Painting Procedure

download Painting Procedure

of 62

description

Industrial Painting Procedure as applied in oil and gas business.

Transcript of Painting Procedure

  • 5/20/2018 Painting Procedure

    1/62

  • 5/20/2018 Painting Procedure

    2/62

    COMPANY Contract No:

    FAC-2009-CW690260

    CONTRACTOR Contract No.:

    C0109 WAV

    Doc. No.: WAV-PR-GE200-016

    Rev. No.: B

    PAINTING PROCEDURE Page 2 of 19

    This is a CONFIDENTIAL document and remains the sole property of WAV. It shall not be shown to Third Parties nor used for purposes other than those for which it is intended .

    TABLE OF CONTENTS

    1. INTRODUCTION 5

    1.1 General 5

    1.2 Objective 5

    1.3

    Abbreviations and Definitions 5

    1.4 References 6

    2.0 RESPONSIBILITIES 6

    2.1 Fabrication Manager 7

    2.2 Field Engineer 7

    2.3 Blasting & Painting Supervisor 7

    2.4 Painting Foreman 7

    2.5 Quality Control Engineer / Inspector 7

    3.0 PROCEDURE 7

    3.1

    Painting Qualification Test 8

    3.2

    Accepted Brand 8

    3.3 Material Storage and Handling 8

    3.4 Release of Fabricated items for Painting 8

    3.5 Pre-Surface Preparation 9

    3.6 Surface Preparation 9

    3.7 Coating Application 9

    3.8

    Painting Touch-up and Repair 10

    3.9 Finish Colour 10

    3.10

    Coating Thickness 10

    3.11

    Records 10

    4.0 INSPECTION FREQUENCY 11

    ATTACHMENTS 13

  • 5/20/2018 Painting Procedure

    3/62

    COMPANY Contract No:

    FAC-2009-CW690260

    CONTRACTOR Contract No.:

    C0109 WAV

    Doc. No.: WAV-PR-GE200-016

    Rev. No.: B

    PAINTING PROCEDURE Page 3 of 19

    This is a CONFIDENTIAL document and remains the sole property of WAV. It shall not be shown to Third Parties nor used for purposes other than those for which it is intended .

    ATTACHMENT A- Painting Qualification Test Report 14

    ATTACHMENT B- Daily Blasting & Painting Report 16

    ATTACHMENT C- Final Painting Acceptance Report 18

    ATTACHMENT D- COM-SU-2.02-A 20

    REVISION HISTORY

  • 5/20/2018 Painting Procedure

    4/62

    COMPANY Contract No:

    FAC-2009-CW690260

    CONTRACTOR Contract No.:

    C0109 WAV

    Doc. No.: WAV-PR-GE200-016

    Rev. No.: B

    PAINTING PROCEDURE Page 4 of 19

    This is a CONFIDENTIAL document and remains the sole property of WAV. It shall not be shown to Third Parties nor used for purposes other than those for which it is intended .

    Revision Date Page Descript ion Approved

    OA 22.09.09 All Issued for IDC AOC

    A 29.09.09 All Issued for Approval AOC

    B 18.12.09 All Issued for Approval DA

  • 5/20/2018 Painting Procedure

    5/62

    COMPANY Contract No:

    FAC-2009-CW690260

    CONTRACTOR Contract No.:

    C0109 WAV

    Doc. No.: WAV-PR-GE200-016

    Rev. No.: B

    PAINTING PROCEDURE Page 5 of 19

    This is a CONFIDENTIAL document and remains the sole property of WAV. It shall not be shown to Third Parties nor used for purposes other than those for which it is intended .

    1. INTRODUCTION

    1.1 General

    CHEVRON NIGERIA LIMITED (COMPANY) has awarded to West African Ventures

    (CONTRACTOR) a 2-year Call-out Contract for the Transportation and Installation of Pipelines and

    Risers (TIP).

    The Scope of Work includes: Installation engineering, procurement (except COMPANY supplied

    materials), project management, transportation, fabrication, offshore installation, pre-commissioning

    and remedial painting (where applicable) for the following:

    Pipelines with a nominal diameter of 6 (168.3mm) 18 (457.2mm) for various services in water

    depths of 4.70m to 16.50m.

    Above Facilities are to be installed in COMPANY Escravos Offshore Assets in Nigeria.

    1.2 Objective

    The objective of this procedure is to detail the project requirements governing the surface

    preparation and external painting process both at onshore and offshore facilities where fabrication

    will take place for the structural component.

    1.3 Abbreviations and Definit ions

  • 5/20/2018 Painting Procedure

    6/62

    COMPANY Contract No:

    FAC-2009-CW690260

    CONTRACTOR Contract No.:

    C0109 WAV

    Doc. No.: WAV-PR-GE200-016

    Rev. No.: B

    PAINTING PROCEDURE Page 6 of 19

    This is a CONFIDENTIAL document and remains the sole property of WAV. It shall not be shown to Third Parties nor used for purposes other than those for which it is intended .

    1.3.1 Definitions

    COMPANY Chevron Nigeria Limited

    CONTRACTOR West Africa Ventures Limited

    1.3.2 Abbreviations

    QA/QC Quality Assurance / Quality Control

    DFT Dry Film Thickness

    WFT Wet Film Thickness

    1.4 References

    1.4.1 Codes and Standards

    NACE National Association of Corrosion Engineers

    SSPC SP1 Society for Protective Coating (Solvent Cleaning)

    1.4.2 COMPANY Provided Documents

    COM-SU-2.02A Material and application of painting and protective coating

    SPEC. 0.01 COMPANY General Project procedure

    1.4.3 CONTRACTOR Documents

    WAV-PR-GE200-0 Inspection and Test Procedure

    WAV-PR-09-001 Calibration Control Procedure

    2.0 RESPONSIBILITIES

  • 5/20/2018 Painting Procedure

    7/62

    COMPANY Contract No:

    FAC-2009-CW690260

    CONTRACTOR Contract No.:

    C0109 WAV

    Doc. No.: WAV-PR-GE200-016

    Rev. No.: B

    PAINTING PROCEDURE Page 7 of 19

    This is a CONFIDENTIAL document and remains the sole property of WAV. It shall not be shown to Third Parties nor used for purposes other than those for which it is intended .

    2.1 Fabrication Manager

    The Fabrication Manager shall ensure that this procedure shall be followed and all of its

    requirements are strictly adhered to at all times. The Fabrication Manager is responsible for ensuring

    that all activities defined in this procedure shall always be performed by trained, experienced

    employees, and in a manner that is acceptable to Industrial Practice, applicable procedures,

    COMPANY Specifications, and Procedures.

    2.2 Field Engineer

    Field Engineer shall support the Fabrication Manager on all technical matters pertaining to the work.

    He monitors that the work is carried out as per the applicable procedures and in accordance with thetechnical specifications. Where deviations area necessary, he assists the Fabrication Manager in

    planning these and where additional engineering is required he liaises with the Senior Project

    Engineer based in the office.

    2.3 Blasting & Painting Supervisor

    The blasting and painting supervisor is responsible for the overall supervision of the blasting and

    painting activities, ensures that the operation is done correctly, ensures that all equipment are working

    correctly. He shall work in coordination with Fabrication Manager and have authority to disseminate an

    instruct his subordinates regarding the requirements of this procedure.

    2.4 Painting Foreman

    The Painting foreman shall ensure all activities defined in this procedure are carried out in accordance

    with specification and by qualified blasting and painting personnel. He shall ensure the blasting and

    painting activity is performed in a safe and environmentally friendly manner.

    2.5 Quality Contro l Engineer / Inspector

    The QA/QC Engineer/Inspector is responsible for the quality of the work. He is responsible for the

    monitoring of the blasting and painting process in line with COMPANY painting specification and the

    procedure. He ensures that batch / calibration certificates for the paints and inspection equipment are iplace. He shall work directly with the Fabrication Manager and Blasting and Painting Supervisor. Shou

    any deviation arise during the process he must notify them immediately.

    3.0 PROCEDURE

  • 5/20/2018 Painting Procedure

    8/62

    COMPANY Contract No:

    FAC-2009-CW690260

    CONTRACTOR Contract No.:

    C0109 WAV

    Doc. No.: WAV-PR-GE200-016

    Rev. No.: B

    PAINTING PROCEDURE Page 8 of 19

    This is a CONFIDENTIAL document and remains the sole property of WAV. It shall not be shown to Third Parties nor used for purposes other than those for which it is intended .

    3.1 Painting Qualification Test

    Prior to mobilization and commencement of all project painting operation, the painting qualification

    test will be carried out which will include surface preparation, mixing, application and inspection.

    This will be done in the presence of designated COMPANY representative on site.

    All surface preparation and painting test will be made under simulated site condition if done in the

    workshop environment. All inspection such as visual examination, cleanliness and film thickness

    tests shall be performed strictly to the COMPANYs specification.

    3.2 Accepted Brand

    Only specified painting system from painting system data sheets shall be used, unless alternates

    are reviewed by CONTRACTOR and COMPANY duly notified in writing.

    The CONTRACTOR shall only use paints which comply with Federal, State and Local air pollution

    regulation

    The Iamsub paint which is the COMPANY approved alternate coating system for the riser flange

    weld area shall be applied as per manufacturer specifications whenever it is used.

    The latest issue of the paint manufacturers product data sheets, application instructions and

    Material Safety data sheets shall be available at the painting site and complied with during paintingoperations.

    3.3 Material Storage and Handling

    Painting materials shall be stored and handled in accordance with the manufacturers instructions

    Materials shall be delivered to the place of application in unopened, original containers bearing a

    legible product designation, batch number, expiry date, shelf life, date of manufacture and colour

    codes applicable to the project specification.

    The specified paint; primers, intermediate and topcoat together with their associated thinners shall

    be stored in cool dry environments free from heat, heat sources, segregated away for all nakedflames, welding sparks and maintained at room temperature.

    Painted items shall be protected from damage by use of non abrasive supports during storage.

    Coated surfaces shall be protected from damage during lifting or handling by use of soft packing

    between slings where possible. Where damage to painted surface is unavoidable these areas shall

    be clearly identified and repaired in accordance with painting and touch up specified in this

    procedure

    3.4 Release of Fabricated items for Painting

  • 5/20/2018 Painting Procedure

    9/62

    COMPANY Contract No:

    FAC-2009-CW690260

    CONTRACTOR Contract No.:

    C0109 WAV

    Doc. No.: WAV-PR-GE200-016

    Rev. No.: B

    PAINTING PROCEDURE Page 9 of 19

    This is a CONFIDENTIAL document and remains the sole property of WAV. It shall not be shown to Third Parties nor used for purposes other than those for which it is intended .

    After fabrication and inspection is completed, the fabricated item that has passed all shop

    inspection and released by the Quality department shall be considered ready for painting.

    All fabricated items shall proceed to blasting and painting operations after all fabrication shop

    preparations have been completed. The tag indicating the number of fabricated spool shall be used

    for identification, where ever possible all spool number shall be marked on the internal surface or

    spool ends before final release for site identification.

    3.5 Pre-Surface Preparation

    Prior to commencing surface preparation the QC inspector shall ensure that blasting operations donot destroy the traceability numbers or tags. Any material that is found to be untraceable either

    before or after blasting and painting operations shall be immediately segregated for separate

    identification.

    Visual inspection shall be done on the steel surface to detect the presence of oil, grease, wax, dirt

    and other foreign matter. If detected solvent cleaning as per SSPC SP1 shall be complied with prior

    to any tool or abrasive cleaning. The degreased surface shall be further washed with fresh water to

    remove all traces of degreaser chemicals.

    All items that are exposed to marine environment will be washed down with potable fresh water to

    remove any salt contamination. This procedure shall also be performed on all metal surfaces thatdo not require painting.

    Raised face of weld neck flange shall be protected by covering with masking tape and grease.

    All weld spatter and residual flux shall be entirely removed. Excessively rough welding, sharp

    edges and corners shall be ground relatively smooth prior to abrasive blast cleaning

    Blasting shall not be permitted when steel surface is less than 3 degree centigrade above dew

    point.

    3.6 Surface Preparation

    The surface preparation shall be as detailed in section 4.0 COMPANY specification (COM-SU-

    2.02-A) on Materials and application of painting and protective coatings (see Attachment D)

    3.7 Coating Application

  • 5/20/2018 Painting Procedure

    10/62

    COMPANY Contract No:

    FAC-2009-CW690260

    CONTRACTOR Contract No.:

    C0109 WAV

    Doc. No.: WAV-PR-GE200-016

    Rev. No.: B

    PAINTING PROCEDURE Page 10 of 19

    This is a CONFIDENTIAL document and remains the sole property of WAV. It shall not be shown to Third Parties nor used for purposes other than those for which it is intended .

    The coating application shall be as detailed in section 5.0 COMPANY specification (COM-SU-2.02-

    A) on Materials and application of painting and protective coatings (see Attachment D)

    3.8 Painting Touch-up and Repair

    Before application of any further coat of material, all damages of previous coat shall be repaired. All

    loose paint shall be removed and feather edged. All surface irregularities and contamination shall

    be removed.

    If the surface being prepared lies adjacent to a sound surface which is to be repaired, the surface

    preparation shall overlap the coated surface by at least 25mm.The remainder of existing coated surface shall be properly protected with shields or screens to

    prevent any possible damage to the coating.

    Area with inadequate coating thickness shall be thoroughly cleaned and if necessary abraded.

    Additional coat shall be applied blending in with the final coating on adjoining areas.

    3.9 Finish Colour

    The finish painting colour shall be as detailed in Table 1 and 2 of section 7.2 of COMPANY

    specification (COM-SU-2.02-A) on Materials and application of painting and protective coatings

    (see Attachment D)

    3.10 Coating Thickness

    The coating thickness shall be as detailed in APPENDIX B of COMPANY specification (COM-SU-

    2.02-A) on Materials and application of painting and protective coatings (see Attachment D)

    3.11 Records

  • 5/20/2018 Painting Procedure

    11/62

    COMPANY Contract No:

    FAC-2009-CW690260

    CONTRACTOR Contract No.:

    C0109 WAV

    Doc. No.: WAV-PR-GE200-016

    Rev. No.: B

    PAINTING PROCEDURE Page 11 of 19

    This is a CONFIDENTIAL document and remains the sole property of WAV. It shall not be shown to Third Parties nor used for purposes other than those for which it is intended .

    All quality assurance records generated during blasting and painting shall be reviewed and

    approved by the QA/QC Manager or his representative and shall be maintained and controlled by

    Field Engineer.

    The quality assurance records that will be generated during the blasting and painting operations

    are as follows.

    WAV-SF-Q-218 Painting Qualification Test Report (Attachment A)

    WAV-SF-Q-041 Daily Blasting and Painting Report (Attachment B)

    WAV-SF-Q-216 Final Painting Acceptance Report (Attachment C)

    4.0 INSPECTION FREQUENCY

  • 5/20/2018 Painting Procedure

    12/62

    COMPANY Contract No:

    FAC-2009-CW690260

    CONTRACTOR Contract No.:

    C0109 WAV

    Doc. No.: WAV-PR-GE200-016

    Rev. No.: B

    PAINTING PROCEDURE Page 12 of 19

    This is a CONFIDENTIAL document and remains the sole property of WAV. It shall not be shown to Third Parties nor used for purposes other than those for which it is intended .

    The frequency of inspection shall be as detailed in the inspection frequency matrix below

    INSPECTION FREQUENCY MATRIX

    ITEM TEST TYPE METHOD FREQUENCY ACCEPTANCE

    CRITERIA

    CONSEQUENCES

    1 Environmental

    Conditions

    Relative humidity,

    Dew point Ambient

    and steel

    temperature

    Start of each

    shift and every 3

    hours onward

    30C of

    dew point temp.

    No blasting or

    painting

    2 VisualExamination

    Visual Examinationfor contamination

    matter, sharp

    edges, weld

    spatters, silvers,

    rust grade etc.

    100% visual ofall surfaces spot

    check

    Impurities free To be removed

    3 Surface

    preparation and

    cleanliness

    As per COMPANY

    Spec. COM-SU-

    2.02-A

    100% visual of

    all surfaces, spot

    check

    As per COMPANY

    Spec. COM-SU-

    2.02A

    Re-cleaning or Re-

    blasting

    4 Roughness Comparator or

    Profile thickness

    gauge

    Each component

    or once per 10m

    As COMPANY

    Spec. COM-SU-

    2.02A

    Re-blasting

    5 Visual

    examination of

    coating

    Visual to determine:

    curing,

    contamination,

    solvent retention,

    pinholes/popping,

    sagging, surface

    defects

    100% visual of

    surface after

    each coat

    Irregularities Free Remove or Repair

    6 Film Thickness DFT Thickness

    Measurement

    5 points average Thickness as per

    COMPANY Spec.

    COM-SU-2.02A

    Recoat, Repair or

    additional coat

  • 5/20/2018 Painting Procedure

    13/62

    COMPANY Contract No:

    FAC-2009-CW690260

    CONTRACTOR Contract No.:

    C0109 WAV

    Doc. No.: WAV-PR-GE200-016

    Rev. No.: B

    PAINTING PROCEDURE Page 13 of 19

    This is a CONFIDENTIAL document and remains the sole property of WAV. It shall not be shown to Third Parties nor used for purposes other than those for which it is intended .

    ATTACHMENTS

  • 5/20/2018 Painting Procedure

    14/62

    COMPANY Contract No:

    FAC-2009-CW690260

    CONTRACTOR Contract No.:

    C0109 WAV

    Doc. No.: WAV-PR-GE200-016

    Rev. No.: B

    PAINTING PROCEDURE Page 14 of 19

    This is a CONFIDENTIAL document and remains the sole property of WAV. It shall not be shown to Third Parties nor used for purposes other than those for which it is intended .

    ATTACHMENT A- Painting Qualification Test Report

  • 5/20/2018 Painting Procedure

    15/62

    West African Venture Limited

    Project Title :

    Project No : Report No : PQTR-

    Client : Date :

    Location :

    PAINTING DETAIL

    A Test Panel Dimensions:

    B

    Item

    1 Abrasive

    2 Primer Coat

    3 Intermediate Coat

    4 Top / Single Coat

    Material Safety Datasheets for Paint and Abrasive

    Manufacturers latest recommendations for Application

    JSA for Joint Coating

    Oil trap checked for cleanliness

    Surface preparation clean and dry

    Surface Temperature a minimum 3 C above the Dew Point

    Relative Humidity shall not exceed 90% during primer application

    Pipe Coating to Rough Abrasion

    Abrasive Type:

    Abrasive Size:

    Surface Profile required 37 to 60 micron.

    Surface preparation Standard Archived : SSPC SP 5 SSPC SP 10

    Primer Coat Intermediate Coat

    Top Coat / Single Coat

    Paints shall be uniform applied by spray in accordance with the Manufacturers recommendations

    Painting shall be uniformly applied without runs, sags, solvent blister dry spray other blemishes.

    The spray shall be held no closer then 200mm or more then 600mm from the surface.

    Spray gun will be held angle to the substrate.

    Each pass shall over lap the previous one by 50% overlapping.

    Paint shall be rotected from rain, contamination and condensation until it is com letel dr .

    PAINTING QUALIFICATION TEST REPORT

    Product NameManufacture Product Type Applicator Name Remark

    Value

    Test Part

    Product Data

    JS

    Environmental Condition

    Status

    Description

    Part A Part B

    Surface Preparation

    DescriptionItem

    Mixing Part

    A

    Application

    Mixing

    Overcoat and Top coat shall be applied in accordance with the minimum and maximum over

    coating interval time specified by the manufacture.

    Visual inspection shall be done on all layer of paint application.

    Irregularities shall be rectified before application of next layer.

    ENVIRONMENTAL CONDITION Applicable Not Applicable

    Test Date: Test Time: Test Requirement:

    No Surface temperature

    1st Primer Coat

    2nd Intermediate Coat

    3rd Top / Single Coat

    HOLIDAY DETECTION : Applicable Not Applicable

    Test Date: Test Time: Test Requirement:

    ADHESION TEST Applicable Not Applicable

    Test Date: Test Time: Test Requirement:

    Test

    A

    B

    DRY FILM THICKNESS Applicable Not Applicable

    Test Date: Test Time: Test Requirement:

    Average DFT

    Primer Coat

    Intermediate Coat

    Top Coat / Single Coat

    SEAWATER IMMERSION TEST Applicable Not Applicable

    Test Date: Test Time: Test Requirement:

    Result as per attached Seawater Immersion Test Report.

    AGEING RESISTANCE TEST Applicable Not Applicable

    Test Date: Test Time: Test Requirement:

    Result as per attached Ageing Resistance Test Report.

    CATHODIC DISBONDING TEST Applicable Not Applicable

    Test Date: Test Time: Test Requirement:

    Result as per attached Cathodic Disbonding Test Report.

    Manufacturer / Vendor Representative WAV Representative Client Representative

    Inspector: Inspector: Inspector:

    Signature: Signature: Signature:

    Date: Date: Date:

    DFT 5

    Test Location Pipe temperature

    DFT 2 DFT 3 DFT 4Product namePaint Coats

    VERIFICATION

    DFT 1

    Remark

    Remark

    Time Dry Bulb Wet Bulb Relative Humidity

    Operator NameStatusMethodSerial NoModelMake

    Status

    DateVoltsTravel

    Coating Temperature Failure Mode Value psi/s Value Mpa/s

    Paint coats

    H

    G

    F

    E

    D

    C

    B

    Form No. WAV-SF-Q-218

  • 5/20/2018 Painting Procedure

    16/62

    COMPANY Contract No:

    FAC-2009-CW690260

    CONTRACTOR Contract No.:

    C0109 WAV

    Doc. No.: WAV-PR-GE200-016

    Rev. No.: B

    PAINTING PROCEDURE Page 16 of 19

    This is a CONFIDENTIAL document and remains the sole property of WAV. It shall not be shown to Third Parties nor used for purposes other than those for which it is intended .

    ATTACHMENT B- Daily Blasting & Painting Report

  • 5/20/2018 Painting Procedure

    17/62

    West African Venture L imited

    Project Title :

    Project No : Report No : DBPR-

    Client : Date : _____________________

    Location :

    Workshop Offshore Manufacture

    Product identity : ______________________________________________________________________________________

    Item / Joint No. :

    1. _______________________________________ 5. _______________________________________

    2. _______________________________________ 6. _______________________________________

    3. _______________________________________ 7. _______________________________________

    4. _______________________________________ 8. _______________________________________

    Coating Type : Paint Epoxy Field Joint Coating Fusion Bonding Epoxy

    Others :

    SP 11 SP 3 SP 2 SP 1

    Solvent clean SManual Clean StdPower Brush Standard RequiredBlast Standard Required

    DAILY BLASTING & PAINTING REPORT

    SP 10 SP 5

    ras ve ype: ar me:

    Abbrasive Size: End Time:

    Surface Profile :

    Holiday Detection : Yes No K.V. Required : _____________ Kv Brush Type Ring Type

    Time

    Start Paint Time : Finish Paint Time :

    ReCo

    Part A Part B Min Max By Layer Tim

    1st Coat

    2nd Coat

    3rd Coat

    4th Coat

    Comments :

    WAV QA/QC Inspector Clients Representative

    Signature : _________________________________________ Signature : _________________________________________

    Name : ____________________________________________ Name : ____________________________________________

    Date : _____________________________________________ Date : _____________________________________________

    Paint Name Colour Application MethodBatch No

    Surface Temperture(CDew Point (C)

    VERIFICATION

    No Coat

    Dry Bulb (C)

    DFT DFT Average

    Total

    Relative Humidity %Wet Bulb(C)

    Form No: WAV-SF-Q-041

  • 5/20/2018 Painting Procedure

    18/62

    COMPANY Contract No:

    FAC-2009-CW690260

    CONTRACTOR Contract No.:

    C0109 WAV

    Doc. No.: WAV-PR-GE200-016

    Rev. No.: B

    PAINTING PROCEDURE Page 18 of 19

    This is a CONFIDENTIAL document and remains the sole property of WAV. It shall not be shown to Third Parties nor used for purposes other than those for which it is intended .

    ATTACHMENT C- Final Painting Acceptance Report

  • 5/20/2018 Painting Procedure

    19/62

    West African Venture Limited

    Project Title :

    Project No : Report No : FPAR-

    Client : Date : ______________________

    Location :

    Product Identity

    Project :

    Client :

    Contractor :

    Platform :

    Material :

    Piece Mark / Spool No :

    Refer Drawing No:

    Refer Daily Blasting and Coating Report No: DBCR:

    SURFACE PREPRATION

    Surface Prepration :

    Abrasive Type :

    Size:

    FINAL PAINTING ACCEPTANCE REPORT

    Surface Profile:

    PAINTING APPLICATION

    Paint System :

    Application Method :

    Start Date :

    End Date :

    1st Coat

    2nd Coat

    3rd Coat

    4th Coat

    WEATHER CONDITION

    No Coat

    1st Coat

    2nd Coat

    3rd Coat

    4th Coat

    Comments :

    WAV QA/QC Inspector Clients Representative

    Signature : _________________________________________ Signature : _________________________________________

    Name : ____________________________________________ Name : ____________________________________________

    Date : _____________________________________________ Date : _____________________________________________

    Batch NoColour

    DFT AverageVISUAL

    Part A Part B Total By Layer

    Dry Bulb (C)

    VERIFICATION

    Wet Bulb(C) Relative Humidity % Dew Point(C) Sur face Tempertur e(C)

    No Coat Paint Name

    Form No: WAV-SF-Q-216

  • 5/20/2018 Painting Procedure

    20/62

    COMPANY Contract No:

    FAC-2009-CW690260

    CONTRACTOR Contract No.:

    C0109 WAV

    Doc. No.: WAV-PR-GE200-016

    Rev. No.: B

    PAINTING PROCEDURE Page 20 of 19

    This is a CONFIDENTIAL document and remains the sole property of WAV. It shall not be shown to Third Parties nor used for purposes other than those for which it is intended .

    ATTACHMENT D- COM-SU-2.02-A

  • 5/20/2018 Painting Procedure

    21/62

    October 2007 2007 Chevron USA Inc. All rights reserved. 1 of 42

    This document is the confidential property of Chevron USA Inc. Neitherthe whole nor any part of this document may be disclosed to any thirdparty without the prior written consent of Chevron USA Inc. Neither thewhole nor any part of this document may be reproduced, stored in anyretrieval system or transmitted in any form or by any means (electronic,mechanical, reprographic, recording or otherwise) without the prior writ-ten consent of Chevron USA Inc.

    COM-SU-2.02-A

    MATERIALS AND APPLICATION OF PAINTING AND PROTECTIVE COATINGS

    APPLICATIONS: TOPSIDES, FIXED PLATFORMS

  • 5/20/2018 Painting Procedure

    22/62

    Materials and App li cat ion of Paint ing and Protec tive Coat ings COM-SU-2.02-A

    October 2007 2007 Chevron USA Inc. All rights reserved. 2 of 42

    CONTENTS

    1.0 Scope ..........................................................................................................................4

    2.0 References ..................................................................................................................4

    2.1 ......Purchaser Documents ......................................................................................42.2 ......Industry Codes and Standards .........................................................................4

    3.0 General ........................................................................................................................5

    3.1 ......Accepted Brands ..............................................................................................53.2 ......Manufacturers Data Sheets .............................................................................63.3 ......Mixing of Coatings of Different Manufacturers .................................................63.4 ......Color .................................................................................................................63.5 ......Preconstruction Primers ...................................................................................63.6 ......Weld-Through Primers .....................................................................................63.7 ......Paint Free Surfaces ..........................................................................................73.8 ......Galvanizing .......................................................................................................7

    3.9 ......Pipe Penetration Sleeves .................................................................................83.10 ....Flanges .............................................................................................................83.11 ....Tank Interiors ...................................................................................................83.12 ....Fireproofing ......................................................................................................83.13 ....Valves, Actuators and Specialty Items .............................................................83.14 ....Vulcanized Rubber Coatings ............................................................................8

    4.0 Surface Preparation ...................................................................................................8

    4.1 ......Preparation for Abrasive Blasting .....................................................................84.2 ......Hand or Power Tool Cleaning ..........................................................................94.3 ......Abrasive Blasting ............................................................................................104.4 ......Galvanized and Aluminum Surfaces ..............................................................11

    5.0 Coating App lication .................................................................................................12

    5.1 ......General Application Requirements .................................................................125.2 ......Weather Conditions ........................................................................................125.3 ......Materials .........................................................................................................135.4 ......Mixing and Thinning .......................................................................................135.5 ......Shelf and Pot Life ...........................................................................................135.6 ......Spray Application ...........................................................................................135.7 ......Priming ...........................................................................................................145.8 ......Top-Coating ....................................................................................................145.9 ......Film Thickness ...............................................................................................145.10 ....Defects ...........................................................................................................15

    5.11 ....Touch-Up ........................................................................................................155.12 ....Brush or Roller Application .............................................................................15

    6.0 Inspection .................................................................................................................15

    6.1 ......General ...........................................................................................................156.2 ......Compressed Air Cleanliness ..........................................................................166.3 ......Abrasive Material ............................................................................................166.4 ......Environmental Conditions ..............................................................................16

  • 5/20/2018 Painting Procedure

    23/62

    Materials and App li cat ion of Paint ing and Protec tive Coat ings COM-SU-2.02-A

    October 2007 2007 Chevron USA Inc. All rights reserved. 3 of 42

    6.5 ......Surface Preparation (Including Touch-Up Preparation) .................................176.6 ......Coating Application ........................................................................................176.7 ......Inspection by Purchaser .................................................................................176.8 ......Coating Manufacturers Representatives .......................................................18

    7.0 Coating Systems ......................................................................................................18

    7.1 ......Coating Systems ............................................................................................187.2 ......Finish Color Schedule ....................................................................................18

    Appendices

    A Coat ing Select ion Guideline: Offshore Structures and Wharves ........................20

    B Coating System Data Sheets ...................................................................................23

  • 5/20/2018 Painting Procedure

    24/62

    Materials and App li cat ion of Paint ing and Protec tive Coat ings COM-SU-2.02-A

    October 2007 2007 Chevron USA Inc. All rights reserved. 4 of 42

    1.0 SCOPE

    This specification covers the surface preparation, materials, coating application and inspection

    requirements for coating the fabricated steel, equipment and appurtenances of offshore structures.

    2.0 REFERENCES

    1. Protective coatings shall comply with applicable federal, state, and local codes and regulationson surface preparation, coating application, storage, handling, safety, and environmental

    requirements, including the recommendations of Society for Protective Coatings (SSPC)

    PA Guide 3.

    2. The following documents are referenced herein and are considered part of this specification.

    3. Use the edition of each referenced document in effect on the date of the publication of this

    specification.

    2.1 Purchaser Documents

    COM-SU-5191 Coating Systems

    COM-EF-844 Coating Inspection Report FormsAny discrepancies or conflicts among the documents below and with Technical Requirements

    shall be called to the attention of the Purchaser for resolution.

    2.2 Industry Codes and Standards

    American Society for Testing and Materials (ASTM)

    A 90 Standard Test Method for Weight [Mass] of Coating on Iron and Steel

    Articles with Zinc or Zinc-Alloy Coatings

    A 123 Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and

    Steel Products

    A 143 Standard Practice for Safeguarding Against Embrittlement of Hot-DipGalvanized Structural Steel Products and Procedure for Detecting

    Embrittlement

    A 153 Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel

    Hardware

    A 385 Standard Practice for Providing High-Quality Zinc Coatings (Hot-Dip)

    D 4285 Standard Test Method for Indicating Oil or Water in Compressed Air

    D 4417 Standard Test Methods for Field Measurement of Surface Profile of Blast

    Cleaned Steel

    E 337 Standard Test Method for Measuring Humidity with a Psychrometer (theMeasurement of Wet- and Dry-Bulb Temperatures)

  • 5/20/2018 Painting Procedure

    25/62

    Materials and App li cat ion of Paint ing and Protec tive Coat ings COM-SU-2.02-A

    October 2007 2007 Chevron USA Inc. All rights reserved. 5 of 42

    National Association of Corrosion Engineers International (NACE)

    No. 1 (SSPC-SP 5) White Metal Blast Cleaning

    (Joint Surface Preparation Standard)

    No. 2 (SSPC-SP 10) Near-White Metal Blast Cleaning

    (Joint Surface Preparation Standard)

    No. 3 (SSPC-SP 6) Commercial Blast Cleaning

    (Joint Surface Preparation Standard)

    No. 4 (SSPC-SP 7) Brush-Off Blast Cleaning

    (Joint Surface Preparation Standard)

    RP0188 Discontinuity (Holiday) Testing of New Protective Coatings on

    Conductive Substrates

    Society for Protective Coatings (SSPC)

    PA 1 Shop, Field, and Maintenance Painting of Steel

    PA 2 Measurement of Dry Coating Thickness with Magnetic Gages

    PA Guide 3 A Guide to Safety in Paint Application

    SP 1 Solvent Cleaning

    SP 2 Hand Tool Cleaning

    SP 3 Power Tool Cleaning

    SP 5 (NACE No. 1) White Metal Blast Cleaning

    (Joint Surface Preparation Standard)

    SP 6 (NACE No. 3) Commercial Blast Cleaning

    (Joint Surface Preparation Standard)

    SP 7 (NACE No. 4) Brush-off Blast Cleaning(Joint Surface Preparation Standard)

    SP 10 (NACE No. 2) Near-White Metal Blast Cleaning

    (Joint Surface Preparation Standard)

    SP 11 Power Tool Cleaning to Bare Metal

    SP COM Surface Preparation Commentary for Steel and Concrete Substrates

    VIS 1 Guide and Reference Photographs for Steel Surfaces Prepared by

    Dry Abrasive Blast Cleaning

    3.0 GENERAL

    3.1 Accepted Brands

    1. Only specified coating systems from the Coating System Data Sheets shall be used, unless

    alternates are reviewed by Purchaser in writing.

    2. The Supplier shall only use coatings complying with federal, state and local air pollution

    regulations.

  • 5/20/2018 Painting Procedure

    26/62

    Materials and App li cat ion of Paint ing and Protec tive Coat ings COM-SU-2.02-A

    October 2007 2007 Chevron USA Inc. All rights reserved. 6 of 42

    3.2 Manufacturer s Data Sheets

    1. The latest issue of the coating manufacturers product data sheets, application instructions, and

    Material Safety Data Sheets shall be available at the painting site and complied with during

    painting operations.

    2. Inspection requirements are defined in Purchasers specification.

    3.3 Mixing of Coatings of Different Manufacturers

    1. Each multicoat system shall use materials from a single manufacturer unless reviewed by

    Purchaser in writing.

    2. Offsite equipment manufacturers shall use the same brand for a coating system as the prime

    Supplier unless reviewed by Purchaser in writing. In the prime Suppliers fabrication yards

    and offshore, only one manufacturer shall be used for each coating system.

    3.4 Color

    1. The finish coat color of external coating systems shall be per Section 7.2.

    2. Contrasting colors shall be used for each of the intermediate coats to allow inspection for full

    coverage.

    3. Finish colors for purchased equipment shall be specified on purchase orders.

    4. For a gray finish color, the intermediate color recommendations are beige for intermediate

    coat, with white for the second intermediate coat for four-coat systems.

    3.5 Preconst ruc tion Pr imers

    1. Inorganic zinc primers may be used as preconstruction primers but weld bevels must be free of

    primer before welding.

    2. This can be done by masking prior to coating or by grinding or sandblasting before welding.

    3. The coating-free area shall extend a minimum of two inches (5.08 cm) from the weld bevel.

    4. Non-inorganic zinc preconstruction primers shall be removed by blasting to bare metal prior to

    application of the required paint system.

    5. Supplier shall not apply successive coats over any non-inorganic zinc preconstruction primers

    in order to avoid undermining the protection provided by inorganic zinc primers.

    3.6 Weld-Through Pr imers

    1. Weld-through primers shall not be used unless welding qualification tests show no detrimental

    effects, such as unacceptable porosity or mechanical properties.

    2. The use of weld-through primers must be reviewed by the Purchaser in writing prior to their

    use.

    3. If the primers are accepted, inspection for weld bevel cleanliness shall be performed on

    production work prior to priming.

  • 5/20/2018 Painting Procedure

    27/62

    Materials and App li cat ion of Paint ing and Protec tive Coat ings COM-SU-2.02-A

    October 2007 2007 Chevron USA Inc. All rights reserved. 7 of 42

    3.7 Paint Free Surfaces

    The following surfaces shall not be abrasive blasted or painted unless otherwise specified:

    1. Concrete

    2. Galvanized steel

    3. Stainless steel4. MONEL

    5. COPPER or copper alloys

    6. Fiberglass reinforced plastic

    7. Aluminum weather jacketing of insulation

    8. Interior surfaces of piping and equipment

    9. Instruments, gauge glasses, nameplates

    10. Machined surfaces

    11. The top surface of the drilling skid beam (also known as the drilling skid rail) near the top

    surface of the drill deck should not be painted.

    3.8 Galvanizing

    1. Gratings, ladders, cages, stairways, handrails, handrail sockets, helideck apron frames and

    miscellaneous hardware shall be prepared for hot dipped galvanizing in accordance with

    ASTM A 385.

    2. These items shall be galvanized in accordance with ASTM A 123. The weight of the zinc

    coating shall be confirmed by testing to ASTM A 90.

    3. Hot dipped galvanizing of bolts, nuts, and washers shall conform to ASTM A 153 and

    ASTM A 143.

    4. Handrails and stairways shall be painted after galvanizing with Purchasers CoatingSystem 3.5 of Appendix A.

    5. The design of items requiring galvanizing shall take cognizance of maximum length, limited

    by the galvanizing process.

    6. Fabrication of items to be galvanized shall be completed (including cutting, welding and

    cleanup) prior to solvent cleaning and acid pretreatment, and galvanizing.

    7. Steel grating shall be banded prior to galvanizing.

    8. Banding shall be seal welded.

    9. Whenever possible, each item shall be galvanized in a single hot dip. The final surface shall be

    free of overlaps, spikes, teardrops, cracks or flakes.

    10. If weepholes are used to prevent overpressuring, they shall be sealed after galvanizing by a

    method reviewed by the Purchaser. Plastic and lead plugs are not acceptable.

    11. Galvanized parts shall be repaired with System 1.8.1 of Appendix A.

    a. Before application of the repair coating, surfaces shall be washed using fresh water.

    b. Rust and surface contaminants shall be removed in accordance with SSPC-SP 3.

    c. After removing contaminants, the parts shall be solvent washed.

  • 5/20/2018 Painting Procedure

    28/62

    Materials and App li cat ion of Paint ing and Protec tive Coat ings COM-SU-2.02-A

    October 2007 2007 Chevron USA Inc. All rights reserved. 8 of 42

    3.9 Pipe Penetrat ion Sleeves

    1. Pipe penetration sleeves shall be painted through finish coat prior to running pipe.

    2. Penetration sleeves should have a minimum 1 inch (2.54 cm) clearance on the radius between

    the inner diameter (ID) of the reinforcement and the outer diameter (OD) of the pipe for

    coating maintenance.

    3.10 Flanges

    Flange surfaces (excluding gasket surfaces) and bolt holes shall be coated with the primer and

    intermediate coats before assembly.

    3.11 Tank In ter iors

    Inside surfaces of manways, nozzles, bosses and other connections shall be blasted and coated

    with the same system as the internal surfaces of the tank or vessel.

    3.12 Fireproo fing

    1. Only proprietary fireproofing specified by the Purchaser shall be used.

    2. The primer specified in System 4.4 of Appendix Ashall be used.

    3. Exceptions to this must be reviewed by the Purchaser.

    3.13 Valves, Actuators and Specialty Items

    1. Valves, actuators and specialty items supplied by Supplier without a coating system that

    conforms to this specification shall be blasted and recoated.

    2. In cases where removing the existing coating is not possible, use System 3.7 from

    Appendix A.

    3.14 Vulcanized Rubber Coatings

    1. Vulcanized neoprene rubber is used on risers in splash zone areas. These coatings are appliedby the manufacturer and not on site. The manufacturers have their own proprietary processes

    developed for the application and vulcanization of the rubber. The rubber shall have the

    following properties:

    2. Coating System 4.3 in Appendix Aof this specification is used for vulcanized rubber.

    4.0 SURFACE PREPARATION

    4.1 Preparat ion for Abrasive Blasting

    1. Sharp edges, such as those occurring in rolled structural members as well as those resulting

    from flame cutting, welding, etc., shall be removed by any suitable method such as a soft

    grinding wheel before sandblasting and application of any coat of paint (refer to SSPC-SP 5

    and SSPC-SP COM).

    ShoreA Durometer 65 5

    Tensile strength > 2000 psi

    Elongation > 400%

    Tear strength > 40 N/mm

  • 5/20/2018 Painting Procedure

    29/62

    Materials and App li cat ion of Paint ing and Protec tive Coat ings COM-SU-2.02-A

    October 2007 2007 Chevron USA Inc. All rights reserved. 9 of 42

    2. Neither welding, nor grinding, including cosmetic grinding, is permitted on the pressure

    resisting components and welds of pressure vessels and piping after hydrostatic testing, unless

    reviewed in writing by the Purchaser.

    3. Surfaces to be coated shall be clean of contaminants that would affect the integrity of the

    coating system.

    a. Prior to surface preparation, the surfaces shall be cleaned as necessary to remove oil,grease, dirt, salts or other foreign material.

    b. This cleaning shall be by appropriate detergent and/or solvent cleaning.

    c. Detergent or solvent cleaning shall be performed as outlined in SSPC-SP 1, or NACE

    equivalent.

    d. Solvents used to clean stainless steel shall be free of substances such as chlorides, sulfur,

    halogens, or metallic pigments.

    4. The presence of oil shall be checked by shining a black light on the steel surface.

    5. Test surfaces that will be coated prior to abrasive blasting or surface preparation for chloride,

    sulfate, and nitrate salt contamination using the CHLOR*TEST test kit or equivalent.

    a. Test sites shall be selected to be representative of the surface as a whole.

    b. Test at the rate of three tests for the first 1000 ft2(93 m2) or part thereof, and one test for

    each additional 3000 ft2(279 m2)or part thereof.

    c. For immersion service, the following are the maximum acceptable levels:

    (1) Chloride: 3 g/cm2

    (2) Nitrate: 5 g/cm2

    (3) Sulfate: 10 g/cm2

    d. For non-immersion service, the following are the maximum acceptable levels:

    (1) Chloride: 5 g/cm2

    (2) Nitrate: 10 g/cm2

    (3) Sulfate: 15 g/cm2

    e. Salt contaminated surfaces will require high-pressure water washing (minimum 3000 psi)

    20.7 MPa using high purity water or a solution of water and CHLOR*RIDsoluble salt

    remover or equivalent.

    f. Test and treat surface as required until test results are less than or equal to the limits listed

    in Section 4.1, item 5c.

    4.2 Hand or Power Tool Cleaning

    1. When reviewed, hand tool cleaning or power tool cleaning shall be per SSPC-SP 2,

    SSPC-SP 3, SSPC-SP 11, or NACE equivalent.

    2. Purchaser approval is required on a case by case basis prior to substituting power tool cleaning

    for abrasive blasting.

    3. When hand or power tool cleaning is required on stainless steel only stainless steel wire

    brushes that have not been previously used on carbon steel surfaces may be used.

  • 5/20/2018 Painting Procedure

    30/62

    Materials and App li cat ion of Paint ing and Protec tive Coat ings COM-SU-2.02-A

    October 2007 2007 Chevron USA Inc. All rights reserved. 10 of 42

    4.3 Abrasive Blasting

    1. Abrasive blasted surfaces shall be blasted in accordance with the SSPC or NACE blast

    specified on the Coating System Data Sheets in Appendix B.

    2. The anchor pattern shall be as specified in Appendix B.

    3. Abrasive blast cleaning shall be performed with a clean, sharp grade of abrasive.

    4. Only dry, grit-type abrasives shall be used. Grain size shall be suitable for producing the

    specified anchor profile.

    5. Abrasives shall be free of dust, dirt, and other foreign matter and shall be kept dry.

    6. Silica or other abrasive substances containing more than 1 percent crystalline silica shall not

    be used as an abrasive blasting material.

    7. If automatic blasting equipment is used, the abrasive mix shall be maintained so that a

    consistently sharp profile is produced. The mix shall be 75 percent grit, 25 percent shot.

    8. Prior to the start of blasting, the Supplier shall select an appropriate blast air pressure with

    abrasive and mesh size to attain the specified anchor pattern.

    9. The Supplier shall demonstrate to the Purchaser that the selected nozzle pressures and abrasiveshall provide the specified anchor pattern by blasting a representative piece of steel and

    measuring the anchor pattern using Testex Inc. Press-O-Filmtape or Purchaser-reviewed

    equal as described in ASTM D 4417 Method C.

    10. Any change in nozzle pressure, abrasive or mesh size shall be qualified in the same way prior

    to the change.

    11. Blast air pressure shall be a minimum of 90 psig unless the demonstration test proves

    acceptable otherwise.

    12. Weld areas shall be ground, chipped or wire brushed as necessary prior to blasting to remove

    rust, residual flux and weld spatter.

    13. Steel surface slivers, laminations, laps, scabs or seams exposed by blasting shall be reported tothe Purchaser, investigated, and repaired on any portion of the steel to be painted by the

    Supplier using rules from the applicable code for repairs prior to coating. Repaired areas shall

    be reblasted prior to coating.

    14. Prior to abrasive blasting, valves, sight glasses, name tags, machinery, electrical fixtures,

    stainless steel electrical control panels, etc., subject to damage from either the blast or from the

    abrasive material remaining shall be protected.

    15. When possible, name tags should be installed after painting is complete.

    16. If it is not possible to coat under tags, their edges shall be sealed with silicone to prevent

    moisture accumulation.

    17. Cadmium-plated, Teflon-coated, electroplated, metallized or other specially coated items

    shall not be blasted unless otherwise directed by Purchaser.

    18. Blasting shall be performed in dry weather. Dry blast cleaning operations shall not be

    conducted on surfaces exposed to rain, water spray, or any other moisture.

    19. Abrasive blast cleaning shall not be performed when the ambient or substrate temperature is

    less than 5F (1.5C) above the dew point temperature.

  • 5/20/2018 Painting Procedure

    31/62

    Materials and App li cat ion of Paint ing and Protec tive Coat ings COM-SU-2.02-A

    October 2007 2007 Chevron USA Inc. All rights reserved. 11 of 42

    20. Dew point temperature shall be determined by sling psychrometer in accordance with

    ASTM E 337 or equivalent electronic device, at the location where the work is being

    performed.

    21. Substrate temperature shall be determined with a surface thermometer.

    22. Blast cleaned surfaces that show evidence of rust bloom or that have been left uncoated more

    than four hours shall be re-cleaned to the specified degree of cleanliness prior to coating.23. After blasting and immediately before spraying, dust and loose residues shall be removed by

    brushing, blowing off with clean dry air, or vacuum cleaning.

    24. Blasting shall be accomplished so that previously painted surfaces are not contaminated by

    abrasive or blast wastes.

    25. No inhibitive washes or holding primers intended to prevent rusting shall be used after

    blasting.

    26. A minimum of 4 inches (10.16 cm) around the edge of blasted areas shall be left unprimed

    unless adjoining a coated surface.

    27. Subsequent blasting shall continue a minimum of 1 inch (2.54 cm) into the primed surfaces.

    28. These requirements are to ensure that no coating is applied over unblasted steel.

    29. The rough edge of the blasted coating shall be feather-edged by power or hand sanding with a

    grit wheel or sandpaper.

    30. When the coating is damaged down to the steel, spot cleaning is necessary.

    31. These damaged areas shall be cleaned by blasting or power tool cleaning. Purchaser approval

    is required on a case by case basis prior to substituting power tool cleaning for abrasive

    cleaning.

    32. After the metal surface has been cleaned, the edge of the surrounding coating shall be feather-

    edged to remove cracked, loose or damaged coating.

    33. Feather-edging shall be accomplished by power or hand sanding with a grit wheel orsandpaper.

    34. The prepared surface shall be free of loose, burnt, or blistered coating.

    35. Welding undercut and porosity shall be repaired prior to application of the coating.

    36. Blast cleaned surfaces shall be inspected for proper cleaning prior to painting. SSPC-VIS 1

    shall be used as a visual standard for confirming the degree of surface cleanliness.

    37. The anchor profile shall be verified in accordance with ASTM D 4417 Method C using either

    course or extra-course replica tape and a spring loaded micrometer.

    4.4 Galvanized and Aluminum Surfaces

    1. Aluminum surfaces which are specified to be painted shall be pretreated with an acid washbase.

    2. Galvanized surfaces which require painting shall be brush blasted (SSPC-SP 7) with fine grit

    or sand with lower nozzle pressure prior to painting.

    3. Galvanized pieces, such as gratings, which will be installed over steel surfaces to be painted,

    will interfere with painting and shall not be installed prior to painting the underlying steel.

    4. If the galvanized pieces must be installed before final painting, they shall first be brush blasted

    per item 2above and coated with the same intermediate coating as the underlying steel.

  • 5/20/2018 Painting Procedure

    32/62

    Materials and App li cat ion of Paint ing and Protec tive Coat ings COM-SU-2.02-A

    October 2007 2007 Chevron USA Inc. All rights reserved. 12 of 42

    5. The underlying steel shall be abrasive blasted and primed with the intermediate coat applied

    prior to installing (clipping) galvanized pieces over the steel.

    6. If the galvanized grating is welded to the underlying steel, welds shall be blasted with

    miniblaster to prevent damage to nearby painted surfaces.

    5.0 COATING APPLICATION

    5.1 General Appl icat ion Requirements

    1. Application shall be in accordance with SSPC-PA 1, the coating manufacturers published

    application instructions, MSDSs, and the requirements specified herein.

    2. Application equipment shall be as recommended by the coating manufacturer, shall be clean

    and in good condition, and shall be suitable for applying the coating as specified.

    3. The number of coats to be applied shall never be fewer than the number of coats required by

    this specification and shall have individual coat dry film thicknesses not less than the

    minimum thickness specified.

    4. Wet film thicknesses are to be verified at the start of work (until the painter is familiar with the

    paint and work) with a wet film thickness gauge.

    5. Thickness requirements shall be met with each coat and total thickness shall not be made-up

    in any one coat.

    5.2 Weather Conditions

    1. Painting done outdoors shall be done in daylight hours and completed at least one hour prior to

    sundown.

    2. Indoor painting is allowed 24 hours a day if the specified metal and air temperatures and

    relative humidity requirements are met inside the building or vessel during preparation,

    painting and curing.

    3. Coatings shall be applied within the environmental conditions shown in the coatingmanufacturers data sheets.

    4. No coating shall be applied when any of the following conditions are present:

    a. When the ambient or surface temperatures are above or below the manufacturers recom-

    mended temperature limits.

    b. The ambient or substrate temperature is less than 5F (1.5C) above the dew point temper-

    ature. Dew point temperature shall be determined by sling psychrometer in accordance

    with ASTM E 337 or equivalent electronic device, at the location where the work is being

    performed. Substrate temperature shall be determined with a surface thermometer.

    c. During strong or gusty conditions, particularly for spray application.

    d. During rain, snow, or fog, or on damp surfaces or surfaces that may have frost.5. If rain falls on painted surfaces prior to paint becoming rainproof, surfaces shall be reblasted

    and repainted.

  • 5/20/2018 Painting Procedure

    33/62

    Materials and App li cat ion of Paint ing and Protec tive Coat ings COM-SU-2.02-A

    October 2007 2007 Chevron USA Inc. All rights reserved. 13 of 42

    5.3 Materials

    1. Coating materials shall be furnished in the manufacturers unopened containers, clearly

    identifiable, and shall be kept covered, clean and protected. Materials older than the

    manufacturers recommended shelf life shall not be used.

    2. Solvents used for thinning shall be as recommended by the coating manufacturer.

    3. Materials shall be handled and stored in accordance with the manufacturers latest publishedinstructions and SSPC-PA 1 Article 5.1.

    5.4 Mixing and Thinning

    1. Components shall be thoroughly mixed as per recommendations noted in the manufacturers

    data sheets.

    2. Mixing shall be done in clean containers, free from traces of grease, other paints or

    contaminants.

    3. Containers shall be kept covered to prevent contamination by dust, dirt or stain.

    4. Paint shall be mechanically mixed in full batches.

    5. Multi-component coatings, such as inorganic zinc, epoxies and urethanes, shall have the

    components accurately measured according to the manufacturers directions.

    6. Mixing of partial kits is not acceptable.

    7. Thinning shall not exceed the allowable volatile organic compound (VOC) level for the

    coating used.

    5.5 Shelf and Pot Life

    1. Materials that have exceeded the coating manufacturers recommended shelf life shall not be

    used.

    2. The coating manufacturers recommended pot life shall not be exceeded. When this limit is

    reached, the spray pot shall be emptied and cleaned, and new material mixed.

    5.6 Spray Application

    1. Suppliers applicators shall be skilled in the proper application technique for each coating.

    Proper equipment, per the coating manufacturers data sheets, shall be used. Applicators or

    equipment failing to meet this requirement, to the Purchasers or the coating manufacturers

    satisfaction, shall be removed from coating application.

    2. Spray guns, lines, and pressure pots shall be cleaned prior to adding new material. The air

    caps, nozzles and needles shall be those recommended by the coating manufacturer for the

    material being sprayed.

    3. Moisture traps, separators and driers shall be installed between the air supply and the pressure

    pot. The drain valve must be kept open slightly to permit continuous draining of anycondensate during operations.

    4. Operating pressures shall comply with the recommendation of the coating manufacturer.

    Pressure pots shall be equipped with pressure regulators and gauges.

    5. Paint shall be applied in a uniform layer, with 50 percent overlapping of the previous pass.

    During application, the spray gun shall be held perpendicular to the surface being painted.

  • 5/20/2018 Painting Procedure

    34/62

    Materials and App li cat ion of Paint ing and Protec tive Coat ings COM-SU-2.02-A

    October 2007 2007 Chevron USA Inc. All rights reserved. 14 of 42

    5.7 Priming

    1. The specified coating system primer shall be applied within four hours from the time that

    surfaces are cleaned and before rusting, discoloration, or surface contamination occurs.

    2. Surfaces to be coated shall be clean, dust-free, and dry before application of any coating and

    shall meet applicable hand, power tool or abrasive blasting surface preparation requirements

    before priming.3. Care shall be exercised to prevent overspray, spillage or application of coatings to surfaces for

    which they are not intended. Skips, sags, and drips are to be repaired.

    4. Inorganic zinc primer shall be applied using an agitated pot.

    5.8 Top-Coating

    1. Each coat of paint shall be of contrasting color to indicate extent of coverage.

    2. Coatings shall be allowed to dry for at least the minimum time recommended by the paint

    manufacturer, considering temperature and humidity, before applying succeeding coats.

    3. Maximum overcoat time shall be limited to the manufacturers recommendation.

    4. When the maximum overcoat time has been exceeded, Supplier shall perform additional

    surface preparation as agreed to by Purchasers representative.

    5. Additional surface preparation shall include, but not be limited to, hand sanding, pressure

    washing, mist coat application, degreasing or reblasting.

    6. Prior to top-coating an inorganic zinc primer, the cure of the primer shall be verified. Inorganic

    primers that are properly cured will polish to bright metal without powdering or loss of

    material when firmly scraped with the edge of a coin.

    7. Inorganic zinc primers shall have overspray removed with a stiff bristle brush or wire screen

    and shall be clean and thoroughly cured prior to top-coating.

    8. When spray applying over inorganic zinc primers, a mist coat shall be used to avoid bubbling.

    The mist coat may be a thinned coat or may be applied by a quick pass of the spray gun priorto applying the full coat, but allowing sufficient time for solvent evaporation.

    5.9 Film Thickness

    1. Wet film thickness shall be checked during the application of each coat to assure the specified

    dry film thickness (DFT) will be met.

    2. Wet film thickness measurements are not suitable for some materials such as inorganic zinc

    primers, flake filled epoxies, etc.

    3. The DFT of each coat shall be checked in accordance with the procedures defined by

    SSPC-PA 2 using a magnetic gauge that has been properly calibrated.

    4. Coating thickness on stainless steel shall be checked using a Type 2 gauge suitable for use onnon-ferrous substrates. Measurements shall be taken after removal of dry spray and overspray.

    5. Gauges shall be adjusted to compensate for the substrate effect prior to application of any

    coating.

  • 5/20/2018 Painting Procedure

    35/62

    Materials and App li cat ion of Paint ing and Protec tive Coat ings COM-SU-2.02-A

    October 2007 2007 Chevron USA Inc. All rights reserved. 15 of 42

    5.10 Defects

    1. Coatings shall be free of defects such as runs, sags, pin holes, voids, blisters, wrinkles, mud

    cracking and bubbles.

    2. Dry spray and overspray shall be removed.

    3. The DFT of each coat shall not be outside the specified range.

    5.11 Touch-Up

    1. Prior to application of any coat, defects and damage to the previous coat(s) shall be repaired.

    Damage to finished work shall be thoroughly cleaned and recoated.

    2. Damaged areas shall be spot blast cleaned or power tool cleaned as necessary to restore any

    exposed steel to its original degree of cleanliness.

    3. Loose, cracked, and damaged coating shall be removed and the adjacent sound coating

    feathered back approximately 2 inches (5.08 cm) to form a uniform and smooth surface.

    4. Feathering shall be done by hand or power sanding with a grit wheel or sandpaper.

    5. The prepared surface shall be free of loose, burnt, or blistered coating.

    6. Unless specified otherwise, the coating used for repair shall be the same as the original and

    shall have the same DFT.

    5.12 Brush or Roller Application

    1. Written Purchaser approval is required before brush or roller application can be substituted for

    spray application.

    2. Inaccessible and restricted areas which prevent spray application of paint at the proper

    inclination angles shall be boxed in and seal welded prior to paint application.

    3. Welds which cannot be properly spray coated shall be brush or stripe coated with an reviewed

    coating before applying successive spray coats over the primer coating.

    4. Brushes shall be of a style and quality that will enable proper application of the coating.

    5. Brushing shall be done so that a smooth coat with uniform thickness is obtained. When

    applying coatings with a brush, multiple coats may be required to achieve the specified

    millage.

    6.0 INSPECTION

    6.1 General

    1. The Supplier shall perform inspections necessary to ensure that surface preparation and

    coating application complies with the requirements of this specification.

    2. The indicated records shall be kept daily and shall be submitted to the Purchaser at least

    weekly.

    3. Form COM-EF-844, or an reviewed equivalent Daily Coatings Inspection Report, shall be

    used to record this information.

    4. Purchasers authorized inspector(s) shall be given adequate notice prior to the start of surface

    preparation and coating application so that they can witness the work.

    5. The Purchasers authorized inspector shall have the option to witness or repeat any of these

    functions as necessary.

  • 5/20/2018 Painting Procedure

    36/62

    Materials and App li cat ion of Paint ing and Protec tive Coat ings COM-SU-2.02-A

    October 2007 2007 Chevron USA Inc. All rights reserved. 16 of 42

    6. Materials, equipment, and work shall be available to Purchasers authorized inspector(s).

    Purchasers authorized inspector(s) shall have access to the work site during the progress of

    the work and shall have the right to conduct any inspection or testing deemed necessary to

    ensure that the coatings are properly applied.

    7. Instruments used in inspection activities (e.g., thermometer, pyrometers, hygrometers,

    thickness gauges, profile gauges, and holiday detectors) shall be supplied by the Supplier in

    proper working order and calibrated prior to use.

    6.2 Compressed Air Cleanliness

    1. The cleanliness of compressed air supply used for blast cleaning, pneumatic tools, and spray

    equipment shall be checked for oil and water contamination in accordance with ASTM

    D 4285.

    2. Lines shall be tested separately.

    3. Testing shall be performed at the beginning and end of each work shift and at not less than

    four-hour intervals.

    4. In the event that contamination is discovered, necessary corrective actions shall be made and

    the air supply re-tested.

    5. Surfaces that are determined to have been blasted with contaminated air shall be cleaned with

    solvent and re-blasted with clean air and abrasive.

    6. Coatings that are determined to have been applied using contaminated air shall be removed

    and reapplied using clean air.

    6.3 Abrasive Material

    1. Recirculated shot and grit used for abrasive cleaning shall be tested for the presence of oil by

    immersing in water and checking for oil flotation.

    2. Tests shall be made at the start of blasting, at four-hour intervals thereafter, and at the end of

    blasting.3. If oil is evident, contaminated abrasive shall be replaced with clean abrasive and retested

    before proceeding.

    4. Steel blasted since the last satisfactory test shall be re-blasted.

    6.4 Envi ronmental Condit ions

    1. The following shall be checked and recorded at the beginning of each days operation and

    several times during the application process:

    a. ambient temperature

    b. relative humidity

    c. dew point

    d. moisture-free surface

    e. temperature of the surface to be coated

    2. These recordings shall be compared with criteria stated in item 4of Section 5.2in this

    specification and the manufacturers data sheets.

    3. If any criteria is exceeded, coating shall not be applied.

  • 5/20/2018 Painting Procedure

    37/62

    Materials and App li cat ion of Paint ing and Protec tive Coat ings COM-SU-2.02-A

    October 2007 2007 Chevron USA Inc. All rights reserved. 17 of 42

    6.5 Surface Preparation (Including Touch-Up Preparation)

    Immediately prior to priming, blasted surfaces shall be inspected by the following methods to

    verify that the specified surface preparation has been achieved:

    1. The anchor pattern shall be verified using Press-O-Film tape as described in ASTM D 4417

    Method C. The measurements shall be recorded on COM-EF-844.

    2. The degree of cleanliness shall be verified by comparison to SSPC-VIS 1. The cleanliness

    shall be recorded on COM-EF-844.

    6.6 Coating Application

    1. Dry film thicknesses shall be measured using a Microtest Magnetic Film Thickness Gauge or

    Purchaser-reviewed equal in accordance with SSPC-PA 2.

    2. The dry film thickness gauge shall be calibrated to the Purchasers satisfaction at the

    beginning of coating work and thereafter, regularly and whenever the Purchaser requests

    recalibration.

    3. Calibration of the film thickness gauge shall be made using the procedures in SSPC-PA 2.

    Record the thickness for each coat as work proceeds as well as the total thickness of eachfinished coating system on COM-EF-844.

    4. The entire surface of internal linings shall be inspected for holidays per NACE RP0188. When

    testing hard-to-get-at locations around appurtenances and nozzles, a small sponge attachment

    shall be used.

    5. Areas containing holidays shall be locally sandblasted to bare metal, recoated with the same

    system and retested for holidays. Detected holidays, correction and final holiday-free

    inspection shall be recorded on the COM-EF-844.

    6. The entire surface of splash zone coatings shall be inspected for holidays using a Purchaser-

    reviewed high voltage spark type detector. The voltage setting shall be determined based on

    Table 1 from NACE RP0188.

    7. Areas containing holidays shall be locally sandblasted to bare metal, recoated and reinspected.

    8. Areas found to contain runs, overspray, pinholes, sags and/or other signs of improper

    application shall be repaired in accordance with the manufacturers recommendations at the

    Suppliers expense.

    6.7 Inspection by Purchaser

    1. Work shall be subject to Purchaser inspection.

    2. The Purchasers inspectors shall be given at least two days notice prior to the start of surface

    preparation or coating application so that they can witness the work.

    3. Work shall not proceed past each of the inspection hold points defined below without the

    approval of the Purchasers inspectors.

    a. Completion of surface preparation, prior to primer application

    b. Completion of application of each coat (primer, intermediate and top-coat)

    c. Holiday detection and repair (internal linings and splash zone coatings only)

    d. Final acceptance of completed coating work

  • 5/20/2018 Painting Procedure

    38/62

    Materials and App li cat ion of Paint ing and Protec tive Coat ings COM-SU-2.02-A

    October 2007 2007 Chevron USA Inc. All rights reserved. 18 of 42

    4. The Purchasers inspectors shall ensure that necessary inspections are carried out at each hold

    point.

    5. Purchasers inspectors shall have the right to condemn any materials, equipment or work not

    in compliance with this specification.

    6. Necessary corrective actions shall be performed by the Supplier at Suppliers expense.

    7. Scaffolding, beam clamps, or any other equipment which will interfere with or damage coatingshall not be used.

    8. Supplier shall provide safe access to all areas for inspection by Purchaser.

    9. Supplier shall maintain the area to prevent contamination of coatings (i.e., wet down dusty

    fabrication and painting areas including the surrounding grounds when dry conditions are

    experienced).

    10. Prior to final coating acceptance, Supplier shall wash the entire platform with fresh water and

    apply a finish coat to areas stained and contaminated by grinding, weld spatter, general traffic,

    etc.

    6.8 Coating Manufacturers RepresentativesThe coating manufacturers representatives shall have access to the work site during the progress

    of the work to perform any inspection and testing deemed necessary to ensure that the coatings are

    properly applied.

    7.0 COATING SYSTEMS

    7.1 Coating Systems

    The Purchaser will specify the coating systems to be used from COM-SU-5191and the Technical

    Requirements.

    7.2 Fin ish Color Schedule

    1. Finish colors shall be as specified in Table 1. Color cards shall be submitted for the Purchaser

    Representatives approval prior to commencement of painting.

    2. Table 2shows the Federal color numbers for the color schedule.

    Table 1: Finish Colors (1 of 2)

    Splash zones (including steel grating at top of jacket and boat

    landing(s))

    Light silver grey

    Jacket, structural steel Light silver grey

    Deck surfaces Light silver grey

    Underside of deck surfaces White

    Vessels, tanks and heat exchanges Light silver grey

    Stacks Light silver grey

    Pumps, compressors, mixers, and drivers Light silver grey

    Piping

    General Light silver grey

    Control valves Light silver grey

    Fuel gas Light silver grey

  • 5/20/2018 Painting Procedure

    39/62

    Materials and App li cat ion of Paint ing and Protec tive Coat ings COM-SU-2.02-A

    October 2007 2007 Chevron USA Inc. All rights reserved. 19 of 42

    Firewater (including foam lines) Safety red

    Uninsulated valves, flanges, and other items in insulated piping

    systems

    Light silver grey

    Fire equipment Safety red

    Safety barriers Safety yellow

    Miscellaneous ungalvanized structural steel Light silver grey

    Galvanized steel

    Handrails, guardrails Safety yellow

    Sockets, stairways, railings Safety yellow

    Ladders, cages Safety yellow

    Helideck apron framing Safety yellow

    Electrical panels, equipment, housing, brackets, supports and

    other items

    Light silver grey

    Helideck background Light silver grey

    Helideck markings:

    (Per API RP 2L as modified below) Background

    Aiming circle letter H and boundary Black

    Walkways Black

    Logo and facility name Black (logo colors per Purchaser

    instructions)

    Helideck safety panels Safety yellow and black stripes

    Safety station locations Safety green

    Platform identification signs Black letters on white back-

    ground

    Potable water piping Safety green

    Physical hazards (including overheadobstructions, split pipe type deck curbing

    which can be walked on)

    Yellow and black stripes orchecks

    Walkways on deck plate Black

    Quarters building (exterior) White

    Cranes Safety yellow

    Subsea componentsdrilling templates, jacket guides, bottom

    riser sections and flanges, J-tube guides

    White

    Table 2: Federal Color Numbers for Color Schedule

    16440 Light silver grey

    11120 Safety red

    13591 Safety yellow

    17038 Black

    12300 Safety orange

    14120 Safety green

    17925 White

    Table 1: Finish Colors (2 of 2)

  • 5/20/2018 Painting Procedure

    40/62

    Materials and App li cat ion of Paint ing and Protec tive Coat ings COM-SU-2.02-A

    October 2007 2007 Chevron USA Inc. All rights reserved. 20 of 42

    APPENDIX A

    COATING SELECTION GUIDELINE:OFFSHORE STRUCTURES AND WHARVES

    EQUIPMENT COATINGSYSTEM TITLE

    CODE C/E: VESSELS AND HEAT EXCHANGERS (EXTERNAL COATINGS)

    Uninsulated carbon steel, to 200F (93C) 3.1 Self-cured inorganic zinc epoxy (high

    build)/aliphatic polyurethane

    Uninsulated 200400F (93204C)

    (carbon steel)

    2.5 Inorganic zinc/silicone acrylic

    Uninsulated 200400F (93204C)

    (austenitic SS)

    2.3 Silicone alkyd/silicone acrylic

    Uninsulated carbon steel, 4001000F

    (204538C)

    2.4 Self-cured inorganic zinc/silicone

    Uninsulated duplex and austenitic SS, to 200F

    (93C)

    2.1 Polyamide epoxy (high build)/aliphatic

    polyurethane

    Uninsulated duplex and austenitic SS

    4001000F (204538C)

    2.7 High temperature silicone

    Insulated, up to 425F (218C)

    (for carbon steel, duplex SS, and austenitic SS)

    12.1 Epoxies under insulation

    Insulated 4251000F (218 to 538C)

    (for carbon steel, duplex SS and austenitic SS)

    12.7 Thin film coating for use under insulation

    at high temperatures

    CODE D: TANKS (EXTERIOR)

    Uninsulated to 200F (93C) 3.1 Self-cured inorganic zinc/epoxy (high

    build)/aliphatic polyurethane

    Insulated, up to 425F (218C) 12.1 Epoxies Under Insulation

    Insulated, 4251000F (218538C)

    (for carbon steel, duplex SS and austenitic SS)

    12.7 Thin film coating for use under insulation

    at high temperatures

    CODE G/K: PUMPS, TURBINES, COMPRESSORS AND DRIVERS

    Uninsulated, to 200F (93C) 3.7 Manufacturers standard/universal primer

    epoxy (high build)/aliphatic polyurethane

    Uninsulated, 2001000F (93538C) 2.4 Self-cured inorganic zinc/silicone

    Insulated pumps and turbines, to 425F (218C) 12.1 Epoxies under insulation

    Motors or engines 3.7 Manufacturers standard/universal primer/

    aliphatic polyurethane

    Externally insulated exhaust ducts to 425F

    (218C) (carbon steel type)

    12.1 Epoxies under insulation

  • 5/20/2018 Painting Procedure

    41/62

    Materials and App li cat ion of Paint ing and Protec tive Coat ings COM-SU-2.02-A

    October 2007 2007 Chevron USA Inc. All rights reserved. 21 of 42

    CODE J: INSTRUMENTS

    Instrument supports (galvanized steel) 3.6 Polyamide epoxy (high build) aliphatic

    polyurethane

    Weatherproof housings (steel) 3.1 Self-cured inorganic zinc/epoxy (high

    build)/aliphatic polyurethane

    Instrument tubing (stainless) None

    Instruments (galvanized or aluminum) None

    CODE L: PIPING (INCLUDING VALVES AND FITTINGS)

    Uninsulated carbon steel to 200F (93C) 3.1 Self-cured inorganic zinc/epoxy (high

    build)/aliphatic polyurethane

    Uninsulated 200400F (93204C)

    (carbon steel)

    2.5 Inorganic zinc/silicone acrylic

    Uninsulated 200400

    F (93

    204

    C)(austenitic SS) 2.3 Silicone alkyd/silicone acrylic

    Uninsulated carbon steel, 4001000F

    (204538C)

    2.4 Self-cured inorganic zinc/silicone

    Uninsulated duplex and austenitic SS, to 200F

    (93C)

    2.1 Polyamide epoxy (high build)/aliphatic

    polyurethane

    Uninsulated duplex and austenitic SS above 400F

    (204C)

    2.7 High temperature silicone

    Insulated, up to 425F (218C) (for carbon steel,

    duplex SS, and austenitic SS)

    12.1 Epoxies under insulation

    Insulated, 425F to 1000F (218 to 538C)

    (for carbon steel, duplex SS and austenitic SS)

    12.7 Thin film coating for use under insulation

    at high temperatures

    CODE M: STRUCTURAL

    Jacket above splash zone, deck, modules to 200F

    (93C)

    3.1 Self-cured inorganic zinc/epoxy (high

    build)/aliphatic polyurethane

    Jacket or deck above splash zone, uninsulated,

    200400F (93204C)

    2.5 Inorganic zinc/silicone acrylic

    Jacket or deck above splash zone, uninsulated,

    4001000(204538C)F

    2.4 Self-cured inorganic zinc/silicone

    Jacket splash zone: structural members, conduc-

    tors, J-tubes, barge bumpers, riser guards, boat

    landings, pump casings (external), etc.

    4.1 Splash zone coatings

    Jacket splash zone: appurtenances 4.1 Splash zone coatings

    Galvanized floor grating repair 1.8.1 Aluminum mastic epoxy primer

    Fireproof steel 4.4 Polyamide epoxy/fireproofing/polyamide

    epoxy (high build)/aliphatic polyurethane

    Risers 4.3 Vulcanized neoprene for splash zone

    EQUIPMENTCOATING

    SYSTEMTITLE

  • 5/20/2018 Painting Procedure

    42/62

    Materials and App li cat ion of Paint ing and Protec tive Coat ings COM-SU-2.02-A

    October 2007 2007 Chevron USA Inc. All rights reserved. 22 of 42

    Riser clamps:Exteriorin splash zone

    Interiorvulcanized neoprene

    (all clamps)

    Hinges(in splash zone)

    4.1

    4.3

    1.8.1

    Splash zone coatings

    vulcanized neoprene for splash zones

    Aluminum mastic epoxy primer

    Galvanized stairways, ladders, handrails,

    helideck apron frame, etc.

    3.6 Polyamide epoxy, aliphatic polyurethane

    Floor plate 4.6 Epoxy non-skid

    Barge bumpers: Exterior

    Interior

    4.1

    1.4

    Splash zone coatings

    polyamide epoxy

    CODE P: ELECTRICAL EQUIPMENT

    Galvanized or aluminum equipment None (We recommend not coating.)

    Steel 3.1 Self-cured inorganic zinc/polyamide epoxy

    (high build)/aliphatic polyurethane

    Electrical supports (galvanized steel) 3.5 Epoxy mastic/polyamide epoxy (highbuild)/aliphatic polyurethane

    CODE S: MISCELLANEOUS EQUIPMENT

    Subsea completion equipment

    to 200F (93C)

    above 200F (93C)

    8.5

    8.5

    High temperature immersion coatings

    High temperature immersion coatings

    Skim pile, pump caissons:

    External

    External

    Internal

    3.1

    4.1

    1.4

    Above splash zone

    Splash zone coatings

    Polyamide epoxy (above and below

    caisson bioshield coatings)

    Pump column pipes: internal and external 1.4 Polyamide epoxy

    CODE T: TANK OR VESSEL (INTERNAL LININGS)

    Produced water and seawater to 180F (82C) 8.5 High temperature immersion coatings

    Potable water service 8.3 FDA approved epoxy

    Crude oil and produced water to 200F (93C) 8.5 High temperature immersion coatings

    Crude oil and produced water 200249F

    (93120C) w/o cathodic protection

    8.5 High temperature immersion coatings

    Crude oil and produced water 200249F

    (93120C) with cathodic protection

    8.5 High temperature immersion coatings

    Crude oil and produced water 250300F

    (121149C)

    8.5 High temperature immersion coatings

    Diesel storage 8.7 Epoxy phenolic

    EQUIPMENTCOATING

    SYSTEMTITLE

  • 5/20/2018 Painting Procedure

    43/62

    Materials & Appl ication of Painting & Protective Coatings COM-SU-2.02-A

    APPENDIX BChevron Coating System Data Sheets

    October 2007 2007 Chevron USA Inc. All rights reserved. Page 23 of 42

    Coating System 1.4 Polyamide Epoxy (primer only)

    Surface Preparation: SSPC-SP10 (NACE No. 2) near-white metal blast finish.

    Anchor Pattern: 1.5 - 2.5 mils

    Primer Tie-Coat Top-Coat

    Paint Polyamide Epoxy - -

    DFT (mils) 3.0 - 4.0 - -

    Total DFT (minimum): 3.0 mils

    Touch-Up: Use this system.

    Specific Notes:

    (a) Where moisture will tend to collect (such as at insulation support rings) use 2 coats ofPolyamide Epoxy.

    (b) For Duplex Stainless Steels, document/record the chloride content of the polyamide epoxy.Polyamide Epoxy shall not contain iron oxide pigment.

    Acceptable Brands:

    Manufacturer Primer Tie-Coat Top-Coat

    Ameron Amercoat 385 - -

    Carboline Carboguard 890 - -Hempel 15570 - -International Interseal 670HS - -Jotun Penguard Express - -Sherwin Williams Epoxy Primer

    B67R5/B67V5- -

    Sigma SigmaCover 280 - -

  • 5/20/2018 Painting Procedure

    44/62

    Materials & Appl ication of Painting & Protective Coatings COM-SU-2.02-A

    October 2007 2007 Chevron USA Inc. All rights reserved. Page 24 of 42

    Coating System 1.8.1 Epoxy Mastic Aluminum Filled Primer for Galvanizing Repair

    Surface Preparation: SSPC-SP6 (NACE No. 3) commercial blast finish.SSPC-SP11 power tool cleaning is acceptable on a case by case basiswith prior Company approval.

    Anchor Pattern: 1.5- 2.5 mils

    Primer Tie-Coat Top-Coat

    Paint Epoxy Mastic Aluminum - -

    DFT (mils) 5.0 - 6.0 - -

    Total DFT (minimum): 5.0 mils

    Touch-Up: Use this system.

    Specific Notes:

    Acceptable Brands:

    Manufacturer Primer Tie-Coat Top-Coat

    Ameron Amerlock 400 AL - -CarbolineHempelInternational

    Jotun

    Carbomastic 1545880 ALUInterseal 670 HS AL

    Primastic Universal

    ---

    -

    ---

    -Sherwin Williams Epoxy Mastic Aluminum IIB62S100/BV100

    - -

    Sigma TCP Aluminum 7477 - -

  • 5/20/2018 Painting Procedure

    45/62

    Materials & Appl ication of Painting & Protective Coatings COM-SU-2.02-A

    October 2007 2007 Chevron USA Inc. All rights reserved. Page 25 of 42

    Coating System 2.1 Polyamide Epoxy (high build) / Aliphatic Polyurethane

    Surface Preparation: SSPC-SP10 (NACE No. 2) near-white blast finish.

    Anchor Pattern: 2.0 3.0 mils

    Primer Tie-Coat Top-Coat

    Paint Epoxy-Polyamide

    (high build)

    - Aliphatic