P4 محاضرات هندسة الاساسات د. طارق نجيب
description
Transcript of P4 محاضرات هندسة الاساسات د. طارق نجيب
April 13, 2023 Deep Foundations 1
DEEP FOUNDATIONSDEEP FOUNDATIONS
4th Year Civil
FOUNDATION ENGINEERINGFOUNDATION ENGINEERING
April 13, 2023 Deep Foundations 2
DEEP FOUNDATIONSDEEP FOUNDATIONS
TYPES OF DEEP FOUNDATIONS:
1- PILES الخوازيق
2- CAISSONS القيسوناتبالتغويصوالحفر تنفذ خلوية أساسات
3- PIERS الدعائمذات قواعد أو كبير ذاتقطر خوازيق وهى الكبارى أساسات
يجففداخلها كبير حجم
االسكندرانى -4 اآلبار
April 13, 2023 Deep Foundations 3
PILE FOUNDATIONSPILE FOUNDATIONS
Piles are stiff members used to transmit surface loads to the bearing strata.
Piles are classified to two categories according to the method of load transfer:
1- End bearing piles: ارتكاز خوازيقTip point carries most of the load.
. الخازوق حمل معظم تنقل االرتكاز نقطة2- Friction Piles: احتكاك خوازيق
Side friction carries most of the load.
عن للتربة ينتقل الخازوق حمل معظمالسطحى االحتكاك طريق
April 13, 2023 Deep Foundations 4
Pile ApplicationsPile Applications
LowLowWeightWeight
Soft toSoft toFirm ClayFirm Clay
Large DistributedLarge DistributedWeightWeight
Very Large ConcentratedVery Large ConcentratedWeightWeight
Dense Sand
Strong RockStrong Rock
April 13, 2023 Deep Foundations 5
Piles are used in:Piles are used in:1- Upper soil is weak,
compressible, or could not support the surface loads.
2- The loads are tension, horizontal, or inclined.
3- Problematic soils;
Swelling soils giving tension on the pile.
Collapsing soils, adding down-drag forces on the pile.
4- Scour under bridge piers.
5- Temporary or Permanent Excavation Side Support
April 13, 2023 Deep Foundations 6
Types of Pile Materials
ConcreteConcreteTimberTimber Steel HSteel H CompositeCompositePre-cast ConcretePre-cast Concrete
Steel Concrete
Steel PipeSteel Pipe
Timber
April 13, 2023 Deep Foundations 7
Timber PilesTimber Piles
- Relatively inexpensive
- Usually limited to short lengths [though Douglas Fir does come in longer lengths (higher expense)]
- Low capacity.
- Advantages: Easy handling, Non-corrosive material, If permanently submerged then fairly resistant to decay.
- Disadvantages: May require treatment to prevent decay, insects, and borers from damaging pile. Easily damaged during hard driving and inconvenient to splice.
April 13, 2023 Deep Foundations 8
Steel H-PilesSteel H-Piles
- Advantages: high axial working capacity. Wide variety of sizes. Easy on-site modifications. Fairly easy to drive, minimal soil displacement, good penetration through hard materials (with shoe).
- Disadvantages: high cost, potential delays in delivery, relatively higher corrosion, noisy driving, low bearing and friction areas.
April 13, 2023 Deep Foundations 9
Steel Pipe Piles
May drive closed or open-ended.
Advantages: May be driven empty then filled with cheaper material (concrete). Can provide very high capacities. On-site modifications easy.
Disadvantages: similar to H-piles with additional item–more difficult driving due to soil displacement.
April 13, 2023 Deep Foundations 10
Precast Concrete Piles
- May be prestressed to withstand driving and handling stresses.
- Advantages: High capacity. Usually durable and corrosion resistant in many environments (not marine).
- Disadvantages: Handling, splicing, and cutting more of a problem. Transportation difficulties.
April 13, 2023 Deep Foundations 11
- Piles are bored using drilling rig of internal diameter allowing for casting the concrete till the required depth.
- Casting of concrete starts with withdrawing the drilling rig upwards.
- Capacity of about 100 ton- Advantages: ease of changing lengths by
cutting or slicing the shell. Material costs relatively low. Inspection possible.
- Disadvantage: not feasible in hard soils or rock. Voids in concrete may be created. Splicing problems after concreting.
Continuous Flight Auger (CFA)
April 13, 2023 Deep Foundations 12
- Holes are drilled in the soil then filled with bentonite slurry to support the sides.
- Steel reinforcements are then lowered to the required level.
- Concrete casting is performed from bottom to top with pumps.
- Bentonite slurry is then replaced by the concrete and the slurry is desanded for reuse.
Cast-in-place Concrete Piles
April 13, 2023 Deep Foundations 13
Choice of Pile TypeThe pile type is chosen according to:
- Load Capacity & Pile Spacing
- Constructability
- Soil stratigraphy
- Need for splicing or cutting
- Driving vibrations
- Driving speed.
- Performance
- Environmental suitability (corrosion)
- Availability
- Cost
April 13, 2023 Deep Foundations 14
Pile Load Transfer Mechanism
- Fairly complicated, though understandable.
. منتظم- غير وغالبا= معقد الحمل توزيع- Changes with changes in load because friction along
shaft is fully mobilized when pile has displaced only 5-10 mm whereas maximum point resistance is not fully mobilized until a movement of 10% of the pile diameter (or width) for driven piles or even higher in bored piles.
يتحقق- السطحى االحتكاك األقصىفى الحمل) 10-5عند ( نقطة عند األقصى الحمل ويصل مم
حدود فى أو% 10االرتكاز الخازوق قطر منعرضه.
April 13, 2023 Deep Foundations 15
Mobilization of Base and Shaft Resistance
Mobilization of Base and Shaft Resistance
Shaft
2 - 5mm
Base
10 - 20% diam
Total
Displacement
Load
Shaft ??
April 13, 2023 Deep Foundations 16
Pile Failure SurfacePile Failure Surface
Df
Ground Surface
Arching Action
B
DfPO = Df
Zone of Shear & Volume Decrease
Pult
Failure Surface Along the Shaft
April 13, 2023 Deep Foundations 17
End Bearing PilesEnd Bearing Piles
April 13, 2023 Deep Foundations 18
End bearing piles:End bearing piles:Transmit most of their Transmit most of their loads to the load bearing loads to the load bearing layer (dense sand or layer (dense sand or rock). Most of the pile rock). Most of the pile capacity inferred from capacity inferred from the end bearing point.the end bearing point.
من األكبر الجزء من ينقل األكبر الجزء ينقلطريق عن طريق الحمل عن الحمل
وهى االرتكاز وهى نقطة االرتكاز نقطةترتكز التى ترتكز الخوازيق التى الخوازيق
أو الكثيف الرمل أو على الكثيف الرمل علىالصخر.الصخر.
Pbase
Side Friction
End Bearing
Pile Load, P
April 13, 2023 Deep Foundations 19
Friction Piles:Friction Piles:
April 13, 2023 Deep Foundations 20
Friction Piles:Friction Piles: Transmit most of their Transmit most of their load through the layers load through the layers through which the piles through which the piles pass, i.e., mostly through pass, i.e., mostly through the surface friction with the surface friction with the surrounding soilsthe surrounding soils..
عن الحمل معظم عن ينقل الحمل معظم ينقلاالحتكاك االحتكاك طريق طريق
مثل مثل السطحى السطحىفى المنفذة فى الخوازيق المنفذة الخوازيق. الصرفة الطينية .التربة الصرفة الطينية التربة Pbase
End Bearing
Pile Load, P
Side Friction
April 13, 2023 Deep Foundations 21
Individual Pile Capacity
Methods of Estimating Pile Load Capacity:Methods of Estimating Pile Load Capacity:1- Static Analysis from the Shear Strength Parameters1- Static Analysis from the Shear Strength Parameters
خواصالقصفى- 11 من الخوازيق تحمل قدرة خواصالقصفى- تحديد من الخوازيق تحمل قدرة تحديدالتربة.التربة.
2- Dynamic Driving Formula2- Dynamic Driving Formula
دق- 22 صيغة من الخوازيق تحمل قدرة دق- تحديد صيغة من الخوازيق تحمل قدرة تحديد. المستخدمة .الخوازيق المستخدمة الخوازيق
3- Pile Load Test3- Pile Load Test
تحميل- 33 اختبارات من الخوازيق تحمل قدرة تحميل- تحديد اختبارات من الخوازيق تحمل قدرة تحديدالخوازيق.الخوازيق.
4- Field Tests: SPT, CPT, etc.4- Field Tests: SPT, CPT, etc.
االختبارات- 44 من الخوازيق تحمل قدرة االختبارات- تحديد من الخوازيق تحمل قدرة تحديدالحقلية.الحقلية.
April 13, 2023 Deep Foundations 22
PILE CAPACITYPILE CAPACITY1- Bearing capacity of piles from soil parameters:1- Bearing capacity of piles from soil parameters:
Static Formula Method (QStatic Formula Method (Quu = Q = Qbb + Q + Qss))
Embedded Length = D
Qu = Ultimate Bearing Capacity
Qs = fAs
f = Unit Frictional Resistance
AS = Shaft Area (Pile surface area)
qb = Unit Bearing Capacity
Ab = Area of Pile Base
Qb = qbAb
April 13, 2023 Deep Foundations 23
Base ResistanceBase Resistance
Qb = Ab [cbNc ] for Clay
Qb
Qb = Ab [P'ob Nq] for Sand
Ab = Area of Pile BaseNc = 9 for Piles in ClayNq = Given in Tables
April 13, 2023 Deep Foundations 24
Shaft ResistanceShaft Resistance
Due to cohesion or friction or both
In cohesive soils : Qsc = As . ca
In friction soils: Qsf = As .KHC P'ob tan
P'ob
KHC.P'ob
As
As = Pile Surface Area
April 13, 2023 Deep Foundations 25
Total Pile ResistanceTotal Pile Resistance
Qu = Qb + Qs
Qu = Ab [cb Nc] + As [ca ] For Piles in Clay
Qu = Ab [P'ob Nq] + As [KHC P'ob tan ] for Piles in Sand
April 13, 2023 Deep Foundations 26
Qu = Ab [ P'ob Nq ] + As [ KHC P'ob tan ]
Qu = Ab P'ob Nq + As KHc P'ob tan
Piles in SandPiles in Sand
= 20o for Steel = ¾ for Concrete = ¾ for Timber
April 13, 2023 Deep Foundations 27
Qu = As [KHT P'ob tan ] + W
Tension Piles in SandTension Piles in Sand
W = Pile Weight
Pile Type KHC KHT
H-Section Pile 0.5 – 1.0 0.3 – 0.5 Displacement Pile 1.0 – 1.5 0.6 – 1.0 Displacement Pile, Variable Section 1.5 – 2.0 1.0 – 1.3 Displacement Pile, with Water Jetting 0.4 – 0.9 0.3 – 0.6 Bored Pile (D < 60 cm) 0.7 – 1.5 0.4 – 1.0
Table (1): Values of KHC and KHT from the Egyptian Code
April 13, 2023 Deep Foundations 28
Piles in ClayPiles in Clay
Qu = Ab cbNc + As ca
Qu = Ab [cbNc] + As [ca]
April 13, 2023 Deep Foundations 29
Tension Piles in ClayTension Piles in ClayQu = As [ca] + W W = Pile Weight
Pile Material
Soil Consistency
Cohesion, c (kN/m2)
Adhesion, ca (kN/m2)
Very Soft 0.0 – 12.50 0.0 – 12.50 Soft 12.50 – 25.0 12.50 – 24.0 Medium Sitff 25.0 – 50.0 24.0 – 37.50 Stiff 50.0 – 100.0 37.50 – 47.50
Timber or
Concrete
Very Stiff 100.0 – 200.0 47.50 – 65.0
Very Soft 0.0 – 12.50 0.0 – 12.50 Soft 12.50 – 25.0 12.50 – 23.0 Medium Sitff 25.0 – 50.0 23.0 – 35.0 Stiff 50.0 – 100.0 35.0 – 36.0
Steel
Very Stiff 100.0 – 200.0 36.0 – 37.50
Table (2): Adhesion on Piles in Saturated Clay (Egyptian Code)
April 13, 2023 Deep Foundations 30
Overburden Stress P'obOverburden Stress P'ob
Qu = [Ab P'ob Nq] + [AsKHC P'ob tan ]
Meyerhof Method : P'ob = 'z
Vesic Method : critical depth, zc
for z < zc : P'ob = 'zfor z > zc : P'ob = 'zc
zc/d is a function of after installation Suggested value = 20 d
April 13, 2023 Deep Foundations 31
Max Limit on End Bearing?
Some suggest a limit on end bearing to match experience.
Problems with that approach:more complex than that; need to
consider both strength and compressibility of the soil
friction angle varies with effective stress
Over-consolidation causes changes in bearing capacity
April 13, 2023 Deep Foundations 32
Nq from the Egyptian Code
o 25 30 35 40 Nq 15 30 75 150
Table (3): Nq Values Vs for Sand, Egyptian Code.
for Displacement Pile = ( (before construction) + 40o)/2
for Bored Pile = (before construction) – 3o
Nc for ClayNc = 9.0 for calculating the end bearing resistance of piles in clay.
April 13, 2023 Deep Foundations 33
EXAMPLE
Determine the allowable capacity for the concrete bored pile shown in Figure.Pile Diameter D = 0.50 mPile Length L = 14.0 m
Medium stiff clay:C = 30 kN/m2
Ca = 25 kN/m2
sat = 18 kN/m3
Dense Sand: = 40o sat = 19 kN/m3
Nq = 150, KHC = 1.0
12.00 m
2.00 m
April 13, 2023 Deep Foundations
SOLUTIONSide Friction:Side Friction:Qs = As [ca + KHC P'ob tan ]qs in clay:qs-c = ca = 25 kN/m2
Qs-clay = ca [DLc]= 25 [*0.50*12.0]= 25 *18.85 = 471.25 kN
qs in sand:qs-s = KHC P'ob tanCritical depth Zc= 20 * 0.50 = 10.00 mP'ob = 8 * 10 = 80 kN/m2
Lc = 12.0 m
Ls =2.0 m
P'bo distribution
10.0 m10.0 m
April 13, 2023 Deep Foundations 35
SOLUTION = 3/4 = 30o
Qs-s = 1.0 * 80 * 0.578 = 46.24 kN/m2
Qs-s = qs [DLs]= 46.24 [*0.50*2.0] = 145.27 kN
Total side friction:Qs = Qs-c + Qs-s = 471.25 + 145.27 = 616.52 kNEnd Bearing Resistance:qb = P'ob Nq = 80 * 150 = 12000 kN/m2
Qb = qb * Ab = qb * D2 = 12000 * 0.196= 2356.2 kN
Ultimate Pile Capacity = 616.52 + 2356.2 = 2973 kN
April 13, 2023 Deep Foundations 36
SOLUTIONUltimate Pile Capacity Qult = 2973 kNAllowable Pile CapacityQall = Qult/F.S.Qall = 2973/3.0 = 991 kN
= 99.10 ton
Check of Concrete Capacity:Pc = fc (Ac + 1.14 * n * As)
= 5000 (0.196 + 1.14 * 10 * 0.00196)= 5000 * (0.218) = 1090 kN= 109 ton > 99.10 (Qall-soil) (O.K.)
April 13, 2023 Deep Foundations 37
Pile DrivingPile Driving
April 13, 2023 Deep Foundations 38
Closed End Diesel Hammer
April 13, 2023 Deep Foundations 39
The Fundamental Pile Driving FormulaThe Fundamental Pile Driving Formula
shW
R
s R hW
ResistanceSoilofWorkEnergyHammer
RR
WW
SS
hh
April 13, 2023 Deep Foundations 40
Single ActingSingle Acting Double ActingDouble Acting
April 13, 2023 Deep Foundations 41
Diesel HammerDiesel Hammer Vibratory HammerVibratory Hammer
April 13, 2023 Deep Foundations 42
Where:Where:QQallall = Allowable pile capacity, (kN); = Allowable pile capacity, (kN);
WWrr = Weight of hammer, kN;= Weight of hammer, kN;
HH = Height of hammer fall, m;= Height of hammer fall, m;SS = Amount of pile penetration/blow, (mm);= Amount of pile penetration/blow, (mm);CC = Constant = 25 for drop hammer= Constant = 25 for drop hammer
= 2.50 for steam hammer.= 2.50 for steam hammer.
Engineering News Formula (F.S. = 6):Engineering News Formula (F.S. = 6):
PILE CAPACITY2- From Pile Driving Formula
C S 6H. W1000
Q rall
April 13, 2023 Deep Foundations 43
Determine the allowable pile capacity for a pile of Determine the allowable pile capacity for a pile of diameter D = 0.30 m, driven by a steam hammer, diameter D = 0.30 m, driven by a steam hammer, knowing that:knowing that:Average penetration per blow = 17 mmAverage penetration per blow = 17 mmHammer rating Wr.H = 40 kNHammer rating Wr.H = 40 kN
Example:Example:
PILE CAPACITY2- From Pile Driving Formula
ton34.2 kN 341.9
2.50 17 640 * 1000
Qall
Solution:Solution:
April 13, 2023 Deep Foundations 44
PILE CAPACITY3- Static Pile Load – Test Setup
Reaction Beam
Stiffeners
PlateLoad Cell
Spherical Bearing
Ram
Hydraulic JackBourdon Gage
Dial GageLVDT
Mirror
Scale
Test Pile
Grade
Bracket Attached to PileWire
April 13, 2023 Deep Foundations 45
Typical Arrangement for Load Testing a Pile or Drilled Shaft
Reaction BeamReaction Beam
JackJackDial
GageDial
Gage
Test Pile or Drilled ShaftTest Pile or
Drilled Shaft
Support Beam
Support Beam
Anchor Pile or Drilled ShaftAnchor Pile or Drilled Shaft
April 13, 2023 Deep Foundations 46
Pile Static Load – Test Setup
April 13, 2023 Deep Foundations 47
Pile Static Load – Test Setup
April 13, 2023 Deep Foundations 48
Pile Capacity from Static Pile Load Test
Loading is performed up to a test load of 150% (or 200%) of the pile design load, with steps of 25% of the design load. The ultimate capacity is determined by many methods, for example, the Modified Chen Method.
يساوى اختبار حمل عند الخازوق اختبار 150يتمعلى%) 200أو% ( وذلك التصميمى الحمل من
خطوة كل مقدار الحمل% 25خطوات منتحمل. قدرة أقصى تحديد ويتم التصميمى
طريقة باستخدام .Chenللخازوق المعدلة
April 13, 2023 Deep Foundations 49
Pile Capacity from Static Pile Load Test, Load-Settlement Curve
April 13, 2023 Deep Foundations 50
Pile Capacity from Static Pile Load Test, Modified Chen Method
x = 6.801
b
y = 3.70
April 13, 2023 Deep Foundations 51
Pile Capacity from Static Pile Load Test, Modified Chen Method
Ultimate Pile Capacity from Static Pile Load Test, Using Modified Chen Method:The loading curve is drawn as follows:Horizontal axis = measured settlement ();Vertical axis = measured settlement () /load (P).
b 1.21
Qult Where:Qult = Ultimate pile capacity, (kN);1.2 = Safety factorb = Slope of the /Load Vs. curve.
April 13, 2023 Deep Foundations 52
Pile Capacity from Pile Load TestThree conditions should be satisfied from the pile load test:I- QI- Qultult ≥ 2.00 Q ≥ 2.00 Qallall (D.L. + L.L.) (D.L. + L.L.)
Dead + Live LoadsQult ≥ 1.75 Qall (D.L. + L.L. + W.L.)
Dead + Live + Wind LoadsQult ≥ 1.50 Qall (D.L. + L.L. + W.L.+Eq.L.)
Dead + Live + Wind + Earthquake Loads
1.50 Qat Settlement
Q 1.25at Settlement
all
all
II- Measured II- Measured at 1.25 test load ≤ 1.50 at 1.25 test load ≤ 1.50 at Q at Qallall
April 13, 2023 Deep Foundations 53
Pile Capacity from Pile Load Test
A EL P
* 0.50 D 0.02 max
III- Measured III- Measured ≤ ≤ maxmax
Where:Where:maxmax = maximum pile settlement, (m); = maximum pile settlement, (m);
DD = Pile diameter, (m);= Pile diameter, (m);PP = Pile test load, (ton);= Pile test load, (ton);LL = Pile length, (m);= Pile length, (m);EE = Modulus of elasticity of concrete, (t/m= Modulus of elasticity of concrete, (t/m22))AA = Pile cross-section area.= Pile cross-section area.
April 13, 2023 Deep Foundations 54
Pile Capacity from Pile Load Test
Settlement (mm) Date
Load (kN)
S1 S2 S3 S4
Avg. Sett. (mm)
Loading 9/9/04 0.0 0.00 0.00 0.00 0.00 0.00
250.0 0.59 0.66 0.56 0.58 0.60 500.0 0.88 1.00 0.89 0.93 0.93 750.0 1.85 1.98 1.86 1.92 1.90 1000.0 3.12 3.28 3.20 3.26 3.21 1250.0 4.16 4.34 4.27 4.37 4.29 1500.0 10.11 10.46 10.21 10.41 10.30
Unloading 10/9/04 1250.0 10.11 10.46 10.41 10.21 10.30
1000.0 10.01 10.29 10.07 10.27 10.16 750.0 9.70 9.97 9.80 9.99 9.87 500.0 9.20 9.45 9.35 9.03 9.26 250.0 8.53 8.78 8.79 9.97 8.77 0.0 6.65 6.82 6.83 6.84 6.79
Example:Determine the ultimate pile capacity for a pile of diameter D = 0.60 m, and Length L = 10.50 m, with the test results shown in the table, knowing that the design load is 1000 kN, test load = 1500 kN.
April 13, 2023 Deep Foundations 55
Pile Capacity from Pile Load Test Solution:
I- QI- Qultult 1532 > 1.50 Q 1532 > 1.50 Qallall (1500 kN) (1500 kN)
kN 1532 3.70 * 20.11000 * 6.80
b 1.2
1 Qult
QQultult using modified Chen Method: using modified Chen Method:
1.50 1.34 3.214.29
Qat Settlement
Q 1.25at Settlement
all
all
II- Measured II- Measured at 1.25 test load ≤ 1.5 at 1.25 test load ≤ 1.5 at Q at Qallall
April 13, 2023 Deep Foundations 56
Pile Capacity from Pile Load Test
A EL P
* 0.50 D 0.02 max
III- III- maxmax ≤ ≤ at maximum test load: at maximum test load:
0.283 *10*140
10.50 * 150 * 0.50 0.60 * 0.02
4max
maxmax = 0.012 + 0.002 = 0.014 m = 14 mm = 0.012 + 0.002 = 0.014 m = 14 mm
at test load = 10.30 mm < 14.0 mm (at test load = 10.30 mm < 14.0 mm (maxmax) O.K.) O.K.
E = 140 t/cmE = 140 t/cm22 = 140 * 10 = 140 * 1044 t/m t/m22
April 13, 2023 Deep Foundations 57
PILE CAPACITY4- In-Situ Soil Test Methods
The pile capacity can be determined from The pile capacity can be determined from the field tests as follows:the field tests as follows:
1- Standard Penetration Test (SPT).1- Standard Penetration Test (SPT).
2- Cone Penetration Test (CPT).2- Cone Penetration Test (CPT).
April 13, 2023 Deep Foundations 58
Pile Capacity from SPTQallall = 90 N ( R2) + N' (2 RL), (kN)
Qallall = Pile working load, F.S. = 2.5 for end bearing and 2.0 for side friction.
N = Average SPT, 2R below tip and 6R above tip,
N ≤ 50 (Preferably ≤ 30).
N' = Average SPT in sand layers, along the pile shaft.
R = Pile radius, (m).
L = Pile length within the sand layers, (m).For bored piles, Qallall = 50 up to 100% of that values according
to the pile type and construction method.
April 13, 2023 Deep Foundations 59
Pile Capacity from SPTExample:Determine the
allowable pile capacity for a bored pile constructed in the soil log shown in the table. Knowing that the pile diameter is 50 cm, and the pile length is 9.0 m.
D SPT
1 8
2 11
3 14
4 23
5 28
6 31
7 33
8 36
9 41
10 53
11 55
Clay
Sand
April 13, 2023 Deep Foundations 60
Pile Capacity from SPTD SPT
1 8
2 11
3 14
4 23
5 28
6 31
7 33
8 36
9 41
10 53
11 55
Clay
Sand
Solution:
Qallall = 90 N ( R2) + N' (2 RL), (kN)
N = (N8+N9+N10)/3
= (36+41+50)/3 = 42
N' = (N4+N5+N6+N7+N8+N9)/6
= (23+28+31+33+36+41)/6 = 32
Qall = 90 N ( R2) + N' (2 RL), (kN)
= 90*42*0.196+32*(2**0.25*6)
= 740.9+301.6 = 1042.5 = 104 ton
April 13, 2023 Deep Foundations 61
CPT Correlations
The CPT is very similar to driving piles therefore this test is a good predictor of capacity.
Pile capacity is determined from correlations based on CPT, as presented in the Egyptian Code.
April 13, 2023 Deep Foundations 62
Pile Capacity from CPT
Qallall = 1/3 qc ( R2) + ½ fc (2 RL), (kN)Qallall = Pile working load, F.S. = 3.0 for end bearing and 2.0 for
side friction.
qc = Average CPT tip resistance, 6R below tip and 12R
above tip, qc not exceeding 150 kg/cm2.
= Factor relating the pile diameter to the cone diameter,
assumed = 0.70.
fc = Average CPT side friction along the pile, not exceeding
1.0 kg/cm2.
R = Pile radius, (m).
For bored piles, Qallall = 50 up to 100% of that values according to the pile type and construction method.
April 13, 2023 Deep Foundations 63
Pile Groups
Piles are usually arranged in groups under the columns.
The number of piles in a group is determined as follows:
all
c
Q1.10 * P
N
Where:N = No. of piles;Pc = Column Load;Qall = Allowable load of
a single pile.
April 13, 2023 Deep Foundations 64
Arrangement of Pile GroupsThe spacing between piles in a group can be assumed based on the following:1- Driven piles need higher spacing than bored piles.2- Friction piles need higher spacing than end bearing piles.3- Minimum spacing (S) between piles is 2.5.4- Maximum spacing (S) between piles is 8.0.
April 13, 2023 Deep Foundations 65
S
2 Piles
S
3 Piles S
4 Piles
S
S5 Piles
S S6 Piles
S S
S7 Piles
April 13, 2023 Deep Foundations 66
S S
S
8 Piles
SS
S S9 Piles
April 13, 2023 Deep Foundations 67
Negative Skin Friction Q
L1
Granular Fill
L2
Fc
Fg
Soft Clay
Rock
Original Ground Surface
Downdrag force occurs when the Downdrag force occurs when the soil surrounding the pile settles soil surrounding the pile settles more than the pile itself.more than the pile itself.
Occurred in the following Occurred in the following conditions:conditions:1- Recent fill over very soft soil.1- Recent fill over very soft soil.2- Soils undergoing consolidations.2- Soils undergoing consolidations.3- Lowering of ground water table 3- Lowering of ground water table may cause subsidence and may cause subsidence and consequently –ve skin friction.consequently –ve skin friction.
April 13, 2023 Deep Foundations 68
Negative Skin Friction
Negative Skin Friction is calculated as follows:: كالتالى والخوازيق التربة بين السلبى االحتكاك حساب يتم
-ve skin friction = Weight of soil bounded within the soft layers;+ Pile group surface area of the soft layers * pile-soil
adhesion (Ca)بمجموعة = خارجيا= المحاطة التربة وزن السلبى االحتكاك
الخوازيق +المالصقة الخوازيق لمجموعة السطحية المساحة
الضعيفة للطبقاتبها * المحيطة والتربة الخوازيق بين االلتصاق معامل
The negative skin friction per pile should not exceed the pile skin friction value.
قدرة الواحد للخازوق السلبى االحتكاك يتعدى ال بحيث. الخازوق لذلك السطحى االحتكاك
April 13, 2023 Deep Foundations 69
n m 90n 1) - (m + m 1)-(n
- 1 = Ge
Where:Ge = Group efficiency; = tan-1 (D/S) in degrees;D = Pile diameter (m);S = Pile spacing (m);n = Number of piles in a row;m = Number of pile rows
Efficiency of Pile GroupsEfficiency of Pile Groups
April 13, 2023 Deep Foundations 70
Determine the number, arrangement, and group efficiency of a pile group to support a column load of 520 ton, knowing that the pile capacity is 110 ton, the pile diameter is 60 cm.
ExampleExample
S S6 Piles
Solution:Solution:No. of Piles = (520 * 1.10)/110
= 5.20 take 6 pilesAssume that the pile spacing S = 4 D = 2.40 m = tan-1(D/S ) = tan-1(0.25)
=14.04o
April 13, 2023 Deep Foundations 71
0.818 0.182 - 1
2 * 3 * 90
3 1) - (2 + 2 1)- (3 14.04 - 1 = Ge
n = 3 الواحد الصف فى الخوازيق عددm = 2 الخوازيق صفوف عدد
ExampleExample
S S6 Piles
Pile group capacity:Qg = N * Qall * Ge
Qg = 6 * 110 * 0.818 = 539.88 ton≈ 540 < 570, considered O.K.
April 13, 2023 Deep Foundations 72
Pile Groups Under Eccentric Loads
April 13, 2023 Deep Foundations 73
ex
ey
H
V R
Pile groups under eccentric loads
April 13, 2023 Deep Foundations 74
2y
2x
vy
y .V.e
x
.xV.e
nV
P
Where:
V = Total vertical force on the group
ex = Eccentricity in the x-direction
ey = Eccentricity in the y-direction
April 13, 2023 Deep Foundations 75
Settlement of Pile Groups in Sand (After Skempton)
FoundationFoundation
Zone of Settlement
Zone of Settlement
Ground Prestressed by Pile Driving
Ground Prestressed by Pile Driving
Single Pile Load TestSingle Pile Load Test
April 13, 2023 Deep Foundations 76
Settlement for End Bearing Pile GroupsSettlement for End Bearing Pile Groups
Soft Clay
Sand
Soft Clay
1H:2V H1
Hc
nQa
L
BAnQa
A, B = Pile Group Dimensions
April 13, 2023 Deep Foundations 77
Settlement of Friction Pile GroupsSettlement of Friction Pile Groups
nQa
ABnQa
*H
1H:2V
L 32
L
B, A = Pile Group Dimensions
April 13, 2023 Deep Foundations 78
Pile Group Settlement AnalysisPile Group Settlement Analysis
Where:H = Settlement H = Layer thickness Cc = Compression Index eo = Initial voids ratio PO = Overburden Pressure at the middle of the
consolidating layer. P = Change in Pressure at the middle of the
consolidating layer
o
o
o
cc P
ΔPPLog
e1C
HΔH
April 13, 2023 Deep Foundations 79
Structural Design of the Pile Cap
April 13, 2023 Deep Foundations 80
Failure Modes in the Pile Cap
1- Punching, column or pile.
2- Flexural, due to high tensile stresses.
Design of the Pile CapDesign of the Pile Cap
April 13, 2023 Deep Foundations 81
Failure by Punching
Failure due to high tensile
stressesMinimum thickness of the pile cap = Minimum thickness of the pile cap = 80 cm to assure even distribution of 80 cm to assure even distribution of settlements over the piles, or 2.25 pile settlements over the piles, or 2.25 pile diameter D.diameter D.
April 13, 2023 Deep Foundations 82
The concrete section and area steel are determined The concrete section and area steel are determined from the max. moment, then check of shear and from the max. moment, then check of shear and punching is performed.punching is performed.
1:1 1:1d/2 d
Critical Sec. for Shear
Critical Sec. for Moment
d/2 d