Part-145 Approved Maintenance Organisations

24
Part-145: Approved Maintenance Organisations (Annex II (EC) 2042/2003) Juan Anton Maintenance Regulations Manager Flight Standards Directorate EASA Continuing Airworthiness Workshop Kuwait 20-23 October 2014 TE.GEN.00409-001

description

Presentation EASA Part-145 Maintenance Organization

Transcript of Part-145 Approved Maintenance Organisations

  • Part-145: Approved Maintenance Organisations (Annex II (EC) 2042/2003)

    Juan AntonMaintenance Regulations ManagerFlight Standards DirectorateEASA

    Continuing Airworthiness WorkshopKuwait20-23 October 2014

    TE.GEN.00409-001

  • EC 2042/2003 Article 3

    Organisations and personnel involved in the continuing airworthiness of aircraft and components, including maintenance, shall comply with the provisions of Part-M and where appropriate those specified in Part-145 and Part-66.

    As a consequence, Part-M applies also to Part-145 organisations, in particular the following paragraphs:

    Subpart D: Maintenance standards (maintenance data, performance of maintenance, aircraft defects)

    Subpart E: Components (installation, maintenance, life limited components, control of unserviceable components)

  • EC 2042/2003 Article 4

    Organisations involved in the maintenance of large aircraft or of aircraft used in commercial air transport, and components intended for fitment thereto, shall be approved in accordance with the provisions of Annex II (Part-145).

  • 145.A.10 Scope

    Requirements for approval of an organisation for maintenance of aircraft and components

    Including facilities outside Member State if:

    Identified in exposition

    Control procedures in place

    Authority satisfied that they are integral part of the organisation

  • 145.A.20 Terms of approval

    A rating: maintenance of aircraft and components (according to aircraft maintenance data) while installed on the aircraft (or temporarily removed to facilitate access)

    B rating: maintenance on engines/APU and components (according to engine/APU maintenance data) while installed on the engine/APU (or temporarily removed to facilitate access)

    C rating: maintenance on components other than engine/APU.

    D1 rating: NDT. Only required when the Part-145 performs NDT for other organisations (issuance of Form 1). This is a rating not related to particular aircraft, engines or components.

    NOTE: Refer to M.A.502 for more details.

  • 145.A.20 Terms of approval

    Component certifying staff is only required for B and C rated organisations. When these organisations need to carry out NDT as part of component maintenance, the NDT should be carried out by personnel qualified in accordance with 145.A.30 (f).

    These NDT personnel do not need to be certifying staff. The component maintenance, including the NDT, should be released by appropriate component certifying staff.

    The need for NDT certifying staff qualified in accordance with 145.A.30 (f) and 145.A.35 is only required for D1 rated organisations.

  • 145.A.30 Personnel requirements

    Accountable manager

    Nominated persons

    Accepted by authority, (EASA Form 4)

    Quality manager

    Accepted by authority, (EASA Form 4)

    Sufficient staff

    Man hour planning (all functions, also auditing staff). Reviewed and revised at least every 3 months.

    At least 50% employed staff (not contracted) in every workshop, hangar, flight line and shift, to ensure adequate organisational stability.

  • 145.A.30 Personnel requirements

    Category Release to Service privileges

    A licence

    Minor scheduled line maintenance and simple defect rectification (AMC 145.A.30(g)), personally performed in Part-145 organisation.

    B1/B3 licenceMaintenance on structure, powerplant, and mechanical and electrical systems, avionic line replaceable units (with simple tests).

    B2 licence Maintenance on avionic and electrical systems.

    C licenceBase maintenance of entire aircraft in Part-145 organisation.

  • 145.A.30 Personnel requirements (large aircraft)

    Cat. C

    Cat. B1 Cat. B2

    Cat. B1 Cat. B2

    Cat. A

    Line

    Base

    Mechanic Avionics

    Simple

    tasks

    Certifying

    Base Engineer

    Certifying

    Technician

    Certifying

    Line Mechanic

    Support staff

  • 145.A.30 Personnel requirements (other thanlarge aircraft)

    Cat. C

    Cat. B1/B3 Cat. B2

    Cat. B1/B3 Cat. B2

    Cat. A

    Line

    Base

    Mechanic Avionics

    Simple

    tasks

    Certifying

    Technician

    Certifying

    Line Mechanic

    Certifying

    Technician

    Optional

    or

  • 145.A.30 Personnel requirements

    Exemptions for certifying staff

    Facilities outside EU / Line stations outside EU

    National qualification

    Conditions in Appendix IV

    Repetitive pre-flight ADs. Certifying staff authorisation to flight crew (if allowed by the AD).

    Aircraft operating away from support location. Certifying staff authorisation to commander or flight engineer. Maximum validity 1 year.

    Aircraft grounded away from base (unforeseen) with no certifying staff available. One-off authorisations.

    Reported to NAA within 7 days.

    Rechecked if affect flight safety.

  • 145.A.35 Certifying staff and support staff

    Qualification, training and record requirements are the same for certifying staff and for B1 and B2 support staff.

    All of them must hold a Part-66 licence with the appropriate ratings and have a minimum of 21 years.

    B1 and B2 support staff do not need to be nominated as certifying staff. May be done if this personnel is used also for line maintenance.

  • 145.A.40 Equipment, tools and materials

    Equipment, tools and materials must be:

    Available and used (scope of work)

    Controlled and calibrated (as applicable)

    Part M.A.402(f) requires verification to ensure that no tools or equipment are left inside aircraft/component

  • 145.A.42 Acceptance of components

    Documentation needed for components:

    New components: EASA Form 1 or FAA 8130-3 or TCCA24-0078 (or TCCA Form One).

    Maintained components: EASA Form 1 or FAA 8130-3 (dual release) or TCCA24-0078/Form One (dual release)

    Standard parts and materials (raw / consumable) do not need a Form 1 or equivalent. Certificate of Conformance is enough.

    Installer must check eligibility of component:

    Particular attention to modifications and configuration of aircraft, engines, etc.

  • 145.A.42 Acceptance of components

    PMAs can be accepted if:

    The PMA part is not a critical component". The statement This PMA part is not a critical component should be written in Block 12 of the FAA Form 8130-3; , or

    The PMA part conforms to design data obtained under a licensing agreement from the holder of the FAA design approval. The statement Produced under licensing agreement from the FAA design approval holder should be written in Block 12 of FAA Form 8130-3; or

    The PMA part has received an explicit approval by means of a design change or STC from the Agency or, when this approval was granted prior to 28 September 2003, from any of the National Aviation Authorities of the Members States of the European Union. The reference to this authorization should be written in Block 12 of the FAA Form 8130-3.

  • 145.A.42 Acceptance of components

    145.A.42(c) allows fabrication of a restricted range of parts by the Part-145 organisation:

    Fabricated by the organisation (not by someone else).To be used in the course of undergoing work (not for sale)Within the technical and procedural capabilities of the organisation.In accordance with approved procedures.Using approved data (by TC holder or authority) contained in overhaul or repair manuals, SBs, etc, or as approved by authority.Not eligible for issuance of Form 1.Limited range (bushes, sleeves, shims, control cables, flexible and rigid pipes, electrical cable looms, formed or machined sheel metal panels, secondary structural panels and skin panels).

  • 145.A.45 Maintenance Data

    Hold and use current, available, applicable data in accordance with scope / capability

    Requirements, directives, CDCCL etc. issued by authorityMaintenance / repair instructions issued by TC holder, Part-21 organisation or oversight authority.Standards, recognised standard practices.Instructions modified by organisation iaw procedures.May be provided by operator / customer (must be up to date).

    Part-21 Subpart J Design Organisation may approve minor modifications and minor repairs (major repairs through EASA)

  • 145.A.50 Certification of maintenance

    CRS issued by appropriate Certifying Staff on behalf of organisation before flight when

    All maintenance ordered has been carried out in accordance with MOE procedures, using correct data and no known hazardous non-compliances (see AMC 145.A.50(a) 1.2)

    New defects / incomplete work orders Communicate rectification to operator

    Maintenance not completedOperator informed and agrees

    Inform authority if in doubtDetails entered on release certificateOperators agreement endorsed on certificateIssue CRS within aircraft limitations.

  • 145.A.65 Quality system

    Independent auditsPlanned to cover all aspects in 12 months.Represent complete maintenance activities.Include product sampling.Small organisations (

  • 145.A.75 Privileges

    Maintain aircraft / components (within scope and in accordance with MOE)

    At locations identified in Certificate and MOE.

    At line stations (listed in MOE).

    At any location due to unserviceability of the aircraft or to support occasional line maintenance (procedure).

    By other organisation working under its quality system (see AMC 145.A.75(b)3).

    Issue Certificates of Release to Service

  • 145.A.80 Limitations on the organisation

    The organisation shall only maintain an aircraft or component for which it is approved when all necessary facilities, equipment, tooling, material, maintenance data and certifying staff are available.

  • 145.A.85 Changes to the organisation

    Notify authority (before the change takes place)

    Change of name of organisation or main location

    Additional locations

    Accountable Manager

    Other managers (nominated persons)

    Facilities, equipment, tools, material procedures, scope of work, certifying staff that could affect the approval.

    Possible conditions set by authority

  • 145.A.85 Changes to the organisation

    Particular case of new Line Stations:

    Addition of a new Line Station is considered a change.Must be notified to the authority in advance.The list in the MOE must be amended.The change must be approved by the authority (no indirect approval possible):

    By formal letter, orBy approval of the inclusion in the MOE.

    The authority may perform a physical audit.The authority may replace the audit by a documental assessment of the evidence and investigation performed by the organisation following approved procedures in the MOE. This should only be possible if the competent authority does not have relevant findings open on the Quality System of the organisation.

  • 145.A.90 Continued validity

    Unlimited validity, subject to:

    Continued compliance, appropriate handling of findings.

    Access to the authority.

    Not surrendered or revoked (return to authority)