Passmore Avenue Class Environmental Assessment Study · •PIC #2 tentatively planned for March...
Transcript of Passmore Avenue Class Environmental Assessment Study · •PIC #2 tentatively planned for March...
![Page 1: Passmore Avenue Class Environmental Assessment Study · •PIC #2 tentatively planned for March 2017 •Environmental Study Report –late Spring 2017 •Notice of Study Completion](https://reader033.fdocuments.in/reader033/viewer/2022050503/5f94e7c6f5fbf346b07907d8/html5/thumbnails/1.jpg)
Passmore Avenue
Class Environmental Assessment Study
Public Information Centre #1
November 29, 2016
Photo looking west toward west limit
![Page 2: Passmore Avenue Class Environmental Assessment Study · •PIC #2 tentatively planned for March 2017 •Environmental Study Report –late Spring 2017 •Notice of Study Completion](https://reader033.fdocuments.in/reader033/viewer/2022050503/5f94e7c6f5fbf346b07907d8/html5/thumbnails/2.jpg)
Background and Study Area
• Municipal infrastructure projects are subject to
requirements under the Environmental Assessment Act.
• Passmore Avenue is an east-west collector road in a mixed
commercial/industrial area, located in the north-east part of
the City.
• The study area is bounded by Middlefield Road to the west,
Markham Road to the east, McNicoll Avenue to the south
and Steeles Avenue East to the north.
• Within the study area, Passmore Avenue is urbanized with
four traffic lanes from the Middlefield Road intersection to
approximately 450 metres (m) west of Markham Road.
• The project focus area, from the Markham Road
intersection to approximately 450m west, is a two lane rural
road and is identified in the Official Plan to require a 27m
right-of-way.
The purpose of the study is to identify the preferred alternative to address the deteriorated condition of the roadway.
2
![Page 3: Passmore Avenue Class Environmental Assessment Study · •PIC #2 tentatively planned for March 2017 •Environmental Study Report –late Spring 2017 •Notice of Study Completion](https://reader033.fdocuments.in/reader033/viewer/2022050503/5f94e7c6f5fbf346b07907d8/html5/thumbnails/3.jpg)
Problem and/or Opportunity Statement
Passmore Avenue between Markham Road and approximately 450m west of
the intersection requires rehabilitation to address poor road surface
conditions.
Given the rehabilitation work required, there is an opportunity to improve
connectivity; provide consistency in the number of traffic lanes; address
drainage and water service infrastructure requirements; and consider future
growth in the Study Area as an active employment community.
The Passmore Avenue Environmental Assessment Study will consider
improvements to the public realm to provide greater safety and access
to/from the project focus area for all users and to encourage transit use,
cycling and walking as viable modes of transportation.
3
![Page 4: Passmore Avenue Class Environmental Assessment Study · •PIC #2 tentatively planned for March 2017 •Environmental Study Report –late Spring 2017 •Notice of Study Completion](https://reader033.fdocuments.in/reader033/viewer/2022050503/5f94e7c6f5fbf346b07907d8/html5/thumbnails/4.jpg)
• A planning and decision-making process, approved under the provincial Environmental Assessment Act
• Multi-phase process where level of detail increases as the planning process progresses
• Public and agency consultation
• Considers a reasonable range of alternatives
• Considers impacts to all aspects of the environment (natural, built, cultural, social, economic environments)
• Systematically evaluates net environmental effects
• Passmore Avenue Environmental Assessment is being carried out as a Schedule ‘C’ project, which is the most rigorous process under the Municipal Class Environmental Assessment
What is a Municipal Class Environmental Assessment?
4
![Page 5: Passmore Avenue Class Environmental Assessment Study · •PIC #2 tentatively planned for March 2017 •Environmental Study Report –late Spring 2017 •Notice of Study Completion](https://reader033.fdocuments.in/reader033/viewer/2022050503/5f94e7c6f5fbf346b07907d8/html5/thumbnails/5.jpg)
The Municipal Class Environmental Assessment Process
Phase 1: Identify & Describe Problem(s) & Opportunities
• Develop Problem(s) & Opportunities Statement
Phase 2: Identify Reasonable Range of Alternative Solutions
• Inventory existing environment
• Identify the impact of the alternative solutions after mitigation
• Evaluate the alternative solutions
• Identify a preliminary recommended preferred alternative
solution
Phase 3: Alternative Design Concepts for Preferred Solution
Phase 4: Environmental Study Report
Phase 5: Implementation
Notice of Commencement and
Public Information Centre #1:
November 29, 2016
Notice of Completion
(30-day Public Review Period)
Public
Input
at any
time in
process
and at
Key
Points
Public Information Centre #2:
March, 2017
We are here
5
![Page 6: Passmore Avenue Class Environmental Assessment Study · •PIC #2 tentatively planned for March 2017 •Environmental Study Report –late Spring 2017 •Notice of Study Completion](https://reader033.fdocuments.in/reader033/viewer/2022050503/5f94e7c6f5fbf346b07907d8/html5/thumbnails/6.jpg)
Consultation Plan
• Public and agency input
• Letters to Property owners (potential for/confirmation of impacts)
• Combined Notice of Study Commencement and Notice of Public Information Centre (PIC) #1
• Ad appeared in the November 17, 2016 edition of the Scarborough Mirror
• PIC #1: November 29, 2016
• PIC #2 tentatively planned for March 2017
• Environmental Study Report – late Spring 2017
• Notice of Study Completion
• Environmental Study Report will be made available on the public record and project web page for a 30-day review period
6
![Page 7: Passmore Avenue Class Environmental Assessment Study · •PIC #2 tentatively planned for March 2017 •Environmental Study Report –late Spring 2017 •Notice of Study Completion](https://reader033.fdocuments.in/reader033/viewer/2022050503/5f94e7c6f5fbf346b07907d8/html5/thumbnails/7.jpg)
7
Existing Conditions – Overview
Passmore Avenue
Dynam
ic D
rive
Sta
te C
row
n B
oule
vard
Maybro
ok
Drive
Mid
dle
field
Road Select Avenue
Future Site
Development
Armadale
Church &
Cemetery
Focus Area
7
![Page 8: Passmore Avenue Class Environmental Assessment Study · •PIC #2 tentatively planned for March 2017 •Environmental Study Report –late Spring 2017 •Notice of Study Completion](https://reader033.fdocuments.in/reader033/viewer/2022050503/5f94e7c6f5fbf346b07907d8/html5/thumbnails/8.jpg)
Existing Conditions – Drainage and Pavement
Looking east along the two lane rural section toward Markham Road illustrating truck traffic in this industrial and commercial area. Culvert and ditch drainage repairs due to poor shallow drainage causing wet road structure conditions. Both issues lead to poor pavement structure.
8
Between Markham Road and Dynamic Drive; underground infrastructure requiring repairs.
![Page 9: Passmore Avenue Class Environmental Assessment Study · •PIC #2 tentatively planned for March 2017 •Environmental Study Report –late Spring 2017 •Notice of Study Completion](https://reader033.fdocuments.in/reader033/viewer/2022050503/5f94e7c6f5fbf346b07907d8/html5/thumbnails/9.jpg)
Existing Conditions – Active Transportation and Streetscape
Looking south west along the two lane section toward Dynamic Drive. Facilities on this two lane section of Passmore Avenue focus on motorized vehicles. Active Transportation facilities such as complete sidewalks and cycling infrastructure lacking.
9
Looking west along the two lane section, west of Dynamic Drive. Poor road surface conditions, inconsistent gravel shoulder surfaces, lack of TTC facilities at bus stop. Boulevard trees are prevalent on south boulevard.
![Page 10: Passmore Avenue Class Environmental Assessment Study · •PIC #2 tentatively planned for March 2017 •Environmental Study Report –late Spring 2017 •Notice of Study Completion](https://reader033.fdocuments.in/reader033/viewer/2022050503/5f94e7c6f5fbf346b07907d8/html5/thumbnails/10.jpg)
Existing Conditions – Access
Looking southeast at the two lane section, west of Dynamic Drive. Poor road surface conditions, numerous driveways have access from the single through traffic lanes in each direction.
10
Looking west at west limit.
![Page 11: Passmore Avenue Class Environmental Assessment Study · •PIC #2 tentatively planned for March 2017 •Environmental Study Report –late Spring 2017 •Notice of Study Completion](https://reader033.fdocuments.in/reader033/viewer/2022050503/5f94e7c6f5fbf346b07907d8/html5/thumbnails/11.jpg)
Existing Conditions – Transition 2 to 4 Lanes at West Limit
Four to two-lanes transition. Poor road surface and uneven gravel shoulders with limited drainage transitions to improved road surface, and formal curb and gutters with catchbasins and storm sewers. Width and remaining boulevards are similar and trees are prevalent in both sections.
11
Looking eastLooking west
![Page 12: Passmore Avenue Class Environmental Assessment Study · •PIC #2 tentatively planned for March 2017 •Environmental Study Report –late Spring 2017 •Notice of Study Completion](https://reader033.fdocuments.in/reader033/viewer/2022050503/5f94e7c6f5fbf346b07907d8/html5/thumbnails/12.jpg)
Alternative Solutions
1. Do Nothing (representing
baseline conditions for comparison)
2. Reconstruct roadway to
existing rural conditions
3. Reconstruct roadway to
2-lane urban cross-section,
with public realm and
active transportation improvements
4. Widen roadway to
4-lane urban cross-section,
with public realm and
active transportation improvements
12
![Page 13: Passmore Avenue Class Environmental Assessment Study · •PIC #2 tentatively planned for March 2017 •Environmental Study Report –late Spring 2017 •Notice of Study Completion](https://reader033.fdocuments.in/reader033/viewer/2022050503/5f94e7c6f5fbf346b07907d8/html5/thumbnails/13.jpg)
Evaluation CriteriaPlanning and Policy Context
• Address Official Plan objectives
• Improve connectivity
• Urban Design
• Consider existing and future development
Transportation
• Safety for all mode users
• Operations
• Accessibility for Ontarians With Disabilities Act
(AODA) and City of Toronto Standards
• Multimodal provisions
• Provision for Emergency Services
Natural Environment
• Vegetation and Existing Trees
• Wildlife
• New Tree Plantings
• Air Quality
• Climate Change
Cultural and Built Heritage Environment
• Cultural heritage landscapes
• Built heritage
• Potential for archaeological impacts
Social-Economic Environment
• Noise Impacts
• Property acquisitions
Engineering and Costs
• Drainage/Stormwater Management
• Construction feasibility and staging
• Construction costs and impacts to utilities
• Operations and Maintenance costs
13
![Page 14: Passmore Avenue Class Environmental Assessment Study · •PIC #2 tentatively planned for March 2017 •Environmental Study Report –late Spring 2017 •Notice of Study Completion](https://reader033.fdocuments.in/reader033/viewer/2022050503/5f94e7c6f5fbf346b07907d8/html5/thumbnails/14.jpg)
Evaluation Methodology
• Alternative Solutions evaluated on how they address the problem/opportunity
• The Do Nothing scenario represents baseline for comparison
• Evaluation criteria based on environmental categories, as defined in theEnvironmental Assessment Act
• Assessment process will score each criterion on a 5-point scale, from most to least desirable, and compare alternatives against each other and the baseline
• Systematic approach ensures that the conclusions and recommendations are reached in a clear and logical fashion
• Public and agency input on evaluation criteria and methodology, conclusions and recommendations
• Further refinement of methodology and criteria when considering alternative design concepts
14
![Page 15: Passmore Avenue Class Environmental Assessment Study · •PIC #2 tentatively planned for March 2017 •Environmental Study Report –late Spring 2017 •Notice of Study Completion](https://reader033.fdocuments.in/reader033/viewer/2022050503/5f94e7c6f5fbf346b07907d8/html5/thumbnails/15.jpg)
Technical Studies
Completed:
• Phase 1 Environmental Site Assessment
• Natural Environment Assessment
• Tree Assessment and Arborist Report
• Stage 1 Archaeological Assessment
In addition, plans, profiles and typical cross sections have been prepared to identify constraints and impacts for each of the Alternative Solutions.
Future/Further Studies:
• Transportation Comprehensive Study including collision and traffic reviews
• Geotechnical and hydrogeological investigations
Preliminary design, including cross-section elements, to be considered in the next phase will include: lane widths, boulevard and sidewalk widths, lighting and streetscape (furniture, trees).
15
![Page 16: Passmore Avenue Class Environmental Assessment Study · •PIC #2 tentatively planned for March 2017 •Environmental Study Report –late Spring 2017 •Notice of Study Completion](https://reader033.fdocuments.in/reader033/viewer/2022050503/5f94e7c6f5fbf346b07907d8/html5/thumbnails/16.jpg)
Evaluation Matrix – Summary Results
Category
16
Summary Results and Preferred Solution Recommendation
Alternative 1 Alternative 2 Alternative 3 Alternative 4
Do Nothing Reconstruct to Existing Rural ConditionsReconstruct to 2-Lane Urban Cross-section with Public Realm and
Active Transportation Improvements
Widen to 4-Lane Urban Cross-section with Public Realm and Active
Transportation Improvements
X Does not meet the 4-lane planning objective for a 27 metres right-
of-way.X Does not meet the 4-lane planning objective for a 27 metres right-
of-way.
X Does not meet the 4-lane planning objective for a 27 metres right-
of-way.√ Meets the 4-lane planning objective for a
27 metres right-of-way.
X Does not meet Official Plan policy direction to encourage active
transportation initiatives
X Does not meet Official Plan policy direction to encourage active
transportation initiatives.√ Meets Official Plan policy direction to encourage active
transportation initiatives.
√ Meets Official Plan policy direction to encourage active
transportation initiatives.
X No improvement to existing connectivity or urban design
improvements.
X No improvement to existing connectivity or urban design
improvements.
X No improvement to existing connectivity for vehicles, some urban
design improvements.√ Improved connectivity and urban design improvements.
X Does not provide accessibility or safety improvements. X Does not provide accessibility or safety improvements. √ Provides improved accessibility and safety.√ Provides improved accessibility and significantly greater safety
with 4-lanes.
X Does not provide road consistency. X Does not provide road consistency. X Does not provide road consistency.√ Provides consistency in the number of traffic lanes in the focus
area.
√ No impacts on the natural and social environments. No
archeological impacts.
√ Minimal net impacts to the natural and social environments. No
archeological impacts.
X Moderate net impacts to the natural and social environments. No
archeological impacts.
X Highest net impacts to the natural and social environments. No
archeological impacts.
X Will not address existing pavement issues. √ Will address existing pavement issues. √ Will address existing pavement issues. √ Will address existing pavement issues.
X Will not address drainage issues. X Will not fully address drainage issues. √ Will address existing drainage issues. √ Will address existing drainage issues.
√ No construction costs. X Moderate construction costs. X Moderate construction costs. X Highest construction costs.
X No change to conditions will increase operations and maintenance
costs.√ Improved conditions will reduce operations and maintenance
costs.
X Increased operations and maintenance costs with added public
realm features
X Increased operations and maintenance costs with additional lanes
and public realm features
Not Recommended Not Recommended Not Recommended RECOMMENDED
![Page 17: Passmore Avenue Class Environmental Assessment Study · •PIC #2 tentatively planned for March 2017 •Environmental Study Report –late Spring 2017 •Notice of Study Completion](https://reader033.fdocuments.in/reader033/viewer/2022050503/5f94e7c6f5fbf346b07907d8/html5/thumbnails/17.jpg)
Evaluation Results – Preliminary Preferred Solution
North South
17
Based on the results of the evaluation of impacts, the recommended Preferred Alternative Solution: Widen roadway to 4-lane urban cross-section, with public realm and active transportation improvements.
GrassBoulevard
3.3m
Landscaped Boulevard
Landscaped Area
Note: Cross section elements are preliminary.
Road widths and design will be refined and evaluated in subsequent phases of the study, in accordance with the established evaluation criteria and with public input.
Drive lane
Proposed ROW: 27m
![Page 18: Passmore Avenue Class Environmental Assessment Study · •PIC #2 tentatively planned for March 2017 •Environmental Study Report –late Spring 2017 •Notice of Study Completion](https://reader033.fdocuments.in/reader033/viewer/2022050503/5f94e7c6f5fbf346b07907d8/html5/thumbnails/18.jpg)
Alternative 4 – Widen Roadway to 4-lane Urban Cross-section
MAT
CH
LIN
E A
-A
18
![Page 19: Passmore Avenue Class Environmental Assessment Study · •PIC #2 tentatively planned for March 2017 •Environmental Study Report –late Spring 2017 •Notice of Study Completion](https://reader033.fdocuments.in/reader033/viewer/2022050503/5f94e7c6f5fbf346b07907d8/html5/thumbnails/19.jpg)
Alternative 4 – Widen Roadway to 4-lane Urban Cross-sectionM
ATC
HLI
NE
A-A
19
![Page 20: Passmore Avenue Class Environmental Assessment Study · •PIC #2 tentatively planned for March 2017 •Environmental Study Report –late Spring 2017 •Notice of Study Completion](https://reader033.fdocuments.in/reader033/viewer/2022050503/5f94e7c6f5fbf346b07907d8/html5/thumbnails/20.jpg)
Summary of Impacts of Preferred SolutionPlanning and Policy Context• Consistent with City planning policies and objectives
• Improves connectivity
Transportation• Provides increased safety and improved operations
• Provides consistency in the number of traffic lanes
• Increases accessibility and improved pedestrian
environment
Natural Environment• Grading will have impact on trees requiring some
removals
• Opportunity for new tree plantings• No significant impact to natural features or wildlife
habitat
Cultural and Built Heritage Environment• No impacts to built heritage or cultural heritage
landscapes
• No archaeological potential identified within the project
focus area
Social-Economic Environment• Property acquisition required to meet 4-lane
planning objective
• Reconstructed pavement will minimize noise level
increases
• Road widening will improve traffic flow, but may also
attract more traffic volume and increase noise levels
Engineering and Costs• Improvements to drainage and stormwater management
system
• Property acquisition costs
• Highest capital costs and potential impact to utilities
(relocation)
• Moderate traffic impacts during construction
• Added roadway width and active transportation features
will increase future operations and maintenance costs
20
![Page 21: Passmore Avenue Class Environmental Assessment Study · •PIC #2 tentatively planned for March 2017 •Environmental Study Report –late Spring 2017 •Notice of Study Completion](https://reader033.fdocuments.in/reader033/viewer/2022050503/5f94e7c6f5fbf346b07907d8/html5/thumbnails/21.jpg)
Future Studies
Further studies will be undertaken in the next phase of the process when developing, assessing and evaluating alternative design concepts.
• Transportation Comprehensive Study including collision and traffic reviews
• Geotechnical and Hydrogeological Investigations
Cross section elements to be considered in the next phase will include:
• Lane widths
• Boulevard and sidewalks widths
• Streetscape (street lighting, furniture and trees)
21
![Page 22: Passmore Avenue Class Environmental Assessment Study · •PIC #2 tentatively planned for March 2017 •Environmental Study Report –late Spring 2017 •Notice of Study Completion](https://reader033.fdocuments.in/reader033/viewer/2022050503/5f94e7c6f5fbf346b07907d8/html5/thumbnails/22.jpg)
22
Next Steps
Thank You!Your involvement is essential to the
success of the study.
• Review comments from Public Information Centre (PIC) #1
• Confirm Recommended Alternative Solution
• Develop and Evaluate Alternative Design Concepts
• Identify a recommended preliminary preferred Alternative Design
• Hold PIC #2 (March 2017)
• Confirm Recommended Alternative Design
• Finalize Design of Preferred Alternative Design
• Finalize Environmental Study Report
• Publish Notice of Study Completion and initiate 30-day public review period
Your comments are welcomed at any time throughout the study.
Please provide your feedback with respect to the PIC #1 materials by December 13, 2016.
How to get involved? Provide your feedback now using the online form:
www.toronto.ca/passmore
Input received will
be used to
confirm the
Recommended
Preferred Solution
Contact information:Maogosha Pyjor
Senior Public Consultation Coordinator
City of Toronto, Metro Hall
55 John Street, 19th Floor
Toronto, Ontario, M5V 3C6
Phone: 416-338-2850 Fax: 416-392-2974
Email: [email protected]