Paper 01 - Major_Sea_Crossings
-
Upload
nelson-chin -
Category
Documents
-
view
215 -
download
1
Transcript of Paper 01 - Major_Sea_Crossings
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 1 of 34
11/19/2012
1
Matt Carter | Associate Director
2nd International Seminar on Design & Construction of Second Penang Bridge
Construction of the Superstructure of Major Sea Crossings
2 Second Penang Bridge
Construction of the Superstructure of Major Sea Crossings Mr. Matt Carter, Associate Director
Arup Group Ltd, Hong Kong
11/19/2012
1
Matt Carter | Associate Director
2nd International Seminar on Design & Construction of Second Penang Bridge
Construction of the Superstructure of Major Sea Crossings
2 Second Penang Bridge
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 2 of 34
11/19/2012
2
3 Typical Sea Crossing Bridges
Donghai Bridge Incheon Bridge
Penang Bridge Shenzhen Western Corridor
4 Long Section
Scale H:V = 10:1Maximum water depth = 10mTypical water depth = 2 to 3m
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 3 of 34
11/19/2012
3
5 Stonecutters Bridge, Hong Kong
6 Second Penang Bridge, Malaysia
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 4 of 34
11/19/2012
4
7 Substructure optimization
Substructure is typically around one third of the total cost
Innovative design gives substantial savings
Depends on ground conditions
Innovations:- Construction methods- Lateral pile load tests- Articulation- Seismic isolation
Typical Superstructure
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 5 of 34
11/19/2012
5
9
Quality – Production line casting in a controlled environment
Economy – Repetitive operations, re-use of equipment
Safety – Minimise working at height and over water
Advantages of precast construction
10
Quality Cost Speed of Construction Durability Safety Environmental
Impact Aesthetics
Design Drivers
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 6 of 34
11/19/2012
6
11
Quality Cost Speed of Construction Durability Safety Environmental
Impact Aesthetics
Design Drivers
12
For given site conditions there will be an optimum economic span
With current technologies in shallow seas without navigation requirements this is typically around 50m to 55m
Span
Cost
Low elevation / shallow water
High elevation / deep water
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 7 of 34
11/19/2012
7
Economic Comparison of First Penang Bridge
Based on prevailing costs and available technologies in July 1977
Source: The Penang Bridge, Planning Design and Construction by Tan Sri Datuk Professor Ir. Chin Fung Kee
14
Asia’s first precast segmental bridge
Design & Build contract
Opened 1991
Kwun Tong Bypass Phase 2
Balanced cantilever segment erection
Completed project next to the old Kai Tak Airport Overhead gantry weighted 400 tonnes and was 130m long
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 8 of 34
11/19/2012
8
15
Comparison between First and Second PenangPenang Bridge (1985)
40m PC beam and slab
Second Penang Bridge (2013)55m precast segmental box girders
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 9 of 34
11/19/2012
9
Typical Cross Section
16m is enough for a three lane highway with full width breakdown land
Typically 10 – 16m Typically 10 – 16m
Precast Segmental Span by Span
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 10 of 34
11/19/2012
10
19 Span by Span Erection
20
Erection Sequence
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 11 of 34
11/19/2012
11
21 Erection Gantry
22
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 12 of 34
11/19/2012
12
23
24 Srtuctural Completion
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 13 of 34
11/19/2012
13
Precast Segmental Balanced Cantilever
26 Why balanced cantilever?
Deep Bay Link
West Tsing Yi Viaducts
Span-by-span segmental needs all of the segments in a span to be simultaneously supported by the gantry
Under some design conditions this could lead to a very expensive gantry:- Long spans- Tight radius curves
Shorter projects may not justify investment
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 14 of 34
11/19/2012
14
27 Shenzhen Western Corridor
28
Total only ~ 4 ½ years
• Feasibility Study (incl. Conceptual Design & EIA) Aug 2001 – Sep 2002• Detailed Design Jul 2002 – Jul 2003• Construction Aug 2003 – Dec 2005 (28 months)
Fast Track Design & Construction
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 15 of 34
11/19/2012
15
29
30 Segment erection
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 16 of 34
11/19/2012
16
31
Cantilever tip derricks Segment delivery by barge
Segment storage Short line segment match casting
End Spans
Expansion joints are needed at regular intervals which interfere with balanced cantilever erection
Options- Short end spans – interrupt the rhythm of the bridge- Temporary fixity of joints- Mid span hinge- SWC – hybrid solution
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 17 of 34
11/19/2012
17
33 End span erection
Full Span Launching Method
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 18 of 34
11/19/2012
18
35
36 Project Overview
Project Overview
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 19 of 34
11/19/2012
19
37 Incheon Bridge
38 Full Span Launching Method
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 20 of 34
11/19/2012
20
39 Launching gantry
40 Full Span Casting Factory
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 21 of 34
11/19/2012
21
41
42 Pretensioning
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 22 of 34
11/19/2012
22
43 Erection of first segment
44
Delivery of segments in deep water which is accessible by floating crane
Transportation along the already erected deck by a mutli-wheeled transporter
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 23 of 34
11/19/2012
23
45
Segment transportation is governing load
1,300 tonne segment and 950 tonnetransporter unit
Spread onto four girders
46 Erection equipment
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 24 of 34
11/19/2012
24
Full Span Launching Method
Contractor was experienced with the method Very long viaduct justifies investment in bespoke
launching gantry to achieve very fast construction No variations in deck width, no tight radius curves
in highway alignment Marine environment and availability of large
capacity floating cranes Low level viaduct makes moderate span length
(50m) economical
Comparison of Sea Crossing Construction Methods
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 25 of 34
11/19/2012
25
49
Project Second PenangBridge Incheon Bridge Shenzhen
Western CorridorDeck Type Precast Concrete Box Girder
ProcurementMethod Design & Build Design & Build Engineers Design
Contractor UEM Builders SamsungConstruction JV
Gammon-Skanska-MBEC Joint Venture
Construction Method Span by span precast segmental
Full span precast launching
Balanced cantilever precast segmental
Status Under Construction Completed 2009 Completed 2006
Total Length 16.9 km 12.3 km 5.5 km
Viaduct Length 16.5 km 9.0 km 4.7 km
Width 2 x 14.0 m 2 x 15.7 m 12 x 16.05 m
Typical Span 55 m 50 m 75 m
Typical Bridge Unit Length 330 m 250 m 590 m
Three sea crossings constructed in shallow water in East Asia
50
8092 segments
3 lines of 7 moulds per line (different fabricators)
Storage capacity for 780 segments (2 months supply)
Typical segment – 1 per day
Second Penang Bridge Precast Yard
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 26 of 34
11/19/2012
26
51
360 segments
1 mould
Storage capacity for six segments (<2 weeks production)
One segment every 2 days
Incheon Bridge Precast Yard
52
Project Second PenangBridge Incheon Bridge Shenzhen
Western CorridorNumber of Spans 580 360 90
(Hong Kong section)Number of Gantries 4 2 1 overhead gantry
+ 4 pairs of cantilever derricks
Spans Per Gantry 145 180 16
Number of Segments
8,092 360 1,879
Number of Moulds 3 x 7 = 21 1 6
Segments Per Mould
385 360 313
Peak Cycle Time 4 days per span per gantry
2 days per span per mould
1 week per span pergantry
Theoretical Durationat Peak Productivity
20 months 24 months 4.5 months
Three sea crossings constructed in shallow water in East Asia
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 27 of 34
11/19/2012
27
53
Second Penang Bridge• Design & Build – contractor can tailor method• Contractor had previous experience of span by span segmental• Environmental impacts acceptable with a 55m span
Incheon Bridge• Design & Build – contractor can tailor method • Contractor had previous experience of full span launching• Large number of spans justifies investment in bespoke gantry
Shenzhen Western Corridor• Very fast track project - needs multiple gantries• Limited number of spans – hard to justify bespoke investment• Engineers design – needs flexible method• Environmentally sensitive mud flats needs longer spans (75m)
Conclusions
With constant width and gentle plan curvature a typical span length of 50m to 55m can be constructed by any one of the three methods
Speed of construction depends on number of construction fronts so the cycle time for a single gantry may not dictate project duration
Span by span segmental construction is a versatile method but span is limited to around 55m
Balanced cantilever will be more economical at longer spans
Full span launching will only be economical for very large projects which tends to limit the number of contractors who will adopt it
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 28 of 34
11/19/2012
28
Hong Kong Zhuhai Macau Bridge
• 43.6 km bridge over Pearl River Estuary
• 1st major combined bridge & tunnel sea-crossing in China
• reduce travel time to 0.5 hour from HK and Pearl River West
Macau
Zhuhai
HKSAR
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 29 of 34
11/19/2012
29
LantauIsland
Macau
Zhuhai
Lantau Island
Qin
gzho
u n
avig
atio
nch
anne
l
West Artificial Island East Artificial
IslandTunnel
HKBCFHK Section
58 Mainland Section
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 30 of 34
11/19/2012
30
Flooding Control
Line of bridge completely crosses a major delta outlet
Pier blockage could lead to upstream flooding
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 31 of 34
11/19/2012
31
61
85m span shallow water sections
110m span deep water sections
62 Hong Kong Section
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 32 of 34
11/19/2012
32
63 Hong Kong Link Road
12km long highway
Including 9.4km sea crossing viaduct
64
Design-build contract awarded May 2012 to Dragages-China Harbour-VSL JV
75m precast segmental balanced cantilever
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 33 of 34
11/19/2012
33
Emerging Trends
66 Stainless steel reinforcement
Extension of Design Life Asset Management
Structural Health Monitoring Threat and Vulnerability Assessment
SECOND INTERNATIONAL SEMINARON THE DESIGN & CONSTRUCTION OF THE SECOND PENANG BRIDGE28 – 29 November 2012
Sunway Putra Hotel, Kuala Lumpur
Page 34 of 34
11/19/2012
34
Thank You