Bob Brehm, AK6R Chief Engineer Palomar-Engineers.com Copyright 2015 Palomar Engineers, Inc.
Palomar West Medical Center Segmental Review Brett W. Beekman, S.E. Senior Structural Engineer,...
-
Upload
archibald-rice -
Category
Documents
-
view
213 -
download
0
Transcript of Palomar West Medical Center Segmental Review Brett W. Beekman, S.E. Senior Structural Engineer,...
Palomar West MedicalCenter Segmental Review
Brett W. Beekman, S.E.Senior Structural Engineer, Southern California
Segmental Review Pilot
Palomar West Medical CenterLocated in Escondido, San Diego County
11 story steel framed structure with one basement levelGross square feet: 725,000
Number of beds: 328Estimated construction cost: $400,000,000.00
Segmental Review Pilot
Inpatient TowerFloors 1 - 11
D & T Low-rise BaseFloors 1 - 3
Break Down of Increments
•Increment 1: Foundation Only Package
•Increment 2: Architectural & MEP
•Increment 3: Exterior Curtain Wall Systems
•Increment 4: MEP & Medical Equipment Anchorage
•Increment 5: MEP Pipe, Duct & Conduit Bracing
•Increment 6: Major Structure Except Foundation
Scope of Increments 1 & 6
• Increment 1 originally contained the entire major structure including foundation and was divided into 5 segments
• The foundation was separated into it’s own increment, at owner’s request & became Increment 1
• Increments 2 - 5 were already designated & input into Logbook, OSHPD’s project tracking system
• Increment 6 added and includes the balance of the major structural system
Increments 1 & 6 Segments
Scheduled Actual Scheduled Actual Submittal Submittal Approval Approval
Date Date Date Date
Segment 1 (Detailed Approach) 2/14/07 2/22/07 3/16/07 4/03/07
Segment 2(Loading Criteria) 3/05/07 3/08/07 3/30/07 4/20/07
Segment 3A(Lateral Comp. Model) 4/11/07 4/11/07 7/30/07 8/02/07
Segment 3b(Gravity Comp. Model) 4/11/07 4/11/07 7/30/07 8/02/07
Segment 4(Specs, Gen’l Notes, etc) 6/04/07 6/04/07 8/31/07 9/07/07
Segment5A(Foundation, Basement) 7/02/07 7/02/07 9/28/07 10/12/07
Segment5B(Diaphragm Design) 7/02/07 7/02/07 9/28/07 11/02/07
Increments 1 & 6 Submittals
Increment 1: Foundation Only Submittal
• Submitted on time (9/28/07)• Scheduled completion date 12/21/07 • Change in code necessitated reevaluation of soils report• Ground motion studies were the main focus of the reevaluation.• Alternate Method of Compliance granted allowing use of the 2007 CBC
Increment 6: Superstructure Submittal (excluding foundation)
• Submitted on time (9/28/07)• Scheduled completion date 3/25/08• Revised completion date 4/15/08• A Wind Tunnel study proposed by the SEOR was implemented during
segment 3A and focused on local wind pressures at corner conditions
Increment 2 Submittal
Increment 2: Architectural and MEP Submittal
• Submitted on 9/28/08• Revised submittal on 12/4/07• Scheduled completion date 9/28/08• Several items from Increments 1 or 6 were included in
Increment 2 to facilitate the respective approval schedules
• Items moved to Increment 2 included • Loading Dock and Block House Foundations • Site Walls and Window Washing Davits
Increment 3 Submittal
Increment 3: Exterior Curtain Wall Systems Submittal
• As of 2/15/07, the “Begin the Review Process” was
scheduled as “TBD”• 100% CD set submittal scheduled for 9/07• Review to be completed by 6/08• Unforeseen conditions resulted in a schedule
modification• New schedule for the Curtain Wall Submittal has
been broken into 5 segments
Increment 3 Segments Scheduled Actual Scheduled
Actual Submittal Submittal Approval Approval Date Date Date Date
Segment 1 5/12/08 9/12/08
(Package 1, Phase 1)
Segment 2 6/16/08 10/17/08
(Package 2, Phases 2-3-4)
Segment 3 9/22/08 1/16/09
(Package 3, Phases 5-6)
Segment 4 10/20/08 1/23/09
(Package 4, Phases 7-8)
Segment 5 1/12/09 5/15/09
(Package 5, Phases 9-10)
Increment 4 Submittal
Increment 4: MEP & Medical Equipment Anchorage Submittal:
• As of 2/15/07, the “Begin the Review Process” was scheduled as starting 2/08
• 100% CD set submittal scheduled for 9/08
• Review to be completed by 9/09
• Unforeseen conditions resulted in a schedule modification
• New schedule has been broken into two segments
Increment 4 Segments
Scheduled Actual Scheduled Actual Submittal Submittal Approval Approval
Date Date Date Date
Segment 1 4/30/08 1/30/09 (MEP Equipment Anchorage)
Segment 2 6/30/08 2/27/09 (Medical Equipment Anchorage)
Increment 5 Submittal
Increment 5: MEP Pipe, Duct & Conduit Bracing
• As of 2/15/07, the “Begin the Review Process” was scheduled as
“TBD”• 100% CD set submittal scheduled for 9/08• Review to be completed by 9/09• Unforeseen conditions resulted in a schedule modification• New submittal date is 5/08
• Review to be completed 7/09
The design team has requested the package be submitted and permitted on a floor by floor basis. This request is currently under review.
Phased Review - Lessons Learned
• Continual communication between OSHPD, contract reviewers and designers is essential in segmented review
• Coordination between disciplines on the design team is essential– Continuously updating team on changes in the design
• Submit long lead reviews, i.e. geotech reports, design criteria, AMC, material testing reports, etc., far in advance of plan review submittals
More Lessons Learned
• Deciding what to put into each increment is key – Including “unique” items may shift focus from major
portions of the work
• Use every tool in the box– Reminders and checklists– Review FAQs, PINs & CANs
• Flexibility by all parties is essential in resolving schedule conflicts and design changes
www.oshpd.ca.gov