From the desk of Gabriele Wood E-mail: [email protected] _____________________________________ 4 May 2016 Dear Stakeholder ENVIRONMENTAL IMPACT ASSESSMENT PROCESS PUBLIC PARTICIPATION PROCESS PAULPUTS CSP PROJECT, NORTHERN CAPE PROVINCE NOTIFICATION OF AVAILABILITY OF EIA REPORT AND PUBLIC MEETING Paulputs CSP RF (Pty) Ltd proposes the development of a 200MW Concentrated Solar Power (CSP) project and associated infrastructure. The project development site is located on Portion 4 of the Farm Scuitklip 92 which is located approximately 45km north-east of Pofadder within the Khai-Ma Local Municipality in the Northern Cape. The project is referred to as the Paulputs CSP Project. The purpose of the proposed CSP project is to evacuate the generated power into the Eskom electricity grid. The project is proposed to be bid into the Department of Energy’s (DoE) Renewable Energy Independent Power Producers Procurement (REIPPP) Programme. ENVIRONMENTAL IMPACT ASSESSMENT PROCESS In terms of Sections 24 and 24D of the National Environmental Management Act (Act No 107 of 1998), as read with Government Notices R982 to GN R985; an EIA process is being undertaken for this proposed project. The National Department of Environmental Affairs (DEA) is the competent authority. In order to obtain authorisation, comprehensive, independent environmental studies must be undertaken in accordance with the EIA Regulations, 2014. The DEA accepted the Scoping Report and Plan of Study for the project in February 2016. The application has been assigned the following reference number: 14/12/16/3/3/2/870. Paulputs CSP RF (Pty) Ltd has appointed Savannah Environmental (Pty) Ltd as the independent environmental consultant to undertake the required EIA to identify and assess all the potential environmental impacts associated with the proposed project, and propose appropriate mitigation and management measures in an Environmental Management Programme (EMPr). As part of these environmental studies, Interested and Affected (I&APs) will be actively involved through the public involvement process.

Transcript of Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

Page 1: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

From the desk of Gabriele Wood

E-mail: [email protected]_____________________________________

4 May 2016

Dear Stakeholder

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

PUBLIC PARTICIPATION PROCESS

PAULPUTS CSP PROJECT, NORTHERN CAPE PROVINCE

NOTIFICATION OF AVAILABILITY OF EIA REPORT AND PUBLIC MEETING

Paulputs CSP RF (Pty) Ltd proposes the development of a 200MW Concentrated

Solar Power (CSP) project and associated infrastructure. The project

development site is located on Portion 4 of the Farm Scuitklip 92 which is located

approximately 45km north-east of Pofadder within the Khai-Ma Local Municipality

in the Northern Cape. The project is referred to as the Paulputs CSP Project.

The purpose of the proposed CSP project is to evacuate the generated power into

the Eskom electricity grid. The project is proposed to be bid into the Department

of Energy’s (DoE) Renewable Energy Independent Power Producers Procurement

(REIPPP) Programme.

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

In terms of Sections 24 and 24D of the National Environmental Management Act

(Act No 107 of 1998), as read with Government Notices R982 to GN R985; an EIA

process is being undertaken for this proposed project. The National Department

of Environmental Affairs (DEA) is the competent authority. In order to obtain

authorisation, comprehensive, independent environmental studies must be

undertaken in accordance with the EIA Regulations, 2014. The DEA accepted the

Scoping Report and Plan of Study for the project in February 2016. The

application has been assigned the following reference number:

14/12/16/3/3/2/870.

Paulputs CSP RF (Pty) Ltd has appointed Savannah Environmental (Pty) Ltd as

the independent environmental consultant to undertake the required EIA to

identify and assess all the potential environmental impacts associated with the

proposed project, and propose appropriate mitigation and management measures

in an Environmental Management Programme (EMPr). As part of these

environmental studies, Interested and Affected (I&APs) will be actively involved

through the public involvement process.

Page 2: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

AVAILABILITY OF THE EIA REPORT FOR REVIEW

An EIA Report for the proposed project has been prepared by Savannah

Environmental and is available for review. The review period is from

4 May 2016 – 3 June 2016. The report can be viewed at the Pofadder Public

Library (New Road, Pofadder). The report can also be downloaded from the

website www.savannahsa.com/projects.

Please could you kindly submit your formal comments by sending written

correspondence in this regard. All comments received will be submitted in the

final EIA Report which will be submitted to the DEA. Comments can be made as

a written submission via fax, post or email.

PUBLIC MEETING

In order to facilitate comments on the EIA Report, a public meeting will be held

during the public review period as follows:

Date: Thursday 26 May 2016

Time: 17:30

Venue: Pofadder Civic Hall, Bree Street, Pofadder

The aim of the public meeting is to provide you with more information regarding

the proposed projects (including technical details, project process and timeframes

etc.), to provide a summary of the findings of the Environmental Impact

Assessment Report, to invite comment on the proposed project, and to further

discuss possible issues of specific concern to you which may need to be

addressed.

Please do not hesitate to contact us should you require additional information

and/or clarification regarding the proposed project. Our team welcomes your

participation and looks forward to your involvement throughout this process.

Kind Regards

MRS GABRIELE WOOD

PUBLIC PARTICIPATION AND SOCIAL CONSULTANT

SAVANNAH ENVIRONMENTAL

Page 3: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

EIA PROCESS - PAULPUTS CSP PROJECT, NORTHERN CAPE PROVINCE -

NOTIFICATION OF AVAILABILITY OF EIA REPORT AND PUBLIC MEETING

Assigned to:

Teams: Global Project: Paulputs CSP Tower Facility, NC

From: Gabriele Wood <[email protected]>

To:

Cc:

Bcc: Amanda Bester <[email protected]>, Alistair Silo <[email protected]>, Chris

Fortuin <[email protected]>, Francois van der Heerver <[email protected]>,

Steven Shibambu <[email protected]>, Samantha Ralston <[email protected]>,

Brian Fisher <[email protected]>, Nonhlahla Mkhwanazi

<[email protected]>, Adrian Tiplady <[email protected]>, Jillian Nortje

<[email protected]>, Constant Hoogstad <[email protected]>, Vered Karty

<[email protected]>, Simon Gear <[email protected]>, Peter Cloete

<[email protected]>, Tabbie Roberts <[email protected]>, Leonard Shaw

<[email protected]>, Shaun Cloete <[email protected]>, John Geeringh

<[email protected]>, Jannie Loubser <[email protected]>, Ratha

Andrew Timothy <[email protected]>, Phillip Hine <[email protected]>, Immanuel

Smith <[email protected]>, Jaco Roelefse <[email protected]>, Lizell

Stroh <[email protected]>, Niell van Rensburg <[email protected]>, Jasper

Nieuwoudt <[email protected]>, Skumsa Mancotywa

<[email protected]>, Roger Basson <[email protected]>, Melanie

Miles <[email protected]>, Debbie Hardin <[email protected]>, Jacoline Mans

<[email protected]>, Lukas van Zyl <[email protected]>, Chris Schutte

<[email protected]>, Johan Koegelenberg <[email protected]>, Conrad

Geldenhuys <[email protected]>, Julian Lopez Garrido

<[email protected]>, Henry Raman <[email protected]>, Louis van Heerden

<[email protected]>, Pule Ramaleho Ramaleho Saila

<[email protected]>, Jenetta Sophia Hennig <[email protected]>, Onwabile

Ndzumo <[email protected]>, Thoko Buthelezi <[email protected]>, Mere Kgampe

<[email protected]>, Obakeng Isaacs <[email protected]>, Nozizwe

Makgalemele <[email protected]>, Abe Abrahams <[email protected]>,

Sunday Mabaso <[email protected]>, Karen van Schalkwyk

<[email protected]>, Wonders Dimakatso Viljoen Mothibi

<[email protected]>, Mashudu Marubini <[email protected]>, Charles

Gregory March <[email protected]>, Pheladi Masipa

<[email protected]>, René de Kock <[email protected]>

Subject: EIA PROCESS - PAULPUTS CSP PROJECT, NORTHERN CAPE PROVINCE -

NOTIFICATION OF AVAILABILITY OF EIA REPORT AND PUBLIC MEETING

Body: Dear Stakeholder

Forward

Projects Organisations Stakeholders Calendar Reports Emails more

Search

© 2012 SugarCRM Inc.

EIA PROCESS - PAULPUTS CSP PROJECT, NORTHERN CAPE ... http://savannahsa.sugar-crm.co.za/index.php?module=Emails&action...

1 of 4 04/05/2016 17:19

Page 4: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

on Portion 4 of the Farm Scuitklip 92 which is located approximately 45km north-east of

Pofadder within the Khai-Ma Local Municipality in the Northern Cape. The project is referred

to as the Paulputs CSP Project. Paulputs CSP RF (Pty) Ltd has appointed Savannah

Environmental (Pty) Ltd as the independent environmental consultant to undertake the

required EIA to identify and assess all the potential environmental impacts associated with

the proposed project. An EIA Report for the proposed project has been prepared by

Savannah Environmental and is available for review. Please refer to the attached notification

letter for further details regarding the availability of the EIA Report and Public Meeting.

Please do not hesitate to contact me if you have any queries in this regard.

Kind regards

Mrs Gabriele Wood

Public Participation and Social Consultant

Savannah Environmental (Pty) Ltd

Tel: 27 11 656 3237

Fax: 086 684 0547

Email: [email protected]

www.savannahsa.com

Show Plain Text

Attachments: Paulputs CSP DEIAr Notification 3.05.2016.pdf

Activities

(0 - 0 of 0)

Subject Status ContactDueDate

AssignedUser

Attachments

(1 - 1 of 1)

Subject ContactLastModified

Paulputs CSP DEIAr Notification 3.05.2016.pdf04/05/201617.18

Accounts

edit

© 2012 SugarCRM Inc.

Projects Organisations Stakeholders Calendar Reports Emails more

EIA PROCESS - PAULPUTS CSP PROJECT, NORTHERN CAPE ... http://savannahsa.sugar-crm.co.za/index.php?module=Emails&action...

2 of 4 04/05/2016 17:19

Page 5: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

From the desk of Gabriele Wood

E-mail: [email protected]_____________________________________

4 May 2016

Department of Agriculture, Forestry & Fisheries

Delpen Building, Office 270

Cnr Annie Botha & Union Streets

Pretoria

0084

Tel: 012-319-7619

Email: [email protected]

Dear Ms. Mashudu Marubini

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

PUBLIC PARTICIPATION PROCESS

PAULPUTS CSP PROJECT, NORTHERN CAPE PROVINCE

(DEA REF. No. 14/12/16/3/3/2/870)

NOTIFICATION OF AVAILABILITY OF EIA REPORT AND PUBLIC MEETING

Paulputs CSP RF (Pty) Ltd proposes the development of a 200MW Concentrated Solar Power

(CSP) project and associated infrastructure. The project development site is located on

Portion 4 of the Farm Scuitklip 92 which is located approximately 45km north-east of

Pofadder within the Khai-Ma Local Municipality in the Northern Cape. The project is referred

to as the Paulputs CSP Project.

The purpose of the proposed CSP project is to evacuate the generated power into the Eskom

electricity grid. The project is proposed to be bid into the Department of Energy’s (DoE)

Renewable Energy Independent Power Producers Procurement (REIPPP) Programme.

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

In terms of Sections 24 and 24D of the National Environmental Management Act (Act No

107 of 1998), as read with Government Notices R982 to GN R985; an EIA process is being

undertaken for this proposed project. The National Department of Environmental Affairs

(DEA) is the competent authority. In order to obtain authorisation, comprehensive,

independent environmental studies must be undertaken in accordance with the EIA

Regulations, 2014. The DEA accepted the Scoping Report and Plan of Study for the project

in February 2016. The application has been assigned the following reference number:

14/12/16/3/3/2/870.

Paulputs CSP RF (Pty) Ltd has appointed Savannah Environmental (Pty) Ltd as the

independent environmental consultant to undertake the required EIA to identify and assess

all the potential environmental impacts associated with the proposed project, and propose

appropriate mitigation and management measures in an Environmental Management

Programme (EMPr).

Page 6: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

As part of these environmental studies, Interested and Affected (I&APs) will be actively

involved through the public involvement process.

AVAILABILITY OF THE EIA REPORT FOR REVIEW

An EIA Report for the proposed project has been prepared by Savannah Environmental and

is available for review. The review period is from 4 May 2016 – 3 June 2016. The report

can be viewed at the Pofadder Public Library (New Road, Pofadder). The report can also be

downloaded from the website www.savannahsa.com/projects.

Please could you kindly submit your formal comments by sending written correspondence in

this regard. All comments received will be submitted in the final EIA Report which will be

submitted to the DEA. Comments can be made as a written submission via fax, post or

email.

PUBLIC MEETING

In order to facilitate comments on the EIA Report, a public meeting will be held during the

public review period as follows:

Date: Thursday 26 May 2016

Time: 17:30

Venue: Pofadder Civic Hall, Bree Street, Pofadder

The aim of the public meeting is to provide you with more information regarding the

proposed projects (including technical details, project process and timeframes etc.), to

provide a summary of the findings of the Environmental Impact Assessment Report, to invite

comment on the proposed project, and to further discuss possible issues of specific concern

to you which may need to be addressed.

Please do not hesitate to contact us should you require additional information and/or

clarification regarding the proposed project. Our team welcomes your participation and

looks forward to your involvement throughout this process.

Kind Regards

MRS GABRIELE WOOD

PUBLIC PARTICIPATION AND SOCIAL CONSULTANT

SAVANNAH ENVIRONMENTAL

Page 7: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

From the desk of Gabriele Wood

E-mail: [email protected]_____________________________________

4 May 2016

Department of Agriculture, Forestry & Fisheries

DAFF Directorate: Forestry Management

Louisvale Road

Upington

8800

Tel: 054-338-5909

Email: [email protected]

Dear Ms. Jacoline Mans

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

PUBLIC PARTICIPATION PROCESS

PAULPUTS CSP PROJECT, NORTHERN CAPE PROVINCE

(DEA REF. No. 14/12/16/3/3/2/870)

NOTIFICATION OF AVAILABILITY OF EIA REPORT AND PUBLIC MEETING

Paulputs CSP RF (Pty) Ltd proposes the development of a 200MW Concentrated Solar Power

(CSP) project and associated infrastructure. The project development site is located on

Portion 4 of the Farm Scuitklip 92 which is located approximately 45km north-east of

Pofadder within the Khai-Ma Local Municipality in the Northern Cape. The project is referred

to as the Paulputs CSP Project.

The purpose of the proposed CSP project is to evacuate the generated power into the Eskom

electricity grid. The project is proposed to be bid into the Department of Energy’s (DoE)

Renewable Energy Independent Power Producers Procurement (REIPPP) Programme.

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

In terms of Sections 24 and 24D of the National Environmental Management Act (Act No

107 of 1998), as read with Government Notices R982 to GN R985; an EIA process is being

undertaken for this proposed project. The National Department of Environmental Affairs

(DEA) is the competent authority. In order to obtain authorisation, comprehensive,

independent environmental studies must be undertaken in accordance with the EIA

Regulations, 2014. The DEA accepted the Scoping Report and Plan of Study for the project

in February 2016. The application has been assigned the following reference number:

14/12/16/3/3/2/870.

Paulputs CSP RF (Pty) Ltd has appointed Savannah Environmental (Pty) Ltd as the

independent environmental consultant to undertake the required EIA to identify and assess

all the potential environmental impacts associated with the proposed project, and propose

appropriate mitigation and management measures in an Environmental Management

Programme (EMPr).

Page 8: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

As part of these environmental studies, Interested and Affected (I&APs) will be actively

involved through the public involvement process.

AVAILABILITY OF THE EIA REPORT FOR REVIEW

An EIA Report for the proposed project has been prepared by Savannah Environmental and

is available for review. The review period is from 4 May 2016 – 3 June 2016. The report

can be viewed at the Pofadder Public Library (New Road, Pofadder). The report can also be

downloaded from the website www.savannahsa.com/projects.

Please could you kindly submit your formal comments by sending written correspondence in

this regard. All comments received will be submitted in the final EIA Report which will be

submitted to the DEA. Comments can be made as a written submission via fax, post or

email.

PUBLIC MEETING

In order to facilitate comments on the EIA Report, a public meeting will be held during the

public review period as follows:

Date: Thursday 26 May 2016

Time: 17:30

Venue: Pofadder Civic Hall, Bree Street, Pofadder

The aim of the public meeting is to provide you with more information regarding the

proposed projects (including technical details, project process and timeframes etc.), to

provide a summary of the findings of the Environmental Impact Assessment Report, to invite

comment on the proposed project, and to further discuss possible issues of specific concern

to you which may need to be addressed.

Please do not hesitate to contact us should you require additional information and/or

clarification regarding the proposed project. Our team welcomes your participation and

looks forward to your involvement throughout this process.

Kind Regards

MRS GABRIELE WOOD

PUBLIC PARTICIPATION AND SOCIAL CONSULTANT

SAVANNAH ENVIRONMENTAL

Page 9: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

From the desk of Gabriele Wood

E-mail: [email protected]_____________________________________

4 May 2016

Department of Agriculture, Forestry & Fisheries

Delpen Building, Office 270

Cnr Annie Botha and Union Street

Pretoria

0084

Tel: 012-319-7634

Email: [email protected]

Dear Ms. Thoko Buthelezi

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

PUBLIC PARTICIPATION PROCESS

PAULPUTS CSP PROJECT, NORTHERN CAPE PROVINCE

(DEA REF. No. 14/12/16/3/3/2/870)

NOTIFICATION OF AVAILABILITY OF EIA REPORT AND PUBLIC MEETING

Paulputs CSP RF (Pty) Ltd proposes the development of a 200MW Concentrated Solar Power

(CSP) project and associated infrastructure. The project development site is located on

Portion 4 of the Farm Scuitklip 92 which is located approximately 45km north-east of

Pofadder within the Khai-Ma Local Municipality in the Northern Cape. The project is referred

to as the Paulputs CSP Project.

The purpose of the proposed CSP project is to evacuate the generated power into the Eskom

electricity grid. The project is proposed to be bid into the Department of Energy’s (DoE)

Renewable Energy Independent Power Producers Procurement (REIPPP) Programme.

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

In terms of Sections 24 and 24D of the National Environmental Management Act (Act No

107 of 1998), as read with Government Notices R982 to GN R985; an EIA process is being

undertaken for this proposed project. The National Department of Environmental Affairs

(DEA) is the competent authority. In order to obtain authorisation, comprehensive,

independent environmental studies must be undertaken in accordance with the EIA

Regulations, 2014. The DEA accepted the Scoping Report and Plan of Study for the project

in February 2016. The application has been assigned the following reference number:

14/12/16/3/3/2/870.

Paulputs CSP RF (Pty) Ltd has appointed Savannah Environmental (Pty) Ltd as the

independent environmental consultant to undertake the required EIA to identify and assess

all the potential environmental impacts associated with the proposed project, and propose

appropriate mitigation and management measures in an Environmental Management

Programme (EMPr).

Page 10: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

As part of these environmental studies, Interested and Affected (I&APs) will be actively

involved through the public involvement process.

AVAILABILITY OF THE EIA REPORT FOR REVIEW

An EIA Report for the proposed project has been prepared by Savannah Environmental and

is available for review. The review period is from 4 May 2016 – 3 June 2016. The report

can be viewed at the Pofadder Public Library (New Road, Pofadder). The report can also be

downloaded from the website www.savannahsa.com/projects.

Please could you kindly submit your formal comments by sending written correspondence in

this regard. All comments received will be submitted in the final EIA Report which will be

submitted to the DEA. Comments can be made as a written submission via fax, post or

email.

PUBLIC MEETING

In order to facilitate comments on the EIA Report, a public meeting will be held during the

public review period as follows:

Date: Thursday 26 May 2016

Time: 17:30

Venue: Pofadder Civic Hall, Bree Street, Pofadder

The aim of the public meeting is to provide you with more information regarding the

proposed projects (including technical details, project process and timeframes etc.), to

provide a summary of the findings of the Environmental Impact Assessment Report, to invite

comment on the proposed project, and to further discuss possible issues of specific concern

to you which may need to be addressed.

Please do not hesitate to contact us should you require additional information and/or

clarification regarding the proposed project. Our team welcomes your participation and

looks forward to your involvement throughout this process.

Kind Regards

MRS GABRIELE WOOD

PUBLIC PARTICIPATION AND SOCIAL CONSULTANT

SAVANNAH ENVIRONMENTAL

Page 11: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

From the desk of Gabriele Wood

E-mail: [email protected]_____________________________________

4 May 2016

Department of Energy

Perm Building

65 Phakamile Mabija Street

Kimberley

8301

Tel: 053-807-1752

Attention: Director Northern Cape

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

PUBLIC PARTICIPATION PROCESS

PAULPUTS CSP PROJECT, NORTHERN CAPE PROVINCE

(DEA REF. No. 14/12/16/3/3/2/870)

NOTIFICATION OF AVAILABILITY OF EIA REPORT AND PUBLIC MEETING

Dear Sir/Madam

Paulputs CSP RF (Pty) Ltd proposes the development of a 200MW Concentrated Solar Power

(CSP) project and associated infrastructure. The project development site is located on

Portion 4 of the Farm Scuitklip 92 which is located approximately 45km north-east of

Pofadder within the Khai-Ma Local Municipality in the Northern Cape. The project is referred

to as the Paulputs CSP Project.

The purpose of the proposed CSP project is to evacuate the generated power into the Eskom

electricity grid. The project is proposed to be bid into the Department of Energy’s (DoE)

Renewable Energy Independent Power Producers Procurement (REIPPP) Programme.

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

In terms of Sections 24 and 24D of the National Environmental Management Act (Act No

107 of 1998), as read with Government Notices R982 to GN R985; an EIA process is being

undertaken for this proposed project. The National Department of Environmental Affairs

(DEA) is the competent authority. In order to obtain authorisation, comprehensive,

independent environmental studies must be undertaken in accordance with the EIA

Regulations, 2014. The DEA accepted the Scoping Report and Plan of Study for the project

in February 2016. The application has been assigned the following reference number:

14/12/16/3/3/2/870.

Paulputs CSP RF (Pty) Ltd has appointed Savannah Environmental (Pty) Ltd as the

independent environmental consultant to undertake the required EIA to identify and assess

all the potential environmental impacts associated with the proposed project, and propose

appropriate mitigation and management measures in an Environmental Management

Programme (EMPr).

Page 12: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

As part of these environmental studies, Interested and Affected (I&APs) will be actively

involved through the public involvement process.

AVAILABILITY OF THE EIA REPORT FOR REVIEW

An EIA Report for the proposed project has been prepared by Savannah Environmental and

is available for review. The review period is from 4 May 2016 – 3 June 2016. The report

can be viewed at the Pofadder Public Library (New Road, Pofadder). The report can also be

downloaded from the website www.savannahsa.com/projects.

Please could you kindly submit your formal comments by sending written correspondence in

this regard. All comments received will be submitted in the final EIA Report which will be

submitted to the DEA. Comments can be made as a written submission via fax, post or

email.

PUBLIC MEETING

In order to facilitate comments on the EIA Report, a public meeting will be held during the

public review period as follows:

Date: Thursday 26 May 2016

Time: 17:30

Venue: Pofadder Civic Hall, Bree Street, Pofadder

The aim of the public meeting is to provide you with more information regarding the

proposed projects (including technical details, project process and timeframes etc.), to

provide a summary of the findings of the Environmental Impact Assessment Report, to invite

comment on the proposed project, and to further discuss possible issues of specific concern

to you which may need to be addressed.

Please do not hesitate to contact us should you require additional information and/or

clarification regarding the proposed project. Our team welcomes your participation and

looks forward to your involvement throughout this process.

Kind Regards

MRS GABRIELE WOOD

PUBLIC PARTICIPATION AND SOCIAL CONSULTANT

SAVANNAH ENVIRONMENTAL

Page 13: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

From the desk of Gabriele Wood

E-mail: [email protected]_____________________________________

4 May 2016

Department of Energy

192 Visagie Street

Pretoria

0002

Tel: 012-406-7650

Email: [email protected]

Dear Mr. Pheladi Masipa

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

PUBLIC PARTICIPATION PROCESS

PAULPUTS CSP PROJECT, NORTHERN CAPE PROVINCE

(DEA REF. No. 14/12/16/3/3/2/870)

NOTIFICATION OF AVAILABILITY OF EIA REPORT AND PUBLIC MEETING

Paulputs CSP RF (Pty) Ltd proposes the development of a 200MW Concentrated Solar Power

(CSP) project and associated infrastructure. The project development site is located on

Portion 4 of the Farm Scuitklip 92 which is located approximately 45km north-east of

Pofadder within the Khai-Ma Local Municipality in the Northern Cape. The project is referred

to as the Paulputs CSP Project.

The purpose of the proposed CSP project is to evacuate the generated power into the Eskom

electricity grid. The project is proposed to be bid into the Department of Energy’s (DoE)

Renewable Energy Independent Power Producers Procurement (REIPPP) Programme.

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

In terms of Sections 24 and 24D of the National Environmental Management Act (Act No

107 of 1998), as read with Government Notices R982 to GN R985; an EIA process is being

undertaken for this proposed project. The National Department of Environmental Affairs

(DEA) is the competent authority. In order to obtain authorisation, comprehensive,

independent environmental studies must be undertaken in accordance with the EIA

Regulations, 2014. The DEA accepted the Scoping Report and Plan of Study for the project

in February 2016. The application has been assigned the following reference number:

14/12/16/3/3/2/870.

Paulputs CSP RF (Pty) Ltd has appointed Savannah Environmental (Pty) Ltd as the

independent environmental consultant to undertake the required EIA to identify and assess

all the potential environmental impacts associated with the proposed project, and propose

appropriate mitigation and management measures in an Environmental Management

Programme (EMPr).

Page 14: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

As part of these environmental studies, Interested and Affected (I&APs) will be actively

involved through the public involvement process.

AVAILABILITY OF THE EIA REPORT FOR REVIEW

An EIA Report for the proposed project has been prepared by Savannah Environmental and

is available for review. The review period is from 4 May 2016 – 3 June 2016. The report

can be viewed at the Pofadder Public Library (New Road, Pofadder). The report can also be

downloaded from the website www.savannahsa.com/projects.

Please could you kindly submit your formal comments by sending written correspondence in

this regard. All comments received will be submitted in the final EIA Report which will be

submitted to the DEA. Comments can be made as a written submission via fax, post or

email.

PUBLIC MEETING

In order to facilitate comments on the EIA Report, a public meeting will be held during the

public review period as follows:

Date: Thursday 26 May 2016

Time: 17:30

Venue: Pofadder Civic Hall, Bree Street, Pofadder

The aim of the public meeting is to provide you with more information regarding the

proposed projects (including technical details, project process and timeframes etc.), to

provide a summary of the findings of the Environmental Impact Assessment Report, to invite

comment on the proposed project, and to further discuss possible issues of specific concern

to you which may need to be addressed.

Please do not hesitate to contact us should you require additional information and/or

clarification regarding the proposed project. Our team welcomes your participation and

looks forward to your involvement throughout this process.

Kind Regards

MRS GABRIELE WOOD

PUBLIC PARTICIPATION AND SOCIAL CONSULTANT

SAVANNAH ENVIRONMENTAL

Page 15: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

From the desk of Gabriele Wood

E-mail: [email protected]_____________________________________

4 May 2016

Department of Environmental Affairs

Environment House

473 Steve Biko Road

Pretoria

0001

Tel: 012-399-9514

Email: [email protected]

Dear Ms. Skumsa Mancotywa

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

PUBLIC PARTICIPATION PROCESS

PAULPUTS CSP PROJECT, NORTHERN CAPE PROVINCE

(DEA REF. No. 14/12/16/3/3/2/870)

NOTIFICATION OF AVAILABILITY OF EIA REPORT AND PUBLIC MEETING

Paulputs CSP RF (Pty) Ltd proposes the development of a 200MW Concentrated Solar Power

(CSP) project and associated infrastructure. The project development site is located on

Portion 4 of the Farm Scuitklip 92 which is located approximately 45km north-east of

Pofadder within the Khai-Ma Local Municipality in the Northern Cape. The project is referred

to as the Paulputs CSP Project.

The purpose of the proposed CSP project is to evacuate the generated power into the Eskom

electricity grid. The project is proposed to be bid into the Department of Energy’s (DoE)

Renewable Energy Independent Power Producers Procurement (REIPPP) Programme.

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

In terms of Sections 24 and 24D of the National Environmental Management Act (Act No

107 of 1998), as read with Government Notices R982 to GN R985; an EIA process is being

undertaken for this proposed project. The National Department of Environmental Affairs

(DEA) is the competent authority. In order to obtain authorisation, comprehensive,

independent environmental studies must be undertaken in accordance with the EIA

Regulations, 2014. The DEA accepted the Scoping Report and Plan of Study for the project

in February 2016. The application has been assigned the following reference number:

14/12/16/3/3/2/870.

Paulputs CSP RF (Pty) Ltd has appointed Savannah Environmental (Pty) Ltd as the

independent environmental consultant to undertake the required EIA to identify and assess

all the potential environmental impacts associated with the proposed project, and propose

appropriate mitigation and management measures in an Environmental Management

Programme (EMPr).

Page 16: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

As part of these environmental studies, Interested and Affected (I&APs) will be actively

involved through the public involvement process.

AVAILABILITY OF THE EIA REPORT FOR REVIEW

An EIA Report for the proposed project has been prepared by Savannah Environmental and

is available for review. The review period is from 4 May 2016 – 3 June 2016. The report

can be viewed at the Pofadder Public Library (New Road, Pofadder). The report can also be

downloaded from the website www.savannahsa.com/projects.

Please could you kindly submit your formal comments by sending written correspondence in

this regard. All comments received will be submitted in the final EIA Report which will be

submitted to the DEA. Comments can be made as a written submission via fax, post or

email.

PUBLIC MEETING

In order to facilitate comments on the EIA Report, a public meeting will be held during the

public review period as follows:

Date: Thursday 26 May 2016

Time: 17:30

Venue: Pofadder Civic Hall, Bree Street, Pofadder

The aim of the public meeting is to provide you with more information regarding the

proposed projects (including technical details, project process and timeframes etc.), to

provide a summary of the findings of the Environmental Impact Assessment Report, to invite

comment on the proposed project, and to further discuss possible issues of specific concern

to you which may need to be addressed.

Please do not hesitate to contact us should you require additional information and/or

clarification regarding the proposed project. Our team welcomes your participation and

looks forward to your involvement throughout this process.

Kind Regards

MRS GABRIELE WOOD

PUBLIC PARTICIPATION AND SOCIAL CONSULTANT

SAVANNAH ENVIRONMENTAL

Page 17: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

From the desk of Gabriele Wood

E-mail: [email protected]_____________________________________

4 May 2016

Department of Mineral Resources

Perm Building

65 Phakamile Mabija Street

Kimberley

8300

Tel: 053-807-1700

Email: [email protected]

Dear Mr. Sunday Mabaso

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

PUBLIC PARTICIPATION PROCESS

PAULPUTS CSP PROJECT, NORTHERN CAPE PROVINCE

(DEA REF. No. 14/12/16/3/3/2/870)

NOTIFICATION OF AVAILABILITY OF EIA REPORT AND PUBLIC MEETING

Paulputs CSP RF (Pty) Ltd proposes the development of a 200MW Concentrated Solar Power

(CSP) project and associated infrastructure. The project development site is located on

Portion 4 of the Farm Scuitklip 92 which is located approximately 45km north-east of

Pofadder within the Khai-Ma Local Municipality in the Northern Cape. The project is referred

to as the Paulputs CSP Project.

The purpose of the proposed CSP project is to evacuate the generated power into the Eskom

electricity grid. The project is proposed to be bid into the Department of Energy’s (DoE)

Renewable Energy Independent Power Producers Procurement (REIPPP) Programme.

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

In terms of Sections 24 and 24D of the National Environmental Management Act (Act No

107 of 1998), as read with Government Notices R982 to GN R985; an EIA process is being

undertaken for this proposed project. The National Department of Environmental Affairs

(DEA) is the competent authority. In order to obtain authorisation, comprehensive,

independent environmental studies must be undertaken in accordance with the EIA

Regulations, 2014. The DEA accepted the Scoping Report and Plan of Study for the project

in February 2016. The application has been assigned the following reference number:

14/12/16/3/3/2/870.

Paulputs CSP RF (Pty) Ltd has appointed Savannah Environmental (Pty) Ltd as the

independent environmental consultant to undertake the required EIA to identify and assess

all the potential environmental impacts associated with the proposed project, and propose

appropriate mitigation and management measures in an Environmental Management

Programme (EMPr).

Page 18: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

As part of these environmental studies, Interested and Affected (I&APs) will be actively

involved through the public involvement process.

AVAILABILITY OF THE EIA REPORT FOR REVIEW

An EIA Report for the proposed project has been prepared by Savannah Environmental and

is available for review. The review period is from 4 May 2016 – 3 June 2016. The report

can be viewed at the Pofadder Public Library (New Road, Pofadder). The report can also be

downloaded from the website www.savannahsa.com/projects.

Please could you kindly submit your formal comments by sending written correspondence in

this regard. All comments received will be submitted in the final EIA Report which will be

submitted to the DEA. Comments can be made as a written submission via fax, post or

email.

PUBLIC MEETING

In order to facilitate comments on the EIA Report, a public meeting will be held during the

public review period as follows:

Date: Thursday 26 May 2016

Time: 17:30

Venue: Pofadder Civic Hall, Bree Street, Pofadder

The aim of the public meeting is to provide you with more information regarding the

proposed projects (including technical details, project process and timeframes etc.), to

provide a summary of the findings of the Environmental Impact Assessment Report, to invite

comment on the proposed project, and to further discuss possible issues of specific concern

to you which may need to be addressed.

Please do not hesitate to contact us should you require additional information and/or

clarification regarding the proposed project. Our team welcomes your participation and

looks forward to your involvement throughout this process.

Kind Regards

MRS GABRIELE WOOD

PUBLIC PARTICIPATION AND SOCIAL CONSULTANT

SAVANNAH ENVIRONMENTAL

Page 19: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

From the desk of Gabriele Wood

E-mail: [email protected]_____________________________________

4 May 2016

Department of Mineral Resources

Hopley Centre, cnr of Van der stel & Van Riebeeck Streets

Springbok

8240

Tel: 027-712-8160

Email: [email protected]

Dear Mr. Jasper Nieuwoudt

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

PUBLIC PARTICIPATION PROCESS

PAULPUTS CSP PROJECT, NORTHERN CAPE PROVINCE

(DEA REF. No. 14/12/16/3/3/2/870)

NOTIFICATION OF AVAILABILITY OF EIA REPORT AND PUBLIC MEETING

Paulputs CSP RF (Pty) Ltd proposes the development of a 200MW Concentrated Solar Power

(CSP) project and associated infrastructure. The project development site is located on

Portion 4 of the Farm Scuitklip 92 which is located approximately 45km north-east of

Pofadder within the Khai-Ma Local Municipality in the Northern Cape. The project is referred

to as the Paulputs CSP Project.

The purpose of the proposed CSP project is to evacuate the generated power into the Eskom

electricity grid. The project is proposed to be bid into the Department of Energy’s (DoE)

Renewable Energy Independent Power Producers Procurement (REIPPP) Programme.

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

In terms of Sections 24 and 24D of the National Environmental Management Act (Act No

107 of 1998), as read with Government Notices R982 to GN R985; an EIA process is being

undertaken for this proposed project. The National Department of Environmental Affairs

(DEA) is the competent authority. In order to obtain authorisation, comprehensive,

independent environmental studies must be undertaken in accordance with the EIA

Regulations, 2014. The DEA accepted the Scoping Report and Plan of Study for the project

in February 2016. The application has been assigned the following reference number:

14/12/16/3/3/2/870.

Paulputs CSP RF (Pty) Ltd has appointed Savannah Environmental (Pty) Ltd as the

independent environmental consultant to undertake the required EIA to identify and assess

all the potential environmental impacts associated with the proposed project, and propose

appropriate mitigation and management measures in an Environmental Management

Programme (EMPr).

Page 20: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

As part of these environmental studies, Interested and Affected (I&APs) will be actively

involved through the public involvement process.

AVAILABILITY OF THE EIA REPORT FOR REVIEW

An EIA Report for the proposed project has been prepared by Savannah Environmental and

is available for review. The review period is from 4 May 2016 – 3 June 2016. The report

can be viewed at the Pofadder Public Library (New Road, Pofadder). The report can also be

downloaded from the website www.savannahsa.com/projects.

Please could you kindly submit your formal comments by sending written correspondence in

this regard. All comments received will be submitted in the final EIA Report which will be

submitted to the DEA. Comments can be made as a written submission via fax, post or

email.

PUBLIC MEETING

In order to facilitate comments on the EIA Report, a public meeting will be held during the

public review period as follows:

Date: Thursday 26 May 2016

Time: 17:30

Venue: Pofadder Civic Hall, Bree Street, Pofadder

The aim of the public meeting is to provide you with more information regarding the

proposed projects (including technical details, project process and timeframes etc.), to

provide a summary of the findings of the Environmental Impact Assessment Report, to invite

comment on the proposed project, and to further discuss possible issues of specific concern

to you which may need to be addressed.

Please do not hesitate to contact us should you require additional information and/or

clarification regarding the proposed project. Our team welcomes your participation and

looks forward to your involvement throughout this process.

Kind Regards

MRS GABRIELE WOOD

PUBLIC PARTICIPATION AND SOCIAL CONSULTANT

SAVANNAH ENVIRONMENTAL

Page 21: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

From the desk of Gabriele Wood

E-mail: [email protected]_____________________________________

4 May 2016

Department of Water and Sanitation

Louisvale Road

Upington

8800

Tel: 054-338-5800

Email: [email protected]

Dear Mr. Steven Shibambu

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

PUBLIC PARTICIPATION PROCESS

PAULPUTS CSP PROJECT, NORTHERN CAPE PROVINCE

(DEA REF. No. 14/12/16/3/3/2/870)

NOTIFICATION OF AVAILABILITY OF EIA REPORT AND PUBLIC MEETING

Paulputs CSP RF (Pty) Ltd proposes the development of a 200MW Concentrated Solar Power

(CSP) project and associated infrastructure. The project development site is located on

Portion 4 of the Farm Scuitklip 92 which is located approximately 45km north-east of

Pofadder within the Khai-Ma Local Municipality in the Northern Cape. The project is referred

to as the Paulputs CSP Project.

The purpose of the proposed CSP project is to evacuate the generated power into the Eskom

electricity grid. The project is proposed to be bid into the Department of Energy’s (DoE)

Renewable Energy Independent Power Producers Procurement (REIPPP) Programme.

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

In terms of Sections 24 and 24D of the National Environmental Management Act (Act No

107 of 1998), as read with Government Notices R982 to GN R985; an EIA process is being

undertaken for this proposed project. The National Department of Environmental Affairs

(DEA) is the competent authority. In order to obtain authorisation, comprehensive,

independent environmental studies must be undertaken in accordance with the EIA

Regulations, 2014. The DEA accepted the Scoping Report and Plan of Study for the project

in February 2016. The application has been assigned the following reference number:

14/12/16/3/3/2/870.

Paulputs CSP RF (Pty) Ltd has appointed Savannah Environmental (Pty) Ltd as the

independent environmental consultant to undertake the required EIA to identify and assess

all the potential environmental impacts associated with the proposed project, and propose

appropriate mitigation and management measures in an Environmental Management

Programme (EMPr).

Page 22: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

As part of these environmental studies, Interested and Affected (I&APs) will be actively

involved through the public involvement process.

AVAILABILITY OF THE EIA REPORT FOR REVIEW

An EIA Report for the proposed project has been prepared by Savannah Environmental and

is available for review. The review period is from 4 May 2016 – 3 June 2016. The report

can be viewed at the Pofadder Public Library (New Road, Pofadder). The report can also be

downloaded from the website www.savannahsa.com/projects.

Please could you kindly submit your formal comments by sending written correspondence in

this regard. All comments received will be submitted in the final EIA Report which will be

submitted to the DEA. Comments can be made as a written submission via fax, post or

email.

PUBLIC MEETING

In order to facilitate comments on the EIA Report, a public meeting will be held during the

public review period as follows:

Date: Thursday 26 May 2016

Time: 17:30

Venue: Pofadder Civic Hall, Bree Street, Pofadder

The aim of the public meeting is to provide you with more information regarding the

proposed projects (including technical details, project process and timeframes etc.), to

provide a summary of the findings of the Environmental Impact Assessment Report, to invite

comment on the proposed project, and to further discuss possible issues of specific concern

to you which may need to be addressed.

Please do not hesitate to contact us should you require additional information and/or

clarification regarding the proposed project. Our team welcomes your participation and

looks forward to your involvement throughout this process.

Kind Regards

MRS GABRIELE WOOD

PUBLIC PARTICIPATION AND SOCIAL CONSULTANT

SAVANNAH ENVIRONMENTAL

Page 23: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

From the desk of Gabriele Wood

E-mail: [email protected]_____________________________________

4 May 2016

Eskom Holdings SOC Ltd

Megawatt Park

Maxwell Drive

Sunninghill

2157

Tel: 011-516-7233

Email: [email protected]

Dear Mr. John Geeringh

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

PUBLIC PARTICIPATION PROCESS

PAULPUTS CSP PROJECT, NORTHERN CAPE PROVINCE

(DEA REF. No. 14/12/16/3/3/2/870)

NOTIFICATION OF AVAILABILITY OF EIA REPORT AND PUBLIC MEETING

Paulputs CSP RF (Pty) Ltd proposes the development of a 200MW Concentrated Solar Power

(CSP) project and associated infrastructure. The project development site is located on

Portion 4 of the Farm Scuitklip 92 which is located approximately 45km north-east of

Pofadder within the Khai-Ma Local Municipality in the Northern Cape. The project is referred

to as the Paulputs CSP Project.

The purpose of the proposed CSP project is to evacuate the generated power into the Eskom

electricity grid. The project is proposed to be bid into the Department of Energy’s (DoE)

Renewable Energy Independent Power Producers Procurement (REIPPP) Programme.

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

In terms of Sections 24 and 24D of the National Environmental Management Act (Act No

107 of 1998), as read with Government Notices R982 to GN R985; an EIA process is being

undertaken for this proposed project. The National Department of Environmental Affairs

(DEA) is the competent authority. In order to obtain authorisation, comprehensive,

independent environmental studies must be undertaken in accordance with the EIA

Regulations, 2014. The DEA accepted the Scoping Report and Plan of Study for the project

in February 2016. The application has been assigned the following reference number:

14/12/16/3/3/2/870.

Paulputs CSP RF (Pty) Ltd has appointed Savannah Environmental (Pty) Ltd as the

independent environmental consultant to undertake the required EIA to identify and assess

all the potential environmental impacts associated with the proposed project, and propose

appropriate mitigation and management measures in an Environmental Management

Programme (EMPr).

Page 24: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

As part of these environmental studies, Interested and Affected (I&APs) will be actively

involved through the public involvement process.

AVAILABILITY OF THE EIA REPORT FOR REVIEW

An EIA Report for the proposed project has been prepared by Savannah Environmental and

is available for review. The review period is from 4 May 2016 – 3 June 2016. The report

can be viewed at the Pofadder Public Library (New Road, Pofadder). The report can also be

downloaded from the website www.savannahsa.com/projects.

Please could you kindly submit your formal comments by sending written correspondence in

this regard. All comments received will be submitted in the final EIA Report which will be

submitted to the DEA. Comments can be made as a written submission via fax, post or

email.

PUBLIC MEETING

In order to facilitate comments on the EIA Report, a public meeting will be held during the

public review period as follows:

Date: Thursday 26 May 2016

Time: 17:30

Venue: Pofadder Civic Hall, Bree Street, Pofadder

The aim of the public meeting is to provide you with more information regarding the

proposed projects (including technical details, project process and timeframes etc.), to

provide a summary of the findings of the Environmental Impact Assessment Report, to invite

comment on the proposed project, and to further discuss possible issues of specific concern

to you which may need to be addressed.

Please do not hesitate to contact us should you require additional information and/or

clarification regarding the proposed project. Our team welcomes your participation and

looks forward to your involvement throughout this process.

Kind Regards

MRS GABRIELE WOOD

PUBLIC PARTICIPATION AND SOCIAL CONSULTANT

SAVANNAH ENVIRONMENTAL

Page 25: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

From the desk of Gabriele Wood

E-mail: [email protected]_____________________________________

4 May 2016

Khai Ma Local Municipality

New Street

Pofadder

8890

Tel: 054-933-1014

Email: [email protected]

Dear Ms. Jillian Nortje

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

PUBLIC PARTICIPATION PROCESS

PAULPUTS CSP PROJECT, NORTHERN CAPE PROVINCE

(DEA REF. No. 14/12/16/3/3/2/870)

NOTIFICATION OF AVAILABILITY OF EIA REPORT AND PUBLIC MEETING

Paulputs CSP RF (Pty) Ltd proposes the development of a 200MW Concentrated Solar Power

(CSP) project and associated infrastructure. The project development site is located on

Portion 4 of the Farm Scuitklip 92 which is located approximately 45km north-east of

Pofadder within the Khai-Ma Local Municipality in the Northern Cape. The project is referred

to as the Paulputs CSP Project.

The purpose of the proposed CSP project is to evacuate the generated power into the Eskom

electricity grid. The project is proposed to be bid into the Department of Energy’s (DoE)

Renewable Energy Independent Power Producers Procurement (REIPPP) Programme.

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

In terms of Sections 24 and 24D of the National Environmental Management Act (Act No

107 of 1998), as read with Government Notices R982 to GN R985; an EIA process is being

undertaken for this proposed project. The National Department of Environmental Affairs

(DEA) is the competent authority. In order to obtain authorisation, comprehensive,

independent environmental studies must be undertaken in accordance with the EIA

Regulations, 2014. The DEA accepted the Scoping Report and Plan of Study for the project

in February 2016. The application has been assigned the following reference number:

14/12/16/3/3/2/870.

Paulputs CSP RF (Pty) Ltd has appointed Savannah Environmental (Pty) Ltd as the

independent environmental consultant to undertake the required EIA to identify and assess

all the potential environmental impacts associated with the proposed project, and propose

appropriate mitigation and management measures in an Environmental Management

Programme (EMPr).

Page 26: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

As part of these environmental studies, Interested and Affected (I&APs) will be actively

involved through the public involvement process.

AVAILABILITY OF THE EIA REPORT FOR REVIEW

An EIA Report for the proposed project has been prepared by Savannah Environmental and

is available for review. The review period is from 4 May 2016 – 3 June 2016. The report

can be viewed at the Pofadder Public Library (New Road, Pofadder). The report can also be

downloaded from the website www.savannahsa.com/projects.

Please could you kindly submit your formal comments by sending written correspondence in

this regard. All comments received will be submitted in the final EIA Report which will be

submitted to the DEA. Comments can be made as a written submission via fax, post or

email.

PUBLIC MEETING

In order to facilitate comments on the EIA Report, a public meeting will be held during the

public review period as follows:

Date: Thursday 26 May 2016

Time: 17:30

Venue: Pofadder Civic Hall, Bree Street, Pofadder

The aim of the public meeting is to provide you with more information regarding the

proposed projects (including technical details, project process and timeframes etc.), to

provide a summary of the findings of the Environmental Impact Assessment Report, to invite

comment on the proposed project, and to further discuss possible issues of specific concern

to you which may need to be addressed.

Please do not hesitate to contact us should you require additional information and/or

clarification regarding the proposed project. Our team welcomes your participation and

looks forward to your involvement throughout this process.

Kind Regards

MRS GABRIELE WOOD

PUBLIC PARTICIPATION AND SOCIAL CONSULTANT

SAVANNAH ENVIRONMENTAL

Page 27: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

From the desk of Gabriele Wood

E-mail: [email protected]_____________________________________

4 May 2016

Khai Ma Local Municipality

354 Lang Street

Blyvooruitsig

Pofadder

8890

Tel: 054-933-1000

Email: [email protected]

Dear Cllr Henry Raman

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

PUBLIC PARTICIPATION PROCESS

PAULPUTS CSP PROJECT, NORTHERN CAPE PROVINCE

(DEA REF. No. 14/12/16/3/3/2/870)

NOTIFICATION OF AVAILABILITY OF EIA REPORT AND PUBLIC MEETING

Paulputs CSP RF (Pty) Ltd proposes the development of a 200MW Concentrated Solar Power

(CSP) project and associated infrastructure. The project development site is located on

Portion 4 of the Farm Scuitklip 92 which is located approximately 45km north-east of

Pofadder within the Khai-Ma Local Municipality in the Northern Cape. The project is referred

to as the Paulputs CSP Project.

The purpose of the proposed CSP project is to evacuate the generated power into the Eskom

electricity grid. The project is proposed to be bid into the Department of Energy’s (DoE)

Renewable Energy Independent Power Producers Procurement (REIPPP) Programme.

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

In terms of Sections 24 and 24D of the National Environmental Management Act (Act No

107 of 1998), as read with Government Notices R982 to GN R985; an EIA process is being

undertaken for this proposed project. The National Department of Environmental Affairs

(DEA) is the competent authority. In order to obtain authorisation, comprehensive,

independent environmental studies must be undertaken in accordance with the EIA

Regulations, 2014. The DEA accepted the Scoping Report and Plan of Study for the project

in February 2016. The application has been assigned the following reference number:

14/12/16/3/3/2/870.

Paulputs CSP RF (Pty) Ltd has appointed Savannah Environmental (Pty) Ltd as the

independent environmental consultant to undertake the required EIA to identify and assess

all the potential environmental impacts associated with the proposed project, and propose

appropriate mitigation and management measures in an Environmental Management

Programme (EMPr).

Page 28: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

As part of these environmental studies, Interested and Affected (I&APs) will be actively

involved through the public involvement process.

AVAILABILITY OF THE EIA REPORT FOR REVIEW

An EIA Report for the proposed project has been prepared by Savannah Environmental and

is available for review. The review period is from 4 May 2016 – 3 June 2016. The report

can be viewed at the Pofadder Public Library (New Road, Pofadder). The report can also be

downloaded from the website www.savannahsa.com/projects.

Please could you kindly submit your formal comments by sending written correspondence in

this regard. All comments received will be submitted in the final EIA Report which will be

submitted to the DEA. Comments can be made as a written submission via fax, post or

email.

PUBLIC MEETING

In order to facilitate comments on the EIA Report, a public meeting will be held during the

public review period as follows:

Date: Thursday 26 May 2016

Time: 17:30

Venue: Pofadder Civic Hall, Bree Street, Pofadder

The aim of the public meeting is to provide you with more information regarding the

proposed projects (including technical details, project process and timeframes etc.), to

provide a summary of the findings of the Environmental Impact Assessment Report, to invite

comment on the proposed project, and to further discuss possible issues of specific concern

to you which may need to be addressed.

Please do not hesitate to contact us should you require additional information and/or

clarification regarding the proposed project. Our team welcomes your participation and

looks forward to your involvement throughout this process.

Kind Regards

MRS GABRIELE WOOD

PUBLIC PARTICIPATION AND SOCIAL CONSULTANT

SAVANNAH ENVIRONMENTAL

Page 29: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

From the desk of Gabriele Wood

E-mail: [email protected]_____________________________________

4 May 2016

Khai Ma Local Municipality

New Street

Pofadder

8890

Tel: 054-933-1000

Email: [email protected]

Dear Mr. Roger Basson

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

PUBLIC PARTICIPATION PROCESS

PAULPUTS CSP PROJECT, NORTHERN CAPE PROVINCE

(DEA REF. No. 14/12/16/3/3/2/870)

NOTIFICATION OF AVAILABILITY OF EIA REPORT AND PUBLIC MEETING

Paulputs CSP RF (Pty) Ltd proposes the development of a 200MW Concentrated Solar Power

(CSP) project and associated infrastructure. The project development site is located on

Portion 4 of the Farm Scuitklip 92 which is located approximately 45km north-east of

Pofadder within the Khai-Ma Local Municipality in the Northern Cape. The project is referred

to as the Paulputs CSP Project.

The purpose of the proposed CSP project is to evacuate the generated power into the Eskom

electricity grid. The project is proposed to be bid into the Department of Energy’s (DoE)

Renewable Energy Independent Power Producers Procurement (REIPPP) Programme.

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

In terms of Sections 24 and 24D of the National Environmental Management Act (Act No

107 of 1998), as read with Government Notices R982 to GN R985; an EIA process is being

undertaken for this proposed project. The National Department of Environmental Affairs

(DEA) is the competent authority. In order to obtain authorisation, comprehensive,

independent environmental studies must be undertaken in accordance with the EIA

Regulations, 2014. The DEA accepted the Scoping Report and Plan of Study for the project

in February 2016. The application has been assigned the following reference number:

14/12/16/3/3/2/870.

Paulputs CSP RF (Pty) Ltd has appointed Savannah Environmental (Pty) Ltd as the

independent environmental consultant to undertake the required EIA to identify and assess

all the potential environmental impacts associated with the proposed project, and propose

appropriate mitigation and management measures in an Environmental Management

Programme (EMPr).

Page 30: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

As part of these environmental studies, Interested and Affected (I&APs) will be actively

involved through the public involvement process.

AVAILABILITY OF THE EIA REPORT FOR REVIEW

An EIA Report for the proposed project has been prepared by Savannah Environmental and

is available for review. The review period is from 4 May 2016 – 3 June 2016. The report

can be viewed at the Pofadder Public Library (New Road, Pofadder). The report can also be

downloaded from the website www.savannahsa.com/projects.

Please could you kindly submit your formal comments by sending written correspondence in

this regard. All comments received will be submitted in the final EIA Report which will be

submitted to the DEA. Comments can be made as a written submission via fax, post or

email.

PUBLIC MEETING

In order to facilitate comments on the EIA Report, a public meeting will be held during the

public review period as follows:

Date: Thursday 26 May 2016

Time: 17:30

Venue: Pofadder Civic Hall, Bree Street, Pofadder

The aim of the public meeting is to provide you with more information regarding the

proposed projects (including technical details, project process and timeframes etc.), to

provide a summary of the findings of the Environmental Impact Assessment Report, to invite

comment on the proposed project, and to further discuss possible issues of specific concern

to you which may need to be addressed.

Please do not hesitate to contact us should you require additional information and/or

clarification regarding the proposed project. Our team welcomes your participation and

looks forward to your involvement throughout this process.

Kind Regards

MRS GABRIELE WOOD

PUBLIC PARTICIPATION AND SOCIAL CONSULTANT

SAVANNAH ENVIRONMENTAL

Page 31: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

From the desk of Gabriele Wood

E-mail: [email protected]_____________________________________

4 May 2016

Khai Ma Local Municipality

New Street

Pofadder

8890

Tel: 054-933-1005

Email: [email protected]

Dear Mr. Obakeng Isaacs

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

PUBLIC PARTICIPATION PROCESS

PAULPUTS CSP PROJECT, NORTHERN CAPE PROVINCE

(DEA REF. No. 14/12/16/3/3/2/870)

NOTIFICATION OF AVAILABILITY OF EIA REPORT AND PUBLIC MEETING

Paulputs CSP RF (Pty) Ltd proposes the development of a 200MW Concentrated Solar Power

(CSP) project and associated infrastructure. The project development site is located on

Portion 4 of the Farm Scuitklip 92 which is located approximately 45km north-east of

Pofadder within the Khai-Ma Local Municipality in the Northern Cape. The project is referred

to as the Paulputs CSP Project.

The purpose of the proposed CSP project is to evacuate the generated power into the Eskom

electricity grid. The project is proposed to be bid into the Department of Energy’s (DoE)

Renewable Energy Independent Power Producers Procurement (REIPPP) Programme.

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

In terms of Sections 24 and 24D of the National Environmental Management Act (Act No

107 of 1998), as read with Government Notices R982 to GN R985; an EIA process is being

undertaken for this proposed project. The National Department of Environmental Affairs

(DEA) is the competent authority. In order to obtain authorisation, comprehensive,

independent environmental studies must be undertaken in accordance with the EIA

Regulations, 2014. The DEA accepted the Scoping Report and Plan of Study for the project

in February 2016. The application has been assigned the following reference number:

14/12/16/3/3/2/870.

Paulputs CSP RF (Pty) Ltd has appointed Savannah Environmental (Pty) Ltd as the

independent environmental consultant to undertake the required EIA to identify and assess

all the potential environmental impacts associated with the proposed project, and propose

appropriate mitigation and management measures in an Environmental Management

Programme (EMPr).

Page 32: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

As part of these environmental studies, Interested and Affected (I&APs) will be actively

involved through the public involvement process.

AVAILABILITY OF THE EIA REPORT FOR REVIEW

An EIA Report for the proposed project has been prepared by Savannah Environmental and

is available for review. The review period is from 4 May 2016 – 3 June 2016. The report

can be viewed at the Pofadder Public Library (New Road, Pofadder). The report can also be

downloaded from the website www.savannahsa.com/projects.

Please could you kindly submit your formal comments by sending written correspondence in

this regard. All comments received will be submitted in the final EIA Report which will be

submitted to the DEA. Comments can be made as a written submission via fax, post or

email.

PUBLIC MEETING

In order to facilitate comments on the EIA Report, a public meeting will be held during the

public review period as follows:

Date: Thursday 26 May 2016

Time: 17:30

Venue: Pofadder Civic Hall, Bree Street, Pofadder

The aim of the public meeting is to provide you with more information regarding the

proposed projects (including technical details, project process and timeframes etc.), to

provide a summary of the findings of the Environmental Impact Assessment Report, to invite

comment on the proposed project, and to further discuss possible issues of specific concern

to you which may need to be addressed.

Please do not hesitate to contact us should you require additional information and/or

clarification regarding the proposed project. Our team welcomes your participation and

looks forward to your involvement throughout this process.

Kind Regards

MRS GABRIELE WOOD

PUBLIC PARTICIPATION AND SOCIAL CONSULTANT

SAVANNAH ENVIRONMENTAL

Page 33: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

From the desk of Gabriele Wood

E-mail: [email protected]_____________________________________

4 May 2016

Namakwa District Municipality

Van Riebeeck Street

Springbok

8240

Tel: 027-712-8000

Email: [email protected]

Dear Mr. Chris Fortuin

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

PUBLIC PARTICIPATION PROCESS

PAULPUTS CSP PROJECT, NORTHERN CAPE PROVINCE

(DEA REF. No. 14/12/16/3/3/2/870)

NOTIFICATION OF AVAILABILITY OF EIA REPORT AND PUBLIC MEETING

Paulputs CSP RF (Pty) Ltd proposes the development of a 200MW Concentrated Solar Power

(CSP) project and associated infrastructure. The project development site is located on

Portion 4 of the Farm Scuitklip 92 which is located approximately 45km north-east of

Pofadder within the Khai-Ma Local Municipality in the Northern Cape. The project is referred

to as the Paulputs CSP Project.

The purpose of the proposed CSP project is to evacuate the generated power into the Eskom

electricity grid. The project is proposed to be bid into the Department of Energy’s (DoE)

Renewable Energy Independent Power Producers Procurement (REIPPP) Programme.

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

In terms of Sections 24 and 24D of the National Environmental Management Act (Act No

107 of 1998), as read with Government Notices R982 to GN R985; an EIA process is being

undertaken for this proposed project. The National Department of Environmental Affairs

(DEA) is the competent authority. In order to obtain authorisation, comprehensive,

independent environmental studies must be undertaken in accordance with the EIA

Regulations, 2014. The DEA accepted the Scoping Report and Plan of Study for the project

in February 2016. The application has been assigned the following reference number:

14/12/16/3/3/2/870.

Paulputs CSP RF (Pty) Ltd has appointed Savannah Environmental (Pty) Ltd as the

independent environmental consultant to undertake the required EIA to identify and assess

all the potential environmental impacts associated with the proposed project, and propose

appropriate mitigation and management measures in an Environmental Management

Programme (EMPr).

Page 34: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

As part of these environmental studies, Interested and Affected (I&APs) will be actively

involved through the public involvement process.

AVAILABILITY OF THE EIA REPORT FOR REVIEW

An EIA Report for the proposed project has been prepared by Savannah Environmental and

is available for review. The review period is from 4 May 2016 – 3 June 2016. The report

can be viewed at the Pofadder Public Library (New Road, Pofadder). The report can also be

downloaded from the website www.savannahsa.com/projects.

Please could you kindly submit your formal comments by sending written correspondence in

this regard. All comments received will be submitted in the final EIA Report which will be

submitted to the DEA. Comments can be made as a written submission via fax, post or

email.

PUBLIC MEETING

In order to facilitate comments on the EIA Report, a public meeting will be held during the

public review period as follows:

Date: Thursday 26 May 2016

Time: 17:30

Venue: Pofadder Civic Hall, Bree Street, Pofadder

The aim of the public meeting is to provide you with more information regarding the

proposed projects (including technical details, project process and timeframes etc.), to

provide a summary of the findings of the Environmental Impact Assessment Report, to invite

comment on the proposed project, and to further discuss possible issues of specific concern

to you which may need to be addressed.

Please do not hesitate to contact us should you require additional information and/or

clarification regarding the proposed project. Our team welcomes your participation and

looks forward to your involvement throughout this process.

Kind Regards

MRS GABRIELE WOOD

PUBLIC PARTICIPATION AND SOCIAL CONSULTANT

SAVANNAH ENVIRONMENTAL

Page 35: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

From the desk of Gabriele Wood

E-mail: [email protected]_____________________________________

4 May 2016

Namakwa District Municipality

Van Riebeeck Street

Springbok

8240

Tel: 027-712-8000

Email: [email protected]

Dear Mr. Immanuel Smith

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

PUBLIC PARTICIPATION PROCESS

PAULPUTS CSP PROJECT, NORTHERN CAPE PROVINCE

(DEA REF. No. 14/12/16/3/3/2/870)

NOTIFICATION OF AVAILABILITY OF EIA REPORT AND PUBLIC MEETING

Paulputs CSP RF (Pty) Ltd proposes the development of a 200MW Concentrated Solar Power

(CSP) project and associated infrastructure. The project development site is located on

Portion 4 of the Farm Scuitklip 92 which is located approximately 45km north-east of

Pofadder within the Khai-Ma Local Municipality in the Northern Cape. The project is referred

to as the Paulputs CSP Project.

The purpose of the proposed CSP project is to evacuate the generated power into the Eskom

electricity grid. The project is proposed to be bid into the Department of Energy’s (DoE)

Renewable Energy Independent Power Producers Procurement (REIPPP) Programme.

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

In terms of Sections 24 and 24D of the National Environmental Management Act (Act No

107 of 1998), as read with Government Notices R982 to GN R985; an EIA process is being

undertaken for this proposed project. The National Department of Environmental Affairs

(DEA) is the competent authority. In order to obtain authorisation, comprehensive,

independent environmental studies must be undertaken in accordance with the EIA

Regulations, 2014. The DEA accepted the Scoping Report and Plan of Study for the project

in February 2016. The application has been assigned the following reference number:

14/12/16/3/3/2/870.

Paulputs CSP RF (Pty) Ltd has appointed Savannah Environmental (Pty) Ltd as the

independent environmental consultant to undertake the required EIA to identify and assess

all the potential environmental impacts associated with the proposed project, and propose

appropriate mitigation and management measures in an Environmental Management

Programme (EMPr).

Page 36: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

As part of these environmental studies, Interested and Affected (I&APs) will be actively

involved through the public involvement process.

AVAILABILITY OF THE EIA REPORT FOR REVIEW

An EIA Report for the proposed project has been prepared by Savannah Environmental and

is available for review. The review period is from 4 May 2016 – 3 June 2016. The report

can be viewed at the Pofadder Public Library (New Road, Pofadder). The report can also be

downloaded from the website www.savannahsa.com/projects.

Please could you kindly submit your formal comments by sending written correspondence in

this regard. All comments received will be submitted in the final EIA Report which will be

submitted to the DEA. Comments can be made as a written submission via fax, post or

email.

PUBLIC MEETING

In order to facilitate comments on the EIA Report, a public meeting will be held during the

public review period as follows:

Date: Thursday 26 May 2016

Time: 17:30

Venue: Pofadder Civic Hall, Bree Street, Pofadder

The aim of the public meeting is to provide you with more information regarding the

proposed projects (including technical details, project process and timeframes etc.), to

provide a summary of the findings of the Environmental Impact Assessment Report, to invite

comment on the proposed project, and to further discuss possible issues of specific concern

to you which may need to be addressed.

Please do not hesitate to contact us should you require additional information and/or

clarification regarding the proposed project. Our team welcomes your participation and

looks forward to your involvement throughout this process.

Kind Regards

MRS GABRIELE WOOD

PUBLIC PARTICIPATION AND SOCIAL CONSULTANT

SAVANNAH ENVIRONMENTAL

Page 37: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

From the desk of Gabriele Wood

E-mail: [email protected]_____________________________________

4 May 2016

Ngwao-Boswa Ya Kapa Bokone (Northern Cape Provincial Heritage Resources Authority)

1 Monridge Office Park

Cnr Kekewich Drive & Memorial Road

Kimberley

8301

Tel: 053-831-2537

Email: [email protected]

Dear Mr. Ratha Andrew Timothy

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

PUBLIC PARTICIPATION PROCESS

PAULPUTS CSP PROJECT, NORTHERN CAPE PROVINCE

(DEA REF. No. 14/12/16/3/3/2/870)

NOTIFICATION OF AVAILABILITY OF EIA REPORT AND PUBLIC MEETING

Paulputs CSP RF (Pty) Ltd proposes the development of a 200MW Concentrated Solar Power

(CSP) project and associated infrastructure. The project development site is located on

Portion 4 of the Farm Scuitklip 92 which is located approximately 45km north-east of

Pofadder within the Khai-Ma Local Municipality in the Northern Cape. The project is referred

to as the Paulputs CSP Project.

The purpose of the proposed CSP project is to evacuate the generated power into the Eskom

electricity grid. The project is proposed to be bid into the Department of Energy’s (DoE)

Renewable Energy Independent Power Producers Procurement (REIPPP) Programme.

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

In terms of Sections 24 and 24D of the National Environmental Management Act (Act No

107 of 1998), as read with Government Notices R982 to GN R985; an EIA process is being

undertaken for this proposed project. The National Department of Environmental Affairs

(DEA) is the competent authority. In order to obtain authorisation, comprehensive,

independent environmental studies must be undertaken in accordance with the EIA

Regulations, 2014. The DEA accepted the Scoping Report and Plan of Study for the project

in February 2016. The application has been assigned the following reference number:

14/12/16/3/3/2/870.

Paulputs CSP RF (Pty) Ltd has appointed Savannah Environmental (Pty) Ltd as the

independent environmental consultant to undertake the required EIA to identify and assess

all the potential environmental impacts associated with the proposed project, and propose

appropriate mitigation and management measures in an Environmental Management

Programme (EMPr).

Page 38: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

As part of these environmental studies, Interested and Affected (I&APs) will be actively

involved through the public involvement process.

AVAILABILITY OF THE EIA REPORT FOR REVIEW

An EIA Report for the proposed project has been prepared by Savannah Environmental and

is available for review. The review period is from 4 May 2016 – 3 June 2016. The report

can be viewed at the Pofadder Public Library (New Road, Pofadder). The report can also be

downloaded from the website www.savannahsa.com/projects.

Please could you kindly submit your formal comments by sending written correspondence in

this regard. All comments received will be submitted in the final EIA Report which will be

submitted to the DEA. Comments can be made as a written submission via fax, post or

email.

PUBLIC MEETING

In order to facilitate comments on the EIA Report, a public meeting will be held during the

public review period as follows:

Date: Thursday 26 May 2016

Time: 17:30

Venue: Pofadder Civic Hall, Bree Street, Pofadder

The aim of the public meeting is to provide you with more information regarding the

proposed projects (including technical details, project process and timeframes etc.), to

provide a summary of the findings of the Environmental Impact Assessment Report, to invite

comment on the proposed project, and to further discuss possible issues of specific concern

to you which may need to be addressed.

Please do not hesitate to contact us should you require additional information and/or

clarification regarding the proposed project. Our team welcomes your participation and

looks forward to your involvement throughout this process.

Kind Regards

MRS GABRIELE WOOD

PUBLIC PARTICIPATION AND SOCIAL CONSULTANT

SAVANNAH ENVIRONMENTAL

Page 39: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

From the desk of Gabriele Wood

E-mail: [email protected]_____________________________________

4 May 2016

Northern Cape Department of Agriculture, Land Reform & Rural Development

Kimberlite Building

162 George Street

Kimberley

8301

Tel: 053-838-9102

Email: [email protected]

Dear Mr. Wonders Dimakatso Viljoen Mothibi

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

PUBLIC PARTICIPATION PROCESS

PAULPUTS CSP PROJECT, NORTHERN CAPE PROVINCE

(DEA REF. No. 14/12/16/3/3/2/870)

NOTIFICATION OF AVAILABILITY OF EIA REPORT AND PUBLIC MEETING

Paulputs CSP RF (Pty) Ltd proposes the development of a 200MW Concentrated Solar Power

(CSP) project and associated infrastructure. The project development site is located on

Portion 4 of the Farm Scuitklip 92 which is located approximately 45km north-east of

Pofadder within the Khai-Ma Local Municipality in the Northern Cape. The project is referred

to as the Paulputs CSP Project.

The purpose of the proposed CSP project is to evacuate the generated power into the Eskom

electricity grid. The project is proposed to be bid into the Department of Energy’s (DoE)

Renewable Energy Independent Power Producers Procurement (REIPPP) Programme.

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

In terms of Sections 24 and 24D of the National Environmental Management Act (Act No

107 of 1998), as read with Government Notices R982 to GN R985; an EIA process is being

undertaken for this proposed project. The National Department of Environmental Affairs

(DEA) is the competent authority. In order to obtain authorisation, comprehensive,

independent environmental studies must be undertaken in accordance with the EIA

Regulations, 2014. The DEA accepted the Scoping Report and Plan of Study for the project

in February 2016. The application has been assigned the following reference number:

14/12/16/3/3/2/870.

Paulputs CSP RF (Pty) Ltd has appointed Savannah Environmental (Pty) Ltd as the

independent environmental consultant to undertake the required EIA to identify and assess

all the potential environmental impacts associated with the proposed project, and propose

appropriate mitigation and management measures in an Environmental Management

Programme (EMPr).

Page 40: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

As part of these environmental studies, Interested and Affected (I&APs) will be actively

involved through the public involvement process.

AVAILABILITY OF THE EIA REPORT FOR REVIEW

An EIA Report for the proposed project has been prepared by Savannah Environmental and

is available for review. The review period is from 4 May 2016 – 3 June 2016. The report

can be viewed at the Pofadder Public Library (New Road, Pofadder). The report can also be

downloaded from the website www.savannahsa.com/projects.

Please could you kindly submit your formal comments by sending written correspondence in

this regard. All comments received will be submitted in the final EIA Report which will be

submitted to the DEA. Comments can be made as a written submission via fax, post or

email.

PUBLIC MEETING

In order to facilitate comments on the EIA Report, a public meeting will be held during the

public review period as follows:

Date: Thursday 26 May 2016

Time: 17:30

Venue: Pofadder Civic Hall, Bree Street, Pofadder

The aim of the public meeting is to provide you with more information regarding the

proposed projects (including technical details, project process and timeframes etc.), to

provide a summary of the findings of the Environmental Impact Assessment Report, to invite

comment on the proposed project, and to further discuss possible issues of specific concern

to you which may need to be addressed.

Please do not hesitate to contact us should you require additional information and/or

clarification regarding the proposed project. Our team welcomes your participation and

looks forward to your involvement throughout this process.

Kind Regards

MRS GABRIELE WOOD

PUBLIC PARTICIPATION AND SOCIAL CONSULTANT

SAVANNAH ENVIRONMENTAL

Page 41: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

From the desk of Gabriele Wood

E-mail: [email protected]_____________________________________

4 May 2016

Northern Cape Department of Environment and Nature Conservation

Cnr. Voortrekker and Magasyn Street

Springbok

8240

Tel: 027-718-8800

Email: [email protected]

Dear Ms. Onwabile Ndzumo

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

PUBLIC PARTICIPATION PROCESS

PAULPUTS CSP PROJECT, NORTHERN CAPE PROVINCE

(DEA REF. No. 14/12/16/3/3/2/870)

NOTIFICATION OF AVAILABILITY OF EIA REPORT AND PUBLIC MEETING

Paulputs CSP RF (Pty) Ltd proposes the development of a 200MW Concentrated Solar Power

(CSP) project and associated infrastructure. The project development site is located on

Portion 4 of the Farm Scuitklip 92 which is located approximately 45km north-east of

Pofadder within the Khai-Ma Local Municipality in the Northern Cape. The project is referred

to as the Paulputs CSP Project.

The purpose of the proposed CSP project is to evacuate the generated power into the Eskom

electricity grid. The project is proposed to be bid into the Department of Energy’s (DoE)

Renewable Energy Independent Power Producers Procurement (REIPPP) Programme.

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

In terms of Sections 24 and 24D of the National Environmental Management Act (Act No

107 of 1998), as read with Government Notices R982 to GN R985; an EIA process is being

undertaken for this proposed project. The National Department of Environmental Affairs

(DEA) is the competent authority. In order to obtain authorisation, comprehensive,

independent environmental studies must be undertaken in accordance with the EIA

Regulations, 2014. The DEA accepted the Scoping Report and Plan of Study for the project

in February 2016. The application has been assigned the following reference number:

14/12/16/3/3/2/870.

Paulputs CSP RF (Pty) Ltd has appointed Savannah Environmental (Pty) Ltd as the

independent environmental consultant to undertake the required EIA to identify and assess

all the potential environmental impacts associated with the proposed project, and propose

appropriate mitigation and management measures in an Environmental Management

Programme (EMPr).

Page 42: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

As part of these environmental studies, Interested and Affected (I&APs) will be actively

involved through the public involvement process.

AVAILABILITY OF THE EIA REPORT FOR REVIEW

An EIA Report for the proposed project has been prepared by Savannah Environmental and

is available for review. The review period is from 4 May 2016 – 3 June 2016. The report

can be viewed at the Pofadder Public Library (New Road, Pofadder). The report can also be

downloaded from the website www.savannahsa.com/projects.

Please could you kindly submit your formal comments by sending written correspondence in

this regard. All comments received will be submitted in the final EIA Report which will be

submitted to the DEA. Comments can be made as a written submission via fax, post or

email.

PUBLIC MEETING

In order to facilitate comments on the EIA Report, a public meeting will be held during the

public review period as follows:

Date: Thursday 26 May 2016

Time: 17:30

Venue: Pofadder Civic Hall, Bree Street, Pofadder

The aim of the public meeting is to provide you with more information regarding the

proposed projects (including technical details, project process and timeframes etc.), to

provide a summary of the findings of the Environmental Impact Assessment Report, to invite

comment on the proposed project, and to further discuss possible issues of specific concern

to you which may need to be addressed.

Please do not hesitate to contact us should you require additional information and/or

clarification regarding the proposed project. Our team welcomes your participation and

looks forward to your involvement throughout this process.

Kind Regards

MRS GABRIELE WOOD

PUBLIC PARTICIPATION AND SOCIAL CONSULTANT

SAVANNAH ENVIRONMENTAL

Page 43: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

From the desk of Gabriele Wood

E-mail: [email protected]_____________________________________

4 May 2016

Northern Cape Department of Environment and Nature Conservation

c/o Voortrekker & Magasyn Street

Springbok

8240

Tel: 027-718-8800

Email: [email protected]

Dear Mr. Peter Cloete

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

PUBLIC PARTICIPATION PROCESS

PAULPUTS CSP PROJECT, NORTHERN CAPE PROVINCE

(DEA REF. No. 14/12/16/3/3/2/870)

NOTIFICATION OF AVAILABILITY OF EIA REPORT AND PUBLIC MEETING

Paulputs CSP RF (Pty) Ltd proposes the development of a 200MW Concentrated Solar Power

(CSP) project and associated infrastructure. The project development site is located on

Portion 4 of the Farm Scuitklip 92 which is located approximately 45km north-east of

Pofadder within the Khai-Ma Local Municipality in the Northern Cape. The project is referred

to as the Paulputs CSP Project.

The purpose of the proposed CSP project is to evacuate the generated power into the Eskom

electricity grid. The project is proposed to be bid into the Department of Energy’s (DoE)

Renewable Energy Independent Power Producers Procurement (REIPPP) Programme.

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

In terms of Sections 24 and 24D of the National Environmental Management Act (Act No

107 of 1998), as read with Government Notices R982 to GN R985; an EIA process is being

undertaken for this proposed project. The National Department of Environmental Affairs

(DEA) is the competent authority. In order to obtain authorisation, comprehensive,

independent environmental studies must be undertaken in accordance with the EIA

Regulations, 2014. The DEA accepted the Scoping Report and Plan of Study for the project

in February 2016. The application has been assigned the following reference number:

14/12/16/3/3/2/870.

Paulputs CSP RF (Pty) Ltd has appointed Savannah Environmental (Pty) Ltd as the

independent environmental consultant to undertake the required EIA to identify and assess

all the potential environmental impacts associated with the proposed project, and propose

appropriate mitigation and management measures in an Environmental Management

Programme (EMPr).

Page 44: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

As part of these environmental studies, Interested and Affected (I&APs) will be actively

involved through the public involvement process.

AVAILABILITY OF THE EIA REPORT FOR REVIEW

An EIA Report for the proposed project has been prepared by Savannah Environmental and

is available for review. The review period is from 4 May 2016 – 3 June 2016. The report

can be viewed at the Pofadder Public Library (New Road, Pofadder). The report can also be

downloaded from the website www.savannahsa.com/projects.

Please could you kindly submit your formal comments by sending written correspondence in

this regard. All comments received will be submitted in the final EIA Report which will be

submitted to the DEA. Comments can be made as a written submission via fax, post or

email.

PUBLIC MEETING

In order to facilitate comments on the EIA Report, a public meeting will be held during the

public review period as follows:

Date: Thursday 26 May 2016

Time: 17:30

Venue: Pofadder Civic Hall, Bree Street, Pofadder

The aim of the public meeting is to provide you with more information regarding the

proposed projects (including technical details, project process and timeframes etc.), to

provide a summary of the findings of the Environmental Impact Assessment Report, to invite

comment on the proposed project, and to further discuss possible issues of specific concern

to you which may need to be addressed.

Please do not hesitate to contact us should you require additional information and/or

clarification regarding the proposed project. Our team welcomes your participation and

looks forward to your involvement throughout this process.

Kind Regards

MRS GABRIELE WOOD

PUBLIC PARTICIPATION AND SOCIAL CONSULTANT

SAVANNAH ENVIRONMENTAL

Page 45: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

From the desk of Gabriele Wood

E-mail: [email protected]_____________________________________

4 May 2016

Northern Cape Department of Environment and Nature Conservation

1 Airport Road

Springbok

8240

Tel: 027-718-9906

Email: [email protected]

Dear Mr. Conrad Geldenhuys

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

PUBLIC PARTICIPATION PROCESS

PAULPUTS CSP PROJECT, NORTHERN CAPE PROVINCE

(DEA REF. No. 14/12/16/3/3/2/870)

NOTIFICATION OF AVAILABILITY OF EIA REPORT AND PUBLIC MEETING

Paulputs CSP RF (Pty) Ltd proposes the development of a 200MW Concentrated Solar Power

(CSP) project and associated infrastructure. The project development site is located on

Portion 4 of the Farm Scuitklip 92 which is located approximately 45km north-east of

Pofadder within the Khai-Ma Local Municipality in the Northern Cape. The project is referred

to as the Paulputs CSP Project.

The purpose of the proposed CSP project is to evacuate the generated power into the Eskom

electricity grid. The project is proposed to be bid into the Department of Energy’s (DoE)

Renewable Energy Independent Power Producers Procurement (REIPPP) Programme.

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

In terms of Sections 24 and 24D of the National Environmental Management Act (Act No

107 of 1998), as read with Government Notices R982 to GN R985; an EIA process is being

undertaken for this proposed project. The National Department of Environmental Affairs

(DEA) is the competent authority. In order to obtain authorisation, comprehensive,

independent environmental studies must be undertaken in accordance with the EIA

Regulations, 2014. The DEA accepted the Scoping Report and Plan of Study for the project

in February 2016. The application has been assigned the following reference number:

14/12/16/3/3/2/870.

Paulputs CSP RF (Pty) Ltd has appointed Savannah Environmental (Pty) Ltd as the

independent environmental consultant to undertake the required EIA to identify and assess

all the potential environmental impacts associated with the proposed project, and propose

appropriate mitigation and management measures in an Environmental Management

Programme (EMPr).

Page 46: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

As part of these environmental studies, Interested and Affected (I&APs) will be actively

involved through the public involvement process.

AVAILABILITY OF THE EIA REPORT FOR REVIEW

An EIA Report for the proposed project has been prepared by Savannah Environmental and

is available for review. The review period is from 4 May 2016 – 3 June 2016. The report

can be viewed at the Pofadder Public Library (New Road, Pofadder). The report can also be

downloaded from the website www.savannahsa.com/projects.

Please could you kindly submit your formal comments by sending written correspondence in

this regard. All comments received will be submitted in the final EIA Report which will be

submitted to the DEA. Comments can be made as a written submission via fax, post or

email.

PUBLIC MEETING

In order to facilitate comments on the EIA Report, a public meeting will be held during the

public review period as follows:

Date: Thursday 26 May 2016

Time: 17:30

Venue: Pofadder Civic Hall, Bree Street, Pofadder

The aim of the public meeting is to provide you with more information regarding the

proposed projects (including technical details, project process and timeframes etc.), to

provide a summary of the findings of the Environmental Impact Assessment Report, to invite

comment on the proposed project, and to further discuss possible issues of specific concern

to you which may need to be addressed.

Please do not hesitate to contact us should you require additional information and/or

clarification regarding the proposed project. Our team welcomes your participation and

looks forward to your involvement throughout this process.

Kind Regards

MRS GABRIELE WOOD

PUBLIC PARTICIPATION AND SOCIAL CONSULTANT

SAVANNAH ENVIRONMENTAL

Page 47: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

From the desk of Gabriele Wood

E-mail: [email protected]_____________________________________

4 May 2016

South African National Roads Agency Limited

1 Havenga Street

Oakdale

Bellville

7530

Tel: 021-957-4600

Email: [email protected]

Dear Ms. René de Kock

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

PUBLIC PARTICIPATION PROCESS

PAULPUTS CSP PROJECT, NORTHERN CAPE PROVINCE

(DEA REF. No. 14/12/16/3/3/2/870)

NOTIFICATION OF AVAILABILITY OF EIA REPORT AND PUBLIC MEETING

Paulputs CSP RF (Pty) Ltd proposes the development of a 200MW Concentrated Solar Power

(CSP) project and associated infrastructure. The project development site is located on

Portion 4 of the Farm Scuitklip 92 which is located approximately 45km north-east of

Pofadder within the Khai-Ma Local Municipality in the Northern Cape. The project is referred

to as the Paulputs CSP Project.

The purpose of the proposed CSP project is to evacuate the generated power into the Eskom

electricity grid. The project is proposed to be bid into the Department of Energy’s (DoE)

Renewable Energy Independent Power Producers Procurement (REIPPP) Programme.

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

In terms of Sections 24 and 24D of the National Environmental Management Act (Act No

107 of 1998), as read with Government Notices R982 to GN R985; an EIA process is being

undertaken for this proposed project. The National Department of Environmental Affairs

(DEA) is the competent authority. In order to obtain authorisation, comprehensive,

independent environmental studies must be undertaken in accordance with the EIA

Regulations, 2014. The DEA accepted the Scoping Report and Plan of Study for the project

in February 2016. The application has been assigned the following reference number:

14/12/16/3/3/2/870.

Paulputs CSP RF (Pty) Ltd has appointed Savannah Environmental (Pty) Ltd as the

independent environmental consultant to undertake the required EIA to identify and assess

all the potential environmental impacts associated with the proposed project, and propose

appropriate mitigation and management measures in an Environmental Management

Programme (EMPr).

Page 48: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

As part of these environmental studies, Interested and Affected (I&APs) will be actively

involved through the public involvement process.

AVAILABILITY OF THE EIA REPORT FOR REVIEW

An EIA Report for the proposed project has been prepared by Savannah Environmental and

is available for review. The review period is from 4 May 2016 – 3 June 2016. The report

can be viewed at the Pofadder Public Library (New Road, Pofadder). The report can also be

downloaded from the website www.savannahsa.com/projects.

Please could you kindly submit your formal comments by sending written correspondence in

this regard. All comments received will be submitted in the final EIA Report which will be

submitted to the DEA. Comments can be made as a written submission via fax, post or

email.

PUBLIC MEETING

In order to facilitate comments on the EIA Report, a public meeting will be held during the

public review period as follows:

Date: Thursday 26 May 2016

Time: 17:30

Venue: Pofadder Civic Hall, Bree Street, Pofadder

The aim of the public meeting is to provide you with more information regarding the

proposed projects (including technical details, project process and timeframes etc.), to

provide a summary of the findings of the Environmental Impact Assessment Report, to invite

comment on the proposed project, and to further discuss possible issues of specific concern

to you which may need to be addressed.

Please do not hesitate to contact us should you require additional information and/or

clarification regarding the proposed project. Our team welcomes your participation and

looks forward to your involvement throughout this process.

Kind Regards

MRS GABRIELE WOOD

PUBLIC PARTICIPATION AND SOCIAL CONSULTANT

SAVANNAH ENVIRONMENTAL

Page 49: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

From the desk of Gabriele Wood

E-mail: [email protected]_____________________________________

4 May 2016

Square Kilometre Array (SKA): South Africa

SKA Office, 1st Floor

17 Baker Street

Rosebank

2196

Tel: 011-442-2434

Email: [email protected]

Dear Mr. Adrian Tiplady

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

PUBLIC PARTICIPATION PROCESS

PAULPUTS CSP PROJECT, NORTHERN CAPE PROVINCE

(DEA REF. No. 14/12/16/3/3/2/870)

NOTIFICATION OF AVAILABILITY OF EIA REPORT AND PUBLIC MEETING

Paulputs CSP RF (Pty) Ltd proposes the development of a 200MW Concentrated Solar Power

(CSP) project and associated infrastructure. The project development site is located on

Portion 4 of the Farm Scuitklip 92 which is located approximately 45km north-east of

Pofadder within the Khai-Ma Local Municipality in the Northern Cape. The project is referred

to as the Paulputs CSP Project.

The purpose of the proposed CSP project is to evacuate the generated power into the Eskom

electricity grid. The project is proposed to be bid into the Department of Energy’s (DoE)

Renewable Energy Independent Power Producers Procurement (REIPPP) Programme.

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

In terms of Sections 24 and 24D of the National Environmental Management Act (Act No

107 of 1998), as read with Government Notices R982 to GN R985; an EIA process is being

undertaken for this proposed project. The National Department of Environmental Affairs

(DEA) is the competent authority. In order to obtain authorisation, comprehensive,

independent environmental studies must be undertaken in accordance with the EIA

Regulations, 2014. The DEA accepted the Scoping Report and Plan of Study for the project

in February 2016. The application has been assigned the following reference number:

14/12/16/3/3/2/870.

Paulputs CSP RF (Pty) Ltd has appointed Savannah Environmental (Pty) Ltd as the

independent environmental consultant to undertake the required EIA to identify and assess

all the potential environmental impacts associated with the proposed project, and propose

appropriate mitigation and management measures in an Environmental Management

Programme (EMPr).

Page 50: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser

As part of these environmental studies, Interested and Affected (I&APs) will be actively

involved through the public involvement process.

AVAILABILITY OF THE EIA REPORT FOR REVIEW

An EIA Report for the proposed project has been prepared by Savannah Environmental and

is available for review. The review period is from 4 May 2016 – 3 June 2016. The report

can be viewed at the Pofadder Public Library (New Road, Pofadder). The report can also be

downloaded from the website www.savannahsa.com/projects.

Please could you kindly submit your formal comments by sending written correspondence in

this regard. All comments received will be submitted in the final EIA Report which will be

submitted to the DEA. Comments can be made as a written submission via fax, post or

email.

PUBLIC MEETING

In order to facilitate comments on the EIA Report, a public meeting will be held during the

public review period as follows:

Date: Thursday 26 May 2016

Time: 17:30

Venue: Pofadder Civic Hall, Bree Street, Pofadder

The aim of the public meeting is to provide you with more information regarding the

proposed projects (including technical details, project process and timeframes etc.), to

provide a summary of the findings of the Environmental Impact Assessment Report, to invite

comment on the proposed project, and to further discuss possible issues of specific concern

to you which may need to be addressed.

Please do not hesitate to contact us should you require additional information and/or

clarification regarding the proposed project. Our team welcomes your participation and

looks forward to your involvement throughout this process.

Kind Regards

MRS GABRIELE WOOD

PUBLIC PARTICIPATION AND SOCIAL CONSULTANT

SAVANNAH ENVIRONMENTAL

Page 51: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser
Page 52: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser
Page 53: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser
Page 54: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser
Page 55: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser
Page 56: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser
Page 57: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser
Page 58: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser
Page 59: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser
Page 60: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser
Page 61: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser
Page 62: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser
Page 63: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser
Page 64: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser
Page 65: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser
Page 66: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser
Page 67: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser
Page 68: Paulputs CSP DEIAr Notification 3.05 · 2018. 1. 20. · , Jannie Loubser