Overview of the Last Planner System - Cal Poly
Transcript of Overview of the Last Planner System - Cal Poly
LCI Education
& Training
Overview of the Last Planner® SystemCollaborative Construction Progress Planning – Spec. 013200
LCI Education
& Training31 October 2018
David Umstot, PE
LCI Education
& Training
Why use Last Planner®?
Completed Ahead ofSchedule
Completed UnderBudget
Low Lean Intensity High Lean Intensity
3X
2X
LCI Education
& Training
Workflow & Risk
Workflow losses are real, lead to adversarial relations, and are difficult to quantify, so…
Everyone protects themselves by adding contingency and/or holding back labor to keep utilization high.
This further reduces workflow predictability and increases project risk.
By their/our actions, we increase that risk and shift it along.
LCI Education
& Training
1. Traditional planning systems are unable to produce
predictable workflow.
2. Workflow reliability directly affects system speed and cost.
3. All plans are forecasts, all forecasts are wrong, the longer the
forecast the more wrong it is, the more detailed the more wrong
it is.
KEY CONCEPTS:
LCI Education
& Training
Last Planner® System Benefits:
Improves communication & reliability
Fosters an enjoyable environment, trust & collaboration
Promotes early stakeholder engagement
Improves visibility of the project plan (transparency)
Creates team buy in
Rapid learning through metrics, revealing areas for improvement
Improves planning in both design & construction phases
LCI Education
& Training
Last Planner® System
Milestone Planning
Phase “Pull” Planning
Look Ahead Planning
Weekly Work Planning
Learning/Improving
Set milestones
Specify handoffs
Make work ready
Make promises
PPC/Variance
SHOULD
CAN
WILL
DID
5 Connected
Conversations
LCI Education
& Training
Phase
Pull
Planning
Look
Ahead
Planning
Weekly
Work
Planning
Daily
Huddle
Last Planner® System
LCI Education
& Training
Who is the Last Planner?
A Last Planner can
make the reliable
commitment to
complete the work
Person closest to
work, with authority
to make decisions
creates schedule
LCI Education
& Training
Milestone Planning
Phase Pull Plan Phase Pull Plan
Define the overall road map and gain alignment
Identify milestones important to client and
stakeholders – especially immovable dates
Informs the Phase Pull Planning
LCI Education
& Training
Phase Pull Planning
• Phase of the work (8-12 wks)
Phase Pull Planning
• After – add dates and transfer
to the Look Ahead Plan
• Work out the structure and
durations
• Informed by the Milestone Plan
LCI Education
& Training
Pull Example
Mike G 5 days4 Crew
Underground Piping
Zone 1
Vaults Backfilled
Dave S 3 days3Crew
Backfill Vaults
Zone 1
Vaults Set
Mike G 3days4 Crew
Vaults Set
Zone 1
Vaults on Site
Dave S 3days3 Crew
Backfill UG Piping
Zone 1
UG Piping
Promise Promise Promise
RequestRequest
LCI Education
& Training
Constraint
Description Responsible
Person &
CO
Date
Needed
Look Ahead Planning
LCI Education
& Training
Boards in Weekly Meeting Space
6 Look
Ahead Plan
Weekly
Boards
Look Ahead Planning
LCI Education
& Training
32
Daily Huddle
3. What needs to
be re-planned?
2. What will I
complete?
1. What did I
complete?
LCI Education
& Training
Future Training Opportunities
• CSU Dominguez Hills - Friday, November 16, 2018
• Cal Poly San Luis Obispo – Tuesday, December 11, 2018
• CSU East Bay – Wednesday, February 27, 2019
• CSU Sacramento – Friday, March 15, 2019
LCI Education
& Training
Questions?David Umstot, PE, CEM