Paper on Supercritical Technology for Power Generation

download Paper on Supercritical Technology for Power Generation

of 18

Transcript of Paper on Supercritical Technology for Power Generation

  • 8/12/2019 Paper on Supercritical Technology for Power Generation

    1/18

  • 8/12/2019 Paper on Supercritical Technology for Power Generation

    2/18

    TABLE OF CONTENTS

    Overview 1

    Indian Energy Scenario .....................................................................................................................................................1Capacity Addition in India ...............................................................................................................................................1

    The way forward...............................................................................................................................................................2

    Supercritical Technology..................................................................................................................................................2

    Purpose of this Paper .......................................................................................................................................................2

    About Supercritical Technology 3

    Background ........................................................................................................................................................................3

    Supercritical technology in Power Generation .............................................................................................................4

    In order to develop additional power generation capacity, the existing domestic manufacturing capacityneeds to be up-graded and enhanced. For the reasons stated above there is a preference for super-critical

    technology in the country................................................................................................................................................4

    About 60% of coal based capacity in XII Plan and 100% capacity in XIII Plan is planned to be based on

    supercritical technology. Table below gives the projected capacity addition based on supercritical

    technology up to 13th Plan: ............................................................................................................................................4

    Expected Efficiency Range for Supercritical Units ........................................................................................................4

    Methodology for Induction of Supercritical Technology in India ..............................................................................5

    The Implementation of Supercritical Technology.........................................................................................................6

    Supercritical Projects Planned ....................................................................................................................................6

    Supercritical Projects under Execution .....................................................................................................................7

    Manufacturing Facilities for Supercritical technology in India ................................................................................7

    Domestic Manufacturers ............................................................................................................................................7

    International manufacturers ........................................................................................................................................7

    1. Turbine Manufacturing: ................................................................................................................................................9

    2.Boiler Manufacturing: ..................................................................................................................................................13

    Conclusion 15

    Contact Us 16

  • 8/12/2019 Paper on Supercritical Technology for Power Generation

    3/18

    Supercritical Technology:The dawn of a new era in power generation

    December 2009 Page 1 of 16

    OVERVIEW

    Indian Energy Scenario

    India is one of the fastest growingeconomies of the world today with an ever-rising energy requirement, needed to sustainits momentum of growth and enable its

    emergence on the global platform. Itsenergy requirement has almost doubled inthe past decade and it exhibits no signs ofthis trend reversing in the coming decades.

    Source: Infraline

    The installed power generation capacity ofIndia stands above 1,51,070 MW, yet thepower deficit continues being very high.

    According to CEA reports, the power deficitfor the month of July, 2009 was 12,983 MW(11.3% of the overall requirement).

    For an economy on the path ofdevelopment, reducing consumption alone isnot a feasible solution especially when theper capita consumption is deplorably low at704 kWh

    1, less than one third of the World

    average.

    Hence, increasing present generationcapacity as quickly as possible through rapidcapacity addition is the only solution forbridging this demand and supply gap.

    1For 2007-08, CEA

    Capacity Addition in India

    The Government is making continuousefforts to meet the growing requirement forpower through capacity additions. Each fiveyear plan foresees achievement of a setlevel of capacity addition. These targets areset by fuel source for central, state andprivate sectors. Presently coal is thedominant fuel source and central sector hasmade the maximum contribution to the

    capacity addition.

    Over the past, the government has oftenfailed to achieve the targets fixed for theseplans. The 10

    thPlan (2002-07) is one such

    case in point where only 21,000 MW out of atarget of about 41,000 mw additionalcapacity was achieved.

  • 8/12/2019 Paper on Supercritical Technology for Power Generation

    4/18

    Supercritical Technology:The dawn of a new era in power generation

    December 2009 Page 2 of 16

    In the ongoing 11th Plan which is ending onMarch 31, 2012, only 19,000 MW (24%) ofthe capacity addition target of 78,700 MWhas been added despite the plan havingcrossed the half way mark on November2009.

    The analysis of this lacklustre performanceduring the 10

    th plan indicates that the

    domestic equipment manufacturers cannothandle a capacity of more than 20,000 MWin a five year period. This inadequacy ofproduction capacity was found to be themajor reason for delay and hence shortfall incapacity addition. Though BHEL, theprimary domestic power equipmentmanufacturer, is in the process ofaugmenting its capacity to about 10,000 MWper annum (of which a capacity base of8,000 MW per year was achieved in thebeginning of 2008), it alone cannot bridgethe gap. A lot more is required to be done inthis regard.

    The way forward

    The Indian Power Generation sector isplagued by two major problems- slow paceof capacity addition and inefficientgenerating units. The first can be attributedto inadequate equipment manufacturingcapacity in the country and problems in

    securing fuel supply and the second to highash content of domestic coal which is thedominant fuel source in the present fuel mixfor power generation and use of sub criticaltechnology which is a relatively inefficienttechnology.

    Incremental capacity is crucial to Indiasdevelopment plan and hence the obstaclesin achieving the desired performance needto be overcome. Capacity additions throughprogressively larger generation units whichwould help attain economies of scale and

    time, and use of more efficient technologieslike supercritical technology is the only wayforward. This has been recognized by theGovernment as well and is reflected by itsplans for manufacturing indigenoussupercritical technology and developingUltra Mega Power Plants for introducing thesame.

    Supercritical Technology

    Coal having a contribution of over 50% inthe total installed capacity of India and over80% in the actual generation, assumes avery important role in Indian power sector.

    Though coal is Indias most abundant fuelresource, its reserves are limited. To usethis resource most wisely and to reduce CO2emissions which cause global warming,technology enabling higher generatingefficiency is required. Supercriticaltechnology is one such technology.

    Supercritical (SC) power plants operate attemperatures and pressures above thecritical point of water, i.e. above thetemperature (373 Deg C) and pressure(225 kg/cm

    2) at which the liquid and gas

    phases of water coexist in equilibrium, atwhich point there is no difference betweenwater gas and liquid water. This results inhigher efficiencies.

    The efficiency of supercritical units rangesfrom 37-40% depending on design,operating parameters and coal type which ismore efficient than sub critical by about 2-3percentage points. For a typical 700 MWplant, one percentage point efficiency gainresults in reduction of 2.4% in fuelconsumption implying a substantial

    reduction in fuel costs, quantity used andCO2emissions over a 30 year period.

    Presently all the coal based units operatingin the country are based on sub-criticaltechnology. It has been projected that byconstructing power plants based on supercritical units, CO2 emissions could bereduced significantly by 2025.

    Purpose of this Paper

    Supercritical technology is being inducted inthe country through a number ofsupercritical units that are underconstruction. In 2008, the Government ofIndia decided upon bulk tendering by NTPCand DVC as the methodology for awardingunits of Supercritical power plants. Theseplants are typically large with minimum unitcapacity of 660 mw. One of the primaryobjectives of introducing Ultra Mega Power

  • 8/12/2019 Paper on Supercritical Technology for Power Generation

    5/18

    Supercritical Technology:The dawn of a new era in power generation

    December 2009 Page 3 of 16

    Plants was to pave the way for progressiveindigenization of supercritical technology.

    Several companies expressed interest inaugmenting or setting up manufacturingfacilities in the country for supercritical units.

    The list included Bhel for Boiler and TurbineGenerator (BTG), Ansaldo Caldie GB(Boiler), L&TMHI (Boiler and TG),ToshibaJSW (TG) and Alstom-BharatForge (TG). Larsen & Toubro already had atie-up with Mitsubishi Heavy Industries of

    Japan for manufacturing supercritical steamturbines and generators in India.

    This paper attempts to evaluate the impactof supercritical technology in power sectoralong with the role it is likely to assume in

    the future. It contains a summary of thestatus of manufacturing facilities in India forsupercritical equipments (boilers, turbinesand generators) and Indias preparednessfor implementing the same in generation ofpower.

    A

    BOUT

    S

    UPERCRITICAL

    T

    ECHNOLOGY

    Background

    The 1992 climate treaty made it clear that,while the developed nations must take theresponsibility for the current buildup ofgreenhouse gases in the atmosphere andnecessarily take the lead in combatingclimate change; developing nations alsohave a role to play in protecting the globalclimate.

    In 1997, Kyoto Protocol enforced theindustrialized nations to specify and commitfor legally binding reductions in emissions of

    greenhouse gases. Although developingcountries, including India and China, did notcommit to reductions immediately because

    of lower per-capita emissions and inability toabsorb the initial costs of changing tocleaner fuels, the pressure on them to do sois building up.

    India and China are projected to becomemajor carbon emitting nations because oftheir energy requirements and coalgeneration sources. The graph belowdepicts the trends of carbon intensity ofthese two nations in the past (1980-2003).

    China has made great strides in reducingCO2 emissions from coal fired generationunder its large substitutes for small (LSS)program. It is now Indias prerogative to

    demonstrate its efforts for the betterment ofthe environment a cause India believes in.

    Source: World Bank, 2007

  • 8/12/2019 Paper on Supercritical Technology for Power Generation

    6/18

    Supercritical Technology:The dawn of a new era in power generation

    December 2009 Page 4 of 16

    Supercritical technology inPower Generation

    In order to develop additional powergeneration capacity, the existing domestic

    manufacturing capacity needs to be up-graded and enhanced. For the reasons

    stated above there is a preference for super-critical technology in the country.

    About 60% of coal based capacity in XIIPlan and 100% capacity in XIII Plan isplanned to be based on supercriticaltechnology. Table below gives the projectedcapacity addition based on supercriticaltechnology up to 13th Plan:

    Sub critical Super Critical Total Thermal

    In MWAs % of

    totalIn MW

    As % oftotal

    In MW

    11th Plan 44490 85.5% 7540 14.5% 52030

    12th Plan 30473 41.1% 43640 58.9% 74113

    13th Plan 0 0% 64100 100% 64100

    Source: Ministry of Power

    Expected Efficiency Range forSupercritical Units

    The table below provides a comparativeanalysis of turbine heat rate and boiler

    efficiency with super critical parametersusing domestic and imported coal. Thegross efficiency achieved with super criticalparameters is well above 40% usingimported coal.

    *86% boiler efficiency is assumed for domestic coal and 88% for imported coalSource: Ministry of Power, 2006

    PARAMETERS PARAMETERS

    247/535/566

    (Pressure (kg/cm2) /Temp Deg C)

    247/566/592

    (Pressure(kg/cm2) /Temp Deg C)

    TurbineHR

    Boilerefficiency

    Grossefficiency

    TurbineHR

    Boilerefficiency

    Grossefficiency

    88%*39.75%

    88%40.28%

    Case-I TurbineHeat Rate=1904 asQuoted for 660MW &parameters asgiven

    1904

    86%*38.84%

    1879

    86%39.45%

    88%40.06%

    88%40.79%

    Case-II TurbineHeat Rate

    =1880 as perBHEL for 660MW &parameters asgiven

    1880

    86%39.15%

    1855

    86%39.87%

  • 8/12/2019 Paper on Supercritical Technology for Power Generation

    7/18

    Supercritical Technology:The dawn of a new era in power generation

    December 2009 Page 5 of 16

    Supercritical Technology is widelyestablished and accepted with more than500 units in operation across the world. InIndia, NTPC is implementing the technologyat Sipat and Barh thermal power stationswith super critical parameters of up to

    5660C. In Japan and Germany, they could

    achieve a temperature range of 566 to593

    0C. The highest ever efficiency achieved

    with super critical technology is at atemperature 600

    0C.

    Widely prevalent cycle parameters of supercritical technology are

    Parameter Prevalent Value Remarks

    Pressure 246 -250 kg/cm2

    538/538 deg C

    538/566 deg CPresent in Sipat & Barh TPS

    of NTPC

    566/593 deg CMainly in Japan & Germany

    Temperature

    593/593 or 600/600 deg C Highest efficiency gain oversub critical technology

    Methodology for Induction ofSupercritical Technology inIndia

    After several discussions on the issue ofinduction of supercritical technology forcapacity addition in the power sector, amethodology for the same was decided in

    July 2008 by central government. This wasfollowed by several recommendations andrevisions and at last the approach to beadopted for super critical technologyinduction was finalized in February, 2009.

    According to the approach:

    NTPC and DVC would go in for bulktendering of 11 units of 660 MW in 5projects via International CompetitiveBidding (ICB).

    The companies would be allowed to bid

    separately for boilers and turbines. The tender for Boiler Package will be

    split between two bidders. The lowestbidder (R1) in the boiler package will getthree projects and the second-lowestbidder (R2) will get two projects aftermatching price quoted by R1. Thenumber of units for each bidder wouldbe decided as per the groupings that will

    be taken up by NTPC (to be decided ata later stage).

    The Turbine and generator packagewillcomprise of five projects, the tender forwhich will be in groupings of 2+ 2 + 1(i.e. three bidders). This package ismore in number in terms of groupingsbecause there are more players (four orfive) in this category. In respect ofturbine generator package, if BHEL isR1, the 2nd grouping will go to R2 and3rd grouping (of one project) to R3subject to price matching.

    In either case, if BHEL is not the lowestbidder, it will be given the groupearmarked for the second lowest biddersubject to price matching.

    The winners of the tender would berequired to set up manufacturingfacilities in India with a PhasedManufacturing Program (PMP). In caseof existing manufacturing facilities ofsuch bidders in India the facilities wouldbe appropriately augmented.

    The PMP envisages setting up ofmanufacturing facilities for boiler andturbine generators in 48 and 52 monthsrespectively. It was agreed that bidderswill be asked to give firm commitment toset up manufacturing facilities within thisperiod as a part of qualificationrequirement.

  • 8/12/2019 Paper on Supercritical Technology for Power Generation

    8/18

    Supercritical Technology:The dawn of a new era in power generation

    December 2009 Page 6 of 16

    It was proposed that the first unit of theproject awarded to a bidder becompleted within 48 months with a gapof 6 months between units for the sameproject. The gap would be of 2 monthsbetween the first units of different

    projects awarded to the same bidder.

    Induction of super-critical units through bulktendering was accorded the highest priorityby the Ministry of Power (MOP). As per theMOP guidelines issued vide letter datedSeptember 4, 2009, Notice Inviting Tender(NIT) is to be issued within 45 days of issueof this letter i.e. before October 18, 2009.

    NTPC floated tenders inviting bids for 11units of 660 mw on October 16, 2009. Theunits for which the bids were invited include

    nine units of NTPC and two units ofDamodar Valley Corporation. The 11 unitsare to be used in five power projects in thestates of Bihar, Uttar Pradesh, Maharashtraand Jharkhand. The company invitedseparate international competitive bids forboiler and steam turbine generator (STG)sets. So far, five companiesBhel, L&T-Mitsubishi Heavy Industries (MHI) combine,

    Alstom-Bharat Forge, Toshiba-JSW andItalian company Ansaldo Caldie haveexpressed their interest in participating inthe bulk tendering for supercriticalequipment.

    At the time of deciding upon themethodology, there were three prospectivebidders for the Boiler package: BHEL-

    Alstom, L&T-Mitsubishi and Ansaldo, and

    fourfor the Steam Turbine Generator (STG)package: BHEL-Siemens, L&T-Mitsubishi,Bharat Forge-Alstom and Toshiba-JSW.However, other players may also come uponce the tenders are issued.

    The Implementation ofSupercritical Technology

    Supercritical Projects Planned

    The Ultra Mega Power Projects along withsome other power plants have beenenvisaged to be set up with supercriticalparameters. NTPC and the state utilitieshave proposed to set up a number of powerstations based on supercritical technology.

    The list of projects include NTPCs Darlipalliin Orissa (4x800 mw), Tanda expansion inUttar Pradesh (2x660 mw), Pench inMadhya Pradesh (2x660 mw), NTPC-UttarPradesh joint ventures Mejja in UP (2x660mw), NTPC-Bihar JVs New Nabinagar inBihar (2x660 mw), Mahagencos Koradi inMaharashtra (3x660 mw), MahagencosDhopawe in Maharashtra (2x800 mw),BHEL-UP JVs Obra in UP (2x800 mw) andBhel-Tamil Nadu Electricity Board JVsUdangudi in Tamil Nadu (2x800 mw).

    The following table summarizes the detailsof Supercritical Thermal Power Projects(other than UMPPs) under construction inIndia:

  • 8/12/2019 Paper on Supercritical Technology for Power Generation

    9/18

    Supercritical Technology:The dawn of a new era in power generation

    December 2009 Page 7 of 16

    S. No

    Sector/ State

    Project / ImplementingAgency

    LOAdate

    Capacity(MW)

    AnticipatedCommissioning date

    Central Sector

    1

    Barh STPP NTPC

    Unit -1

    Unit-2Unit-3

    03/05

    660660

    660

    11/1205/1311/13

    2

    Bihar

    Barh STPP St. II NTPCUnit -1Unit-2

    10/08

    660660

    03/1301/14

    3

    Chhattisgarh

    Sipat -I NTPC

    Unit-1Unit-2

    Unit-3

    04/04 660660

    660

    03/1005/10

    11/10

    State Sector

    4 AndhraPradesh

    Krishnapatnam APPDCLUnt-1Unit-2

    07/08 800800

    08/1202/13

    Private Sector

    5 Mundra TPP Ph.ll AdaniPower Ltd.Unit-1Unit-2

    09/07

    660660

    03/1108/11

    6

    Gujarat

    Mundra TPP Ph.Ill AdaniPower Ltd.Unit-1

    Unit-2Unit-3

    01/08

    660660660

    05/1108/11

    11/11

    7 Haryana Jhajjar TPP JhajjarPower LtdUnit-1

    Unit-2

    03/09 660660

    12/1106/12

    8

    Tirora TPP Ph.l Adani

    PowerUnit-1

    Unit-2

    02/08

    660660

    04/1107/11

    9

    Maharashtra

    Tirora TPP Ph.ll AdaniPower

    Unit-102/08 660 10/11

    Source: Infraline database, July 2009

  • 8/12/2019 Paper on Supercritical Technology for Power Generation

    10/18

    Supercritical Technology:The dawn of a new era in power generation

    December 2009 Page 8 of 16

    Supercritical Projects under

    Execution

    Currently, supercritical technologies areunder installation at Sipat and Barh thermalpower stations of NTPC. Tata PowersMundra project (UMPP) also importedturbines from Toshiba and boilers fromDoosan, Korea with super criticalparameters.

    Manufacturing Facilities for

    Supercritical technology in

    India

    Considering the large capacity additionrequired for supercritical based projects inthe country, it is necessary to set upadequate manufacturing capacity within thecountry so that the necessary facility andtechnology is available to provide long termsupport for services and spares.

    Domestic Manufacturers

    BHELhas already entered into collaboration

    with Alstom and Siemens for manufacturingof super-critical boilers and turbo-generatorsrespectively. It is in the process ofaugmenting its manufacturing capacity forcoal based thermal units to about 10,000MW per annum by December, 2009 whichcan cater to sub-critical and/or supercriticalunits.

    International manufacturers

    Efforts are being made to attract

    international manufacturers for taking up theequipment manufacturing in India. Someinternational manufacturers have alreadyformed or are in the process of forming jointventure companies with Indian partners toset up manufacturing facilities forsupercritical boilers and turbine generatorsin the country.

    The proposal for bulk tendering of fiveprojects constituting eleven units withmandatory condition of setting upmanufacturing facilities within the country

    sparks off a new era in super criticalequipment manufacturing in India. It helps inattracting new players into the sector.

    A brief synopsis of these new and upcomingventures is as under:

    Venture Product and itsannual Production

    Capacity

    Date ofsigning JVagreement

    Date ofProduction(Planned)

    SCBoilers

    SCTurbine-

    generators

    5thNov

    2007Jun 2010

    L&T/MHI

    4000MW

    4000 MW

    16th

    April2007 (forboilers)

    Oct 2009

    Toshiba-JSW

    500-1000MW

    per unit X 4units

    2nd

    Sept2008

    Jan 2011

    BharatForge-

    Alstom

    - 5000 MW 10th

    Nov2008

    Mid 2011

    GBEngg./Ansaldo

    2000MW

    NA Jan 2011

    In addition to the above, some moremanufacturers have also shown interest insetting up manufacturing facilities in thecountry.

  • 8/12/2019 Paper on Supercritical Technology for Power Generation

    11/18

    Supercritical Technology: The dawn of a new era in power generation

    December 2009 Page 9 of 16

    I

    NDIA

    S

    P

    REPAREDNESS IN

    S

    ETTING UP

    M

    ANUFACTURING

    F

    ACILITIES FOR

    S

    UPER

    C

    RITICAL

    U

    NITS

    The details of Joint Venture companies and progress made in setting up manufacturing facilities forsupercritical units by BHEL and new joint ventures as on July 2009are summarized below.

    1. Turbine Manufacturing:

    The Joint Ventures between:

    L&T - MHI (Turbine)

    Name of JV company L&T MHI Turbine Generators Pvt. Ltd .

    Date of incorporation of JVcompany

    5th November 2007

    Equity structure Larsen & Toubro Ltd. - 51 % Shares

    Mitsubishi Heavy Industries - 49%

    Shares Mitsubishi Electric Company - 10% of MHI's 49% Shares

    Product range Supercritical Turbines and Generators of 500 MW-1000 MW STCC150 MW-300 MW

    Production capacity per annum 4000 MW/Annum

    Date of signing JV agreement 5th November 2007

    Technology transfer agreement

    a. Date of signing

    b. Period of validity in years

    Turbine - 5th Nov'07, Generator - 6th Nov'07

    20 Years for both.

    Planned investment Total Investment Rs. 1252 Crores (Rs.1030 Cr. is for land, buildingconstruction & plant machineries)

    Land for works

    a. Location

    b. Land area envisaged

    c. Progress regardingacquisition

    Hazira - Surat

    70 Acres

    Approved, Government land possession taken

    No. of personnel recruited andplan for recruitment & training

    Manpower - 250 (July'09-) Final Manpower - 971 OperatorsTraining under progress. Executives Training in JapanCommenced.

    Progress of construction offacilities Under Progress.

    Progress of ordering ofmachinery

    Critical equipment ordering completed

    Planned date of start ofproduction

    30th June 2010

    Panned date of completion ofall required facilities

    31st March 2015 - Investment Completion as per PhasedManufacturing Program

  • 8/12/2019 Paper on Supercritical Technology for Power Generation

    12/18

    Supercritical Technology: The dawn of a new era in power generation

    December 2009 Page 10 of 16

    Toshiba - JSW Turbine & Generator Pvt. Ltd.

    Name of JV company Toshiba JSW Turbine & Generator Pvt. Ltd.

    Date of incorporation of JVcompany

    2nd of September 2008

    Equity structure

    Toshiba Corporation: 75%

    JSW Energy Limited: 20%

    JSW Steel Limited: 5%

    Product rangeSteam Turbine & Generator for thermal power station:500MW-1,000MW/Unit

    Production capacity per annum 500MW-1,000MW/Unit x 4Unit

    Date of signing JV agreement 7th of May 2008

    Technology transfer agreement Not yet signed. It will be signed by the end of August.

    Planned investment INR 8,000,000,000

    Land for works

    a. Location

    Vaikkadu and Amullavoyal villages of Ambattur taluk,Tiruvallur district, Chennai, Tamil Nadu

    b. Land area envisaged 98.88 acres

    c. Progress regarding acquisition

    The land acquisition has already been done by theGovernment of Tamil Nadu

    No. of personnel recruited and planfor recruitment & training

    Planned employment-Total 500 in five years Start recruitingfrom July 2009 and start training from January 2010

    Progress of construction of facilities

    Groundbreaking: July, 2009 (Plan.: Final construction:October, 2010 (plan)

    Start of manufacture: January, 2011 (plan)

    Progress of ordering of machinery Major Machineries have been already ordered.

    Planned date of start of production January 2011

    Planned date of completion of allrequired facilities

    October 2015

  • 8/12/2019 Paper on Supercritical Technology for Power Generation

    13/18

    Supercritical Technology: The dawn of a new era in power generation

    December 2009 Page 11 of 16

    Bharat Forge - Alstom

    Name of JVcompany Bharat Forge Ltd. And Alstom are in the process of setting up two joint venturecompanies. The names (Names of the JV companies arc subject to nameavailability and necessary approvals.) of these two joint venture companies areas follows:-

    1. Alstom Bharat Forge Power Limited (ABPL)

    2. Kalyani Alstom Power Limited (KAPL)

    The investing entities from both sides are Bharat Forge Limited, Pune. India andAlstom Power Holdings, SA, Paris, France.

    Date ofincorporationof JV company

    The process of receiving statutory approvals on setting up of these companies isnearing completion. Preparatory steps for incorporation of the JV companieshave been completed. Upon receiving statutory approvals, incorporation of the

    companies would be undertaken during the next few weeks time. As per ourinternal deadlines, incorporation process is set to be completed by middle ofOctober 2009.

    Equitystructure

    The equity share capital in the two companies will be held by Bharat Forge andAlstom in the proportion mentioned below.

    JV Company BFL Alstom

    Alstom Bharat Forge Power Limited 49% 51%

    Kalyani Alstom Power Limited 51% 49%

    Product

    range

    The JVs will be manufacturing Steam Turbine Generator sets, which is

    composed of Steam Turbine Generator Package comprised of the steam turbine,the generator, the condenser, the heaters and al! the associated sub systemsneeded to operate the turbine and the generator; and Balance of Turbinecomposed of a!! the equipment required to completed the steam and watercycles.

    These products will be manufactured for the following range of products coalbased electrical power generating plants of 600-800 MW range, based on supercritical technology coal based electrical power generating plants of 300 - 800 MWrange, based on sub - critical technology

    Productioncapacity perannum

    The two joint venture companies jointly, in the fully ramped up stage, will havethe production capacity to manufacture 5000 MW of Steam Turbine Generatorsets per annum.

    Date ofsigning JV

    BFL and Alstom have already entered into a joint venture and shareholdersagreement on November 10, 2008

    Technologytransferagreement

    a. Date of signing : 14th July 2009

    b. Period of validity in years : 25 years

  • 8/12/2019 Paper on Supercritical Technology for Power Generation

    14/18

    Supercritical Technology: The dawn of a new era in power generation

    December 2009 Page 12 of 16

    Land for works a. Location

    b. Land area envisaged

    c. Progress regarding acquisition

    Currently, the JV companies have got in principle allocation of three sites. Detailsof these three sites are as follows

    100 acres plot at Mundra Port SEZ

    200 acres plot at Dahej, allocated by Government of Gujarat

    250 acres plot at Krishnapatnam port

    Technical evaluation of these three sites for suitability of setting up themanufacturing unit is currently underway. Selection of the final site will becompleted in next two weeks once technical evaluation report is finalized andsubmitted

    No. ofpersonnelrecruited andplan forrecruitment &training

    In the fully ramped up stage, the two companies will have - 1750 personnel.

    CEO and other key personnel of the two JVs have been already identifiedhowever, further recruitment shall be initiated as soon as the joint venture

    companies are incorporated. Detailed training inputs have been identified andschedule for training the recruited staff is being finalized. Works of both the JVpartners in India and abroad as also works of the machine tool suppliers wouldbe some of the key training points. Apart from this, need-based class roomtraining would be imparted in India and abroad in related institutions. A detailedinduction plan for manpower has been finalized.

    Progress ofconstruction offacilities

    Complete layout and civil designing work including utilities planning and logisticsfor both the joint ventures has been completed. Construction of facilities willbegin once the land is transferred to the JVs upon incorporation and is slated tobe taken up after monsoons.

    Progress of

    ordering ofmachinery

    Most of the machine specifications have been finalized and quotes taken from

    identified vendors across the world. The JV companies will place orders posttheir incorporation.

    Date of start ofproduction

    The JVs plan to start production by mid of 2011.(Planned)

  • 8/12/2019 Paper on Supercritical Technology for Power Generation

    15/18

    Supercritical Technology: The dawn of a new era in power generation

    December 2009 Page 13 of 16

    2.Boiler Manufacturing:

    L&T-MHI (Boi ler)

    Name of JV company L&T-MHI. Boilers Pvt. Ltd

    Date of incorporation of JV company 18th April, 2007

    Equity structure L&T-51%. MHI-49%

    Product rangeSupercritical Boilers & Pulverisers in the rangebetween 500 - 1000 MW and above.

    Production capacity per annum 4000 MW/annum

    Date of signing JV agreement 16th April, 2007

    Technology transfer agreement

    a. Date of signing : 27th October, 2006b. Period of validity in years : 20 years

    Planned investment Rs. 750 Crores

    Land for works

    a. Location Hazira, Gujarat for Supercritical BoilerPressure Parts & Pulverizes;

    b. Land area envisaged 70 Acres ;

    c. Progress regarding acquisition - Acquired

    No. of personnel recruited and plan forrecruitment & training

    Manpower - 380 (July'07), Total Planned - 1500

    Training : Engineering Training completed at MHI-Nagasaki, Japan

    Progress of construction of facilities

    Shops A & B completed in April, 2009.

    Balance shops (C, D, E&F) expected to be completedby August 2009.

    Progress of ordering of machineryAll machineries have been ordered and deliverieshave commenced.

    Planned date of start of production October, 2009

    Planned date of completion of allrequired facilities

    December, 2009

    Planned date of completion of allrequired facilities

    All required facilities are expected to be available byMarch 2012.

  • 8/12/2019 Paper on Supercritical Technology for Power Generation

    16/18

    Supercritical Technology: The dawn of a new era in power generation

    December 2009 Page 14 of 16

    ANSALDO GB

    Name of JV company Ansaldo Caldie Boilers India Pvt Ltd

    Date of incorporation of JVcompany

    07 February, 2005

    Equity structure Ansaldo Caldie S.p.A., Italy - 85%

    GB Engineering Enterprises, India - 15%

    Product range Super critical and Sub critical boilers of all size

    Production capacity per annum 2000 MW per annum

    Date of signing JV agreement Not applicable

    Technology transfer agreement Technology for Sub-critical boilers available Technology forSupercritical boilers under transfer.

    Date of signing Sub-critical Boilers - 31 October 2008 Super-Critical Boilers -under finalization expected to be completed by end of 2009.

    Period of validity in years Sub-critical Boilers - 10 years

    Planned investment Present Equity - Rs. 20 Millions

    August 2009 - Rs. 20 Million

    December 2009 - Rs 500 Million

    By Dec 2010 - Rs 500 Million in phased manner

    Land for works Acquisition in progress

    Location Tada, Andhra Pradesh

    Land area envisaged 100 acres

    Progress regarding acquisition Legal formalities in progress

    No. of personnel recruited and planfor recruitment & training

    Present strength - 100Dec. 2009 - 150Dec. 2010 - 400Training to commence from March, 2010

    Progress of construction of facilities To be started after acquisition of land

    Progress of ordering of machinery Dialogue started with potential vendors.Planned date of start of -production January, 2011

    Planned date of completion of allrequired facilities

    May, 2011

  • 8/12/2019 Paper on Supercritical Technology for Power Generation

    17/18

    Supercritical Technology:The dawn of a new era in power generation

    December 2009 Page 15 of 16

    CONCLUSION

    The construction of the 1980 MW Sipat coalfired power plant by NTPC marks the newgeneration of supercritical power plants forIndia. The induction of this technology bringswith it a lot of hope and questions. Thoughthe application of the technology in powergeneration is not a panacea for theproblems of delays in capacity addition andinefficient units plaguing the generationsector, it has the potential to act as animportant stepping stone to evolving one.

    The large size of units will enable fastercapacity addition due to economies of scale.The fact that it is a proven technology forreducing environmental impact may helpspeeding up capacity additions further bymeans of support from environmentallobbyists and faster environmentalclearances. Supercritical technology will alsosignificantly address the issue ofinefficiencies in generation.

    Supercritical technology may be the right

    solution but it is unfortunately not a readymade one. Till recently, most benefits of thistechnology were known to accrue for goodquality, low ash content coal. So there maybe some upgradations required to adopt itfor Indian high ash coal.

    The benefits are defined. It is the duration oftransition from sub critical to super criticalthat will determine the timing of thesebenefits. The transitional phase will dependon the speed with which new manufacturingcapacities for this technology are set up, the

    existing ones upgraded, and the time takenby manpower of existing generatingcompanies to adapt to a new technology.

    Whether on time or post delays, thetechnology and manufacturing willmaterialize, what is important and worthcelebrating is Indias commitment to use itsresources preciously and act responsibly inreducing its carbon footprint.

  • 8/12/2019 Paper on Supercritical Technology for Power Generation

    18/18

    of a new era in power generation

    December 2009 Page 1 of 17

    Contact Us

    SHRINJAN KHOSLAPower Practice

    Infraline Energy Research

    14th Floor, Atmaram Towers

    1, Tolstoy Road

    New Delhi - 110 001. India.

    Tel: +91 11 6625 0040 (Direct)

    Facsimile: +91 11 6625 0099

    Email: [email protected]