P4 محاضرات هندسة الاساسات د. طارق نجيب

82
January 15, 2022 Deep Foundations 1 DEEP FOUNDATIONS DEEP FOUNDATIONS 4 th Year Civil FOUNDATION ENGINEERING FOUNDATION ENGINEERING

description

محاضرات هندسة الاساسات د. طارق نجيب الجزء الرابع

Transcript of P4 محاضرات هندسة الاساسات د. طارق نجيب

Page 1: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 1

DEEP FOUNDATIONSDEEP FOUNDATIONS

4th Year Civil

FOUNDATION ENGINEERINGFOUNDATION ENGINEERING

Page 2: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 2

DEEP FOUNDATIONSDEEP FOUNDATIONS

TYPES OF DEEP FOUNDATIONS:

1- PILES الخوازيق

2- CAISSONS القيسوناتبالتغويصوالحفر تنفذ خلوية أساسات

3- PIERS الدعائمذات قواعد أو كبير ذاتقطر خوازيق وهى الكبارى أساسات

يجففداخلها كبير حجم

االسكندرانى -4 اآلبار

Page 3: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 3

PILE FOUNDATIONSPILE FOUNDATIONS

Piles are stiff members used to transmit surface loads to the bearing strata.

Piles are classified to two categories according to the method of load transfer:

1- End bearing piles: ارتكاز خوازيقTip point carries most of the load.

. الخازوق حمل معظم تنقل االرتكاز نقطة2- Friction Piles: احتكاك خوازيق

Side friction carries most of the load.

عن للتربة ينتقل الخازوق حمل معظمالسطحى االحتكاك طريق

Page 4: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 4

Pile ApplicationsPile Applications

LowLowWeightWeight

Soft toSoft toFirm ClayFirm Clay

Large DistributedLarge DistributedWeightWeight

Very Large ConcentratedVery Large ConcentratedWeightWeight

Dense Sand

Strong RockStrong Rock

Page 5: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 5

Piles are used in:Piles are used in:1- Upper soil is weak,

compressible, or could not support the surface loads.

2- The loads are tension, horizontal, or inclined.

3- Problematic soils;

Swelling soils giving tension on the pile.

Collapsing soils, adding down-drag forces on the pile.

4- Scour under bridge piers.

5- Temporary or Permanent Excavation Side Support

Page 6: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 6

Types of Pile Materials

ConcreteConcreteTimberTimber Steel HSteel H CompositeCompositePre-cast ConcretePre-cast Concrete

Steel Concrete

Steel PipeSteel Pipe

Timber

Page 7: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 7

Timber PilesTimber Piles

- Relatively inexpensive

- Usually limited to short lengths [though Douglas Fir does come in longer lengths (higher expense)]

- Low capacity.

- Advantages: Easy handling, Non-corrosive material, If permanently submerged then fairly resistant to decay.

- Disadvantages: May require treatment to prevent decay, insects, and borers from damaging pile. Easily damaged during hard driving and inconvenient to splice.

Page 8: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 8

Steel H-PilesSteel H-Piles

- Advantages: high axial working capacity. Wide variety of sizes. Easy on-site modifications. Fairly easy to drive, minimal soil displacement, good penetration through hard materials (with shoe).

- Disadvantages: high cost, potential delays in delivery, relatively higher corrosion, noisy driving, low bearing and friction areas.

Page 9: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 9

Steel Pipe Piles

May drive closed or open-ended.

Advantages: May be driven empty then filled with cheaper material (concrete). Can provide very high capacities. On-site modifications easy.

Disadvantages: similar to H-piles with additional item–more difficult driving due to soil displacement.

Page 10: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 10

Precast Concrete Piles

- May be prestressed to withstand driving and handling stresses.

- Advantages: High capacity. Usually durable and corrosion resistant in many environments (not marine).

- Disadvantages: Handling, splicing, and cutting more of a problem. Transportation difficulties.

Page 11: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 11

- Piles are bored using drilling rig of internal diameter allowing for casting the concrete till the required depth.

- Casting of concrete starts with withdrawing the drilling rig upwards.

- Capacity of about 100 ton- Advantages: ease of changing lengths by

cutting or slicing the shell. Material costs relatively low. Inspection possible.

- Disadvantage: not feasible in hard soils or rock. Voids in concrete may be created. Splicing problems after concreting.

Continuous Flight Auger (CFA)

Page 12: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 12

- Holes are drilled in the soil then filled with bentonite slurry to support the sides.

- Steel reinforcements are then lowered to the required level.

- Concrete casting is performed from bottom to top with pumps.

- Bentonite slurry is then replaced by the concrete and the slurry is desanded for reuse.

Cast-in-place Concrete Piles

Page 13: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 13

Choice of Pile TypeThe pile type is chosen according to:

- Load Capacity & Pile Spacing

- Constructability

- Soil stratigraphy

- Need for splicing or cutting

- Driving vibrations

- Driving speed.

- Performance

- Environmental suitability (corrosion)

- Availability

- Cost

Page 14: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 14

Pile Load Transfer Mechanism

- Fairly complicated, though understandable.

. منتظم- غير وغالبا= معقد الحمل توزيع- Changes with changes in load because friction along

shaft is fully mobilized when pile has displaced only 5-10 mm whereas maximum point resistance is not fully mobilized until a movement of 10% of the pile diameter (or width) for driven piles or even higher in bored piles.

يتحقق- السطحى االحتكاك األقصىفى الحمل) 10-5عند ( نقطة عند األقصى الحمل ويصل مم

حدود فى أو% 10االرتكاز الخازوق قطر منعرضه.

Page 15: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 15

Mobilization of Base and Shaft Resistance

Mobilization of Base and Shaft Resistance

Shaft

2 - 5mm

Base

10 - 20% diam

Total

Displacement

Load

Shaft ??

Page 16: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 16

Pile Failure SurfacePile Failure Surface

Df

Ground Surface

Arching Action

B

DfPO = Df

Zone of Shear & Volume Decrease

Pult

Failure Surface Along the Shaft

Page 17: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 17

End Bearing PilesEnd Bearing Piles

Page 18: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 18

End bearing piles:End bearing piles:Transmit most of their Transmit most of their loads to the load bearing loads to the load bearing layer (dense sand or layer (dense sand or rock). Most of the pile rock). Most of the pile capacity inferred from capacity inferred from the end bearing point.the end bearing point.

من األكبر الجزء من ينقل األكبر الجزء ينقلطريق عن طريق الحمل عن الحمل

وهى االرتكاز وهى نقطة االرتكاز نقطةترتكز التى ترتكز الخوازيق التى الخوازيق

أو الكثيف الرمل أو على الكثيف الرمل علىالصخر.الصخر.

Pbase

Side Friction

End Bearing

Pile Load, P

Page 19: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 19

Friction Piles:Friction Piles:

Page 20: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 20

Friction Piles:Friction Piles: Transmit most of their Transmit most of their load through the layers load through the layers through which the piles through which the piles pass, i.e., mostly through pass, i.e., mostly through the surface friction with the surface friction with the surrounding soilsthe surrounding soils..

عن الحمل معظم عن ينقل الحمل معظم ينقلاالحتكاك االحتكاك طريق طريق

مثل مثل السطحى السطحىفى المنفذة فى الخوازيق المنفذة الخوازيق. الصرفة الطينية .التربة الصرفة الطينية التربة Pbase

End Bearing

Pile Load, P

Side Friction

Page 21: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 21

Individual Pile Capacity

Methods of Estimating Pile Load Capacity:Methods of Estimating Pile Load Capacity:1- Static Analysis from the Shear Strength Parameters1- Static Analysis from the Shear Strength Parameters

خواصالقصفى- 11 من الخوازيق تحمل قدرة خواصالقصفى- تحديد من الخوازيق تحمل قدرة تحديدالتربة.التربة.

2- Dynamic Driving Formula2- Dynamic Driving Formula

دق- 22 صيغة من الخوازيق تحمل قدرة دق- تحديد صيغة من الخوازيق تحمل قدرة تحديد. المستخدمة .الخوازيق المستخدمة الخوازيق

3- Pile Load Test3- Pile Load Test

تحميل- 33 اختبارات من الخوازيق تحمل قدرة تحميل- تحديد اختبارات من الخوازيق تحمل قدرة تحديدالخوازيق.الخوازيق.

4- Field Tests: SPT, CPT, etc.4- Field Tests: SPT, CPT, etc.

االختبارات- 44 من الخوازيق تحمل قدرة االختبارات- تحديد من الخوازيق تحمل قدرة تحديدالحقلية.الحقلية.

Page 22: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 22

PILE CAPACITYPILE CAPACITY1- Bearing capacity of piles from soil parameters:1- Bearing capacity of piles from soil parameters:

Static Formula Method (QStatic Formula Method (Quu = Q = Qbb + Q + Qss))

Embedded Length = D

Qu = Ultimate Bearing Capacity

Qs = fAs

f = Unit Frictional Resistance

AS = Shaft Area (Pile surface area)

qb = Unit Bearing Capacity

Ab = Area of Pile Base

Qb = qbAb

Page 23: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 23

Base ResistanceBase Resistance

Qb = Ab [cbNc ] for Clay

Qb

Qb = Ab [P'ob Nq] for Sand

Ab = Area of Pile BaseNc = 9 for Piles in ClayNq = Given in Tables

Page 24: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 24

Shaft ResistanceShaft Resistance

Due to cohesion or friction or both

In cohesive soils : Qsc = As . ca

In friction soils: Qsf = As .KHC P'ob tan

P'ob

KHC.P'ob

As

As = Pile Surface Area

Page 25: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 25

Total Pile ResistanceTotal Pile Resistance

Qu = Qb + Qs

Qu = Ab [cb Nc] + As [ca ] For Piles in Clay

Qu = Ab [P'ob Nq] + As [KHC P'ob tan ] for Piles in Sand

Page 26: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 26

Qu = Ab [ P'ob Nq ] + As [ KHC P'ob tan ]

Qu = Ab P'ob Nq + As KHc P'ob tan

Piles in SandPiles in Sand

= 20o for Steel = ¾ for Concrete = ¾ for Timber

Page 27: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 27

Qu = As [KHT P'ob tan ] + W

Tension Piles in SandTension Piles in Sand

W = Pile Weight

Pile Type KHC KHT

H-Section Pile 0.5 – 1.0 0.3 – 0.5 Displacement Pile 1.0 – 1.5 0.6 – 1.0 Displacement Pile, Variable Section 1.5 – 2.0 1.0 – 1.3 Displacement Pile, with Water Jetting 0.4 – 0.9 0.3 – 0.6 Bored Pile (D < 60 cm) 0.7 – 1.5 0.4 – 1.0

Table (1): Values of KHC and KHT from the Egyptian Code

Page 28: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 28

Piles in ClayPiles in Clay

Qu = Ab cbNc + As ca

Qu = Ab [cbNc] + As [ca]

Page 29: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 29

Tension Piles in ClayTension Piles in ClayQu = As [ca] + W W = Pile Weight

Pile Material

Soil Consistency

Cohesion, c (kN/m2)

Adhesion, ca (kN/m2)

Very Soft 0.0 – 12.50 0.0 – 12.50 Soft 12.50 – 25.0 12.50 – 24.0 Medium Sitff 25.0 – 50.0 24.0 – 37.50 Stiff 50.0 – 100.0 37.50 – 47.50

Timber or

Concrete

Very Stiff 100.0 – 200.0 47.50 – 65.0

Very Soft 0.0 – 12.50 0.0 – 12.50 Soft 12.50 – 25.0 12.50 – 23.0 Medium Sitff 25.0 – 50.0 23.0 – 35.0 Stiff 50.0 – 100.0 35.0 – 36.0

Steel

Very Stiff 100.0 – 200.0 36.0 – 37.50

Table (2): Adhesion on Piles in Saturated Clay (Egyptian Code)

Page 30: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 30

Overburden Stress P'obOverburden Stress P'ob

Qu = [Ab P'ob Nq] + [AsKHC P'ob tan ]

Meyerhof Method : P'ob = 'z

Vesic Method : critical depth, zc

for z < zc : P'ob = 'zfor z > zc : P'ob = 'zc

zc/d is a function of after installation Suggested value = 20 d

Page 31: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 31

Max Limit on End Bearing?

Some suggest a limit on end bearing to match experience.

Problems with that approach:more complex than that; need to

consider both strength and compressibility of the soil

friction angle varies with effective stress

Over-consolidation causes changes in bearing capacity

Page 32: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 32

Nq from the Egyptian Code

o 25 30 35 40 Nq 15 30 75 150

Table (3): Nq Values Vs for Sand, Egyptian Code.

for Displacement Pile = ( (before construction) + 40o)/2

for Bored Pile = (before construction) – 3o

Nc for ClayNc = 9.0 for calculating the end bearing resistance of piles in clay.

Page 33: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 33

EXAMPLE

Determine the allowable capacity for the concrete bored pile shown in Figure.Pile Diameter D = 0.50 mPile Length L = 14.0 m

Medium stiff clay:C = 30 kN/m2

Ca = 25 kN/m2

sat = 18 kN/m3

Dense Sand: = 40o sat = 19 kN/m3

Nq = 150, KHC = 1.0

12.00 m

2.00 m

Page 34: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations

SOLUTIONSide Friction:Side Friction:Qs = As [ca + KHC P'ob tan ]qs in clay:qs-c = ca = 25 kN/m2

Qs-clay = ca [DLc]= 25 [*0.50*12.0]= 25 *18.85 = 471.25 kN

qs in sand:qs-s = KHC P'ob tanCritical depth Zc= 20 * 0.50 = 10.00 mP'ob = 8 * 10 = 80 kN/m2

Lc = 12.0 m

Ls =2.0 m

P'bo distribution

10.0 m10.0 m

Page 35: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 35

SOLUTION = 3/4 = 30o

Qs-s = 1.0 * 80 * 0.578 = 46.24 kN/m2

Qs-s = qs [DLs]= 46.24 [*0.50*2.0] = 145.27 kN

Total side friction:Qs = Qs-c + Qs-s = 471.25 + 145.27 = 616.52 kNEnd Bearing Resistance:qb = P'ob Nq = 80 * 150 = 12000 kN/m2

Qb = qb * Ab = qb * D2 = 12000 * 0.196= 2356.2 kN

Ultimate Pile Capacity = 616.52 + 2356.2 = 2973 kN

Page 36: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 36

SOLUTIONUltimate Pile Capacity Qult = 2973 kNAllowable Pile CapacityQall = Qult/F.S.Qall = 2973/3.0 = 991 kN

= 99.10 ton

Check of Concrete Capacity:Pc = fc (Ac + 1.14 * n * As)

= 5000 (0.196 + 1.14 * 10 * 0.00196)= 5000 * (0.218) = 1090 kN= 109 ton > 99.10 (Qall-soil) (O.K.)

Page 37: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 37

Pile DrivingPile Driving

Page 38: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 38

Closed End Diesel Hammer

Page 39: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 39

The Fundamental Pile Driving FormulaThe Fundamental Pile Driving Formula

shW

R

s R hW

ResistanceSoilofWorkEnergyHammer

RR

WW

SS

hh

Page 40: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 40

Single ActingSingle Acting Double ActingDouble Acting

Page 41: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 41

Diesel HammerDiesel Hammer Vibratory HammerVibratory Hammer

Page 42: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 42

Where:Where:QQallall = Allowable pile capacity, (kN); = Allowable pile capacity, (kN);

WWrr = Weight of hammer, kN;= Weight of hammer, kN;

HH = Height of hammer fall, m;= Height of hammer fall, m;SS = Amount of pile penetration/blow, (mm);= Amount of pile penetration/blow, (mm);CC = Constant = 25 for drop hammer= Constant = 25 for drop hammer

= 2.50 for steam hammer.= 2.50 for steam hammer.

Engineering News Formula (F.S. = 6):Engineering News Formula (F.S. = 6):

PILE CAPACITY2- From Pile Driving Formula

C S 6H. W1000

Q rall

Page 43: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 43

Determine the allowable pile capacity for a pile of Determine the allowable pile capacity for a pile of diameter D = 0.30 m, driven by a steam hammer, diameter D = 0.30 m, driven by a steam hammer, knowing that:knowing that:Average penetration per blow = 17 mmAverage penetration per blow = 17 mmHammer rating Wr.H = 40 kNHammer rating Wr.H = 40 kN

Example:Example:

PILE CAPACITY2- From Pile Driving Formula

ton34.2 kN 341.9

2.50 17 640 * 1000

Qall

Solution:Solution:

Page 44: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 44

PILE CAPACITY3- Static Pile Load – Test Setup

Reaction Beam

Stiffeners

PlateLoad Cell

Spherical Bearing

Ram

Hydraulic JackBourdon Gage

Dial GageLVDT

Mirror

Scale

Test Pile

Grade

Bracket Attached to PileWire

Page 45: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 45

Typical Arrangement for Load Testing a Pile or Drilled Shaft

Reaction BeamReaction Beam

JackJackDial

GageDial

Gage

Test Pile or Drilled ShaftTest Pile or

Drilled Shaft

Support Beam

Support Beam

Anchor Pile or Drilled ShaftAnchor Pile or Drilled Shaft

Page 46: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 46

Pile Static Load – Test Setup

Page 47: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 47

Pile Static Load – Test Setup

Page 48: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 48

Pile Capacity from Static Pile Load Test

Loading is performed up to a test load of 150% (or 200%) of the pile design load, with steps of 25% of the design load. The ultimate capacity is determined by many methods, for example, the Modified Chen Method.

يساوى اختبار حمل عند الخازوق اختبار 150يتمعلى%) 200أو% ( وذلك التصميمى الحمل من

خطوة كل مقدار الحمل% 25خطوات منتحمل. قدرة أقصى تحديد ويتم التصميمى

طريقة باستخدام .Chenللخازوق المعدلة

Page 49: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 49

Pile Capacity from Static Pile Load Test, Load-Settlement Curve

Page 50: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 50

Pile Capacity from Static Pile Load Test, Modified Chen Method

x = 6.801

b

y = 3.70

Page 51: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 51

Pile Capacity from Static Pile Load Test, Modified Chen Method

Ultimate Pile Capacity from Static Pile Load Test, Using Modified Chen Method:The loading curve is drawn as follows:Horizontal axis = measured settlement ();Vertical axis = measured settlement () /load (P).

b 1.21

Qult Where:Qult = Ultimate pile capacity, (kN);1.2 = Safety factorb = Slope of the /Load Vs. curve.

Page 52: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 52

Pile Capacity from Pile Load TestThree conditions should be satisfied from the pile load test:I- QI- Qultult ≥ 2.00 Q ≥ 2.00 Qallall (D.L. + L.L.) (D.L. + L.L.)

Dead + Live LoadsQult ≥ 1.75 Qall (D.L. + L.L. + W.L.)

Dead + Live + Wind LoadsQult ≥ 1.50 Qall (D.L. + L.L. + W.L.+Eq.L.)

Dead + Live + Wind + Earthquake Loads

1.50 Qat Settlement

Q 1.25at Settlement

all

all

II- Measured II- Measured at 1.25 test load ≤ 1.50 at 1.25 test load ≤ 1.50 at Q at Qallall

Page 53: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 53

Pile Capacity from Pile Load Test

A EL P

* 0.50 D 0.02 max

III- Measured III- Measured ≤ ≤ maxmax

Where:Where:maxmax = maximum pile settlement, (m); = maximum pile settlement, (m);

DD = Pile diameter, (m);= Pile diameter, (m);PP = Pile test load, (ton);= Pile test load, (ton);LL = Pile length, (m);= Pile length, (m);EE = Modulus of elasticity of concrete, (t/m= Modulus of elasticity of concrete, (t/m22))AA = Pile cross-section area.= Pile cross-section area.

Page 54: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 54

Pile Capacity from Pile Load Test

Settlement (mm) Date

Load (kN)

S1 S2 S3 S4

Avg. Sett. (mm)

Loading 9/9/04 0.0 0.00 0.00 0.00 0.00 0.00

250.0 0.59 0.66 0.56 0.58 0.60 500.0 0.88 1.00 0.89 0.93 0.93 750.0 1.85 1.98 1.86 1.92 1.90 1000.0 3.12 3.28 3.20 3.26 3.21 1250.0 4.16 4.34 4.27 4.37 4.29 1500.0 10.11 10.46 10.21 10.41 10.30

Unloading 10/9/04 1250.0 10.11 10.46 10.41 10.21 10.30

1000.0 10.01 10.29 10.07 10.27 10.16 750.0 9.70 9.97 9.80 9.99 9.87 500.0 9.20 9.45 9.35 9.03 9.26 250.0 8.53 8.78 8.79 9.97 8.77 0.0 6.65 6.82 6.83 6.84 6.79

Example:Determine the ultimate pile capacity for a pile of diameter D = 0.60 m, and Length L = 10.50 m, with the test results shown in the table, knowing that the design load is 1000 kN, test load = 1500 kN.

Page 55: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 55

Pile Capacity from Pile Load Test Solution:

I- QI- Qultult 1532 > 1.50 Q 1532 > 1.50 Qallall (1500 kN) (1500 kN)

kN 1532 3.70 * 20.11000 * 6.80

b 1.2

1 Qult

QQultult using modified Chen Method: using modified Chen Method:

1.50 1.34 3.214.29

Qat Settlement

Q 1.25at Settlement

all

all

II- Measured II- Measured at 1.25 test load ≤ 1.5 at 1.25 test load ≤ 1.5 at Q at Qallall

Page 56: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 56

Pile Capacity from Pile Load Test

A EL P

* 0.50 D 0.02 max

III- III- maxmax ≤ ≤ at maximum test load: at maximum test load:

0.283 *10*140

10.50 * 150 * 0.50 0.60 * 0.02

4max

maxmax = 0.012 + 0.002 = 0.014 m = 14 mm = 0.012 + 0.002 = 0.014 m = 14 mm

at test load = 10.30 mm < 14.0 mm (at test load = 10.30 mm < 14.0 mm (maxmax) O.K.) O.K.

E = 140 t/cmE = 140 t/cm22 = 140 * 10 = 140 * 1044 t/m t/m22

Page 57: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 57

PILE CAPACITY4- In-Situ Soil Test Methods

The pile capacity can be determined from The pile capacity can be determined from the field tests as follows:the field tests as follows:

1- Standard Penetration Test (SPT).1- Standard Penetration Test (SPT).

2- Cone Penetration Test (CPT).2- Cone Penetration Test (CPT).

Page 58: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 58

Pile Capacity from SPTQallall = 90 N ( R2) + N' (2 RL), (kN)

Qallall = Pile working load, F.S. = 2.5 for end bearing and 2.0 for side friction.

N = Average SPT, 2R below tip and 6R above tip,

N ≤ 50 (Preferably ≤ 30).

N' = Average SPT in sand layers, along the pile shaft.

R = Pile radius, (m).

L = Pile length within the sand layers, (m).For bored piles, Qallall = 50 up to 100% of that values according

to the pile type and construction method.

Page 59: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 59

Pile Capacity from SPTExample:Determine the

allowable pile capacity for a bored pile constructed in the soil log shown in the table. Knowing that the pile diameter is 50 cm, and the pile length is 9.0 m.

D SPT

1 8

2 11

3 14

4 23

5 28

6 31

7 33

8 36

9 41

10 53

11 55

Clay

Sand

Page 60: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 60

Pile Capacity from SPTD SPT

1 8

2 11

3 14

4 23

5 28

6 31

7 33

8 36

9 41

10 53

11 55

Clay

Sand

Solution:

Qallall = 90 N ( R2) + N' (2 RL), (kN)

N = (N8+N9+N10)/3

= (36+41+50)/3 = 42

N' = (N4+N5+N6+N7+N8+N9)/6

= (23+28+31+33+36+41)/6 = 32

Qall = 90 N ( R2) + N' (2 RL), (kN)

= 90*42*0.196+32*(2**0.25*6)

= 740.9+301.6 = 1042.5 = 104 ton

Page 61: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 61

CPT Correlations

The CPT is very similar to driving piles therefore this test is a good predictor of capacity.

Pile capacity is determined from correlations based on CPT, as presented in the Egyptian Code.

Page 62: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 62

Pile Capacity from CPT

Qallall = 1/3 qc ( R2) + ½ fc (2 RL), (kN)Qallall = Pile working load, F.S. = 3.0 for end bearing and 2.0 for

side friction.

qc = Average CPT tip resistance, 6R below tip and 12R

above tip, qc not exceeding 150 kg/cm2.

= Factor relating the pile diameter to the cone diameter,

assumed = 0.70.

fc = Average CPT side friction along the pile, not exceeding

1.0 kg/cm2.

R = Pile radius, (m).

For bored piles, Qallall = 50 up to 100% of that values according to the pile type and construction method.

Page 63: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 63

Pile Groups

Piles are usually arranged in groups under the columns.

The number of piles in a group is determined as follows:

all

c

Q1.10 * P

N

Where:N = No. of piles;Pc = Column Load;Qall = Allowable load of

a single pile.

Page 64: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 64

Arrangement of Pile GroupsThe spacing between piles in a group can be assumed based on the following:1- Driven piles need higher spacing than bored piles.2- Friction piles need higher spacing than end bearing piles.3- Minimum spacing (S) between piles is 2.5.4- Maximum spacing (S) between piles is 8.0.

Page 65: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 65

S

2 Piles

S

3 Piles S

4 Piles

S

S5 Piles

S S6 Piles

S S

S7 Piles

Page 66: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 66

S S

S

8 Piles

SS

S S9 Piles

Page 67: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 67

Negative Skin Friction Q

L1

Granular Fill

L2

Fc

Fg

Soft Clay

Rock

Original Ground Surface

Downdrag force occurs when the Downdrag force occurs when the soil surrounding the pile settles soil surrounding the pile settles more than the pile itself.more than the pile itself.

Occurred in the following Occurred in the following conditions:conditions:1- Recent fill over very soft soil.1- Recent fill over very soft soil.2- Soils undergoing consolidations.2- Soils undergoing consolidations.3- Lowering of ground water table 3- Lowering of ground water table may cause subsidence and may cause subsidence and consequently –ve skin friction.consequently –ve skin friction.

Page 68: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 68

Negative Skin Friction

Negative Skin Friction is calculated as follows:: كالتالى والخوازيق التربة بين السلبى االحتكاك حساب يتم

-ve skin friction = Weight of soil bounded within the soft layers;+ Pile group surface area of the soft layers * pile-soil

adhesion (Ca)بمجموعة = خارجيا= المحاطة التربة وزن السلبى االحتكاك

الخوازيق +المالصقة الخوازيق لمجموعة السطحية المساحة

الضعيفة للطبقاتبها * المحيطة والتربة الخوازيق بين االلتصاق معامل

The negative skin friction per pile should not exceed the pile skin friction value.

قدرة الواحد للخازوق السلبى االحتكاك يتعدى ال بحيث. الخازوق لذلك السطحى االحتكاك

Page 69: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 69

n m 90n 1) - (m + m 1)-(n

- 1 = Ge

Where:Ge = Group efficiency; = tan-1 (D/S) in degrees;D = Pile diameter (m);S = Pile spacing (m);n = Number of piles in a row;m = Number of pile rows

Efficiency of Pile GroupsEfficiency of Pile Groups

Page 70: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 70

Determine the number, arrangement, and group efficiency of a pile group to support a column load of 520 ton, knowing that the pile capacity is 110 ton, the pile diameter is 60 cm.

ExampleExample

S S6 Piles

Solution:Solution:No. of Piles = (520 * 1.10)/110

= 5.20 take 6 pilesAssume that the pile spacing S = 4 D = 2.40 m = tan-1(D/S ) = tan-1(0.25)

=14.04o

Page 71: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 71

0.818 0.182 - 1

2 * 3 * 90

3 1) - (2 + 2 1)- (3 14.04 - 1 = Ge

n = 3 الواحد الصف فى الخوازيق عددm = 2 الخوازيق صفوف عدد

ExampleExample

S S6 Piles

Pile group capacity:Qg = N * Qall * Ge

Qg = 6 * 110 * 0.818 = 539.88 ton≈ 540 < 570, considered O.K.

Page 72: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 72

Pile Groups Under Eccentric Loads

Page 73: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 73

ex

ey

H

V R

Pile groups under eccentric loads

Page 74: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 74

2y

2x

vy

y .V.e

x

.xV.e

nV

P

Where:

V = Total vertical force on the group

ex = Eccentricity in the x-direction

ey = Eccentricity in the y-direction

Page 75: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 75

Settlement of Pile Groups in Sand (After Skempton)

FoundationFoundation

Zone of Settlement

Zone of Settlement

Ground Prestressed by Pile Driving

Ground Prestressed by Pile Driving

Single Pile Load TestSingle Pile Load Test

Page 76: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 76

Settlement for End Bearing Pile GroupsSettlement for End Bearing Pile Groups

Soft Clay

Sand

Soft Clay

1H:2V H1

Hc

nQa

L

BAnQa

A, B = Pile Group Dimensions

Page 77: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 77

Settlement of Friction Pile GroupsSettlement of Friction Pile Groups

nQa

ABnQa

*H

1H:2V

L 32

L

B, A = Pile Group Dimensions

Page 78: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 78

Pile Group Settlement AnalysisPile Group Settlement Analysis

Where:H = Settlement H = Layer thickness Cc = Compression Index eo = Initial voids ratio PO = Overburden Pressure at the middle of the

consolidating layer. P = Change in Pressure at the middle of the

consolidating layer

o

o

o

cc P

ΔPPLog

e1C

HΔH

Page 79: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 79

Structural Design of the Pile Cap

Page 80: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 80

Failure Modes in the Pile Cap

1- Punching, column or pile.

2- Flexural, due to high tensile stresses.

Design of the Pile CapDesign of the Pile Cap

Page 81: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 81

Failure by Punching

Failure due to high tensile

stressesMinimum thickness of the pile cap = Minimum thickness of the pile cap = 80 cm to assure even distribution of 80 cm to assure even distribution of settlements over the piles, or 2.25 pile settlements over the piles, or 2.25 pile diameter D.diameter D.

Page 82: P4 محاضرات هندسة الاساسات  د. طارق نجيب

April 13, 2023 Deep Foundations 82

The concrete section and area steel are determined The concrete section and area steel are determined from the max. moment, then check of shear and from the max. moment, then check of shear and punching is performed.punching is performed.

1:1 1:1d/2 d

Critical Sec. for Shear

Critical Sec. for Moment

d/2 d