![Page 1: Paving the way - icm.clsbe.lisboa.ucp.pticm.clsbe.lisboa.ucp.pt/docentes/url/jfr/pm/Paving the way.pdf · Ana Mafalda Roque Patrícia Gabriel Dan Naumov Benedikt Schulz Mariana Cadete.](https://reader034.fdocuments.in/reader034/viewer/2022051908/5ffc42564c10ee7f5035721f/html5/thumbnails/1.jpg)
Project Management
Paving the way
to the mile-high city
![Page 2: Paving the way - icm.clsbe.lisboa.ucp.pticm.clsbe.lisboa.ucp.pt/docentes/url/jfr/pm/Paving the way.pdf · Ana Mafalda Roque Patrícia Gabriel Dan Naumov Benedikt Schulz Mariana Cadete.](https://reader034.fdocuments.in/reader034/viewer/2022051908/5ffc42564c10ee7f5035721f/html5/thumbnails/2.jpg)
Agenda
Introduction
Challenges
Solutions
Triple Constraint Quality
Time
Cost
Results
Lessons Learned
![Page 3: Paving the way - icm.clsbe.lisboa.ucp.pticm.clsbe.lisboa.ucp.pt/docentes/url/jfr/pm/Paving the way.pdf · Ana Mafalda Roque Patrícia Gabriel Dan Naumov Benedikt Schulz Mariana Cadete.](https://reader034.fdocuments.in/reader034/viewer/2022051908/5ffc42564c10ee7f5035721f/html5/thumbnails/3.jpg)
Introduction
Denver International Airport Opened in 1995 with 5 runways
Runway 16R/34L – Larger and technological advanced
Needed a runway that could accommodate larger jets
The project team committed to delivering the completed runway in less than three years. The original project budget was set at $166 million (US)
![Page 4: Paving the way - icm.clsbe.lisboa.ucp.pticm.clsbe.lisboa.ucp.pt/docentes/url/jfr/pm/Paving the way.pdf · Ana Mafalda Roque Patrícia Gabriel Dan Naumov Benedikt Schulz Mariana Cadete.](https://reader034.fdocuments.in/reader034/viewer/2022051908/5ffc42564c10ee7f5035721f/html5/thumbnails/4.jpg)
Introduction
November 2000:
Project defined
and approved by
the client
September 2001
Terrorist attacks
impact financing
and slow project
December 2002
threats of
project failure,
Congress
approves a
temporary
financial
solution
May 2003
Paving
Begins
June 2003
First flight
lands on
the runway
July 2003
Sixty days before
completion, the
FAA request
flight checks to
verify the runway
control system
be accelerated
by 30 days
September 2003
Runway 16R/34L
opens to
commercial
traffic
![Page 5: Paving the way - icm.clsbe.lisboa.ucp.pticm.clsbe.lisboa.ucp.pt/docentes/url/jfr/pm/Paving the way.pdf · Ana Mafalda Roque Patrícia Gabriel Dan Naumov Benedikt Schulz Mariana Cadete.](https://reader034.fdocuments.in/reader034/viewer/2022051908/5ffc42564c10ee7f5035721f/html5/thumbnails/5.jpg)
Challenges
Upcoming next generation of larger jets
Need of a new model of runway constructions
No disruption of the daily operations
100% acceptance testing on all materials
Adjustment of the project schedule
9/11
![Page 6: Paving the way - icm.clsbe.lisboa.ucp.pticm.clsbe.lisboa.ucp.pt/docentes/url/jfr/pm/Paving the way.pdf · Ana Mafalda Roque Patrícia Gabriel Dan Naumov Benedikt Schulz Mariana Cadete.](https://reader034.fdocuments.in/reader034/viewer/2022051908/5ffc42564c10ee7f5035721f/html5/thumbnails/6.jpg)
Solutions - Methodologies
Initiating Process
Planning Process
Time Management
Procurement Management
![Page 7: Paving the way - icm.clsbe.lisboa.ucp.pticm.clsbe.lisboa.ucp.pt/docentes/url/jfr/pm/Paving the way.pdf · Ana Mafalda Roque Patrícia Gabriel Dan Naumov Benedikt Schulz Mariana Cadete.](https://reader034.fdocuments.in/reader034/viewer/2022051908/5ffc42564c10ee7f5035721f/html5/thumbnails/7.jpg)
Solutions - Methodologies
Risk Management Knowledge
Procurement Process
Ability to recover from
several setbacks
![Page 8: Paving the way - icm.clsbe.lisboa.ucp.pticm.clsbe.lisboa.ucp.pt/docentes/url/jfr/pm/Paving the way.pdf · Ana Mafalda Roque Patrícia Gabriel Dan Naumov Benedikt Schulz Mariana Cadete.](https://reader034.fdocuments.in/reader034/viewer/2022051908/5ffc42564c10ee7f5035721f/html5/thumbnails/8.jpg)
Tripple constraint
TC
Q
![Page 9: Paving the way - icm.clsbe.lisboa.ucp.pticm.clsbe.lisboa.ucp.pt/docentes/url/jfr/pm/Paving the way.pdf · Ana Mafalda Roque Patrícia Gabriel Dan Naumov Benedikt Schulz Mariana Cadete.](https://reader034.fdocuments.in/reader034/viewer/2022051908/5ffc42564c10ee7f5035721f/html5/thumbnails/9.jpg)
Quality
Contractors accent on quality
Government control (FAA)
Materials quality control and quality assurance team
Daily reports & weekly meetings
![Page 10: Paving the way - icm.clsbe.lisboa.ucp.pticm.clsbe.lisboa.ucp.pt/docentes/url/jfr/pm/Paving the way.pdf · Ana Mafalda Roque Patrícia Gabriel Dan Naumov Benedikt Schulz Mariana Cadete.](https://reader034.fdocuments.in/reader034/viewer/2022051908/5ffc42564c10ee7f5035721f/html5/thumbnails/10.jpg)
Time
30-day buffer
Jeppesen Charts updates
Multi-tasking approach to the project
Instead of delays, they took actions
Earlier finish
![Page 11: Paving the way - icm.clsbe.lisboa.ucp.pticm.clsbe.lisboa.ucp.pt/docentes/url/jfr/pm/Paving the way.pdf · Ana Mafalda Roque Patrícia Gabriel Dan Naumov Benedikt Schulz Mariana Cadete.](https://reader034.fdocuments.in/reader034/viewer/2022051908/5ffc42564c10ee7f5035721f/html5/thumbnails/11.jpg)
Cost
Team approach
“Accident” budget
$12M less
![Page 12: Paving the way - icm.clsbe.lisboa.ucp.pticm.clsbe.lisboa.ucp.pt/docentes/url/jfr/pm/Paving the way.pdf · Ana Mafalda Roque Patrícia Gabriel Dan Naumov Benedikt Schulz Mariana Cadete.](https://reader034.fdocuments.in/reader034/viewer/2022051908/5ffc42564c10ee7f5035721f/html5/thumbnails/12.jpg)
Results
First runway designed to handle the next generation of aircraft
Early finish – 18 days ahead of schedule
$12 million under budget
![Page 13: Paving the way - icm.clsbe.lisboa.ucp.pticm.clsbe.lisboa.ucp.pt/docentes/url/jfr/pm/Paving the way.pdf · Ana Mafalda Roque Patrícia Gabriel Dan Naumov Benedikt Schulz Mariana Cadete.](https://reader034.fdocuments.in/reader034/viewer/2022051908/5ffc42564c10ee7f5035721f/html5/thumbnails/13.jpg)
Recognition
PMI Mile Hi Chapter’s project of the year
![Page 14: Paving the way - icm.clsbe.lisboa.ucp.pticm.clsbe.lisboa.ucp.pt/docentes/url/jfr/pm/Paving the way.pdf · Ana Mafalda Roque Patrícia Gabriel Dan Naumov Benedikt Schulz Mariana Cadete.](https://reader034.fdocuments.in/reader034/viewer/2022051908/5ffc42564c10ee7f5035721f/html5/thumbnails/14.jpg)
Lessons learned
Establish an unofficial deadline
Detailed plan
Contingency budget
Tight and close control
Clear relationship with stakeholders
![Page 15: Paving the way - icm.clsbe.lisboa.ucp.pticm.clsbe.lisboa.ucp.pt/docentes/url/jfr/pm/Paving the way.pdf · Ana Mafalda Roque Patrícia Gabriel Dan Naumov Benedikt Schulz Mariana Cadete.](https://reader034.fdocuments.in/reader034/viewer/2022051908/5ffc42564c10ee7f5035721f/html5/thumbnails/15.jpg)
Project Management
Ana Mafalda Roque
Patrícia Gabriel
Dan Naumov
Benedikt Schulz
Mariana Cadete