P03 Project Planning & Estimating
Transcript of P03 Project Planning & Estimating
Project Planning
and Estimating
DJ201 0407
© Copyright ESI International April 2007 All rights reserved.
No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording, or otherwise, without the prior written permission of ESI International.
ESI grants federal government users "Restricted Rights" (as the term is defined in FAR 52.227-14 and DFARS 252.227-7013). Use, reproduction, or disclosure of these materials is subject to the restrictions set forth in the MOBIS, FSS, or contract under which the materials were provided.
All material from A Guide to the Project Management Body of Knowledge (PMBOK® Guide) is reprinted with permission of the Project Management Institute, Four Campus Boulevard, Newtown Square, Pennsylvania 19073-3299, USA, a worldwide organization of advancing the state-of-the-art in project management. Phone: (610)356-4600, Fax: (610)356-4647.
PMI® did not participate in the development of this publication and has not reviewed the content for accuracy. PMI® does not endorse or otherwise sponsor this publication and makes no warranty, guarantee, or representation, expressed or implied, as to its accuracy or content. PMI® does not have any financial interest in this publication and has not contributed any financial resources.
The names of all companies and characters used in these materials are purely fictional. Any resemblance to any existing or no longer existing company or living or dead person is not intended, and is purely coincidental.
“PMI” is a service and trademark of the Project Management Institute, Inc., which is registered in the United States and other nations.
“PMBOK” is a trademark of the Project Management Institute, Inc., which is registered in the United States and other nations.
“PMP” is a certification mark of the Project Management Institute, Inc., which is registered in the United States and other nations.
ESI International Arlington, VA USA
CONTENTS Page
Project Planning and Estimating .......................................................................... 1-1 Workshop Agenda ................................................................................ 1-3 Workshop Objectives ........................................................................... 1-4 Introduction: Review of Project Management and the WBS................... 1-5 What Is a Project? ................................................................................. 1-6 Project Management ............................................................................. 1-7 Project Life Cycle.................................................................................. 1-8 Why Scheduling and Cost Control? ....................................................... 1-9 Organizing the WBS ........................................................................... 1-10 WBS Review....................................................................................... 1-11 Exercise 1: Office Move ...................................................................... 1-12 Estimating ........................................................................................... 1-13 Estimating Basics................................................................................. 1-14 Estimating Recommendations ............................................................. 1-15 Resource Planning .............................................................................. 1-16 Roles and Responsibilities Matrix........................................................ 1-17 Resources as Sources for Estimates ...................................................... 1-18 Estimating Durations ........................................................................... 1-19 Duration Considerations ..................................................................... 1-20 Productivity and Availability in Resource-Driven Estimates.................. 1-21 Exercise 2: Estimating Task Cost and Duration..................................... 1-22 Program Evaluation and Review Technique (PERT).............................. 1-23 Scheduling Techniques ....................................................................... 1-24 Scheduling Techniques ....................................................................... 1-25 Setting Milestones............................................................................... 1-26 Gantt Charts ....................................................................................... 1-27 WBS and Network Diagramming ........................................................ 1-28 Precedence Diagramming Method (PDM) ........................................... 1-29 Scheduling Sample ............................................................................. 1-30 PDM Sample ...................................................................................... 1-31 Exercise 3: Network Diagram for the Office Move............................... 1-32 Basic Scheduling................................................................................. 1-33 Forward Pass ...................................................................................... 1-34 Backward Pass .................................................................................... 1-35 Total Float .......................................................................................... 1-36 Free Float............................................................................................ 1-37 Critical Path ........................................................................................ 1-38 Lag and Lead Times ............................................................................ 1-39 Hammock Activity .............................................................................. 1-40 Techniques for Decreasing Project Duration (Schedule Compression) . 1-41 Resource Trade-Offs: Leveling............................................................. 1-42 Baselines ............................................................................................ 1-43 The Basics of Baselines ....................................................................... 1-44
© ESI April 2007 dj201-tc iii
0BCONTENTS
Page
iv © ESI April 2007 dj201-tc
Cost Baseline ...................................................................................... 1-45 Cost Baseline Sample.......................................................................... 1-46 Baseline Costs Plus Reserve ................................................................ 1-47 Exercise 4: Develop a Baseline............................................................ 1-48 Workshop Review .............................................................................. 1-50 Bibliography and Suggested Reading................................................... 1-51
Project Planning and Estimating
© ESI 1
Project Planning and Estimating
Project Planning and Estimating
© ESI 2
© ESI April 2007 1-3dj201-01.ppt
Workshop Agenda
Introduction: Review of Project Management and the Work Breakdown Structure (WBS)EstimatingScheduling TechniquesBaselines
© ESI April 2007 1-4dj201-01.ppt
Workshop Objectives
By the end of this course, you will be able to—Use the WBS to identify, assign, and tabulate resource requirementsPredict costs and work times using specific levels and estimate types from the WBSUse the WBS to develop a network diagramCalculate schedules using the Precedence Diagramming Method (PDM)Interpret data gained from time-phased distribution of project costs
Project Planning and Estimating
© ESI 3
© ESI April 2007 1-5dj201-01.ppt
Introduction: Review of Project Management and the WBS
© ESI April 2007 1-6dj201-01.ppt
What Is a Project?
A temporary endeavor undertaken to create a unique product, service, or result.
—PMBOK® Guide, p. 5
“PMBOK” is a trademark of the Project Management Institute, Inc., which is registered in the United Statesand other nations.
ProjectC
Ongoing Business Operation
ProjectD
ProjectE
ProjectA
ProjectB
Program X
Program Y
Cancelled
Project Planning and Estimating
© ESI 4
© ESI April 2007 1-7dj201-01.ppt
Project Management
[T]he application of knowledge, skills, tools and techniques to project activities to meet [the] project requirements[A]ccomplished through the application and integration of the project management processes of initiating, planning, executing, monitoring and controlling, and closing.
—PMBOK® Guide, p. 8
Sound project management helps ensure success.
© ESI April 2007 1-8dj201-01.ppt
Project Life CycleProject Life Cycle Used in this Workshop
Initiation Definition Planning Implementation Closure
Project
Phase Purpose
Initiation Introduce project to obtain approval and create project charter
Definition Document project scope, deliverables, and methods for containing scope
Planning Create plan to document the activities required to complete the project, the sequence of activities, the resources assigned to the activities, and the resulting schedule and budgets
Implementation Execute and manage the plan, using artifacts created in the planning phase
Closure Formally review the project, including lessons learned and turnover of project documentation
Project Planning and Estimating
© ESI 5
© ESI April 2007 1-9dj201-01.ppt
Why Scheduling and Cost Control?
The triple constraint—Has the most clearly measurable indexes for project managementDelivers business results
It’s what we do!Scope
Cost
Time
© ESI April 2007 1-10dj201-01.ppt
Organizing the WBS
Define the project—ScopeTasksWork packagesTechnical baseline
Organize the WBS to—Allow for realistic estimatingAllow assignment to a single organizational unit or allow for exclusive responsibility
Use tools consistent with your comfort level and project needs
Project Planning and Estimating
© ESI 6
© ESI April 2007 1-11dj201-01.ppt
WBS Review
The WBS should—Be consistentBe task-oriented and start with a verb, or be deliverables oriented and start with a noun Be decomposed to your level of controlEnsure that each work package accomplishes a discrete work element Make work packages SMART
© ESI April 2007 1-12dj201-01.ppt
Office Move
Exercise 1
Use the following major categories to develop a WBS of those activities necessary to accomplish an office move: project management; pre-move activities; moving activities; post-move activities.
Arrange the following tasks as work packages under the four headings described above: select furniture; prepare office for move; hold kickoff meeting; set up utilities (wiring and so on); complete internal construction to final floor plan; plan move; move/relocate; install new furniture, communications equipment, and computers; install new signs; close out project.
Project Planning and Estimating
© ESI 7
© ESI April 2007 1-13dj201-01.ppt
Estimating
© ESI April 2007 1-14dj201-01.ppt
Estimating Basics
An estimate—Is a quantitative assessment of the likely amount or outcomeIs usually applied to project costs, resources, effort, and durations and is usually preceded by a modifier Should always include some indication of accuracy
“Resources” are—Skilled human resourcesEquipmentSuppliesBudgets or funds
Source: PMBOK® Guide, pp. 360, 372
Project Planning and Estimating
© ESI 8
© ESI April 2007 1-15dj201-01.ppt
Estimating Recommendations
Use the most accurate method availableCommunicate the level of precisionGain agreement on the level of precisionInvolve the teamAssess the environmentBase estimates on historyUse standards (if available)
Do not develop estimates from the budgetBase estimates on known or committed operational plansAccount for likely conditions and circumstancesBase estimates on assumptions of staff, team, and working conditionsInclude date and version stampDo not pad the estimates
© ESI April 2007 1-16dj201-01.ppt
Resource Planning
Fundamental questionsWhat needs to be done?Who and what do we need?Who can do the work?What can do the work?Who and what can we get?What level of excellence and competence is essential?How will we use the resources?How will the resources affect schedules and costs?
Project Planning and Estimating
© ESI 9
© ESI April 2007 1-17dj201-01.ppt
Roles and Responsibilities Matrix
1.1.1
1.1.2
1.1.3
Resource
Task Pat Jean Francis
R—ResponsibleA—AccountableC—ConsultI—Inform
Source: PMBOK® Guide, p. 206
© ESI April 2007 1-18dj201-01.ppt
Resources as Sources for Estimates
Who provides the best estimates?Outside sourcesThose who know the workThose who are accountableThose who do the work
Project Planning and Estimating
© ESI 10
© ESI April 2007 1-19dj201-01.ppt
Estimating Durations
Working time?
Personal time?
© ESI April 2007 1-20dj201-01.ppt
Duration Considerations
Effort hours: Resource hours required to complete a task (24 effort hours = 3 resource days)Working time: Period of time in which actual work on a project or task can and should be completed (24 hours = 3 days)Elapsed time: Calendar duration, including weekends, holidays, and breaks (24 hours = 1 day)Productivity: Rate at which work is producedAvailability: Resources present and ready to workContiguous duration: Work time that is not interruptedInterruptible duration: Work time that may be interrupted
Project Planning and Estimating
© ESI 11
© ESI April 2007 1-21dj201-01.ppt
Productivity and Availability in Resource-Driven Estimates
EffortCost= x Unit Cost
Productivity
Effort/ProductivityDuration=
Availability
© ESI April 2007 1-22dj201-01.ppt
Three team members are being considered for an assignment. Your subject matter expert estimated that the task will take 90 effort hours for an individual with average productivity. The following resource matrix provides measures of individual productivity, availability, and unit cost for each team member.
Calculate the cost and duration for each person to accomplish the task.
$6040%100%$8040%120%$4550%60%Install communications equipment
$/HrAvailProd$/HrAvailProd$/HrAvailProdTask
JuanKimBill
Estimating Task Cost and Duration
Exercise 2
Project Planning and Estimating
© ESI 12
© ESI April 2007 1-23dj201-01.ppt
NOTE: PERT is useful in estimating cost as well as schedule.
( )
( )
+ × +
+ × +=( )
Optimistic 4 Most Likely PessimisticEstimated Time =
6
3 days 4 5 days 8 days = 5.17 days
6te
Program Evaluation and Review Technique (PERT)
© ESI April 2007 1-24dj201-01.ppt
Scheduling Techniques
Project Planning and Estimating
© ESI 13
© ESI April 2007 1-25dj201-01.ppt
Scheduling Techniques
Milestone chartsGantt chartsNetwork diagrams
© ESI April 2007 1-26dj201-01.ppt
Setting Milestones
Milestones—Are significant eventsDenote achievements regarding time, money, and tasksConsume no time
Task 1 complete
200,000,000 Yen spent
500 resource-hours expended
5 10 15 20
Project Planning and Estimating
© ESI 14
© ESI April 2007 1-27dj201-01.ppt
Gantt Charts
Task A
Task B
Task C
Task D
Task E
Task F
ProjectMonth 1 2 3 4 5 6 7
Today
Task A
Task B
Task C
Task D
Task E
Task F
ProjectMonth 1 2 3 4 5 6 7
Today
= Plan= Actual
= Planned Start= Actual Start
= Planned Finish= Actual Finish
© ESI April 2007 1-28dj201-01.ppt
WBS and Network Diagramming
1.1.1 1.1.2 1.2.1 1.2.2 1.3.1 1.3.2
1.31.21.1
WBS1.0
StartStart A C D
B E F
StartFinish
Use only the workpackages to build the
network schedule.
Project Planning and Estimating
© ESI 15
© ESI April 2007 1-29dj201-01.ppt
Precedence Diagramming Method (PDM) A schedule network diagramming technique in which schedule activities are represented by boxes (or nodes). Schedule activities are graphically linked by one or more logical relationships ...
—PMBOK® Guide, p. 367
PDM uses activity-on-node (AON) diagramsArrows show various relationships (finish-start, start-start, finish-finish, start-finish) Accommodates lag and lead
Start 1.1.1 1.1.2 1.2.2
1.3.1 1.3.2
Finish
1.2.1
© ESI April 2007 1-30dj201-01.ppt
Scheduling Sample
Construction chart for a house
Activities and Times to Build a House
Activity
Immediately Preceding Activity
Expected Completion Time (days)
(a) Excavate — 5 (b) Pour foundation a 2 (c) Plumb outside a 6 (d) Frame b 12 (e) Plumb inside d 10 (f) Wire d 9 (g) Build roof d 5 (h) Lay brick b 9 (i) Inspect plumbing c, e 1 (j) Nail shingles g 2 (k) Cover walls f, i, j 3 (l) Finish interior k 9 (m) Finish exterior h, g 7 (n) Landscape m 8
Project Planning and Estimating
© ESI 16
© ESI April 2007 1-31dj201-01.ppt
PDM Sample
Start (a) Excavate5.0 days
(c) Plumboutside6.0 days
(b) Pourfoundation
2.0 days
(d) Frame12.0 days
(e) Plumb inside10.0 days
(f) Wire9.0 days
(i) Inspectplumbing1.0 day
(k) Cover walls3.0 days
(l) Finishinterior9.0 days
Finish
(j) Nail shingles2.0 days
(g) Build roof5.0 days
(m) Finishexterior7.0 days
(n) Landscape8.0 days
(h) Lay brick9.0 days
© ESI April 2007 1-32dj201-01.ppt
10Install new furniture/communications equipment/computers
45Complete internal construction to final floor plan (build out)
15Install new signs
5Close out project
30Set up utilities
5Move/relocate
20Prepare office for move
25Select furniture
1Hold kickoff meeting
20Plan move
Duration (days)Work Package/Activities
Using the WBS you developed for the office move and the durations provided below, build a network diagram for the office move.
Network Diagram for the Office Move
Exercise 3
Project Planning and Estimating
© ESI 17
© ESI April 2007 1-33dj201-01.ppt
Basic Scheduling
Earlystart (ES)
How _________ can this activity _________based on the network logic and constraints?
Earlyfinish (EF)
Latestart (LS)
Latefinish (LF)
© ESI April 2007 1-34dj201-01.ppt
Forward Pass
Duration=7Task A
0 7
EFES
LS LF
Duration=6Task C
7 13
EFES
LS LF
Duration=3Task G
13 16
EFES
LS LF
Start Duration=2Task H
16 18
EFES
LS LF
Finish
Duration=3Task B
0 3
EFES
LS LF
Duration=3Task D
3 6
EFES
LS LF
Duration=2Task F
3 5EFES
LS LF
Duration=3Task E
6 9
EFES
LS LF
ES + duration = EF
Project Planning and Estimating
© ESI 18
© ESI April 2007 1-35dj201-01.ppt
Backward Pass
Duration=7Task A
0 7
70
EFES
LS LF
Duration=6Task C
7 13
137
EFES
LS LF
Duration=3Task G
13 16
1613
EFES
LS LF
Start Duration=2Task H
16 18
1816
EFES
LS LF
Finish
Duration=3Task B
0 3
107
EFES
LS LF
Duration=3Task D
3 6
1310
EFES
LS LF
Duration=2Task F
3 5
1311
EFES
LS LF
Duration=3Task E
6 9
1613
EFES
LS LF
© ESI April 2007 1-36dj201-01.ppt
Total Float
Activities—not projects—may have float. Total float (also called slack, float, or path float)
“The total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date”*Late finish minus early finish (LFj – EFj) Late start minus early start (LSj– ESj)
J*Source: PMBOK® Guide, p. 378
Project Planning and Estimating
© ESI 19
© ESI April 2007 1-37dj201-01.ppt
Free Float
The amount of time that a schedule activity can be delayed without delaying the early start of any immediately following schedule activities.
—PMBOK® Guide, p. 362
I J
© ESI April 2007 1-38dj201-01.ppt
Critical Path
Path on which any delay in project activities will affect the project scheduleLongest of all paths through the projectPath with the least float or slack timeShortest time to complete the project
Start 1.1.1 1.1.2 1.2.2
1.2.1 1.3.1 1.3.2
FinishStart Finish9
34
43
6
Project Planning and Estimating
© ESI 20
© ESI April 2007 1-39dj201-01.ppt
Lag and Lead Times
Lag A modification of a logical relationship that directs a delay in the successor activity.
—PMBOK® Guide, p. 363
Lead A modification of a logical relationship that allows an acceleration of the successor activity.
—PMBOK® Guide, p. 363
A B
Time Units
FS* + 1
A
B
Time Units
FS* – 1
*FS=Finish–Start
© ESI April 2007 1-40dj201-01.ppt
Hammock Activity
A group of related schedule activities aggregated at some summary level, and displayed/reported as a single activity at that summary level.
—PMBOK® Guide, p. 362
Test system10
Monitor contract180HA
Install cars20
Install rail150
Project Planning and Estimating
© ESI 21
© ESI April 2007 1-41dj201-01.ppt
Techniques for Decreasing Project Duration (Schedule Compression)
Crashing tasks: Reducing the duration of activities on the critical path in any possible wayCrashing a network: A “[s]chedule compression technique in which cost and schedule trade-offs are analyzed to determine how to obtain the greatest amount of compression for the least incremental cost”*Fast tracking: “A schedule compression technique in which phases or activities that normally would be done in sequence are performed in parallel”*
*Source: PMBOK® Guide, pp. 145-146
© ESI April 2007 1-42dj201-01.ppt
Resource Trade-Offs: Leveling
Leveling is the rescheduling of tasks with float to resolve resource issuesSteps:
Determine early and late schedulesEvaluate resource loading for each scheduleIdentify free floatAdjust activities (tasks) on an activity-by-activity basis within the float to fit available resourcesDetermine new schedule
Project Planning and Estimating
© ESI 22
© ESI April 2007 1-43dj201-01.ppt
Baselines
© ESI April 2007 1-44dj201-01.ppt
The Basics of Baselines
A baseline is the original approved plan, plus approved scope changesThe baseline establishes a reference against which project managers can measure actual project progress
Project Planning and Estimating
© ESI 23
© ESI April 2007 1-45dj201-01.ppt
Cost Baseline
ContractPrice
ContractBudget Base
Contract Feeor Profit
ReservePerformanceMeasurement
Budget
UndistributedBudget
DistributedBudget
Project Budget Model
© ESI April 2007 1-46dj201-01.ppt
Cost Baseline Sample
BDur=4
CDur=5
Start
Finish
ADur=3
DDur=4
EDur=3
FDur=4
0
500
1,000
1,500
2,000
2,500
0 5 10 15 20
$
Days
Project Planning and Estimating
© ESI 24
© ESI April 2007 1-47dj201-01.ppt
Baseline Costs Plus Reserve
Reserve is money or time provided for in the project plan to mitigate cost, schedule, or performance risk.
—Ward, p. 188
Cost to Complete (CTC)
Reserve
Baselinecosts
Time
T1 T2 T3
Budget at Completion(BAC)
$
© ESI April 2007 1-48dj201-01.ppt
Using the graph on the next slide, develop a cumulative cost curve based on the network diagram you created for the office move.
$15,000Install new furniture/communications equipment/computers
$20,000Complete internal construction to final floor plan (build out)
$1,000Install new signs
$0Close out project
$150Set up utilities
$10,000Move/relocate
$1,100Prepare office for move
$0Select furniture
$50Hold kickoff meeting
$0Plan move
Estimated CostWork Package/Activities
Develop a Baseline
Exercise 4
Project Planning and Estimating
© ESI 25
© ESI April 2007 1-49dj201-01.ppt
Develop a Baseline (continued)
Exercise 4
Time
$
© ESI April 2007 1-50dj201-01.ppt
Workshop Review
By now, you should be able to—Use the WBS to identify, assign, and tabulate resource requirementsPredict costs and work time using specific levels and estimate types from the WBSUse the WBS to develop a network diagramCalculate schedules using the Precedence Diagramming Method (PDM)Interpret data gained from time-phased distribution of project costs
Project Planning and Estimating
© ESI 26
© ESI April 2007 1-51dj201-01.ppt
Bibliography and Suggested Reading
Project Management Institute. A Guide to the Project Management Body of Knowledge.Newtown Square, Pa.: Project Management Institute, 2004.Ward, LeRoy, ed. Project Management Terms: A Working Glossary. Arlington, Va.: ESI International, 2000.
© ESI April 2007 1-52dj201-01.ppt
The ESI Team appreciates your time.