Parametric Estimation for reliable IT Project Estimates Frank Vogelezang Manager Pricing Office –...

17
Parametric Estimation for reliable IT Project Estimates Frank Vogelezang Manager Pricing Office – Ordina MPC Member – COSMIC

Transcript of Parametric Estimation for reliable IT Project Estimates Frank Vogelezang Manager Pricing Office –...

Page 1: Parametric Estimation for reliable IT Project Estimates Frank Vogelezang Manager Pricing Office – Ordina MPC Member – COSMIC.

Parametric Estimationfor reliable IT Project Estimates

Frank VogelezangManager Pricing Office – Ordina MPC Member – COSMIC

Page 2: Parametric Estimation for reliable IT Project Estimates Frank Vogelezang Manager Pricing Office – Ordina MPC Member – COSMIC.

IntroductionFrank Vogelezang

Pricing Office- Setting commercial price for our service offerings- Challenging internal estimates with parametrics

2 17

120 km new railway

Extending the supportfor the method byby targeted guidelines and improved documentation

Page 3: Parametric Estimation for reliable IT Project Estimates Frank Vogelezang Manager Pricing Office – Ordina MPC Member – COSMIC.

AgendaParametric Estimation for reliable IT Project Estimates

Estimating

Getting a grip on IT cost and schedule

Functional Size

Translating requirements to manageable numbers

The power of parametrics

Building on proven reference datafor cost and schedule estimationfrom internal or external sources

3 17

Page 4: Parametric Estimation for reliable IT Project Estimates Frank Vogelezang Manager Pricing Office – Ordina MPC Member – COSMIC.

EstimatingGetting a grip on IT cost and schedule

Page 5: Parametric Estimation for reliable IT Project Estimates Frank Vogelezang Manager Pricing Office – Ordina MPC Member – COSMIC.

Estimating IT projectsTwo essential routes

Objective

Size

Effort

The Expert

Parametrics

5 17

Schedule & Cost

Page 6: Parametric Estimation for reliable IT Project Estimates Frank Vogelezang Manager Pricing Office – Ordina MPC Member – COSMIC.

Definition of an estimateGetting grip on IT cost and schedule

An estimate is an analytical and unbiased prediction of how long it takes and what it will cost

The bias comes from the interplay with targets, commitments and plans

6 17

Page 7: Parametric Estimation for reliable IT Project Estimates Frank Vogelezang Manager Pricing Office – Ordina MPC Member – COSMIC.

Viable estimation = Reliable estimatesGetting grip on IT cost and schedule

Analytical Can you verify in some way what your experts tell you?

Unbiased Will an expert give the same answer twice?

Prediction 100% certainty costs too much time and resources!

7 17

Page 8: Parametric Estimation for reliable IT Project Estimates Frank Vogelezang Manager Pricing Office – Ordina MPC Member – COSMIC.

Functional SizeTranslating requirements to manageable numbers

2.7

M

Page 9: Parametric Estimation for reliable IT Project Estimates Frank Vogelezang Manager Pricing Office – Ordina MPC Member – COSMIC.

Functional Size : Function Point AnalysisTranslating requirements to manageable numbers

FPA stands for FunctionPointAnalysis

What the software should be able to do (functionality)Functionexpressed in a number Pointbased on an objectively described method Analysis

Something intangible like functionality becomes a physical number that can be used for calculations

Five ISO/IEC standards: COSMIC, FiSMA, IFPUG, Mk II & NESMA

9 17

Page 10: Parametric Estimation for reliable IT Project Estimates Frank Vogelezang Manager Pricing Office – Ordina MPC Member – COSMIC.

Exit (X)

COSMIC Function Point Analysis : ISO/IEC 19761Translating requirements to manageable numbers

Entry (E)

Write (W) Read (R)

10 17

Page 11: Parametric Estimation for reliable IT Project Estimates Frank Vogelezang Manager Pricing Office – Ordina MPC Member – COSMIC.

The power of parametricsBuilding on proven reference data

Page 12: Parametric Estimation for reliable IT Project Estimates Frank Vogelezang Manager Pricing Office – Ordina MPC Member – COSMIC.

Parametric reality checkBuilding on proven reference data

Paul Masson’sLaw

Parkinson’sLaw

Brooks’Law

Minimal time

Optimal effort

Schedule

Effor

t / C

ost

RealisticProductivity

12 17

Page 13: Parametric Estimation for reliable IT Project Estimates Frank Vogelezang Manager Pricing Office – Ordina MPC Member – COSMIC.

How much certainty do you needBuilding on proven reference data

Prob

abili

ty

Schedule / Cost

0%

€ 750

.000

50%

€ 1.

000.

000

75% €

1.25

0.00

0

90% €

1.90

0.00

0First likely option, overly optimistic

50/50 median result, for a balanced portfolio

75% for fixed price projects

90% for safety critical systems

13 17

Page 14: Parametric Estimation for reliable IT Project Estimates Frank Vogelezang Manager Pricing Office – Ordina MPC Member – COSMIC.

Keep track of the actual projectWhere will it end?

Schedule Variance

Time Variance

Cost VarianceBudget Variance

Actual costEarned value

14 17

Page 15: Parametric Estimation for reliable IT Project Estimates Frank Vogelezang Manager Pricing Office – Ordina MPC Member – COSMIC.

Forecast of the outcome with parametricsBuilding on proven reference data for cost and schedule estimation

ScheduleSlippage

CostOverrun

Actual costEarned valueTotal cost (forecast)Total value (planned)

15 17

Page 16: Parametric Estimation for reliable IT Project Estimates Frank Vogelezang Manager Pricing Office – Ordina MPC Member – COSMIC.

The power of parametricsViable estimates and cost-effective projects

Estimate & Plan Create a baseline parametric estimate Develop a Project Plan

Monitor and Control Document actuals Create forecast based on parametrics Re-estimate and establish new baseline

Measure and Analyse Establish variances for the whole project Determine parametric parameters Incorporate this knowledge in future estimates and plans

Estimate&

Plan

Actuals

Baseline

Baseline(s) vsFinal Actuals

Experience &Knowledge

Measure&

Analyse

Monitor&

Control

16 17

Page 17: Parametric Estimation for reliable IT Project Estimates Frank Vogelezang Manager Pricing Office – Ordina MPC Member – COSMIC.

17

[email protected]

ThePriceofIT.blogspot.com

@FrankVogelezang

FrankVogelezang

www.linkedin.com/in/frankvogelezang

www.cosmicon.com