Pcm642topic04(Lp)3perpage

10
PCM642 – Topic 4 1 PCM 642 – Topic 4 Cost Estimating PROJECT COST MANAGEMENT 642 COST ESTIMATING - INTRODUCTION PCM 642 – Topic 4 Cost Estimating LECTURE OVERVIEW Definition Purpose Categorising Estimates for project management Level of effort Quality of an estimate Components Inputs and sources Outputs PCM 642 – Topic 4 Cost Estimating DEFINITION Project cost management comprises: Resource Planning, Cost Estimating , Cost Budgeting, Cost Control .

description

Cost Estimation in engineering Lecture Topic 4

Transcript of Pcm642topic04(Lp)3perpage

  • PCM642 Topic 4

    1

    PCM 642 Topic 4Cost EstimatingPROJECT COST MANAGEMENT 642

    COST ESTIMATING - INTRODUCTION

    PCM 642 Topic 4Cost EstimatingLECTURE OVERVIEW

    DefinitionPurposeCategorisingEstimates for project managementLevel of effortQuality of an estimateComponentsInputs and sourcesOutputs

    PCM 642 Topic 4Cost EstimatingDEFINITION

    Project cost management comprises:

    Resource Planning,

    Cost Estimating,

    Cost Budgeting,

    Cost Control .

  • PCM642 Topic 4

    2

    PCM 642 Topic 4Cost EstimatingDEFINITION

    Definition (contd)PMI:

    developing an approximation (estimate) of the costs of the resources needed to complete project activities ... it involves developing an

    t f th lik l tit ti lt assessment of the likely quantitative result

    AACE:compilation of all the costs of the elements of a project or effort included within an agreed-upon scope

    PCM 642 Topic 4Cost EstimatingCOST ESTIMATING

    now answer Class exercises: Question 1

    PCM 642 Topic 4Cost EstimatingPURPOSES FOR COST ESTIMATES

    Economic Evaluation Help determine whether project is economically viable

    Budgeting & Cost ControlBudgeting and consequent cost control of the project

    Time Estimating gEstimate related to resource availability & estimate

    durationFunding Approval

    Estimate will indicate funding needsComparing Alternatives

    Cost evaluation between alternatives.eg.design solutions.

  • PCM642 Topic 4

    3

    PCM 642 Topic 4Cost EstimatingPURPOSES (CONTD)

    Costing Scope Changes Determine costs of scope changes on projects.

    Costing Legal Claims Estimates involved in claims & agreeing settlement

    T d iTenderingClient procures service/product from external organsation: Contractor

    Estimate prepared to formulate tender Client

    Estimate as benchmark to measure competitiveness of contractor's bid .

    PCM 642 Topic 4Cost EstimatingCATEGORISING ESTIMATES

    BENEFITS Standardises basis of estimate:

    l f f l l d Level of information available to produce estimate

    The type of data that should be used

    The level of expected accuracy

    PCM 642 Topic 4Cost EstimatingCATEGORISING ESTIMATES

    Projects can be classified according to the following: Degree of project definition

    extent and type of input information available for estimating End usage of the estimate

    eg. For feasibility studies, funding authorisation, budgets Estimating methodology

    t h ti ( b d d l ti hi b t t & j t stochastic ( based around relationships between costs & project parameters generally other than direct measure of project elements)

    deterministic - definitive measure of items Accuracy range

    degree final cost will vary from estimate (traditionally expressed as + or - % around point estimate

    Level of effort to prepare the estimate Indicates cost, time, resources required. (typically expressed as

    % of total costs) .

  • PCM642 Topic 4

    4

    PCM 642 Topic 4Cost EstimatingTYPES OF ESTIMATES

    Class Level ofProject

    Definition

    Typicalpurpose of

    estimate

    Typicalestimating

    method

    Accuracy relativeto Class 1

    Effort relativeto Class

    55 0 2% Screening or

    FeasibilityStochastic or

    Judgement10 to 20 1

    4 1 5% Concept study Primarily 5 to 10 2 to 44 1 5% Concept studyor Feasibility

    PrimarilyStochastic

    5 to 10 2 to 4

    3 10 40% Budget,Authorisation,

    or Control

    Mixed, butprimarily

    stochastic

    3 to 6 3 to 10

    2 30 60% Control orTender

    Primarilydeterministic

    2 to 3 5 to 20

    1 50 - 100% CheckEstimate or

    Tender

    Deterministic 1 10 to100

    PCM 642 Topic 4Cost EstimatingPROJECT MANAGEMENT ESTIMATES

    In construction projects;

    AIQS Cost management Manual specifies types:Project stage AIQS Cost planning stage

    AIQS Cost Common name of costing

    Inception A Brief Brief stage cost

    Indicative cost

    Development B Outline proposals Outline proposals cost

    Preliminary estimate

    C Sketch design Sketch design cost plan

    Limit of cost estimate

    D - Documentation Tender document cost plan

    Tender estimate

    PCM 642 Topic 4Cost EstimatingPROJECT MANAGEMENT ESTIMATES

    For project management;No specific type dictated

    However, generally according to level , g y gof project definition

    Suits PM as it mirrors PLC

    Type of estimate changes with greater detail

  • PCM642 Topic 4

    5

    PCM 642 Topic 4Cost EstimatingORDER-OF-MAGNITUDE ESTIMATES

    Characteristics 'ball park', conceptual', guesstimate earliest estimate. Decide which way (& whether) to go with

    project quick, simple, inexpensive: 1 to 150 hours used when little information available false sense of accuracy. (+75% to -25%) typically parametric estimating .

    Can be used for: evaluating general feasibility of a project evaluating cost consequences of proposed design modifications establishing preliminary budget for control purposes during

    design screening alternative projects for further detailed analysis .

    PCM 642 Topic 4Cost EstimatingBUDGET ESTIMATES

    Characteristics prepared with some preliminary scope expected accuracy +25% to -10% typically parametric or semi-detailed deterministic .

    Can be used for: setting preliminary budget &/or funding approval

    screening project & confirming economic viability.

    PCM 642 Topic 4Cost EstimatingDEFINITIVE ESTIMATES

    Characteristics Based on extensive amount of detailed information Level of project definition between 30% and 100% Expected degree of accuracy +/- 5% level of effort 500 to 10,000 hours

    ll d b typically deterministic, bottom-up estimating

    Can be used for: bid, bid evaluation, contract changes, legal claims .

  • PCM642 Topic 4

    6

    PCM 642 Topic 4Cost EstimatingLEVEL OF EFFORT

    must understand level of effort required Could be pressured into producing an estimate of;

    Higher expected accuracy in insufficient time

    Categorising avoids this problemP i i h k d l l f ff f Participants then know expected level of effort fortypes of estimate

    Cost of preparing estimates (Humphreys and English)

    Accuracy range (%)

    $1,000,000 project

    $10,000,000 project

    $20,000,000 project

    -5+ 15 20,000 50,000 90,000-15 + 30 6,000 15,000 30,000-30 + 50 1,500 4,000 8,000

    PCM 642 Topic 4Cost EstimatingLEVEL OF EFFORT

    Pm must also watch overspending on effort

    For internal projects it is not worthwhileproducing an estimate more accurate than thecontrol estimate because it costs more tocontrol estimate, because it costs more toproduce than the value of the data

    Turner (1993)

    Read Turners (1993) example on the Tutorial sheet

    PCM 642 Topic 4Cost EstimatingESTIMATING

    now answer Class exercises: Question 2now answer Class exercises: Question 2

  • PCM642 Topic 4

    7

    PCM 642 Topic 4Cost EstimatingQUALITY OF AN ESTIMATE

    Validity Estimate considered valid if basis for preparing it is also valid eg if previous similar project used to estimate proposed

    project, all differences between the two must be properly taken into account

    Reliability Reliable = methodical process followed by identifying, Reliable methodical process followed by identifying,

    evaluating, using and recording all relevant information availableAccuracy

    Accuracy = freedom from errorPrecision

    = how many significant digits we use in calculations precise figure can still be inaccurate if error is made .

    PCM 642 Topic 4Cost EstimatingCOST COMPONENTS

    Labour - 2 parts: payment direct to person, PLUS on-costs.eg. payroll tax,

    Materials - Usually obtained from manufacturers and suppliers. Equipment - Used but not consumed - useable on other projects. Subcontract - Elements performed by external firm.p y Fees - eg insurance and licence agreements Organisational Overheads-eg general office staff,office rent.

    Internal project - included to give full cost; Contractor tendering - included as only means to recoup OH

    Profit & Risk Internal project: not usually applicable Tender: yes

    PCM 642 Topic 4Cost EstimatingESTIMATING - TYPES OF COSTS

    2 costs - usually calculated separatelywithin an estimate.

    Direct costs Costs readily traceable to the project .

    I di t t Indirect costs All costs other than direct costs, PM usually has some control over direct but little or

    no control over indirect costs" "a considerable amount of time is very often devoted

    to defining and estimating the direct costs, with indirect costs taking a secondary importance (Patrascu, 1988) .

  • PCM642 Topic 4

    8

    PCM 642 Topic 4Cost EstimatingESTIMATING

    now answer Class exercises: Questions 3 and 4

    PCM 642 Topic 4Cost EstimatingESTIMATING INPUTS

    Project Documents eg: scope statement, specification, drawings,

    contract. Work Breakdown Structure (WBS)

    WBS identifies project elements. Each can have a cost cost

    Type, quantity & cost of resources determined & element costed.

    WBS ensures that all identified work has been estimated (PMI)

    Historical Information in-house cost records; similar projects; published

    cost information; government figures; university research

    PCM 642 Topic 4Cost EstimatingESTIMATING INPUTS

    Organisational Policies eg., preferred estimating methods, resource costs, rent or buy

    Project team skills and knowledge eg project team, consultants, g p j , ,subcontractors, suppliers .

    Resource Breakdown Structure RBS advocated by Rad (2002) provides standard costs for organisational resources

  • PCM642 Topic 4

    9

    PCM 642 Topic 4Cost EstimatingSOURCES OF DATA

    The availability of historical data is paramount in the development and use of estimating models (Rad, 2002).

    Data may be derived from any of the following: Suppliers quotes Trade literature tech lit textbooks Trade literature, tech lit, textbooks Company historical data, standard costs Computer systems Government figures

    PLUSPMs experience

    (See NASA website for cost estimating)

    PCM 642 Topic 4Cost EstimatingESTIMATING - OUTPUTS

    Cost Estimate generally expressed in $ but may be in other units.

    e.g. hoursSupporting Detail

    estimate should describe scope basis (i.e., how was it developed) basis (i.e., how was it developed) assumptions indication of the range of the cost estimate

    Cost Management Plan describe how cost variances will be managed. e.g.

    different responses to major problems than to minor ones

    plan may be formal or informal, highly detailed or broad framed, based on needs of the project stakeholders .

    PCM 642 Topic 4Cost EstimatingESTIMATING

    now answer Class exercises: Question 5

  • PCM642 Topic 4

    10

    PCM 642 Topic 4Cost EstimatingETHICS

    Ethics: Fudge estimates !! (Bent & Humphreys

    , 1996) manipulate to suit a particular purposeman pu a u a par u ar purp Living with consequences of manipulation

    may be far worse than giving a realistic cost estimate

    Estimates used as political tool!

    PCM 642 Topic 4Cost EstimatingESTIMATING - SUMMARY

    The estimate can only ever be as good as the estimators skill and experience will allow and the relevance and accuracy of the relevance and accuracy of the information on which it is based

    (Lindsay Castell, 2010!!)

    PCM 642 Topic 4Cost EstimatingESTIMATING - SUMMARY

    End of topic End of topic