Palomar West Medical Center Segmental Review Brett W. Beekman, S.E. Senior Structural Engineer,...

16
Palomar West Medical Center Segmental Review Brett W. Beekman, S.E. Senior Structural Engineer, Southern California

Transcript of Palomar West Medical Center Segmental Review Brett W. Beekman, S.E. Senior Structural Engineer,...

Page 1: Palomar West Medical Center Segmental Review Brett W. Beekman, S.E. Senior Structural Engineer, Southern California.

Palomar West MedicalCenter Segmental Review

Brett W. Beekman, S.E.Senior Structural Engineer, Southern California

Page 2: Palomar West Medical Center Segmental Review Brett W. Beekman, S.E. Senior Structural Engineer, Southern California.

Segmental Review Pilot

Palomar West Medical CenterLocated in Escondido, San Diego County

11 story steel framed structure with one basement levelGross square feet: 725,000

Number of beds: 328Estimated construction cost: $400,000,000.00

Page 3: Palomar West Medical Center Segmental Review Brett W. Beekman, S.E. Senior Structural Engineer, Southern California.

Segmental Review Pilot

Inpatient TowerFloors 1 - 11

D & T Low-rise BaseFloors 1 - 3

Page 4: Palomar West Medical Center Segmental Review Brett W. Beekman, S.E. Senior Structural Engineer, Southern California.

Break Down of Increments

•Increment 1: Foundation Only Package

•Increment 2: Architectural & MEP

•Increment 3: Exterior Curtain Wall Systems

•Increment 4: MEP & Medical Equipment Anchorage

•Increment 5: MEP Pipe, Duct & Conduit Bracing

•Increment 6: Major Structure Except Foundation

Page 5: Palomar West Medical Center Segmental Review Brett W. Beekman, S.E. Senior Structural Engineer, Southern California.

Scope of Increments 1 & 6

• Increment 1 originally contained the entire major structure including foundation and was divided into 5 segments

• The foundation was separated into it’s own increment, at owner’s request & became Increment 1

• Increments 2 - 5 were already designated & input into Logbook, OSHPD’s project tracking system

• Increment 6 added and includes the balance of the major structural system

Page 6: Palomar West Medical Center Segmental Review Brett W. Beekman, S.E. Senior Structural Engineer, Southern California.

Increments 1 & 6 Segments

Scheduled Actual Scheduled Actual Submittal Submittal Approval Approval

Date Date Date Date

Segment 1 (Detailed Approach) 2/14/07 2/22/07 3/16/07 4/03/07

Segment 2(Loading Criteria) 3/05/07 3/08/07 3/30/07 4/20/07

Segment 3A(Lateral Comp. Model) 4/11/07 4/11/07 7/30/07 8/02/07

Segment 3b(Gravity Comp. Model) 4/11/07 4/11/07 7/30/07 8/02/07

Segment 4(Specs, Gen’l Notes, etc) 6/04/07 6/04/07 8/31/07 9/07/07

Segment5A(Foundation, Basement) 7/02/07 7/02/07 9/28/07 10/12/07

Segment5B(Diaphragm Design) 7/02/07 7/02/07 9/28/07 11/02/07

Page 7: Palomar West Medical Center Segmental Review Brett W. Beekman, S.E. Senior Structural Engineer, Southern California.

Increments 1 & 6 Submittals

Increment 1: Foundation Only Submittal

• Submitted on time (9/28/07)• Scheduled completion date 12/21/07 • Change in code necessitated reevaluation of soils report• Ground motion studies were the main focus of the reevaluation.• Alternate Method of Compliance granted allowing use of the 2007 CBC

Increment 6: Superstructure Submittal (excluding foundation)

• Submitted on time (9/28/07)• Scheduled completion date 3/25/08• Revised completion date 4/15/08• A Wind Tunnel study proposed by the SEOR was implemented during

segment 3A and focused on local wind pressures at corner conditions

Page 8: Palomar West Medical Center Segmental Review Brett W. Beekman, S.E. Senior Structural Engineer, Southern California.

Increment 2 Submittal

Increment 2: Architectural and MEP Submittal

• Submitted on 9/28/08• Revised submittal on 12/4/07• Scheduled completion date 9/28/08• Several items from Increments 1 or 6 were included in

Increment 2 to facilitate the respective approval schedules

• Items moved to Increment 2 included • Loading Dock and Block House Foundations • Site Walls and Window Washing Davits

Page 9: Palomar West Medical Center Segmental Review Brett W. Beekman, S.E. Senior Structural Engineer, Southern California.

Increment 3 Submittal

Increment 3: Exterior Curtain Wall Systems Submittal

• As of 2/15/07, the “Begin the Review Process” was

scheduled as “TBD”• 100% CD set submittal scheduled for 9/07• Review to be completed by 6/08• Unforeseen conditions resulted in a schedule

modification• New schedule for the Curtain Wall Submittal has

been broken into 5 segments

Page 10: Palomar West Medical Center Segmental Review Brett W. Beekman, S.E. Senior Structural Engineer, Southern California.

Increment 3 Segments Scheduled Actual Scheduled

Actual Submittal Submittal Approval Approval Date Date Date Date

Segment 1 5/12/08 9/12/08

(Package 1, Phase 1)

Segment 2 6/16/08 10/17/08

(Package 2, Phases 2-3-4)

Segment 3 9/22/08 1/16/09

(Package 3, Phases 5-6)

Segment 4 10/20/08 1/23/09

(Package 4, Phases 7-8)

Segment 5 1/12/09 5/15/09

(Package 5, Phases 9-10)

Page 11: Palomar West Medical Center Segmental Review Brett W. Beekman, S.E. Senior Structural Engineer, Southern California.

Increment 4 Submittal

Increment 4: MEP & Medical Equipment Anchorage Submittal:

• As of 2/15/07, the “Begin the Review Process” was scheduled as starting 2/08

• 100% CD set submittal scheduled for 9/08

• Review to be completed by 9/09

• Unforeseen conditions resulted in a schedule modification

• New schedule has been broken into two segments

Page 12: Palomar West Medical Center Segmental Review Brett W. Beekman, S.E. Senior Structural Engineer, Southern California.

Increment 4 Segments

Scheduled Actual Scheduled Actual Submittal Submittal Approval Approval

Date Date Date Date

Segment 1 4/30/08 1/30/09 (MEP Equipment Anchorage)

Segment 2 6/30/08 2/27/09 (Medical Equipment Anchorage)

Page 13: Palomar West Medical Center Segmental Review Brett W. Beekman, S.E. Senior Structural Engineer, Southern California.

Increment 5 Submittal

Increment 5: MEP Pipe, Duct & Conduit Bracing

• As of 2/15/07, the “Begin the Review Process” was scheduled as

“TBD”• 100% CD set submittal scheduled for 9/08• Review to be completed by 9/09• Unforeseen conditions resulted in a schedule modification• New submittal date is 5/08

• Review to be completed 7/09

The design team has requested the package be submitted and permitted on a floor by floor basis. This request is currently under review.

Page 14: Palomar West Medical Center Segmental Review Brett W. Beekman, S.E. Senior Structural Engineer, Southern California.

Phased Review - Lessons Learned

• Continual communication between OSHPD, contract reviewers and designers is essential in segmented review

• Coordination between disciplines on the design team is essential– Continuously updating team on changes in the design

• Submit long lead reviews, i.e. geotech reports, design criteria, AMC, material testing reports, etc., far in advance of plan review submittals

Page 15: Palomar West Medical Center Segmental Review Brett W. Beekman, S.E. Senior Structural Engineer, Southern California.

More Lessons Learned

• Deciding what to put into each increment is key – Including “unique” items may shift focus from major

portions of the work

• Use every tool in the box– Reminders and checklists– Review FAQs, PINs & CANs

• Flexibility by all parties is essential in resolving schedule conflicts and design changes

Page 16: Palomar West Medical Center Segmental Review Brett W. Beekman, S.E. Senior Structural Engineer, Southern California.

www.oshpd.ca.gov