Project Schedule
CPTC Modernization 3Q 2016 – 2Q 2019
Concourse T North Extension 2Q 2017 – 1Q 2022
Concourse G 3Q 2017 – 1Q 2027
Concourse D TBD
Key Projects Project Schedule
Taxiway Replacement – 2016 1Q 2017 – 1Q 2018
Runway 9L End-Around Taxi-way
1Q 2018 – 1Q 2021
Taxiway/Runway 9L Pave-ment Replacement
1Q 2018 – 1Q 2019
Ground Transportation Modi-fications (CV Hold Lot)
2Q 2016 – 4Q 2017
Cargo 2A/2B Site Preparation 2Q 2017 – 2Q 2019
Key Projects Project Schedule
ATL West Parking Deck 2Q 2017 – 1Q 2019 West Curb Relocation 3Q 2017 – 3Q 2018
Plane Train Turnback Exten-sion Phase 1 / West Curb
3Q 2017 – 2Q 2019
Sullivan Road Park-Ride Lot 3Q 2017 – 3Q 2018
SUPPORT FACILITIES
HOTEL
Key Projects
Hotel
Mixed Use Commercial Complex
Travel Plaza
Key Projects
Fire Station #40 1Q 2017 – 3Q 2018
Building Renewal - Replacement (Non-CPTC)
3Q 2017 – 4Q 2035
Aviation Maintenance Complex Consolidation
TBD