PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure...

46
PBN AIRSPACE DESIGN Victor Hernandez RO ATM/SAR International Civil Aviation Organization

Transcript of PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure...

Page 1: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 1

PBN AIRSPACE DESIGN

Victor HernandezRO ATM/SAR

International Civil Aviation Organization

Page 2: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 2

PBN Airspace Redesign 

Page 3: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 3

ATC Sectorization

APP APP E

ACC Lower

APP W

Upper ACC Sectors Upper ACC Sectors

ACC S1 ACC S2 ACC S3

GEOGRAFICA FUNCIONAL

Page 4: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 4

PBN Airspace Design 

Doc 9613 Manual PBN

Volumen IParte A ‐ Airspace ConceptParte B –Implementation Procceses

Volumen II –Navigation Specifications

Doc 9902, PBN in Airspace Design

Page 5: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 5

PBN Airspace Design

Page 6: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 6

6

PBN Airspace Design

Page 7: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 7

Activity 1 

CapacityEnvironmentAccessibilitySafetyEfficiency

7

Agree on Operational Objectives

Page 8: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 8

Activity 2 

Airspace Design Multidisciplinary TeamLead by ATM / airspace specialistATCOs (Air Traffic controllers)ATM & CNS specialistProcedure designersTechnical pilots……

Page 9: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 9

Activity 3 3 – Project objectives, scope and timescales

$$

Implementation Date(s)Phases of Work?

$$

Which Human Resources?What about the budget?

What is the 

What  cannot be done?

Objective ?How much can be done?

Page 10: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 10

PLANNING EXAMPLEEXAMPLE PROJECT PLAN

ACTIVITYNumber of 

DaysPLAN 1 Agree on Operational Requirements 10

2 Create Airspace Design Team 53 Agree on Objectives, Scope & Timeline 154 Analyze Reference Scenario 155 Select Safety Criteria, Safety Policy, & Performance Criteria 106 Agree on CBS/ATM Assumptions 12

DESIGN 7 Design Airspace Routes and Holds 148 Initial Procedure Design 209 Design Airspace Volumes and Sectors 2010 Confirm ICAO Navigation Specification 5

VALIDATE 11 Airspace Concept Validation 2012 Finalize Procedure Design 2213 Procedure Validation 20

IMPLEMENT 14 ATC System Integration 3015 Awareness and Training Material 3016 Implementation 117 Post Implementation Review 30

TOTAL DAYS REQUIRED 279

Page 11: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 11

Activity 4

Assessment of present operationsIdentification of positive and negativeBenchmarkAvoids repeats of design flaws

Analysis of the reference scenario

Page 12: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 12

Activity 5 

Select Safety Management systemSelect Safety Assessment MethodologyWhat evidence is needed to prove safety of designSet success criteria

Select Safety Criteria, SafetyPolicy and Performance Criteria

Page 13: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 13

Activity 6Agree on ATM/CNS assumptions

Page 14: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 14

Activity 7

Arrivals DeparturesTransitVFRMilitary

Design the Airspace

AVOID trying to fit the routes into the existing airspace volumes

Page 15: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 15

Activity 8

Capability/functionality needed?

Fleet capability/functionality available?

Coverage provided by available Navaid infrastructure?

Design according to ICAO Doc 8168 and Doc 9905InitiationCollect & Validate DataCreate Conceptual DesignReview by Stakeholders

Initial Procedural Design

Page 16: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 16

Activity 9

Design Airspace Volumes and Sectors

SectorisationAirspace volumeIterations possible

Page 17: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 17

Activity 10

Confirm ICAO Navigation specification

Review NAV specsIdentify appropriate specGo to Validation and ImplementationIf no appropriate spec

Apply Trade off

Page 18: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 18

Activity 11

Airspace Concept Validation

Prove ATM operability & validity

Assess objectives

Identify possible weak points

Provide evidence and proof to support Safety Assessment

Page 19: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 19

Activity 12

Finalization of procedure design

Design according to ICAO Doc 8168 and Doc 9905Apply CriteriaDocument and StoreSupport Safety Assessment

Output:Draft procedure layoutsCalculation outputsTextual description of procedure

Page 20: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 20

Activity 13

Procedure validation

Verification of terrain, obstacle and aeronautical data used to support designValidate intended use of procedure (match to conceptual design)Validate correct application of criteriaValidate fly ability and human factors (charting)Flight Inspection (if required)

Page 21: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 21

Activity 14

ATC System Integration

Changes to ATC system interfaces and displays to ensure controllers have the necessary information on aircraft capabilities and the appropriate displays to support the new routings. Such system changes could include modifications to: 

Air Traffic Flight Data Processor (FDP) Air Traffic Radar Data Processor (RDP) ATC situation display ATC support tools 

Page 22: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 22

Activity 15Awareness and Training Material

The introduction of PBN can involve considerable investment in terms of training, education and awareness material for both flight crew and controllers. 

Printed training packagesComputer based trainingNOTAMSICAO provides additional training material and seminars. 

Page 23: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 23

Activity 16

Implementation

Have the Safety and Performance Criteria been satisfied;Have the required changes been made to the ATM system;Have the required changes been made to the ground navigation systems;Do the assumptions and conditions upon which the Airspace Concept has been developed still pertain. (are traffic flows as forecast, is the fleet suitably equipped and approved etc);Are the critical enablers all in place.;Have the pilots and controllers received appropriate training. 

Page 24: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 24

Activity 17

Post Implementation MonitoringKeep LOG Assess if objectives are metMeasurement ProgrammeSMS safety assessment – collect evidence

Page 25: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 25

Good Design Practice

Segregate Arrivalslaterally and verticallyfrom Departures

Page 26: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 26

Good Design Practice

Segregate Arrivalslaterally and verticallyfrom Departures

Page 27: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 27

Good Design Practice

✈ Segregation of routes and entry/exit points

✈ Plan for vertical separation

Page 28: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 28

Good Design Practice

070

7

25

25

D DD DD D

A A

RWY27 RWY09R2.1 R2.1

Fix the same Exit/Entry points for different RWY configurations

Handoff between ACC and APP should not change with RWY configuration

TA boundary TA boundary

Page 29: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 29

Good Design Practice

AX

R3 R3

A

R3

ENTRY GATE

✈ Gradually converge inbound flows

✈ Group similar inbound flows in entry gates

Page 30: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 30

Good Design Practice

07 2

5

07

25

07 2

5

XX

R1.1 R1.2: (Graph 5-1)R1.3

R1.1 R1.2: (Graph 5-1)R1.3

High Complexity

R1.1 R1.2: met (Graph 5-1)R1.3

XX X

07

25R1.1

R1.2: (Graph 5-1)R1.3

ManagedComplexity

Minimise CrossingComplexity

Page 31: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 31

H1X

H.1 R1.2 (Graph 5-1)

DA

AX

H1

Terminal Airspace Boundary

A

Terminal Airspace Boundary

Terminal Airspace Boundary

H1Merging of routes at holdingpoint may be too complex.

H2

Terminal Airspace Boundary

Terminal Airspace Boundary

A A

H2 H2

Holds

Good design practiceGood design practice

Page 32: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 32

Continuous Descent Operations

( CDO )

Design Methods

Page 33: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 33

CDO Design Methods

• Design to select the shortest path

Page 34: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 34

CDO Design Methods

• Design to select the shortest path

Page 35: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 35

1000m

2000m

3000m

4000m

5000m

CDO Design Methods

• Long path plus “shortcuts” are inefficient

Page 36: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 36

CDO Design Methods

1. Select the shortest path.2. Modify path as necessary in response to: 

• airspace, • terrain,  • departure paths,• other traffic.

3. Apply required speeds and or altitude profiles.4. Review and modify as necessary.

Page 37: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 37

CDO Design Methods

CDO STAR waypoints may contain:

Altitudes restrictions may be• “At”, • “At or above”,• “At or below”,• or a window of both “At or above and at or below”

1. Speed restrictions2. Altitude restrictions

Limit speed and altitude restrictions to the minimum necessary.• In general speed restrictions should not be less than 280kt above 

10,000 msl.• Speed restrictions must have an associated altitude restriction (FMS 

requirement)

Page 38: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 38

Closed Path CDO CalculationsExample ‐ refined with simulation

Page 39: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 39

CCO Roadmap

Page 40: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 40

CCO Defined

CCO is an aircraft operating technique made possible by

1. appropriate airspace and procedure design2. appropriate ATC clearances 

enabling the execution of a flight profile optimized to the performance of the aircraft, allowing the aircraft to attain initial cruise flight level at optimum air speed with climb engine thrust settings set throughout the climb, thereby reducing total fuel burn and emissions during the whole flight. 

Page 41: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 41

CCO & CDO Design Methods

• Where a trade‐off between CCO and CDO is unavoidable, the local analysis and decision making should take into account that a level segment for an aircraft in descent would normally burn less fuel than for the same duration of level segment for an equivalent aircraft in climb. 

• Often there is far more unnecessary level flight in the descent phase than in the climb phase. 

• The balance will depend on local characteristics such as the extent of level flight in both phases, the significance of noise in the areas affected etc. 

BALANCE:

Page 42: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 42

Profile Interaction

Page 43: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 43

Profile Interaction

Page 44: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 44

Profile Interaction

Page 45: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 45

QUESTIONS?

Page 46: PBN AIRSPACE DESIGN - International Civil Aviation ... Airspace Design ... 12 Finalize Procedure Design 22 13 Procedure Validation 20 IMPLEMENT 14 ATC System Integration 30 15 Awareness

November 2013 Page 46

Thank You