PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October...

38
Part II – Responses to Comments Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-161 COMMENTS AND RESPONSES: ORGANIZATIONS (O1-O7) CONTENTS COMMENTS AND RESPONSES: ORGANIZATIONS (O1-O7) .................... II-161 Comment Set O1: Association of California Cities, Orange County .... II-162 Comment Set O2: Banning Ranch Conservancy ................................ II-164 Comment Set O3: Bolsa Chica Conservancy ..................................... II-167 Comment Set O4: Building Industry Association of Southern California Inc. ...................................................................................... II-169 Comment Set O5: CalDesal ................................................................ II-171 Comment Set O6: California Chamber of Commerce ......................... II-174 Comment Set O7: California Coastal Protection Network (CCPN) ..... II-176 The master responses provided in Section II.2, Master Responses, MR-1 through MR-8, address similar comments received from multiple commenters on the Draft Supplemental EIR and, therefore, many individual responses to comments refer back to the master responses. These Master Responses are: MR-1, Scope of the Commission’s Discretionary Action MR-2, Lease Modification Project Scope MR-3, Responsible Vs. Lead Agency & Supplemental Vs. Subsequent EIR MR-4, Piecemealing MR-5, Diffuser Entrainment Mortality and Species Affected MR-6, Marine Protected Areas MR-7, Cumulative Impacts MR-8, Alternatives

Transcript of PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October...

Page 1: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-161

COMMENTS AND RESPONSES: ORGANIZATIONS (O1-O7)

CONTENTS

COMMENTS AND RESPONSES: ORGANIZATIONS (O1-O7) .................... II-161

Comment Set O1: Association of California Cities, Orange County .... II-162

Comment Set O2: Banning Ranch Conservancy ................................ II-164 Comment Set O3: Bolsa Chica Conservancy ..................................... II-167 Comment Set O4: Building Industry Association of Southern

California Inc. ...................................................................................... II-169

Comment Set O5: CalDesal ................................................................ II-171 Comment Set O6: California Chamber of Commerce ......................... II-174

Comment Set O7: California Coastal Protection Network (CCPN) ..... II-176

The master responses provided in Section II.2, Master Responses, MR-1 through MR-8, address similar comments received from multiple commenters on the Draft Supplemental EIR and, therefore, many individual responses to comments refer back to the master responses. These Master Responses are:

• MR-1, Scope of the Commission’s Discretionary Action • MR-2, Lease Modification Project Scope • MR-3, Responsible Vs. Lead Agency & Supplemental Vs. Subsequent EIR • MR-4, Piecemealing • MR-5, Diffuser Entrainment Mortality and Species Affected • MR-6, Marine Protected Areas • MR-7, Cumulative Impacts • MR-8, Alternatives

Page 2: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

October 2017 Final Supplemental EIR – PRC 1980.1 Lease Amendment Page II-162 Poseidon Seawater Desalination at Huntington Beach Project

Comment Set O1: Association of California Cities, Orange County

O1-1

Page 3: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163

COMMENT SET O1: ASSN. OF CALIFORNIA CITIES, ORANGE CO. (cont.)

RESPONSE TO COMMENT SET O1: ASSN. OF CALIFORNIA CITIES, ORANGE CO.

O1-1 The commenter’s expression of support for the Project will be provided to the Commission for consideration in its decision-making process. The Project that will be considered by the Commission is the proposed Lease Modification Project, as defined in Section 2 of this Supplemental EIR. (See also master responses MR-1, Scope of the Commission’s Discretionary Action, and MR-2, Lease Modification Project Scope.)

O1-1 cont.

Page 4: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

October 2017 Final Supplemental EIR – PRC 1980.1 Lease Amendment Page II-164 Poseidon Seawater Desalination at Huntington Beach Project

Comment Set O2: Banning Ranch Conservancy

O2-1

O2-2

Page 5: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-165

COMMENT SET O2: BANNING RANCH CONSERVANCY (cont.)

O2-2 cont.

O2-3

O2-4

Page 6: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

October 2017 Final Supplemental EIR – PRC 1980.1 Lease Amendment Page II-166 Poseidon Seawater Desalination at Huntington Beach Project

RESPONSE TO COMMENT SET O2:

ASSOCIATION OF CALIFORNIA CITIES, ORANGE COUNTY

O2-1 The commenter’s expression of opposition to the Project will be provided to the Commission for consideration in its decision-making process. (See also master responses MR-1, Scope of the Commission’s Discretionary Action, and MR-2, Lease Modification Project Scope.)

O2-2 See master response MR-3, Responsible Vs. Lead Agency & Supplemental Vs. Subsequent EIR regarding project need.

O2-3 See master response MR-8, Alternatives.

O2-4 Part I, Section I.7, Requirements for Recirculation, identifies the primary examples of when an EIR must be recirculated (see State CEQA Guidelines, § 15088.5, subd. (a)(1)-(3).) As discussed in Section I.6, Summary of Major Changes to Draft Supplemental EIR, the major changes to the Draft Supplement EIR do not meet the Guidelines’ threshold for recirculation. Section III contains the revisions to the document. See also master response MR-3, Responsible Vs. Lead Agency & Supplemental Vs. Subsequent EIR.

Page 7: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-167

Comment Set O3: Bolsa Chica Conservancy

O3-1

Page 8: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

October 2017 Final Supplemental EIR – PRC 1980.1 Lease Amendment Page II-168 Poseidon Seawater Desalination at Huntington Beach Project

COMMENT SET O3: BOLSA CHICA CONSERVANCY (cont.)

RESPONSE TO COMMENT SET O3: BOLSA CHICA CONSERVANCY

O3-1 The commenter’s expression of support for the Project and request for mitigation funding to be used towards sand management for the Bolsa Chica wetlands will be provided to the Commission for consideration in its decision-making process. The Project that will be considered by the Commission is the proposed Lease Modification Project, as defined in Section 2 of this Supplemental EIR. (See also master responses MR-1, Scope of the Commission’s Discretionary Action, and MR-2, Lease Modification Project Scope.)

Page 9: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-169

Comment Set O4: Building Industry Association of Southern California

Inc.

O4-1

Page 10: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

October 2017 Final Supplemental EIR – PRC 1980.1 Lease Amendment Page II-170 Poseidon Seawater Desalination at Huntington Beach Project

RESPONSE TO COMMENT SET O4:

BUILDING INDUSTRY ASSOCIATION OF SOUTHERN CALIFORNIA INC.

O4-1 The commenter’s expression of support for the Project will be provided to the Commission for consideration in its decision-making process. The Project that will be considered by the Commission is the proposed Lease Modification Project, as defined in Section 2 of this Supplemental EIR. (See also master responses MR-1, Scope of the Commission’s Discretionary Action, and MR-2, Lease Modification Project Scope.)

Page 11: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-171

Comment Set O5: CalDesal

O5-1

Page 12: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

October 2017 Final Supplemental EIR – PRC 1980.1 Lease Amendment Page II-172 Poseidon Seawater Desalination at Huntington Beach Project

COMMENT SET O5: CALDESAL (cont.)

O5-1 cont.

Page 13: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-173

RESPONSE TO COMMENT SET O5: CALDESAL

O5-1 The commenter’s expression of support for the Project will be provided to the Commission for consideration in its decision-making process. The Project that will be considered by the Commission is the proposed Lease Modification Project, as defined in Section 2 of this Supplemental EIR. (See also master responses MR-1, Scope of the Commission’s Discretionary Action, and MR-2, Lease Modification Project Scope.)

Page 14: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

October 2017 Final Supplemental EIR – PRC 1980.1 Lease Amendment Page II-174 Poseidon Seawater Desalination at Huntington Beach Project

Comment Set O6: California Chamber of Commerce

O6-1

Page 15: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-175

COMMENT SET O6: CALIFORNIA CHAMBER OF COMMERCE (cont.)

RESPONSE TO COMMENT SET O6: CALIFORNIA CHAMBER OF COMMERCE

O6-1 The commenter’s expression of support for the Project will be provided to the Commission for consideration in its decision-making process. The Project that will be considered by the Commission is the proposed Lease Modification Project, as defined in Section 2 of this Supplemental EIR. (See also master responses MR-1, Scope of the Commission’s Discretionary Action, and MR-2, Lease Modification Project Scope.)

O6-1 cont.

Page 16: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-176

Comment Set O7: California Coastal Protection Network (CCPN)

O7-1

Page 17: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

COMMENT SET O7: CCPN (cont.)

Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-177

Page 18: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

COMMENT SET O7: CCPN (cont.)

October 2017 Final Supplemental EIR – PRC 1980.1 Lease Amendment Page II-178 Poseidon Seawater Desalination at Huntington Beach Project

Page 19: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

COMMENT SET O7: CCPN (cont.)

Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-179

Page 20: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

COMMENT SET O7: CCPN (cont.)

October 2017 Final Supplemental EIR – PRC 1980.1 Lease Amendment Page II-180 Poseidon Seawater Desalination at Huntington Beach Project

Page 21: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

COMMENT SET O7: CCPN (cont.)

Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-181

Page 22: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

COMMENT SET O7: CCPN (cont.)

October 2017 Final Supplemental EIR – PRC 1980.1 Lease Amendment Page II-182 Poseidon Seawater Desalination at Huntington Beach Project

Page 23: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

COMMENT SET O7: CCPN (cont.)

Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-183

Page 24: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

COMMENT SET O7: CCPN (cont.)

October 2017 Final Supplemental EIR – PRC 1980.1 Lease Amendment Page II-184 Poseidon Seawater Desalination at Huntington Beach Project

Page 25: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

COMMENT SET O7: CCPN (cont.)

Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-185

Page 26: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

COMMENT SET O7: CCPN (cont.)

October 2017 Final Supplemental EIR – PRC 1980.1 Lease Amendment Page II-186 Poseidon Seawater Desalination at Huntington Beach Project

Page 27: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

COMMENT SET O7: CCPN (cont.)

Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-187

Page 28: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

COMMENT SET O7: CCPN (cont.)

October 2017 Final Supplemental EIR – PRC 1980.1 Lease Amendment Page II-188 Poseidon Seawater Desalination at Huntington Beach Project

Page 29: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

COMMENT SET O7: CCPN (cont.)

Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-189

Page 30: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

COMMENT SET O7: CCPN (cont.)

October 2017 Final Supplemental EIR – PRC 1980.1 Lease Amendment Page II-190 Poseidon Seawater Desalination at Huntington Beach Project

Page 31: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

COMMENT SET O7: CCPN (cont.)

Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-191

Page 32: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

COMMENT SET O7: CCPN (cont.)

October 2017 Final Supplemental EIR – PRC 1980.1 Lease Amendment Page II-192 Poseidon Seawater Desalination at Huntington Beach Project

Page 33: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

COMMENT SET O7: CCPN (cont.)

Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-193

Page 34: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

COMMENT SET O7: CCPN (cont.)

October 2017 Final Supplemental EIR – PRC 1980.1 Lease Amendment Page II-194 Poseidon Seawater Desalination at Huntington Beach Project

Page 35: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-195

COMMENT SET O7: CCPN PUBLIC MEETING TRANSCRIPT

O7-2

Page 36: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

October 2017 Final Supplemental EIR – PRC 1980.1 Lease Amendment Page II-196 Poseidon Seawater Desalination at Huntington Beach Project

COMMENT SET O7: CCPN PUBLIC MEETING TRANSCRIPT (cont.)

O7-4

O7-3

Page 37: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-197

COMMENT SET O7: CCPN PUBLIC MEETING TRANSCRIPT (cont.)

O7-4 cont.

O7-5

O7-6

Page 38: PART II – RESPONSES TO COMMENTS · Final Supplemental EIR – PRC 1980.1 Lease Amendment October 2017 Poseidon Seawater Desalination at Huntington Beach Project Page II-163 COMMENT

Part II – Responses to Comments

October 2017 Final Supplemental EIR – PRC 1980.1 Lease Amendment Page II-198 Poseidon Seawater Desalination at Huntington Beach Project

COMMENT SET O7: CCPN PUBLIC MEETING TRANSCRIPT (cont.)

RESPONSE TO COMMENT SET O7: CCPN

O7-1 The commenter’s expression of opposition to the Project will be provided to the Commission for consideration in its decision-making process. The Project that will be considered by the Commission is the proposed Lease Modification Project, as defined in Section 2 of this Supplemental EIR. (See also master responses MR-1, Scope of the Commission’s Discretionary Action, and MR-2, Lease Modification Project Scope.)

O7-2 See master responses MR-3, Responsible Vs. Lead Agency & Supplemental Vs. Subsequent EIR, and MR-4, Piecemealing.

O7-3 See master response MR-7, Cumulative Impacts.

O7-4 See master response MR-2, Lease Modification Project Scope.

O7-5 See master response MR-4, Piecemealing.

O7-6 See master response MR-3, Responsible Vs. Lead Agency & Supplemental Vs. Subsequent EIR.

O7-6 cont.