PA Route 233 Corridor Study FINAL REPORT - Squarespace · Penn Township PA Route 233 Corridor Study...

64
PA Route 233 Corridor Study FINAL REPORT Penn Township, Pennsylvania June 2016

Transcript of PA Route 233 Corridor Study FINAL REPORT - Squarespace · Penn Township PA Route 233 Corridor Study...

PA Route 233 Corridor StudyFINAL REPORT

Penn Township, PennsylvaniaJune 2016

Penn Township PA Route 233 Corridor Study 

2        

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Funding for this study was provided by Penn Township and grants from the Tri‐County Regional Planning Commission’s Regional Connections Grant Program.  

   

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    3 

Message from Penn Township  

Dear township resident:  The PA Route 233 Corridor Study Final Report is a tangible example of Penn Township’s desire to plan for the future of our community.  It  follows previous efforts such as a new Township zoning ordinance  (2006) and update  to our municipal comprehensive plan  (2013). Based on  the experiences of other municipalities, we know that if we don’t work proactively at managing our township’s growth possibilities, other governmental agencies and economic pressures may do so for us, perhaps in ways we do not prefer.  We are all aware of the dramatic changes that have taken place in our economy over the past 25 years and how those changes  are  now  being  reflected  in  our  surrounding landscape. Central Pennsylvania and Cumberland County in  particular  have  been  a  magnet  for  growth  in  the development  of  warehousing  and  distribution  centers. These developments have brought  jobs  to  the area, but have  also  introduced  increased  truck  traffic,  congestion, safety concerns, and environmental impacts that must also be addressed.   Our  area’s  regional  position  and  transportation  assets  continue  to make  us  an  attractive  destination  for warehousing and distribution activity. These centers have historically centered on key interchanges along the I‐81  corridor  throughout  the  Cumberland  Valley.  Penn  Township  joined  the  growing  number  of  area municipalities that have warehousing facilities with the construction of the Key Logistics Park in 2009.    The  current  leadership  of  Penn  Township  has  sought  to  achieve  a  suitable  balance  between  economic development interests and the preservation of our rural character. In addition to our existing plans and land use management ordinances, we have worked to preserve our existing farmland. Penn Township in fact has nearly  3,000  acres  preserved  for  that  use  (within  Cumberland  County,  only  neighboring West  Pennsboro Township  has  more).  Our  February  2014  amendments  to  the  zoning  ordinance  provided  for  additional allowable uses by condition in our agricultural zones. The PA Route 233 Corridor Study builds on these efforts by identifying additional steps that should be taken proactively planning for the future of our community.  As you read the report, we trust you will appreciate the thought that has gone into identifying the steps we move forward with in order to best preserve Penn Township as a desirable place to both live and work. We also look forward to the prospect of implementing the recommendations and improvement options identified in this plan. As such, it represents a blueprint for us as we move forward in working with those who have a vested  interest  in  the outcomes of  this  study and  in Penn Township: YOU, our  fellow  township  residents; township land owners; investors and developers; and governmental agencies.   Sincerely,    Gary Martin, Chairman Penn Township Board of Supervisors 

Dan Ries, ChairmanPenn Township Planning Commission 

 

If we don’t work proactively at 

managing growth possibilities, other 

governmental agencies and economic 

pressures may do so for us, perhaps in 

ways we do not prefer. 

Penn Township PA Route 233 Corridor Study 

4        

                                     

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    5 

 

TableofContents 

Existing Study Area Conditions ........................................................................................ 9 

Background/Overview ................................................................................................. 10 

Location ........................................................................................................................ 11 

Population and Employment ....................................................................................... 13 

Building Permits ........................................................................................................... 15 

Traffic and Transportation ........................................................................................... 15 

Traffic Safety ................................................................................................................. 18 

Traffic Control ............................................................................................................... 18 

Miscellaneous Transportation Services ....................................................................... 20 

Land Use ....................................................................................................................... 20 

Future Land Use ............................................................................................................ 23 

Zoning Districts ............................................................................................................. 26 

Public Participation & Stakeholder Engagement ......................................................... 31 

Open House #1: Issue Identification ............................................................................. 32 

Scenario Development .................................................................................................. 35 

Open House #2: Review of Draft Recommendations ................................................... 37 

Improvement Options and Implementation Plan ........................................................ 39 

 

 

  

 

 

 

 

Penn Township PA Route 233 Corridor Study 

6        

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    7 

 

Acknowledgements 

Penn Township wishes to thank the members of the board of supervisors and planning 

commission for their insights and active participation in carrying out this study. Their 

constructive dialog, review of materials, and participation was essential to this effort.  

Supervisors 

Gary Martin, Chairman 

Kenneth Sheaffer, Vice‐Chairman 

Amos Seiders 

 

Planning Commission 

Dan Ries, Chairman 

Gary Cribb, Vice Chairman 

Marcia Leeds, Secretary 

Kathleen Hughes 

Victor Barrick 

Dennis Shoff 

Max Klein ‐ Resigned effective Jan. 1, 2016 (elected to Township Auditor position) 

Wayne Stevenson ‐ Appointed January 4, 2016 

 

Consulting Team (Michael Baker International) 

Brian Funkhouser, AICP, Project Manager 

Steve Gault, P.E., PTOE 

Penn Township PA Route 233 Corridor Study 

8        

 

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    9 

Existing Study Area Conditions    

Penn Township PA Route 233 Corridor Study 

10        

Background/Overview 

Changes in transportation and economics have been changing the landscape of western 

Cumberland County and the Cumberland Valley for many years – from the Indian trails of 

the  seventeenth  and  eighteenth  centuries,  to  the  designation  of  more  modern 

transportation facilities such as US 11 during the 1920s. These advances were followed 

by the building of the Pennsylvania Turnpike in the 1940s, and Interstate 81 in 1962.  

In more recent years, the emergence of the information economy and the rise that has 

given  to  the  need  for massive warehouse  facilities within major  population  centers, 

continues  to  mark  western  Cumberland  County.  In  fact,  the  region  can  now  be 

characterized as much for  its warehousing activity as  its rolling farmland.   E‐commerce 

and online retail sales have put retailers and other shippers and receivers under more 

pressure  to  compress  their  supply  chains  and  place more  of  their  inventory  in  local 

locations, closer to the consumer. As this new economy has evolved, Cumberland County 

has taken even greater care in planning for its transportation infrastructure, most notably 

with the  landmark 1999 study of Exit 12 (now 44)  in South Middletown Township, and 

continuing with successive studies of Exit 29, and Exits 48 and 49, in 2006.  

Over the past 10 years, demand for warehousing space throughout Cumberland County 

has only continued to grow. Even since the  interchange studies that were conducted a 

decade ago, total warehouse space within the county has increased by 40 percent, to a 

present‐day total of 42.6 million square feet (Figure 1).  

Figure 1: Warehousing Space in Cumberland County (feet2), 2004‐15 

 

Source: Cumberland Area Economic Development Corporation 

20,000

25,000

30,000

35,000

40,000

45,000

2005 2007 2009 2011 2013 2015

Squ

are

Foo

tage

(00

0s)

Year

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    11 

Penn Township  is positioned near the crosshairs of the county’s two major  interstates, 

just 16 miles south from where the two intersect. Exit 37, as I‐81’s lone interchange within 

the township, serves as  its gateway to the national highway network. The Township  is 

following  its municipal  counterparts  in experiencing demand  for warehousing activity, 

this after municipal water and sewer service has been extended. Over the past five or six 

years,  new  warehouses  have  arrived  in  the  area  (some  pre‐dating  zoning),  creating 

hundreds of new  jobs,  introducing  changes  in  travel patterns, and  creating additional 

demands on the community’s transportation infrastructure. 

More warehouses  are  planned.  In March  2013,  the  Township  rezoned  163  acres  of 

agricultural  land  (the  Ickes  family  farm)  to  Commercial‐Industrial.  The  change made 

possible the potential development of a proposed Penn Commerce Center that will add 

up to 2.5 M additional square feet of warehousing space directly across Centerville Road 

from  Key  Logistics.  Additional  warehouses  are  also  planned  in  neighboring  West 

Pennsboro Township. 

All of the new warehouses will have an ongoing impact, not only on the area economy, 

but on its transportation infrastructure. While the warehouses have improved (and are 

expected to continue to improve) the township’s economy, the municipality is challenged 

to plan for additional growth and development pressure so that it can be accommodated 

in a way that is sustainable and in alignment with public preferences.   

With  that,  the  Township  commissioned  a  study  of  the  PA  233  corridor,  including  its 

transportation attributes and surrounding land use, to address how it can best accomplish 

the following: 

What types of businesses should be encouraged to locate in the township, and in 

which areas? 

Are there parcels that should be rezoned to better reflect “highest and best use”? 

In taking a 20‐year view of the municipality, how should the zoning ordinance be 

revised in balancing the needs of development with public preferences? 

In  addition  to  the  zoning  ordinance, what  other  land  use management  tools 

should be explored for future township use?  

With the ongoing demand for warehousing, how can the township best protect 

the residential character of its neighborhoods, most notably Centerville? 

What geometric and safety changes,  if any, should be made  to the township’s 

roadway network, including Exit 37 and PA 233, to accommodate an anticipated 

increase in truck traffic? 

Location 

The PA 233 study corridor is located in western Cumberland County, as shown in Figure 

2. The corridor has a north‐south orientation and straddles the Interstate 81 corridor. It 

is located entirely within Penn Township, a rural municipality located 10 miles west of 

Penn Township PA Route 233 Corridor Study 

12        

the county seat of Carlisle. For planning purposes, the Township has limited the study 

corridor to the area between US 11 at its northern extent, to PA 174 (Walnut Bottom 

Road) at its southern extent. The borough of Newville is the study area’s nearest 

commercial center, and is located on PA 233 just 4 miles north of the I‐81 interchange 

(Exit 37). 

Figure 2: Study Area Regional Location 

 

Source: Michael Baker International 

Figure 3 shows the extent of the immediate regional roadway network adjacent to the 

PA 233 corridor. 

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    13 

Figure 3: PA Route 233 Corridor Study Area (and Surrounding Roadway Network) 

 

Source: PennDOT; Michael Baker International 

Population and Employment 

With  a  2010  population  of  only  2,924,  the  township  is  one  of  the  least  populated 

municipalities in Cumberland County. More recent five‐year estimates from the American 

Community Survey (2013) estimate the township’s population at 2,932. By contrast, the 

township’s population 25 years ago was 2,202, as recorded by the US Census. Figure 4 

depicts population change in the township over the past 25 years. 

Penn Township PA Route 233 Corridor Study 

14        

Figure 4: Population Change, Penn Township, 1990‐2013 

 

Source: U.S. Census; American Community Survey (2009‐13) 

Just as total population has a bearing on travel demand and trip generation, so too does 

employment. Until recent years, Penn Township served as a “bedroom community” to 

employment  destinations  elsewhere  within  Cumberland  County  and  the  Harrisburg 

Metropolitan  Statistical  Area  (MSA).  In  recent  years  however,  it  has  become  an 

employment destination in its own right. The development of Key Logistics Park on a 207‐

acre tract in 2009 presaged the arrival of major new employers in the 600,000 ft2 Office 

Depot distribution hub (part of a 1.2 M ft2 building), which ushered in a new era in the 

Township’s economy, as it introduced 250 new jobs to the area. The development of a 

Sheetz in 2011 with 30 to 40 employees of its own just outside of the study area beyond 

its northern limit attests to the attractiveness of the study area as a place to do business, 

and also signaled the potential of additional commercial growth. The development of the 

Unilever  logistics  center  in 2012 only  added  to  the growing number of  jobs available 

within the township. The 1.5 M ft2 Unilever facility added 450 jobs to Penn Township’s 

growing  total.  More  warehouses  are  planned  within  the  study  area  (as  well  as  in 

neighboring  West  Pennsboro  Township)  which  has  precipitated  the  need  for  a 

comprehensive  review  of  the  township’s  land  use  and  supporting  transportation 

infrastructure through this study.  

The warehousing employment numbers for Penn Township contribute to a growing total 

of these types of jobs within Cumberland County overall. According to the Pennsylvania 

Department of Labor and Industry, of the approximately 114,225 jobs within the county, 

5,454,  or  4.8  percent,  are within  the warehousing  and  storage  facility  industry.  This 

contrasts with the state rate of 2.2 percent.  

0

500

1,000

1,500

2,000

2,500

3,000

3,500

1990 2000 2010 2013

Pop

ulat

ion

Year

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    15 

Building Permits 

Residential development pressure has eased within the township since the recession of 

2007‐09. Annual residential building permit data from the Cumberland County Planning 

Commission indicate that – for the decade ending 2014 – there were a total of 99 new 

housing units  created within  the  township.  Figure 5  compares  trends  in new housing 

activity within the township to that of the county, and demonstrates that the township 

largely mirrors the county in trends in new housing starts. 

 Figure 5: Residential Building Permits, Penn Township and Cumberland County, 2004‐14 

 

Source: Cumberland County Planning Commission 

Traffic and Transportation  

The  PA  Route  233  corridor  (also  known  as  Centerville Road)  is  a  2‐lane  state‐owned 

roadway with an average daily traffic volume of approximately 6,900 vehicles per day to 

the north of Interstate 81, and approximately 3,200 south of the interstate. Throughout 

the study area, the roadway is comprised of 10‐foot travel lanes, with shoulder widths of 

10 feet.1 The posted speed limit along PA 233 is 45 miles per hour within the vicinity of 

the I‐81 interchange, and 55 miles per hour within the remainder of the study area. 

PennDOT  and  the  Harrisburg  Area  Transportation  Study  (HATS)  have  functionally 

classified PA 233 as a Minor Arterial north of the I‐81 interchange, and as a Rural Major 

Collector south of the interchange. As such, the roadway links the Township’s residents 

                                                            1 As part of the development of the Penn Commerce Center, a 275‐foot southbound left turn lane with a 305‐foot approach taper and 105‐foot bay taper will be installed along PA 233 at the intersection with the Key Logistics Driveway. 

0

200

400

600

800

1,000

1,200

1,400

1,600

1,800

0

5

10

15

20

25

30

35

2004 2006 2008 2010 2012 2014

Penn Twp County

Penn Township PA Route 233 Corridor Study 

16        

and businesses to more strategic roadways, such as Interstate 81. Minor Arterials in rural 

areas  such  as Penn Township  are  typically designed  to provide  relatively high overall 

speeds, with minimum interference to through movement. Rural Major Collectors gather 

traffic from Local Roads and funnel it to the Arterial network. In a rural environment, Rural 

Major Collectors generally serve primarily intra‐county travel (rather than statewide) and 

constitute  those  routes  on which  predominant  travel  distances  are  shorter  than  on 

Arterial routes. Because of this, more moderate speeds may be posted. Within the study 

area, US 11 and PA 174 (east of the Village of Centerville) are also classified as Rural Major 

Collectors.  Interstate  81  is  the most  strategic  roadway within  the  study  area,  and  is 

classified as an Interstate. It carries traffic volumes of nearly 30,000 vehicles a day in both 

directions. The remaining roadways within the study area, such as Cornman Drive (T‐426), 

Showaker Road (T‐427), and Hair Road (T‐429) are all local roads, and not on the Federal‐

aid system. Figure 6 shows the study area’s functional classification of roadways. 

Figure 6: Functional Classification of Study Area Roadways 

 

 

Source: PennDOT Bureau of Planning and Research 

PA 233’s location within Cumberland County, coupled with its physical attributes, makes 

it an attractive corridor for warehouse development. The wide shoulders allow for proper 

accommodation of other modes of transportation, such as bicycle and horse and buggy. 

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    17 

Its proximity to Interstate 81 and even the Pennsylvania Turnpike have introduced more 

truck traffic to the area: truckers now routinely exit the Turnpike at the Blue Mountain 

interchange  and  traverse  the  rural  routes of PA 641  and PA 233  through Newville  in 

serving the warehouses  in Penn Township. This results  in a savings of 40 miles for the 

carrier, but also introduces some unwanted side effects to the surrounding community. 

The corridor is also frequently used for the delivery of sand from Mt. Holly Springs to the 

Pennsy Supply quarry off of US 11. 

Within the study area, there are no projects formally 

programmed as part of the state’s 2015 Twelve Year 

Program.2    A  proposed  project  that  post‐dated  the 

adoption  Harrisburg  MPO’s  20‐year  Regional 

Transportation Plan (RTP) was submitted by the Penn 

Township  supervisors  in  early  2015.  The  candidate 

project  involves the Exit 37  interchange. Supervisors 

called  out  several  concerns,  including  lane  widths 

under  Interstate  81  that  are  too  narrow  to 

accommodate  turning  lanes. The project  submission 

further notes that the truck traffic being generated by 

warehousing  activity  immediately  adjacent  to  the 

interchange  is causing delays when truckers attempt 

to  turn  left  from  northbound  PA  233,  onto 

southbound Interstate 81.  

Additionally, the ramp design and lack of merger lanes on the interstate causes conflicts, 

particularly northbound, where the onramp shares capacity with a deceleration lane with 

a PennDOT rest area. The two ramps are approximately 800 feet apart, creating a very 

short weaving area for traffic entering the interstate. Crash data from PennDOT for the 

five‐year period ending December 2015 indicate that there have been 7 crashes on this 

segment of the Interstate. A majority (4) were rear‐end crashes, while 5 involved personal 

damage only. There have been no fatalities. 

                                                            2 A TYP project within Penn Township – a $1.8 million replacement of the Walnut Bottom Road Bridge on PA 174 – is located outside of the study area, on the border with South Newton Township. It is slated for replacement within the mid‐term (2019‐26) period of the 2015 Twelve Year Program. 

The I‐81 Interchange  Exit 37 

The two bridges that carry Interstate 81 over PA 233 were constructed in 1963. The northbound and southbound bridges both have a “fair” condition rating of 5 (on a scale of 0 to 9) and sufficiency ratings of 81 and 84, respectively. The sufficiency rating is essentially an overall rating of a bridge’s “fitness for duty”. 

Penn Township PA Route 233 Corridor Study 

18        

On the local system, there are no projects planned or programmed, although there was a 

new culvert installed on Gettle Road (T‐428) as the study was being conducted.  

 

Traffic Safety 

During  the  5‐year  period  ending  2014,  the  study  corridor  has  been  the  site  of  22 

reportable crashes. The most common crash type includes angle collisions (10), followed 

by rear‐end collisions (5). The severity of crashes is generally minor in nature, although 

there have been two fatalities recorded – one each in 2012 and in 2013. 

Traffic Control 

There  are  currently  two  signalized  intersections  within  the  study  corridor.  The  first 

controls access at  the  intersection of PA 233 and  the  I‐81 southbound  ramp, and was 

installed  in 2007. Recent  (2013)  traffic  studies have determined  that  the  intersection 

already satisfies warrants for a protected/permitted left turn phase along the northbound 

approach of PA 233 at the I‐81 southbound ramps. 

The second is located at PA 233’s intersection with US 11. Penn Township shares the cost 

of maintaining this signal with West Pennsboro Township.  

A third traffic signal is slated to be constructed at the shared entrance between the Key 

Logistics Park and  the  forthcoming Penn Commerce Center. A  full evaluation of  traffic 

signal warrants was conducted at this location and was found to have met warrants for 

the peak hour under the opening year (2017) and development traffic volumes. 

Bridge Condition Ratings

9   Excellent Condition ‐ New 8   Very Good Condition ‐ no problems noted. 7   Good Condition ‐ some minor problems. 6   Satisfactory Condition ‐ structural elements show some minor deterioration. 5   Fair Condition ‐ all primary structural elements are sound but may have minor section loss, cracking, spalling or scour. 

4   Poor Condition ‐ advanced section loss, deterioration, spalling or scour. 3   Serious Condition ‐ loss of section, deterioration of primary structural elements.  Fatigue cracks in steel or shear cracks in concrete may be present. 

2   Critical Condition ‐ advanced deterioration of primary structural elements.  Fatigue cracks in steel or shear cracks in concrete may be present or scour may have removed substructure support.  Unless closely monitored it may be necessary to close the bridge until corrective action is taken. 

1   “Imminent” Failure Condition ‐ major deterioration or section loss present in critical structural components or obvious vertical or horizontal movement affecting structure stability.  Bridge is closed to traffic but corrective action may put it back in light service. 

0   Failed Condition ‐ out of service; beyond corrective action. 

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    19 

A  fourth  traffic  signal  could  also  be  installed  within  the  study  corridor.  A  recent 

(November  2013)  traffic  impact  study  (TIS)  for  the  Penn  Commerce  Center  has 

recommended eventual signalization of PA 233 at the northbound onramp to Interstate 

81.  Existing  volumes  currently  do  not  satisfy  warrants  for  signalization.  The  Penn 

Commerce Center developer has agreed to monitor this intersection for a period of five 

years following full build‐out in order to determine when traffic signal warrants are met 

and to signalize the intersection at that time. As part of this proposed improvement, the 

TIS also suggests that a southbound left turn advance phase (“protected left”) be provided 

at this intersection. Capacity analyses of the intersection completed as part of the Penn 

Commerce Center TIS found that the intersection will operate at unacceptable levels of 

service by 2022 if congestion there is not mitigated. 

PA 233’s intersection with PA 174 is controlled by a stop sign. 

Other traffic observations throughout the study area include the following:  

Trucks don’t stop exiting Key Logistics. Truckers were frequently observed not 

stopping at the intersection upon leaving Key Logistics. 

Posted speed limits are inconsistent. Northbound is 55 from PA 174, drops to 50 

mph approaching I‐81 then drops to 45 mph north of I‐81. Southbound is 45 mph 

from US 11 then goes to 55 south of I‐81. There could be a 50 mph sign missing 

because  there  isn’t  a  sign  at  all  across  from where  it  changes  from  50  to  45 

northbound.  This  probably  exceeds  the  ½  mile  spacing  requirement  in  the 

PennDOT regulations. 

No Parking signage is inconsistent. Some signs have arrows, and the arrows are 

inconsistent. Some point side to side, one points up and down. Parking is enacted 

by local ordinance, and since the Pennsylvania State Police do not enforce local 

ordinances,  the No Parking  signs are essentially useless without a  local police 

department for enforcement.   

There  are  several  overlapping  emergency  detour  routes.  This  creates  sign 

clutter,  which  could  reduce  the  effectiveness  of  other  signage.  There  is  an 

instruction sign on the I‐81 SB off‐ramp visible in Google Street View, but it is no 

longer present (I‐81 Detour Follow Red). 

The near side “No Turn on Red” sign is missing on the I‐81 SB off‐ramp. The sign 

is  visible  in  Google  Street  View,  but  not  present  today.  It  should  be  there 

according to the signal permit. 

Lack of park and ride directional signage. There is a sign on I‐81 SB mainline for 

the park and ride at this exit, but there is no directional signage to direct motorists 

from the ramp to the park and ride. 

Warehouse directional signing is confusing. The warehouse directional signage 

installed by the Township can be confusing since the signs point to the right. The 

signs should be pointing straight to advise truckers to remain on PA 233 until they 

Penn Township PA Route 233 Corridor Study 

20        

arrive  at  the  warehouse  entrance.  The  signs  should  have  a  regular  green 

background since they would be considered guide signs. 

Miscellaneous Transportation Services 

Other transportation features of note within the corridor include the presence of a 50‐

space park and ride lot, which is located at the northwest quadrant of the interchange. 

Capital Area Transit serves the lot, which serves as an intermediate stop on CAT’s longer 

distance, Route 81 commuter service to Shippensburg. Service times include stops at 5:50 

and 6:50 in the morning, and 4:40 and 5:10 in the evening. Two other runs provide express 

service between Shippensburg and Harrisburg, with no stops at the Newville/Exit 37 park 

and ride. 

There  are  no  sidewalks within  the  study  area,  although  pedestrian  pushbuttons  are 

provided at PA 233’s signalized intersection with the southbound offramps of Interstate 

81.  

Land Use 

The PA Route 233 study area  is approximately 1.8 square miles  in size, or  less than 10 

percent of the Township’s total land area. The study area contains 64 parcels consisting 

of  1,400  total  acres  featuring  a  mix  of  land  uses,  including  agricultural,  industrial, 

residential, and institutional. By far the most dominant use of land within the study area 

is  agricultural,  of which  there  are  nearly  1,200  acres.  Industrial  uses  are  next most 

common, at 195 acres. Figure 7 shows the distribution of land uses within the study area, 

while Figure 8 contains a map of the area’s existing land use, by parcel. 

Figure 7: PA Route 233 Study Area Existing Land Use 

 

Source: Cumberland County GIS 

Agricultural, 81.4%

Commercial 2.0%

Industrial 13.6%

Institutional <1%Residential

1.6% Vacant <1%

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    21 

Figure 8: PA Route 233 Corridor Study Area Existing Land Use 

 

Source: Cumberland County GIS 

According  to data  supplied by Cumberland County,  there  are 227  acres protected by 

agricultural easements within the study area. The designation places certain restrictions 

upon the land to maintain and permanently preserve high quality, functional farmland. 

The owner retains all privileges of land ownership, except the ability to sell the property 

Penn Township PA Route 233 Corridor Study 

22        

for  non‐agricultural  development  or  to  develop  the  property  for  non‐agricultural 

purposes. The agricultural conservation easements are permanent. If a landowner wishes 

to sell the land, the easement is transferred and the new landowner must continue to use 

the property exclusive for agricultural purposes. Penn Township has a total of 2,982 acres 

of farmland that has been preserved for that use (or nearly 20 percent of the county’s ag 

land preservation total). Within Cumberland County, only neighboring West Pennsboro 

Township (3,213) has preserved more acreage. 

A  greater  share  of  the  study  area  is  within 

Agricultural Security Areas (ASA). These properties 

are  not  preserved  for  agricultural  uses,  yet  have 

been officially designated as an agricultural district 

by Penn Township.  ASAs are intended to promote 

more permanent and viable farming operations by 

strengthening  the  farming  community’s  sense  of 

security in land use and the right to farm. Within the 

study area,  there are 19 parcels consisting of 946 

acres enrolled in ASA. Countywide, there are 71,947 

acres of land enrolled in ASA. 

Despite  the  dominance  of  agricultural  uses 

throughout  the  Township,  the  arrival  of 

warehousing  activity  in  recent  years  has  changed 

not only the landscape, but has provided a financial boost, as evidenced by recent local 

realty transfer tax revenues (Figure 9). 

Figure 9: Penn Township Realty Transfer Tax Revenues, 2004‐13 

 

Source: PA Department of Community and Economic Development 

$0

$50

$100

$150

$200

$250

$300

$350

$400

$450

Dol

lars

($0

00s)

Year

Ag Security Areas

An agricultural security area 

(ASA) is a tract of agricultural 

land that has been officially 

designated as an agricultural 

district by the local 

municipality. ASAs are intended 

to promote more permanent 

and viable farming operations 

by strengthening the farming 

community’s sense of security 

in land use and the right to 

farm.

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    23 

Future Land Use 

The Township’s Future Land Use Plan, as documented within its overall comprehensive 

plan  (2013),  is  a  foundational  element  of  how  the  municipality  views  land  use 

management. As such, the future land use plan guides the creation and maintenance of 

the Township’s zoning ordinance and the management tools that are needed to guide 

future development throughout the community.  

The future land use plan should not be viewed in the same vein as zoning: the future land 

use plan (and map) is intended to guide the mixes and types of future development as 

opposed to zoning, which  is much more regulatory  in nature. As such, the focus of the 

future land use plan is oriented more toward promoting compatibility among various land 

use  activities, while  the  zoning  ordinance  is  centered  on  the  definition  of  narrowly‐

defined districts consisting of permitted and conditional uses.  

The Township’s future land use plan identifies six major land use categories: Agricultural, 

Residential, Conservation, Commercial/Industrial, Mining, and Floodplain. These uses are 

briefly described in the following points: 

Agricultural – Within the study area, the Township has designated approximately 

62 percent of  its  land area to agricultural uses. The district  is so designated to 

promote the ongoing preservation of the township’s agricultural resources. Given 

the  flexible  nature of  the  future  land use plan  (and  the  Township’s  intent  to 

accommodate a variety of uses),  the district  is also expected  to accommodate 

certain commercial and industrial uses, particularly those that are in support of 

agricultural‐related activities. 

Residential – The promotion of residential development within the township is 

focused on areas that do not possess prime agricultural soil and have access to 

transportation  infrastructure. These areas primarily  include the PA 174/Walnut 

Bottom Road corridor, and the villages of Centerville and Cumminstown.  

Conservation  –  Intense  development  is  discouraged within  the  Conservation 

district  for  a  variety  of  reasons:  soils  typically  cannot  sustain  on‐lot  septic 

systems, access to transportation is limited, and development along steep slope 

areas  would  create  large‐scale  erosion  concerns.  This  district  generally 

encompasses  the  southern  third  of  the  township,  or  the  northern  piedmont 

region of South Mountain. 

Commercial/Industrial  –  Areas  designated  for  this  use  are  focused  on major 

transportation corridors within the township that offer a high degree of visibility 

and mobility. These include Centerville Road, US 11, and areas adjacent to the I‐

81 interchange. 

Penn Township PA Route 233 Corridor Study 

24        

Mining – The Mining District consists of one small area in the northwestern area 

of the Township. The purpose of this zone is to reserve an area of the Township 

for quarrying and the processing of quarry raw materials. 

Floodplain ‐ The Township’s comprehensive plan recognizes the Yellow 

Breeches Creek as a valuable resource, and seeks to protect the integrity of the 

waterway and the quality of its waters. As such, the future land use plan 

provides that a high priority be placed upon floodplain preservation as defined 

along the floodplain boundaries of the Yellow Breeches. 

The study area’s future land use is as shown in Figure 10. 

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    25 

Figure 10: PA Route 233 Corridor Study Area Future Land Use 

 

Source: Cumberland County GIS 

Penn Township PA Route 233 Corridor Study 

26        

Zoning Districts 

Penn Township’s zoning ordinance dates to 2006 and manages land use, lot size, building 

heights,  and  development  densities.  The  zoning  ordinance  contains  the  following 

districts: 

Conservation (C) – This zone is intended to preserve and protect the Township’s 

sensitive  environmental  features,  as  well  as  to  protect  life  and  property  by 

limiting development  in areas with severe development constraints. Permitted 

uses  include:  forestry‐related,  fisheries,  public  and  non‐public  parks  and 

playgrounds, natural areas or wildlife refuges, single family dwellings, and drive‐

in produce stands. Minimum lot size is 4 acres. There are no parcels within the 

study area that are zoned Conservation, even though approximately 30 percent 

of the Township is zoned for this use. 

Agricultural (A) – This zoning district is composed of areas within the township 

whose predominate and use is devoted to agricultural activities and is established 

to  protect  and  stabilize  agriculture  as  an  on‐going  and  economic  activity  by 

permitting only  those  land uses  and  activities which  are  either  agricultural  in 

nature  or  act  in  direct  support. Moreover,  the  district  is  intended  to  protect 

productive  farmland,  the  Township’s  most  important  natural  resource.  In 

addition  to agriculture, other permitted uses within  this district  include  single 

family dwellings, churches, fire stations, and other public buildings. A majority of 

the study area (56 percent) is zoned as Agricultural, although it should be noted 

that  only  one  parcel  has  an  agricultural  easement.  Overall,  the  study  area 

contains over 781 acres that are zoned as Agricultural.  

Residential  (R)  ‐  Residential  zones  within  the  township  are  centered  in 

established rural communities or adjacent to significant community development 

areas.  The  Township  permits  a  variety  of  uses  within  this  zone,  including 

residential,  agricultural,  schools,  and  a  variety  of  low‐density  commercial 

applications (e.g., barber/beauty shops) and home‐based businesses. There are 

several parcels  consisting of 37 acres within  the  study area  that are  zoned as 

Residential,  consisting  of  just  3  percent  of  the  study  area’s  land  area.  These 

parcels  are  centered  on  the  Village  of  Centerville  and  fronting  along Walnut 

Bottom Road (PA 174). 

Commercial‐Industrial (CI) – This zoning district is intended to provide locations 

for those areas necessary to meet the Township’s commercial needs, and goods 

and services of a commercial nature. It is also intended to permit and encourage 

limited  industrial  development  that  would  be  compatible  with  surrounding 

residential or  agricultural  areas. Development within  this  zone  is  expected  to 

access  the  roadway  network  through major  roadways,  as  opposed  to  lower‐

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    27 

order,  neighborhood  streets.  Typical  permitted  uses  entail  a wide  variety  of 

commercial and  industrial applications,  including warehousing and distribution 

centers. There are approximately 617 acres, or 43 percent of the study area, that 

are zoned for these uses.  

Quarry (Q) – The Quarry zone is intended to reserve an area of the township for 

quarrying operations and the processing of quarrying materials. These areas lie 

outside of the study area. 

Floodplain (FP) – The Floodplain District  is  intended to restrict development  in 

flood prone areas to those uses that will not be damaged by periodic inundation 

or that will not increase flood heights be reducing the floodway cross‐sectional 

area. There are no parcels zoned as Floodplain within the study area. 

The study area includes three different zoning districts, as shown in Figure 11. 

Penn Township PA Route 233 Corridor Study 

28        

Figure 11: PA Route 233 Corridor Study Area Zoning Districts 

 

Source: Cumberland County GIS 

 

Table 1 summarizes zoning provisions within the study area.  

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    29 

 

Table 1: Penn Township Zoning Ordinance Summary 

Zoning District  Code Minimum Lot Area 

Max. Lot Coverage 

Parcel Count 

Acreage Percent of Study Area 

Agricultural  A  44,000 ft2  10%  32  781  56% 

Commercial/ Industrial 

CI  5 acres/  10 acres 

70%  15  617  43% 

Residential R  20,000 ft2/ 

10,000 ft2 10%  17  37  3% 

Source: Penn Township Zoning Ordinance Notes: One acre equals 43,560 feet2. Minimum lot size in the Agricultural District may be required to be increased to accommodate on‐lot sewage disposal (and an alternative site) as determined by the Pennsylvania Department of Environmental Protection (DEP). Minimum lot areas within the Residential District are dictated on whether or not public water or sewer services are available onsite. Minimum lot sizes in the Commercial/Industrial District differ, depending on whether the use is considered a “Small Area Use,” or a “Large Area Use.”   

 

 

 

 

 

 

 

 

 

 

 

 

Penn Township PA Route 233 Corridor Study 

30        

 

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    31 

 

 

 

 

 

 

 

    

Public Participation & Stakeholder Engagement

Penn Township PA Route 233 Corridor Study 

32        

The study process included two formal opportunities for public participation, consisting 

of a pair of public open houses held at various stages of the study process. 

OpenHouse#1:IssueIdentificationThe  Township  conducted  its  first  study  open  house  at  the  township  building  on  the 

evening of October 8, 2015. The purpose of the open house was to introduce the study 

to the public and identify any issues over and above those that had already been outlined 

and  discussed  in  a  draft  Community  Assessment  Report. Meeting  participants  were 

presented with an overview of the study, and encouraged to provide comment. An exit 

survey was  also  used  to  capture  public  preferences,  leading  up  the  identification  of 

development scenarios. The Township promoted the meeting through area newspapers 

such as the Carlisle Sentinel, the Newville Valley Times‐Star, and through direct mailings 

to all property owners within the study area.  A total of 30 people attended this first open 

house. 

The Township also administered an exit  survey as part of  the open house  to  capture 

additional information on individual levels of concerns related to traffic safety, economic 

development, land use, and other issues. Table 2 depicts the results of the exit survey, 

which represents the viewpoints of 22 individuals.  

Table 2: Open House Exit Survey Results (by percent) 

Issue Importance 

High  Medium  Low 

LAND USE/ECONOMIC DEVELOPMENT 

a) Planning for the development of additional warehousing and distribution centers 

41% 9% 41%

b) Strengthening Township ability to manage land use  32% 26% 14%

c) Identifying areas for potential zoning changes  27% 41% 41%

d) Agricultural land preservation  68% 23% 9%

TRAFFIC/TRANSPORTATION  

e) Directing truck drivers to warehousing destinations (signing) 

73% 18% 5%

f) Widening the lanes on Centerville Road under I‐81  55% 5% 26%

g) Addressing traffic conflicts related to the rest area  27% 36% 27%

h) Providing areas for overnight truck parking  27% 14% 45%

i) Enforcing traffic laws (e.g., speeding, etc.)  59% 32% 5%

j) Accommodating bicycle, pedestrian, and horse and buggy traffic 

41% 27% 27%

k) Improving public transportation (CAT) service  27% 32% 36%

l) Improving the park and ride lot  27% 27% 41%

Source: Penn Township Community Survey 

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    33 

The Township also asked a series of questions to better gauge public perceptions and 

preferences across a range of study topic areas. The results are depicted in Table 3. 

Table 3: Open House Exit Survey Results: Public Preferences (by percent) 

Question Strongly Agree 

Agree Don’t Care/ Don’t Know 

Disagree Strongly Disagree 

a) The interchange/Exit 37 should be modified to better accommodate truck traffic. 

50% 18% 9% 0% 23%

b) More areas within the township should be rezoned to Commercial/Industrial. 

9% 14% 0% 23% 55%

c) The Township does a good job in protecting agricultural and residential areas from warehousing development. 

14% 41% 22% 5% 18%

d) I feel safe when traveling on Centerville Road. 

18% 32% 5% 9% 36%

e) The Township should be doing more to develop recreational opportunities within the community. 

9% 50% 31% 5% 5%

f) The Township should consider public‐private partnership opportunities for providing additional areas for overnight truck parking. 

9% 32% 22% 14% 23%

g) Others? (write‐in) 

Source: Penn Township Community Survey 

A third exit survey question asked respondents to indicate what types of new land uses 

they would  like  to  see develop within  the  study area. Figure 12 demonstrates public 

response  to  this  important  question, which was  used  to  guide  the  identification  and 

characteristics  of  the  development  scenarios.  Nearly  half  of  all  survey  respondents 

indicated a preference for agricultural land uses, or vacant, undeveloped land. 

Penn Township PA Route 233 Corridor Study 

34        

Figure 12: Public Land Development Preferences, Penn Township 

 

Source: Penn Township Community Survey 

Highlights of other common themes expressed at the open house included: 

Traffic/Transportation  

Interest was expressed in PennDOT improving the interchange. The proposal in 

fact was  rated  as  a  “high  priority” by  65 percent of  survey  respondents.  The 

Township has approached the MPO regarding placing a proposed project on the 

region’s  long range transportation plan. There are competing concerns that an 

improved  interchange will  introduce more  truck  traffic  and  the  types  of  land 

development that may not necessarily be welcome in Penn Township. 

Environmental  conditions  were  cited  by  many  after  years  of  warehousing 

development throughout the Cumberland Valley. Air quality concerns from idling 

trucks in particular were raised by the public. 

As one resident noted: “We need to be concerned about children’s health and 

safety” as part of the study process.  

The location of the rest area and the lack of a weaving lane between it and the 

northbound on‐ramp of I‐81 is also a safety concern. 

Some substandard pavement conditions along PA 233 were mentioned, including 

the presence of sink holes. 

0 5 10 15 20 25 30

None / No Development Desired

Manufacturing

Commercial / Industrial

Residential

Office

Agricultural

Percent

Land Use Type

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    35 

Existing signing along PA 233 does not appear to do an effective job in directing 

truckers to the area’s warehouses. 

Land Use 

The public expressed concerns with the impact the new warehouses would have 

on taxes, surrounding property values, and the ability to sell their own properties 

once and if additional warehouses move into the area. With the recent arrival of 

warehouses, the Township in fact has been able to eliminate taxes, including the 

occupational tax and property taxes. 

The public also raised concerns on zoning and how potential changes would be 

made after the study is completed.  

The decline in new housing starts in the township was attributed as much to the 

rise of warehousing development as much as any influence by the soft economy.   

ScenarioDevelopmentThe Township identified three development scenarios based on the following inputs: 1) 

input received from the public open house/exit survey, 2) local knowledge of the study 

area,  and  3)  professional  planning  judgment  from  officials  within  Penn  Township, 

Cumberland  County  Planning,  and  the  Township’s  planning  consultant.  The  scenarios 

consider a planning horizon out to the year 2036 and allow planners and decision‐makers 

to be able to understand and anticipate the impacts of prospective developments. 

The scenarios are as depicted and defined in Table 4. 

Table 4: PA Route 233 Development Scenarios 

Scenario  Description 

Base Case Describes how the area could be expected to develop over the next 20 years, based on the land use management provisions in place in 2016. 

Build‐out  Represents a worst case scenario – if the area were to “build out” to the maximum extent allowable by existing zoning and other land use ordinances. 

Public Preferred Incorporates public preferences as gleaned from the study open house. 

 

For the traffic analysis, the reader should note that the projected change in traffic volume 

is a function of the specific land use scenarios. Land use characteristics serve as “inputs” 

into the traffic model. Thus, each land use is assigned a trip generation rate which is the 

number  of  trips  a  particular  land  use  produces  and  attracts  per  one  specific  unit  of 

measure. For example, for every single family dwelling unit, there is an average of 9.55 

Penn Township PA Route 233 Corridor Study 

36        

trips generated per day. These rates are established by the  Institute of Transportation 

Engineers (ITE) and were used to develop trip tables for each of the three scenarios which 

represent the changes in land use and the corresponding changes in trip generation. Trip 

generation rates are as depicted in Table 5. 

Table 5: Illustrative ITE Trip Generation Rates 

    Rates 

Land Use  Base Unit  AM Peak ADT  ADT Range 

Residential             

Single Family Home per dwelling unit 

.75  9.55     4.31‐21.85 

Apartment Building per dwelling unit 

.41  6.63     2.00‐11.81 

Condo/Townhome per dwelling unit 

.44  10.71     1.83‐11.79 

Retirement Community per dwelling unit 

.29  5.86   

Mobile Home Park per dwelling unit 

.43  4.81     2.29‐10.42 

Recreational Home per dwelling unit 

.30  3.16     3.00‐3.24 

Retail             Shopping Center  per 1,000 GLA  1.03  42.92     12.5‐270.8 Discount Club  per 1,000 GFA  65  41.8     25.4‐78.02 Restaurant (High‐turnover)  per 1,000 GFA  9.27  130.34     73.5‐246.0 Convenience Mart w/ Gas Pumps 

per 1,000 GFA    845.60    578.52‐1,084.72 

Convenience Market (24‐hour) 

per 1,000 GFA  65.3  737.99     330.0‐1,438.0 

Specialty Retail  per 1,000 GFA  6.41  40.67     21.3‐50.9 Office             Business Park  per employee  .45  4.04     3.25‐8.19 General Office Building  per employee  .48  3.32     1.59‐7.28 R & D Center  per employee  .43  2.77     .96‐10.63 Medical‐Dental  per 1,000 GFA  3.6  36.13     23.16‐50.51 Industrial             Industrial Park  per employee  .43  3.34     1.24‐8.8 Manufacturing  per employee  .39  2.10     .60‐6.66 Warehousing  1,000 GFA  .55  3.89     1.47‐15.71 Other             Service Station  per pump  12.8  168.56     73.0‐306.0 City Park  per acre  1.59  N/A     N/A County Park  per acre  .52  2.28      17‐53.4 State Park  per acre  .02  .61     .10‐2.94 

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    37 

    Rates 

Movie Theatre    w/Matinee 

per movie screen 

89.48  529.47    143.5‐171.5 

Saturday (PM 

Peak)     

Day Care Center  per 1,000 GFA  13.5  79.26    57.17‐126.07 

Source: Institute of Transportation Engineers (ITE)

Trip generation numbers – or background traffic growth rates – for the Base Case Scenario 

was derived using trip generation rates from PennDOT’s Bureau of Planning and Research. 

PennDOT has estimated  an  annual  traffic  growth  rate of 0.68 percent  for Rural Non‐

interstate  roadways  in  Cumberland  County.  This  rate was  compounded  to  the  study 

horizon year of 2035.  

OpenHouse#2:ReviewofDraftRecommendationsThe Township hosted a second public open house on April 14, 2016. The purpose of the 

meeting was to present a set of draft recommendations to the public to obtain feedback. 

The planning team presented an overview of the study and the recommendations being 

proposed. A question and answer period followed, and participants were encouraged to 

complete an exit survey, the results of which are documented in Table 6. 

Table 6: Public Preferences on Proposed Study Recommendations 

Statement Comments/ Suggestions 

a) Revise the Township Zoning Ordinance to allow for stand‐alone Commercial and Industrial zoning districts 

 

Enough already 

b) Revise the Township’s Zoning District map to account in part for proposed changes in the zoning districts 

Oppose changes so don’t agree 

with revisions 

c) Develop an Official Map  

none received 

d) Adopt an Access Management ordinance 

Help regulate access to Rt 233 

e) Approach Unilever concerning dedicating their existing driveway to the Township 

 

Who will then be responsible for 

the cost of maintaining the access?  

Unless Unilever or successor is 

responsible, unfair to local 

taxpayers. 

Penn Township PA Route 233 Corridor Study 

38        

Statement Comments/ Suggestions 

Please consider option of traffic 

circle rather than traffic light. 

f) Develop a Noise Ordinance    

But if do noise, should also do light 

ordinance. Character of Township 

is being destroyed.  

Adopt a light ordinance as well. We 

are losing too much of our night 

sky. 

g) Use the provisions of Act 209 to pay for off‐site transportation improvements (impact fees) 

none received 

h) Expand/improve the existing park and ride lot 

  

State owned? 

It works as it is now. 

Vandalism is an issue of the park & 

ride.  

i) Petition PennDOT and the Harrisburg MPO for needed changes to the Exit 37 interchange 

 

none received

 

Other issues raised by the public during the meeting included: 

Bus stop concern at 811 Centerville Road ‐ 3 accidents in last 6 weeks 

A request for a light ordinance to better manage light pollution from the area’s 

warehouses 

The stop bar on northbound PA 233 at the I‐81 southbound ramp may need to be 

moved back  

Township planning commission members in the audience also requested a video of the 

diverging diamond concept.  

The  study’s  improvement  options  and  implementation  plan  are  presented  in  greater 

detail in the following chapter.   

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    39 

 

 

 

  

  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Improvement Options and Implementation Plan

Penn Township PA Route 233 Corridor Study 

40        

Background/Overview 

The PA 233 study process has included the development of a profile of existing conditions 

within the study area, a facilitated public open house, and meetings with the township 

planning commission to discuss potential improvements. The following list was offered to 

the  study  steering  committee  as  a  starting  point  for  further  discussion.  The 

recommendations address the following study issues: 

Improve safety and protect the capacity of the PA 233 corridor 

Discourage the number of new truck trips on PA 174, Walnut Bottom Road 

Limit development north of  the  interchange  to  agricultural, or  low‐density 

commercial uses 

Manage the number of new access points onto the PA 233 corridor 

Address  the  lack  of  a  weaving  area  on  I‐81  northbound  between  the 

interchange and the rest area 

Recommendations are discussed here in greater detail, and are in no priority order. 

Draft Study Recommendations  

Revise the Township Zoning Ordinance to allow for stand‐alone Commercial 

and Industrial zoning districts.  

Revise  the Township’s Zoning District map  to account  in part  for proposed 

changes in the zoning districts.  

Develop an Official Map.  

Update the Comprehensive Plan. 

Adopt an Access Management ordinance.  

Approach Unilever concerning dedicating their driveway to the Township.  

Update the Township’s Noise Ordinance. 

Use the provisions of Act 209 to pay for off‐site transportation improvements 

(impact fees). 

Improve the existing park and ride lot.  

Petition the Harrisburg MPO for needed changes to the Exit 37 interchange.  

Consider sound barriers as part of any interchange improvement. 

Consider enlarging the rest area on I‐81 northbound. 

A discussion of the recommendations addresses the following subheadings: 

Statement of the recommendation itself 

Details surrounding the recommendation 

Why it is necessary 

Recommended priority 

Expected benefits 

Level of community support. 

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    41 

A. Revise the Township zoning ordinance to allow for stand‐alone Commercial and 

Industrial zoning districts.  

Priority: HIGH  Benefit: Providing further definition to the Township’s zoning ordinance will provide the municipality with greater management over the type of land uses being proposed in the future. 

Planning Level Cost Estimate: $5,000 

Public Preference: At both study open houses, the public voiced a desire to maintain the area’s agrarian character. 

Background: The Township zoning ordinance currently features 6 zoning districts and 

dates back to 2006. Commercial and Industrial uses are currently rolled up into one 

district with a wide variety of permitted uses. Segregating these uses will allow the 

Township to have greater management over the type of land uses being proposed in 

the future. The Cumberland County Planning Commission has created a draft of both 

district zoning chapters, which could be used as a starting point by the Township. 

 

 

 

   

Action: 

The Township planning commission should review existing uses that are allowed 

by right within the existing Commercial/Industrial zoning district classification 

and  segregate  these  uses  within  a  stand‐alone  Commercial  and  Industrial 

districts. Proposed revisions to the zoning ordinance should be reviewed by the 

Township solicitor and presented to the supervisors for adoption. The study makes 

recommendations  as  to  how  certain  parcels  should  be  rezoned,  and  are  as 

depicted in  

 

Table 7 while Figure 13 shows the existing zoning designations of the study area 

parcels. 

Penn Township PA Route 233 Corridor Study 

42        

Table 7: Proposed Study Area Zoning Changes Parcel Number 

Current Zoning Proposed Zoning 

Comments 

1.2  Commercial/ 

Industrial  Industrial 

‐ Would continue to accommodate warehousing uses proposed; preliminary plans have already been submitted 

1.3  Commercial/ 

Industrial  Commercial 

‐ The study proposes this parcel be reserved for commercial traveler services, including hotel and restaurant as examples 

1.4  Commercial/ 

Industrial  Commercial 

‐ Parcel could accommodate a 100k SF shopping center if the drive‐in “turns over” 

2.6  Agricultural  Commercial 

‐ Constitutes as the only instance of “up‐zoning” in the study area; would accommodate uses complementary to the warehouses 

2.7  Commercial/ 

Industrial  Industrial 

‐ Should serve uses that are complementary to the warehouses 

2.9  Residential  Industrial 

and Residential 

‐ Zoning for this parcel would be split between the two uses, and follow the parcel’s natural features 

2.11  Commercial 

/Industrial  Industrial 

‐ A 2M SF warehouse has been proposed for the Ickes property 

2.12  Agricultural  Agricultural 

‐ Tract should remain as Agricultural to serve as a buffer between agricultural/residential and warehousing activities. 

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    43 

Figure 13: Study Area Parcel Numbering (by Zoning District Classification) 

 

   

Penn Township PA Route 233 Corridor Study 

44        

B. Develop an Official Map.  

Priority: HIGH  Benefit: The Official Map would help implement the recommendations of this land use study and the comprehensive plan by preemptively identifying those areas that would be needed for the public interest, such as transportation improvements. It ensures future development is compatible with the Township’s goals. 

Planning Level  Cost Estimate: $5,000 

Public Preference: The Township’s desire for an Official Map to guide future decision‐making regarding land use and transportation has been a stated desire from the outset of the study process.  

Background: Article IV, Section 401 of the Pennsylvania Municipalities Planning Code 

(MPC) grants authority to municipalities like Penn Township to create an Official Map 

and ordinance. The purpose of the Official Map would be to account for right‐of‐way 

needed for service roads, changes in interchange geometry, and relocation of certain 

township roads. Service roads are needed to protect future capacity of the PA 233 

corridor, particularly north of the existing Unilever driveway intersection with PA 233. 

Points of  access onto US  11  and PA 233  for  a potentially  redeveloped parcel 1.4 

(current site of the drive‐in movie theater) should also be noted, as well as a proposed 

realignment of Hair Road.  

 

Under  the MPC,  listing all or a portion of a particular property on an Official Map 

provides notice to landowners and developers of the municipality’s goals for public 

infrastructure  in  that  location.  The  designation  on  the  Official  Map  does  not 

constitute  a  taking  in  and  of  itself,  but  gives  the municipality  an  opportunity  to 

negotiate  acquisition  of  property,  or  other  rights  to  a  property,  before  any 

development occurs on the property. Essentially, the municipality has the first right 

of refusal to acquire the necessary property before it develops, whether by purchase 

or eminent domain.  

 

The power of an Official Map can be further enhanced if compliance with the Official 

Map is incorporated into other Township land use ordinances, such as the Subdivision 

and  Land  Development  Ordinance  (SALDO)  and/or  the  Zoning  Ordinance.  For 

example, the MPC authorizes a SALDO to require public dedication of land. Using this 

power, the SALDO could require public dedication of  land  identified on the Official 

Map. 

 

   

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    45 

 

C. Update the Township Comprehensive Plan. 

Priority: HIGH  Benefit: This action provides a relatively inexpensive solution for improving safety and capacity along PA 233 and throughout the township. 

Planning Level  Cost Estimate: $5,000 

Public Preference: The public has expressed a desire for improved planning within Penn Township. 

Background: The comprehensive plan is the “North Star” among the township’s planning 

tools  in  representing  the  community’s  interests.  The  plan  highlights  a  vision  and  a 

statement  of  objectives  of  the  municipality  concerning  its  character  and  future 

development. The plan addresses community concerns that are broader than  just  land 

use and transportation, and include recreational needs, housing, community facilities and 

utilities, and others. The state’s Municipalities Planning Code  (MPC)  recommends  that 

municipalities  review  their  comprehensive plans  for  currency  a minimum of  every 10 

years.  Although  the  township’s  current  plan  was  last  amended  in  2013,  this 

recommendation  is  timely,  especially  given  current  development  trends  and  ongoing 

pressure for new development within the township. The comprehensive plan serves as a 

guide  for  all  other  planning  documents  and  tools,  including  the  official map,  zoning 

ordinance, and subdivision and land development ordinance. 

 

 

 

 

 

 

 

 

Action: 

The  Township  planning  commission  should  develop  an  Official  Map  for 

consideration and adoption by  the Township  supervisors. PennDOT and other 

state agencies have developed guidance on  this  through Publication 703  (June 

2011). The supervisors must provide a 45‐day review period and a minimum of 

one public hearing prior to adoption. The need for an Official Map is important, 

given potential improvement options being explored for the Exit 37 interchange. 

Penn Township PA Route 233 Corridor Study 

46        

 

Action: 

The Township planning commission should update the municipal comprehensive 

plan. Supervisors have expressed a desire for all the township’s planning‐related 

documents  to be  in  synch with one  another. An updated  comprehensive plan 

could include the outcomes of the PA Route 233 Corridor Study as well as establish 

a foundation for the township’s other land use management ordinances, including 

the zoning ordinance, and the subdivision and land development ordinance. New 

tools proposed by this study would also be shaped by an updated comprehensive 

plan, and would include a new official map, and access management policy. Other 

initiatives could include a potential Farmland Overlay district to make the existing 

Agricultural District more “ag‐friendly.”   

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    47 

D. Address access management needs throughout the corridor.  

Priority: HIGH  Benefit: This action provides a relatively inexpensive solution for improving safety and capacity along PA 233 and throughout the township. 

Planning Level  Cost Estimate: $5,000 

Public Preference: The public has expressed a desire for greater management of access to PA 233/Centerville Road through the study process. 

Background:  Protecting  the  safety  and  capacity  of  the  PA  233  corridor  can  be 

accomplished  in part  through  the adoption of an access management ordinance. The 

intent of the ordinance would be to control the number and spacing of new driveways 

and points of ingress and egress onto PA 233. For reference, PennDOT in 2006 developed 

a  model  access  management  ordinance,  which  can  be  accessed  here: 

http://www.dot.state.pa.us/public/PubsForms/Publications/PUB%20574.pdf.  

 

 

   

Actions: 

The  Township  planning  commission  should  develop  an  Access Management 

Ordinance  for  consideration  and  adoption  by  the  Township  supervisors.  This 

would address techniques such as shared driveways and parking areas, driveway 

lengths,  and  the  encouragement  of  new  development  to  access  the  public 

roadway network through  lower‐order roadways such as Township roads. Over 

time,  the  Township  should  attempt  to  obtain  an  average  spacing  of  250  feet 

between access drives. PennDOT’s model ordinance  can be accessed online at 

http://www.penndot.gov  and  can  be  used  as  a  guide  in  developing  a  local 

ordinance.  

 

The Township should approach Unilever concerning a possible dedication of its 

existing driveway  to the municipality.  In  tandem with  the previous action,  the 

Township should investigate the potential of taking ownership of this private road. 

Future access to adjoining parcels could then come from this roadway, as opposed 

to creating additional points of access onto PA 233. 

Penn Township PA Route 233 Corridor Study 

48        

E. Update the township’s noise ordinance and address lighting.  

Priority: MEDIUM  Benefit: Would help industrial uses such as warehouses to be a “good neighbor” to the township’s existing residential areas by helping the area avoid safety and nuisance problems related to excessive noise and obtrusive lighting. 

Planning Level  Cost Estimate: $10,000 

Public Preference: This recommendation received strong support from those who were in attendance during the second public open house. 

Background: The Township has done a good job in recent years in trying to manage the 

environmental  impacts  caused  by  the  development  of  warehouses  within  the  rural 

community. An example of  this  includes a  required 20‐foot berm  to block warehouse 

noise,  including  vehicular  back‐up  alarms.  The  Township  currently  does  have  a  noise 

ordinance, but  it  is  inadequate. Such an updated ordinance can address development 

related to warehouses, but can also address nuisance noises such as truck garages, impact 

wrenches, fireworks, and church clarions. As a recommendation, a noise ordinance can 

limit the allowable noise  level(s) at different times of the day for different zoned areas 

(i.e.,  residential,  commercial,  industrial)  and  protect  residential  areas.  The maximum 

allowable  noise  levels  are  typically  higher  during  daytime  hours  and  lower  during 

nighttime hours. 

Likewise, a  lighting  standards could be added  to  the  zoning ordinance  to manage  the 

amount of glare and light pollution caused by industrial uses such as warehouses. 

 

 

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    49 

 

 

F. Use  the  provisions  of  Act  209  to  pay  for  off‐site  transportation  improvements 

(impact fees). 

Priority: HIGH  Benefit: Helps fund transportation improvements, or incremental improvement needs, made necessary by new development. 

Planning Level  Cost Estimate: $50,000 

Public Preference: Surveys of the public have registered general agreement with the recommendation.   

Background:  Article  V‐A  of  the  Pennsylvania  Municipalities  Planning  Code  (MPC), 

commonly  referred  to  as  Act  209,  can  be  used  by municipalities  to  pay  for  off‐site 

transportation impacts, such as improvements to the PA 233 interchange with I‐81. The 

Pennsylvania General Assembly enacted the law to ensure that the cost of needed capital 

improvements can be applied to new developments  in a manner that will allocate the 

cost of those improvements among developers. This power is given to municipalities such 

as Penn Township that have adopted a municipal comprehensive plan, subdivision and 

land development ordinance, and zoning ordinance. There are currently no municipalities 

within  Cumberland  County  that  administer  their  own  Transportation  Impact  Fee 

ordinance. 

 

Actions: 

The  Township  planning  commission  should  develop  a  Light  Ordinance  for 

consideration and adoption by the Township supervisors. The lighting ordinance 

can be included within the Township’s existing Subdivision and Land Development 

ordinance, or developed as a stand‐alone ordinance. Regardless,  the ordinance 

should address several key  issues,  including: maximum allowable  illuminance at 

the  property  boundary,  permitted  luminaire  types,  aiming  and  shielding, 

maximum mounting heights, excessive glare, curfew hours, and penalties for code 

infractions. The ordinance should also cover how light would be measured, as well 

as how complaints would be addressed. 

 

The Township should update its noise ordinance for consideration and adoption 

by  the  Township  supervisors.  Such  an  ordinance  could  include  allowances  or 

exemptions  for  certain  uses,  such  as  authorized  emergency  vehicles  or  utility 

companies, bells or chimes from schools or religious  institutions,  lawn care and 

maintenance equipment, power tools between 7 a.m. and 10 p.m., and properly 

permitted construction. Also possible exemptions could include sporting events, 

establishments  with  entertainment  permits,  parades,  and  special  events  and 

engines regulated by PennDOT. 

Penn Township PA Route 233 Corridor Study 

50        

Impact  fees only apply  to new development proposed after  the Township publishes a 

notice  of  intent  that  it  plans  to  adopt  impact  fees.  Developments  currently  “in  the 

pipeline” are grandfathered in under existing regulations and would not be subject to pay 

the  impact  fee.  The  Township  should  carefully  evaluate  the  status  of  proposed 

developments prior to beginning the impact fee process to ensure an impact fee would 

be feasible. 

 

Enacting an impact fee is a five‐step process beginning with establishment of an advisory 

committee to oversee the process. Three reports then need to be generated: a land use 

assumptions report, a roadway sufficiency analysis, and a capital improvements plan. The 

process culminates with the adoption of an ordinance.  

 

Following  the MPC  requirements,  traffic  impact  fees  could be used  to  fund up  to 50 

percent of the cost of the  interchange  improvements.  Impact fees are collected at the 

time of building permit issuance for new development in the designated service area. 

 

 

 

G. Improve the existing park and ride lot.  

Priority: LOW  Benefit: Encourages use of modes other than the single‐occupant vehicle for travel. 

Planning Level  Cost Estimate: $100,000 

Public Preference: This issue did not register as a high priority among the public.  

Background:  The  50‐space  park  and  ride  lot  is  unimproved.  Improvements  such  as 

enlarging  the  size of  lot, with  improved  lighting  could be  accomplished  as part of  an 

overall interchange improvement. Moreover, a realignment of Hair Road could improve 

safety  and  economic  development  potential  by  taking  local  traffic  away  from  the 

interchange, and providing for a four‐leg intersection with the new warehouse driveway 

that  is  currently planned  for  the opposite  side of PA 233  (or parcel 1.2). Capital Area 

Transit  (CAT) serves the park and ride  lot, which serves as an  intermediate stop on  its 

longer distance, Route 81 commuter service between Harrisburg and Shippensburg. 

 

Action: 

The  Township  planning  commission  should  use  the  provisions  of  Act  209  to 

leverage the availability of private funding to fund public improvements, where 

possible. A  typical  impact  fee  levy  is  in  the  range of $1,500  to $2,000  for each 

proposed peak hour trip, which would have the benefit of generating $1.5 to $2.0 

million in revenue. See also PennDOT Publication 639: Transportation Impact Fees 

(2009). 

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    51 

Figure 14 and Figure 15 provide more information on the commuting characteristics of 

the township’s resident workers. 

 

 

 

Figure 14: Penn Township Resident Worker Destinations (2014) 

 Source: U.S. Census LEHD 

Action: 

Consider  the  improving  the  park  and  ride  lot  as  part  of  any  design  for  an 

improved interchange.  The park and ride is an important facility for the township 

and the greater Newville area, helping to facilitate intermodalism and journey‐to‐

work trips. While Penn Township has become more of an employment destination 

in recent years, it remains a net exporter of labor, as a majority of the township’s 

resident  workers  commute  to  destinations  outside  of  the  township  such  as 

Harrisburg (30 miles away) and Chambersburg (25 miles) for employment. 

Penn Township PA Route 233 Corridor Study 

52        

Figure 15: Penn Township Journey‐to‐Work Commutation Patterns (2014) 

 Source: U.S. Census LEHD 

 

H. Address safety and capacity needs at the Interstate 81 interchange. 

Priority: HIGH  Benefit: Addresses safety and capacity at the interchange, as the “Do Nothing” alternative is forecasted to yield unacceptable levels of service by 2035. 

Planning Level  Cost Estimate: Upwards of $15 million, depending upon option chosen 

Public Preference: Public preferences are mixed on the future of the interchange, as some want to see safety and capacity improved, while others acknowledge (as a benefit) the limiting factor the interchange has on development within the area. 

Background: Interstate 81’s interchange with PA 233/Centerville Road is Penn Township’s 

“front door” to the national highway network. The  interchange was constructed  in the 

early 1960s and appears on the regional long range transportation plan as a long‐range 

need.  The  arrival  of  warehousing  activity  in  Penn  Township  and  throughout  the 

Cumberland  Valley  is  challenging  the  60‐year‐old  design  of  the  interchange.  The 

juxtaposition of the interchange with a rest area on the northbound side of the interstate 

also introduces concerns with heavy trucks plying the grade of the northbound onramp 

trying  to merge with  other  truck  traffic  that  is  decelerating  into  the  rest  area.  The 

Township is also interested in addressing the horizontal curvature of PA 233 through the 

interchange as part of any proposed improvement. 

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    53 

The study advanced five alternatives, which are described in more detail in the following 

points: 

No Build (Do Nothing) – The “no build” alternative  is  included as a baseline 

from which to plan. This alternative would retain the existing transportation 

infrastructure,  including  lane  configuration  and  intersection  traffic  control. 

While this alternative is the least expensive option, it results in unacceptable 

levels of service for several movements by 2035.  

Improved Diamond – This alternative  includes an additional traffic signal at 

the northbound off‐ramp of Interstate 81, and additional turning lanes on PA 

233 and both I‐81 off‐ramps. The addition of turning lanes on PA 233 would 

effectively remove the existing shoulders, which would affect non‐motorized 

travel through the interchange. The lack of a shoulder would also make future 

maintenance and protection of traffic much more challenging as future bridge 

work is being performed. This alternative would provide acceptable levels of 

service for all movements through the  intersection through 2035. Figure 16 

graphically illustrates the Improved Diamond Interchange option. 

Figure 16: Improved Diamond Interchange Alternative 

 

Partial Cloverleaf – This alternative yields the most improved level of service 

and entails  the  construction of new  loop  ramps and  the  relocation and/or 

removal of existing  ramps. The  I‐81 bridge structures would be widened  to 

accommodate acceleration  lanes, thus  increasing the weaving area distance 

between the northbound on‐ramp and the deceleration  lane for the nearby 

rest area. This option provides the best operation for PA 233 traffic passing 

through  the  interchange  since  there would be no  traffic  signals within  the 

Penn Township PA Route 233 Corridor Study 

54        

interchange. Hair Road would also be relocated as part of this option. Figure 

17 illustrates the Partial Cloverleaf option. 

Figure 17: Partial Cloverleaf Alternative 

 

  

Diverging Diamond – This option represents a relatively new traffic technique, 

as  there  are  currently  no  diverging  diamond  interchanges  (DDI)  in 

Pennsylvania  (although  one  is  under  construction  and  others  are  being 

considered). This design favors movements coming on and off the interstate 

(in Exit 37’s case, this represents approximately 75 percent of all traffic). The 

on‐ and off‐ramps would be YIELD–controlled, while through traffic on PA 233 

would be controlled by  signals on either  side of  the  interchange, and  their 

movements would be reversed (see Figure 18). As such, it reduces conflicting 

traffic  for  left  turning  movements.  The  alternative,  while  relatively 

inexpensive,  provides  mixed  results,  with  superior  levels  of  service  for 

interstate‐related traffic coming at the expense of through movements on PA 

233.   

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    55 

Figure 18: Diverging Diamond Interchange Alternative 

 

 

Relocated On‐ramps – This option moves the on‐ramps further away from the 

interchange  to  align  with  proposed  realignments  of  local  roads.  This 

alternative features a lengthened northbound on‐ramp that would run on an 

alignment behind the existing rest area before entering I‐81 at a point nearly 

0.7 mile  north  of  the  interchange.  The  new  on‐ramp  for  northbound  I‐81 

would be two lanes. Turning lanes would be added to PA 233 and a new traffic 

signal added at the northbound off‐ramp’s intersection with PA 233. Hair Road 

and the existing park and ride lot would be relocated to a point north of their 

existing locations. This option also includes sound walls along the south side 

of I‐81.  

Estimated Cost < $2 million

Penn Township PA Route 233 Corridor Study 

56        

Figure 19: Relocated On‐ramps Alternative 

 

 

All  the alternatives exhibited varying degrees of effectiveness, and are as depicted  in 

Table 8, Table 9, and Table 10 at the end of this chapter. 

 

 

 

Actions: 

Petition the Harrisburg Area Transportation Study  (the metropolitan planning 

organization encompassing Penn Township), to move the Exit 37 interchange to 

near‐term phases of the long range transportation plan. The development of the 

region’s  2019  Transportation  Improvement  Program  begins  in  spring  2017. 

Getting the interchange onto nearer‐term phases of the long range plan is likely 

not  feasible,  given  the  overwhelming  demands  across  the  region  for 

transportation funding. The Township should present the results of this study to 

the  Harrisburg  MPO  for  consideration  as  future  plans  and  programs  are 

contemplated. 

 

Develop a Point of Access Study for the Exit 37 interchange. FHWA requirements 

dictate  that any  change  to an  interstate  interchange  require a Point of Access 

study. 

Estimated Cost $5 million

Penn Township  PA Route 233 Corridor Study 

FINAL REPORT    57 

I. Consider sound barriers as part of any interchange improvement. 

Priority: MEDIUM  Benefit: Mitigates noise being generated by truck traffic using the interchange. 

Planning Level  Cost Estimate: $750 million 

Public Preference: This recommendation was not formally presented to the public, although options oriented toward mitigating noise (such as updating the Township’s noise ordinance) were well received.  

Background: A common complaint associated with the development of warehousing in 

the  area  is  related  to  unwanted  noise  pollution.  Other  non‐point  sources  of  noise 

pollution come from the trucks that service the warehouses found within the study area. 

The on‐ramp to I‐81 northbound at Exit 37 features a grade that causes heavy laboring of 

vehicle engines, which increases traffic noise levels to surrounding areas. Traffic noise can 

be mitigated through the use of berms or other man‐made features for noise abatement. 

 

 

J. Consider enlarging the rest area on I‐81 northbound. 

Priority: MEDIUM  Benefit: Removes potential for truckers to park along the Exit 37 on‐ and off‐ramps. 

Planning Level  Cost Estimate: $1 to $5 million 

Public Preference: This recommendation was also not formally presented to the public, although there were concerns expressed with improving traffic safety as it related to trucks within the study area.  

Background: PennDOT (then the Department of Highways) built the rest area and opened 

it  to  travelers  in  the  early 1970s.  There  are  vending machines  and overnight parking 

available at the rest area, including 22 spaces for trucks.  

The shortage of available truck parking in Pennsylvania has been well documented, most 

notably through the state Transportation Advisory Committee (TAC) study of 2007, which 

Action: 

Consider sound walls as part of any final design for an improved interchange. The 

proposed  sound  wall  buffering  township  properties  from  I‐81  would  add 

approximately $750,000 to any improved interchange design.  Acoustical engineers 

can evaluate sources and patterns of noise to determine if noise barriers would be 

appropriate and cost effective as part of any interchange improvement alternative 

that would be advanced.  

Penn Township PA Route 233 Corridor Study 

58        

noted that I‐81 is a priority corridor within the state, and one that exhibits unmet parking 

demand.3 

Truckers routinely fill the rest area to capacity before parking along the shoulders of the 

on‐ and off‐ramps at Exit 37, which poses safety, efficiency, and environmental impacts. 

This  also  causes pavement distress  for  the  shoulders  along  these  ramps, which were 

intended only for short‐term parking. An expanded rest area would have a dual benefit 

of serving travelers while addressing the need for additional truck parking along the I‐81 

corridor and within the study area.   

There  are  currently  no  projects  programmed  involving  the  rest  area,  although  the 

Department does plan to make electrical upgrades over the near‐term.   

 

 

                                                            3 A 2012 study done by Shippensburg University for the I‐81 Corridor Coalition inventoried the availability of truck parking spaces along the corridor, concluding that there were just over 2,600 total truck parking spaces (commercial and rest area) throughout the state.  

Action: 

The  Township  should  approach  PennDOT’s  Facilities  Department  regarding 

planning and programming options for the rest area.  Future coordination should 

be done in conjunction with the Harrisburg MPO involving any future planning and 

preliminary engineering design work for the adjacent interchange. Option 5 of the 

interchange alternatives for example includes direct access to the rest area from a 

proposed on‐ramp to I‐81 (see Figure 19).  

Penn Township PA Route 233 Corridor Study 

FINAL REPORT  59 

Table 8: Interchange Scenario Comparison Matrix Interchange Scenario 

Description  Pros  Cons  Estimated Cost 

No Build  Retains existing interchange 

configuration and traffic control  + Least expensive option ‐ All but two movements operate in a failed condition by 2035 

N/A 

Improved Diamond  

Signalize both ramp intersections with PA 233 

Widen ramps to provide separate turning lanes 

Additional turning lanes 

Use shoulders to add a lane under the bridge 

+ Short‐term, easy to implement + Would buy time until the structures on I‐81 would need to be replaced in ~30 years  

+ Limited‐to‐no right‐of‐way acquisition required 

‐ Would lose the shoulders under the bridge for horse and buggy movement 

‐ Future MPT of bridge work would be a concern 

$1M 

Partial Cloverleaf 

Construct new PA 233 SB to I‐81 NB loop ramp 

Construct new I‐81 SB to PA 233 SB loop ramp 

Relocate PA 233 to I‐81 SB ramp 

Relocate I‐81 NB to PA 233 ramp 

Widen bridge structures for acceleration lanes 

Remove existing NB on‐ramp 

Relocate Hair Road 

+ Addresses lack of weaving area before the rest area 

+ Best improvement to operations (LOS “B” in AM and PM) 

‐ Most expensive option ‐ Could not be developer‐funded 

‐ Significant right‐of‐way acquisition required 

$5 ‐ $15M 

Diverging Diamond 

Signals control only through movements 

PA 233 through movements reversed through the interchange so left turns don’t require crossing opposing traffic 

On‐ and off‐ramps are YIELD controlled 

+ Gives priority to traffic interchanging with the interstate, or 75% of the traffic 

+ Short‐term, easy to implement + Would buy time until the structures on I‐81 would need to be replaced in ~30 years 

+ Limited‐or‐no right‐of‐way acquisition required 

‐ Does not work as well for through traffic on PA 233 (LOS “D” and “E” NB in PM and AM peak, respectively) 

‐ Limited shoulder width under the bridge for horse and buggy movement (median required to separate reversed traffic movements) 

< $2M 

Penn Township PA Route 233 Corridor Study 

60    

Interchange Scenario 

Description  Pros  Cons  Estimated Cost 

Relocated  On‐ramps 

Moves existing on‐ and off‐ramp alignments farther from the interchange to align with proposed realignments of local roads. 

+ Opens up area at the interchange’s NW quadrant for commercial development 

+ Addresses the lack of a weaving area before the rest area 

+ Removes traffic from I‐81 bridges + Increased spacing between ramp terminals could allow left turn lanes to be constructed beyond the I‐81 overpass, allowing shoulders to be maintained under I‐81 

‐ Significant right‐of‐way acquisition required 

‐ Providing access from the relocated Exit 37 northbound on‐ramp into the rest area will be challenged by creating a merge area with a high speed differential 

$5 M 

    

Penn Township PA Route 233 Corridor Study 

FINAL REPORT  61 

Table 9: Interchange Scenario Level of Service (seconds of delay) – Weekday A.M. Peak Hour* 

Movement 2013 Existing Diamond 

2035 Existing Diamond 

2035 Improved Diamond 

2035 Partial Cloverleaf 

2035 Diverging Diamond 

A: I‐81 NB to PA 233 NB  D (57.9)  F (3028)  D (57.9)  C (50.3)  D (58.4) 

B: I‐81 NB to PA 233 SB  C (47.8)  F (2478)  C (40.7)  C (35.3)  A (0.9) 

C: I‐81 SB to PA 233 NB  C (36.7)  F (169)  D (55.4)  A (10.2)  A (2.7) 

D: I‐81 SB to PA 233 SB  D (55.3)  F (206)  D (61.4)  D (71.0)  B (22.0) 

E: PA 233 SB to I‐81 NB  B (22.0)  E (88.4)  C (36.4)  A (0.0)  B (25.2) 

F: PA 233 SB to I‐81 SB  A (3.6)  C (51.5)  A (0.0)  B (28.9)  A (0.0) 

G: PA 233 NB to I‐81 NB  A (0.0)  A (0.0)  C (31.7)  C (36.9)  A (2.7) 

H: PA 233 NB to I‐81 SB  A (7.3)  F (547)  C (47.1)  B (25.7)  C (34.5) 

I: PA 233 SB thru interchange  B (19.5)  E (85.9)  B (15.5)  A (14.0)  C (38.3) 

J: PA 233 NB thru interchnge  A (4.6)  F (545)  C (34.5)  A (8.5)  E (90.6) 

Overall Interchange  B (19.5)  F (519)  C (38.4)  B (23.0)  B (28.9)  

Table 10: Interchange Scenario Level of Service (seconds of delay) – Weekday P.M. Peak Hour 

Movement 2013 Existing Diamond 

2035 Existing Diamond 

2035 Improved Diamond 

2035 Partial Cloverleaf 

2035 Diverging Diamond 

A: I‐81 NB to PA 233 NB  C (44.3)  F (17203)  D (64.5)  D (56.2)  C (47.7) 

B: I‐81 NB to PA 233 SB  B (27.6)  F (17002)  B (28.8)  C (41.2)  A (1.5) 

C: I‐81 SB to PA 233 NB  C (48.0)  F (242)  C (51.0)  B (22.0)  A (5.9) 

D: I‐81 SB to PA 233 SB  D (63.7)  F (269)  B (28.4)  C (54.2)  C (32.5) 

E: PA 233 SB to I‐81 NB  B (24.1)  C (45.2)  C (44.2)  A (0.0)  B (27.9) 

F: PA 233 SB to I‐81 SB  A (8.6)  B (18.0)  A (0.0)  B (28.9)  A (0.0) 

G: PA 233 NB to I‐81 NB  A (0.0)  A (0.0)  B (28.9)  D (64.2)  A (2.7) 

H: PA 233 NB to I‐81 SB  A (13.9)  F (199)  C (40.2)  B (28.5)  C (34.2) 

I: PA 233 SB thru interchange  B (21.6)  C (42.7)  B (20.2)  B (15.7)  C (51.1) 

J: PA 233 NB thru interchange 

A (11.2)  F (196.3) C (30.9) 

A (11.8)  D (78.6) 

Overall Interchange  C (32.3)  F (2392)  C (36.1)  B (29.3)  C (30.3) 

Key: Level of Service (Experienced Travel Time); Experienced Travel Time = Control Delay from signals, stop control, and yield control + Extra Distance Travel Time (such as loop ramps); Source: Highway Capacity Manual (TRB)  *Note: From a Level of Service perspective, the Relocated On‐ramp Alternative would be very similar to the Improved Diamond Alternative. 

Penn Township PA Route 233 Corridor Study 

62    

Table 11: Implementation Plan Matrix Project/Initiative  Actions  Priority  Timing  Lead 

A. Stand‐alone Commercial and Industrial zoning districts 

Revise Zoning Ordinance (text and map) to segregate Commercial and Industrial uses within the township. Recommendations by specific parcel are included elsewhere within this report.  

High  Medium‐term Township planning commission 

B. Official Map  Develop an Official Map to address proposed interchange improvements and to identify future areas to be acquired for public purposes.  

High  Medium‐term Township planning commission 

C. Comprehensive Plan  Update the comprehensive plan. High  Near‐term 

Township planning commission 

D. Access Management  Develop an Access Management Plan. 

High  Medium‐term Township planning commission 

E. Noise and Light Ordinance  Develop ordinances to manage noise and light. 

Medium  Medium‐term Township planning commission 

F. Enact Impact Fees (Act 209)  Leverage private dollars for public transportation improvements. 

High  Ongoing Township Supervisors 

G. Park and ride lot  In tandem with future work proposed for the Exit 37 interchange. 

Low  Long‐term  PennDOT 

H. Address safety and capacity needs at the Exit 37 interchange 

Develop a Point of Access Study; petition HATS to put the interchange on a future TIP for design work. 

High  Long‐term  PennDOT 

I. Consider sound barriers as part of any interchange improvement 

Investigate this element as part of any preliminary engineering work  Medium  Long‐term  PennDOT 

J. Consider enlarging the rest area 

Coordinate with the Harrisburg MPO and PennDOT’s Facilities Department as progress is made on Recommendation H. 

Medium  Long‐term  PennDOT 

Note: Near‐term = 0‐1 year; Medium‐term = 1‐2 years; Long‐term = > 2 years 

Penn Township PA Route 233 Corridor Study 

FINAL REPORT    63 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Contact Information:  

Brian Funkhouser, AICP, Project Manager 

4431 North Front Street, 2nd floor 

Harrisburg, PA  17110 

(717) 213‐6236 

[email protected]