Overview of New Practices & Policy Skewed Bridges.

81
Overview of New Overview of New Practices & Policy Practices & Policy Skewed Bridges Skewed Bridges

Transcript of Overview of New Practices & Policy Skewed Bridges.

Page 1: Overview of New Practices & Policy Skewed Bridges.

Overview of New Overview of New Practices & PolicyPractices & Policy

Skewed BridgesSkewed Bridges

Page 2: Overview of New Practices & Policy Skewed Bridges.

What does all this mean?What does all this mean?

Page 3: Overview of New Practices & Policy Skewed Bridges.

Preliminary Design ConsiderationsPreliminary Design Considerations

• What potential skewed solutions should be considered?

• What about non-skewed

solutions?

Page 4: Overview of New Practices & Policy Skewed Bridges.

Potential Skewed SolutionsPotential Skewed Solutions

1.1. Erect Girders PlumbErect Girders Plumb

2.2. Erect Girders Out-of-PlumbErect Girders Out-of-Plumb

3.3. Stiffen SuperstructureStiffen Superstructure

4.4. ““Lean-on” BracingLean-on” Bracing

Page 5: Overview of New Practices & Policy Skewed Bridges.

Potential Solutions – Solution 1Potential Solutions – Solution 1Erect Girders PlumbErect Girders Plumb

Erect girders plumb → Girders rotate Erect girders plumb → Girders rotate out of plumb during deck placement out of plumb during deck placement (girders will be permanently twisted)(girders will be permanently twisted)

Page 6: Overview of New Practices & Policy Skewed Bridges.

How much twist is too much ?How much twist is too much ?

ODOT Limit:

≤ 0.6°

Or

1/8” per ft.

x

1

Page 7: Overview of New Practices & Policy Skewed Bridges.

For Line Girder Analysis:For Line Girder Analysis:If δ ≤ S/100 then ≤ 0.6°

S

δ

Page 8: Overview of New Practices & Policy Skewed Bridges.

Potential Solutions – Solution 2Potential Solutions – Solution 2Erect Girders out of PlumbErect Girders out of Plumb

Erect girders out of plumb (twisted) → Erect girders out of plumb (twisted) → Girders rotate to plumb during deck Girders rotate to plumb during deck placementplacement

Page 9: Overview of New Practices & Policy Skewed Bridges.

Potential Solutions – Solution 3Potential Solutions – Solution 3Stiffen SuperstructureStiffen Superstructure

Add steel Add steel – Bigger flangesBigger flanges– Deeper websDeeper webs– Add girder line(s)Add girder line(s)

Use shored constructionUse shored construction

Use only upon approval from Use only upon approval from OSEOSE

Page 10: Overview of New Practices & Policy Skewed Bridges.

Potential Solutions – Solution 4Potential Solutions – Solution 4 Lean-on Bracing Lean-on Bracing

Internal Lean on Bracing (Solution “4I”)Internal Lean on Bracing (Solution “4I”)

External Lean on Bracing (Solution “4E”)External Lean on Bracing (Solution “4E”)

Page 11: Overview of New Practices & Policy Skewed Bridges.

Skewed Bridge Design Process (Steel Beams/Girders)

Check That DesignRates Using PC-BARS

Skew > 45°

Girder Twist < 1/8”/ft?

Girder Twist < 1/8”/ft?

No

Girder Twist < 1/8”/ft?

No

Implement External Lean-on Bracing*

Implement Internal Lean-on Bracing with

Refined Analysis*

No

Finish DesignUsing Refined Analysis:Erect Girders VerticalAnd Allow To Rotate

Check That DesignRates Using PC-BARS

Yes

Yes

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Stiffen Design:0% to ± 25%

Additional Steel

DifferentialDeflections

< S/100

No No

Design Using LineGirder Analysis

Yes

Yes

Yes

Stiffen Design:0% to ± 25%

Additional Steel

Perform Refined Analysis*

Page 12: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Design Using LineGirder Analysis

Check That DesignRates Using PC-BARS

Yes

Skewed Bridge Design Process

(Branch #1)

Page 13: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Design Using LineGirder Analysis

Check That DesignRates Using PC-BARS

Yes

30° < Skew ≤ 45°

Skewed Bridge Design Process

(Branch #1)

Page 14: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Design Using LineGirder Analysis

Check That DesignRates Using PC-BARS

Yes

Perform Line Girder Analysis for “Optimized” Design.

Remember:Main girder elements act independently and effect of crossframes are ignored.

Skewed Bridge Design Process

(Branch #1)

Page 15: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Design Using LineGirder Analysis

Check That DesignRates Using PC-BARS

Yes

Skewed Bridge Design Process

(Branch #1)

S

δ

Page 16: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Design Using LineGirder Analysis

Check That DesignRates Using PC-BARS

Yes Complete Design Using Line Girder Analysis for “Optimized” Design

Skewed Bridge Design Process

(Branch #1)

Potential Skew Solution 1: Erect Girders Plumb

Page 17: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Design Using LineGirder Analysis

Check That DesignRates Using PC-BARS

Yes

Check Design Rating Using PC-BARS

• Rating for New bridges must equal or exceed HS-25

• Rating assumes no future wearing surface

• Should be considered during preliminary element sizing

Skewed Bridge Design Process

(Branch #1)

Page 18: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Design Using LineGirder Analysis

Check That DesignRates Using PC-BARS

Yes

Skewed Bridge Design Process

(Branch #1)

Required for Preliminary Design

Page 19: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Design Using LineGirder Analysis

Check That DesignRates Using PC-BARS

Stiffen Design:0% to ± 25%

Additional Steel

DifferentialDeflections

< S/100

Yes

No

Skewed Bridge Design Process

(Branch #2)

Page 20: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Design Using LineGirder Analysis

Check That DesignRates Using PC-BARS

Stiffen Design:0% to ± 25%

Additional Steel

DifferentialDeflections

< S/100

Yes

No

Skewed Bridge Design Process

(Branch #2)

Stiffen design: Increase “Optimized” steel design 0% to ±25% (By Weight)• Increase depth• Increase flange sizes• Add girder(s)

Potential Skew Solution 3: Stiffen Superstructure

Page 21: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Design Using LineGirder Analysis

Check That DesignRates Using PC-BARS

Stiffen Design:0% to ± 25%

Additional Steel

DifferentialDeflections

< S/100

Yes

No

Skewed Bridge Design Process

(Branch #2)

S

δ

Page 22: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Design Using LineGirder Analysis

Check That DesignRates Using PC-BARS

Stiffen Design:0% to ± 25%

Additional Steel

DifferentialDeflections

< S/100

Yes

No

Skewed Bridge Design Process

(Branch #2)

Complete Design Using Line Girder Analysis for Stiffened DesignPotential Skew Solution 1: Erect Girders Plumb

Page 23: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Design Using LineGirder Analysis

Check That DesignRates Using PC-BARS

Stiffen Design:0% to ± 25%

Additional Steel

DifferentialDeflections

< S/100

Yes

No

Skewed Bridge Design Process

(Branch #2)

Required for Preliminary Design

Page 24: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Stiffen Design:0% to ± 25%

Additional Steel

Perform Refined Analysis*

Girder Twist < 1/8”/ft?

Finish DesignUsing Refined Analysis:Erect Girders VerticalAnd Allow To Rotate

DifferentialDeflections

< S/100

NoNo

Yes

Check That DesignRates Using PC-BARS

Skewed Bridge Design Process

(Branch #3)

Page 25: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Stiffen Design:0% to ± 25%

Additional Steel

Perform Refined Analysis*

Girder Twist < 1/8”/ft?

Finish DesignUsing Refined Analysis:Erect Girders VerticalAnd Allow To Rotate

DifferentialDeflections

< S/100

No

Yes

Check That DesignRates Using PC-BARS

Skewed Bridge Design Process

(Branch #3)

Perform Refined Analysis* to account for crossframe-girder interaction.

No

* Begin Refined Analysis by sizing primary members using member sizes from “Optimized” Line Girder Analysis.

Page 26: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Stiffen Design:0% to ± 25%

Additional Steel

Girder Twist < 1/8”/ft?

Finish DesignUsing Refined Analysis:Erect Girders VerticalAnd Allow To Rotate

DifferentialDeflections

< S/100

No

Yes

Check That DesignRates Using PC-BARS

Skewed Bridge Design Process

(Branch #3)No

1/8”

1’

Perform Refined Analysis*

Page 27: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Stiffen Design:0% to ± 25%

Additional Steel

Girder Twist < 1/8”/ft?

Finish DesignUsing Refined Analysis:Erect Girders VerticalAnd Allow To Rotate

DifferentialDeflections

< S/100

No

Yes

Check That DesignRates Using PC-BARS

Skewed Bridge Design Process

(Branch #3)No

Complete Design Using Refined AnalysisPotential Skew Solution 1: Erect Girders Plumb

Perform Refined Analysis*

Page 28: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Stiffen Design:0% to ± 25%

Additional Steel

Perform Refined Analysis*

Girder Twist < 1/8”/ft?

Finish DesignUsing Refined Analysis:Erect Girders VerticalAnd Allow To Rotate

DifferentialDeflections

< S/100

No

Yes

Check That DesignRates Using PC-BARS

Skewed Bridge Design Process

(Branch #3)No

Required for Preliminary Design

Page 29: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Stiffen Design:0% to ± 25%

Additional Steel

Girder Twist < 1/8”/ft?

Finish DesignUsing Refined Analysis:Erect Girders VerticalAnd Allow To Rotate

DifferentialDeflections

< S/100

No

Check That DesignRates Using PC-BARS

Skewed Bridge Design Process

(Branch #4)No

Girder Twist < 1/8”/ft?

No

Yes

Stiffen Design:0% to ± 25%

Additional Steel

Perform Refined Analysis*

Page 30: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Stiffen Design:0% to ± 25%

Additional Steel

Girder Twist < 1/8”/ft?

Finish DesignUsing Refined Analysis:Erect Girders VerticalAnd Allow To Rotate

DifferentialDeflections

< S/100

No

Check That DesignRates Using PC-BARS

Skewed Bridge Design Process

(Branch #4)No

Girder Twist < 1/8”/ft?

No

Yes

Stiffen Design:0% to ± 25%

Additional Steel

Potential Skew Solution 3: Stiffen Super.

Increase “Optimized” steel design 0% to ± 25% (by weight) then recheck twist.

Perform Refined Analysis*

Page 31: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Stiffen Design:0% to ± 25%

Additional Steel

Perform Refined Analysis*

Girder Twist < 1/8”/ft?

Finish DesignUsing Refined Analysis:Erect Girders VerticalAnd Allow To Rotate

DifferentialDeflections

< S/100

No

Check That DesignRates Using PC-BARS

Skewed Bridge Design Process

(Branch #4)No

Girder Twist < 1/8”/ft?

No

Yes

Stiffen Design:0% to ± 25%

Additional Steel

Required for Preliminary Design

Page 32: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Stiffen Design:0% to ± 25%

Additional Steel

Girder Twist < 1/8”/ft?

Finish DesignUsing Refined Analysis:Erect Girders VerticalAnd Allow To Rotate

DifferentialDeflections

< S/100

No

Check That DesignRates Using PC-BARS

Skewed Bridge Design Process

(Branch #5)No

Girder Twist < 1/8”/ft?

NoStiffen Design:0% to ± 25%

Additional Steel

Girder Twist < 1/8”/ft?

Implement Internal Lean-on Bracing with

Refined Analysis*

No

Yes

Perform Refined Analysis*

Page 33: Overview of New Practices & Policy Skewed Bridges.

Girder Twist < 1/8”/ft?

NoStiffen Design:0% to ± 25%

Additional Steel

No

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Stiffen Design:0% to ± 25%

Additional Steel

Girder Twist < 1/8”/ft?

Finish DesignUsing Refined Analysis:Erect Girders VerticalAnd Allow To Rotate

DifferentialDeflections

< S/100

No

Check That DesignRates Using PC-BARS

Skewed Bridge Design Process

(Branch #5)

Implement Internal Lean-on Bracing with

Refined Analysis*

Girder Twist < 1/8”/ft?

Yes

NoPotential Skew Solution 4:

Implement Internal Lean-on Bracing using Refined Analysis *

Perform Refined Analysis*

* Begin Refined Analysis for Lean-on bracing by sizing primary members using member sizes from “Optimized” Line Girder

Analysis.

Page 34: Overview of New Practices & Policy Skewed Bridges.

Check GirderTwist

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Stiffen Design:0% to ± 25%

Additional Steel

Girder Twist < 1/8”/ft?

Finish DesignUsing Refined Analysis:Erect Girders VerticalAnd Allow To Rotate

DifferentialDeflections

< S/100

No

Check That DesignRates Using PC-BARS

Skewed Bridge Design Process

(Branch #5)

Implement Internal Lean-on Bracing with

Refined Analysis*

Girder Twist < 1/8”/ft?

Yes

No Perform Refined Analysis*

Girder Twist < 1/8”/ft?

Stiffen Design:0% to ± 25%

Additional Steel

NoPotential Skew Solution 3:

If “No” increase “Optimized” steel design 0 to ±25% (by weight) and recheck twist.

Page 35: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Stiffen Design:0% to ± 25%

Additional Steel

Perform Refined Analysis*

Girder Twist < 1/8”/ft?

Finish DesignUsing Refined Analysis:Erect Girders VerticalAnd Allow To Rotate

DifferentialDeflections

< S/100

No

Check That DesignRates Using PC-BARS

Skewed Bridge Design Process

(Branch #5)

Implement Internal Lean-on Bracing with

Refined Analysis*

Girder Twist < 1/8”/ft?

Yes

No

Girder Twist < 1/8”/ft?

Stiffen Design:0% to ± 25%

Additional Steel

No

Required for Preliminary

Design

Page 36: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Stiffen Design:0% to ± 25%

Additional Steel

Girder Twist < 1/8”/ft?

DifferentialDeflections

< S/100

No

Skewed Bridge Design Process

(Branch #6)

Implement Internal Lean-on Bracing with

Refined Analysis*

Girder Twist < 1/8”/ft?

Check That DesignRates Using PC-BARS

Implement External Lean-on Bracing*

No

No Perform Refined Analysis*

Girder Twist < 1/8”/ft?

Stiffen Design:0% to ± 25%

Additional Steel

No

Page 37: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Stiffen Design:0% to ± 25%

Additional Steel

Girder Twist < 1/8”/ft?

DifferentialDeflections

< S/100

No

Skewed Bridge Design Process

(Branch #6)

Implement Internal Lean-on Bracing with

Refined Analysis*

Girder Twist < 1/8”/ft?

Check That DesignRates Using PC-BARS

Implement External Lean-on Bracing*

No

No

* Size primary members using “Optimized”

steel design from Line Girder analysis.

Perform Refined Analysis*

Girder Twist < 1/8”/ft?

Stiffen Design:0% to ± 25%

Additional Steel

No

Potential Skew Solution 4:

Implement External Lean-on Bracing with Refined Analysis*

Page 38: Overview of New Practices & Policy Skewed Bridges.

Skewed Bridge Design Process

(Branch #6)DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Stiffen Design:0% to ± 25%

Additional Steel

Perform Refined Analysis*

Girder Twist < 1/8”/ft?

DifferentialDeflections

< S/100

No

Implement Internal Lean-on Bracing with

Refined Analysis*

Girder Twist < 1/8”/ft?

No

Check That DesignRates Using PC-BARS

Implement External Lean-on Bracing*

No

Girder Twist < 1/8”/ft?

Stiffen Design:0% to ± 25%

Additional Steel

No

Required for Preliminary

Design

Page 39: Overview of New Practices & Policy Skewed Bridges.

Skew > 45°

Girder Twist < 1/8”/ft?

Finish DesignUsing Refined Analysis:Erect Girders VerticalAnd Allow To Rotate

Yes

Check That DesignRates Using PC-BARS

Skewed Bridge Design Process

(Branch #7)Perform Refined Analysis*

Page 40: Overview of New Practices & Policy Skewed Bridges.

Skew > 45°

Girder Twist < 1/8”/ft?

Finish DesignUsing Refined Analysis:Erect Girders VerticalAnd Allow To Rotate

Yes

Check That DesignRates Using PC-BARS

Skewed Bridge Design Process

(Branch #7)Skew > 45°

Perform Refined Analysis*

Page 41: Overview of New Practices & Policy Skewed Bridges.

Skew > 45°

Girder Twist < 1/8”/ft?

Finish DesignUsing Refined Analysis:Erect Girders VerticalAnd Allow To Rotate

Yes

Check That DesignRates Using PC-BARS

Skewed Bridge Design Process

(Branch #7)

* Begin Refined Analysis by sizing primary members using member sizes from “Optimized” Line Girder Analysis.

Perform Refined Analysis*

Page 42: Overview of New Practices & Policy Skewed Bridges.

Skew > 45°

Perform Refined Analysis*

Girder Twist < 1/8”/ft?

Finish DesignUsing Refined Analysis:Erect Girders VerticalAnd Allow To Rotate

Yes

Check That DesignRates Using PC-BARS

Skewed Bridge Design Process

(Branch #7)

Required for Preliminary Design

Page 43: Overview of New Practices & Policy Skewed Bridges.

Skew > 45°

Girder Twist < 1/8”/ft?

Finish DesignUsing Refined Analysis:Erect Girders VerticalAnd Allow To Rotate

Check That DesignRates Using PC-BARS

Yes

Skewed Bridge Design Process

(Branch #8)

NoGirder Twist < 1/8”/ft?

Stiffen Design:0% to ± 25%

Additional Steel

Perform Refined Analysis*

Page 44: Overview of New Practices & Policy Skewed Bridges.

Skew > 45°

Girder Twist < 1/8”/ft?

Finish DesignUsing Refined Analysis:Erect Girders VerticalAnd Allow To Rotate

Check That DesignRates Using PC-BARS

Yes

Skewed Bridge Design Process

(Branch #8)

NoGirder Twist < 1/8”/ft?

Stiffen Design:0% to ± 25%

Additional Steel

Perform Refined Analysis*

Required for Preliminary Design

Page 45: Overview of New Practices & Policy Skewed Bridges.

Skew > 45°

Girder Twist < 1/8”/ft?

Finish DesignUsing Refined Analysis:Erect Girders VerticalAnd Allow To Rotate

No

Check That DesignRates Using PC-BARS

Girder Twist < 1/8”/ft?

Yes

Skewed Bridge Design Process

(Branch #9)

Implement Internal Lean-on Bracing with

Refined Analysis*

No Girder Twist < 1/8”/ft?

Perform Refined Analysis*

Stiffen Design:0% to ± 25%

Additional Steel

Page 46: Overview of New Practices & Policy Skewed Bridges.

Skew > 45°

Girder Twist < 1/8”/ft?

Finish DesignUsing Refined Analysis:Erect Girders VerticalAnd Allow To Rotate

No

Check That DesignRates Using PC-BARS

Girder Twist < 1/8”/ft?

Yes

Skewed Bridge Design Process

(Branch #9)

Implement Internal Lean-on Bracing with

Refined Analysis*

No Girder Twist < 1/8”/ft?

Perform Refined Analysis*

Stiffen Design:0% to ± 25%

Additional Steel

Required for Preliminary

Design

Page 47: Overview of New Practices & Policy Skewed Bridges.

Check That DesignRates Using PC-BARS

Skew > 45°

Girder Twist < 1/8”/ft?

Girder Twist < 1/8”/ft?

No

Skewed Bridge Design Process

(Branch #10)

No

Implement External Lean-on Bracing*

Implement Internal Lean-on Bracing with

Refined Analysis*

No Girder Twist < 1/8”/ft?

Perform Refined Analysis*

Stiffen Design:0% to ± 25%

Additional Steel

Page 48: Overview of New Practices & Policy Skewed Bridges.

Check That DesignRates Using PC-BARS

No

Skewed Bridge Design Process

(Branch #10)

Implement External Lean-on Bracing*

Skew > 45°

Girder Twist < 1/8”/ft?

No

Girder Twist < 1/8”/ft?

Implement Internal Lean-on Bracing with

Refined Analysis*

No Girder Twist < 1/8”/ft?

Perform Refined Analysis*

Stiffen Design:0% to ± 25%

Additional Steel

Required for Preliminary

Design

Page 49: Overview of New Practices & Policy Skewed Bridges.

Skewed Bridge Design Process (Steel Beams/Girders)

Check That DesignRates Using PC-BARS

Skew > 45°

Girder Twist < 1/8”/ft?

Girder Twist < 1/8”/ft?

No

No

Implement External Lean-on Bracing*

Implement Internal Lean-on Bracing with

Refined Analysis*

No

Finish DesignUsing Refined Analysis:Erect Girders VerticalAnd Allow To Rotate

Check That DesignRates Using PC-BARS

Yes

Yes

DifferentialDeflections

< S/100

30° < Skew ≤ 45°

Perform Line Girder Analysis

Stiffen Design:0% to ± 25%

Additional Steel

DifferentialDeflections

< S/100

No No

Design Using LineGirder Analysis

Yes

Yes

Yes

Girder Twist < 1/8”/ft?

Perform Refined Analysis*

Stiffen Design:0% to ± 25%

Additional Steel

Page 50: Overview of New Practices & Policy Skewed Bridges.

What about skewed PrestressedWhat about skewed PrestressedI-Beams Superstructures?I-Beams Superstructures?

Page 51: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

Perform Line Girder Analysis

Design Using LineGirder Analysis

Check That DesignRates Using PC-BARS

Stiffen DesignDifferentialDeflections

< S/100

YesYes

NoNo

Alternate Superstructure

Type

Skewed Bridge Design Process

Prestressed Beams/Girders: Skew > 30°

Page 52: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

Perform Line Girder Analysis

Design Using LineGirder Analysis

Check That DesignRates Using PC-BARS

Yes

Skewed Bridge Design Process

(Branch #1)

Page 53: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

Perform Line Girder Analysis

Design Using LineGirder Analysis

Check That DesignRates Using PC-BARS

Yes

Perform Line Girder Analysis for “Optimized” Design.

Skewed Bridge Design Process

(Branch #1)

Page 54: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

Perform Line Girder Analysis

Design Using LineGirder Analysis

Check That DesignRates Using PC-BARS

Yes

S

δ

Skewed Bridge Design Process

(Branch #1)

Page 55: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

Perform Line Girder Analysis

Design Using LineGirder Analysis

Check That DesignRates Using PC-BARS

Yes Complete Design Using Line Girder Analysis for “Optimized” DesignPotential Skew Solution 1: Erect Girders Plumb

Skewed Bridge Design Process

(Branch #1)

Page 56: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

Perform Line Girder Analysis

Design Using LineGirder Analysis

Check That DesignRates Using PC-BARS

Yes

Check That Design Rates Using PC-BARS

Skewed Bridge Design Process

(Branch #1)

Page 57: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

Perform Line Girder Analysis

Design Using LineGirder Analysis

Check That DesignRates Using PC-BARS

Yes

Skewed Bridge Design Process

(Branch #1)

Required for Preliminary

Design

Page 58: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

Perform Line Girder Analysis

Design Using LineGirder Analysis

Check That DesignRates Using PC-BARS

Stiffen DesignDifferentialDeflections

< S/100

YesYes

No

Skewed Bridge Design Process

(Branch #2)

Page 59: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

Perform Line Girder Analysis

Design Using LineGirder Analysis

Check That DesignRates Using PC-BARS

Stiffen DesignDifferentialDeflections

< S/100

YesYes

No

Stiffen Design:

• Add beam line

• Increase beam size

Skewed Bridge Design Process

(Branch #2)

Page 60: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

Perform Line Girder Analysis

Design Using LineGirder Analysis

Check That DesignRates Using PC-BARS

Stiffen DesignDifferentialDeflections

< S/100

YesYes

No

Skewed Bridge Design Process

(Branch #2)

S

δ

Page 61: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

Perform Line Girder Analysis

Design Using LineGirder Analysis

Check That DesignRates Using PC-BARS

Stiffen DesignDifferentialDeflections

< S/100

YesYes

No

Skewed Bridge Design Process

(Branch #2)

Required for Preliminary

Design

Page 62: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

Perform Line Girder Analysis

Stiffen DesignDifferentialDeflections

< S/100

NoNo

Alternate Superstructure

Type

Skewed Bridge Design Process

(Branch #3)

Page 63: Overview of New Practices & Policy Skewed Bridges.

DifferentialDeflections

< S/100

Perform Line Girder Analysis

Stiffen DesignDifferentialDeflections

< S/100

NoNo

Alternate Superstructure

TypeDesign Alternate Structure Type

Skewed Bridge Design Process

(Branch #3)

Page 64: Overview of New Practices & Policy Skewed Bridges.

Non-skewed AlternativesNon-skewed Alternatives

Designers should consider:Designers should consider: Longer spans that eliminate or reduce skewLonger spans that eliminate or reduce skew Straddle Bents that span the under-bridge Straddle Bents that span the under-bridge

featurefeature

For alternatives with similar costs:

ODOT will prefer reduced skews over “Lean on” construction.

Page 65: Overview of New Practices & Policy Skewed Bridges.

Detail Design ConsiderationsDetail Design Considerations

• Stakeholder Responsibilities

• Intermediate Crossframes

• End Crossframes

• End Diaphragms

• Bearings

Page 66: Overview of New Practices & Policy Skewed Bridges.

Stakeholder ResponsibilitiesStakeholder Responsibilities

Designer Responsibilities:

• Structural design during deck placement & final condition

• Structural stability during deck placement

Page 67: Overview of New Practices & Policy Skewed Bridges.

Stakeholder ResponsibilitiesStakeholder Responsibilities

Contractor Responsibilities:

• Detailing bracing members to fit under steel dead load with

girders plumb at erection

• Structural stability during erection

• Structural stability during deck placement (if different than plan)

Page 68: Overview of New Practices & Policy Skewed Bridges.

Intermediate CrossframesIntermediate Crossframes2004 ODOT BDM Design Requirements2004 ODOT BDM Design Requirements

“On skewed structures, in order to accommodate differential dead load deflections of adjacent stringers that exceed ½ inch at any intermediate crossframe location, the erection bolt holes in the crossframe members should be detailed as slotted holes. Hole dimensions shall be 1/16” wider than the nominal bolt diameter and ¾” longer than the nominal bolt diameter. Holes in the stiffeners shall be 3/16” larger than the diameter of the erection bolts. Final bolting and welding shall not be completed until after the deck concrete has been placed.“

Page 69: Overview of New Practices & Policy Skewed Bridges.

Intermediate CrossframesIntermediate Crossframes

No Slots in Crossframe members:

Slots cause:• Insufficient bracing • Exaggerated

deflections/rotations

Page 70: Overview of New Practices & Policy Skewed Bridges.

Intermediate CrossframesIntermediate Crossframes

Bracing members should be fully tightened Bracing members should be fully tightened and welded during deck placementand welded during deck placement

Fully Tighten Bolts

Field weld

Type 3 Type 4

Page 71: Overview of New Practices & Policy Skewed Bridges.

Intermediate CrossframesIntermediate Crossframes

Design bracing members for Refined Analysis Loads

• Start with GSD-1-96

• Add beef wherenecessary

Page 72: Overview of New Practices & Policy Skewed Bridges.

End Crossframes: Skews End Crossframes: Skews > 30°DO NOT INSTALL END CROSSFRAME DIAGONALS UNTIL DECK PLACEMENT IN ADJACENT SPAN IS COMPLETE.

End Armor

Bottom Chord

Diagonals

Page 73: Overview of New Practices & Policy Skewed Bridges.

• Eliminates girder end rotation caused by decambering• Simplifies refined analysis model• Reduces locked-in stresses• Temporary bracing should be investigated

Bottom Chord

End Armor

End Crossframes: Skews End Crossframes: Skews > 30° DO NOT INSTALL END CROSSFRAME DIAGONALS UNTIL DECK PLACEMENT IN ADJACENT SPAN IS COMPLETE.

Page 74: Overview of New Practices & Policy Skewed Bridges.

End DiaphragmsEnd DiaphragmsSteel Superstructures (Skew > 30°) ORSteel Superstructures (Skew > 30°) ORConcrete Superstructures (Skew > 10°)Concrete Superstructures (Skew > 10°)

Place diaphragms after deck placement in adjacent span is complete.

Stage 1

Stage 2

Page 75: Overview of New Practices & Policy Skewed Bridges.

End DiaphragmsEnd DiaphragmsSteel Superstructures (Skew > 30°) ORSteel Superstructures (Skew > 30°) ORConcrete Superstructures (Skew > 10°)Concrete Superstructures (Skew > 10°)

Stage 1

Stage 2

• Eliminates girder end rotation caused by decambering• Simplifies refined analysis model• Reduces locked-in stresses in end diaphragm & main members and reduces potential for cracking• Temporary end bracing should be considered

Page 76: Overview of New Practices & Policy Skewed Bridges.

BearingsBearingsRotationsRotations

Design Bearings for the out-of-plane rotations.

• Use results from refined analysis

- OR -

• 1/8” per ft. (max.)

Page 77: Overview of New Practices & Policy Skewed Bridges.

BearingsBearingsLoad PlatesLoad Plates

Do not bevel load plate in transverse direction.

• Forces girder web out-of-plane during erection

• Complicates bearing fabrication

Page 78: Overview of New Practices & Policy Skewed Bridges.

BearingsBearingsSize Bearings for Refined Analysis ReactionsSize Bearings for Refined Analysis Reactions

FixedBearings

ExpansionBearings

Page 79: Overview of New Practices & Policy Skewed Bridges.

Policy ChangesPolicy ChangesBridge Design Manual (BDM)Bridge Design Manual (BDM)

New Appendix SectionNew Appendix Section::ODOT Guide for the Design of Skewed ODOT Guide for the Design of Skewed SuperstructuresSuperstructures

Page 80: Overview of New Practices & Policy Skewed Bridges.

SummarySummary

An itemized summary is provided at the back of the seminar handout and is available for download at our website:

www.dot.state.oh.us/se/skew/skew.htm

Page 81: Overview of New Practices & Policy Skewed Bridges.

Questions ??Questions ??

Email Questions to:

[email protected]