1
Parker-Davis Project Fiscal Year 2018 Rates & Charges
June 14, 2017
Florence Brooks
Public Utilities Specialist
Agenda
• FY 2017 Rate Calculation Summary
• FY 2018 Standard Calculation Parameters
• FY 2018 Charge Determinates • Generation:
• Purchase Power
• Transmission: • WAPA O&M • Other Revenue • Reservations
• Preliminary FY 2018 Charges
• Optional Restructuring of Principal (Transmission)
• Next Steps and Contact Information
2 PDP FY18 Rates Presentation
FY 2017 Rate Calculation Summary
Generation Charges
Purchase Power and Wheeling projection increased from $1m to $2m, resulting in an 8% increase to the composite generation charge
Transmission Charges
Transmission costs increased 5%, while Other Revenue decreased 15%.
We reduced a 12% transmission charge increase to 7% by deferring 50% of the FY17 principal payment to future years
3 PDP FY18 Rates Presentation
Standard Calculation Parameters
• Actual work plans are used for O&M expenses when available. Work plans are escalated for inflation in remaining years of cost evaluation period (rate window)
• Ten-Year Plan information from WAPA and Reclamation is used to project capital costs
• Costs not readily identified as generation or transmission are allocated via the Cost Apportionment Study
• Transmission and generation sales projections are based on contractual values
4 PDP FY18 Rates Presentation
FY18 Generation Charge Determinates
(Purchase Power)
• Purchase power is difficult to project given the volatility of hydrology and energy pricing
• We take a minimal approach with projections to prevent adverse rate impacts
• While we will continue with the minimal approach, we are increasing our projections to more closely align them with recent actual expenses
5 PDP FY18 Rates Presentation
• Beginning in FY17, we agreed to increase purchase power projections by $340k per year until $3m is reached in FY 2022:
• Actual purchase power costs that exceed projections impact the carryover available in future fiscal years
6 PDP FY18 Rates Presentation
2017 2018 2019 2020 2021 2022
Annual PPW $1.3m $1.7m $2.0m $2.4m $2.7m $3.0m
5-Yr Avg in Rate $2.0m $2.4m $2.6m $2.8m $3.0m $3.0m
FY18 Generation Charge Determinates
(Purchase Power)
FY18 Generation Charge Determinates
(Purchase Power)
7 PDP FY18 Rates Presentation
Year Expenses
2012 $1.0m
2013 $3.8m
2014 $3.3m
2015 $5.2m
2016 $3.6m
2017 (Rate) $1.3m
Prelim 2018 $1.7m
FY18 Generation Charge Determinates
Average Annual Expenses (in millions)
8 PDP FY18 Rates Presentation
FY17-21 FY18-22 Change
WAPA O&M $2.1 $2.3 $0.2
CME & Western General $0.4 $0.2 $(0.2)
BOR O&M $10.3 $10.7 $0.4
Purchase Power $2.0 $2.3 $0.3
BOR Replacements $2.6 $1.5 $(1.1)
P&I $0.1 $0.1 -
Total $17.5 $17.1 $(0.4)
FY18 Generation Charge Determinates
Average Annual Expenses (in millions)
9 PDP FY18 Rates Presentation
CME/Western
General$0.2
PurchasePower$2.3
WAPA
O&M$2.3
P&I$0.1
BOR O&M$10.7
BOR Replacements$1.5
FY18 Generation Charge Determinates
Average Annual Other Revenue, Carryover, Revenue Requirement and Reservations ($ in millions)
10 PDP FY18 Rates Presentation
FY17-21 FY18-22 Change
Other Revenue $0.3 $0.3 $(0.0)
Carryover $1.5 $0.7 $(0.8)
Total $1.8 $1.0 $(0.8)
Revenue Requirement $15.7 $16.1 $0.4
Reservations (GWh) 1,425 1,425 -
FY18 Transmission Charge Determinates
(WAPA’s O&M)
11 PDP FY18 Rates Presentation
FY17-21 FY18-22 Change
WAPA O&M $28.7 $33.1 $4.4
Western General $4.5 $1.5 $(3.0)
CME & Multi-Project $(1.2) $(1.2) -
Total $32.0 $33.4 $1.4
Average Annual Expenses (in millions)
• Vegetation Management is estimated to be $3.9m in FY18 & FY19 with $1m in the out years
• Direct charging of Overhead
FY18 Transmission Charge Determinates
(Other Revenue) • Other Revenues are composed of all transmission
related sales except for NITS and firm point-to-point
• Downward trend primarily due to decreases in short-term and non-firm sales
• Although we need to adjust our projections, we need a balanced approach similar to purchase power
• Reduce Other Revenue by approximately $0.7m a year to $7.6m and will reassess the projection each year
• Projections are higher than recent actuals:
12 PDP FY18 Rates Presentation
FY18 Transmission Charge Determinates
(Other Revenue)
13 PDP FY18 Rates Presentation
Year Other Rev
2012 $12.5m
2013 $9.0m
2014 $8.0m
2015 $7.4m
2016 $5.3m
2017 (Rate) $8.3m
Prelim 2018 $7.6m
FY18 Transmission Charge Determinates
(Reservations)
14 PDP FY18 Rates Presentation
Average FY17-21 FY18-22 Change
Reservations (MW) 2804 2612 (192)
• South Point reduction of 285 MW
• BCP Post 2017 net reduction
• Assumes reservation increase & recovery in FY2021
FY18 Transmission Charge Determinates
Average Annual Expenses (in millions)
15 PDP FY18 Rates Presentation
FY17-21 FY18-22 Change
WAPA O&M $28.7 $33.1 $4.4
Western General $4.5 $1.5 $(3.0)
CME & Multi-Project $(1.2) $(1.2) -
Purchase Power/Wheeling $1.9 $1.9 -
P&I $27.4 $28.4 $1.0
Total $61.3 $63.7 $2.4
FY18 Transmission Charge Determinates
Average Annual Expenses (in millions)
16 PDP FY18 Rates Presentation
WAPA O&M
$33.1 P&I
$28.4
Western General
$1.5 Purchase
Power$1.9
FY18 Transmission Charge Determinates
Average Annual Other Revenue, Carryover, and Reservations ($ in millions)
17 PDP FY18 Rates Presentation
FY17-21 FY18-22 Change
Other Revenue $8.6 $7.6 $(1.0)
Carryover $4.6 $2.3 $(2.3)
Total $13.2 $9.9 $(3.3)
Revenue Requirement $48.1 $53.8 $5.7
Reservations (MW) 2,804 2,612 (192)
Preliminary FY 2018 Charges
18 PDP FY18 Rates Presentation
FY17 (current)
FY18 (proposed) Change
Energy (mills/kWh) 5.52 5.65 0.13 2.4%
Capacity (kW-Month) $2.42 $2.47 $0.05 2.1%
Composite w/o Tran (mills/kWh)
11.03 11.30 0.27 2.4%
Firm Tran (kW-Month) $1.43 $1.61 $0.18 12.6%
NITS Revenue Requirement
$46.2m $45.5m $(0.7) 1.5%
Optional Restructuring of Principal
• Last year, we deferred 50% of the planned FY17 principal payment to mitigate a transmission charge increase from 12% to 7%
• Although a short-term strategy, we can again defer the upcoming principal payment and spread that principal across future periods
• A 100% deferral of principal would cost approximately $5.5m over the 40-50 year repayment period but mitigate the increase to the FY18 charge:
19 PDP FY18 Rates Presentation
FY18 Charge (proposed)
Change from FY17 Charge
(kW-Month)
100% Principal Payment $1.61 $0.18 12.6%
0% Principal Payment $1.46 $0.03 2.1%
Questions/Thoughts
20 PDP FY18 Rates Presentation
Next Steps
• Information regarding the P-DP rates and charges to be posted on WAPA’s website:
https://www.wapa.gov/regions/DSW/Rates/Pages/Parker-Davis-New-format.aspx
• Generation costs finalized at Advancement of Funds Annual Funding Board - 7/20/2017
• Proposed charges will be finalized in July/August and become effective for the October 2017 service month
21 PDP FY18 Rates Presentation
WAPA Contacts
Florence Brooks
602-605-2479
Scott Lund
602-605-2442
22 PDP FY18 Rates Presentation