AURUM – PHASE 02 – Photo Report
• Key Plan showing the Camera positions , Click on the Icon to review respective status:
1
2
3
5
4
6
AURUM_Photo Report - Phase 02
![Page 2: Pacifica - Aurum Pride Towers Photos](https://reader031.fdocuments.in/reader031/viewer/2022030122/58a2fda81a28ab5d1c8b6e55/html5/thumbnails/2.jpg)
Key Plan
Comments :
• TOWER-A&B, BLOCKWORK, PLASTERINGB WORK IN PROGRESS.
Phase 02 – Photo report Position - 01
12
3
5
4
6
AURUM_Photo Report - Phase 02
![Page 3: Pacifica - Aurum Pride Towers Photos](https://reader031.fdocuments.in/reader031/viewer/2022030122/58a2fda81a28ab5d1c8b6e55/html5/thumbnails/3.jpg)
Key Plan
Comments :
• Tower A : 8th & 9th , 10th floor Block work & 2nd and 3rd floor plastering work in progress.
Phase 02 – Photo report Position - 02
12
3
5
4
6
AURUM_Photo Report - Phase 02
![Page 4: Pacifica - Aurum Pride Towers Photos](https://reader031.fdocuments.in/reader031/viewer/2022030122/58a2fda81a28ab5d1c8b6e55/html5/thumbnails/4.jpg)
Key Plan
Comments :
• Tower A & D ; Block work , Plastering work in progress
Phase 02 – Photo report Position - 03
12
3
5
4
6
AURUM_Photo Report - Phase 02
![Page 5: Pacifica - Aurum Pride Towers Photos](https://reader031.fdocuments.in/reader031/viewer/2022030122/58a2fda81a28ab5d1c8b6e55/html5/thumbnails/5.jpg)
Key Plan
Comments :
• Tower D : 10th,11th,12th,14th floor block work and 1st and 2nd floor Plastering work is in progress.
Phase 02 – Photo report Position - 04
12
3
5
4
6
AURUM_Photo Report - Phase 02
![Page 6: Pacifica - Aurum Pride Towers Photos](https://reader031.fdocuments.in/reader031/viewer/2022030122/58a2fda81a28ab5d1c8b6e55/html5/thumbnails/6.jpg)
Key Plan
Comments :
• Tower A : 8th & 9th , 10th floor Block work & 2nd and 3rd floor plastering work in progress.
Phase 02 – Photo report Position - 05
12
3
5
4
6
AURUM_Photo Report - Phase 02
![Page 7: Pacifica - Aurum Pride Towers Photos](https://reader031.fdocuments.in/reader031/viewer/2022030122/58a2fda81a28ab5d1c8b6e55/html5/thumbnails/7.jpg)
Key Plan
Comments :
• Tower B : 14th & 15th floor Block work and 5th 6th floor plastering work is in progress.
Phase 02 – Photo report Position - 06
12
3
5
4
6
AURUM_Photo Report - Phase 02
![Page 8: Pacifica - Aurum Pride Towers Photos](https://reader031.fdocuments.in/reader031/viewer/2022030122/58a2fda81a28ab5d1c8b6e55/html5/thumbnails/8.jpg)
Key Plan
Comments :
• RETAINING WALL FOOTING AND STARTER- REINFORCEMENT AND CONCRETE IN PROGRESS.
Phase 02 – Photo report
12
3
5
4
6
AURUM_Photo Report - Phase 02
![Page 9: Pacifica - Aurum Pride Towers Photos](https://reader031.fdocuments.in/reader031/viewer/2022030122/58a2fda81a28ab5d1c8b6e55/html5/thumbnails/9.jpg)
Key Plan
Comments :
PODIUM RAMP-1 SHUTTERING IN PROGRESS
Phase 02 – Photo report
12
3
5
4
6
AURUM_Photo Report - Phase 02
![Page 10: Pacifica - Aurum Pride Towers Photos](https://reader031.fdocuments.in/reader031/viewer/2022030122/58a2fda81a28ab5d1c8b6e55/html5/thumbnails/10.jpg)
Key Plan
Comments :
• CENTER PODIUM COLUMN, FOOTING,GRADE SLAB-SHUTTERING,REINFORCEMENT.CONCRETE IN PROGRESS.
Phase 02 – Photo report
12
3
5
4
6
AURUM_Photo Report - Phase 02
![Page 11: Pacifica - Aurum Pride Towers Photos](https://reader031.fdocuments.in/reader031/viewer/2022030122/58a2fda81a28ab5d1c8b6e55/html5/thumbnails/11.jpg)
Key Plan
Comments :
• CENTER PODIUM COLUMN, FOOTING,GRADE SLAB-SHUTTERING,REINFORCEMENT.CONCRETE IN PROGRESS..
Phase 02 – Photo report Position - 08
12
3
5
4
6
AURUM_Photo Report - Phase 02
![Page 12: Pacifica - Aurum Pride Towers Photos](https://reader031.fdocuments.in/reader031/viewer/2022030122/58a2fda81a28ab5d1c8b6e55/html5/thumbnails/12.jpg)
Comments :
• INTERNAL PLASTERING WORK IN PROGRESS.
Phase 02 – Photo report
AURUM_Photo Report - Phase 02
![Page 13: Pacifica - Aurum Pride Towers Photos](https://reader031.fdocuments.in/reader031/viewer/2022030122/58a2fda81a28ab5d1c8b6e55/html5/thumbnails/13.jpg)
Comments :
• INTERNAL PLASTERING WORK IN PROGRESS.
Phase 02 – Photo report
AURUM_Photo Report - Phase 02
![Page 14: Pacifica - Aurum Pride Towers Photos](https://reader031.fdocuments.in/reader031/viewer/2022030122/58a2fda81a28ab5d1c8b6e55/html5/thumbnails/14.jpg)
COMMENTS :
• TYPICAL FLOOR BLOCKWORK IN PROGRESS.
Phase 02 – Photo report
AURUM_Photo Report - Phase 02
![Page 15: Pacifica - Aurum Pride Towers Photos](https://reader031.fdocuments.in/reader031/viewer/2022030122/58a2fda81a28ab5d1c8b6e55/html5/thumbnails/15.jpg)
COMMENTSTYPICAL FLOOR BLOCKWORK IN PROGRESS.
Phase 02 – Photo report
AURUM_Photo Report - Phase 02