Georgia Institute of Technology Barb Ericson Georgia Institute of Technology Sept 2006 Introduction…
Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the...
Transcript of Part 1 of 11, Georgia Institute of Technology, Transmittal ... · FINAL SURVEY REPORT for the...
Georgia 0 College of Engineering
June 14, 2002 Office of the Dean Docket No. 50-160
United States Nuclear Regulatory Commission Mail Stop 012-G13 Washington, D.C. 20555-0001
Attention: Mr. Daniel E. Hughes, Project Manager Non-Power Reactors and Decommissioning Project Directorate Division of Reactor Program Management Office of Nuclear Reactor Regulation
Subject: Transmittal of Final Survey Report, Georgia Tech Research Reactor (GTRR) D&D Project
References: 1. Georgia Tech Research Reactor NRC Amendment 14 to Facility License No. R-97.
2. NRC Docket No. 50-160
Dear Mr. Hughes:
We are pleased to transmit the "Final Survey Report for the Georgia Institute of Technology Research Reactor
Facility, NRC License No. R-97", Revision 0, June 2002, submitted by Shaw Environmental & Infrastructure,
Inc., as prepared by Duratek, Inc. This Report serves as the basis by which we ask the United States Nuclear
Regulatory Commission to grant full and unrestricted release of the Georgia Tech Research Reactor, and
termination of NRC Facility License No. R-97.
In transmitting this Final Survey Report, Georgia Institute of Technology neither approves nor disapproves the
Report. We have worked closely with the Decommissioning Contractor throughout the decommissioning
project, but ultimately the Decommissioning Contractor is obligated under its contract with the State of
Georgia to submit a Final Survey Report that is acceptable to the USNRC.
If you have any questions regarding this transmittal, please contact me at (404) 894-2982, or Dr. Nolan E.
Hertel, Director, Neely Nuclear Research Center, (404) 894-3601.
Sincerely,
J. Narl Davidson Interim Dean College of Engineering Chair, Technical Safety Review Committee
Enclosure: Final Survey Report for the Georgia Institute of Technology Research Reactor Facility, Revision 0,
dated June 2002, four volumes.
Cc: Dr. G. Wayne Clough, President, Georgia Institute of Technology Mr. Robert K. Thompson, SVP, Georgia Institute of Technology Ms. Amelia Gambino, Georgia Tech Office of Communications Mr. Stephen Holmes, USNRC Inspector Mr. Jon M. Richards, USEPA, Region IV Mr. Thomas Hill, Georgia Department of Natural Resources Members, Technical Safety Review Committee
College of Engineering Atlanta, Georgia 30332-0360 U.S.A. PHONE 404.894.3350 FAX 404-894-0168
AU)it of the Univzersity Systen of Georgia An Equal Education and Eniployment Opportunity histitttit.o.. A(0 (
Shaw Environmental & Infrastructure, Inc.
11560 Great Oaks Way, Suite 500
Alpharetta, GA 30022-2424 770.475.8994
Fax 770.777.9545
Sh~awThe Shaw Group Inc.
June 10, 2002
Mr. Bob Eby
Executive Engineer, GSFIC Project 1-47
CH2M Hill
151 Lafayette Dr. Suite 110
Oak Ridge, TN 37830
Re: GSFIC Project No. 1-47
Ga. Tech Research Reactor Decommissioning
Final Survey Report Rev. 0
Dear Mr. Eby,
Please find enclosed five copies of the Final Survey Report Rev. 0, dated June 2002.
This marks the completion of all work on the contract for the Georgia Tech Research Reactor
Decommissioning. In accordance with Article E-41- Notice of Readiness for Final Inspection, Shaw
Environmental & Infrastructure, Inc. hereby requests that a final inspection be made promptly by the
Engineer and the United States Nuclear Regulatory Commission (USNRC). It is our understanding that
a 3 to 6 month period will be required for the USNRC to perform the necessary survey work to allow
unrestricted free release of the facility.
If you should have any questions, please contact me at (770) 663-1452 or via e-mail at
gkalinauskas(dtheitgroup.com.
Sincerely yours, Shaw Environmental & Infrastructure, Inc.
Gede Kalinauskas
Project Engineer
Enclosure
Shaw Environmental & Infrastructure, Inc.
Mr. Bob Eby, June 10, 2002 Page 2 of 2
Cc: Butch Daniels, Shaw E&I, (w/o enc.)
Gunnar Jones, Shaw E&I, (w/o enc.)
Paul Jones, Duratek, (w enc.)
Steve Marske, CH2M HILL, (w enc.)
v/Dr. Rod Ice, Ga. Tech, (w enc.)
Doug Ivey, GSFIC, (w enc.)
Shaw E&I file: 784357
L Shiaw Shaw Environmental & Infrastructure, Inc.
FINAL SURVEY REPORT
for the Georgia Institute of Technology
Research Reactor Facility NRC License No. R-97
GSFIC Project 1-47
Revision 0 June 2002
Client Approvals:
Executive Engineer
Technical Safety Review Committee
Shaw Shaw Environmental & Infrastructure, Inc.
11560 Great Oaks Way, Suite 500 Alpharetta, Georgia 30022
628 Gallaher Road Kingston, Tennessee 37763
Date
Date
*Duratek'
B
ShawShaw Environmental & Infrastructure, Inc.
FINAL SURVEY REPORT
for the Georgia Institute of Technology
Research Reactor Facility
NRC License Number R-97
GSFIC Project 1-47
Document Number GT-PL-FR-001 Shaw E&I Project No. 784357
Duratek, Inc. / Shaw E&I, Inc.
Prepared By
Revision 0 Date: June 2002
June 2002
Date
wJ�7
Quality Assurance
Engineering
Manager Approval
6D/ate /Zo Date
Date1
Date
Date
Date
Date
FINAL SURVEY REPORT
for the
GEORGIA INSTITUTE OF TECHNOLOGY RESEARCH REACTOR FACILITY
NRC LICENSE NUMBER R-97
Revision 0 June 2002
Prepared by:
Reviewed by:
Approved by:
Paul Jones, Survey Supervisor Radiological Engineering and Field Services
Doug Sedult, CHP, Senior Radiological Engineer Radiological Engineering and Field Services
Robert Hornbeck, Operations Manager, Commercial Operations Radiological Engineering and Field Services
Date.-o4 .
Date66O
D ate
Prepared By: Duratek, Inc.
Commercial Operations 628 Gallaher Road Kingston, TN 37763
TABLE OF CONTENTS
1.0 INTR O D U CTIO N A N D SCO PE ..................................................................................... 1
1.1 Introduction ...................................................................................................... 1 1.2 Project Scope ....................................................................................................... 2
2.0 BACKGROUND INFORMATION ............................................................................ 2
2.1 Facility D escription ............................................................................................ 2 2.1.1 B asem ent ................................................................................................. 2 2.1.2 First Floor ................................................................................................ 3 2.1.3 Second Floor ............................................................................................ 4 2.1.4 Reactor Y ard ............................................................................................ 4
2.2 Operating H istory ................................................................................................. 4 2.3 M anagem ent Approach ....................................................................................... 9 2.4 D ecom m issioning Activities .............................................................................. 9
3.0 FIN AL SUR V EY ............................................................................................................. 20
3.1 Introduction ....................................................................................................... 20 3.2 Survey Guideline V alues .................................................................................. 21
3.2.1 Criteria for Release for Unrestricted Use for Building Surfaces ....... 21 3.2.2 Site Specific Guideline V alues, SPGLs ................................................. 23 3.2.3 Criteria for Release for Unrestricted Use of Open Land Areas ............ 24
3.3 Instrum entation ................................................................................................ 25 3.3.1 Instrum ent Calibration .......................................................................... 27 3.3.2 Sources ................................................................................................... 27 3.3.3 M inim um D etectable Activity .............................................................. 27
3.4 Survey Organization ......................................................................................... 29 3.5 Survey D esign ................................................................................................... 29
3.5.1 U naffected Areas .................................................................................. 29 3.5.2 N on-Suspect A ffected Areas ................................................................. 29 3.5.3 Suspect A ffected Areas ....................................................................... 30 3.5.4 Survey Area Breakdow n ....................................................................... 30
3.6 A rea Re-Classification and Investigation ......................................................... 31 3.7 Survey Package D evelopm ent ......................................................................... 31 3.8 Survey R equirem ents ....................................................................................... 31
3.8.1 Suspect A ffected Areas .......................................................................... 32 3.8.2 N on-Suspect Affected Areas ................................................................. 32 3.8.3 U naffected Areas ..................................................................................... 32
3.9 Gridding ............................................................................................................... 33 3.10 Quality A ssurance and Quality Control ............................................................ 33
3.10.1 Selection of Personnel .......................................................................... 34 3.10.2 W ritten Procedures ................................................................................. 34 3.10.3 Instrumentation Selection, Calibration and Operation .......................... 34
3.11 D ocum entation ................................................................................................... 35 3.12 D ata R eduction and Statistical Evaluation ........................................................ 36
3.12.1 D ata A nalysis ....................................................................................... 36
i REVISION 0
3.12.2 B ackground .......................................................................................... 36 3.12.3 Measurements of Total Beta Activity ................................................... 36 3.12.4 Measurements of Removable Alpha and Beta Activity ........................ 37 3.12.5 Measurements of Removable H-3 Activity ......................................... 38 3.12.6 Exposure Rate Measurements .............................................................. 38 3.12.7 Samples of Open Land Areas of Reactor Yard ..................................... 4P
4.0 SURVEY RESULTS ................................................................................................... 41
4.1 Background Results Summ ary .......................................................................... 41 4.2 Package 1 - Helium and Lead Tank Cooling Water Lines ............................... 42 4.3 Package 2 - Reactor Building 2nd Floor Below 2 Meters ................................. 47
4.4 Package 3 - Reactor Building 2nd Floor Above 2 Meters ................................. 54 4.5 Package 4 - Reactor Building 1 st Floor Below 2 Meters ................................. 60 4.6 Package 5 - Reactor Building 1st Floor Above 2 Meters ................................. 67 4.7 Package 6 - Reactor Building Ventilation Hold-Up Duct ................................ 72 4.8 Package 7 - Reactor Building Ventilation ....................................................... 77 4.9 Package 8 - Suspect Affected Yard Areas ....................................................... 84 4.10 Package 9 - Unaffected Asphalt and Concrete Yard Areas ............................. 91 4.11 Package 10 - Reactor Building and Stack ....................................................... 97 4.12 Package 11 - Reactor Building Basement Drain Lines ...................................... 102
4.13 Package 12 - Process Equipment Room Below 2 Meters .................................. 108
4.14 Package 13 - Process Equipment Room Above 2 Meters .................................. 115 4.15 Package 14 - Yard Open Land Areas ................................................................. 120 4.16 Package 15 - Basement Air Compressor Room ................................................. 124 4.17 Package 16 - Areas Outside Process Equipment Room Below 2 Meters .......... 130
4.18 Package 17 - Areas Outside Process Equipment Room Above 2 Meters .......... 137
4.19 Package 18 - Reactor Vessel Tunnel .................................................................. 142
4.20 Package 19 - Bism uth Leak Area ....................................................................... 149 4.21 Package 20 - Reactor Ventilation Above 2 Meters ............................................ 156 4.22 Package 21 - Elevator Equipment Room and Shaft ........................................... 161 4.23 Package 22 - Misc. Pipes and Penetrations ........................................................ 167
5.0 CO NCLUSIO NS ........................................................................................................... 174
6.0 REFEREN CES .............................................................................................................. 174
7.0 ATTACH M ENTS ......................................................................................................... 174
Attachment A Worksheets for Calculations of Site Specific Guideline Values Attachment B Final Survey Packages 1 through 22
REVISION 0ii
LIST OF FIGURES AND TABLES
FIGURE NUMBER
Figure 2.1
Figure 2.2
Figure 2.3
Figure 2.4
Figure 2.5
Figure 4-lA
Figure 4-1B
Figure 4-1C
Figure 4-4D
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
4-2A
4-2B
4-2C
4-2D
4-2E
4-3A
4-3B
4-3C
4-3D
4-4A
4-4B
4-4C
4-4D
4-4E
4-5A
4-5B
4-5C
Figure 4-5D
TITLE PAGE
R eactor Y ard .................................................................. 5
Containment Building Basement ........................................ 6
Containment Building First Floor .......................................... 7
Containment Building Second Floor .................................... 8
Site L ayout ................................................................... 19
Helium and Lead Tank Cooling Water Lines - Map .................. 43
Helium and Lead Tank Cooling Water Lines Direct Beta Activity.... 44
Helium and Lead Tank Cooling Water Lines Removable Beta A ctivity ........................................................................ 45
Helium and Lead Tank Cooling Water Lines Removable H-3
A ctivity ...................................................................... 46
Reactor Building 2 nd Floor Below 2 Meters - Map .................... 49
2'• Floor Below 2 Meters Direct Beta Activity ......................... 50
2 nd Floor Below 2 Meters Exposure Rate Measurements .............. 51
2 nd Floor Below 2 Meters Removable Beta Activity .................. 52
2 nd Floor Below 2 Meters Removable H-3 Activity ................... 53
Reactor Building 2 nd Floor Above 2 Meters - Map ...................... 56
2nd Floor Above 2 Meters Direct Beta Activity ........................... 57 2nd Floor Above 2 Meters Removable Beta Activity ..................... 58
2 nd Floor Above 2 Meters Removable H-3 Activity ...................... 59
Reactor Building 1st Floor Below 2 Meters - Map ..................... 62
1st Floor Below 2 Meters Direct Beta Activity ......................... 63
1st Floor Below 2 Meters Exposure Rate Measurements ............... 64
1"t Floor Below 2 Meters Removable Beta Activity ................... 65
1 st Floor Below 2 Meters Removable H-3 Activity .................... 66
Reactor Building 1 st Floor Above 2 Meters - Map ....................... 68
1st Floor Above 2 Meters Direct Beta Activity ......................... 69
1 st Floor Above 2 Meters Removable Beta Activity .................... 70
1st Floor Above 2 Meters Removable H-3 Activity .................... 71
REVISION 0.°.
Figure
Figure
Figure
Figure
Figure
Figure
Figure
4-6A
4-6B
4-6C
4-6D
4-7A
4-7B
4-7C
Figure 4-7D
Figure 4-7E
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
4-8A
4-8B
4-8C
4-8D
4-8E
4-9A
4-9B
4-9C
4-9D
4-9E
4-10A
4-10B
4-10C
4-1OD
4-1 1A
4-1iB
4-11C
4-1ID
4-12A
4-12B
Reactor Building Ventilation Hold-Up Duct - Map ................... 73
Hold-Up Duct Direct Beta Activity ...................................... 74
Hold-Up Duct Removable Beta Activity ............................... 75
Hold-Up Duct Removable H-3 Activity .................................... 76
Reactor Building Ventilation Room and Stack - Map .................. 79
Reactor Building Ventilation Below 2 Meters Direct Beta Activity... 80
Reactor Building Ventilation Below 2 Meters Exposure Rate M easurem ents .................................................................. 81
Reactor Building Ventilation Below 2 Meters Removable Beta A ctivity ...................................................................... 82
Reactor Building Ventilation Below 2 Meters Removable H-3 A ctivity ...................................................................... 83
Yard Suspect Affected Areas - Map ........................................ 86
Yard Suspect Affected Areas Direct Beta Activity ........................ 87
Yard Suspect Affected Areas Exposure Rate Measurements ............ 88
Yard Suspect Affected Areas Removable Beta Activity .......... 89
Yard Suspect Affected Areas Removable H-3 Activity .................. 90
Yard Unaffected Areas - Map ............................................... 92
Yard Unaffected Areas Direct Beta Activity ............................ 93
Yard Unaffected Areas Exposure Rate Measurements .................. 94
Yard Unaffected Areas Removable Beta Activity ......................... 95
Yard Unaffected Areas Removable H-3 Activity ......................... 96
Reactor Building Exterior - Map ............................................ 98
Reactor Building and Stack Exterior Direct Beta Activity ............... 99
Reactor Building and Stack Exterior Removable Beta Activity ......... 100
Reactor Building and Stack Exterior Removable H-3 Activity ......... 101
Basement Drain Lines - Map .............................................. 104
Basement Drain Lines Direct Beta Activity ............................... 105
Basement Drain Lines Removable Beta Activity ......................... 106
Basement Drain Lines Removable H-3 Activity .......................... 107
Process Equipment Room Below 2 Meters - Map ........................ 110
Process Equipment Room Below 2 Meters Direct Beta Activity ....... 111
REVISION 0iv
Figure 4-12C Process Equipment Room Below 2 Meters Exposure Rate M easurem ents .................................................................. 112
Figure 4-12D Process Equipment Room Below 2 Meters Removable Beta A ctivity ......................................................................... 113
Figure 4-12E Process Equipment Room Below 2 Meters Removable H-3 A ctivity ......................................................................... 114
Figure 4-13A Process Equipment Room Above 2 Meters - Map ........................ 116
Figure 4-13B Process Equipment Room Above 2 Meters Direct Beta Activity ...... 117
Figure 4-13C Process Equipment Room Above 2 Meters Removable Beta A ctivity .......................................................................... 118
Figure 4-13D Process Equipment Room Above 2 Meters Removable H-3 A ctivity ......................................................................... 119
Figure 4-14A Yard Open Land Areas - Map ............................................... 122
Figure 4-14B Yard Open Land Areas Exposure Rate Measurements .................. 123
Figure 4-15A Air Compressor Room - Map ............................................... 125
Figure 4-15B Air Compressor Room Direct Beta Activity .............................. 126
Figure 4-15C Air Compressor Room Exposure Rate Measurements ................... 127
Figure 4-15D Air Compressor Room Removable Beta Activity ........................ 128
Figure 4-15E Air Compressor Room Removable H-3 Activity ......................... 129
Figure 4-16A Areas Outside Process Equipment Room Below 2 Meters - Map...... 132
Figure 4-16B Areas Outside Process Equipment Room Below 2 Meters Direct B eta A ctivity ................................................................... 133
Figure 4-16C Areas Outside Process Equipment Room Below 2 Meters Exposure R ate M easurem ents ........................................................... 134
Figure 4-16D Areas Outside Process Equipment Room Below 2 Meters Rem ovable Beta A ctivity ..................................................... 135
Figure 4-16E Areas Outside Process Equipment Room Below 2 Meters Removable H-3 Activity ............................... 136
Figure 4-17A Areas Outside Process Equipment Room Above 2 Meters - Map...... 138
Figure 4-17B Areas Outside Process Equipment Room Above 2 Meters Direct B eta A ctivity ................................................................... 139
Figure 4-17C Areas Outside Process Equipment Room Above 2 Meters Rem ovable Beta Activity ..................................................... 140
Figure 4-17D Areas Outside Process Equipment Room Above 2 Meters Rem ovable H-3 A ctivity ...................................................... 141
Figure 4-18A Vessel Tunnel - M ap ......................................................... 144
REVISION 0V
Figure 4-18B Vessel Tunnel Direct Beta Activity ........................................ 145
Figure 4-18C Vessel Tunnel Exposure Rate Measurements ............................. 146
Figure 4-18D Vessel Tunnel Removable Beta Activity ................................... 147
Figure 4-18E Vessel Tunnel Removable H-3 Activity .................................... 148
Figure 4-19A Bismuth Leak Area - Map ................................................... 151
Figure 4-19B Bismuth Leak Area Direct Beta Activity ................................... 152
Figure 4-19C Bismuth Leak Area Exposure Rate Measurements ....................... 153
Figure 4-19D Bismuth Leak Area Removable Beta Activity ............................ 154
Figure 4-19E Bismuth Leak Area Removable H-3 Activity ............................. 155
Figure 4-20A Reactor Ventilation Above 2 Meters - Map ............................... 157
Figure 4-20B Reactor Ventilation Above 2 Meters Direct Beta Activity .............. 158
Figure 4-20C Reactor Ventilation Above 2 Meters Removable Beta Activity ........ 159
Figure 4-20D Reactor Ventilation Above 2 Meters Removable H-3 Activity......... 160
Figure 4-21A Elevator Equipment Room and Shaft - Map ................................ 162
Figure 4-21B Elevator Equipment Room and Shaft Direct Beta Activity .............. 163
Figure 4-21C Elevator Equipment Room and Shaft Exposure Rate M easurem ent .................................................................. 164
Figure 4-21D Elevator Equipment Room and Shaft Removable Beta Activity ....... 165
Figure 4-21E Elevator Equipment Room and Shaft - Removable H-3 Activity...... 166
Figure 4-22A Misc. Pipes and Penetrations First Floor (01PO0) Map ................... 168
Figure 4-22B Misc. Pipes and Penetrations First Floor (02P00) Map ................... 169
Figure 4-22C Misc. Pipes and Penetrations Basement (02P00) Map ................... 170
Figure 4-22D Misc. Pipes and Penetrations Direct Beta Activity ........................ 171
Figure 4-22E Misc. Pipes and Penetrations Removable Beta Activity .......... 172
Figure 4-22F Misc. Pipes and Penetrations Removable H-3 Activity .................. 173
TABLE TITLE PAGE
NUMBER
Table 2.1 Georgia Tech Waste Disposition ........................................ 18
Table 3.1 Radionuclide Specific Guideline Values ................................ 22
Table 3.2 Site Specific Guideline Values for Total Beta Activity and Removable Beta Activity ................................................. 24
Table 3.3 Radionuclide Specific Soil Guideline Values .......................... 25
REVISION 0vi
Table
"Table
Table
Table
Table
Table
Table
Table
Table
Table
Table
Table
Table
Table
Table
Table
Table
Table
Table
Table
Table
Table
Table
Table
Table
.Table
REVISION 0
3.4
3.5
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
4.11
4.12
4.13
4.14
4.15
4.16
4.17
4.18
4.19
4.20
4.21
4.22
4.23
4.24
Final Survey Instrumentation ............................................... 26
Field and Laboratory Instrumentation MDA's ......................... 28
Direct Beta Background Study of Concrete and Asphalt ............... 41
Survey Package 1 Final Survey Results ................................... 42
Survey Package 2 Final Survey Results ................................ 48
Survey Package 3 Final Survey Results ................................. 54
Survey Package 4 Final Survey Results ................................. 61
Survey Package 5 Final Survey Results ................................. 67
Survey Package 6 Final Survey Results ................................. 72
Survey Package 7 Final Survey Results .................................... 77
Survey Package 8 Final Survey Results ................................. 84
Survey Package 9 Final Survey Results ................................. 91
Survey Package 10 Final Survey Results ................................... 97
Survey Package 11 Final Survey Results .................................. 102
Survey Package 12 Final Survey Results .................................. 109
Survey Package 13 Final Survey Results .................................. 115
Survey Package 14 Final Exposure Rate Results ......................... 120
Yard Open Land Areas Soil Sample Gamma Spectroscopy Results .... 121
Survey Package 15 Final Survey Results................................... 124
Survey Package 16 Final Survey Results .................................. 131
Survey Package 17 Final Survey Results .................................. 137
Survey Package 18 Final Survey Results ................................... 142
Survey Package 19 Final Survey Results .................................. 149
Survey Package 20 Final Survey Results .................................. 156
Survey Package 21 Final Survey Results ...................... I ........... 161
Survey Package 22 Final Survey Results .................................. 167
vii
GA TECH RESEARCH REACTOR
1.0 INTRODUCTION AND SCOPE
1.1 Introduction
IT Corporation (IT) is under contract to the Georgia State Financing and Investment Commission (GSFIC) to decommission the Georgia Institute of Technology Research Reactor (GTRR) and its associated systems. IT upon completion of the decommissioning activities is contracted to issue a Final Survey Report (FSR). Duratek executed the Final Survey under subcontract to IT with oversight and support from IT Corporation.
The GTRR was located within the Neely Nuclear Research Center (NNRC) on the campus of the Georgia Institute of Technology (Ga. Tech). The GTRR was built in the early 1960's as a research and training reactor. It was used to explore the frontiers of biology and material sciences as well as to teach engineers the principles of nuclear power plant operation. It first went critical on December 31, 1964. The reactor was operated under the United States Nuclear Regulatory Commission (NRC) License, Number R-97. It was originally designed for 1 MW thermal (t) output and upgraded to produce 5 MW (t) in 1974. Reactor operation ceased on November 17, 1995.
No single factor led to the GTRR decommissioning. However, there was one factor that catalyzed the decision process - the 1996 Summer Olympic Games. The Ga. Tech campus was home to over ten thousand athletes from over 160 countries. The high visibility of the Olympic Games led to increased questions about reactor security and also heightened public interest in reactor operations. In addition, the reactor had reached its 30-year design lifetime. It was time to reevaluate operating systems and upgrade areas within the containment building. Student enrollment in nuclear engineering and reactor utilization had significantly decreased. Thus, a combination of all these factors led the administration of Ga. Tech to decide to decommission th6 GTRR.
All nuclear fuel was removed from the facility in February, 1996 prior to the Olympic Games. At that time the NRC amended Ga. Tech's license and granted Ga. Tech a Possession-Only-License (POL). A short time later, the Ga. Tech administration decided to decommission the nuclear reactor. In 1999, the NRC approved a license amendment to the POL to dismantle the GTRR in accordance with the GTRR Decommissioning Plan prepared by NES, Inc. (Document No. 82A9083 Rev. 3, dated June, 1998). IT began decommissioning activities in November, 1999. The work involved the dismantlement and removal of all NRClicensable materials, equipment and structures from the site.
REVISION 0
FINAL SURVEY REPORT
1
1.2 Project Scope
The ultimate goal of the Final Survey was to attain release of the GTRR facility for unrestricted use and the termination of NRC License Number R-97. The NRC approved GTRR Decommissioning Plan states, that for building surfaces, the criteria for release for unrestricted use shall be as specified in NRC Regulatory Guide 1.86, Termination of Operating Licenses for Nuclear Reactors, Table 1 "Acceptable Surface Contamination Levels". The GTRR decommissioning contract also states that the exposure rate from residual radioactivity can not exceed ambient background levels by more than 5 uR/hr (average) at 1 meter. The Final Survey was conducted in accordance with the Final Survey Plan which incorporated guidance contained in NUREG/CR-5849, Manual for Conducting Surveys in Support of License Termination (as referenced in the GTRR Decommissioning Plan).
2.0 BACKGROUND INFORMATION
2.1 Facility Description
The Neely Nuclear Research Center is located in the north-central part of the Ga. Tech campus in the city of Atlanta, Georgia. The NNRC is comprised of a containment building, hot cell, support laboratories, classrooms and offices. The GTRR was located inside the containment building which is situated on the southeast side of the NNRC.
The reactor containment building consists of three floors. The building is a cylindrical welded steel tank with a diameter of 82 feet and a 12-inch-thick internal concrete wall. The roof is a torispherical dome, approximately 50 feet above ground level. The reactor yard surrounds the containment building. It consists of both paved and open land areas. The containment building and reactor yard are shown in Figure 2.1.
2.1.1 Basement
The basement of the containment building housed the reactor process system equipment, the exhaust ventilation equipment and the electrical load center for the building. It can be reached by elevator or stairway from the first floor of the containment building. There is no direct personnel access from the basement of the containment building to the adjoining basement of the NNRC. The reactor process equipment was located within a room surrounded by 2-foot thick concrete walls. This room contained the primary coolant system and heat exchangers, reactor overflow and purification system, heavy water storage tank, heavy water recombiner, helium makeup system, secondary water system, and thermal shield cooling water system. Adjacent to the process equipment room is the containment building exhaust system blower and High Efficiency Particulate Air (HEPA) filters. Cast into the basement slab is a large
REVISION 0
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
2
holdup volume for the exhaust air. Another large void in this concrete slab provided an expansion chamber, which was connected to the helium/nitrogen space above the reactor core through a rupture disk.
The basement also contained the reactor sump, the Motor Control Center (MCC) electrical panel, the biomedical facility door hydraulic system, an elevator equipment room, a cooling water system for the bismuth blocks and three rooms, which housed the service air compressors, pneumatic transfer systems (rabbit systems) and an experimental area. The basement plan is shown in Figure 2.2.
2.1.2 First Floor
The first floor of the containment building, which is also the ground elevation, contained the reactor and its bioshield. The GTRR was a 5 MW thermal, heavy water moderated, cooled and reflected reactor that was fueled with uranium aluminum alloy plates. As stated earlier, the fuel elements were removed from the facility in February, 1996. The reactor was equipped with numerous horizontal and vertical experimental ports for access to fast and slow neutron beams. The reactor vessel was an aluminum, cylindrical tank approximately 6 feet in diameter and 10.4 feet high. The reactor's neutron flux was controlled by four aluminum-clad cadmium shim safety blades and an aluminum-clad cadmium regulating rod. The reactor vessel sat on a steel support structure and was suspended within a 2-foot thick graphite reflector. Graphite stringers surrounded the reactor from beneath the vessel and in a radial direction. A 0.25 inch thick cylindrical boral sleeve encompassed the graphite stringers. The nuclear reactor and graphite reflector were housed inside a lead shield tank. The lead shield tank consisted of 3.5 inches of lead sandwiched between two layers of steel. All of the above was enclosed within a 4.75 foot thick concrete and iron aggregate biological shield.
The first floor also contained a vertical water-filled spent fuel storage hole which was approximately 19 feet long and extended into the basement slab. This spent fuel storage hole was located inside one of the first floor structural support columns. A Plug Storage Vault with 18 horizontal storage tubes was set into the outside wall of the containment building on the first floor.
The first floor of the containment building can be accessed by one of three routes: the main air lock leading from the NNRC building; a smaller personnel air lock leading from the outside yard; and a truck door. There was plenty of space available on this floor to conduct experiments using one of the many horizontal beam ports. A thermal column was located on one side of the reactor while a shielded irradiation room (the biomedical facility) was situated on the opposite side immediately adjacent to the reactor. Figure 2.3 shows the first floor plan.
REVISION 03
FINAL SURVEY REPORT
2.1.3 Second Floor
The second floor is 15 feet above the first floor and provided access to the top of the reactor. It can be reached by either using an elevator or stairs. A walkway (catwalk) runs completely around the circumference of the building on this elevation. The reactor control room occupies much of the second floor. An Emergency Core Cooling System (ECCS) tank was located on the second floor above the catwalk. Air was supplied to the containment building through an air-conditioning unit, which was located on top of the control room. An overhead 20-ton capacity polar crane that services the reactor building is supported by rails approximately 15 feet above the second floor. Figure 2.4 provides a plan of the second floor.
2.1.4 Reactor Yard
The grounds surrounding the containment building consist of an asphalt surface extending from the access gate around the containment building to a metal storage building, concrete surfaces adjacent to the containment building, gravel in the southwest comer formerly occupied by the cooling tower, and grass in the remaining areas.
2.2 Operating History
The GTRR was built in the 1960's as a component part of the Neely Nuclear Research Center. The reactor first went critical on December 31, 1964. It was licensed to operate at 1 MW (t) output for a thirty year period. In 1974 the license was amended and the reactor was upgraded to produce 5 MW (t). It continued to operate at this level until reactor operations ceased on November 17, 1995. The GTRR logged approximately 40,000 MW-hrs of operation.
The reactor was designed to accommodate many different research applications. The reactor produced a thermal flux of greater than 1014 neutrons/cm2/sec at a power of 5 MW(t). There were ten horizontal beam ports, two horizontal through ports (one above the reactor core and one below the reactor core), fourteen vertical ports, two large troughs located below the reactor, and a pneumatic tube conveyance system that could be used for research activities. Experiments were performed utilizing high intensity neutron beams, gamma ray beams, as well as a uniform thermal neutron flux through a large sized beam. The pneumatic tube system provided the ability to perform short irradiations or irradiations that required rapid sample recovery. Students and researchers employed the reactor to investigate materials science properties, to study nuclear physics and other frontiers of nuclear research.
Although there was a biomedical irradiation facility, no biomedical experiments were ever performed.
REVISION 0
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
4
FINAL SURVEY REPORT
Figure 2.1 Reactor Yard
REVISION 0
AOCM8
FENCE LINE
N-4
GA TECH RESEARCH REACTOR
5
GA TECH RESEARCH REACTOR FTh�AL SURVEY REPORT
Figure 2.2 Containment Building Basement
REVISION 0
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
6
FINAL SURVEY REPORT
Figure 2.3 Containment Building First Floor
REVISION 0
GA TECH RESEARCH REACTOR
7
GA TECH RESEARCH REACTOR
Figure 2.4 Containment Building Second Floor
REVISION 0
FINAL SURVEY REPORT
8
2.3 Management Approach
The GSFIC, as the owner, and on behalf of the using agency, Ga. Tech, contracted IT Corporation to decommission the GTRR in accordance with the NRC approved GTRR Decommissioning Plan. IT Corporation was responsible for the management and execution of all decommissioning activities. In addition to performing site work tasks, IT provided site radiation protection, health and safety, and quality assurance personnel. IT's primary subcontractor for this project was GTS Duratek (Duratek) which was responsible for the initial survey, all waste management activities, including packaging and transportation, and the final survey of the facility.
The Ga. Tech Radiation Safety Officer, who is responsible for all radiation safety matters on campus, reviewed and approved all Radiation Work Permits (RWPs) and radioactive waste shipping documents for the project. As the licensee, the Radiation Safety Office monitored the radiation exposure of all decommissioning personnel.
The GSFIC contracted CH2M HILL to serve as the Executive Engineer for this project. CH2M HILL personnel provided technical oversight and consultation to Ga. Tech during the course of the project. They coordinated the review of various project documents, monitored daily decommissioning activities and performed independent audits of the work.
A Technical Safety Review Committee (TSRC), consisting of six members appointed by the president of Ga. Tech from the faculty and the private sector, reviewed and approved all plans and procedures for the decommissioning project. Any deviations from the GTRR Decommissioning Plan, were screened by a Title 10 Code of Federal Regulations Chapter 50.59 (10 CFR 50.59) safety screening and evaluation process, and approved by the TSRC prior to implementation.
2.4 Decommissioning Activities
IT's decommissioning activities began with the development of necessary site specific plans and procedures. Once approved, personnel and equipment were mobilized to the project site in November, 1999. Two temporary office trailers were located in the southwest comer of the yard outside the containment building (see Figure 2.5). These trailers housed the management and technical support personnel. Project files and site logs were maintained in the larger site office trailer. A laboratory trailer, equipped with the necessary radiological analysis / counting equipment, was located at the north end of the yard adjacent to the NNRC. A decon trailer was situated next to the containment building's secondary personnel air lock and it served as the main access control point into the containment building during decommissioning activities. The decon trailer contained personnel protective equipment and clothing, a change area, lockers, showers, and wash sinks. Radiation Work Permits and Work Packages were
REVISION 0
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
9
located in the decon trailer for personnel review prior to entering the containment building.
After completing all required training and orientation classes, site personnel commenced the initial site survey. The purpose of this survey was to assess the existing radiological conditions of the facility. The radiation levels and radioactive contamination levels were compared with those described in the report entitled GTRR Decommissioning Project Radiological Characterization Report, prepared by NES, Inc. This data was used to prepare RWPs and perform ALARA reviews for the decommissioning work packages. In addition to surveys, two core borings were obtained from the biological shield. These borings were sectioned and sent to an off-site laboratory for radiation analysis to determine the extent of activation in the bioshield concrete.
A detailed site inventory of radioactive materials was compiled during the initial site survey. Most of these items were located on the first floor and occupied floor space necessary for decommissioning operations. Empty sealand containers, received from Duratek, were brought into the containment building through the truck door. Radioactive materials that could not be decontaminated to radiological free release limits were packaged and placed in these containers. Once the containers were full they were sealed and transported out of the containment building through the truck door using the polar crane, rollers and a forklift truck. Full sealand containers were temporarily stored on paved or concrete surfaces within the controlled area of the site. A flatbed trailer was used to ship the full sealand containers from the NNRC to Duratek's Bear Creek, Tennessee Facility. Radioactive materials that were received at the Bear Creek facility were either processed for disposal at Envirocare's disposal site in Utah, processed through Duratek's Green Is Clean Safecheck Program for disposal at the Carter's Valley Landfill in Churchhill, TN, or recycled by Duratek. Items in the containment building that were surveyed after decontamination and found to meet radiological free release criteria were removed from the building and placed adjacent to the metal storage building on site.
Reactor dismantlement operations commenced in January 2000. All nonessential electrical components were disconnected at the motor control center, located in the basement. The only components considered essential were the building HEPA filtered ventilation system, the polar crane, and the stack fan. These components remained operational throughout the decommissioning operation. Once power was disconnected from the nonessential components, electricians detached all electrical wire terminations to allow for safe removal of these items by decontamination technicians.
REVISION 0
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
10
Auxiliary systems, such as the space heating hot water, domestic hot water, chilled water and city water systems, were isolated and tagged out-of-service on the NNRC side of the containment building. Meanwhile, the cold water supply line from the NNRC remained energized while its return line was tagged closed. In addition, the interconnecting compressed air line from the NNRC to the containment building remained open. After these systems were isolated, dismantling operations began in the basement with the removal of three air conditioning units which were contaminated above release limits. These units were cut free from their chilled water lines, transported to the first floor and placed in a sealand container.
In order to provide access to the primary coolant system in the process equipment room, the secondary water system components and piping spool pieces were
unbolted at convenient flange connections and separated from the system. These items were either rigged to the polar crane and lifted out of the basement through the equipment hatch and placed in a sealand container or placed directly in a B-25 box in the basement. The entire secondary water system was removed up to the flange connections adjacent to the containment building penetrations. A blind flange was bolted to the secondary cooling water supply line to minimize water leakage into the process equipment room.
Other systems in the process equipment room, such as the heavy water recombiner, helium makeup system, the overflow return and purification system and the thermal shield cooling system were dismantled by first cutting small bore pipes into manageable sections or unbolting components and pipes at flange connections. Drip containments were used to collect any residual water in the piping systems. Larger components were transported by forklift to the equipment hatch then lifted by polar crane out of the basement and placed directly in sealand containers, while smaller pipe sections or components were placed in B-25 boxes. Once the B-25 boxes were full, they were brought up to the first floor and emptied into an appropriate sealand container.
The primary coolant system was dismantled in a similar fashion. However, the stainless steel components from this system were segregated from other steel components and placed in a separate sealand container. Residual heavy water collected from this system was poured into a separate stainless steel drum and returned to the Department of Energy's Savannah River Site. The large primary coolant system components, such as the heavy water tank and heat exchangers, were rigged to anchors installed in the ceiling and carefully moved with chains and come-alongs to the equipment hatch opening. At this point, these components were rigged to the polar crane, lifted out of the basement and placed in sealand containers for shipment to Duratek's metal melt facility in Bear Creek, Tennessee.
REVISION 0
GA TECH RESEARCH REACTOR FINA-L SURVEY REPORT
11
Primary coolant system piping extended from the process equipment room into the reactor pipe tunnel through a temporary concrete shield wall. This shield wall was demolished with the use of expandable grout and handheld jackhammers. Local HEPA filtered ventilation systems were used to control dust in this area during demolition operations. Concrete pieces were collected by hand and with shovels and then placed in B-25 boxes for future disposal.
The other radioactively contaminated systems located in basement rooms or areas adjacent to the process equipment room were disassembled as described above. The two pneumatic transfer systems (rabbit systems) were separated from their pneumatic tubing and power supplies. Each of these systems was packaged for shipment and transported to a sealand container on the first floor. The bismuth cooling system was cut into manageable pieces, carried to the first floor by elevator or polar crane and placed in the appropriate sealand container.
Wooden timbers were placed under each comer of the biomedical room door to provide support while the door's hydraulic system was disengaged and removed. Hydraulic fluid was drained from the system and collected in clean 55 gallon drums. The hydraulic system was disassembled and removed from the basement area to a sealand container.
On the first floor of the containment building, a neutron diffractometer and a water transfer system (guppy system) were still attached to the reactor. The neutron diffractometer was disassembled by rigging various pieces to the polar crane and placing them in a sealand container. Water was drained from the guppy system and placed in a 55 gallon drum for disposal. The guppy system piping was removed from the horizontal beam port and cut into manageable sections for disposal. Other parts of this system were disassembled and placed in a sealand container.
The air conditioning unit on top of the control room on the second floor of the containment building was cut free from its chilled water lines. It was rigged to the polar crane and transferred from the top of the control room to a sealand container. An auxiliary fan which provided additional cooling air flow to the control room was disassembled and removed. An Emergency Core Cooling System (ECCS) which was connected to the reactor was also located on the second floor of the containment building. The ECCS tank was situated on a platform above the second floor catwalk. Piping to this tank was cut and the tank was lifted off the platform with the polar crane. Piping from the ECCS tank to the reactor was cut into manageable lengths and placed in a sealand container along with the ECCS tank.
Dismantlement of the reactor itself commenced in March, 2000, once all the connecting pipes and components were removed. The horizontal beam port plugs were pulled out of each of the horizontal beam ports. The horizontal beam gates were lifted from the top of the reactor with the polar crane and all graphite plugs
REVISION 0
FINAL SURVEY REPORTGA TECHt RESEARCH REACTOR
12
GA TECH RESEARCH REACTOR
were removed from the horizontal beam ports with long handle tools. The horizontal beam port aluminum thimbles were extracted with long handle tools or chains and come-alongs. Fission chambers and other nuclear instruments were removed from their horizontal ports around the base of the reactor. The polar crane was used to lift plugs and aluminum thimbles out of each of the vertical experimental ports from the top of the reactor. Graphite plugs were placed in B-25 boxes and the fission chambers were stored in a 55 gallon drum, while all other metal items were placed in sealand containers.
A nuclear startup source was located within one of the vertical experimental ports. It was removed from the reactor with the assistance of the fuel transfer cask in order to minimize radiation exposure to personnel. The fuel transfer cask was transported by polar crane to the top of the reactor and situated over the vertical port. The sliding door of the cask was opened and a hook was lowered to retrieve the startup source. Once the startup source was engaged, it was raised into the fuel transfer cask and the entire assembly was lowered to the first floor by polar crane. At this point, the startup source was lowered just enough to allow the very end of the assembly to be cut and placed in a shielded lead container for temporary storage. The remainder of the assembly was retrieved from the fuel transfer cask and placed in a sealand container.
Eyebolts were installed in the reactor lead cover plate. It was rigged to the polar crane and removed from the top of the reactor. The reactor's upper top shield was rigged in a similar fashion and hoisted by the polar crane. Both of these components were placed in sealand containers for shipment to Duratek.
The drive mechanism for the regulating rod, which was located on the outside wall of the bioshield, was electrically disconnected and mechanically disassembled. Once the regulating rod was released from its drive mechanism, it was slowly extracted with the polar crane, from the reactor vessel, through the lower top shield. The regulating rod was placed on top of the reactor and covered with lead blankets to reduce radiation exposure. It was cut into two sections with a band saw. The lower section, which contained cadmium was transferred to the plug storage vault for temporary storage, while the upper section was placed in a sealand container.
Eyebolts were inserted into the lower top shield and it was rigged to the polar crane., The lower top shield was carefully raised from the reactor and lowered through the equipment hatch into a containment area built in the process equipment room in the basement. IT Corporation subcontracted Bluegrass Concrete Cutting Inc. to cut the lower top shield into two sections with a diamond wire saw within this containment area. The bottom section, which contained approximately 8 inches of lead shielding material and had a significant radiation dose rate associated with the bottom plate, was separated from the remaining nonradioactive section. After the cut was completed, the two pieces of the lower top shield were placed in appropriate sealand containers for shipment to Duratek.
REVISION 0
FINAL SURVEY REPORT
13
The shim safety drive mechanisms were uncoupled from the shim safety blades in
the same fashion as the regulating rod. Once each shim safety blade was released
from its drive mechanism, it was extracted from the reactor vessel and placed under lead blankets on top of the bioshield. The lower section of each shim safety
blade, which contained cadmium, was separated from the remainder of the rod and placed in the plug storage vault for temporary storage. The upper section was
transferred to a sealand container.
Three biomedical room shutter shield blocks were pulled out of their shaft enclosure using eyebolts and the polar crane. Prior to lifting the last shield block, the hydraulic cylinder, which operated the biomedical room shutter, was disconnected from the bottom of this block. Once this shield block was removed, hydraulic fluid was drained from the cylinder and collected in a clean 55 gallon
drum. The cylinder was disassembled and placed in a sealand container. Bismuth shield blocks were extracted from the biomedical room window with a special
lifting tool supported by the polar crane. The bismuth shield cooling water
system pipes were cut and placed in the appropriate sealand container.
After completion of an inspection to verify that the reactor vessel's horizontal ports, pipe extensions and other connections were free from any obstruction, the
vessel was rigged to the polar crane. The reactor vessel was slowly pulled out of
the bioshield and surveyed. Since the top portion of the vessel was not activated, it was cut with a circular saw and transferred into a sealand container. The
remaining bottom section of the reactor vessel was subsequently pulled completely out of the bioshield and laid on its side in an empty sealand container.
The reactor vessel's pipe extensions were carefully cut with a long handle tool
close to the bottom of the vessel. Meanwhile, the graphite retaining sleeve was
removed from the bioshield cavity. It was immediately transferred into a radioactive waste shipping liner. The shipping liner was located behind a temporary shield wall to minimize radiation exposure to personnel, as this liner
was to receive all the highly radioactive components. Once the pipe extensions were removed from the bottom of the reactor vessel, the vessel was rigged to the
polar crane and transferred from the sealand container to the radioactive waste
shipping liner. The above pipe extensions, the startup source and other highly
radioactive components were retrieved from various temporary storage containers
and placed inside the shipping liner. After the shipping liner was filled, it was
sealed and prepared for shipment to Chem Nuclear's (CNSI) Barnwell, South
Carolina disposal facility. A separate shielded cask shipment was made for this purpose.
Decommissioning activities continued in April, 2000, with the mechanical
removal of the thermal column doors. Once the graphite blocks and stringers
were uncovered, a containment tent complete with HEPA filtered ventilation was
constructed around the thermal column opening to minimize the spread of
graphite dust and radioactive contamination. Graphite blocks and graphite
stringers were removed by hand from the thermal column opening toward the
REVISION 0
FINqAL SURVEY REPORT
14
GA TECH RESEARCH REACTOR
center of the bioshield. The graphite stringers were packaged in B-25 boxes inside the containment tent. When the boxes were full, graphite removal operations were temporarily suspended to allow replacement of full boxes with empty ones inside the containment tent. It was discovered that the graphite closest to the reactor vessel was activated and required segregation from other graphite for disposal purposes. These graphite stringers, with higher radiation levels, were placed in separate B-25 boxes and shipped directly to Chem Nuclear's Barnwell, South Carolina disposal site.
In June, 2000, the outer steel plate walls of the bioshield were sectioned into 4' x
8' or 4' x 4' pieces. A needle gun was used to scrape the lead based paint off the
steel plate surfaces along anticipated cut lines. The steel plate was cut with an oxy-gasoline torch and pried loose from the bioshield concrete with a hoe-ram and placed in sealand containers. Other metal items that were temporarily stored in the plug storage vault, such as the cadmium ends of the shim safety blades and regulating rod were also placed in this sealand container and shipped to Duratek's metal melt facility.
Once the steel plate was removed from the concrete bioshield, a containment tent was constructed inside the containment building. The purpose of this tent was to minimize the spread of concrete dust and contamination during subsequent bioshield concrete demolition operations. The containment tent roof was supported by the polar crane hook, while the tent walls hung from the second floor catwalk railing down to the first floor. The tent surrounded the entire concrete bioshield and provided enough space on the first floor for heavy concrete demolition equipment. The containment tent was equipped with five HEPA filtered ventilation units and a water mist system for dust suppression. An exhaust system was also installed inside the tent to remove combustion gases from the operating equipment and minimize the buildup of carbon monoxide (CO) gas. A track hoe and a back hoe each equipped with a hoe-ram attachment were employed to demolish the bioshield concrete. Based on the bioshield core sample analytical results, concrete was removed in layers. The bioshield outer concrete, extending to the center line of the horizontal beam gate vertical inserts, was demolished first. This concrete contained very little radioactivity. The second pass with the hoe-ram demolished the remaining concrete up to the outer walls of the lead shield tank. Once a pile of concrete rubble was produced by the hoe-rams, a front end loader mounted on a Bobcat scooped up the rubble and placed it in B-25 boxes. The boxes were sealed, weighed and removed from the containment building by forklift for future shipment to Duratek. At Duratek's Bear Creek, Tennessee facility the B-25 boxes were analyzed for radioactivity and segregated for disposal either at Envirocare's site in Utah or at a local approved Tennessee landfill.
When most of the bioshield concrete was removed, a hydraulic shear attachment was mounted on the track hoe. The hydraulic shear cut and detached the remaining metal components of the horizontal beam ports, vertical experimental
REVISION 0
FINAL SURVEY REPORT
15
ports, spent fuel holes, reactor vessel support structure and any other structural steel from the top and outer walls of the lead shield tank. All these metal items were stockpiled in the containment tent until a sealand container was brought into the building. Any residual concrete that was hidden by these components was
removed by the back hoe mounted hoe-ram. Upon completion of the bioshield concrete demolition, the containment tent was removed along with the heavy
construction equipment to allow the polar crane to load metal debris into a sealand container.
Bolts that held the lead shield tank lid in place were cut with a portable saw. The
lead shield tank lid was rigged to the polar crane and transferred to the floor. It
was shrink wrapped in plastic and prepared for shipment to Duratek.
IT Corporation subcontracted the Barnhart Crane and Rigging Co. (Barnhart) in October, 2000 to remove the lead shield tank from the containment building. Barnhart installed a gantry hydraulic lift system on the first floor. The lead shield
tank was rigged to the gantry and slowly hoisted out of the depression in the first
floor. Once it was above the floor elevation, the lead shield tank was carried by
the gantry lift along the system tracks towards the truck door. At this location, the
lead shield tank was surveyed, prepared for shipment and shrink wrapped in
plastic. The tank was rotated 90 degrees and transferred out of the containment building with forklift trucks. After it was brought outside, it was wrapped once
again in plastic and transported by two heavy lift forklifts to an overweight load bearing lowboy trailer. The lead shield tank was placed on the trailer and transported to Duratek's facility in Tennessee.
Activated concrete in the area beneath the lead shield tank was removed with the
back hoe mounted hoe-ram. Local HEPA filtered ventilation was used to control
dust during this concrete demolition. A steel template that aligned the reactor
bottom nozzles was removed from this area by the hoe-ram. This created a large opening into the reactor pipe tunnel. Concrete debris was retrieved from the reactor pipe tunnel area and placed in a B-25 box while the metal plate was placed in a sealand container.
The plug storage vault was examined to insure that all holes were empty and clean. Caps were secured to each vault hole. The entire plug storage vault was
extracted from its wall cavity in November 2000 with a forklift truck and the
polar crane. The vault was prepared for shipment and transferred out of the
building through the truck door. It was shipped on a flatbed truck to Duratek.
The spent fuel storage hole located within a structural column in the process equipment room was contaminated above the site release limits. This hole
extended 19' 3t" from the first floor into the basement concrete slab. A chemical
decontamination process was tested in a NNRC laboratory to check its effectiveness on the stainless steel surfaces of the spent fuel storage hole. The test
results were promising, so a chemical decontamination loop was built in the
REVISION 0
FINAL SURVEY REPORT
16
process equipment room complete with chemical injection tanks, a heater and a recirculation pump. Chemicals were mixed in the chemical tanks and injected into the spent fuel storage hole. The solution was heated and circulated for a short period of time. The acidic chemical decontamination process was applied a total of three times. The spent chemical solution was neutralized with caustic and pumped into 55-gallon drums for shipment to Duratek. Radiation survey results, however, indicated that the very bottom plate of the spent fuel storage hole was still above the site release limits. Mechanical decontamination methods were attempted but proved ineffective on the very bottom plate. A remotely operated electrical hoe-ram was employed to break up the concrete floor in the area adjacent to the column to gain access to the bottom plate. The hoe-ram successfully punctured the outer wall of the spent fuel storage hole pipe and severed the bottom plate from the remainder of the pipe. This plate was retrieved and transferred to an appropriate sealand container, while the concrete debris was placed in B-25 boxes.
The reactor building sump was tagged out-of -service and disconnected from the low-level radioactive waste system. The sump pump and discharge piping were removed from the basement elevation. The remaining sludge in the sump was pumped into 55-gallon drums for disposal by Duratek. Basement drain lines that directed water to the sump were flushed with high pressure water to remove any residual contamination and debris. This water was collected in 55 gallon drums and processed for disposal by Duratek.
Sections of the ventilation system were removed during demolition activities to allow future access for survey instruments. All ducts that were removed were placed in sealand containers, except for the elbow that connected the holdup duct to the HEPA filtered ventilation system. This elbow was detached, surveyed and left in the building for future reuse.
When decommissioning activities were complete, Duratek commenced informational radiation surveys of floor and wall surfaces to verify that these surfaces met the final release criteria. Several locations throughout the containment building required further concrete removal in order to achieve the release criteria. These areas included portions of the process equipment room floor and walls, the heavy water storage tank pit floor and walls, the reactor pipe tunnel floor and wall surfaces, the rupture disk pipe tunnel area, the biomedical facility shutter block shaft and floor area, the biomedical facility door hydraulic sump area, the biomedical room floor and spots on the first and second floors of the containment building. Angel grinders, needle guns and, as necessary, jack hammers were employed to remove concrete from these contaminated areas. Local HEPA filtered ventilation was used during these operations to minimize the spread of contamination and suppress concrete dust.
REVISION 0
FINAL SURVEY REPORTGA TECH RESEARCH REACTOR
17
GA TECH RESEARCH REACTOR
During the informational survey of the reactor pipe tunnel in January, 2001, Duratek discovered that the overpressure pipe chase walls were above the site release criteria. It was determined that the concrete in these walls was activated. Expandable grout was used to fracture the concrete and assist with its removal. Electric chisels and hammers were utilized to complete the concrete demolition in this area. Up to an additional 12 inches of concrete was taken out of the walls in the overpressure pipe chase.
When all decommissioning activities in the containment building were complete, the containment building's service air system was dismantled. The interconnecting service air pipe was isolated on the NNRC side of the containment building and capped in the basement. The containment building air isolation valves were placed in an open position, to allow air to circulate through the building, while the service air operators for these valves were removed. The air receiver tanks were depressurized and transported to a sealand container. The service air compressors located in the basement were dismantled and transferred to the first floor. Service air pipe was cut into manageable pieces and removed from the containment building in B-25 boxes. The inflatable rubber seals of the main air lock, the personnel air lock and the truck door were unbolted and removed.
Fifty-six (56) total radioactive waste shipments were made during the GTRR decommissioning. The final waste shipment occurred on August 3, 2001. All radioactive waste was sent to one of four consignees. The radioactive waste consignees were Duratek Inc., CNSI Barnwell, Envirocare of Utah, and Westinghouse Savannah River Site. Table 2.1 shows the total weight shipped to each of the four consignees.
Final Surveys began in May, 2001. The survey method and results are presented in the following sections.
TABLE 2.1 Georgia Tech Waste Disposition
WASTE COSIGNEE WASTE WEIGHT (LBS) Duratek 1,574,865 lbs
CNSI-Barnwell 59,364 lbs Envirocare 840 lbs
Westinghouse SRS 500 lbs
REVISION 0
FINAL SURVEY REPORT
18
GA TECH RESEARCH REACTOR
FIGURE 2.5 SITE LAYOUT
ACCESS GATE
OFFICE 1 TRAILERS
RETAINING
REVISION 0
FINAL SURVEY REPORT
19
GA TECH RESEARCH REACTOR
3.0 FINAL SURVEY
3.1 Introduction
The purpose of the Final Survey Report is to demonstrate that the GTRR facility meets the guideline values established for release for unrestricted use. This required the collection of accurate and reliable data to determine residual activity levels. The Final Survey was performed in accordance with GTRR projectspecific procedures and the Final Survey Plan.
Implementation of the Final Survey included the following:
" Duratek supervisory personnel performed a preliminary inspection of the survey areas to identify survey requirements, including special survey situations, and to provide specific survey instructions.
"* A survey package was prepared for each survey area.
"* Suspect Affected survey areas were gridded to provide a systematic method for the collection of survey data.
"* Each survey area had a sufficient number of measurements taken to accurately represent the surface being surveyed.
"* Survey locations were marked and mapped in all non-gridded areas.
" Survey measurements were performed and samples analyzed using appropriately calibrated instrumentation. Daily source and background checks were carried out before and after each day's work.
"* Survey data collected during the final survey was downloaded from the survey instrument into a database for storage and processing.
" Completed survey packages were reviewed by supervisory personnel to ensure that all required surveys were performed and that the packages contained all necessary information.
" Survey results were reviewed by supervisory personnel to verify that the criteria for release for unrestricted use were not exceeded. Areas of residual activity were identified, evaluated, and reclassified as required.
REVISION 0
FINAL SURVEY REPORT
20
FINAL SURVEY REPORT
3.2 Survey Guideline Values
3.2.1 Criteria for Release for Unrestricted Use for Building Surfaces
Site Specific Guideline Values, SPGLs, were derived for use in demonstrating that the Georgia Tech Research Reactor met the criteria for release for unrestricted use. These SPGLs were based on the radionuclide specific guideline values contained in NRC Regulatory Guide 1.86 except for H-3 and Fe-55. The guideline values for H-3 and Fe-55 were increased based on instructions from the Executive Engineer for this project (Reference 6.4). The increase in guideline values for H-3 and Fe-55 was consistent with previous NRC policy contained in NRC Policy Memorandum SECY-94-145. Although higher than the NRC Regulatory Guide 1.86 limits, these increased guideline values are orders of magnitude lower than the current guideline values for H-3 and Fe-55 specified in the NRC License Termination Rule. Table 3.1 lists the radionuclide specific guidelines used in deriving the SPGLs. With the exception of footnote "f', the footnotes to Table 3.1 are identical to those associated with Table 1 of Regulatory Guide 1.86.
REVISION 021
GA TECH RESEARCH REACTOR
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
Table 3.1 Radionuclide Specific Guideline Values
u-.NaT, u-/.5), u-zia, ana associaTea decay products
'Where surface contamination by both alpha and beta-gamma emitting nuclides exists, the limits established for alpha and beta-gamma emitting nuclides should apply independently. bAs used in this table, dpm (disintegrations per minute) means the rate of emissions by radioactive material as determined by correcting the counts per minute observed by an appropriate detector for background, efficiency, and geometric factors associated with the instrumentation. cMeasurements of average contaminant should not be averaged over more than 1 square meter. For objects of less surface area, the average should be derived for each object. dThe maximum contamination level applies to an area of not more than 100 cm 2. eThe amount of removable radioactive material per 100 cm2 of surface area should be determined by wiping that
area with dry filter or soft absorbent paper, applying moderate pressure, and assessing the amount of radioactive material on the wipe with an appropriate instrument of known efficiency. When removable contamination on objects of less surface area is determined, the pertinent levels should be reduced proportionally and the entire surface should be wiped. f Letter from Executive Engineer to IT Corporation dated 4/18/00 providing alternate H-3 and Fe-55 guidelines for the Ga Tech Research Reactor Decommissioning (Reference 6. 4). Removable contamination to be assessed as described in Footnote e, except using a wet smear.
REVISION 0
Transuranics, Ra-226, Ra-228, 100 dpm/100 cm 2 300 dpm/100 cm 2 20 dpm/100 cm 2
Th-230, Th-228, Pa-231, Ac-227, I125, 1-129 Th-Nat, Th-232, Sr-90, Ra-223, 1,000 dpm/100 cm 2 3,000 dpm/100 cm 2 200 dpm/100 cm 2
Ra-224, U-232, 1-126, 1-131, 1-133 H-3 and Fe-55f 200,000 dpm/100 cm 2 600,000 dprr/100 cm 2 10,000 dpm/100 cm 2
Beta-gamma emitters (nuclides with 5,000 dpm /100 cm 2 15,000 dpm /100 cm 2 1,000 dpm /100 cm 2
decay modes other than alpha emission or spontaneous fission) except Sr-90 and others mentioned above
22
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
3.2.2 Site Specific Guideline Values, SPGLs
The site specific guideline values for demonstrating that the Georgia Tech Research Reactor facility met the criteria for release for unrestricted use were derived based on guidance contained in NUREG/CR-5849, the radionuclide specific guideline values listed in Table 3.1, and the actual radionuclide mix as determined by sample analysis. The SPGLs were calculated using the following formula:
F SPGL = n fi
i~i
Where: F = the fraction of the assumed radionuclide mix that is
considered detectable, unitless.
fi = the relative fraction of radionuclide i, unitless.
GLi = the radionuclide specific guideline value for radionuclide i taken from Table 3.1, dpm/100 cm2 .
n - the number of radionuclides present in the radionuclide mix.
Site specific guideline values for total beta activity and removable beta activity were calculated according to the above formula using the sample analysis results from three samples collected within the Georgia Tech Research Reactor Containment Building. Attachment A contains the spreadsheets used to perform these calculations. The results of these calculations are summarized in Table 3.2.
REVISION 023
Table 3.2 Site Specific Guideline Values
for Total Beta Activity and Removable Beta Activity
Sapl Dscitiu PG dpm7100 cm) SPGL (dpmi/1O CM2)
GEL- 1, Concrete Sample From 1,500 104 Under Reactor Vessel
GEL-2, Concrete Sample From Pit 3,800 688 Beneath Door To Biomedical
Room GEL-3, Primary Coolant Resin 2,000 148
Sample AVERAGE 2,400 313
In order to demonstrate compliance with the criteria for release for unrestricted use, the three sample SPGL's listed in Table 3.2 were averaged for a site SPGL.
3.2.3 Criteria for Release for Unrestricted Use of Open Land Areas
Under Subpart E, of 10 CFR 20.1402, NRC licenses may be terminated and a site released for unrestricted use if the residual radioactivity that is distinguishable from background results in a total effective dose equivalent, TEDE, that does not exceed 25 mrem/yr and the residual radioactivity has been reduced to levels that are as low as reasonably achievable, ALARA. NRC has published (Federal Register Vol. 64 page 68396, December 7, 1999) screening values for selected radionuclides in surface soils. Open land areas with activity concentrations less than the screening values are deemed to be in compliance with the 25 mrem/yr unrestricted release dose limit in 10 CFR 20.1402.
Table 3.3 lists screening values for the GTRR radionuclides of interest. These values were either published by the NRC or calculated using NRC methodology. These screening values were used as the site specific guideline values for open land areas. Surface soil samples (0-6 inches) were collected from open land areas within the reactor yard and compared to the criteria listed in Table 3.3. These soil samples were used to confirm the results of the characterization survey and demonstrate that the open land areas within the reactor yard fence met the criteria for release for unrestricted use and that the levels are ALARA.
REVISION 0
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
24
r-A TECH RESE ARCH REACTORFNASUVYRPT
Table 3.3 Radionuclide Specific Soil GuidelineValues
H-3 110
Fe-55 10,000
Pu-239/240 2.3
U-233/234 13.0
U-238 14.0
Ni-59 5,500
Cs-134 5.7
Cs-137 11.0
Co-60 3.8
Eu-152 8.7
Eu-154 8.0
Mn-54 15.0
Ag-ll0m 3.9
Zn-65 6.2
Sr-90 1.7
C-14 12.0
Ni-63 2,100
Tc-99 19.0
3.3 Instrumentation
Selection and use of instrumentation ensured sensitivities were sufficient to detect the radionuclides of interest at the required minimum detectable activities. A list
of the instruments, types of radiation detected, and their calibration sources is provided in Table 3.4.
The Ludlum Model 2350 Data Logger and various detectors were used for direct surface and exposure rate measurements. The data logger is a micro-processor computer based counting instrument designed for use with a wide range of detectors. NaI(T1) scintillation, gas-flow proportional detectors, and GM detectors were used to obtain field measurements for Final Surveys.
REVISION 0
FINAL SURVEY REPORT
25
GA TECH RESEARCH REACTOR
Detector selection depended on the survey to be performed, surface contour and survey area size. For direct measurements, the 126 cm 2 gas-flow proportional detector was normally used. A 1" x 1" NaI(Tl) gamma scintillation detector was used for gamma exposure rate measurements.
Specialized gas-flow proportional and GM pipe detectors were used in conjunction with a Ludlum Model 2350 to survey the interior surfaces of drains, piping, and penetrations remaining in the GTRR facility.
Smears for removable alpha and beta contamination were analyzed using a Protean Low Background Alpha/Beta Counter or equivalent.
Smears for removable low energy beta emitters such as H-3 were analyzed using a Beckman Liquid Scintillation System.
An EG&G Ortec Gamma Spectroscopy System, or equivalent, was used for gamma isotopic identification and quantification.
Table 3.4 Final Survey Instrumentation
REVISION 0
Detector TRadiatin 1Clbation Instrument/Detector jType jDetecte Souce jUse
Ludlum Model 2350/43-68 Gas-flow proportional Beta 99Tc ([) Direct measurements (126 cm2)
Ludlum Model 2350/44-2 NaI scintillator Gamma 137 Cs Gamma exposure rate
Ludlum Model 2350/44-40 Shielded GM (15.5 cm2) Beta 99Tc ([) Direct measurements
Ludlum Model 2350/43-94 and Gas-flow proportional pipe Beta 9 9Tc (•) Direct measurements Ludlum Model 2350/43-98 detectors inside pipes
Protean Low Background Gas-Proportional Alpha and 230Th (C) Smear counting Planchet Counter Beta 99Tc (P)
Beckman Liquid Scintillation Liquid Scintillation Beta 3H ([) Tritium Analysis
System Low Energy
Gamma Spectroscopy System HPGe Gamma Mixed Nuclide identification Gamma and quantification
FINAL SURVEY REPORT
26
FINAL SURVEY REPORT
3.3.1 Instrument Calibration
Data loggers and associated detectors were calibrated on a semi-annual basis using National Institute of Standards and Technology (NIST) traceable sources and calibration equipment.
The data logger calibration included:
* High Voltage calibration * Discriminator/threshold calibration * Window calibration * Alarm operation verification * Scaler calibration verification
The detector calibration included:
* Operating voltage determination * Calibration constant determination * Dead time correction determination
Calibration labels showing instrument identification number, calibration date and calibration due date were attached to all field instrumentation. The presence of a current calibration label was verified by the user before each use.
3.3.2 Sources
All sources used for calibration or efficiency determinations for the survey were selected to be representative of the instrument's response to the identified nuclides and were traceable to NIST.
Radioactive sources used for instrument response checks and efficiency determination were controlled by health physics technicians. Sources were stored securely and were issued to survey technicians as needed in the field.
3.3.3 Minimum Detectable Activity
Minimum Detectable Activity (MDA) is defined as the smallest amount or concentration of radioactive material in a sample that will yield a net positive count with a 5% probability of falsely interpreting background responses as true activity. The MDA value is dependent upon the counting time, geometry, sample size, detector efficiency and background count rate. The equation used for calculating the MDA for field instrumentation is:
REVISION 0
GA TECH RESEARCH REACTOR
27
GA TECH RESEARCH REACTOR
2.71 +32 Rbb MDA- tS ts tb
A
100
Where: MDA =
Rb =
tb =
ts
E A -
Minimum Detectable Activity (dpm/100 cm) Background Count Rate (cpm) Background Count Time (min) Sample Count Time (min) Detector Efficiency (counts/disintegration) Detector Area (cm2)
The a priori MDAs for the final survey were set at, or less than, 25% of the Site Specific Guideline Value. Table 3.5 provides the a priori MDA's that were established for the GTRR Final Survey. Count times were established up to a maximum of I minute, such that, in areas where background exposure rates allowed, these MDA's were achieved.
Table 3.5 Field and Laboratory Instrumentation MDA's
Direct Beta Surveys 600 dpm/1 O0 cm2
Removable Beta Surveys 75 dpm/100 cm2
Removable Alpha Surveys 15 dpm/1 00 cm2
Gamma Spec (Co-60, Cs-137) 0.1 pCi/g
Removable H-3 Surveys 200 dpm/1 00 cm2
Note ': Actual values varied based on count times, background, efficiency, etc. Refer to the individual survey packages for an estimate of the MDAs achieved.
The a priori MDAs for laboratory instruments were established at the 95% confidence level. MDAs were determined from the instrument supplied software algorithms or analysis spreadsheets using the above MDA equation. Count times used for the Protean Alpha-Beta Counter, the Ortek Gamma Spectroscopy System, and the Beckman Liquid Scintillation Counter were established to ensure that the desired MDA sensitivity was achieved. Background analysis and QC checks were performed daily to monitor for changes that would affect the MDA.
REVISION 0
FINAL SURVEY REPORT
28
3.4 Survey Organization
The Duratek Survey Supervisor reported to the IT Project Manager, who in turn reported to the Executive Engineer technically, and the Georgia State Financing and Investment Commission (GSFIC) contractually.
The on-site project survey team was supported by the resources of Duratek's Corporate Office. Additional oversight and support from Duratek's professional engineering and quality assurance staff was provided, as necessary, to the Duratek Survey Supervisor. Independent oversight was provided by the IT Quality Assurance Manager in accordance with the Quality Assurance Project Plan & Quality Assurance Procedures for the Georgia Institute of Technology Research Reactor Decommissioning Project.
Survey teams consisted of personnel trained, qualified, and experienced in field radiological survey procedures.
3.5 Survey Design
For the purpose of conducting the Final Survey at the GTRR facility, the survey areas were classified into three different categories. First, the survey areas were divided into Affected and Unaffected Areas based upon the initial characterization surveys, remedial actions, and historical information. Affected Areas were then subdivided into Suspect and Non-Suspect Areas. Each area was designated as a specific survey area and subdivided as necessary to facilitate the performance of Final Surveys. Large areas were subdivided into several survey units, and small like areas located on the same floor were combined into one survey unit. Equipment present in a survey area would normally be included within that area and was classified accordingly. However, each piece of equipment was evaluated and appropriately classified as determined by the Survey Supervisor based on initial survey and post-remediation survey data.
3.5.1 Unaffected Areas
An Unaffected Area was defined as any area where there was no known history of the storage or use of unsealed licensed radioactive material. Survey results that indicate the presence of radioactive material or contamination precluded an area from being classified as Unaffected.
3.5.2 Non-Suspect Affected Areas
A Non-Suspect Affected Area was defined as upper walls and overhead areas above two meters in an Affected area with minimal contamination potential based upon a review of the processes, history of the area, and characterization survey results. Survey results in excess of 25% of the
REVISION 0
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
29
site-specific guideline values (SPGLs) precluded an area from being classified as Non-Suspect Affected.
3.5.3 Suspect Affected Areas
A Suspect Affected Area was defined as an area not meeting the requirements specified for Unaffected and Non- Suspect Affected areas. Upper walls and overhead surfaces above two meters with survey results in excess of 25% the SPGLs were classified as Suspect Affected, except for the containment ceiling insulation which was reclassified if the survey results were in excess of 50% of the SPGLs.
3.5.4 Survey Area Breakdown
The following is the survey area breakdown for the performance of final surveys at the Ga. Tech Research Facility.
* Unaffected Areas
- Reactor yard areas not classified as affected (package 9) - Exterior surfaces of the Reactor Building (package 10) - Reactor yard open land areas (package 14) - Elevator equipment room and elevator shaft (package 21)
* Non-Suspect Affected Areas
- Reactor building 2nd floor upper walls (above 2 meters) and dome (package 3)
- Reactor building 1lt floor upper walls (package 5) - Reactor building basement, process equipment room upper walls
and ceiling (package 13) - Reactor building basement outside the process equipment room
above 2 meters (package 17) - Reactor building ventilation system and stack above 2 meters
(package 20)
0 Suspect Affected Areas
- Helium and reactor cooling water lines (package 1) - Reactor building 2nd floor and walls below 2 meters (package 2) - Reactor building 1lt floor and lower walls (package 4) - Reactor building ventilation hold-up duct (package 6) - Reactor building ventilation system and stack below 2 meters
(package 7) - Reactor yard areas used for the storage of radioactive materials
(package 8)
REVISION 0
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
30
- Basement drain lines (package 11) - Reactor building basement, process equipment room, floor and
lower walls (package 12) - Compressor Room (package 15) - Reactor building basement outside the process equipment room
floor and lower walls, including the reactor building sump (package 16)
- Vessel Tunnel (package 18) - Bismuth Leak Area (package 19) - Miscellaneous piping and penetrations inside reactor building
(package 22)
3.6 Area Re-Classification and Investigation
If during performance of the Final Survey, survey results indicated the presence of contamination in excess of 25% of the SPGL in an unaffected area, or survey results in excess of 50% of the SPGL on the containment ceiling insulation, or in excess of 25% of the SPGL in any additional non-suspect affected areas, the area, or a part thereof, was classified as a suspect affected area and an investigative survey performed. The investigative survey consisted of surveying the surrounding 9 square meters of the elevated survey point as if it were a suspect affected area.
3.7 Survey Package Development
A survey package was developed for each survey area. A walk-down of the area was performed, and a worksheet prepared containing a description of the survey area, historical information (as available), general survey instructions, location codes, specific survey instructions for any abnormal conditions within the survey area, and completion and review signature blocks.
During the survey, the packages were updated with direct and removable contamination survey data, exposure rate survey data, and results of any special surveys or sample analyses performed. These survey packages are summarized in section 4.0 Survey Results. The completed packages can be found in Attachment B of this report.
3.8 Survey Requirements
The Final Survey protocol was designed in part with NUREG/CR-5849 and other NRC approved final survey plans used at other Decommissioning and Decontamination projects as follows.
REVISION 0
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
31
3.8.1 Suspect Affected Areas
* 100% scan of the affected surface for beta contamination to identify areas of elevated activity requiring further investigation.
0 One direct measurement for each 1 m2 of area for total beta contamination. The floors and lower walls were gridded depending upon the number of interferences in the areas.
One measurement for each 1 m2 of area for removable beta and alpha contamination.
One exposure rate measurement at 1 meter above the floor at corresponding direct measurement locations to identify any areas with elevated radiation levels relative to the normal background that required additional investigation. Exposure rate measurements were not collected above obstructed measurement locations (obstructions due to equipment, permanent structures, etc.).
3.8.2 Non-Suspect Affected Areas
"* A 10% scan for beta contamination on building surfaces to identify areas of elevated activity requiring further investigation. The actual scanning coverage required for each non-suspect affected survey area (i.e. upper walls and ceilings) was dependent upon the contamination potential for these surfaces and was specified by the Survey Supervisor to the Survey Technician. The locations for scanning were chosen by the technician performing the survey, and were based on most probable areas for contamination.
"* Minimum of one measurement for fixed beta, and removable alpha and beta contamination per 20 M2, or 30 measurements, whichever was the greater for each survey area.
"* Additional measurements for direct beta, and removable alpha and
beta contamination on area equipment and structures, if applicable.
3.8.3 Unaffected Areas
A 10% scan for beta contamination on building surfaces to identify areas of elevated activity requiring further investigation. The locations for scanning were chosen by the technician performing the survey, and were based on most probable areas for contamination.
REVISION 0
FINAL SURVEY REPORTGA TECH RESEARCH REACTOR
32
"* Minimum of one measurement for fixed beta, and removable alpha and beta contamination per 50 M2 , or 30 measurements, whichever was the greater for each survey area.
"* One exposure rate measurement at 1 meter above the floor at corresponding direct measurement locations to identify any areas with elevated radiation levels relative to the normal background that required additional investigation. Exposure rate measurements were not collected above obstructed measurement locations (obstructions due to equipment, permanent structures, etc.).
"* Random measurements for direct beta, and removable alpha and beta contamination on area equipment and structures, including measurements in locations where contamination could likely accumulate.
"* Open land areas in the yard received a gamma scan covering at least
10% of the accessible areas. In addition, a minimum of 30 surface (0-6 inches) soil samples were collected at biased locations. The
RSO and EE approved the biased soil sample locations prior to collection of samples.
3.9 Gridding
The Final Survey Plan specified a gridded survey method for affected area floors
and lower walls. For affected areas where gridding could not be performed, the
areas were measured and evenly spaced measurements taken and marked at a
frequency of 1 measurement per square meter.
Unaffected and Non-Suspected Affected areas were not gridded. Each survey
point location was marked and mapped identifying the approximate survey location.
3.10 Quality Assurance and Quality Control
The GTRR project Quality Assurance Program was constructed to ensure that all
quality and regulatory requirements were satisfied. All activities affecting quality
were controlled by project procedures and the Project Quality Assurance Plan.
These procedures ensured that the appropriate equipment, environmental conditions, quality controls and prerequisites for any given activity were met. The
following Quality Control measures were implemented as an integral part of the
final release survey process.
REVISION 0
FINAL SURVEY REPORT
33
3.10.1 Selection of Personnel
Final Survey supervisory personnel were required to have extensive experience and familiarity with survey procedures and processes, including NUREG/CR-5849 and the Final Survey Plan. They were required to have prior experience with the radionuclide(s) of concern and a working knowledge of the instruments used to detect the radionuclides on site. The Survey Supervisor had to have a minimum of five years of experience in performing and supervising final release surveys where NUREG/CR-5849 guidelines were implemented.
The selection of supervisory personnel to direct the survey was based upon their experience and familiarity with the survey procedures and processes. Likewise, Health Physics Technicians who performed the surveys were selected based upon their qualifications and experience.
3.10.2 Written Procedures
All survey tasks which were essential to survey data quality were controlled by project procedures.
3.10.3 Instrumentation Selection, Calibration and Operation
Duratek selected instruments proven to reliably detect the radionuclides present at the GTRR. Laboratory counting instruments (i.e. Protean Alpha/Beta Counter, Beckman Liquid Scintillation Unit, and EG&G Ortec Gamma Spectroscopy System) were calibrated on-site using calibrated sources traceable to National Institute of Standards and Technology (NIST). All other instruments were calibrated off-site by Duratek or qualified vendors under approved procedures using calibration sources traceable to the National Institute of Standards and Technology (NIST). All instruments brought to the GTRR project site had current calibration certificates.
All detectors were subject to daily response checks when in use. Measurements were performed using approved written procedures for each instrument. Issue, control and accountability of all survey instrumentation were established by an instrumentation control procedure. Procedures for calibration, maintenance, accountability, operation and quality control of radiation detection instruments were written to implement the guidelines established in American National Standard Institute (ANSI) standard ANSI N323-1978 and ANSI N42.17A-1989.
REVISION 0
FINAL SURVEY REPORTGA TECH RESEARCH REACTOR
34
3.11 Documentation
Records of surveys were maintained in a separate survey package for each survey area in accordance with project procedures. The specific records that were compiled in a survey package were:
" Survey Package Worksheet giving the package identification, survey location information, historical information of area surveyed, general survey instructions and any specific survey instructions.
" Survey Comment Addendum provided for comments from the survey technician regarding any unusual situation that was encountered while surveying, as applicable.
"* The Survey Unit Diagram of the area that was surveyed, as available. Survey grids were represented on the drawing.
"* Printouts of laboratory analysis results.
"* Ludlum Model 2350 data files and Paradox® converted values for all radiation survey measurements.
Survey measurements were taken using the Ludlum Model 2350 Data Logger system. Upon completion of an individual survey unit or combination of units, the contents of the data logger's memory were downloaded to a Paradox® Database. The download process utilized a proprietary program developed by Ludlum Measurements, Inc., and revised by Duratek to fit specific survey needs.
A printed report, referred to as a Survey Report, was then generated for review. All raw data, converted data, and information by survey location code were presented in the report. This report was reviewed by the survey technician, survey supervisor and Certified Health Physicist for completeness, accuracy, any suspect entries and comparison to the site specific guideline values.
Any changes to the database tables such as detector efficiency, background, etc., that could affect survey results required the survey supervisor's approval. In addition, changes to data in the primary table required a written explanation on a change request attached to the survey report and maintained as a permanent record.
Data and document control included maintaining raw data files, translated data files (Paradox@ data files) and corrected data files showing documentation of all corrections. Paradox® program scripts and related data and information, including modifications, used for the development of the report were identified and controlled to ensure accurate identification. The databases were backed-up daily,
REVISION 0
FINAL SURVEY REPORTGA TECH RESEARCH REACTOR
35
and archived on a weekly basis. All survey records will be turned over to GA Tech with the issuance of this Final Survey Report.
3.12 Data Reduction and Statistical Evaluation
3.12.1 Data Analysis
Data collected during the Final Survey of the Georgia Tech Research Reactor was analyzed in accordance with the guidance contained in the Final Survey Plan. Survey data, for measurements of total beta activity, removable beta activity, removable H-3 activity, and exposure rate was grouped by survey unit or survey area as appropriate. Survey results were corrected as appropriate to account for background, including naturally occurring radioactive material present in building materials and as a result of instrument noise.
3.12.2 Background
In order to analyze the survey results associated with total beta activity measurements and exposure rate measurements, the analyses accounted for the naturally occurring radioactive background. For the analysis of the total beta activity measurement, this required a background study in an area representative of the areas surveyed during the final survey, using the same instrumentation and survey protocols that are used during the final survey. For exposure rate measurements, an alternative approach for defining background was required. This alternative approach is discussed in more detail in Section 3.12.6.
3.12.3 Measurements of Total Beta Activity
Measurement results for total beta activity from each survey unit, once corrected for background, were compared directly to the site specific guideline value for total beta activity. If any individual measurement result exceeded this value, then the measurement result was compared to the average and maximum criteria as defined in the footnotes to Table 3.1 as follows:
Individual measurement results less than 3 times the site specific guideline value for total beta activity were accepted provided that the affected area was limited to less than approximately 100 cm2.
NOTE: For the purpose of assessing the size of the contaminated area, an area of 126 cm2 corresponding to the size of the open window on the Ludlum Model 43-68 gas flow proportional detector was used.
REVISION 0
FINAL SURVEY REPORTGA TECH RESEARCH REACTOR
36
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
If any individual measurement result, in any square meter, was between 1
and 3 times the site specific guideline value for total beta activity the average beta activity in the square meter was evaluated. The average beta activity in the square meter, weighted by sizes of the areas of elevated activity, was accepted provided that the average was less than the site specific guideline value for total beta activity.
Once the individual measurements results for total beta activity from a
given survey unit were determined to meet the site specific guideline value
or the average and maximum criteria as defined in the footnotes to Table
3.1, the 95 percent confidence level of the mean for the survey unit was evaluated using the following equation:
Sx Ux X x+ t(o.a, df)
Where: Ux = 95 percent confidence level of the mean, dpm/100 cm
x = mean to-a, df) = 95 percent confidence level for n-I degrees of
freedom, unitless Sx = standard deviation n = number of individual measurement results used to
calculate the mean and the standard deviation
Values of Ux less than the site specific guideline value provide assurance, at the 95% confidence level, that the true mean for a given survey unit is
less than the site specific guideline value.
Measurement results of total beta activity are presented graphically by survey unit. Included with each graph are the following statistics: the
maximum result obtained in each survey unit, the mean result, the standard deviation in the results, the number of measurements in the
survey unit, and the 95 percent confidence level of the mean for the survey unit.
3.12.4 Measurements of Removable Alpha and Beta Activity
Measurement results for removable beta activity from each survey unit were compared directly with the site specific guideline value for removable beta activity.
REVISION 037
Measurement results of removable beta activity are presented graphically by survey unit. Included with each graph are the following statistics: the maximum result obtained in each survey unit, the mean result, the standard deviation in the results, the 95 percent confidence level of the mean for the survey unit and the number of measurements in the survey unit.
All measurement results for removable alpha activity were verified to be less than MDA. Therefore, no statistics were performed for removable alpha activity.
3.12.5 Measurements of Removable H-3 Activity
Measurement results for removable H-3 activity from each survey unit were compared directly to the radionuclide specific guideline value for removable H-3 discussed in Section 3.2.1 and provided in Table 3.1. Tritium was the predominate radionuclide in the assumed radionuclide mixes used to calculate the site specific guideline values. Thus, such a comparison aids in the validation of the derivation of the site specific guideline values.
Measurement results of removable H-3 activity are presented graphically by survey unit. Included with each graph are the following statistics: the maximum result obtained in each survey unit, the mean result, the standard deviation in the results, the 95 percent confidence level of the mean for the survey unit and the number of measurements in the survey unit.
3.12.6 Exposure Rate Measurements
The Final Survey Plan required that exposure rate measurements from each survey unit be compared to the background exposure rate established for that survey unit. Exposure rate measurement results that exceeded the established background by more than 5.0 uR/hr required investigation. While on the surface this sounded like a relatively straight forward requirement, the unique design of the Georgia Tech Reactor Building made it next to impossible to find a similar structure, not associated with the use of licensed radioactive material, for use in establishing background exposure rates. Exposure rates from naturally occurring sources in a relatively small area often vary by a factor of 2 or more due to geometry considerations and differences in materials of construction. Background exposure rate measurements collected in buildings on the Georgia Tech Campus, not associated with the use of licensed radioactive material, varied by a factor of 3.
REVISION 0
FINAL SURVEY REPORTGA TECH RESEARCH REACTOR
38
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
The difficulty in identifying suitable background exposure rates for evaluating the final survey data was not unexpected and was discussed briefly in Section 4.9.1 of the Final Survey Plan. Since a structure, not associated with the use of licensed radioactive materials, similar in
structure to the Reactor Building could not be identified for the purposes of establishing background exposure rates, an alternative means of estimating background exposure rates was proposed. The alternative means of estimating background exposure rates was discussed in detail with the Georgia Tech RSO and the Executive Engineer during a meeting on March 1, 2002.
The alternative approach, adopted for this Final Survey Report, for establishing background exposure rates for the various survey units within the Reactor Building stipulated that the background exposure rate would be estimated from the mean of all of the exposure rate measurements in a given survey unit once outliers were accounted for. However, prior to using the exposure rate from a given survey unit to estimate the background exposure rate, the survey unit must not exceed the Site Specific Guideline Values for both total (scans and direct measurements) and removable (smears) beta activity.
For a given survey unit the background exposure rate was established as follows:
"* Initially the mean exposure rate for the survey unit was established using all available exposure rate measurements.
"* The standard deviation of the exposure rates for the survey unit was established using all available exposure rate measurements.
"* Those exposure rates that exceeded the initial mean exposure rate by more that 2 standard deviations (outliers) were removed from the data set and the mean exposure rate re-established.
The re-established mean exposure rate (with potential outliers removed) was used as the best estimate of the background exposure rate for a given survey unit.
When using this alternative approach to establish background exposure rates, an alternative approach for identifying individual exposure rates that require investigation was also required. This latter alternative approach stated that individual exposure rates that exceeded the established background by more than 5 uR/hr and exceeded the initial mean exposure rate by more than 2 standard deviations require investigation. Individual exposure rates that do not exceed the mean by more than 2 standard deviations are used to estimate the mean and are considered representative of background.
REVISION 0
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
39
All exposure rate measurements collected as part of the final survey that exceeded the established background by more than a 5 uR/hr and exceeded the initial mean by more than 2 standard deviations were identified and investigated as part of the final survey.
Exposure rate measurement results are presented graphically by survey unit. Included with each graph are the following statistics: The maximum result obtained in each survey unit, the mean result, the standard deviation in the results, the mean plus 2 standard deviations, the 95 percent confidence level of the mean for the survey unit and the number of measurements in the survey unit. The background level, as calculated by the above alternate approach, is presented as the "Baseline" on the Exposure Rate graphs.
3.12.7 Samples of Open Land Areas of Reactor Yard
Based on the fact that the open land areas of the reactor yard were classified as unaffected, the sample results were compared to individual radionuclide guideline values shown in Table 3.3. No analysis results were found greater than 10% of the individual radionuclide specific concentration and none of the sum of fractions of the gamma emitting nuclides exceeded 25%, therefore, no additional sample analysis was required.
REVISION 0
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
40
4.0 SURVEY RESULTS
The final survey data was evaluated on a survey unit basis for each area and is presented
graphically in the following sections along with a brief description of the area which was
surveyed. The data is presented graphically for easy comparison to the release guideline
values/levels. Included with the figures are summary statistics including the number of
measurements, survey unit mean and maximum, standard deviation of the data
population, and the 95% confidence level of the mean. The MDA for each individual
measurement is also provided on the graphs as an MDA line.
The survey packages containing the survey data download files, smear analysis sheets,
sample analysis results and the survey package worksheets are provided in Attachment B.
The data presented in the following sections is a summary of the data provided in these
survey packages.
4.1 Background Results Summary
Ideally, background measurements are taken on materials from a similar building
that was constructed during the same time frame and known to be free of licensed
radioactive material. The Georgia Institute of Technology Facilities Building
located at 915 Atlantic Drive was used to estimate background for the purpose of evaluating direct beta activity measurements. Table 4.1 provides a summary of
the direct beta background study of concrete and asphalt.
Table 4.1 Direct Beta Background Study of
Concrete and Asphalt
REVISION 0
FINAL SURVEY REPORTGA TECH RESEARCH REACTOR
41
FINAL SURVEY REPORT
4.2 Package 1 - Helium and Lead Tank Cooling Water Lines
Classification: Suspect Affected
Survey Package 1 encompassed the reactor building ground floor helium and lead tank cooling water lines. These lines travel between the first floor and the basement inner wall of the reactor building. Figure 4-1A provides the locations of lines H-1 through H-22. Lines H-1 through H-14 were helium lines and lines H15 through H-22 were lead tank cooling water lines. Each pipe was originally swiped using a small cloth that was pulled through the entire length of pipe to verify that there was no loose activity present. There were decontamination activities performed on the inside of the piping. Decontamination consisted of using industrial strength drain cleaners. The final survey included 100 % beta scans on the inside of the piping, three direct beta measurement for each pipe, two smears for removable surface contamination (beta and alpha) for each pipe, and two smears on the inside of each pipe to assess H-3 contamination levels.
Survey Package 1 was divided into 22 survey units they are numbered HI through H22.
The final survey results for Survey Package 1 are summarized below and presented graphically in Figures 4-1 B, 4-1 C, and 4-1D.
Table 4.2 Survey Package 1
Final Survey Results Type of # of Meas. Mean Max Stand Dev 95 % CL of mean
Measurement dpm/100 cm2 dpm!100 cm 2 dpm/100 cm 2 dpm/100 cm2
Direct Beta 66 570 2036 469 683 *Removable Alpha 44 N/A N/A N/A N/A
Removable Beta 44 7 125 32 17 Removable H-3 44 140 417 68 163 * = All results < MDA ( Highest MDA 8.60 dpm/1OOCm 2)
As can be seen from the above table, none of the final survey results for Survey Package 1 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 1 demonstrate that the helium and lead tank cooling water lines meet the criteria for release for unrestricted use.
REVISION 0
GA TECH RESEARCH REACTOR
42
Figure 4-4A Package 1
Map
Georgia Tech Research Reactor Package 01 Helium & Lead Tank Cooling Water Lines
0 H #k- Denotes L7 number and approximate location of helium and lead tank cooling water lines.
REVISION 0
FINAL SURVEY REPORTGA TECH RESEARCH REACTOR
43
FINAIL SUJRVEY REPORTGA. 'ECH RESEARCH REACTOR
Figure 4-1B Package 1
Direct Beta Activity
Helium and Lead Tank Cooling Water Lines Direct Beta Activity7000
6000
5000
4000
3000
2000
1000
0
-1000H-1 H-2 H-3 H-4 H-5 H-6 H-7 H-8 H-9 H-1O H-i1 H-12 H-13 H-14 H-15 H-16 H-17 H-i8 H-19 H-20 H-21 H-22
Coolant Line Number
REVISION 0
MDA
0 0
$
z
(
44,
rECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-4C Package 1
Removable Beta Activity
Helium and Lead Tank Cooling 'Water Lines
600
500
400
300
200
100
0
-100
Removable Beta
MDA
H-1 H-2 H-3 H-4 H-5 H-6 H-7 H-8 H-9 H-10 H-11 H-12 H-13 H-14 H-15 H-16 H-17 H-18 H-19 H-20 H-21 H-22
Coolant Line Number
REVISION 0
0
0
I.
45
GA - tCf RESEARCH REACTOR
0 0-
/
F
Figure 4-1D Package 1
Removable H-3 Activity
Helium and Lead Tank Cooling Water Lines Removable H-3 Activity4700
4300
3900
3500
3100
2700
2300
1900
1500
1100
700
300
Measurements: 44 Mean: 140 dpm/100 din2 Maximum: 417 dpm/100 cra2 Std Deviation: 68 dpm/100 cm2 95% CL on Mean: 163 dpmn/100 cm2
S1iiiK - INi elm .Uiil-100 _ .. .. . . . . . . .. .. .. ... .. .
MDA
REVISION 0
H-1 11-2 11-3 H-4 H-5 H1-6 H-7 H-8 H-9 H-JO 11-11 H-12 H-13 11-14 H-15 11-16 H-17 H-18 H-19 H-20 11-21 H-22
Coolant Line Number
46
I-
4.3 Package 2 - Reactor Building 2nd Floor Below 2 Meters
Classification: Suspect Affected
Survey Package 2 encompassed the second floor of the reactor building. See Figure 4-2A for an overview. The second floor of the reactor building is composed of a small floor area that extends to the top of the reactor and a walkway that runs completely around the circumference of the reactor building. The floor area includes the reactor control room.
The need to perform decontamination activities on the second floor of the reactor building resulted in Survey Package 2 being classified as suspect affected for purposes of the final survey. Where practical, accessible surfaces were gridded. The final survey included 100 % beta scans, one direct beta measurement for each m2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each m2 of accessible surface area, one exposure rate measurement for each m2 of accessible floor area, and a number of smears to assess H-3 contamination levels.
Survey Package 2 was divided into the following survey units:
"• Walkway floor "* Outer Reactor Building wall (below 2 meters from the top of the walkway) "* ECCS tank platform "* Walkway Handrail "* Floor outside of the Control Room (CR) "* Floor inside Control Room "* Control Room wall 1 "* Control Room wall 2 "* Control Room wall 3 "* Control Room wall 4 "* Control Room electrical panel "* Ventilation Ducting
The final survey results for Survey Package 2 are summarized below and presented graphically in Figures 4-2B, 4-2C, 4-2D, and 4-2E.
REVISION 0
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
47
Table 4.3 Survey Package 2
Final Survey Results Type of # of Meas. Mean Max Stand Dev 95 % CL of mean
Measurement dpm/100 cm 2 dpM/100 cm 2 dpmlr100 cm2 dpml1 00 cm 2
Direct Beta 440 40 1396 234 62 *Removable Alpha 443 N/A N/A N/A N/A
Removable Beta 443 5 37 8 6 Exposure Rate 151 11.8 uR/hr 15.1 uR/hr 1.2 uR/hr 12 uR/hr
Removable H-3 31 191 839 137 247 * = All results < MDA (maximum MDA is 10 dpm/100cm2).
As can be seen from the above table, none of the final survey results for Survey Package 2 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 2 demonstrate that the second floor of the reactor building meets the criteria for release for unrestricted use.
REVISION 0
FINAL SURVEY REPORTGA TECH RESEARCH REACTOR
48
Figure 4-2A Package 2
Map
REACTOR BUILDING 2nd FLOOR BELOW 2 METERS
01 SO1-ECCs Tank Platform
N
REVISION 0
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
49
( FINAL SURVEY REPORTGA TECH RESEARCH REACTOR
Figure 4-2B Package 2
Direct Beta Activity
2nd Floor Below 2 Meters Direct Beta Activity
MDA
Surface
REVISION 0
7000
6000
5000
4000
3o00
2000
1000
0
0wm
$
z
0
-1000
50
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-2 C Package 2
Exposure Rate Measurements
'-4
0
20.0 19.0 18.0 17.0 16.0 15.0
14.0 13.0 12.0 11.0 10.0
9.0
8.0 7.0 6.0 5.0
4.0 3.0 2.0 1.0 0.0
2nd Floor Below 2 Meters Exposure Rate Measurements Measurements: 151 Mean: 11.8 pR/hr
Std Deviation: 1.2 p4R/hr
Baseline + 2 Std. Dev: 14.2 tR/hr Maximum: 15.1 tR/hr 95% CL on Mean: 12.0 IR/hr
- ------ J
Baseline
........
Surface
REVISION 0
. ... ... .. ....ll l l l
51
( Gt) LECH RESEARCH REACTOR K ( FINAL SURVEY REPORT
Figure 4-2D Package 2
Removable Beta Activity
2nd Floor Below 2 Meters Removable Beta Activity
MDA
Surface
REVISION 0
0
0•
$
600
500
Ann
300
200
100
0
-100
Measurements: 443 Mean: 5 dpm/100 cm2 Maximum: 37 dpm/100 c-m2 Std Deviation: 8 dpm/100 crn2 95% CL on Mean: 6 dpm/100 cm2
FINA SURVEY REPORT
1" .. m I- ,0 1 I- 1 41ImIA1t_. 1011,Nl " 111 SI il''l l''ll . . .. H// - " IMW IIII111,0 M M 0M"'"" HM• II..
52
GA fECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-2E Package 2
Removable H-3 Activity
2nd Floor Below 2 Meters Removable H-3 Activity
MDA
Surface
REVISION 0
4700
4300
0 0
$ 4b C.)
Q)
0
3900
3500
3100
2700
2300
1900
1500
1100
700
300
-100
FINAL SURVEY REPORTGA fECH RESEARCH REACTOR
% .1 %N %,ý %'ý 11 %N1 0
53
GA TECH RESEARCH REACTOR
4.4 Package 3 - Reactor Building 2nd Floor Above 2 Meters
Classification: Non-Suspect Affected
Survey Package 3 encompassed the second floor of the reactor building above 2 meters. See Figure 4-3A for an overview. The second floor of the reactor building consisted of the ceiling and wall areas 2 meters above the 2 'd floor. The wall proceeds vertically until reaching the crane rail. The roof then projects torispherically and peaks -15' above the crane rail.
There was no decontamination required in these areas. The final survey included 10 % biased beta scans, one direct beta measurement for each 20 m2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each 20 m2 of accessible surface area, and a number of smears to assess H-3 contamination levels. The biased locations were chosen by the technician performing the survey, and were based on the most probable areas for contamination.
Survey Package 3 was divided into the following survey units:
"* Walls from 2 meters to crane rail and top of the Control Room "* Overhead above crane rail "* Crane hoists "* Overhead inside of Control Room "* Reactor building intake vent "* Control Room intake
The final survey results for Survey Package 3 are summarized below and presented graphically in Figures 4-3B, 4-3C, and 4-3D
Table 4.4 Survey Package 3
Final Survey Results Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean
Measurement dpm/100 cm2 dpm/100 cm2 dpm/l00 cm2 dpm/100 cm 2
Direct Beta 85 120 517 243 172 *Removable Alpha 85 N/A N/A N/A N/A
Removable Beta 85 6 40 8 8 Removable H-3 35 223 752 178 291
* = All results < MDA (Highest MDA is 8.60 dpm/100cm2 )
REVISION 0
FINAL SURVEY REPORT
54
As can be seen from the above table, none of the final survey results for Survey Package 3 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was
exceeded, derivation of the SPGL based on the site radionuclide mix has been
validated. The final survey results for Survey Package 3 demonstrate that the
second floor of the reactor building above 2 meters meets the criteria for release for unrestricted use.
REVISION 0
FINAL SURVEY REPORT
55
GA TECH RESEARCH REACTOR
Figure 4-3A Package 3
Map
REACTOR BUILDING 2nd FLOOR ABOVE 2 METERS
ýýT' 01V01-Reactor Building Intake Vent 020H1-Inside Overhead of Control Room
./ 01OH1-Walls from 2 meters to crane rail 010H2-Overhead above Crane Rail
REVISION 0
FINAL SURVEY REPORT
56
GA.t'ECH RESEARCH REACTORFINAL SURVEY REPORT
Figure 4-3B Package 3
Direct Beta Activity
2nd Floor Above 2 Meters Direct Beta Activity7000
6000
5000
4000
3000
2000
1000
0
-1000
Surface
REVISION 0
Measurements: 85 Mean: 120 dpm/100 cm2 Maximum: 517 dpm/100 cm2
Std Deviation: 243 dpm/100 cm2 95% CL on Mean: 172 dpm/100 cm2
-- - - - - - - - ----- - -- -----
0
z- MDA
57
GA IECH RESEARCH REACTOR( (
FINAL SURVEY REPORT
Figure 4-3C Package 3
Removable Beta Activity
2nd Floor Above 2 Meters Removable Beta Activity
Measurements: 85 Mean: 6 dpm/100 cm2 Maximum: 40 dpmrl00 cm2
Std Deviation: 8 dpm/100 cm2 95% CL on Mean: 8 dpm/100 c=2
600
500
400
300
200
100
0
-100
Surface
REVISION 0
0<
MDA
58
TECH RESEARCH REACTOR
FINAL SURVEY REPORT
Figure 4-3D Package 3
Removable H-3 Activity
2nd Floor Above 2 Meters Removable H-3 Activity4700
4300
3900
3500
3100
2700
2300
1900
1500
1100
700
300MDA
-100
Grid Row
REVISION 0
0<
0D
FINAL SURVEY REPORT(
59
4.5 Package 4 - Reactor Building 1st Floor Below 2 Meters
Classification: Suspect Affected
Survey Package 4 consisted of the entire 1 st floor and all wall surfaces below 2 meters of the reactor building. See Figure 4-4A for an overview. This includes the main floor, biomedical room and the plug storage vault.
For the purpose of the Final survey, Survey Package 4 was classified as suspect affected. Decontamination was required on - 40% of the main floor. The walls of the I" floor and the plug storage vault did not require any decontamination. All accessible surfaces were gridded.
The final survey included 100 % beta scans, one direct beta measurement for each m2 of accessible surface area, one smear for removable surface contamination (beta and alpha) for each m2 of accessible surface area, one exposure rate measurement for each m2 of accessible floor area, and a number of smears to assess H-3 contamination levels.
Survey Package 4 was divided into the following survey units:
"* Floor "* Wall 1 (grids 48-50 do not exist) "* Walls 2,4,5 "* Wall 3 (grid A-3 does not exist) "* Stairwell from 2 nd floor to basement "* Heaters 1-4 "* Trenches 1-8 "* Fuel storage pit "* Pressure relief valves "* Vent duct "* Inside elevator "* Secondary personnel hatch "* Airlock to lab building "* Biomedical room
"* Floor "* Walls 1-4 (grid A2 does not exist) "* Overhead (above 2 meters) "* Floor drain
"* Plug storage vault "* Floor "* Wall 1 (gridded as continuous wall) "* Ceiling (not above 2 meters)
REVISION 060
FINAL SURVEY REPORT
The final survey results for Survey Package 4 are summarized below and presented graphically in Figures 4-4B, 4-4C, 4-4D, and 4-4E.
Table 4.5 Survey Package 4
Final Survey Results
Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean Measurement dpm/100 cm 2 dpm/100 cm2 dpm/100 cm2 dpm/100 cm2
Direct Beta 1027 209 2457 394 233 *Removable Alpha 1022 N/A N/A N/A N/A
Removable Beta 1022 6 170 12 6 Exposure Rate 520 13.1 uRihr 21.4 uRihr 2.4 uRihr 13.5 uR/hr
Removable H-3 75 324 4243 524 461
* = All results < MDA (Highest MIDA is 13.68 dpm/100cm 2 )
During the initial Final Survey of Trench 6, one direct beta measurement exceeded the Site Specific Guideline Value, SPGL. A follow-up investigation (see Attachment B, package 4, file 213) did not result in any additional direct beta measurement in excess of the SPGL. For the grid in question, the average contamination level, including the one measurement result that exceeded the SPGL, did not exceed the SPGL.
One exposure rate measurement exceeded the SPGL. This measurement result can be attributed to the proximity to the Neely Building Hot Cell and source storage vault.
As can be seen from the above table, none of the Final Survey results with the exception of the one direct beta measurement and the one exposure rate measurement exceeded the SPGL's. In addition, based on the result of the H-3 measurements, there is no reason to question the derivation of the SPGL's. The Final Survey results for Survey Package 4 demonstrate that the 1 st floor of the reactor building below 2 meters meets the criteria for release for unrestricted use.
REVISION 061
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-4A Package 4
Map
REACTOR BUILDING 1 ST FLOOR BELOW 2 METERS
Vent 1 (01VO1) no longer connected.
REVISION 0
GA TECH RESEARCH REACTOR FI:NAL SURVEY REPORT
62
( G• 1'ECH RESEARCH REACTOR(
FINAL SURVEY REPORT
Figure 4-4B Package 4
Direct Beta Activity I
1 st Floor Below 2 Meters Direct Beta Activity
Measurements: 1027 Mean: 209 dpm/100 cm2 Maximum: 2457 dpm/100 cm2 Std Deviation: 394 dpm/100 cm2 95% CL on Mean: 233 dpm/100 cm2
Surface.
REVISION 0
7000
6000
5000
4000
21iN1IJYVuV -
Pz 2000
1000
0
-1000
- MDAit it III
ju 1
11 --- --------- "T F
63
C)
4.1
Cf)
(-i ý4 Cý Cý 016 t-: wi 4 Iýi ýli 14 C; Cý 06 t-: wi 4 rý (Ii 14 6 eq r4 N
aliell ainsodxa
m
cod
(•. TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-4D Package 4
Removable Beta Activity
1st Floor Below 2 Meters Removable Beta Activity
.... ... ... . A. . , [ MDA
0
-100
Surface
REVISION 0
600
500
4
0p
Measurements: 1022 Mean: 6 dpmrl00 cm2 Maximum: 170 dpmlO00 cm2 Std Deviation: 12 dpm/100 cm2 95% CL on Mean: 6 dpm/100 cm2
400
300
200
100
65
( GA fECH RESEARCH REACTOR
( FINAL SURVEY REPORT
Figure 4-4E Package 4
Removable H-3 Activity
1st Floor Below 2 Meters Removable H-3 Activity4700
Measurements: 75
4300 Mean: 324 dpm/100 dn2 Maximum: 4243 dpm/100 cm2 Std Deviation: 524 dpm/100 cmI2
3900 95 % CL on Mean: 461 dpm/100 cm2
3500
3100
2700
2300
1900
1500
1100
700
300MDA
-100 .............
Surface
REVISION 0
0
0<
41 ip V"o-Ok", ", ̀ 5 "1 %, %N %N, %4P %-ý %040,
66
4.6 Package 5 - Reactor Building 1 st Floor Above 2 Meters
Classification: Non-Suspect Affected
Survey Package 5 encompassed the first floor of the reactor building above 2 meters. See Figure 4-5A for an overview. The first floor of the reactor building consisted of the outer wall areas from 2 meters vertically - 12' to the bottom of the 2 nd floor catwalk, (includes bottom of the catwalk) and the outside of the biomedical room above 2 meters to the bottom of the 2 nd floor.
There was no decontamination required in these areas. The final survey included 10 % biased beta scans, one direct beta measurement for each 20 m2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each 20 m2 of accessible surface area, and a number of smears to assess H-3 contamination levels. The biased locations were chosen by the technician performing the survey, and were based on the most probable areas for contamination.
Survey Package 5 was divided into the following survey units:
"* Outer wall from 2 meters to the bottom of the 2 nd floor walkway "* Outside of biomedical room from 2 meters to the bottom of the 2nd floor
The final survey results for Survey Package 5 are summarized below and presented graphically in Figures 4-5B, 4-5C, and 4-5D.
Table 4.6 Survey Package 5
Final Survey Results Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean
Measurement dpm/100 cm2 dpm/100 cm 2 dpm/100 cm2 dpm/100 cm2
Direct Beta 50 63 830 257 139 *Removable Alpha 50 N/A N/A N/A N/A
Removable Beta 50 2 49 9 4 Removable H-3 30 182 1889 318 313 • = All results < MDA (Highest MDA is 5.17 dpm/100cm2 )
During the final survey of the outer wall overhead, one direct beta measurement (830 dpm/100cm 2) exceeded the non-suspect affected action level of 600 dpm/100 cm2 . A follow-up investigation (see Attachment B, package 5, file 163) did not result in any activity in excess of 600 dpm/1 00 cm 2, therefore, no further action was required.
As can be seen from the above table, none of the final survey results for Survey Package 5 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 5 demonstrate that the first floor of the reactor building above 2 meters meets the criteria for release for unrestricted use.
REVISION 0
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
67
Figure 4-5A Package 5
Map
Reactor Building 1 st Floor Areas Above 2 Meters
01 OH1 - Outer Wall from 2 meters to bottom of 2nd floor walkway.
01OH2 - Outside of biomedical room from 2 meters to bottom of 2nd floor walkway.
REVISION 0
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
68
, L.. TECH RESEARCH REACTOR.(
FINAL SIIUVr�V 1�EPO1�T
Figure 4-5B Package 5
Direct Beta Activity
1st floor Above 2 Meters Direct Beta Activity
MDA
'0
Surface
REVISION 0
7000
6000
5000
4000
3000
2000
1000z
0
-1000
FINAL SURV E, Y -P UPOR T
69
( GA t'ECH RESEARCH REACTOR\'
FINAL SURVEY REPORT
Figure 4-5C Package 5
Removable Beta Activity
1st floor Above 2 Meters Removable Beta Activity
Measurements: 50 Mean: 2 dpm/100 cnm2
Maximum: 49 dpm/100 crn2 Std Deviation: 9 dpm/100 cm2
95% CL on Mean: 4 dpm/100 cm2
+±++r-.i--i~n+..±-++ +u ni -.+MDA
Surface
REVISION 0
, 600
500
0•
0
400
300
200
.100
0
-100
70
""L [ECH RESEARCH REACTOR
0
(FINAL SURVEY REPORT
Figure 4-5D Package 5
Removable H-3 Activity
1st Floor Above 2 Meters Removable H-3 Activity4700
4300
3900
3500
3100
2700
2300
1900
1500
1100
700
300
-100
-1I
Location 20
in' ,,,,snm n~~~ml m .1n0~m| 11,m5 5. 1 1LI 1
01OH1
MDA
01OH2
Surface
REVISION 0
Measurements: 30 Mean: 182 dpm/100 dm2 Maximum: 1889 dpmlO00 cm2 Std Deviation:318 dpm/100 cm2 95% CL on Mean: 313 dpm/100 cm2
71
4.7 Package 6 - Reactor Building Ventilation Hold-Up Duct
Classification: Suspect Affected
Survey Package 6 consisted of the hold-up duct that is located directly below the floor in the basement of the reactor building. The hold-up duct is part of the reactor building ventilation system on the intake side of the HEPA filters. See Figure 4-6A for an overview of this area.
There was a small amount of decontamination activities in the hold-up duct. The damper louvers were removed and disposed of as radioactive waste. A small amount of aggressive decon was required on the floor. The surfaces were gridded into 1 m2 grids. The final survey included 100 % beta scans, one direct beta measurement for each m2 of accessible surface area, one smear for removable surface contamination (beta and alpha) for each m2 of accessible surface area, and a number of smears to assess H-3 contamination levels. Exposure rate readings were not required in the hold-up duct due to its unique geometry. The ducts geometry is such that any reading one meter above the floor surface is within one foot from the ceiling and approximately one foot from at least two walls.
Survey Package 6 was divided into the following survey units:
"* Floor inside hold-up duct "* Hold-up duct wall 1 through 4 "* Hold-up duct ceiling
The final survey results for Survey Package 6 are summarized below and presented graphically in Figures 4-6B, 4-6C, and 4-6D.
Table 4.7 Survey Package 6
Final Survey Results Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean
Measurement dpm/100 cm2 dpm/100 cm2 dpmi/100 cm 2 dpm/100 cm2
Direct Beta 130 436 1396 308 489 * Removable Alpha 130 N/A N/A N/A N/A
Removable Beta 130 0 21 5 1 Removable H-3 30 184 529 102 226 • - All results < MDA (Highest MDA is 7.63 dpm/l 00Cm 2).
As can be seen from the above table, none of the final survey results for Survey Package 6 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 6 demonstrate that the hold-up duct of the reactor building meets the criteria for release for unrestricted use.
REVISION 0
FINAL SURVEY REPORT
72
Figure 4-6A Package 6
Map
Reactor Building Ventillation Hold-Up Duct
N-->Wall 2 (01W02)
REVISION 0
GA TECH RESEARCH REACTOR
73
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-6B Package 6
Direct Beta Activity
Hold-up Duct Direct Beta Activity7000
6000
5000
4000
3000
2000
1000- MDA
000
-1000-
Surface
REVISION 0
zP
1ý %
74
T ( • TECH RESEARCH REACTOR(
FINAI, •qTIRVE.V RE.PORT
Figure 4-6C Package 6
Removable Beta Activity
Hold-up Duct Removable Beta Activity
Surface
REVISION 0
600
500
0
400
300
200
100
0
-100
MDA
FlNAY,.virj-Pvr,.y -ur,.PnuT
75
Gr. ECH RESEARCH REACTOR
Figure 4-6D Package 6
Removable H-3 Activity
FINAL SURVEY REPORT
Hold-Up Duct Removable H-3 Activity4700
4300
3900
3500
3100
2700
2300
1900
1500
1100
700
300
-100
s�xSurface
REVISION 0
MDA
0 0
�0
0
76
FINAL SURVEY REPORT
4.8 Package 7 - Reactor Building Ventilation
Classification: Suspect Affected
Survey Package 7 encompassed the reactor ventilation unit (located in the basement of the reactor building), reactor building stack main vent room, stack kanne chamber room, and the reactor building stack. See Figure 4-7a.
Decontamination was required on the floor of the HEPA ventilation unit and the floor of the stack. Where practical, accessible surfaces were gridded. The final survey included 100 % beta scans, one direct beta measurement for each m2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each m2 of accessible surface area, one exposure rate measurement for each mn2 of accessible floor area, and a number of smears to assess H-3 contamination levels.
Survey Package 7 was divided into the following survey units:
"* Inside of the reactor ventilation unit "* Floor of stack main vent room "* Walls 1 through 8 of the stack main vent room "* Floor of the instrument room "* Vent pipe chamber room "* Stack fan "* Instrumentation "* Stack floor "* Stack wall
The final survey results for Survey Package 7 are summarized below and presented graphically in Figures 4-7B, 4-7C, 4-7D, and 4-7E.
Table 4.8 Survey Package 7
Final Survey ResultsType of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean
Measurement dpm/100 cm2 dpm/100 cm2 dpm/100 cm 2 dpm/100 cm2
Direct Beta 131 136 1584 379 201
*Removable Alpha 131 N/A N/A N/A N/A
Removable Beta 131 5 122 17 7
Exposure Rate 14 15.6 uR/hr 17.5 uR/hr 1.0 uR/hr 16.2 uR/hr Removable H-3 35 371 2068 424 534
* = All results < MDA (Highest MDA is 8.60 dprr1 00cm 2 )
As can be seen from the above table, none of the final survey results for Survey Package 7 exceeded the Site Specific Guideline Values (SPGLs). Since neither
REVISION 0
GA TECH RESEARCH REACTOR
77
the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 7 demonstrate that the reactor building ventilation meets the criteria for release for unrestricted use.
REVISION 0
FINAL SURVEY REPORT
78
GA TECH RESEARCH REACTOR
Figure 4-7A Package 7
Map
REACTOR BUILDING VENTILATION ROOM AND STACK Package 07 (A0207)
Roughing Filter Bank HEPA Filter Bank
Approximately 15' of pipe not shown
N VWall 9 (O1WO9) IN
REVISION 0
FINAL SURVEY REPORT
79
, TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-7B Package 7
Direct Beta Activity
-1000 1
Surface
40 44% 4p p ý
REVISION 0
Pi
7000
6000
5000
4000
3000
2000
1000
0
- MDA
80
Gz-. tECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-7C Package 7
Exposure Rate Measurements
C
Reactor Building Ventilation Below 2 Meters Exposure Rate Measurements 23.0 22.0 - Measurements: 14
21.0 Mean: 15.6 pR/hr Std Deviation: 1.0 pR/hr
20.0 Baseline + 2 Std. Dev: 17.6 IR/hr
19.0 - Maximum: 17.5 pR/hr
180 95% CL on Mean: 16.2 pR/hr
17.0 16.0 A
15.014.013.0o 12.0-11.0 10.0
9.0 t ot 8.0
.7.0 6.0 5.04.03.02.0 1.0 0.0 4 - - II T
01FOl 01F02
Surface
Baseline
REVISION 081
( GA TECH RESEARCH REACTOR( F
FINAL SURVEY REPORT
Figure 4-7D Package 7
Removable Beta Activity
Reactor Building Ventilation Below 2 Meters Removable Beta Activity
4 4? 4? 4? 4? 4? 4 x�x�x
Surface
REVISION 0
600
500
400
300
200
100
09
0
Measurements: 131 Mean: 5 dpm/100 cm2 Maximum: 122 dpm/100 cm2 Std Deviation: 17 dpm/100 cm2 95% CL on Mean: 7 dpm/100 cm2
.49I Ii I4 Iww pI0
_1 fin
MDA
I"InnU
82
Gý, TECH RESEARCH REACTOR
4700
4300
3900
3500
3100
2700
2300
1900
1500
1100
700
300
-100
REVISION 0
(
0•
0•
'U
Figure 4-7E Package 7
Removable H-3 Activity Reactor Building Ventilation Below 2 Meters
Removable H-3 Activity
Measurements: 35 Mean: 371 dpm/100 din2 Maximum: 2068 dpm/100 cm2 Std Deviation: 424 dpm/100 crn2 95 % CL on Mean: 534 dpm/100 cm2
Surface
MDA
(
83
4.9 Package 8 - Suspect Affected Yard Areas
Classification: Suspect Affected
Survey Package 8 encompassed the reactor facility yard. The suspect affected yard areas included an asphalt paved area, and a concrete walk way that runs approximately 2700 around the reactor building. These areas were included in this package due to egress from the reactor building during normal operations and decommissioning activities. Both areas were used for storage of radioactive material in accordance with approved procedures. See Figure 4-8A for an overview of these areas. Decontamination was limited to two small (<100 cm2 each) areas located on the concrete walkway immediately outside the Neely Research Center high bay doors.
Where practical, accessible surfaces were gridded into lm2 grids. The final survey included 100 % beta scans, one direct beta measurement for each m2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each m 2 of accessible surface area, one exposure rate measurement for each m2 of accessible area, and a number of smears to assess H-3 contamination levels.
Survey Package 8 was divided into the following survey units:
* Concrete walkway * Paved radioactive material storage area 1 0 Paved radioactive material storage area 2
The final survey results for Survey Package 8 are summarized below and presented graphically in Figures 4-8B, 4-8C, 4-8D, and 4-8E.
Table 4.9 Survey Package 8
Final Survey Results Type of # of Meas. Mean Max Stand Dev 95 % CL of mean
Measurement dpm/100 cm2 dpm/100 cm' dpm/100 cm2 dpm/100 cm2
Direct Beta 643 283 1998 410 315 *Removable Alpha 643 N/A N/A N/A N/A
Removable Beta 643 0 37 4 0 Exposure Rate 643 11.7 uR/hr 17.4 uR/hr 1.2 uR/hr 11.8 uR/hr
Removable H-3 32 161 424 66 188 *- All results < MDA (Highest MDA is 3.53 dpm/lO00cm 2).
REVISION 0
GA TECH RESEARCH REACTOR
84
FINAL SURVEY REPORT
As can be seen from the above table, with the exception of the exposure rate measurements, none of the final survey results for Survey Package 8 exceeded the
Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation
of the SPGL based on the site radionuclide mix has been validated. Upon frrther
investigation it was determined that the elevated exposure rate measurement results were due to the location of radioactive materials within the Neely Building immediately east of these data locations.
The final survey results for Survey Package 8 demonstrates that the reactor facility yard concrete walkway and asphalt paved areas meet the criteria for
release for unrestricted use.
REVISION 0
FINAL SURVEY REPORTGA TECH RESEARCH REACTOR
85
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-8A Package 8
Map
Yard Suspect Afffected Areas
.ETADNETG FENCE LINE
North >S_ = Suspect Afffected Areas
REVISION 0
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
86
GA TECH RESEARCH REACTOR FINAL �TIRVEV RE�1IT
Figure 4-8B Package 8
Direct Beta Activity
7000
6000
I *
4.)
5000
4000
3000.
2000
1000
0
-1000
Affected Areas Direct Beta
MDA
Surface
REVISION 0
FINAL SURVEY REPORT
(
87
C (GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-8C Package 8,
Exposure Rate Measurements
Yard Suspect Affected Areas Exposure Rate Measurements 23.0 22.0 - Measurements: 643
21.0 Mean: 11.7 /R/hr Std Dev: 1.2 uR/hr
20.0 - Baseline + 2 Std. Dev: 14.2ttR/hr
19.0 Maximum: 17.4 gR/hr
18.0 95% CL on Mean:, 11.8 /zR/lr
170 "Z 16.0
15.0
S14.0S 13.0 -'
"120 - Baseline
S10.0.
9.0 S8.01 0 7.0
6.05.0 4.0
3.02.0
1.0 0.0
Surface
REVISION 0
(
88
k,ý TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-8D Package 8
Removable Beta Activity
Yard Suspect Affected Areas Removable Beta Activity600
500
400
300
200
100
0
MDA
Surface
REVISION 0
0
.0
"0
89
( (1 TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-8E Package 8
Removable H-3 Activity
Yard Suspect Affected Areas Removable H-3 Activity 4700 4700 ~ ~Measurements: 3218 cm
4300 Mean: 161 dpm/100 di2 Maximum: 424 dpm/100 cm2
3900- Std Deviation: 66 dpm/100 cm2 95% CL on Mean: 18dpm/lO0 m
3500
3100
", 2700
- 2300
S1900
" 1500
a 1100
S70 0
300 MDA
-100
Surface
REVISION 090
GA TECH RESEARCH REACTOR
4.10 Package 9 - Unaffected Asphalt and Concrete Yard Areas
Classification: Unaffected
Survey Package 9 encompassed the outside yard areas of the reactor facility. See Figure 4-9A for an overview. The unaffected asphalt paved areas and concrete walkways occupy approximately 605 square meters. This area was not used for storage of radioactive material.
There was no decontamination required in this area. The final survey included 10 % beta scans, one direct beta measurement for each m2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each m2
of accessible surface area, one exposure rate measurement for each m2 of accessible surface area, and a number of smears to assess H-3 contamination levels.
Survey Package 9 was divided into the following survey unit:
* Asphalt or concrete paved areas.
The final survey results for Survey Package 9 are summarized below and presented graphically in Figures 4-9B, 4-9C, 4-93D, and 4-9E.
Table 4.10 Survey Package 9
Final Survey Results Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean
Measurement dpm/100 cm2 dpm/100 cm2 dpm/100 cm2 dpm/100 cm2
Direct Beta 34 4 595 357 124 *Removable Alpha 34 N/A N/A N/A N/A
Removable Beta 34 0 10 3 1 Exposure Rate 34 12 uR/hr 16.2 uR/hr 1.4 uR/hr 12.4 uR/hr
Removable H-3 34 145 441 84 178 * = All results <MDA (Highest MDA is 5.17 dpm/100cm2).
As can be seen from the above table, none of the final survey results for Survey Package 9 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 9 demonstrate that the unaffected yard areas of the reactor facility meet the criteria for release for unrestricted use.
REVISION 0
FINAL SURVEY REPORT
91
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-9A Package 9
Map
Yard Unafffected Areas
ACCESS GATE
S_ = Unafffected Areas North >
REVISION 092
ITECH RESEARCH REACTOR
FINAL SURVEY REPORT
Figure 4-9B Package 9
Direct Beta Activity
Yard Unaffected Areas Direct Beta Activity7000
6000
5000
4000
3000
2000
1000
0
-1000
Surface
REVISION 0
V
.4
z
MDA
FINAL SURVEY REPORT
93
L LECH RESEARCH REACTOR( (
FINAL SURVEY REPORT
Figure 4-9C Package,9
Exposure Rate Measurements
Yard Unaffected Areas Exposure Rate Measurements Measurements: 34 Mean: 12.0 IAR/hr Std Deviation: 1.4 AR/hr Baseline + 2 Std. Dev: 14.7 IR/hr Maximum: 16.2 AR/hr 95% CL on Mean: 12.4 ttR/hr
:I' _-ý ,
Baseline
Surface
REVISION 0
23.0 22.0 21.0 20.0 19.0 18.0 17.0 16.0 15.0 14.0 13.0 12.0 11.0 10.0
9.0 8.0 7.0 6.0 5.0 4.0 3.0 2.0 1.0 0.0
C
94
\ TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-9D Package 9
Removable Beta Activity
Yard Unaffected Areas Removable Beta Activity
0 0
"0
c*J
600
500
400
300
200
100
0
-100
Measurements: 34 Mean: 0 dpm/100 cm2 Maximum: 10 dpm/100 cm2 Std Deviation: 3 dpm/100 cm2 95% CL on Mean: 1 dpm/100 cm2
Surface
REVISION 0
MDA
FINAL SURVEY REPORT
95
_ TECH RESEARCH REACTOR
0
C0
FINAL. �TTRVEV REPORT
Figure 4-9E Package 9
Removable H-3 Activity
Yard Unaffected Areas Removable H-3 Activity4700
4300
3900
3500
3100
2700
2300
1900
1500
1100
700
300
-100MDA
Surface
REVISION 0
Measurements: 34
Mean: 145 dpm/100 dmi2 Maximum: 441 dpm/100 cm2 _
Std Deviation: 84 dpm/100 cm2 95 % CL on Mean: 178 dpm/100 cm2
FINAL SURVEY R1wpn12T
96
FINAL SURVEY REPORT
4.11 Package 10 - Reactor Building and Stack
Classification: Non-Suspect Affected
Survey Package 10 encompassed the reactor building exterior walls, dome surfaces, and the stack. See Figure 4-1 GA for an overview of this area. There were no decontamination activities on the building exterior.
The final survey included a minimum of 10 % beta scans, one direct beta measurement for each 50 m2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each 50 m2 of accessible surface area, and a number of smears to assess H-3 contamination levels.
Survey Package 10 has only one survey unit that includes both the stack and reactor building exterior.
The final survey results for Survey Package 10 are summarized below and presented graphically in Figures 4-1OB, 4-1OC, and 4-1OD.
Table 4.11 Survey Package 10
Final Survey Results Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean
Measurement dpm/IOO cm dpm/100 cm2 dpm/I00 cm dpm/100 cm2
Direct Beta 30 20 483 212 95 * Removable Alpha 30 N/A N/A N/A N/A
Removable Beta 30 5 45 9 8 Removable H-3 30 142 260 51 163 * = All results < MDA (Highest MDA 5.17 dpm/100cm2).
As can be seen from the above table, none of the final survey results for Survey Package 10 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 10 demonstrates that the reactor building and stack exteriors meet the criteria for release for unrestricted use.
REVISION 0
GA TECH RESEARCH REACTOR
97
FINAL SURVEY REPORT
Figure 4-10A Package 10
Map
Reactor Building Exterior
North
REVISION 0
GA TECH RESEARCH REACTOR
98
( ( ( C. TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-10B Package 10
Direct Beta Activity
Reactor Building and Stack Exterior Direct Beta Activity
7000
Measurements: 30
Mean: 20 dpm/100 cm2 6000 Maximum: 483 dpm/100 cm2
Std Deviation: 212 dpm/100 cm2
95% CL on Mean: 95 dpm/100 cm2
S5000
S4000
3000
S2000
1000 -D SMDA
-1000
Surface
REVISION 0
/
99
L•. rECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-10C Package 10
Removable Beta Activity
Reactor Building & Stack Exterior Removable Beta Activity600
500
0 0
"0
$
400
300
200
100
0
-100
MDA
N
Surface
REVISION 0
i' t\
.100
L. TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-10D Package 10
Removable H-3 Activity
Reactor Building & Stack Exterior Removable H-3 Activity 4700
Smeasurements: 30
4300 mean: 142 dpm/100 dn2 Maximum: 260 dpm/100 cm2
0Std Deviation: 51 dpm/100 c392 3900 95 % CL on Mean: 163 dpm/100 -ra2
S3500
S3100
S2700
, 2300
1900 W ,•1500
S1100
S700
300 300 -M D A
-100
Surface
REVISION 0101
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
4.12 Package 11 - Reactor Building Basement Drain Lines
Classification: Suspect Affected
Survey Package 11 encompassed the reactor building basement drain lines. Drain
lines DOI through D09 traveled to the basement floor sump. Drain line D10 traveled between the heavy water storage tank pit and the reactor vessel tunnel
shaft. See Figure 4-1 1A for a map showing the drain line layout.
Portions of the drain lines up to 20 feet upstream of the sump were contaminated
and required decontamination. Decontamination was accomplished using
industrial strength drain cleaning solutions and high pressure water spray systems.
After decontamination, the drain lines were flushed twice to ensure an absolute
minimum amount of loose debris remained for final surveys.
The Final Survey for Drain Lines DOI-D10 included:
* A 100 % beta scan of all accessible surfaces
* A minimum of three (3) direct beta measurements on each pipe
* A minimum of two (2) smears on the inside of each pipe for removable surface contamination (gross beta and gross alpha)
* A minimum of two (2) smears on the inside of each pipe to assess H-3 contamination levels (liquid scintillation analysis)
In addition, Drain Lines D03, D04 and D1O were surveyed every foot. These lines
were easily accessible and known to be contaminated prior to decontamination.
Drains DO, D02 and D05 through D09 were surveyed every foot until passing the first elbow.
The final survey results for Survey Package 11 are summarized below and presented graphically in Figures 4-1 lB, 4-11 C, and 4-1 1D.
Table 4.12 Survey Package 11
Final Survey Results
Type of # of Meas. Mean Max. Stand. Dev. 95 % CL ot mean Measurement dpm/100 cm 2 dpm/100 cm 2 dpm/100 cm2 dpm/1OO cm 2
Direct Beta 118 264 1736 505 355
*Removable Alpha 20 A N/A N/A N/A
Removable Beta 20 3 1 5 5
Removable H-3 420 773 159 501
-= l results < MA 1( Highest MDA is 5.7 I pm/1OOcm 2)
REVISION 0102
FINAL SURVEY REPORTGA TECH RESEARCH REACTOR
FINAL SURVEY REPORT
As can be seen from the above table, none of the final survey results for Survey Package 11 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 11 demonstrate that the Reactor Building Basement Drain Lines meet the criteria for release for unrestricted use.
REVISION 0
GA TECH RESEARCH REACTOR
103
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-11A Package 11
Map
Basement Drain Lines
Sump
REVISION 0
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
104
( (,. TECH RESEARCH REACTORFINAL SURVEY REPORT
Figure 4-11B Package 11
Direct Beta Activity
7000
6000
09
z9
Basement Drain Lines Direct Beta Activity
5000
4000
3000
2000
1000
0
-1000
I- MDA
Surface
REVISION 0
(
,%S 0. %ý 0 %S llý
105
L rECH RESEARCH REACTOR( (
FINAl, STIRVF VY REPORT
Figure 4-11C Package 11
Removable Beta Activity
Basement Drain Lines Removable Beta Activity
MDA
N
Surface
REVISION 0
600
500
400
300
200
100
0
0
�;I.
0
-100
FINA SURVEY REPORT
106
GA fECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-111D Package 11
Removable H-3 Activity
Basement Drain Lines Removable H-3 Activity
300
-100
i V,$ ýp z, Z4 zo Z, 00 00 ZA ZA ý, Z% Zo
Surface
REVISION 0
I MDA
4700
4300
S3900
3500
"3100
"• 2700
S23 0'0
S1900
1500
o1100
S700
107
4.13 Package 12 - Process Equipment Room Below 2 Meters
Classification: Suspect Affected
Survey Package 12 encompassed the reactor building process equipment room located in the basement. The floor of this room is approximately 160 m2. See Figure 4-12A for an overview. This area contained several pieces of contaminated equipment (e.g. primary coolant filtration system, two large heat exchangers, misc. coolant lines and the D20 tank). It also contained the heavy water storage tank pit.
Approximately 60% of the floor area required decontamination. The walls required only minor decontamination. The floor surface of the heavy water storage tank pit required 100% decontamination. Approximately 40% of the wall surfaces of the pit required decontamination. Where practical, accessible surfaces were gridded.
The final survey included 100 % beta scans, one direct beta measurement for each m2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each m 2 of accessible surface area, one exposure rate measurement for each m2 of accessible floor area, and a number of smears to assess H-3 contamination levels.
Survey Package 12 was divided into the following survey units:
"* Process equipment room floor "* Process equipment room walls 1-3 "* Structures 1-6 "* Trench to bottom of spent fuel storage pit "* Trench at doorway "* Penetrations 1-4 "* D20 pit floor "* D20 pit walls 1-4
The final survey results for Survey Package 12 are summarized below and presented graphically in Figures 4-12B, 4-12C, 4-12D, and 4-12E.
REVISION 0
GA TECH RESEARCH REACTOR FIN-AL SURVEY REPORT
108
GA TECH RESEARCH REACTOR
Table 4.13 Survey Package 12
Final Survey Results Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean
Measurement dpmlO00 cm2 dpm/100 cm2 dpm/100 cm2 dpm/100 cm 2
Direct Beta 396 553 2320 351 587 *Removable Alpha 395 N/A N/A N/A N/A
Removable Beta 395 1 109 9 1 Exposure Rate 171 18.4 uR/hr 22.2 uR/hr 1.8 uR/hr 18.7 uRJhr Removable H-3 59 158 756 117 193
* = All results < MDA (Highest MDA is 5.17 dpm/I00cm2 )
As can be seen from the above table, none of the final survey results for Survey Package 12 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 12 demonstrate that the process equipment room below 2 meters meets the criteria for release for unrestricted use.
REVISION 0
FINAL SURVEY REPORT
109
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-12A Package 12
Map
Process Equipment Room Below 2 Meters
REVISION 0
GA TECH RESEARCH REACTOR FIN-AL SURVIEY REPORT
110
• TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-12B Package 12
Direct Beta Activity
Process Equipment Room Below 2 Meters Direct Beta Activity 7000000Measurements: 396
Mean: 553 dpm/100 cm2
6000- Maximum: 2320 dpnf100 cm2 Std Deviation: 351 dpm/100 cm2 95% CL on Mean: 587 dpm/100 -m2
5000
o 4000
S3000
oo2000-
1000
0
-1000
- MDA
Surface
REVISION 0
.......................................
/
Ill
( GA iECH RESEARCH REACTOR
30.0
25.0
rj� 0
20.0
15.0
10.0
5.0
0.0
FINAL SURVEY REPORT
Figure 4-12C Package 12
Exposure Rate Measurements
Process Equipment Room Below 2 Meters Exposure Rate Measurements
Measurements: 171 Mean: 18.4 IAR/hr Std Deviation: 1.8 IPR/hr Baseline + 2 Std. Dev: 22.0 uR/hr Maximum: 22.2 AR/hr 95% CL on Mean: 18.7 yR/hr
if
A IAAAII, ItAAAA AA.0 11 AAIi 11AL IJ nA111,l1 AA1- 1K L AI
II Hi II1n'1BU HH 1V1Hl1 ill 1 1H1H 1 H 1 111L it1111 fil 1
Surface
REVISION 0
Baseline
.. ........
112
( GA [ECH RESEARCH REACTOR( (R FINAL SURVEY REPORT
Figure 4-12D Package 12
Removable Beta Activity
Process Equipment Room Below 2 Meters Removable Beta Activity600
500
400
300
200
100
0
-100
Surface
REVISION 0
MDA
113
GA t'ECH RESEARCH REACTOR(
FINAL SURVEY REPORT
Figure 4-12E Package 12
Removable H-3 Activity
Process Equipment Room Below 2 Meters Removable H-3 Activity4700
4300
3900
3500
3100
2700
2300
1900
1500
1100
700
300
-100
,,,
Surface
REVISION 0
0 0
c.�J
0
MDA
Measurements: 59 Mean: 158 dpm/100 dm2 Maximum: 756 dpm/100 cm2 Std Deviation: 117 dpm/100 cm2 95% CL on Mean: 193 dpm/100 cm2
i
N 1$ $ ,ýZk 4z 4z ýslv CP CJV'
114
GA TECH RESEARCH REACTOR
4.14 Package 13 - Process Equipment Room Above 2 Meters
Classification: Non-Suspect Affected
Survey Package 13 encompassed the reactor building process equipment room walls above 2 meters and the ceiling located in the basement. This package also includes the equipment access hatches that are located in the ceiling of this room. See Figure 4-13A for an overview. This package excludes 3 grids of wall 1 (01W01) row C which were reclassified to suspect affect (see Attachment B, package 13, surface 01W01, grids C12 through C14).
The final survey included 10 % biased beta scans, one direct beta measurement for each 20m2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each in2 of accessible surface area, and a number of smears to assess H-3 contamination levels. The biased locations were chosen by the technician performing the survey, and were based on the most probable areas for contamination.
This survey package has only one survey unit that includes the overhead areas of the process equipment room.
The final survey results for Survey Package 13 are summarized below and presented graphically in Figures 4-13B, 4-13C, and 4-13D.
Table 4.14 Survey Package 13
Final Survey Results Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean
Measurement dpm/100 cm2 dpm/100 cm2 dpm/100 cm 2 dpm/100 cm 2
Direct Beta 30 359 588 134 407 *Removable Alpha 30 N/A N/A N/A N/A
Removable Beta 30 -2 6 3 0 Removable H-3 30 143 458 68 .171 * - All results < MDA (Highest MDA is 5.17 dpm/100cm 2 )
As can be seen from the above table, none of the final survey results for Survey Package 13 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 13 demonstrate that the process equipment room above two meters meets the criteria for release for unrestricted use.
REVISION 0
FINAL SURVEY REPORT
115
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-13A Package 13
Map
Process Equipment Above 2 Meters
REVISION 0116
(
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-13B Package 13
Direct Beta Activity
Process Equipment Room Above 2 Meters Direct Beta Activity
Measurements: 30 Mean: 359 dpm/100 cm2 Maximum: 588 dpmi100 cm2 Std Deviation: 134 dpm/100 cm2 95% CL on Mean: 407 dpm/100 cm2
7000
6000
5000
4000
3000
2000
1000
MDA
Surface
REVISION 0
Ii .:. ii Iii p.m. i.Iiiii.iii� I I � p � I I I I
0
0
-1000
-1
-1
-1
(
117
r ECH RESEARCH REACTOR(
li'INAT[. •ITIRVEV R1WPC1RT
Figure 4-13C Package 13
Removable Beta Activity
Process Equipment Room Above 2 Meters Removable Beta Activity
Measurements: 30 Mean: -2 dpm/100 crn2 Maximum: 6 dpm/100 era2
Std Deviation: 3 dpro/l00 cm2 95 % CL on Mean: 0 dpi/ 100 cm2
Surface
REVISION 0
600
500
400
300
200
100
Piz
44
Oh
-100
MDA
fl -1
118
( GA TECH RESEARCH REACTOR (
FINAL SURVEY REPORT
Figure 4-13D Package 13
Removable H-3 Activity
Process Equipment Room Above 2 Meters Removable H-3 ActivityMeasurements: 30 Mean: 143 dpm/100 din2 Maximum: 458 dpm/100 cm2 Std Deviation: 68 dpm/100 cm2 95 % CL on Mean: 171 dpm/100 cm2 ,
4700
4300
3900
3500
3100
2700
2300
1900
1500
1100
700
300
-100
P.i 0 0D
0D
REVISION 0
;I I iu lip w
Surface
MDA
119
4.15 Package 14 - Yard Open Land Areas
Classification: Unaffected
Survey package 14 encompassed 908 square meters of the Unaffected Open Land
Areas of the Reactor Facility Yard. The Open Land Areas of the Reactor Facility
Yard border the south and east sides of the reactor containment building and the
paved road as depicted in figure 4-14A titled "Yard Unaffected Open Land
Areas." The unaffected yard areas were not used for radioactive materials storage.
The survey was conducted by establishing a survey map, see Attachment B, which defined the number and sample location for each required sample. At each
sample location the following was performed:
"* A nine meter square gamma scan to identify elevated areas of activity.
"* One exposure rate measurement at one meter. "* A 0 to 6" soil sample for gamma analysis.
The exposure rate results are summarized in the table below and presented graphically in Figure 4-14B.
Table 4.15 Survey Package 14
Final Exposure Rate Results
Type of # of Meas. Mean Max Std. Dev. 95% CL of mean Measurement
Exposure Rate 30 11.6uR 14.5 uR 1.4uR 12.1uR
The soil analysis results are summarized in the accompanying Table 4.16 titled "Yard Open Land Areas Soil Sample Gamma Spectroscopy Results."
The final survey results for Survey Package 14 demonstrate that the Open Land
Areas meet the criteria for release for unrestricted use.
REVISION 0
FINAL SURVEY REPORTGA TECH RESEARCH REACTOR
120
Gti TECH RESEARCH REACTOR FINAL SURVEY REPORT
Table 4.16 Yard Open Land Areas
Soil Sample Gamma Spectroscopy Results
Sample # Mn-54 Co-60 Zn-65 Cs-137 Eu-152
Activity Uncertainty Activity Uncertainty Activity Uncertainty Activity Uncertainty Activity Uncertainty pci/g pci/g pci/g pci/g pci/g pci/g pci/g pci/g pci/g pci/g
1 <MDA N/A <MDA N/A <MDA N/A <MDA N/A <MDA N/A 2 <MDA N/A <MDA N/A <MDA N/A 3.3116e-1 9.462e-2 <MDA N/A 3 <MDA N/A <MDA N/A <MDA N/A <MDA N/A <MDA N/A 4 <MDA N/A 3.1647e- 1 7.975e-2 <MDA N/A 2.1931 e- 1 7.878e-2 <MDA N/A 5 <MDA N/A <MDA N/A <MDA N/A <MDA N/A <MDA N/A 6 <MDA N/A <MDA N/A <MDA N/A <MDA N/A <MDA N/A 7 <MDA N/A <MDA N/A <MDA N/A 2.8515e-1 9.376e-2 <MDA N/A 8 2.3105e-1 7.925e-2 <MDA N/A <MDA N/A <MDA N/A <MDA N/A 9 <MDA N/A <MDA N/A <MDA N/A 5.1734e-1 1.314e-1 <MDA N/A
9QC <MDA N/A <MDA N/A <MDA N/A 6.6839e-1 1.504e-1 <MDA N/A 10 <MDA N/A <MDA N/A <MDA N/A <MDA N/A <MDA N/A 11 2.894e-1 1.008e-1 <MDA N/A <MDA N/A 5.1477e-1 1.329e-1 <MDA N/A 12 <MDA N/A <MDA N/A <MDA N/A <MDA N/A <MDA N/A 13 <MDA N/A <MDA N/A <MDA N/A 5.1321e-1 1.372e-1 <MDA N/A 14 <MDA N/A <MDA N/A <MDA N/A 5.3419e-1 1.296e-1 <MDA N/A 15 <MDA N/A <MDA N/A <MDA N/A 6.4240e-1 1.464e-1 <MDA N/A 16 2.5035e-1 8.716e-2 <MDA N/A <MDA N/A 4.1563e-1 1.11le-1 <MDA N/A 17 2.0613e-1 7.791e-2 <MDA N/A <MDA N/A 3.3850e-1 9.875e-2 <MDA N/A
17QC <MDA N/A <MDA N/A <MDA N/A <MDA N/A <MDA N/A 18 <MDA N/A <MDA N/A <MDA N/A 4.4211 e- 1 1.215e-I <MDA N/A 19 <MDA N/A <MDA N/A <MDA N/A 3.4755e-1 9.830e-2 <MDA N/A 20 <MDA N/A <MDA N/A <MDA N/A 7.8097e-1 1.302e-1 <MDA N/A 21 3.8315e-1 1.155e-1 <MDA N/A <MDA N/A 5.3670e-1 1.352e-1 <MDA N/A 22 <MDA N/A <MDA N/A <MDA N/A 3.6222e-1 1.025e-1 <MDA N/A 23 <MDA N/A <MDA N/A <MDA N/A 5.5403e-1 1.430e-l <MDA N/A 24 <MDA N/A <MDA N/A <MDA N/A <MDA N/A <MDA N/A 25 <MDA N/A <MDA N/A <MDA N/A 3.8700e-1 1.117e-1 <MDA N/A 26 <MDA N/A <MDA N/A <MDA N/A 3.9772e-1 1.136e-1 <MDA N/A 27 <MDA N/A <MDA N/A <MDA N/A 4.3390e-1 1.203e-1 <MDA N/A 28 <MDA N/A <MDA N/A <MDA N/A 3.8199e-1 1.103e-1 <MDA N/A 29 <MDA N/A <MDA N/A <MDA N/A 1.43e-1 2.89e-2 <MDA N/A 30 <MDA N/A <MDA N/A <MDA N/A 2.6984e-1 9.693e-2 <MDA N/A
Ag-110m and CS-134not included in nuclide library used to analyze soil samples. No unidentified photo peaks found that are associated with Ag-1 10m or Cs-134.
For each sample, none of the individual radionuclide analyses results exceeded 10% of the of the radionuclide specific guideline values listed in Table 3.3.
121 REVISION 0
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-14A Package 14
Map
Yard Open Land Areas
FENCE LTNE
ACCESS GATE
NEELY NUCLEAR RESEARCH CENTER
S_ = Unafffected Open Land Areas North ->
REVISION 0
RETAIN'ING
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
122
( GA. iECH RESEARCH REACTOR( (
FINAL SUR VEY RE'PORT
Figure 4-14B Package 14
Exposure Rate Measurements
Yard Open Land Areas Exposure Rate Measurements
Baseline
NCZ 1,- 0 0 ~ 00 0ý (Z M t't kn ý0 t lN 000 CN Q5 . ('t kn 1f 0 t 000 Qý C 1ý Nýb N Ný! N
Cz C Cz z QýQý q :Z
Location
REVISION 0
15.0
14.0
13.0
12.0
11.0
10.0
9.0
8.0
7.0.
6.0
5.0
4.0
3.0
2.0-
0
1.0
0.0
123
4.16 Package 15 - Basement Air Compressor Room
Classification: Suspect Affected
Survey Package 15 encompassed a small room in the basement of the reactor building that housed two air compressors. See Figure 4-15A for an overview of this area.
There was no need to perform decontamination activities in this area. Where practical, accessible surfaces were gridded into lm2 grids. The final survey included 100 % beta scans, one direct beta measurement for each m 2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each m2 of accessible surface area, one exposure rate measurement for each mi2 of accessible floor area, and a number of smears to assess H-3 contamination levels.
Survey Package 15 was divided into the following survey units:
"* Floor inside compressor room "* Compressor room walls 1 through 4 "* Ventilation duct 1 located in wall 3 "* Ventilation duct 2 located in wall 1
The final survey results for Survey Package 15 are summarized below and presented graphically in Figures 4-15B, 4-15C, 4-15D, and 4-15E.
Table 4.17 Survey Package 15
Final Survey Results
Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean
Measurement dpm/100 cm2 dpm/100 cm2 dpm/100 cm2 dpm/100 cm 2
Direct Beta 96 879 1975 491 977
*Removable Alpha 96 N/A N/A N/A N/A
Removable Beta 96 1 32 6 2
Exposure Rate 12 34.2 uR/hr 41.6 uR/hr 4.1 uR/hr 36.6 uR/hr
Removable H-3 31 215 905 192 293
• = All results < MDA (Highest MDA is 3.91dpm/100cmL)
Two exposure rate measurement results collected in this area are slightly elevated.
However, the estimated background exposure rate in this area is also elevated. All of the exposure rate measurement results collected in this area are within 2
standard deviation of the mean and meet the criteria established for evaluating exposure rate measurement results.
As can be seen from the above table and figures 4-15A through 4-15E, none of the final survey results for Survey Package 15 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific
guideline value for removable H-3 was exceeded, derivation of the SPGL based
on the site radionuclide mix has been validated. The final survey results for
Survey Package 15 demonstrate that the compressor room of the reactor building
meets the criteria for release for unrestricted use.
FINAL SURVEY REPORTGA TECH RESEARCH REACTOR
REVISION 0124
(( TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-15A Package 15
Map
Air Compressor Room
AD
C
1 2
01W0Z (Wall 2)
4 5 601V0t (Ventl)
)VO021
01W03 (Wall 3)
a1Wal (Wall 1)A
D C B A 3 4 5
01(01 (Floor1)
A B C D
A
6 5 4 3
01W04 (Walla4) D - Deontes I Meter Grid
REVISION 0
3
2
125
I!TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-15B Package 15
Direct Beta Activity
Air Compressor Room Direct Beta Activity 7000 7000 Measurements: 96
6000Mean: 879 dpm/100 cm2 6000 Maximum: 1975 dpm/100 cm2
Std Deviation: 491 dpm/100 cm2 95 % CL on Mean: 977 dpni/100 cm2
5000
S4000
S3000
* 2000 II
.. . . . . ..
S1000l z
- MDA
-1000
Surface
126 tP'%7T tTnrj AJA••V .LIkJ&V. V
GA .ECH RESEARCH REACTORFINA SUREY RPO(
FINAL SURVEY REPORT
Figure 4-15C Package 15
Exposure Rate Measurements
Rate Measurements
Baseline
O1FO1
Surface
REVISION 0
1�
rj� 0
45.0
40.0
35.0
30.0
25.0
20.0
15.0
10.0
5.0
0.0
(
127
TECH RESEARCH REACTOR
FINAL SURVEY REPORT
Figure 4-15D Package 15
Removable Beta Activity
Air Compressor Room Removable Beta Activity
0m
0
600
500
400
300
200
100
0
-100
Measurements: 96 Mean: I dpm/100 era2
Maximum: 32 dpm/100 cm2 Std Deviation: 6 dpm/100 Hm2 95 % CL on Mean: 2 dpm/100 era2
4�&44�
�\
Surface
128 REVISION 0
MDA
FINAL SURVEY REPORT
(- TECH RESEARCH REACTOR
FINAL SURVEY REPORT
Figure 4-15E Package 15
Removable H-3 Activity
0 0
4e�1
0
Air Compressor Room Removable H-3 Activity4700
4300
3900
3500
3100
2700
2300
1900
1500
1100
700
300
-100
10%N 10%v
Surface
REVISION 0
MDA
129
GA TECH RESEARCH REACTOR
4.17 Package 16 - Areas Outside Process Equipment Room Below 2 Meters
Classification: Suspect Affected
Survey Package 16 consisted of several areas outside the process equipment room located in the basement. See Figure 4-16A for an overview. This area contained several pieces of contaminated equipment (e.g., pneumatic transfer system, biomedical door hydraulic system, D 2 0 analysis equipment and misc. coolant system lines).
Approximately 10% of the floor area required decontamination. The walls required only minor decontamination. Where practical, accessible surfaces were gridded.
The final survey included 100 % beta scans, one direct beta measurement for each m 2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each m 2 of accessible surface area, one exposure rate measurement for each m2 of accessible floor area, and a number of smears to assess H-3 contamination levels.
Survey Package 17 was divided into the following survey units:
" Rupture disk chamber room "* Floor "* Walls 1-4 "* Ceiling
"* Rabbit room "* Floor "* Walls 1-4
" Experiment room "* Floor "* Walls 1-4
" MCC panel area "* Floor "* Walls 1-3 "* Sump "* Rx vent duct "* A/C vent duct "* Cement blocks "* MCC Panel
" Stairwell general area 0 Floor 0 Walls 1-2 * Structures 1-4 (columns) 0 Structure 5 (exterior of HEPA ventilation unit)
REVISION 0
FINAL SURVEY REPORT
130
The final survey results for Survey Package 16 are summarized below and presented graphically in Figures 4-16B, 4-16C, 4-16D, and 4-16E.
Table 4.18 Survey Package 16
Final Survey Results Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean
Measurement dpm/100 cm 2 dpm/100 cm 2 dpm/100 cm 2 dpm/100 cm 2
Direct Beta 808 294 2046 414 323 *Removable Alpha 808 N/A N/A N/A N/A
Removable Beta 808 2 67 7 3
ExposureRate 348 18.4 uR/hr 35.4 uR/hr 3.3 uR/hr 18.7 uRihr Removable H-3 95 233 1760 269 296 * = All results < MDA (Highest MDA is 5.17 dpm/100cm 2 )
During the Final Survey several of the exposure rate measurements exceeded the SPGL. These measurements were investigated and all were found to be attributed to their location immediately outside the air compressor room block walls. The air compressor room block walls were determined to be composed of materials containing elevated levels of naturally occurring radioactive materials (see package 15).
As can be seen from the above table, none of the final survey results, with the exception of the exposure rate measurements, for Survey Package 16 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 16 demonstrate that the areas outside the process area room of the basement meets the criteria for release for unrestricted use.
REVISION 0
FINAL SURVEY REPORTGA TECH RESEARCH REACTOR
131
GA TCH RSEARH RECTORFINAL SUTRVEY R~EPORT
Figure 4-16A Package 16
Map
Areas Outside Process Equipment Room Below 2 Meters
• R•• , 055S°
'05S05 05WO1•
05S03 05F01
rocess Equipment Roo Stairwell General Area
Helium Rupture Disk Chamber * 05S02
(below slab)
0 05W02
Rabbit Roo 02 0 2W[4 05S01"
02W03 - .3W403F4
04W02 3W4 03W
03W03 Experim oom
C?04F1 CC XSp04V02
% o4wol N--
REVISION 0
GA TECH RESEARCH REACTOR
132
((
-1000
Surface
133 REVISION 0
TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-16B Package 16
Direct Beta Activity
Areas Outside Process Equipment Room Below 2 Meters
Direct Beta Activity 7000
Measurements: 808
Mean: 294 dpm/100 cm2
6000 Maximum: 2046 dpm/100 cm2
Std Deviation: 414 dpm/100 cm2
95% CL on Mean: 323 dpm/100 cm2
S5 0 0 0
0I4000
$ 3000
S2000
Z 1000 MDA o 91a
0 ... .. --------
~'ECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-16.C Package 16
Exposure, Rate Measurements
Areas Outside Process Equipment Room Below 2 Meters Exposure Rate Measurements 40.0
Baselie + 2 td. DvBa25.lpR/e
15.0
10.0
5.0
Surface
134 D~ T 1 f k
F- ~Eviol IN V
-i .ECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-16D Package 16
Removable Beta Activity
Areas Outside Process Equipment Room Below 2 Meters Removable Beta Activity
600
Measurements: 808
Mean: 2 dpm/100 5m2 500- Maximum: 67 dpm/lO0 cmna Std Deviation: 7 dpm/100 cm2 95% CL ont Mean: 3 dpm/100 cm2
,• 400
S300
'' 200
100
00
-100
MDA
Surface
REVISION 0135
TECH RESEARCH REACTOR F]
Figure 4-16E Package 16
Removable H-3 Activity
Areas Outside Process Equipment Room Below 2 Meters Removable H-3 Activity
W W-4
0J
<0
0
4700
4300
3900
3500
3100
2700
2300
1900
1500
1100
700
300
-100
( INAL SURVEY REPORT
MDA
iý 0 e*1,eI,
Surface
REVISION 0
Measurements: 95 Mean: 233 dpm/ 100 dm2 Maximum: 1760 dpm/100 cm2 Std Deviation: 269 dpmi/100 rm2 95% CL on Mean: 296 dpm/100 cm2
0F001, Row F, Location 6 04V01, Locations 4 & 5
-t/,0ý1 " 160"
136
4.18 Package 17 - Areas Outside Process Equipment Room Above 2 Meters
Classification: Non-Suspect Affected
Survey Package 17 encompassed the area outside the process equipment room above 2 meters. It is located in the basement of the reactor building. See Figure 4-17A for an overview. This area consisted of several areas outside the process equipment room and included the wall surfaces from 2 meters above the floor up to and including the ceiling.
There was no decontamination required in these areas. The final survey included 10% biased beta scans, one direct beta measurement for each 20 m2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each 20 m2 of accessible surface area, and a number of smears to assess H-3 contamination levels. The biased locations were chosen by the technician performing the survey, and were based on the most probable areas for contamination.
Survey Package 17 was divided into the following survey units:
"* Rabbit room (overhead above 2 meters) "* Experiment room (overhead above 2 meters) "* MCC panel area (overhead above 2 meters) "* Stairwell general area (overhead above 2 meters)
The final survey results for Survey Package 17 are summarized below and presented graphically in Figures 4-17B, 4-17C, and 4-17D.
Table 4.19 Survey Package 17
Final Survey Results Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean
Measurement dpm/100 cm 2 dpm/100 cm2 dpm/100 cm 2 dpm/100 cm 2
Direct Beta 35 213 574 251] 296 *Removable Alpha 35 N/A N/A N/A N/A
Removable Beta 35 -2 73 -1 Removable H-3 35 110 153 19 117 * - All results < MDA ( Highest MDA is 5.17 dpm/1O00cm 2 )
As can be seen from the above table, none of the final survey results for Survey Package 17 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 17 demonstrate that the areas outside the process equipment room above 2 meters meet the criteria for release for unrestricted use.
REVISION 0
FINAL SURVEY REPORTGA TECH RESEARCH REACTOR
137
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-17A Package 17
Map
Areas Outside Process Equipment Room Above 2 Meters
REVISION 013 8
( GA IECH RESEARCH REACTOR ( FINAL SURVEY REPORT
Figure 4-17B Package 17
Direct Beta Activity
Areas Outside Process Equipment Room Above 2 Meters Direct Beta Activity
SMDA. .ImImI~I .
. . 1 -
Surface
REVISION 0
7000
6000
5000
4000
3000
2000
1000
0
Measurements: 35 Mean: 213 dpm/100 cm2 Maximum: 574 dpm/100 cm2 Std Deviation: 251 dpm/100 cm2 95% CL on Mean: 296 dpm/100 cm2
0
-1000
FINAL SURVEY REPORT
-1
139
. . . . . . . . . . . .
LA TECH RESEARCH REACTOR
0
0
�0
600
500
400
300
200
100
0
-100
FINAL SURVEY REPORT
Figure 4-17C Package 17
Removable Beta Activity
Areas Outside Process Equipment Room Above 2 Meters Removable Beta Activity
Measurements: 35 Average: -2 dpm/100 din2 Maximum: 7 dpm/100 crD2 Std Deviation: 3 dpm/100 cm2 95% CL on Mean: -1 dpm/100 c=2
-*-- * m--- -* m*-* $-* * -* [ -" = - 9 - * - , n*--l9--* *+* *-* * *'dmdl
Surface
REVISION 0
- MDA
FINA SURVEY REPORT
140
ý. - TECH RESEARCH REACTOR
0•
0•
$
4700
4300
3900
3500
3100
2700
2300
1900
1500
1100
700
300
-100
FINAL SURVEY REPORT
Figure 4-17D Package 17
Removable H-3 Activity
Areas Outside Process Equipment Room Above 2 Meters Removable H-3 Activity
Measurements: 35
Mean: 110 dpm/100 din2 Maximum: 153 dpm/100 cm2 Std Deviation: 19 dpm/100 cm2
, ~95% CL on Mean: 117 dpm/1O0 =m2
MDA
Surface
REVISION 0
I
I
141
4.19 Package 18 - Reactor Vessel Tunnel
Classification: Suspect Affected
Survey Package 18 encompassed the reactor vessel tunnel and alcove area, The tunnel is located in the basement of the reactor building. See Figure 4-18A for an overview of this area.
There were decontamination activities in this area. Decontamination consisted of concrete removal from a portion the floor and all of the walls. Where practical, accessible surfaces were gridded into lm 2 grids. The final survey included 100 % beta scans, one direct beta measurement for each m2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each m2 of accessible surface area, one exposure rate measurement for each m 2 of accessible floor area, and a number of smears to assess H-3 contamination levels.
Survey Package 18 was divided into the following survey units:
"* Floor inside tunnel "* Tunnel wall 1 "* Tunnel wall 2 "* Tunnel wall 3 "* Tunnel ceiling "* Tunnel trench
The final survey results for Survey Package 18 are summarized below and presented graphically in Figures 4-18B, 4-18C, 4-18D, and 4-18E.
Table 4.20 Survey Package 18
Final Survey Results Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean
Measurement dpm/100 cm2 dpm/100 cmr dpm/100 cm2 dpm/100 cm2 Direct Beta 59 778 1926 325 861
*Removable Alpha 59 N/A N/A N/A N/A
Removable Beta 59 -1 20 4 0 Exposure Rate 10 28.3 uR/hr 35.2 uR/hr 4.3 uR/hr 31 uR/hr
Removable H-3 30 176 825 150 238 *=All results < MDA (Highest MDA 1.91 dpm/1 00cm 2)
REVISION 0
GA TECH RESEARCH REACTOR
142
FINAL SURVEY REPORT
As shown in Table 4.20, the exposure rate measurement results collected in this area are slightly elevated. However, the estimated background exposure rate in this area is also slightly elevated. All of the exposure rate measurement results collected in this area are within 2 standard deviation of the mean and meet the criteria established for evaluating exposure rate measurement results.
As can be seen from the above table and the following figures 4-18A through 4-18E, none of the final survey results for Survey Package 18 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. Upon further investigation it was determined that the elevated exposure rate measurement results were due to the geometry effects of the survey area i.e. immediately adjacent concrete structures.
The final survey results for Survey Package 18 demonstrate that the tunnel and alcove area of the reactor building meet the criteria for release.
REVISION 0
FINAL SURVEY REPORTGA TECH RESEARCH REACTOR
143
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-18A Package 18
Map
Vessel Tunnel
N
Vessel Tunnel
REVISION 0144
( G,. T ECH RESEARCH REACTOR ( ( FINAl, NTIRVF.V RE.POIRT
Figure 4-18B Package 18
Direct Beta Activity
Vessel Tunnel Direct Beta Activity7000
6000
5000
4000
3000
2000
1000
- MDA
0
-1000
Surface
REVISION 0
40
z
FjNA1r..0%1rjPVYV -UPPOPT
(
145
GA iECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-18C Package 18
Exposure Rate Measurements
Vessel Tunnel Exposure Rate MeasurementsMeasurements: 10 Mean: 28.3 ItR/hr Std Deviation: 4.3 dR/hr Baseline + 2 Std. Dev: 36.9 IR/hr Maximum: 35.2 AR/hr 95% CL on Mean: 31.0 ILR/hr
A A A ABaseline
O1FO1
Surface
REVISION 0
40.0
35.0
k
('
30.0
25.0
20.0
15.0
10.0 -
5.0
0.0-
FINAL SURVEY REPORT
I! A
146
T , TECH RESEARCH REACTOR FINA SUREV RPORFINAL SURVEY REPORT
Figure 4-18D Package 18
Removable Beta Activity
Vessel Tunnel Removable Beta Activity
Surface
REVISION 0
600
500
0
400
300
200
100
0
-100
MDA
(
147
( ( • TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-18E Package 18
Removable H-3 Activity
Vessel Tunnel Removable H-3 Activity 4700
4300Measurements: 30 4300-Mean: 176 dpm/100 din2 Maximum: 825 dpm/100 era2 3900-Std Deviation: 150 dpm/100 cm2 S3900
ۥ. 95 % CL on Mean: 238 dpm/100 era2
o 3500
3100
PW 2700
+-' 2300
S1900
- 1500
1100
S700O
300_ _
SMDA -100
Surface
REVISION 0148
4.20 Package 19 - Bismuth Leak Area
Classification: Suspect Affected
Survey Package 19 consisted of the bismuth leak area located in the basement immediately outside the experimental room. This package also includes the biomedical room door pit. This area contained the hydraulic equipment needed to raise and lower the bio-medical room shield doors. See Figure 4-19A for an overview.
This bismuth leak area and the biomedical room door pit required extensive decontamination resulting in Survey Package 19 being classified as suspect affected for purposes of the Final Survey. Approximately 60% of the floor area required decontamination. The walls of the hydraulic shaft area also required decontamination. Where practical, accessible surfaces were gridded.
The final survey included 100 % beta scans, one direct beta measurement for each m2 of accessible surface area, one smear of removable surface contamination (beta and alpha) for each m 2 of accessible surface area, one exposure rate measurement for each m2 of accessible floor area, and a number of smears to assess H-3 contamination levels.
Survey Package 19 was divided into the following survey units:
"* Floor "* Walls 1-3 (grid A3 does not exist, wall 4 does not exist) "* Trench 1 "* Ceiling "* Biomedical room door
The final survey results for Survey Package 19 are summarized below and presented graphically in Figures 4-19B, 4-19C, 4-19D, and 4-19E.
Table 4.21 Survey Package 19
Final Survey Results Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean
Measurement dpm/100 cm 2 dpm/100 cm2 dpm/100 cm 2 dpm/100 cm 2
Direct Beta 89 400 1233 288 460 *Removable Alpha 89 N/A N/A N/A N/A
Removable Beta 89 1 19 5 2 Exposure Rate 20 16.9 uR/hr 19.3 uR/hr 1.0 uR/hr 17.3 uR/hr
Removable H-3 30 168 347 75 200 * = All results < MDA (Highest MDA is 8.60 dpm/100cm 2 )
REVISION 0
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
149
As can be seen from the above table, none of the final survey results for Survey Package 19 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 19 demonstrate that the bismuth leak area meets the criteria for release for unrestricted use.
REVISION 0
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
150
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-19A Package 19
Map
Bismuth Leak Area
Bismuth Leak Area
REVISION 0151
TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-9B Package 19
Direct Beta Activity
Bismuth Leak Area Direct Beta Activity 7000
Measurements: 89 Mean: 400 dpm/100 cm2
6000 Maximum: 1223 dpm/100 cu2 Std Deviation: 288 dpm/100 cm2 95 % CL on Mean: 460 dpm/ 100 cm2
5000
S 4000
"tZ 3000
2000
"• 1000- MDA
0 o HH I I I I I. Ii1-IlI!,iII I HIil I I I HI1r.HIH
-1000
Surface
REVISION 0152
GA 'TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-19C Package 19
Exposure Rate Measurements
Bismuth Leak Area Exposure Rate Measurements
Baseline
Surface
REVISION 0
25.0 24.0 23.0 22.0 21.0 20.0 19.0 18.0 17.0 16.0 15.0 14.0 13.0 12.0
11.0 10.0
9.0 8.0 7.0 6.0 5.0 4.0 3.0 2.0 1.0 0.0
'-4
rj) 0
t
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
153
TECH RESEARCH REACTOR(
FINAL SURVEY RE'PORT'
Figure 4-19D Package 19
Removable Beta Activity
Bismuth Leak Area Removable Beta Activity600
500
400
300
200
100
0
100
Surface
MDA
& &
REVISION 0
0
0
$
154
TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-19E Package 19
Removable H-3 Activity
Bismuth Leak Area Removable H-3 Activity
Measurements: 30 Mean: 168 dpm/100 din2 Maximum: 347 dpm/100 crn2 Std Deviation: 75 dpm/100 cm2 95 % CL on Mean: 200 dpm/100 cm2
0 0
�eI�
0
4700
4300
3900
3500
3100
2700
2300
1900
1500
1100
700
300
-100
C)
Surface
REVISION 0
-- -I--i - -i--- - -t I ~ I I T'I'0 I n . I 1 I I ' , I -I I I I I. MDA
155
4.21 Package 20 - Reactor Ventilation Above 2 Meters
Classification: Non-Suspect Affected
Survey Package 20 encompassed the reactor building process ventilation system
above 2 meters, including any ceilings. See Figure 4-20A for an overview.
A small area on the floor of the stack was decontaminated since it slightly
exceeded the SPGL. This was always considered a possibility given that the floor
and lower walls of both the stack and the stack fan room were classified as
Suspect Affected.
The final survey included 10 % biased beta scans, one direct beta measurement
for each 20m2 of accessible surface area, one smear of removable surface
contamination (beta and alpha) for each m2 of accessible surface area, and a
number of smears to assess H-3 contamination levels. The biased locations were
chosen by the technician performing the survey, and were based on the most
probable areas for contamination.
Survey Package 20 was divided into the following survey units:
"* Reactor building stack main vent room "* Instrument room "* Reactor building stack
The final survey results for Survey Package 20 are summarized below and
presented graphically in Figures 4-20B, 4-20C, and 4-20D.
Table 4.22 Survey Package 20
Final Survey Results
Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean
Measurement dpm/100 cm 2 dpm/100 cm 2 dpm/100 cm 2 dpm/100 cm 2
Direct Beta 30 92 1219 352 218
*Removable Alpha 30 N/A N/A N/A N/A
Removable Beta 30 2 28 8 5
Removable H-3 30 219 1133 253 323
* All results < MDA (Highest MDA is 5.17 dpm/100cm 2 )
As can be seen from the above table, none of the final survey results for Survey
Package 20 exceeded the Site Specific Guideline Values (SPGLs). Since neither
the SPGL nor the radionuclide specific guideline value for removable H-3 was
exceeded, derivation of the SPGL based on the site radionuclide mix has been
validated. The final survey results for Survey Package 20 demonstrate that the
reactor process ventilation system above two meters meets the criteria for release for unrestricted use.
REVISION 0
FINAL SURVEY REPORTGA TECH RESEARCH REACTOR
156
GA TCH RSEARH RECTORFINAL SUR VEY REPOR~T
Figure 4-20A Package 20
Map
Reactor Ventilation Above 2 Meters
N
REVISION 0
GA TECHI RESEARCH REACTOR
157
GA TECH RESEARCH REACTORFINAL SURVEY REPORT
Figure 4-20B Package 20
Direct Beta Activity
Reactor Ventilation, Above 2 Meters Direct Beta. Activity7000
6000
5000
4000
3000
2000
1000
0
-1000
Surface
REVISION 0
MDA
0 0
"0
z
158
( JECH RESEARCH REACTOR (FINAL SURVEY REPORT
Figure 4-20C Package 20
Removable Beta Activity
Reactor Ventilation Above 2 Meters Removable Beta Activity
MDA
Surface
REVISION 0
600
500
3-4 0
400
300
200
100
0
-100
159
A TECH RESEARCH REACTOR (
Figure 4-20D Package 20
Removable H113 Activity
Reactor VentilationAbove 2 Meters Removable H-3 Activity
0 0
"0
Q
0
4700
4300
3900
3500
3100
2700
2300
1900
1500
1100
700
300
-100 MDA
Surface
REVISION 0160
4.22 Package 21 - Elevator Equipment Room and Shaft
Classification: Unaffected
Survey Package 21 encompassed the reactor building elevator equipment room and the elevator shaft. See Figure 4-21A for an overview.
No decontamination was required in these areas. No known radioactive materials were transported through these areas.
The final survey included 10% beta scans, one direct beta measurement for each 20 m2 of accessible surface area, one exposure rate measurement at each corresponding direct beta measurement on the floor, one smear of removable surface contamination (beta and alpha) for each 20 m2 of accessible surface area, and a number of smears to assess H-3 contamination levels.
Survey Package 21 was divided into the following survey units:
"* Elevator shaft "• Elevator equipment room
The final survey results for Survey Package 21 are summarized below and presented graphically in Figures 4-21B, 4-21C, 4-21D and 4-21E.
Table 4.23 Survey Package 21
Final Survey Results Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean
Measurement dpm/100 cm2 dpm/100 cm 2 dpm/100 cm 2 dpm/100 cm 2
Direct Beta 30 158 580 243 245 *Removable Alpha 30 N/A N/A N/A N/A
Removable Beta 30 9 64 16 15 Exposure Rate 6 17.9 uR/hr 19.5 uRihr 1.4 u R/hr 19 uR/hr
Removable H-3 30 307 1130 266 417 * - All results < MDA (Highest MDA is. 8.60 dpm/1 00cm2 )
As can be seen from the above table, none of the final survey results for Survey Package 21 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 21 demonstrate that elevator shaft and equipment room meet the criteria for release for unrestricted use.
REVISION 0
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
161
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-21A Package 21
Map
Elevator Equipment Room and Shaft
REVISION 0162
GI [ECH RESEARCH REACTOR FINAL SUJRVEY REPORT
Figure 4-21B Package 21
Direct Beta Activity
Elevator Equipment Room & Shaft Direct Beta Activity7000
-6000
5000
4000
3000
2000
1000
0
-1000
Surface
REVISION 0
MDA
"z:
Measurements: 30 Mean: 158 dpm/100 c=2 Maximum: 580 dpm/100 cm2 Std Deviation: 243 dprn/100 =2 95% CL on Mean: 245 dpm/100 cm2
FINAL SURVEY REPOR
163
GA fECH RESEARCH REACTOR(
FINAL SURVEY REPORT
Figure 4-21C Package 21
Exposure Rate Measurements
Elevator Equipment Room & Shaft Exposure Rate Measurements
Measurements: 6 _____________________________________________Mean: 17.9,u/LRhr _____________
Std Deviation: 1.4 ItR/hr Baseline + 2 Std. Dey: 20.6 AzR/hr Maximum: 19.5 ItR/hr_______________
95 % CL on Mean: 19.0 /AR/hr
40.0
35.0
30.0
25.0
20.0
15.0
10.0
5.0
0.0 r.'
Baseline
Surface
REVISION 0
________ 4.'�
"0"
A A
I
164
Gt& TECH RESEARCH REACTOR(
FINAL SURVEY REPORT
Figure 4-21D Package 21
Removable Beta Activity
Elevator Equipment Room & Shaft Removable Beta Activity
MDA
Surface
REVISION 0
600
500
400
300
200
100
0
0
$
-1
Measurements: 30 Mean: 9 dpm/100 cm2 Maximum: 64 dpm/100 cm2 Std Deviation: 16 dpm/100 cm2 95% CL on Mean: 15 dpm/100 cnr2
0
-100
FINAL SURVEY REPORT
-1
,, , , ' ' .. ' - , ,, - • - ,,,, -- , ,,,, , ' ' _.",'m , ,± ,,•.+-j• 4 -"+-j.±- ,,+ : -
/ (
165
T GiA TECH RESEARCH REACTOR
.¶ 0
FINAL �TTflVFV 1�EPORT
Figure 4-21E Package 21
Removable H-3 Activity
Elevator Equipment Room & Shaft Removable H-3 Activity 4700
4300 Measurements: 30 Mean: 307 dpm/100 dm2 Maximum: 1130 dpm/100 cm2
3900 Std Deviation: 266 dpm/100 cm2 95% CL on Mean: 417 dpm/100 cm2
3500
3100
2700
2300
1900
1500
1100
7OO
3OO
-100-
Surface
REVISION 0
MDA
FINAL SURVEY 111 PORT
(
166
GA TECH RESEARCH REACTOR
4.23 Package 22 - Misc. Pipes and Penetrations
Classification: Suspect Affected
Survey Package 22 encompassed various pipes and penetrations found on the reactor building first floor and other miscellaneous areas in the basement. See Figures 4-22A, 4-22B and 4-22C for an overview.
No decontamination was required in any of these penetrations and pipes.
The final survey included 100 % beta scans of all accessible areas, one direct beta measurement for each penetration, one smear of removable surface contamination (beta and alpha) for each m 2 of accessible surface area, and a number of smears to assess H-3 contamination levels.
Survey Package 22 was divided into the following survey units:
"* 1 st floor plug holes
"* Other penetrations & pipes ( all areas)
The final survey results for Survey Package 22 are summarized below and presented graphically in Figures 4-22D, 4-22E, and 4-22F.
Table 4.24 Survey Package 22
Final Survey Results Type of # of Meas. Mean Max. Stand. Dev. 95 % CL of mean
Measurement dpm/100 cm2 dpm/100 cm2 dpm/100 cm2 dpm/100 cm 2
Direct Beta 118 225 1767 608 335 *Removable Alpha 120 N/A N/A N/A N/A
Removable Beta 120 9 102 15 12 Removable H-3 30 210 650 129 264
* - All results < MDA (Highest MDA is. 8.60 dpm/1 00cm2 )
As can be seen from the above table, none of the final survey results for Survey Package 22 exceeded the Site Specific Guideline Values (SPGLs). Since neither the SPGL nor the radionuclide specific guideline value for removable H-3 was exceeded, derivation of the SPGL based on the site radionuclide mix has been validated. The final survey results for Survey Package 22 demonstrate that these penetrations and pipes meet the criteria for release for unrestricted use.
REVISION 0
FINAL SURVEY REPORT
167
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-22A Package 22
Misc. Pipes and Penetrations First Floor (01P00)
__ (D - Denotes L8 number and approximate location of pipe or penetration.
REVISION 0
GA TECH RESEARCHJ REACTOR FINAL SURVEY REPORT
168
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-22B Package 22
Misc. Pipes and Penetrations First Floor (02P00)
Q - Denotes L8 number and approximate location of pipe or penetration.
REVISION 0
FLNAL SURVEY REPORTGA TECH RESEARCH REACTOR
169
GA TECH RESEARCH REACTOR FINAL SURVEY REPOR~T
Figure 4-22C Package 22
Misc. Pipes and Penetrations Basement (02P00)
Elevator Equipment Room
N---
0 - Denotes L8 number and approximate location of pipe or penetration.
REVISION 0
FINAL SURVEY REPOR
170
/TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-22D Package 22
Direct Beta Activity
Misc. Pipes and Penetrations Direct Beta Activity 7000
Measurements: 118 Mean: 225 dpm/100 cm2 6000 Maximum: 1767 dpm/100 cm2
Std Deviation: 608 dpm/100 cm2 95% CL on Mean: 335 dpm/100 cm2
S5000
- 4000
' 3000
2000 MDA
1000
1-11 1 111 1~II. M2I1 lil l Ijj. II11111 J 1 ,1I11 I 1 '1 1 - -H I II- I i
-1000
Surface
171 'D U:• o1,-.LN ,).. 1,V 101 k.IN V
I
Misc. Pipes and Penetrations Removable Beta Activity600
500
400
300
200
100
0
-100
Surface
172
MDA
REVISION 0
34
0
Measurements: 120 Mean: 9 dpm/100 cm2 Maximum: 102 dpm/100 cm2 Std Deviation: 15 dpm/100 cm2 95% CL on Mean: 12 dpm/100 cm2
J'J•:J:l• •; JWF'~l~ •=~l•J l~l~;IJ"•tU~lJ;~lJ~~rl=;I~ • • •~ l• ii•'r;ii;••HH•----------:i•I~~iif
/TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-22E Package 22
Removable Beta Activity
/
_ TECH RESEARCH REACTOR FINAL SURVEY REPORT
Figure 4-22F Package 22
Removable H-3 Activity
Misc. Pipes and Penetrations Removable H-3 Activity 4700
4300measurements: 30 4300-Mean: 210 dpm/100 d-2 Maximum: 650 dpm/100 cm2
3900 Std Deviation: 129 dpm/100 cm2 95 % CL on Mean: 264 dpm/100 cm2
S3500
- 3100
,e 2700
. 2300
S1900 1500
S1100
p4 700 300
_____"_ i__l_____ ,-_____________i____,__ ,i__ ______ _ ,!• • I• ;,1 •MDA
-100
Surface
173 1?T)VTQTC~ .1XT'- V Li 0~1
5.0 CONCLUSIONS
Based on the results of the final survey presented in Section 4, the Georgia Institute of Technology Research Reactor located at 900 Atlantic Drive in Atlanta, Georgia meets the requirements for release for unrestricted use. As a result, it is recommended that the NRC radioactive material license number R-97 be terminated.
6.0 REFERENCES
6.1 NES Inc., Georgia Institute of Technology Research Reactor Decommissioning
Plan, June 1998.
6.2 USNRC Regulatory Guide 1.86, Termination of Operating Licenses for Nuclear
Reactors.
6.3 USNRC NUREG/CR-5 849, Manual for Conducting Radiological Surveys in
Support of License Termination, Draft, June, 1992
6.4 Letter from GSFIC Project 1-47 Executive Engineer (CH2MHill) to IT Corporation, Response to letter dated April 5, 2000, Final Release Survey Plan Request for Complete, Definite, and Clear Instructions (Article E-3), April 18, 2000.
6.5 10 CFR19, Notices, Instructions, and Reports to Workers; Inspections
6.6 10 CFR20, Standards for Protection Against Radiation.
6.7 American National Standard Institute, ANSI N323-1978, Radiation Protection
Instrumentation Test and Calibration
6.8 American National Standard Institute, ANSI N42.17A- 1989, Performance
Specifications for Health Physics Instrumentation - Portable Instrumentation for Use in Normal Environmental Conditions
6.9 The IT Group, Quality Assurance Project Plan & Quality Assurance Procedures for the Georgia Institute of Technology Research Reactor Decommissioning Project
7.0 ATTACHMENTS
Attachment A Worksheets for Calculations of Site Specific Guideline Values
Attachment B Final Survey Packages 1 through 22
REVISION 0
FINAL SURVEY REPORTGA TECH RESEARCH REACTOR
174
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
Attachment A
Worksheets for Calculations of Site Specific Guideline Values
REVISION 0
FINAL SURVEY REPORTGA TECH RESEARCH REACTOR
ATTACHMENT A
Calculation of Site-Specific Guideline Values (SPGLs)
The equation used to calculate the site-specific guideline value for each of the three samples is:
F SPGL =
ZL 1
Where: F = The fraction of the radionuclide mix that is considered detectable, unitless.
fi = The relative fraction of radionuclide i in the mix, unitless
GL1 = The radionuclide specific guideline, dpm/100 cm 2 from
Table 2.1
Using this equation, a site-specific guideline value (SPGL) was calculated for both average total
activity and removable activity for each of three samples selected for 10 CFR Part 61 analysis.
Average SPGLs were then calculated based on the SPGLs obtained for each sample. The
calculated SPGLs are summarized in the table below.
Calculation of Site-Specific Guideline Values
rflescrintion
Calculated guideline value for average total activity
Sam pie GEL-1 Concrete under Reactor Vessel
1�
Activity ) (dDm/100cm)
. . . .ri . . •
1,500
Sample G Concret
Biomedica Pit
Activi (dpm/100
EL-2 - Sample GEL-3 e in Primary Resin
I Door Sam pie
ty 2 Activity 1cm ) (dpm/100cm
2
3,800 2,000
48
Average of Samples
GEL-i, 2, & 3
Activity (dpm/1OOcm 2
)
2,400
313Calculated guideline value for 104 688
removable activity
(
SITE SPECIFIC GUIDELINE, SPGL, BASED ON GEL-I (TOTAL ACTIVITY)
RADIONUCLIDE SPECIFIC GUIDELINE FOR H-3 AND Fe-55 RAISED TO 200,000 dpm/100 cmA2
SAMPLE GEL-1 (CONCRETE SAMPLE) COLLECTED UNDER VESSEL ON 1/12/00
NUCLIDE
H-3 Fe-55
Pu-239/240 U-233/234
U-238 Ni-59
Cs-134 Cs-137 Co-60 Eu-152 Eu-154 Mn-54
Ag-I 10m Zn-65 Sr-90 C-14 Ni-63 Tc-99
Act pCi/g
3.170E+04 1.670E+02
1.71 OE+00 1.650E+00
7.560E-01 1.21 OE+00 1.530E+02 7,040E+00 1.41 OE+00
7.350E-01 2.11 OE+02 6.930E+01 1.91 OE+00
3.232E+04
HALF-LIFE years
1.228E+01 2.700E+00 2.413E+04 1.592E+05 4.460E+09 7.500E+04 2.062E+00 3.017E+01 5.271 E+00 1.360E+01 8.800E+00 8.600E-01 6.800E-01 6.700E-01 2.860E+01 5.730E+03 1.001 E+02 2.130E+05
Detectable Y/N
N N N N Y N Y Y Y Y Y N Y N Y Y N Y
GL
2.OOOE+05 2.OOOE+05 1.000E+02 5.000E+03 5.OOOE+03 5.000E+03 5.OOOE+03 5.OOOE+03 5.OOOE+03 5.OOOE÷03 5.OOOE+03 5.OOOE+03 5.OOOE+03 5.OOOE+03 1.OOOE+03 5.000E+03 5.OOOE+03 5.OOOE+03
f
9,808E-01 5.167E-03 0.OOOE+00 5.291 E-05 5.105E-05 0.000E+00 2.339E-05 3.744E-05 4.734E-03 2.178E-04 4.363E-05 0.OOOE+00 0.OOOE+00 0.OOOE+00 2.274E-05 6.528E-03 2,144E-03 5.91 OE-05
9,999E-01
SPGL 1.516E+03
F
5.106E-05
2,339E-05 3.744E-05 4.734E-03 2.178E-04 4.363E-05
0.000E+00
2.274E-05 6.529E-03
5.91 OE-05
1 .172E-02
f/G L
4.904E-06 2.584E-08 0.000E+00 1.058E-08 1.021E-08 0.OOOE+00 4.678E-09 7.488E-09 9.468E-07 4.356E-08 8.725E-09 0.000E+00 0.OOOE+00 0.000E+00 2.274E-08 1.306E-06 4.288E-07 1 .182E-08
7.731 E-06
(
SITE SPECIFIC GUIDELINE, SPGL, BASED ON GEL-2 (TOTAL ACTIVITY)
RADIONUCLIDE SPECIFIC GUIDELINE FOR H-3 AND Fe-55 RAISED TO 200,000 dpm/100 cm^2
SAMPLE GEL-2 (CONCRETE SAMPLE) COLLECTED IN MEDICAL DOOR TO PIT ON 1/12/00
NUCLIDE Act HALF-LIFE Detectable GL f F f/GL pCi/g years Y/N
H-3 1.390E+02 1.228E+01 N 2.OOOE+05 1.382E-01 6.909E-07 Fe-55 4.680E+02 2,700E+00 N 2.000E+05 4.652E-01 2,326E-06
Pu-239/240 < 2.413E+04 N 1.000E+02 0.000E+00 0,OOOE+00 U-233/234 9.520E-01 1.592E+05 N 5.OOOE+03 9.463E-04 1.893E-07
U-238 6.850E-01 4.460E+09 Y 5.OOOE+03 6.809E-04 6.809E-04 1.362E-07 Ni-59 < 7.500E+04 N 5.OOOE+03 0.OOOE+00 0.OOOE+00
Cs-134 < 2.062E+00 Y 5.000E+03 0.OOOE+00 0.OOOE+00 0.000E+00 Cs-137 2.460E+00 3.017E+01 Y 5,000E+03 2.445E-03 2.445E-03 4.891E-07 Co-60 2.340E+02 5.271E+00 Y 5.OOOE+03 2.326E-01 2.326E-01 4,652E-05 Eu-152 1.460E+00 1.360E+01 Y 5.000E+03 1.451 E-03 1,451 E-03 2,903E-07 Eu-154 < 8.800E+00 Y 5.OOOE+03 0.000E+00 0.OOOE+00 0.OOOE+00 Mn-54 < 8.600E-01 N 5.OOOE+03 0.000E+00 0.000E+00
Ag-110m < 6.800E-01 Y 5.OOOE+03 0.OOOE+00 0.OOOE+00 O.OOOE+00 Zn-65 < 6.700E-01 N 5.OOOE+03 0.000E+00 0,OOOE+00 Sr-90 < 2.860E+01 Y 1.OOOE+03 0.OOOE+00 0.OOOE+00 0.OOOE+00 C-14 7.740E+01 5.730E+03 Y 5.OOOE+03 7.694E-02 7.694E-02 1.539E-05 Ni-63 8.200E+01 1.001 E+02 N 5,OOOE+03 8,151 E-02 1.630E-05 Tc-99 < 2.130E+05 Y 5.OOOE+03 0.OOOE+00 0.OOOE+00 0.OOOE+00
1.006E+03 1.OOOE+00 3.141 E-01 8,233E-05
SPGL 3.815E+03
l,
(
SITE SPECIFIC GUIDELINE, SPGL, BASED ON GEL-3 (TOTAL ACTIVITY)
RADIONUCLIDE SPECIFIC GUIDELINE FOR H-3 AND Fe-55 RAISED TO 200,000 dpm/100 cmA2
SAMPLE GEL-3 (RESIN SAMPLE) FROM PRIMARY COOLANT SYSTEM COLLECTED 1/12/00
NUCLIDE Act HALF-LIFE Detectable GL f F f/GL pCi/g years Y/N
H-3 4.880E+07 1.228E+01 N 2.000E+05 9.827E-01 4.913E-06 Fe-55 2.020E+03 2.700E+00 N 2.OOE+05 4.068E-05 2.034E-10
Pu-239/240 9.460E-01 2.413E+04 N 1.OOOE+02 1.905E-08 1.905E- 10 U-233/234 6.860E-01 1.592E+05 N 5,OOOE+03 1.381 E-08 2.763E-1 2
U-238 < 4.460E+09 Y 5.OOOE+03 0.OOOE+00 0.OOOE+00 0.OOOE+00 Ni-59 2.690E+01 7.500E+04 N 5.OOOE+03 5.417E-07 1,083E- 10
Cs-134 1.700E+01 2.062E+00 Y 5.OOOE+03 3.423E-07 3.423E-07 6.847E- 11 Cs-137 4.220E+03 3.017E+01 Y 5.OOOE+03 8,498E-05 8.498E-05 1,700E-08 Co-60 1.220E+04 5.271E+00 Y 5.OOOE+03 2.457E-04 2.457E-04 4.913E-08 Eu-152 1.310E+01 1.360E+01 Y 5.OOOE+03 2.638E-07 2.638E-07 5.276E-11 Eu-1 54 < 8.800E+00 Y 5.OOOE+03 0.OOOE+00 O.OOOE+00 0.OOOE+00 Mn-54 5.330E+01 8.600E-01 N 5.OOOE+03 1.073E-06 2.147E-10
Ag-110m 1.220E+02 6.800E-01 Y 5.OOOE+03 2.457E-06 2.457E-06 4.913E-10 Zn-65 1.500E+02 6.700E-01 N 5.OOOE+03 3.021 E-06 6.041 E-10 Sr-90 6.570E+03 2.860E+01 Y 1.OOOE+03 1.323E-04 1.323E-04 1,323E-07 C-14 8.320E+05 5.730E+03 Y 5.OOOE+03 1.675E-02 1.675E-02 3.351E-06 Ni-63 •4.800E+03 1.001 E+02 N 5.OOOE+03 9.666E-05 1.933E-08 Tc-99 1.140E+02 2.130E+05 Y 5.OOOE+03 2.296E-06 2.296E-06 4.591E-10
4.966E+07 1.OOOE+00 1.722E-02 8.484E-06
SPGL 2.030E+03
"( (/
SI I E SPECIFIC GUIDELINE, SPGL, BASED ON GEL-I (REMOVABLE ACTIVITY)
RADIONUCLIDE SPECIFIC GUIDELINE FOR H-3 AND Fe-55 RAISED TO 10,000 dpm/100 cmA2
SAMPLE GEL-1 COLLECTED UNDER VESSEL ON 1/12/00
NUCLIDE Act HALF-LIFE Detectable GL f F f/GL
pCi/g years Y/N
H-3 3.170E+04 1.228E+01 N 1.000E+04 9.808E-01 9.808E-05
Fe-55 1.670E+02 2.700E+00 N 1.000E+04 5.167E-03 5.167E-07
Pu-239/240 < 2.413E+04 N 2.000E+01 0.000E+00 0.000E+00
U-233/234 1.710E+00 1.592E+05 N 1.OOOE+03 5.291 E-05 5.291 E-08
U-238 1.650E+00 4.460E+09 Y 1.OOOE+03 5.105E-05 5.105E-05 5.105E-08
Ni-59 < 7.500E+04 N 1.OOOE+03 0.OOOE+00 0.OOOE+00
Cs-134 7.560E-01 2.062E+00 Y 1.OOOE+03 2.339E-05 2.339E-05 2.339E-08
Cs-137 1.210E+00 3.017E+01 Y 1.OOOE+03 3.744E-05 3.744E-05 3.744E-08
Co-60 1.530E+02 5.271 E+00 Y 1.000E+03 4.734E-03 4.734E-03 4.734E-06
Eu-152 7.040E+00 1.360E+01 Y 1.000E+03 2.178E-04 2.178E-04 2.178E-07
Eu-1 54 1.41 OE+00 8.800E+00 Y 1.000E+03 4.363E-05 4.363E-05 4.363E-08
Mn-54 < 8.600E-01 N 1.000E+03 0.OOOE+00 0.000E+00
Ag-110m < 6.800E-01 Y 1.000E+03 0.000E+00 0.OOOE+00 0.000E+00
Zn-65 < 6.700E-01 N 1.000E+03 0.000E+00 0.000E+00
Sr-90 7.350E-01 2.860E+01 Y 2.OOOE+02 2.274E-05 2.274E-05 1.137E-07
C-14 2.11OE+02 5.730E+03 Y 1.OOOE+03 6.528E-03 6.528E-03 6.528E-06
Ni-63 6.930E+01 1.001 E+02 N 1.000E+03 2.144E-03 2.144E-06
Tc-99 1.910E+00 2.130E+05 Y 1.000E+03 5.910E-05 5.910E-05 5.910E-08
3.232E+04 9.999E-01 1.172E-02 1.126E-04
SPGL 1.041 E+02
b, E SPECIFIC GUIDELINE, SPGL, BASED ON GEL-2 (REMOVABVLr- ACTIVITY)
RADIONUCLIDE SPECIFIC GUIDELINE FOR H-3 AND Fe-55 RAISED TO 10,000 dpm/100 cmA2
SAMPLE GEL-2 COLLECTED AT DOOR TO PIT ON 1/12/00
NUCLIDE Act HALF-LIFE Detectable GL f F f/GL pCi/g years Y/N
H-3 1.390E+02 1.228E+01 N 1.000E+04 1.382E-01 1.382E-05 Fe-55 4.680E+02 2.700E+00 N 1.OOOE+04 4.652E-01 4.652E-05
Pu-239/240 < 2.413E+04 N 2.OOOE+01 0.000E+00 O.000E+00 U-233/234 9.520E-01 1.592E+05 N 1.000E+03 9.463E-04 9.463E-07
U-238 6.850E-01 4.460E+09 Y 1.000E+03 6.809E-04 6.809E-04 6.809E-07 Ni-59 < 7.500E+04 N 1.000E+03 0.000E+00 0.OOOE+00
Cs-1 34 < 2.062E+00 Y 1.000E+03 0.OOOE+00 O.OOOE+00 0.000E+00 Cs-1 37 2.460E+00 3.017E+01 Y 1.000E+03 2.445E-03 2.445E-03 2.445E-06 Co-60 2.340E+02 5.271 E+00 Y 1.000E+03 2.326E-01 2.326E-01 2.326E-04 Eu-152 1.460E+00 1.360E+01 Y 1.000E+03 1.451 E-03 1.451 E-03 1.451 E-06 Eu-1 54 < 8.800E+00 Y 1.000E+03 0.OOOE+00 0.000E+00 0.000E+00 Mn-54 < 8.600E-01 N 1.000E+03 0.OOOE+00 0.OOOE+00
Ag-110m < 6.800E-01 Y 1.OOOE+03 0.OOOE+00 0.000E+00 0.OOOE+00 Zn-65 < 6.700E-01 N 1.000E+03 0.OOOE+00 0.OOOE+00 Sr-90 < 2.860E+01 Y 2.OOOE+02 0.OOOE+00 0.000E+00 0.000E+00 C-14 7.740E+01 5.730E+03 Y 1.000E+03 7.694E-02 7.694E-02 7.694E-05 Ni-63 8.200E+01 1.001 E+02 N 1.000E+03 8.151 E-02 8.151 E-05 Tc-99 < 2.130E+05 Y 1.000E+03 0.000E+00 0.OOOE+00 0.OOOE+00
1.006E+03 1.OOOE+00 3.141 E-01 4.569E-04
SPGL 6.875E+02
/(
E SPECIFIC GUIDELINE, SPGL, BASED ON GEL-3 (REMOVABLt ACTIVITY)
RADIONUCLIDE SPECIFIC GUIDELINE FOR H-3 AND Fe-55 RAISED TO 10,000 dpm/100 cmA2
SAMPLE GEL-3 RESIN SAMPLE COLLECTED 1/12/00
NUCLIDE Act HALF-LIFE Detectable GL f F f/GL pCi/g years Y/N
H-3 4.880E+07 1.228E+01 N 1.000E+04 9.827E-01 9.827E-05 Fe-55 2.020E+03 2.700E+00 N 1.000E+04 4.068E-05 4.068E-09
Pu-239/240 9.460E-01 2.413E+04 N 2.OOOE+01 1.905E-08 9.525E-10 U-233/234 6.860E-01 1.592E+05 N 1.OOOE+03 1.381 E-08 1.381 E-1 1
U-238 < 4.460E+09 Y 1.000E+03 0.000E+00 0.OOOE+00 0.OOOE+00 Ni-59 2.690E+01 7.500E+04 N 1.000E+03 5.417E-07 5.417E-10
Cs-134 1.700E+01 2.062E+00 Y 1.OOOE+03 3.423E-07 3.423E-07 3.423E-10 Cs-137 4.220E+03 3.017E+01 Y 1.OOOE+03 8.498E-05 8.498E-05 8.498E-08 Co-60 1.220E+04 5.271 E+00 Y 1.OOOE+03 2.457E-04 2.457E-04 2.457E-07 Eu-152 1.310E+01 1.360E+01 Y 1.OOOE+03 2.638E-07 2.638E-07 2.638E-10 Eu-154 < 8.800E+00 Y 11.000E+03 0.OOOE+00 0.000E+00 0.OOOE+00 Mn-54 5.330E+01 8.600E-01 N 1.000E+03 1.073E-06 1.073E-09
Ag-1I0m 1.220E+02 6.800E-01 Y 1.OOOE+03 2.457E-06 2.457E-06 2.457E-09 Zn-65 1.500E+02 6.700E-01 N 1.OOOE+03 3.021E-06 3.021 E-09 Sr-90 6.570E+03 2.860E+01 Y 2.OOOE+02 1.323E-04 1.323E-04 6.615E-07 C-14 8.320E+05 5.730E+03 Y 1.000E+03 1.675E-02 1.675E-02 1.675E-05 Ni-63 4.800E+03 1.001 E+02 N 1.OOOE+03 9.666E-05 9.666E-08 Tc-99 1.140E+02 2.130E+05 Y 1.000E+03 2.296E-06 2.296E-06 2.296E-09
1.000E+03 4.966E+07 1.OOOE+00 1.722E-02 1.161 E-04
SPGL 1.483E+02
ATTACHMENT A, Page 2
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT
Attachment B
Final Survey Packages 1 through 22
REVISION 0
GA TECH RESEARCH REACTOR FINAL SURVEY REPORT