Paso del Norte Watershed Council Activities
August 2004• Postponement of planned demonstration of Coordinated Database/GIS for Congressionals on September 10, 2004
• City of Las Cruces regrets not having staff to represent it on Council
• Postponement of approval of by-laws and business plan until next meeting
• Next meeting October 6, 2004, at NMDA in Las Cruces
• Annual meeting, date to be determined
• URGWOM Technical meeting, October 14
Nancy N. Hanks, Ph.D., Program CoordinatorPaso del Norte Watershed Council
![Page 2: Paso del Norte Watershed Council Activities August 2004 Postponement of planned demonstration of Coordinated Database/GIS for Congressionals on September.](https://reader035.fdocuments.in/reader035/viewer/2022081901/5a4d1b5b7f8b9ab0599ab1fd/html5/thumbnails/2.jpg)
Paso del Norte Watershed Council
Funding Sources UpdateSeptember 24, 2004
![Page 3: Paso del Norte Watershed Council Activities August 2004 Postponement of planned demonstration of Coordinated Database/GIS for Congressionals on September.](https://reader035.fdocuments.in/reader035/viewer/2022081901/5a4d1b5b7f8b9ab0599ab1fd/html5/thumbnails/3.jpg)
Funding Sources, 2001-2005Paso del Norte Watershed Council
Funding Source Begin EndTotal $ Amount
Program Coordinator $ Funding
Coordinated Database ProjectEPWU Coordinated Database Project, Phase I 5/1/2002 12/31/2003 50,000 0
EPWU Coordinated Database Project, Phase II 2/19/2004 3/19/2005 65,739 0
US Army Corp of Engineers, Phases I & II 4/16/2003 9/30/2005 185,000 5,355
Programs & General Administrative Support EPWU Cooperative Agreement, Phase I 8/22/2002 1/6/2004 32,699 18,622
EPWU Cooperative Agreement, Phase II 2/1/2004 2/28/2005 49,119 22,912
River Network 1/1/2002 3/15/2004 29,611 19,629
U S Bureau of Reclamation 5/1/2002 9/30/2006 20,000 3,579
World Wildlife Fund: Public Outreach 3/26/2002 7/31/2003 5,704 0
U S Bureau of Reclamation: Gray Water Reuse ($20,000 TAES) 9/1/2004 8/31/2007 2,037 2,037
Totals $ 439,909 $72,134
![Page 4: Paso del Norte Watershed Council Activities August 2004 Postponement of planned demonstration of Coordinated Database/GIS for Congressionals on September.](https://reader035.fdocuments.in/reader035/viewer/2022081901/5a4d1b5b7f8b9ab0599ab1fd/html5/thumbnails/4.jpg)
$0
$50,000
$100,000
$150,000
$200,000
$250,000
ProgramFunding by
EPWU
ProgramFunding by
Others
PC FundingEPWU
PC FundingOthers
Funding Source
Funding Amount
WW FBORUSCOERiver NetworkEPWU
Paso del Norte Watershed CouncilAdministrative and Project Funding Sources
AndProgram Coordinator (PC) Funding Sources
![Page 5: Paso del Norte Watershed Council Activities August 2004 Postponement of planned demonstration of Coordinated Database/GIS for Congressionals on September.](https://reader035.fdocuments.in/reader035/viewer/2022081901/5a4d1b5b7f8b9ab0599ab1fd/html5/thumbnails/5.jpg)
Potential Funding SourcesFunding Source Purpose Amount
RequestedSubmittal Date Status
EPA Targeted Watersheds Grant Program (previously the Watershed Initiative Program)
Socio-economic approaches to water restoration and protection.
To be determined
Submitted November 2002 for $844,000, no award. Next Anticipated submittal date: January 2005
Planned for submittal
EPA Border 2012 Protect public health and the environment along the border.
To be determined
Submitted December 2003 for $135,000, no award. Next Anticipated submittal date: January 2005
Planned for submittal
USDA National Research Initiative, National Integrated Water Quality Program
Assessment and prediction of water resource needs and availability.
In 2004 up to $350,000
March 1, 2005 Planned for submittal
BOR Water 2025 Challenge Grants
Water delivery in an environmentally friendly and cost efficient manner.
To be determined
Anticipated submittal date: April 2005
Planned for submittal
EPA Regional Geographic Initiative Program
Funding Program Coordinator position at full-time.
To be determined
Submitted May 2003 for $75,000, no award. Next Anticipated submittal date: May 2005
Planned for submittal
![Page 6: Paso del Norte Watershed Council Activities August 2004 Postponement of planned demonstration of Coordinated Database/GIS for Congressionals on September.](https://reader035.fdocuments.in/reader035/viewer/2022081901/5a4d1b5b7f8b9ab0599ab1fd/html5/thumbnails/6.jpg)
Potential Funding Sources Continued
Funding Source Purpose AmountRequested
Submittal Date Status
EPA National Center for Environmental Research
Water quality variation in the Elephant Butte Reservoir and its impacts on the sustainability of water supply downstream.
$271,640($3,000 for Program Coordinator)
May 21, 2004 Pending
USGS National Spatial Data Infrastructure Cooperative Agreement Program
Coordinated Database/GIS To be determined Anticipated submittal date: June 2005
Planned for submittal
EPA Assessment and Watershed Protection Program Grant
Develop and refine comprehensive watershed programs
In 2004 up to $100,000
Anticipated submittal date: June 2005
Planned for submittal
USDA National Research Initiative
Enhance the prosperity of small farms and rural agricultural communities
To be determined Anticipated submittal date: October 2005
Planned for submittal
Earmarked Congressional Funding Sponsored by Senator Bingaman
Support for 3 restoration projects, development of Biological Management Plan, public outreach, database/GIS.
$2 million Submitted September 2003 for $2 million, then in August 2004 for database/GIS.
Pending