Patient Shwr Track

1
Track needs to stay on the inside of the orange line, representing the Lift Rail. The track needs to run parallel to the wall instead of angling into the wall, per ZGF. ZGF is pleased with this type of track. You are released to manufacture this type of track for the Patient Bathrooms.

description

Includes Sellen & ZGF's review of the Mock-up showwer track. This is to be reviewed prior to install.

Transcript of Patient Shwr Track

Track needs to stay onthe inside of the orangeline, representing theLift Rail.

The track needs to runparallel to the wallinstead of angling intothe wall, per ZGF.

ZGF is pleased withthis type of track. Youare released tomanufacture this typeof track for the PatientBathrooms.