P14043 – Smart Cane Phase 3

26
+ P14043 – Smart Cane Phase 3 Lauren Bell Jessica Davila Jake Luckman William McIntyre Aaron Vogel

description

P14043 – Smart Cane Phase 3. Lauren Bell Jessica Davila Jake Luckman William McIntyre Aaron Vogel. Overview. Deliverables: Mechanical Parts/Sub Assembly100 % Complete Drawings & Assembly Instructions100 % Completed and Revised Electrical System Simulation100 % C omplete - PowerPoint PPT Presentation

Transcript of P14043 – Smart Cane Phase 3

P14043 Smart Cane Phase 3

P14043 Smart CanePhase 3Lauren Bell Jessica DavilaJake LuckmanWilliam McIntyreAaron Vogel+OverviewDeliverables:Mechanical Parts/Sub Assembly100 % CompleteDrawings & Assembly Instructions100 % Completed and RevisedElectrical System Simulation100 % Complete Electrical PCB + Parts 40 % Parts received, remaining arrive 3/21Subsystem Testing/Verification100 % CompleteFinal Tests Preparation On TrackProcess:DDR & Phase 2 action items100 % CompleteProblem tracking100 % Tracked and PreparedRisk100 % ManagedProgram:Product CostOn TargetProject CostOn TargetProject ScheduleOn ScheduleOther:External Submission:Submitted on 1/29, Status PendingImagine RITOn Target

The project is meeting all goals at this timeAaron2Fabrication and AssemblyMechanical deliverables are complete.

+AaronFirst, show them our working model!! Explain subsystem we showed them last time, then dive into all of the functions of each part. Dont pass around.Talk about issues poor cutting bit precision and improper press fits, making assembly harder. Forgotten tools, inability to quit with fiberglass, causing time to be wasted An example of a fairly simple part that was overlooked3Electrical Testing

+Test Plan Results

+Testing ResultsVoltage in(TP2)TP4(V)TP5 (V)TP6 (V)00001000200030004000503.083.8603.084.61703.084.94803.084.95903.084.971003.084.97+Traceability Matrix - TechnicalSubsystems have passed all preliminary tests

Subsystem test results all within rangesAll test plans and data tables are documented and referencedFinal tests are scheduled and on track in the project plan+Jake/BJShow to prove that subsystem tests and fully integrated tests will prove all engineering requirements

7Traceability Matrix Non technicalPrototype meets all non-technical requirements

Subsystem test results all within rangesAll test plans and data tables are referencedFinal tests are scheduled in the project plan+Jake8Close Out of Action ItemsUpdate tolerancesUpdate Fabrication Instructions for TestingUpdate Assembly Instructions Complete list of connectorsComplete Electrical LayoutUpdate title blocks on drawings Add 5V node for H-bridgeClosed out all action item from previous phases+JakeThis is a list of some of the actions items that we had from past phases, each task has been completed and can be found on our edge website9Problem Solving Matrix

These are major problems we have encountered, the problem tracking was used to close them out.

+LaurenAll problems are being tracked and progress is being madeAll electrical issues need to be trackedFor presentation, do a deep dive on one problem to show example of the process being used

10Problem Solving Product Cost of Purchased PartsLooked into finding cheaper ABS when material changedFound other materials at a lower costOverall was able to reduce cost of purchased parts to below the requirementProduct cost is more than $100 due to the change of material for some partsRequiring more ABS plastic to manufacture handle increased the price of the productFind a cheaper supplier for ABS plastic or find cheaper suppliers for the other parts of the handle and make sure quantity of parts is correct for 10,000 manufactured canesFind cheaper suppliers for parts and correct quantities for 10,000 manufactured canesFor 5 parts we were able to find the quantities that we need for a cheaper pricePrice of product is now $99.31, which meets our requirement of $100The Problem Solving Matrix enabled us to meet our requirements.+Lauren

11Risk CurveAll risks are being managed.+BJThis is the status of our risk curve as of now. Our actual # is 27 and we planned to be at 20 for the sum of the risks importance. The spike in the curve is due to the fact that we were able to think of some more risks that would negatively affect our project. We have completion dates associated with each risk so sticking to our plan, we should be on track to reduce all risks by May 4th

12Risk AssessmentRisk ItemLikelihoodSeverityImportanceDate Risk will be DiminishedIf PCB is not working correctly23611-AprCane does not stay together, durability failure1338-AprTeam Member leaves team1334-MayCane gets damaged during Imagine RIT demonstration1334-MayAssembly between handle and cane fails to hold the two together1338-AprHandle cover material restricts motion of rollers1338-AprABS back cover breaks during testing phase1338-AprSoftware for testing detection system does not identify objects12217-AprMaterial covering handle tears with wear and produce excessive friction11117-AprBiggest risk: PCB working. Will be resolved April 11th. +BJThis chart shows the risks that we have left. The most important risk is that PCB will not work correctly. BJ will be able to explain what effect this will have on our project and what our plans are to mitigate the risk.13Project BudgetMeeting our customer needs under the new budget.+JessThis is a summary graph of our project budget, we requested for an increased budget and thats what the red line represents. We spent $147 more than originally planned14Project Budget ContinuedVerify that we have the correct quantity of partsVerify that we are not missing anything from budgetPlan for things to go wrong have a budget reserveDESCRIPTIONPLANNED QTY.PLANNED COSTACTUAL QTY.ACTUAL COSTDifference in Planned vs ActualABS Plastic0 $ - 5 $ 59.60 $ 59.60 Motor1 $ 15.95 3 $ 47.85 $ 31.90 Double Shielded Bearing 0 $ - 1 $ 6.79 $ 6.79 PCBs & Breadboards .5mm Pitch 12/24 Pin QFP/QFN Adapter1 $ 6.00 2 $ 12.00 $ 6.00 C18,C19,C200 $ - 4 $ 4.36 $ 4.36 10u6 $ 1.80 10 $ 5.70 $ 3.90 Sunlite Bike Reflector w/ Bracket1 $ 6.01 2 $ 9.90 $ 3.89 R22,R40 $ - 3 $ 3.87 $ 3.87 1/32 HSS Corner-Rounding end mill bit1 $ 38.05 1 $ 41.10 $ 3.05 10u1 $ 2.97 $ 5.94 $ 2.97 Si7617DN3 $ 2.91 6 $ 5.82 $ 2.91 L.E.D.3 $ 4.35 5 $ 7.25 $ 2.90 103AT1 $ 2.25 1 $ 4.50 $ 2.25 1.75 MM Drill bit11 $ 1.68 $ 1.68 1.25 MM Drill bit11 $ 1.66 $ 1.66 3.3u1 $ 1.43 2 $ 2.84 $ 1.41 SiS412DN2 $ 1.30 4 $ 2.60 $ 1.30 1" OD Fiberglass Rod1 $ 28.09 1 $ 29.21 $ 1.12 Lessons Learned+JessThis chart just shows some parts with large differences in actual costs vs planned costs. Read take-away box15Project PlanProject is on track with our plan.

+JessThis is our plan for the remainder of the semester 16Customer MeetingApproved increased budgetPresented the manufactured parts and bread boardLearnings:Find a way that works for customer to remind them about meeting

Bring project plan to meetings, so that we are able to tell them exactly when we will be accomplishing deliverables

Make sure to control scope of project

Know what you want to receive from the meeting+LaurenWe met with our customers last week and requested an increase in budget two weeks ago. Briefly discuss information on slide17Imagine RIT

We are on track with deliverables for Imagine RIT.+Lauren18Team Learnings

Communication is key to an efficient and productive team!+Lauren19Next Steps: Phase 4 DeliverablesFull integrated System demo with CustomerTeamAll Testing Complete:ElectricalBJMechanicalAaronAll Documentation CompleteDrawings & Assembly InstructionsJakeTechnical Paper 75% completeJessicaKnown Problems & Risks addressedTeamDemonstrated & documented process methodologyLaurenAchievement of Project GoalsJessica ImagineRITLaurenWorkload is balanced.+Jake20Conclusion ChartProblems EncounteredBudgetMachining FiberglassWork DistributionLearningsCreate a budget reservePlan time for additional machiningTeam communication

We encountered problems, tracked and learned from them, and our project is still on schedule and budget.+AaronWhat we have completed and shown during presentation21Questions?+Action Items RecapDeliverables:Mechanical Sub Assy100 % CompleteMechanical Purchased Parts & Assys100 % CompleteDrawings & Assy Instructions100 % Complete, up to date, in EdgeElectrical System OperationSimulated operation completeElectrical BOM40% Parts received, balance on orderSubsystem Testing/Verification100 % CompleteFinal Test PrepOn TrackProcess:DDR & Phase 2 action itemsClosedProblem tracking1 concern with mitigation plan, trackedRiskAll risks being managedProgram:Product CostOn target ($99.31 est vs, $100.00 goal)Project CostOn Revised target ($845.00 vs. $900.00)Project ScheduleOn plan for Phase 4 completionOther:External Submission:Submitted on 1/29, Status PendingImagine RITOn plan

Imagine RIT Exhibit (Back-up Slide)Virtual Obstacle CourseRisk ItemLikeihoodSeverityImportanceDetection System Not Functional236Crowded Area236Batteries Run Low or Out212Computer Program not functioning339Cane is Dropped224TOTAL27Virtual Obstacle CoursePhysical Obstacle CourseNo Obstacle CourseResources Needed: Functioning prototype with simulator boxXXXFunctional detection systemXXElectricity (Outlet)XProjector ScreenXLaptopXProgramming AbilityXVirtual Interface IntegrationXExtra Space (beyond normal Imagine RIT allowances)XXPosterXXXHandle and cane assembled togetherXXX+Project PlanChart of Submission IdeasRisk Assessment of IdeasRough Poster Outline24PCB Layout

+Phase 4 DeliverablesItem DescriptionDate DueOwnerComplete prototype handle attached to cane3-AprTeamComplete Rotation under Pressure Test8-AprAaronComplete bump height deflection test8-AprJakeComplete maximum grip diameter test8-AprLaurenComplete weight of handle test8-AprLaurenComplete battery test8-AprAaronComplete motor ramp up time test8-AprJakeList of Phase 5 Deliverables10-AprJessProject summary added into poster draft, CAD drawings, etc.10-AprLaurenComplete all electrical testing11-AprBJComplete Peer Review15-AprTeamComplete rough draft of poster15-AprLaurenUpdate edge15-AprJessClose all problems on problem tracking sheet15-AprJessReduce all risks to 015-AprJessPhase 4 Presentation17-AprTeamPoster: final updated results tables and requirements 24-AprLaurenSubmit final poster to MSD office on flash drive29-AprLauren+Jake26