Activity ID Project Start Finish
NASA InstallNASA Install Dec-05-16 Jun-23-17
KSC-NASA Central CampusKSC-NASA Central Campus Dec-05-16 Jun-23-17
REL-03REL-03 Dec-05-16 Dec-08-16
REL-01REL-01 Dec-05-16 Dec-09-16
REL-02REL-02 Dec-05-16 Dec-08-16
REL-04REL-04 Dec-05-16 Dec-08-16
REL-05REL-05 Dec-05-16 Dec-07-16
REL-06REL-06 Dec-05-16 Dec-07-16
REL-07REL-07 Dec-05-16 Dec-07-16
REL-08REL-08 Dec-05-16 Dec-07-16
REL-09REL-09 Dec-05-16 Dec-08-16
REL-10REL-10 Dec-05-16 Dec-13-16
REL-14REL-14 Dec-05-16 Dec-09-16
REL-15REL-15 Dec-05-16 Dec-09-16
REL-16REL-16 Dec-05-16 Dec-08-16
REL-11REL-11 Dec-05-16 Dec-07-16
REL-12REL-12 Dec-05-16 Dec-07-16
REL-13REL-13 Dec-05-16 Dec-07-16
REL-17REL-17 Dec-05-16 Dec-12-16
REL-18REL-18 Feb-09-17 Feb-13-17
REL-19REL-19 Feb-23-17 Feb-24-17
REL-03-CTREL-03-CT Feb-27-17 Mar-02-17
REL-01-CTREL-01-CT Mar-03-17 Mar-10-17
REL-02-CTREL-02-CT Mar-13-17 Mar-16-17
REL-04-CTREL-04-CT Mar-17-17 Mar-22-17
REL-05-CTREL-05-CT Mar-23-17 Mar-28-17
REL-06-CTREL-06-CT Mar-29-17 Mar-31-17
REL-07-CTREL-07-CT Apr-03-17 Apr-06-17
REL-08-CTREL-08-CT Apr-07-17 Apr-11-17
REL-09-CTREL-09-CT Apr-12-17 Apr-18-17
REL-10-CTREL-10-CT Apr-19-17 Apr-28-17
REL-14-CTREL-14-CT May-01-17 May-08-17
REL-15-CTREL-15-CT May-09-17 May-15-17
REL-16-CTREL-16-CT May-17-17 May-22-17
REL-11-CTREL-11-CT May-23-17 May-26-17
REL-12-CTREL-12-CT May-30-17 Jun-01-17
REL-13-CTREL-13-CT Jun-02-17 Jun-06-17
REL-17-CTREL-17-CT Jun-08-17 Jun-15-17
REL-18-CTREL-18-CT Jun-16-17 Jun-21-17
REL-19-CTREL-19-CT Jun-22-17 Jun-23-17
MTAC InstallMTAC Install Dec-05-16 Mar-21-17
Main Terminal & Airport ConcessionMain Terminal & Airport ConcessionDec-05-16 Mar-21-17
REL-01REL-01 Dec-05-16 Dec-06-16
REL-02REL-02 Dec-05-16 Dec-12-16
REL-03REL-03 Dec-05-16 Dec-06-16
REL-04REL-04 Jan-10-17 Jan-12-17
REL-05REL-05 Jan-17-17 Jan-19-17
REL-06REL-06 Jan-24-17 Jan-26-17
REL-07REL-07 Jan-31-17 Feb-03-17
REL-15REL-15 Feb-06-17 Feb-06-17
REL-01-CTREL-01-CT Feb-07-17 Feb-13-17
REL-02-CTREL-02-CT Feb-14-17 Feb-21-17
REL-03-CTREL-03-CT Feb-22-17 Feb-24-17
REL-04-CTREL-04-CT Feb-27-17 Mar-02-17
REL-05-CTREL-05-CT Mar-03-17 Mar-08-17
REL-06-CTREL-06-CT Mar-09-17 Mar-13-17
REL-07-CTREL-07-CT Mar-14-17 Mar-17-17
REL-15-CTREL-15-CT Mar-20-17 Mar-21-17
Shands InstallShands Install Dec-05-16 Jul-31-17
Shands Phase 2Shands Phase 2 Dec-05-16 Jul-31-17
REL-01REL-01 Dec-05-16 Dec-08-16
REL-16REL-16 Dec-05-16 Dec-12-16
Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017
Jun-23-17, NASA Install
Jun-23-17, KSC-NASA Central Campus
Dec-08-16, REL-03
Dec-09-16, REL-01
Dec-08-16, REL-02
Dec-08-16, REL-04
Dec-07-16, REL-05
Dec-07-16, REL-06
Dec-07-16, REL-07
Dec-07-16, REL-08
Dec-08-16, REL-09
Dec-13-16, REL-10
Dec-09-16, REL-14
Dec-09-16, REL-15
Dec-08-16, REL-16
Dec-07-16, REL-11
Dec-07-16, REL-12
Dec-07-16, REL-13
Dec-12-16, REL-17
Feb-09-17 Feb-13-17, REL-18
Feb-23-17 Feb-24-17, REL-19
Feb-27-17 Mar-02-17, REL-03-CT
Mar-03-17 Mar-10-17, REL-01-CT
Mar-13-17 Mar-16-17, REL-02-CT
Mar-17-17 Mar-22-17, REL-04-CT
Mar-23-17 Mar-28-17, REL-05-CT
Mar-29-17 Mar-31-17, REL-06-CT
Apr-03-17 Apr-06-17, REL-07-CT
Apr-07-17 Apr-11-17, REL-08-CT
Apr-12-17 Apr-18-17, REL-09-CT
Apr-19-17 Apr-28-17, REL-10-CT
May-01-17 May-08-17, REL-14-CT
May-09-17 May-15-17, REL-15-CT
May-17-17 May-22-17, REL-16-CT
May-23-17 May-26-17, REL-11-CT
May-30-17 Jun-01-17, REL-12-CT
Jun-02-17 Jun-06-17, REL-13-CT
Jun-08-17 Jun-15-17, REL-17-CT
Jun-16-17 Jun-21-17, REL-18-CT
Jun-22-17 Jun-23-17, REL-19-CT
Mar-21-17, MTAC Install
Mar-21-17, Main Terminal & Airport Concession
Dec-06-16, REL-01
Dec-12-16, REL-02
Dec-06-16, REL-03
Jan-10-17 Jan-12-17, REL-04
Jan-17-17 Jan-19-17, REL-05
Jan-24-17 Jan-26-17, REL-06
Jan-31-17 Feb-03-17, REL-07
Feb-06-17 Feb-06-17, REL-15
Feb-07-17 Feb-13-17, REL-01-CT
Feb-14-17 Feb-21-17, REL-02-CT
Feb-22-17 Feb-24-17, REL-03-CT
Feb-27-17 Mar-02-17, REL-04-CT
Mar-03-17 Mar-08-17, REL-05-CT
Mar-09-17 Mar-13-17, REL-06-CT
Mar-14-17 Mar-17-17, REL-07-CT
Mar-20-17 Mar-21-17, REL-15-CT
Jul-31-17, Shands Install
Jul-31-17, Shands Phase 2
Dec-08-16, REL-01
Dec-12-16, REL-16
USF College of Business... WTG - Install Status - 9 Month (Good) Dec-05-16 14:37
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Milestone
Summary
Page 1 of 6 TASK filter: WTG - 9 Month CW Install Status (Good).
Resource Profile Filter:All Resources
Activity ID Project Start Finish
REL-20REL-20 Dec-05-16 Dec-12-16
REL-19REL-19 Dec-05-16 Dec-09-16
REL-22REL-22 Dec-05-16 Dec-12-16
REL-21REL-21 Dec-05-16 Dec-09-16
REL-26REL-26 Dec-05-16 Dec-12-16
REL-25REL-25 Dec-05-16 Dec-09-16
REL-28REL-28 Dec-05-16 Dec-12-16
REL-27REL-27 Dec-05-16 Dec-09-16
REL-05REL-05 Dec-05-16 Dec-08-16
REL-12REL-12 Dec-05-16 Dec-07-16
REL-11REL-11 Dec-05-16 Dec-08-16
REL-18REL-18 Dec-05-16 Dec-07-16
REL-17REL-17 Dec-05-16 Dec-08-16
REL-24REL-24 Dec-05-16 Dec-07-16
REL-23REL-23 Dec-05-16 Dec-08-16
REL-30REL-30 Dec-05-16 Dec-08-16
REL-29REL-29 Dec-05-16 Dec-09-16
REL-02REL-02 Dec-05-16 Dec-13-16
REL-01-CTREL-01-CT Dec-14-16 Dec-20-16
REL-04-CTREL-04-CT Dec-21-16 Dec-28-16
REL-08-CTREL-08-CT Dec-29-16 Jan-05-17
REL-03-CTREL-03-CT Jan-06-17 Jan-13-17
REL-07-CTREL-07-CT Jan-16-17 Jan-23-17
REL-06-CTREL-06-CT Jan-24-17 Jan-26-17
REL-10-CTREL-10-CT Jan-27-17 Feb-03-17
REL-09-CTREL-09-CT Feb-06-17 Feb-13-17
REL-14-CTREL-14-CT Feb-14-17 Feb-21-17
REL-13-CTREL-13-CT Feb-22-17 Mar-01-17
REL-16-CTREL-16-CT Mar-02-17 Mar-09-17
REL-15-CTREL-15-CT Mar-10-17 Mar-17-17
REL-20-CTREL-20-CT Mar-20-17 Mar-27-17
REL-19-CTREL-19-CT Mar-28-17 Apr-04-17
REL-22-CTREL-22-CT Apr-05-17 Apr-12-17
REL-21-CTREL-21-CT Apr-13-17 Apr-20-17
REL-26-CTREL-26-CT Apr-21-17 Apr-28-17
REL-25-CTREL-25-CT May-01-17 May-08-17
REL-28-CTREL-28-CT May-09-17 May-16-17
REL-27-CTREL-27-CT May-17-17 May-24-17
REL-05-CTREL-05-CT May-25-17 May-31-17
REL-12-CTREL-12-CT Jun-01-17 Jun-05-17
REL-11-CTREL-11-CT Jun-06-17 Jun-12-17
REL-18-CTREL-18-CT Jun-13-17 Jun-16-17
REL-17-CTREL-17-CT Jun-19-17 Jun-23-17
REL-24-CTREL-24-CT Jun-26-17 Jun-28-17
REL-23-CTREL-23-CT Jun-29-17 Jul-05-17
REL-30-CTREL-30-CT Jul-06-17 Jul-12-17
REL-29-CTREL-29-CT Jul-13-17 Jul-19-17
REL-02-CTREL-02-CT Jul-21-17 Jul-31-17
Shands Phase 3Shands Phase 3 Dec-05-16 Feb-10-17
Release 01Release 01 Dec-05-16 Dec-08-16
Release 02Release 02 Dec-08-16 Dec-14-16
Release 03Release 03 Dec-14-16 Dec-20-16
Release 04Release 04 Dec-20-16 Dec-27-16
Release 05Release 05 Dec-27-16 Dec-30-16
Release 06Release 06 Dec-30-16 Jan-04-17
Release 07Release 07 Jan-04-17 Jan-04-17
Release 01-CTRelease 01-CT Jan-05-17 Jan-10-17
Release 02-CTRelease 02-CT Jan-11-17 Jan-17-17
Release 03-CTRelease 03-CT Jan-18-17 Jan-24-17
Release 04-CTRelease 04-CT Jan-25-17 Jan-31-17
Release 05-CTRelease 05-CT Feb-01-17 Feb-06-17
Release 06-CTRelease 06-CT Feb-08-17 Feb-09-17
Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017
Dec-12-16, REL-20
Dec-09-16, REL-19
Dec-12-16, REL-22
Dec-09-16, REL-21
Dec-12-16, REL-26
Dec-09-16, REL-25
Dec-12-16, REL-28
Dec-09-16, REL-27
Dec-08-16, REL-05
Dec-07-16, REL-12
Dec-08-16, REL-11
Dec-07-16, REL-18
Dec-08-16, REL-17
Dec-07-16, REL-24
Dec-08-16, REL-23
Dec-08-16, REL-30
Dec-09-16, REL-29
Dec-13-16, REL-02
Dec-14-16 Dec-20-16, REL-01-CT
Dec-21-16 Dec-28-16, REL-04-CT
Dec-29-16 Jan-05-17, REL-08-CT
Jan-06-17 Jan-13-17, REL-03-CT
Jan-16-17 Jan-23-17, REL-07-CT
Jan-24-17 Jan-26-17, REL-06-CT
Jan-27-17 Feb-03-17, REL-10-CT
Feb-06-17 Feb-13-17, REL-09-CT
Feb-14-17 Feb-21-17, REL-14-CT
Feb-22-17 Mar-01-17, REL-13-CT
Mar-02-17 Mar-09-17, REL-16-CT
Mar-10-17 Mar-17-17, REL-15-CT
Mar-20-17 Mar-27-17, REL-20-CT
Mar-28-17 Apr-04-17, REL-19-CT
Apr-05-17 Apr-12-17, REL-22-CT
Apr-13-17 Apr-20-17, REL-21-CT
Apr-21-17 Apr-28-17, REL-26-CT
May-01-17 May-08-17, REL-25-CT
May-09-17 May-16-17, REL-28-CT
May-17-17 May-24-17, REL-27-CT
May-25-17 May-31-17, REL-05-CT
Jun-01-17 Jun-05-17, REL-12-CT
Jun-06-17 Jun-12-17, REL-11-CT
Jun-13-17 Jun-16-17, REL-18-CT
Jun-19-17 Jun-23-17, REL-17-CT
Jun-26-17 Jun-28-17, REL-24-CT
Jun-29-17 Jul-05-17, REL-23-CT
Jul-06-17 Jul-12-17, REL-30-CT
Jul-13-17 Jul-19-17, REL-29-CT
Jul-21-17 Jul-31-17, REL-02-CT
Feb-10-17, Shands Phase 3
Dec-08-16, Release 01
Dec-14-16, Release 02
Dec-14-16 Dec-20-16, Release 03
Dec-20-16 Dec-27-16, Release 04
Dec-27-16 Dec-30-16, Release 05
Dec-30-16 Jan-04-17, Release 06
Jan-04-17 Jan-04-17, Release 07
Jan-05-17 Jan-10-17, Release 01-CT
Jan-11-17 Jan-17-17, Release 02-CT
Jan-18-17 Jan-24-17, Release 03-CT
Jan-25-17 Jan-31-17, Release 04-CT
Feb-01-17 Feb-06-17, Release 05-CT
Feb-08-17 Feb-09-17, Release 06-CT
USF College of Business... WTG - Install Status - 9 Month (Good) Dec-05-16 14:37
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Milestone
Summary
Page 2 of 6 TASK filter: WTG - 9 Month CW Install Status (Good).
Resource Profile Filter:All Resources
Activity ID Project Start Finish
Release 07-CTRelease 07-CT Feb-10-17 Feb-10-17
USFCOB InstallUSFCOB Install Dec-05-16 Mar-22-17
USF College of BusinessUSF College of Business Dec-05-16 Mar-22-17
REL-04REL-04 Dec-05-16 Dec-07-16
REL-08REL-08 Dec-05-16 Dec-07-16
REL-05REL-05 Dec-05-16 Dec-09-16
REL-06REL-06 Dec-05-16 Dec-08-16
REL-03REL-03 Dec-05-16 Dec-09-16
REL-09REL-09 Dec-05-16 Dec-09-16
REL-10REL-10 Dec-05-16 Dec-07-16
REL-11REL-11 Dec-05-16 Dec-07-16
REL-12REL-12 Dec-05-16 Dec-07-16
REL-13REL-13 Dec-05-16 Dec-08-16
REL-14REL-14 Dec-05-16 Dec-09-16
REL-15REL-15 Dec-05-16 Dec-06-16
REL-16REL-16 Dec-05-16 Dec-06-16
REL-17REL-17 Dec-05-16 Dec-05-16
REL-18REL-18 Dec-05-16 Dec-05-16
REL-19REL-19 Dec-05-16 Dec-05-16
REL-07-CTREL-07-CT Dec-06-16 Dec-12-16
REL-01-CTREL-01-CT Dec-05-16 Dec-20-16
REL-02-CTREL-02-CT Dec-21-16 Dec-29-16
REL-04-CTREL-04-CT Dec-30-16 Jan-03-17
REL-08-CTREL-08-CT Jan-04-17 Jan-09-17
REL-05-CTREL-05-CT Jan-10-17 Jan-17-17
REL-06-CTREL-06-CT Jan-18-17 Jan-23-17
REL-03-CTREL-03-CT Jan-24-17 Jan-31-17
REL-09-CTREL-09-CT Feb-01-17 Feb-08-17
REL-10-CTREL-10-CT Feb-09-17 Feb-13-17
REL-11-CTREL-11-CT Feb-14-17 Feb-17-17
REL-12-CTREL-12-CT Feb-20-17 Feb-23-17
REL-13-CTREL-13-CT Feb-24-17 Mar-01-17
REL-14-CTREL-14-CT Mar-03-17 Mar-09-17
REL-15-CTREL-15-CT Mar-10-17 Mar-14-17
REL-16-CTREL-16-CT Mar-15-17 Mar-16-17
REL-17-CTREL-17-CT Mar-17-17 Mar-20-17
REL-18-CTREL-18-CT Mar-21-17 Mar-21-17
REL-19-CTREL-19-CT Mar-22-17 Mar-22-17
APM-1 InstallAPM-1 Install Dec-05-16 Jul-06-17
APM-1APM-1 Dec-05-16 Jul-06-17
Release 01-GWRelease 01-GW Dec-05-16 Dec-08-16
Release 02-GWRelease 02-GW Dec-05-16 Dec-07-16
Release 03-GWRelease 03-GW Dec-05-16 Dec-07-16
Release 04-GWRelease 04-GW Dec-05-16 Dec-07-16
Release 05-GWRelease 05-GW Dec-05-16 Dec-07-16
Release 06-GWRelease 06-GW Dec-05-16 Dec-06-16
Release 07Release 07 Jan-03-17 Jan-05-17
Release 08Release 08 Jan-06-17 Jan-09-17
Release 09Release 09 Jan-10-17 Jan-11-17
Release 10Release 10 Jan-13-17 Jan-16-17
Release 11Release 11 Jan-17-17 Jan-18-17
Release 12Release 12 Jan-20-17 Jan-23-17
Release 13Release 13 Jan-24-17 Jan-25-17
Release 14Release 14 Jan-27-17 Jan-30-17
Release 15Release 15 Jan-31-17 Jan-31-17
Release 16Release 16 Feb-03-17 Feb-06-17
Release 17Release 17 Feb-07-17 Feb-08-17
Release 18Release 18 Feb-10-17 Feb-13-17
Release 19Release 19 Feb-14-17 Feb-15-17
Release 20Release 20 Feb-17-17 Feb-20-17
Release 21Release 21 Feb-21-17 Feb-22-17
Release 22Release 22 Feb-24-17 Feb-24-17
Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017
Feb-10-17 Feb-10-17, Release 07-CT
Mar-22-17, USFCOB Install
Mar-22-17, USF College of Business
Dec-07-16, REL-04
Dec-07-16, REL-08
Dec-09-16, REL-05
Dec-08-16, REL-06
Dec-09-16, REL-03
Dec-09-16, REL-09
Dec-07-16, REL-10
Dec-07-16, REL-11
Dec-07-16, REL-12
Dec-08-16, REL-13
Dec-09-16, REL-14
Dec-06-16, REL-15
Dec-06-16, REL-16
Dec-05-16, REL-17
Dec-05-16, REL-18
Dec-05-16, REL-19
Dec-12-16, REL-07-CT
Dec-20-16, REL-01-CT
Dec-21-16 Dec-29-16, REL-02-CT
Dec-30-16 Jan-03-17, REL-04-CT
Jan-04-17 Jan-09-17, REL-08-CT
Jan-10-17 Jan-17-17, REL-05-CT
Jan-18-17 Jan-23-17, REL-06-CT
Jan-24-17 Jan-31-17, REL-03-CT
Feb-01-17 Feb-08-17, REL-09-CT
Feb-09-17 Feb-13-17, REL-10-CT
Feb-14-17 Feb-17-17, REL-11-CT
Feb-20-17 Feb-23-17, REL-12-CT
Feb-24-17 Mar-01-17, REL-13-CT
Mar-03-17 Mar-09-17, REL-14-CT
Mar-10-17 Mar-14-17, REL-15-CT
Mar-15-17 Mar-16-17, REL-16-CT
Mar-17-17 Mar-20-17, REL-17-CT
Mar-21-17 Mar-21-17, REL-18-CT
Mar-22-17 Mar-22-17, REL-19-CT
Jul-06-17, APM-1 Install
Jul-06-17, APM-1
Dec-08-16, Release 01-GW
Dec-07-16, Release 02-GW
Dec-07-16, Release 03-GW
Dec-07-16, Release 04-GW
Dec-07-16, Release 05-GW
Dec-06-16, Release 06-GW
Jan-03-17 Jan-05-17, Release 07
Jan-06-17 Jan-09-17, Release 08
Jan-10-17 Jan-11-17, Release 09
Jan-13-17 Jan-16-17, Release 10
Jan-17-17 Jan-18-17, Release 11
Jan-20-17 Jan-23-17, Release 12
Jan-24-17 Jan-25-17, Release 13
Jan-27-17 Jan-30-17, Release 14
Jan-31-17 Jan-31-17, Release 15
Feb-03-17 Feb-06-17, Release 16
Feb-07-17 Feb-08-17, Release 17
Feb-10-17 Feb-13-17, Release 18
Feb-14-17 Feb-15-17, Release 19
Feb-17-17 Feb-20-17, Release 20
Feb-21-17 Feb-22-17, Release 21
Feb-24-17 Feb-24-17, Release 22
USF College of Business... WTG - Install Status - 9 Month (Good) Dec-05-16 14:37
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Milestone
Summary
Page 3 of 6 TASK filter: WTG - 9 Month CW Install Status (Good).
Resource Profile Filter:All Resources
Activity ID Project Start Finish
Release 23Release 23 Feb-27-17 Mar-01-17
Release 24Release 24 Mar-03-17 Mar-06-17
Release 25Release 25 Mar-07-17 Mar-09-17
Release 26Release 26 Mar-13-17 Mar-14-17
Release 27Release 27 Mar-17-17 Mar-21-17
Release 28Release 28 Mar-21-17 Mar-21-17
Release 29Release 29 Mar-22-17 Mar-24-17
Release 30Release 30 Mar-27-17 Mar-29-17
Release 31Release 31 Mar-29-17 Apr-03-17
Release 32Release 32 Apr-03-17 Apr-06-17
Release 01-GW-CTRelease 01-GW-CT Apr-06-17 Apr-11-17
Release 02-GW-CTRelease 02-GW-CT Apr-11-17 Apr-14-17
Release 03-GW-CTRelease 03-GW-CT Apr-14-17 Apr-19-17
Release 04-GW-CTRelease 04-GW-CT Apr-19-17 Apr-24-17
Release 05-GW-CTRelease 05-GW-CT Apr-24-17 Apr-26-17
Release 06-GW-CTRelease 06-GW-CT Apr-26-17 Apr-28-17
Release 07-CTRelease 07-CT Apr-28-17 May-02-17
Release 08-CTRelease 08-CT May-02-17 May-04-17
Release 09-CTRelease 09-CT May-04-17 May-08-17
Release 10-CTRelease 10-CT May-08-17 May-10-17
Release 11-CTRelease 11-CT May-10-17 May-11-17
Release 12-CTRelease 12-CT May-11-17 May-15-17
Release 13-CTRelease 13-CT May-15-17 May-17-17
Release 14-CTRelease 14-CT May-17-17 May-18-17
Release 15-CTRelease 15-CT May-18-17 May-19-17
Release 16-CTRelease 16-CT May-19-17 May-22-17
Release 17-CTRelease 17-CT May-22-17 May-23-17
Release 18-CTRelease 18-CT May-23-17 May-25-17
Release 19-CTRelease 19-CT May-25-17 May-30-17
Release 20-CTRelease 20-CT May-30-17 Jun-01-17
Release 21-CTRelease 21-CT Jun-01-17 Jun-02-17
Release 22-CTRelease 22-CT Jun-02-17 Jun-02-17
Release 23-CTRelease 23-CT Jun-05-17 Jun-07-17
Release 24-CTRelease 24-CT Jun-07-17 Jun-09-17
Release 25-CTRelease 25-CT Jun-09-17 Jun-13-17
Release 26-CTRelease 26-CT Jun-13-17 Jun-14-17
Release 27-CTRelease 27-CT Jun-15-17 Jun-19-17
Release 28-CTRelease 28-CT Jun-19-17 Jun-20-17
Release 29-CTRelease 29-CT Jun-20-17 Jun-22-17
Release 30-CTRelease 30-CT Jun-22-17 Jun-27-17
Release 31-CTRelease 31-CT Jun-27-17 Jun-30-17
Release 32-CTRelease 32-CT Jun-30-17 Jul-06-17
APM-2 InstallAPM-2 Install Dec-05-16 Jan-13-17
APM-2APM-2 Dec-05-16 Jan-13-17
Release 01-GWRelease 01-GW Dec-05-16 Dec-09-16
Release 02-GWRelease 02-GW Dec-05-16 Dec-08-16
Release 03-GWRelease 03-GW Dec-05-16 Dec-09-16
Release 04-GWRelease 04-GW Dec-05-16 Dec-08-16
Release 05Release 05 Dec-05-16 Dec-08-16
Release 06Release 06 Dec-05-16 Dec-08-16
Release 01-GW-CTRelease 01-GW-CT Dec-08-16 Dec-15-16
Release 02-GW-CTRelease 02-GW-CT Dec-15-16 Dec-20-16
Release 03-GW-CTRelease 03-GW-CT Dec-21-16 Dec-28-16
Release 04-GW-CTRelease 04-GW-CT Dec-28-16 Jan-04-17
Release 05-CTRelease 05-CT Jan-04-17 Jan-10-17
Release 06-CTRelease 06-CT Jan-10-17 Jan-13-17
APM-3 InstallAPM-3 Install Dec-05-16 Feb-15-17
APM-3APM-3 Dec-05-16 Feb-15-17
Release 01-GWRelease 01-GW Dec-05-16 Dec-09-16
Release 01-GW-CTRelease 01-GW-CT Jan-06-17 Jan-13-17
Release 02-GWRelease 02-GW Dec-05-16 Dec-08-16
Release 02-GW-CTRelease 02-GW-CT Jan-16-17 Jan-19-17
Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017
Feb-27-17 Mar-01-17, Release 23
Mar-03-17 Mar-06-17, Release 24
Mar-07-17 Mar-09-17, Release 25
Mar-13-17 Mar-14-17, Release 26
Mar-17-17 Mar-21-17, Release 27
Mar-21-17 Mar-21-17, Release 28
Mar-22-17 Mar-24-17, Release 29
Mar-27-17 Mar-29-17, Release 30
Mar-29-17 Apr-03-17, Release 31
Apr-03-17 Apr-06-17, Release 32
Apr-06-17 Apr-11-17, Release 01-GW-CT
Apr-11-17 Apr-14-17, Release 02-GW-CT
Apr-14-17 Apr-19-17, Release 03-GW-CT
Apr-19-17 Apr-24-17, Release 04-GW-CT
Apr-24-17 Apr-26-17, Release 05-GW-CT
Apr-26-17 Apr-28-17, Release 06-GW-CT
Apr-28-17 May-02-17, Release 07-CT
May-02-17 May-04-17, Release 08-CT
May-04-17 May-08-17, Release 09-CT
May-08-17 May-10-17, Release 10-CT
May-10-17 May-11-17, Release 11-CT
May-11-17 May-15-17, Release 12-CT
May-15-17 May-17-17, Release 13-CT
May-17-17 May-18-17, Release 14-CT
May-18-17 May-19-17, Release 15-CT
May-19-17 May-22-17, Release 16-CT
May-22-17 May-23-17, Release 17-CT
May-23-17 May-25-17, Release 18-CT
May-25-17 May-30-17, Release 19-CT
May-30-17 Jun-01-17, Release 20-CT
Jun-01-17 Jun-02-17, Release 21-CT
Jun-02-17 Jun-02-17, Release 22-CT
Jun-05-17 Jun-07-17, Release 23-CT
Jun-07-17 Jun-09-17, Release 24-CT
Jun-09-17 Jun-13-17, Release 25-CT
Jun-13-17 Jun-14-17, Release 26-CT
Jun-15-17 Jun-19-17, Release 27-CT
Jun-19-17 Jun-20-17, Release 28-CT
Jun-20-17 Jun-22-17, Release 29-CT
Jun-22-17 Jun-27-17, Release 30-CT
Jun-27-17 Jun-30-17, Release 31-CT
Jun-30-17 Jul-06-17, Release 32-CT
Jan-13-17, APM-2 Install
Jan-13-17, APM-2
Dec-09-16, Release 01-GW
Dec-08-16, Release 02-GW
Dec-09-16, Release 03-GW
Dec-08-16, Release 04-GW
Dec-08-16, Release 05
Dec-08-16, Release 06
Dec-15-16, Release 01-GW-CT
Dec-15-16 Dec-20-16, Release 02-GW-CT
Dec-21-16 Dec-28-16, Release 03-GW-CT
Dec-28-16 Jan-04-17, Release 04-GW-CT
Jan-04-17 Jan-10-17, Release 05-CT
Jan-10-17 Jan-13-17, Release 06-CT
Feb-15-17, APM-3 Install
Feb-15-17, APM-3
Dec-09-16, Release 01-GW
Jan-06-17 Jan-13-17, Release 01-GW-CT
Dec-08-16, Release 02-GW
Jan-16-17 Jan-19-17, Release 02-GW-CT
USF College of Business... WTG - Install Status - 9 Month (Good) Dec-05-16 14:37
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Milestone
Summary
Page 4 of 6 TASK filter: WTG - 9 Month CW Install Status (Good).
Resource Profile Filter:All Resources
Activity ID Project Start Finish
Release 03Release 03 Dec-09-16 Dec-13-16
Release 03-CTRelease 03-CT Jan-20-17 Jan-25-17
Release 04Release 04 Dec-16-16 Dec-20-16
Release 04-CTRelease 04-CT Jan-26-17 Jan-30-17
Release 05Release 05 Dec-23-16 Dec-28-16
Release 05-CTRelease 05-CT Feb-01-17 Feb-03-17
Release 06Release 06 Dec-27-16 Dec-29-16
Release 06-CTRelease 06-CT Feb-06-17 Feb-09-17
Release 07Release 07 Dec-30-16 Jan-05-17
Release 07-CTRelease 07-CT Feb-10-17 Feb-15-17
CONRAC InstallCONRAC Install Dec-05-16 Jan-27-17
CONRACCONRAC Dec-05-16 Jan-27-17
Release 01Release 01 Dec-05-16 Dec-07-16
Release 02Release 02 Dec-05-16 Dec-07-16
Release 03Release 03 Dec-05-16 Dec-07-16
Release 04Release 04 Dec-05-16 Dec-07-16
Release 05Release 05 Dec-05-16 Dec-06-16
Release 06Release 06 Dec-05-16 Dec-06-16
Release 07Release 07 Dec-05-16 Dec-06-16
Release 08Release 08 Dec-05-16 Dec-05-16
Release 09Release 09 Dec-05-16 Dec-12-16
Release 10Release 10 Dec-05-16 Dec-06-16
Release 11Release 11 Dec-05-16 Dec-06-16
Release 12Release 12 Dec-05-16 Dec-06-16
Release 13Release 13 Dec-05-16 Dec-06-16
Release 01-CTRelease 01-CT Dec-07-16 Dec-09-16
Release 02-CTRelease 02-CT Dec-13-16 Dec-15-16
Release 03-CTRelease 03-CT Dec-16-16 Dec-21-16
Release 04-CTRelease 04-CT Dec-22-16 Dec-26-16
Release 05-CTRelease 05-CT Dec-27-16 Dec-28-16
Release 06-CTRelease 06-CT Dec-30-16 Jan-02-17
Release 07-CTRelease 07-CT Jan-03-17 Jan-04-17
Release 08-CTRelease 08-CT Jan-05-17 Jan-06-17
Release 09-CTRelease 09-CT Jan-09-17 Jan-16-17
Release 10-CTRelease 10-CT Jan-17-17 Jan-18-17
Release 11-CTRelease 11-CT Jan-19-17 Jan-20-17
Release 12-CTRelease 12-CT Jan-23-17 Jan-25-17
Release 13-CTRelease 13-CT Jan-26-17 Jan-27-17
UF Jax InstallUF Jax Install Dec-05-16 Jun-19-17
UF Health - JacksonvilleUF Health - Jacksonville Dec-05-16 Jun-19-17
Release 01Release 01 Dec-05-16 Dec-07-16
Release 01-CTRelease 01-CT Dec-07-16 Dec-09-16
Release 02Release 02 Dec-05-16 Dec-09-16
Release 02-CTRelease 02-CT Dec-13-16 Dec-19-16
Release 03Release 03 Dec-05-16 Dec-06-16
Release 03-CTRelease 03-CT Dec-21-16 Dec-22-16
Release 04Release 04 Dec-05-16 Dec-07-16
Release 04-CTRelease 04-CT Dec-23-16 Dec-28-16
Release 05Release 05 Dec-05-16 Dec-07-16
Release 05-CTRelease 05-CT Dec-29-16 Jan-03-17
Release 06Release 06 Dec-05-16 Dec-08-16
Release 06-CTRelease 06-CT Jan-04-17 Jan-09-17
Release 07Release 07 Dec-05-16 Dec-07-16
Release 07-CTRelease 07-CT Jan-10-17 Jan-12-17
Release 08Release 08 Dec-05-16 Dec-05-16
Release 08-CTRelease 08-CT Jan-13-17 Jan-16-17
Release 09Release 09 Dec-05-16 Dec-06-16
Release 09-CTRelease 09-CT Jan-17-17 Jan-19-17
Release 10Release 10 Dec-05-16 Dec-09-16
Release 10-CTRelease 10-CT Jan-20-17 Jan-27-17
Release 11Release 11 Dec-05-16 Dec-08-16
Release 11-CTRelease 11-CT Jan-30-17 Feb-02-17
Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017
Dec-13-16, Release 03
Jan-20-17 Jan-25-17, Release 03-CT
Dec-16-16 Dec-20-16, Release 04
Jan-26-17 Jan-30-17, Release 04-CT
Dec-23-16 Dec-28-16, Release 05
Feb-01-17 Feb-03-17, Release 05-CT
Dec-27-16 Dec-29-16, Release 06
Feb-06-17 Feb-09-17, Release 06-CT
Dec-30-16 Jan-05-17, Release 07
Feb-10-17 Feb-15-17, Release 07-CT
Jan-27-17, CONRAC Install
Jan-27-17, CONRAC
Dec-07-16, Release 01
Dec-07-16, Release 02
Dec-07-16, Release 03
Dec-07-16, Release 04
Dec-06-16, Release 05
Dec-06-16, Release 06
Dec-06-16, Release 07
Dec-05-16, Release 08
Dec-12-16, Release 09
Dec-06-16, Release 10
Dec-06-16, Release 11
Dec-06-16, Release 12
Dec-06-16, Release 13
Dec-09-16, Release 01-CT
Dec-13-16 Dec-15-16, Release 02-CT
Dec-16-16 Dec-21-16, Release 03-CT
Dec-22-16 Dec-26-16, Release 04-CT
Dec-27-16 Dec-28-16, Release 05-CT
Dec-30-16 Jan-02-17, Release 06-CT
Jan-03-17 Jan-04-17, Release 07-CT
Jan-05-17 Jan-06-17, Release 08-CT
Jan-09-17 Jan-16-17, Release 09-CT
Jan-17-17 Jan-18-17, Release 10-CT
Jan-19-17 Jan-20-17, Release 11-CT
Jan-23-17 Jan-25-17, Release 12-CT
Jan-26-17 Jan-27-17, Release 13-CT
Jun-19-17, UF Jax Install
Jun-19-17, UF Health - Jacksonville
Dec-07-16, Release 01
Dec-09-16, Release 01-CT
Dec-09-16, Release 02
Dec-13-16 Dec-19-16, Release 02-CT
Dec-06-16, Release 03
Dec-21-16 Dec-22-16, Release 03-CT
Dec-07-16, Release 04
Dec-23-16 Dec-28-16, Release 04-CT
Dec-07-16, Release 05
Dec-29-16 Jan-03-17, Release 05-CT
Dec-08-16, Release 06
Jan-04-17 Jan-09-17, Release 06-CT
Dec-07-16, Release 07
Jan-10-17 Jan-12-17, Release 07-CT
Dec-05-16, Release 08
Jan-13-17 Jan-16-17, Release 08-CT
Dec-06-16, Release 09
Jan-17-17 Jan-19-17, Release 09-CT
Dec-09-16, Release 10
Jan-20-17 Jan-27-17, Release 10-CT
Dec-08-16, Release 11
Jan-30-17 Feb-02-17, Release 11-CT
USF College of Business... WTG - Install Status - 9 Month (Good) Dec-05-16 14:37
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Milestone
Summary
Page 5 of 6 TASK filter: WTG - 9 Month CW Install Status (Good).
Resource Profile Filter:All Resources
Activity ID Project Start Finish
Release 12Release 12 Dec-05-16 Dec-07-16
Release 12-CTRelease 12-CT Feb-06-17 Feb-08-17
Release 13Release 13 Dec-05-16 Dec-08-16
Release 13-CTRelease 13-CT Feb-09-17 Feb-14-17
Release 14Release 14 Dec-05-16 Dec-07-16
Release 14-CTRelease 14-CT Feb-15-17 Feb-17-17
Release 15Release 15 Dec-05-16 Dec-06-16
Release 15-CTRelease 15-CT Feb-21-17 Feb-22-17
Release 16Release 16 Dec-05-16 Dec-05-16
Release 16-CTRelease 16-CT Feb-23-17 Feb-24-17
Release 17Release 17 Dec-05-16 Dec-07-16
Release 17-CTRelease 17-CT Feb-27-17 Mar-01-17
Release 18Release 18 Dec-05-16 Dec-09-16
Release 18-CTRelease 18-CT Mar-03-17 Mar-09-17
Release 19Release 19 Dec-05-16 Dec-07-16
Release 19-CTRelease 19-CT Mar-13-17 Mar-15-17
Release 20Release 20 Dec-05-16 Dec-07-16
Release 20-CTRelease 20-CT Mar-17-17 Mar-21-17
Release 21Release 21 Dec-05-16 Dec-08-16
Release 21-CTRelease 21-CT Mar-22-17 Mar-27-17
Release 22Release 22 Dec-05-16 Dec-07-16
Release 22-CTRelease 22-CT Mar-28-17 Mar-30-17
Release 23Release 23 Dec-05-16 Dec-06-16
Release 23-CTRelease 23-CT Apr-03-17 Apr-04-17
Release 24Release 24 Dec-05-16 Dec-08-16
Release 24-CTRelease 24-CT Apr-05-17 Apr-10-17
Release 25Release 25 Dec-05-16 Dec-09-16
Release 25-CTRelease 25-CT Apr-11-17 Apr-18-17
Release 26Release 26 Dec-05-16 Dec-07-16
Release 26-CTRelease 26-CT Apr-19-17 Apr-21-17
Release 27Release 27 Dec-05-16 Dec-07-16
Release 27-CTRelease 27-CT Apr-25-17 Apr-27-17
Release 28Release 28 Dec-05-16 Dec-06-16
Release 28-CTRelease 28-CT Apr-28-17 May-01-17
Release 29Release 29 Dec-05-16 Dec-09-16
Release 29-CTRelease 29-CT May-03-17 May-09-17
Release 30Release 30 Dec-05-16 Dec-07-16
Release 30-CTRelease 30-CT May-10-17 May-15-17
Release 31Release 31 Dec-05-16 Dec-06-16
Release 31-CTRelease 31-CT May-16-17 May-18-17
Release 32Release 32 Dec-05-16 Dec-05-16
Release 32-CTRelease 32-CT May-19-17 May-22-17
Release 33Release 33 Dec-05-16 Dec-08-16
Release 33-CTRelease 33-CT May-23-17 May-26-17
Release 34Release 34 Dec-05-16 Dec-08-16
Release 34-CTRelease 34-CT May-29-17 Jun-02-17
Release 35Release 35 Dec-05-16 Dec-07-16
Release 35-CTRelease 35-CT Jun-05-17 Jun-07-17
Release 36Release 36 Dec-05-16 Dec-06-16
Release 36-CTRelease 36-CT Jun-08-17 Jun-12-17
Release 37Release 37 Dec-05-16 Dec-06-16
Release 37-CTRelease 37-CT Jun-13-17 Jun-14-17
Release 38Release 38 Dec-05-16 Dec-06-16
Release 38-CTRelease 38-CT Jun-15-17 Jun-19-17
Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017
Dec-07-16, Release 12
Feb-06-17 Feb-08-17, Release 12-CT
Dec-08-16, Release 13
Feb-09-17 Feb-14-17, Release 13-CT
Dec-07-16, Release 14
Feb-15-17 Feb-17-17, Release 14-CT
Dec-06-16, Release 15
Feb-21-17 Feb-22-17, Release 15-CT
Dec-05-16, Release 16
Feb-23-17 Feb-24-17, Release 16-CT
Dec-07-16, Release 17
Feb-27-17 Mar-01-17, Release 17-CT
Dec-09-16, Release 18
Mar-03-17 Mar-09-17, Release 18-CT
Dec-07-16, Release 19
Mar-13-17 Mar-15-17, Release 19-CT
Dec-07-16, Release 20
Mar-17-17 Mar-21-17, Release 20-CT
Dec-08-16, Release 21
Mar-22-17 Mar-27-17, Release 21-CT
Dec-07-16, Release 22
Mar-28-17 Mar-30-17, Release 22-CT
Dec-06-16, Release 23
Apr-03-17 Apr-04-17, Release 23-CT
Dec-08-16, Release 24
Apr-05-17 Apr-10-17, Release 24-CT
Dec-09-16, Release 25
Apr-11-17 Apr-18-17, Release 25-CT
Dec-07-16, Release 26
Apr-19-17 Apr-21-17, Release 26-CT
Dec-07-16, Release 27
Apr-25-17 Apr-27-17, Release 27-CT
Dec-06-16, Release 28
Apr-28-17 May-01-17, Release 28-CT
Dec-09-16, Release 29
May-03-17 May-09-17, Release 29-CT
Dec-07-16, Release 30
May-10-17 May-15-17, Release 30-CT
Dec-06-16, Release 31
May-16-17 May-18-17, Release 31-CT
Dec-05-16, Release 32
May-19-17 May-22-17, Release 32-CT
Dec-08-16, Release 33
May-23-17 May-26-17, Release 33-CT
Dec-08-16, Release 34
May-29-17 Jun-02-17, Release 34-CT
Dec-07-16, Release 35
Jun-05-17 Jun-07-17, Release 35-CT
Dec-06-16, Release 36
Jun-08-17 Jun-12-17, Release 36-CT
Dec-06-16, Release 37
Jun-13-17 Jun-14-17, Release 37-CT
Dec-06-16, Release 38
Jun-15-17 Jun-19-17, Release 38-CT
Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017
0h
50h
100h
150h
200h
250h
Actual Units
Remaining Early Units
Overallocated Early Units
Limit
USF College of Business... WTG - Install Status - 9 Month (Good) Dec-05-16 14:37
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Milestone
Summary
Page 6 of 6 TASK filter: WTG - 9 Month CW Install Status (Good).
Resource Profile Filter:All Resources