P03 Project Planning & Estimating

30
Project Planning and Estimating DJ201 0407

Transcript of P03 Project Planning & Estimating

Page 1: P03 Project Planning & Estimating

Project Planning

and Estimating

DJ201 0407

Page 2: P03 Project Planning & Estimating

© Copyright ESI International April 2007 All rights reserved.

No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording, or otherwise, without the prior written permission of ESI International.

ESI grants federal government users "Restricted Rights" (as the term is defined in FAR 52.227-14 and DFARS 252.227-7013). Use, reproduction, or disclosure of these materials is subject to the restrictions set forth in the MOBIS, FSS, or contract under which the materials were provided.

All material from A Guide to the Project Management Body of Knowledge (PMBOK® Guide) is reprinted with permission of the Project Management Institute, Four Campus Boulevard, Newtown Square, Pennsylvania 19073-3299, USA, a worldwide organization of advancing the state-of-the-art in project management. Phone: (610)356-4600, Fax: (610)356-4647.

PMI® did not participate in the development of this publication and has not reviewed the content for accuracy. PMI® does not endorse or otherwise sponsor this publication and makes no warranty, guarantee, or representation, expressed or implied, as to its accuracy or content. PMI® does not have any financial interest in this publication and has not contributed any financial resources.

The names of all companies and characters used in these materials are purely fictional. Any resemblance to any existing or no longer existing company or living or dead person is not intended, and is purely coincidental.

“PMI” is a service and trademark of the Project Management Institute, Inc., which is registered in the United States and other nations.

“PMBOK” is a trademark of the Project Management Institute, Inc., which is registered in the United States and other nations.

“PMP” is a certification mark of the Project Management Institute, Inc., which is registered in the United States and other nations.

ESI International Arlington, VA USA

Page 3: P03 Project Planning & Estimating

CONTENTS Page

Project Planning and Estimating .......................................................................... 1-1 Workshop Agenda ................................................................................ 1-3 Workshop Objectives ........................................................................... 1-4 Introduction: Review of Project Management and the WBS................... 1-5 What Is a Project? ................................................................................. 1-6 Project Management ............................................................................. 1-7 Project Life Cycle.................................................................................. 1-8 Why Scheduling and Cost Control? ....................................................... 1-9 Organizing the WBS ........................................................................... 1-10 WBS Review....................................................................................... 1-11 Exercise 1: Office Move ...................................................................... 1-12 Estimating ........................................................................................... 1-13 Estimating Basics................................................................................. 1-14 Estimating Recommendations ............................................................. 1-15 Resource Planning .............................................................................. 1-16 Roles and Responsibilities Matrix........................................................ 1-17 Resources as Sources for Estimates ...................................................... 1-18 Estimating Durations ........................................................................... 1-19 Duration Considerations ..................................................................... 1-20 Productivity and Availability in Resource-Driven Estimates.................. 1-21 Exercise 2: Estimating Task Cost and Duration..................................... 1-22 Program Evaluation and Review Technique (PERT).............................. 1-23 Scheduling Techniques ....................................................................... 1-24 Scheduling Techniques ....................................................................... 1-25 Setting Milestones............................................................................... 1-26 Gantt Charts ....................................................................................... 1-27 WBS and Network Diagramming ........................................................ 1-28 Precedence Diagramming Method (PDM) ........................................... 1-29 Scheduling Sample ............................................................................. 1-30 PDM Sample ...................................................................................... 1-31 Exercise 3: Network Diagram for the Office Move............................... 1-32 Basic Scheduling................................................................................. 1-33 Forward Pass ...................................................................................... 1-34 Backward Pass .................................................................................... 1-35 Total Float .......................................................................................... 1-36 Free Float............................................................................................ 1-37 Critical Path ........................................................................................ 1-38 Lag and Lead Times ............................................................................ 1-39 Hammock Activity .............................................................................. 1-40 Techniques for Decreasing Project Duration (Schedule Compression) . 1-41 Resource Trade-Offs: Leveling............................................................. 1-42 Baselines ............................................................................................ 1-43 The Basics of Baselines ....................................................................... 1-44

© ESI April 2007 dj201-tc iii

Page 4: P03 Project Planning & Estimating

0BCONTENTS

Page

iv © ESI April 2007 dj201-tc

Cost Baseline ...................................................................................... 1-45 Cost Baseline Sample.......................................................................... 1-46 Baseline Costs Plus Reserve ................................................................ 1-47 Exercise 4: Develop a Baseline............................................................ 1-48 Workshop Review .............................................................................. 1-50 Bibliography and Suggested Reading................................................... 1-51

Page 5: P03 Project Planning & Estimating

Project Planning and Estimating

© ESI 1

Project Planning and Estimating

Page 6: P03 Project Planning & Estimating

Project Planning and Estimating

© ESI 2

© ESI April 2007 1-3dj201-01.ppt

Workshop Agenda

Introduction: Review of Project Management and the Work Breakdown Structure (WBS)EstimatingScheduling TechniquesBaselines

© ESI April 2007 1-4dj201-01.ppt

Workshop Objectives

By the end of this course, you will be able to—Use the WBS to identify, assign, and tabulate resource requirementsPredict costs and work times using specific levels and estimate types from the WBSUse the WBS to develop a network diagramCalculate schedules using the Precedence Diagramming Method (PDM)Interpret data gained from time-phased distribution of project costs

Page 7: P03 Project Planning & Estimating

Project Planning and Estimating

© ESI 3

© ESI April 2007 1-5dj201-01.ppt

Introduction: Review of Project Management and the WBS

© ESI April 2007 1-6dj201-01.ppt

What Is a Project?

A temporary endeavor undertaken to create a unique product, service, or result.

—PMBOK® Guide, p. 5

“PMBOK” is a trademark of the Project Management Institute, Inc., which is registered in the United Statesand other nations.

ProjectC

Ongoing Business Operation

ProjectD

ProjectE

ProjectA

ProjectB

Program X

Program Y

Cancelled

Page 8: P03 Project Planning & Estimating

Project Planning and Estimating

© ESI 4

© ESI April 2007 1-7dj201-01.ppt

Project Management

[T]he application of knowledge, skills, tools and techniques to project activities to meet [the] project requirements[A]ccomplished through the application and integration of the project management processes of initiating, planning, executing, monitoring and controlling, and closing.

—PMBOK® Guide, p. 8

Sound project management helps ensure success.

© ESI April 2007 1-8dj201-01.ppt

Project Life CycleProject Life Cycle Used in this Workshop

Initiation Definition Planning Implementation Closure

Project

Phase Purpose

Initiation Introduce project to obtain approval and create project charter

Definition Document project scope, deliverables, and methods for containing scope

Planning Create plan to document the activities required to complete the project, the sequence of activities, the resources assigned to the activities, and the resulting schedule and budgets

Implementation Execute and manage the plan, using artifacts created in the planning phase

Closure Formally review the project, including lessons learned and turnover of project documentation

Page 9: P03 Project Planning & Estimating

Project Planning and Estimating

© ESI 5

© ESI April 2007 1-9dj201-01.ppt

Why Scheduling and Cost Control?

The triple constraint—Has the most clearly measurable indexes for project managementDelivers business results

It’s what we do!Scope

Cost

Time

© ESI April 2007 1-10dj201-01.ppt

Organizing the WBS

Define the project—ScopeTasksWork packagesTechnical baseline

Organize the WBS to—Allow for realistic estimatingAllow assignment to a single organizational unit or allow for exclusive responsibility

Use tools consistent with your comfort level and project needs

Page 10: P03 Project Planning & Estimating

Project Planning and Estimating

© ESI 6

© ESI April 2007 1-11dj201-01.ppt

WBS Review

The WBS should—Be consistentBe task-oriented and start with a verb, or be deliverables oriented and start with a noun Be decomposed to your level of controlEnsure that each work package accomplishes a discrete work element Make work packages SMART

© ESI April 2007 1-12dj201-01.ppt

Office Move

Exercise 1

Use the following major categories to develop a WBS of those activities necessary to accomplish an office move: project management; pre-move activities; moving activities; post-move activities.

Arrange the following tasks as work packages under the four headings described above: select furniture; prepare office for move; hold kickoff meeting; set up utilities (wiring and so on); complete internal construction to final floor plan; plan move; move/relocate; install new furniture, communications equipment, and computers; install new signs; close out project.

Page 11: P03 Project Planning & Estimating

Project Planning and Estimating

© ESI 7

© ESI April 2007 1-13dj201-01.ppt

Estimating

© ESI April 2007 1-14dj201-01.ppt

Estimating Basics

An estimate—Is a quantitative assessment of the likely amount or outcomeIs usually applied to project costs, resources, effort, and durations and is usually preceded by a modifier Should always include some indication of accuracy

“Resources” are—Skilled human resourcesEquipmentSuppliesBudgets or funds

Source: PMBOK® Guide, pp. 360, 372

Page 12: P03 Project Planning & Estimating

Project Planning and Estimating

© ESI 8

© ESI April 2007 1-15dj201-01.ppt

Estimating Recommendations

Use the most accurate method availableCommunicate the level of precisionGain agreement on the level of precisionInvolve the teamAssess the environmentBase estimates on historyUse standards (if available)

Do not develop estimates from the budgetBase estimates on known or committed operational plansAccount for likely conditions and circumstancesBase estimates on assumptions of staff, team, and working conditionsInclude date and version stampDo not pad the estimates

© ESI April 2007 1-16dj201-01.ppt

Resource Planning

Fundamental questionsWhat needs to be done?Who and what do we need?Who can do the work?What can do the work?Who and what can we get?What level of excellence and competence is essential?How will we use the resources?How will the resources affect schedules and costs?

Page 13: P03 Project Planning & Estimating

Project Planning and Estimating

© ESI 9

© ESI April 2007 1-17dj201-01.ppt

Roles and Responsibilities Matrix

1.1.1

1.1.2

1.1.3

Resource

Task Pat Jean Francis

R—ResponsibleA—AccountableC—ConsultI—Inform

Source: PMBOK® Guide, p. 206

© ESI April 2007 1-18dj201-01.ppt

Resources as Sources for Estimates

Who provides the best estimates?Outside sourcesThose who know the workThose who are accountableThose who do the work

Page 14: P03 Project Planning & Estimating

Project Planning and Estimating

© ESI 10

© ESI April 2007 1-19dj201-01.ppt

Estimating Durations

Working time?

Personal time?

© ESI April 2007 1-20dj201-01.ppt

Duration Considerations

Effort hours: Resource hours required to complete a task (24 effort hours = 3 resource days)Working time: Period of time in which actual work on a project or task can and should be completed (24 hours = 3 days)Elapsed time: Calendar duration, including weekends, holidays, and breaks (24 hours = 1 day)Productivity: Rate at which work is producedAvailability: Resources present and ready to workContiguous duration: Work time that is not interruptedInterruptible duration: Work time that may be interrupted

Page 15: P03 Project Planning & Estimating

Project Planning and Estimating

© ESI 11

© ESI April 2007 1-21dj201-01.ppt

Productivity and Availability in Resource-Driven Estimates

EffortCost= x Unit Cost

Productivity

Effort/ProductivityDuration=

Availability

© ESI April 2007 1-22dj201-01.ppt

Three team members are being considered for an assignment. Your subject matter expert estimated that the task will take 90 effort hours for an individual with average productivity. The following resource matrix provides measures of individual productivity, availability, and unit cost for each team member.

Calculate the cost and duration for each person to accomplish the task.

$6040%100%$8040%120%$4550%60%Install communications equipment

$/HrAvailProd$/HrAvailProd$/HrAvailProdTask

JuanKimBill

Estimating Task Cost and Duration

Exercise 2

Page 16: P03 Project Planning & Estimating

Project Planning and Estimating

© ESI 12

© ESI April 2007 1-23dj201-01.ppt

NOTE: PERT is useful in estimating cost as well as schedule.

( )

( )

+ × +

+ × +=( )

Optimistic 4 Most Likely PessimisticEstimated Time =

6

3 days 4 5 days 8 days = 5.17 days

6te

Program Evaluation and Review Technique (PERT)

© ESI April 2007 1-24dj201-01.ppt

Scheduling Techniques

Page 17: P03 Project Planning & Estimating

Project Planning and Estimating

© ESI 13

© ESI April 2007 1-25dj201-01.ppt

Scheduling Techniques

Milestone chartsGantt chartsNetwork diagrams

© ESI April 2007 1-26dj201-01.ppt

Setting Milestones

Milestones—Are significant eventsDenote achievements regarding time, money, and tasksConsume no time

Task 1 complete

200,000,000 Yen spent

500 resource-hours expended

5 10 15 20

Page 18: P03 Project Planning & Estimating

Project Planning and Estimating

© ESI 14

© ESI April 2007 1-27dj201-01.ppt

Gantt Charts

Task A

Task B

Task C

Task D

Task E

Task F

ProjectMonth 1 2 3 4 5 6 7

Today

Task A

Task B

Task C

Task D

Task E

Task F

ProjectMonth 1 2 3 4 5 6 7

Today

= Plan= Actual

= Planned Start= Actual Start

= Planned Finish= Actual Finish

© ESI April 2007 1-28dj201-01.ppt

WBS and Network Diagramming

1.1.1 1.1.2 1.2.1 1.2.2 1.3.1 1.3.2

1.31.21.1

WBS1.0

StartStart A C D

B E F

StartFinish

Use only the workpackages to build the

network schedule.

Page 19: P03 Project Planning & Estimating

Project Planning and Estimating

© ESI 15

© ESI April 2007 1-29dj201-01.ppt

Precedence Diagramming Method (PDM) A schedule network diagramming technique in which schedule activities are represented by boxes (or nodes). Schedule activities are graphically linked by one or more logical relationships ...

—PMBOK® Guide, p. 367

PDM uses activity-on-node (AON) diagramsArrows show various relationships (finish-start, start-start, finish-finish, start-finish) Accommodates lag and lead

Start 1.1.1 1.1.2 1.2.2

1.3.1 1.3.2

Finish

1.2.1

© ESI April 2007 1-30dj201-01.ppt

Scheduling Sample

Construction chart for a house

Activities and Times to Build a House

Activity

Immediately Preceding Activity

Expected Completion Time (days)

(a) Excavate — 5 (b) Pour foundation a 2 (c) Plumb outside a 6 (d) Frame b 12 (e) Plumb inside d 10 (f) Wire d 9 (g) Build roof d 5 (h) Lay brick b 9 (i) Inspect plumbing c, e 1 (j) Nail shingles g 2 (k) Cover walls f, i, j 3 (l) Finish interior k 9 (m) Finish exterior h, g 7 (n) Landscape m 8

Page 20: P03 Project Planning & Estimating

Project Planning and Estimating

© ESI 16

© ESI April 2007 1-31dj201-01.ppt

PDM Sample

Start (a) Excavate5.0 days

(c) Plumboutside6.0 days

(b) Pourfoundation

2.0 days

(d) Frame12.0 days

(e) Plumb inside10.0 days

(f) Wire9.0 days

(i) Inspectplumbing1.0 day

(k) Cover walls3.0 days

(l) Finishinterior9.0 days

Finish

(j) Nail shingles2.0 days

(g) Build roof5.0 days

(m) Finishexterior7.0 days

(n) Landscape8.0 days

(h) Lay brick9.0 days

© ESI April 2007 1-32dj201-01.ppt

10Install new furniture/communications equipment/computers

45Complete internal construction to final floor plan (build out)

15Install new signs

5Close out project

30Set up utilities

5Move/relocate

20Prepare office for move

25Select furniture

1Hold kickoff meeting

20Plan move

Duration (days)Work Package/Activities

Using the WBS you developed for the office move and the durations provided below, build a network diagram for the office move.

Network Diagram for the Office Move

Exercise 3

Page 21: P03 Project Planning & Estimating

Project Planning and Estimating

© ESI 17

© ESI April 2007 1-33dj201-01.ppt

Basic Scheduling

Earlystart (ES)

How _________ can this activity _________based on the network logic and constraints?

Earlyfinish (EF)

Latestart (LS)

Latefinish (LF)

© ESI April 2007 1-34dj201-01.ppt

Forward Pass

Duration=7Task A

0 7

EFES

LS LF

Duration=6Task C

7 13

EFES

LS LF

Duration=3Task G

13 16

EFES

LS LF

Start Duration=2Task H

16 18

EFES

LS LF

Finish

Duration=3Task B

0 3

EFES

LS LF

Duration=3Task D

3 6

EFES

LS LF

Duration=2Task F

3 5EFES

LS LF

Duration=3Task E

6 9

EFES

LS LF

ES + duration = EF

Page 22: P03 Project Planning & Estimating

Project Planning and Estimating

© ESI 18

© ESI April 2007 1-35dj201-01.ppt

Backward Pass

Duration=7Task A

0 7

70

EFES

LS LF

Duration=6Task C

7 13

137

EFES

LS LF

Duration=3Task G

13 16

1613

EFES

LS LF

Start Duration=2Task H

16 18

1816

EFES

LS LF

Finish

Duration=3Task B

0 3

107

EFES

LS LF

Duration=3Task D

3 6

1310

EFES

LS LF

Duration=2Task F

3 5

1311

EFES

LS LF

Duration=3Task E

6 9

1613

EFES

LS LF

© ESI April 2007 1-36dj201-01.ppt

Total Float

Activities—not projects—may have float. Total float (also called slack, float, or path float)

“The total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date”*Late finish minus early finish (LFj – EFj) Late start minus early start (LSj– ESj)

J*Source: PMBOK® Guide, p. 378

Page 23: P03 Project Planning & Estimating

Project Planning and Estimating

© ESI 19

© ESI April 2007 1-37dj201-01.ppt

Free Float

The amount of time that a schedule activity can be delayed without delaying the early start of any immediately following schedule activities.

—PMBOK® Guide, p. 362

I J

© ESI April 2007 1-38dj201-01.ppt

Critical Path

Path on which any delay in project activities will affect the project scheduleLongest of all paths through the projectPath with the least float or slack timeShortest time to complete the project

Start 1.1.1 1.1.2 1.2.2

1.2.1 1.3.1 1.3.2

FinishStart Finish9

34

43

6

Page 24: P03 Project Planning & Estimating

Project Planning and Estimating

© ESI 20

© ESI April 2007 1-39dj201-01.ppt

Lag and Lead Times

Lag A modification of a logical relationship that directs a delay in the successor activity.

—PMBOK® Guide, p. 363

Lead A modification of a logical relationship that allows an acceleration of the successor activity.

—PMBOK® Guide, p. 363

A B

Time Units

FS* + 1

A

B

Time Units

FS* – 1

*FS=Finish–Start

© ESI April 2007 1-40dj201-01.ppt

Hammock Activity

A group of related schedule activities aggregated at some summary level, and displayed/reported as a single activity at that summary level.

—PMBOK® Guide, p. 362

Test system10

Monitor contract180HA

Install cars20

Install rail150

Page 25: P03 Project Planning & Estimating

Project Planning and Estimating

© ESI 21

© ESI April 2007 1-41dj201-01.ppt

Techniques for Decreasing Project Duration (Schedule Compression)

Crashing tasks: Reducing the duration of activities on the critical path in any possible wayCrashing a network: A “[s]chedule compression technique in which cost and schedule trade-offs are analyzed to determine how to obtain the greatest amount of compression for the least incremental cost”*Fast tracking: “A schedule compression technique in which phases or activities that normally would be done in sequence are performed in parallel”*

*Source: PMBOK® Guide, pp. 145-146

© ESI April 2007 1-42dj201-01.ppt

Resource Trade-Offs: Leveling

Leveling is the rescheduling of tasks with float to resolve resource issuesSteps:

Determine early and late schedulesEvaluate resource loading for each scheduleIdentify free floatAdjust activities (tasks) on an activity-by-activity basis within the float to fit available resourcesDetermine new schedule

Page 26: P03 Project Planning & Estimating

Project Planning and Estimating

© ESI 22

© ESI April 2007 1-43dj201-01.ppt

Baselines

© ESI April 2007 1-44dj201-01.ppt

The Basics of Baselines

A baseline is the original approved plan, plus approved scope changesThe baseline establishes a reference against which project managers can measure actual project progress

Page 27: P03 Project Planning & Estimating

Project Planning and Estimating

© ESI 23

© ESI April 2007 1-45dj201-01.ppt

Cost Baseline

ContractPrice

ContractBudget Base

Contract Feeor Profit

ReservePerformanceMeasurement

Budget

UndistributedBudget

DistributedBudget

Project Budget Model

© ESI April 2007 1-46dj201-01.ppt

Cost Baseline Sample

BDur=4

CDur=5

Start

Finish

ADur=3

DDur=4

EDur=3

FDur=4

0

500

1,000

1,500

2,000

2,500

0 5 10 15 20

$

Days

Page 28: P03 Project Planning & Estimating

Project Planning and Estimating

© ESI 24

© ESI April 2007 1-47dj201-01.ppt

Baseline Costs Plus Reserve

Reserve is money or time provided for in the project plan to mitigate cost, schedule, or performance risk.

—Ward, p. 188

Cost to Complete (CTC)

Reserve

Baselinecosts

Time

T1 T2 T3

Budget at Completion(BAC)

$

© ESI April 2007 1-48dj201-01.ppt

Using the graph on the next slide, develop a cumulative cost curve based on the network diagram you created for the office move.

$15,000Install new furniture/communications equipment/computers

$20,000Complete internal construction to final floor plan (build out)

$1,000Install new signs

$0Close out project

$150Set up utilities

$10,000Move/relocate

$1,100Prepare office for move

$0Select furniture

$50Hold kickoff meeting

$0Plan move

Estimated CostWork Package/Activities

Develop a Baseline

Exercise 4

Page 29: P03 Project Planning & Estimating

Project Planning and Estimating

© ESI 25

© ESI April 2007 1-49dj201-01.ppt

Develop a Baseline (continued)

Exercise 4

Time

$

© ESI April 2007 1-50dj201-01.ppt

Workshop Review

By now, you should be able to—Use the WBS to identify, assign, and tabulate resource requirementsPredict costs and work time using specific levels and estimate types from the WBSUse the WBS to develop a network diagramCalculate schedules using the Precedence Diagramming Method (PDM)Interpret data gained from time-phased distribution of project costs

Page 30: P03 Project Planning & Estimating

Project Planning and Estimating

© ESI 26

© ESI April 2007 1-51dj201-01.ppt

Bibliography and Suggested Reading

Project Management Institute. A Guide to the Project Management Body of Knowledge.Newtown Square, Pa.: Project Management Institute, 2004.Ward, LeRoy, ed. Project Management Terms: A Working Glossary. Arlington, Va.: ESI International, 2000.

© ESI April 2007 1-52dj201-01.ppt