gender
indicator
Baseline data were available or
collected during the design
Other, specify
OVERALL M&E DESIGN SCORE
M&E
IMPLEMENTA-
TION
The M&E function is adequately
equipped and staffed
OVERALL M&E IMPLEMENTATION SCORE
M&E
UTILIZATION The borrower used the tracking
information for decision
OVERALL M&E UTILIZATION SCORE
OVERALL M&E PERFORMANCE SCORE
PCR QUALITY EVALUATION
Criteria PCR-EVN
(1-4) Comments
QUALITY OF PCR
1. Extent of quality and completeness of the PCR
evidence and analysis to substantiate the ratings of
the various sections
2 Covered all the evaluation dimensions, but often
incomplete in factoring required evaluation criteria
for rating.
2. Extent of objectivity of PCR assessment score 2 Empirical based for some of the evaluation criteria
such as project’s outputs and measures of
operational efficiency. Otherwise, limited
objectivity.
3. Extent of internal consistency of PCR assessment
ratings; inaccuracies; inconsistencies; (in various
sections; between text and ratings; consistency of
overall rating with individual component ratings)
2 Often notable divergence between text and ratings.
4. Extent of identification and assessment of key
factors (internal and exogenous) and unintended
effects (positive or negative) affecting design and
implementation
2 No such frame of analysis to uncover influential
factors affecting performance or result
5. Adequacy of treatment of safeguards, fiduciary
issues, and alignment and harmonization
3
6. Extent of soundness of data generating and
analysis process (including rates of returns) in
support of PCR assessment
2 Apparently, the PCR had limited access to
data/evidence necessary for sound technical
analysis as evident from the low-objectivity and
consistency in PCR ratings.
7. Overall adequacy of the accessible evidence (from
PCR including annexure and other data provided)
2 Limited and problematic for the PCREN
validation
8. Extent to which lessons learned (and
recommendations) are clear and based on the PCR
assessment (evidence & analysis)
1 Too many lessons that are not necessarily learned
from the project experience
9. Extent of overall clarity and completeness of the
PCR
2
Other (specify)
PCR QUALITY SCORE 2
PCR compliance with guidelines (PCR/OM ; IDEV)
1. PCR Timeliness (On time = 4; Late= 1) 4
2. Extent of participation of borrower, Co-financiers
& field offices in PCR preparation
3
3. Other aspect(s) (specify)
PCR COMPLIANCE SCORE 3.5
*** rated as Very Good (4), or Good (3), or Fair (2), or Poor (1)
References
African Development Bank Group. 2014. Project completion report for public sector operations (PCR) --
Export Marketing and Quality Awareness Project (EMQAP).
African Development Bank Group. 2012. Staff guidance on project completion reporting and rating.
Quality Assurance Department (ORQR).
African Development Bank Group. 2011. Staff guidance on implementation progress and results (IPR) for
public sector operations. Quality Assurance Department (ORQR).
African Development Fund. 2005. Republic of Ghana: Export Marketing and Quality Awareness Project
(EMQAP). Appraisal Report. Agriculture and Rural Development, OCAR.
Government of the Republic of Ghana, Ministry of Food and Agriculture. Undated. Ghana: Project
completion report for the export marketing and quality awareness project.
African Development Bank. Undated. EMQAP – Project Results Assessment. IDEV
References
Note the following documents were not available to the PCREN: EMQAP Mid-Term
Review (September 2010) and the project’s IPR (April, 2014).