Overview - Minnesota LTAP€¦ · 1 Section 5 Construction Considerations Fall, 2017 Ann Johnson,...
Transcript of Overview - Minnesota LTAP€¦ · 1 Section 5 Construction Considerations Fall, 2017 Ann Johnson,...
1
Section 5
Construction Considerations
Fall, 2017
Ann Johnson, PE Services
Brady Rutman, SRF Consulting Group
Construction Overview
Overview
• Pedestrian Curb Ramp Construction– Standard Plans
– Grade Breaks
– Landings
– Removals
– Curb & Gutter
– Detectable Warnings
– Finishing
– Roundabouts and Median Islands
• Driveway and Sidewalk Construction
– Doorway Landings
2
Curb Ramp Construction
Standard Plans Legend
3
Curb Ramp Construction
Standard Plans
Indicates pedestrian ramp slope shall be between
5% minimum and 8.3% maximum in the direction
shown and the cross slope shall not exceed 2%.
4
S
Landing
S
S
2
Curb Ramp Construction
Standard Plans Indicates pedestrian ramp slopes shall be greater
than 2% and less than 5% in the direction shown
and cross slope shall not exceed 2%.
5
F
Landing
S
S
F F
Curb Ramp Construction
Grade Breaks:
• Specifications for Construction 2521.3D2
• Provide vertical and straight joints parallel with or at right angles to the walk centerline
• Align joints with joints in adjoining work when possible
6
Curb Ramp Construction
Grade Breaks
• All grade breaks within the PAR shall be perpendicular to the path of travel ( See Notes Standard Plans sheets 1 & 2).
7
Curb Ramp Construction
Landing Construction• Standard Plans Sheets 1&2
• To ensure initial ramps and initial landings are properly
constructed, landings shall be cast separately
8
3
Curb Ramp Construction
9
Landing Construction• Follow sidewalk reinforcement detail
Curb Ramp Construction
Landing Construction:
• Fan Ramp: Separate Landing with sidewalk reinforcement
10
Curb Ramp Construction
• Table curb if necessary. Determine controlling elevation (usually lowest elevation) and set at 7%.
11
7%
Curb Ramp Construction
Special Provisions Prosecution of Work (1803)
3) After the curb has been correctly poured, the Contractor has set the
sidewalk forms, and prior to placing the concrete curb ramps/sidewalks,
the Contractor shall verify the requirements in S-1.1B will be achieved.
In addition, the longitudinal slopes shown in the Construction Plans
and the Standard Plans shall be utilized unless these conditions cannot
be met. The starting point for setting the forms on the controlling ramp
leg should be the following:
Steep (S) = 7%
Flat (F) = 4%
Landing = 1.5%
Sidewalk Cross Slope = 1.5%
Fan ramp = 4%
12
4
Curb Ramp Construction
• Verify ramp length, landing dimensions, push button location, and perpendicular grade breaks.
13
7%
Landing
Curb Ramp Construction
• Verify landing is connected to the PAR with perpendicular grade breaks.
14
7%
Landing
Curb Ramp Construction
• Establish both landings with perpendicular grade breaks, verify second ramp is between 2% and 5%.
15
7%
Landing
2-5%(F)
Landing
(F)
(S)
Curb Ramp Construction
• Whenever possible set grades to work within concrete
finishing tolerances.
16
7%
1%4%
1.4%
5
Curb Ramp Construction
17
(S)
(F)
(F)(S)
4” curb
• Use Steep and Flat slopes to help match into surrounding topography and maintain positive boulevard drainage.
Curb Ramp Construction
• When placing curb, check the plan for secondary landings
and adjust top of curb to match landing grades.
18
(S)
Curb Ramp Construction
• When placing curb, check for doorways, steps, bus stops, or
any other features that requires a landing at the back of curb
19
Curb Ramp Construction
20
Ramp Gutter Flow lines
Min. 0.5% Min. positive flow
Max. 2.0% Max. 2%
Preferred 1% Preferred 1%
ADA Preferred Construction Cross Slopes
6
Curb Ramp Construction
V-Curb• Note (3): Edge between new v-curb and in-place structure
shall be sealed and bond breaker shall be used between
existing structure and placed v-curb.
21
Curb Ramp Construction
Removal Limits
• The contractor shall use the appropriate ramp details in the plan and identify the removal limits for sidewalk and curb and gutter.
22
Curb Ramp Construction
Removal Limits
• If the Contractor determines the removal limits are not adequate to meet PROWAG / MnDOT specifications the Contractor shall stop work on that quadrant immediately and consult the Engineer.
23
Curb Ramp Construction
Removal Limits
• Landings required if the approaching sidewalk is inverse grade, also avoid “Tenting” of sidewalk.
24
7
Curb Ramp Construction
Removal Limits• The transition panels cross slope corrections should be 1 linear Ft. of
sidewalk per 0.5% per of cross slope. When PAR width is greater than 6’ or over 5% running slope double the calculated transition length.
25
Example: A transition panel from in place sidewalk with 4.5% cross slope, to new sidewalk at 1.5% cross slope = 6 Linear Ft.
1.5%
4.5%
Curb Ramp Construction
Removal Limits
• If a secondary landing is necessary, check to see if a transition panel will also be needed to make the landing compliant.
26
LandingLanding
Transition
Panel (S)
Curb Ramp Construction
Removal Limits
• Verify removal limits will provide positive drainage as well as maintain existing drainage patterns.
27
Curb Ramp Construction
Removal Limits
• Once the Engineer and Contractor reach agreement on how to proceed the contractor may finish removals.
28
8
Curb Ramp Construction
Curb and Gutter
• Do not overlay PAR curb and gutter.
• New gutter face/flow line must match new road surface (See Standard Plans Sheet 3, note 7)
29
Curb Ramp Construction
Curb and Gutter
• 13% is the maximum rollover allowed.
30
Curb Ramp Construction
Curb and Gutter• Standard Plans Sheet 3, Note 3: For curb machine
placements start gutter slope transitions 10’ outside of all
curb ramps.
31
Curb Ramp Construction
Curb and Gutter
• When constructing directional ramps, the “triangular” concrete piece per MnDOT Standard Plans should be pouredintegral with the curb and gutter (directional curb).
• Maintain positive flow
32
2-3%
9
Curb and Gutter
• Flow Line Profile Alterations, Mill & Overlay Projects
• “Tabling” - maintaining a cross slope of 2% or less within a crosswalk. Required when a roadway is in a stop/yield condition and flow line exceeds 2% slope (and project scope allows)
Curb Ramp Construction
33
Curb Ramp Construction
34
Curb and Gutter
• Flow Line Profile Alterations, Mill & Overlay Projects
• “Raising” - elevating the curb line enough to allow compliant ramps in vertically constrained areas.
Elevation Match point
Curb Ramp Construction
Curb and Gutter
• Bituminous patching on ADA stand-alone projects 1.0% min. – 5.0% max.
35
Curb Ramp Construction
Curb and Gutter
• The contractor shall construct a contraction joint through the curb and gutter section at the bottom of the curb height transition at zero height curb (MnDOT 2531).
36
10
Curb Ramp Construction
Curb and Gutter: Adjustments• Special Situations: “Maximum Extent Feasible”
37
5% Gutter
Output.
Curb Ramp Construction
Curb and Gutter: Adjustments• Special situations: “Maximum Extent Feasible”
38
5% Gutter outflow Landing
Curb Ramp Construction
Detectable Warnings (Truncated Domes)
• Purpose of domes is to inform the user that they are at the edge of the roadway.
• Directionality only works in certain circumstances.
• Directionality should be done only when it works.
• Directional ramps are more difficult to construct with APS criteria.
39
Curb Ramp Construction
40
Detectable Warnings
(Truncated Domes)
• Standard Plate 7038A
• Includes both rectangular and radial
• Radial detectable warnings must accommodate existing radius dimensions to nearest 5’ increment
11
Curb Ramp Construction
Detectable Warnings
• Detectable Warning Surface shall contrast visually with adjacent gutter, roadway, or walkway, either a light-on-dark or dark-on-light.
41
Curb Ramp Construction
Detectable Warnings• (2531) The truncated domes shall be placed in concrete and
shall be pressed firmly into the concrete to the point that
concrete fills the vent holes on the truncated dome plates.
42
Result of domes not installed correctly.
Curb Ramp Construction
Detectable Warnings
• Good detectable edge with not so good placement. (Always check for structures in the PAR)
43
Curb Ramp Construction
Detectable Warnings
• Curb tapers are considered detectable edge when the taper starts within 3” of the edge of the truncated domes.
• Maintain a 2’ continuous detectable edge.
44
3” No step through gaps
12
Curb Ramp Construction
Detectable Warnings• Recommendations from NCHRP
(National Cooperative Highway
Research Program)
• Where slip ramps “T” into trail:
Place domes at top of ramp
• Where trail starts/ends at roadway:
Place domes in the direction of travel
45
Curb Ramp Construction
Construction Finishing
• Spec 1503 Conformity with Contract Documents
• If the Contract requires a maximum or minimum dimension or value, the Contractor shall control the production and processing of the material and the performance of work so that the material or workmanship is not of borderline quality or dimension.
• Spec 2521.3D The Engineer will use a 10” straight edge to measure the surface.
46
Curb Ramp Construction
Construction Finishing• Spec 2521.3D The department considers deviations in the
surface greater than 3/16 inch and deviations in formed concrete greater than ½ inch from the required location as unacceptable work.
47
Curb Ramp Construction
Construction Finishing• Spec 2521.3D The department considers deviations in the
surface greater than 3/16 inch and deviations in formed concrete greater than ½ inch from the required location as unacceptable work.
48
13
Curb Ramp Construction
Construction Finishing• Spec 2521.3D Remove and replace unacceptable work as
directed by the Engineer.
49
Curb Ramp Construction
Construction Finishing• Joint Construction: Spec. 2521.3D2 The Contractor may
form or saw the joints in walking surfaces as approved by the
Engineer.
50
Curb Ramp Construction
Construction Finishing
• Joint Construction: Spec 2521.3D If forming the joints, round joints within the walking surface with a with a ¼ inch radius edge grooving tool.
51 52
Driveway & Sidewalk ConstructionStandard Plans – Sheet 1
14
53
5’ PAR
Driveway & Sidewalk Construction
Driveways• Commercial Apron Slope:
10% Max (8% Max Preferred)
• Residential Apron Slope:
12% Max (8% Max Preferred)
• PAR Width: 4’ Min (5’ Preferred)
• Try all options to maintain 5’
54
1.5%
8%
Driveways• Maximize apron slopes
when driveway match-in
elevations are higher
than roadway elevations
Driveway & Sidewalk Construction
55
Driveway & Sidewalk Construction
Driveways• Back of curb heights
• DW Curb Standard: 1”
• DW Curb Type 2
(Vertically Constrained): 2”
• DW Curb Type 3
(Vertically Constrained): 3”
56
Doorway Landings
• Note 3) 6’ Min. PAR required
when adjacent to buildings.
• Note 4) 2/3 PAR to 1/3 Boulevard
should be used when feasible.
• Note 7) To minimize vibration
and rolling resistance, area
should be free of pavers,
stamped concrete, and/or
excessive jointing.
Driveway & Sidewalk Construction
15
57
Driveway & Sidewalk Construction
Doorway
Landings2% ramp was constructed with landing lower than top of curb.
58
2.0%
Construction: Lessons Learned
• Curb ramp is compliant, but it fits poorly into its surroundings,
and will be difficult to maintain.
59
2%
Landing2%
2%
Construction: Lessons Learned
• Slopes shown are preferred and side slopes could have been grade flush, thus eliminating V-curb.
60
2%-5%
Landing7%
2%-5%
Construction: Lessons Learned
16
Alternate Pedestrian Access Routes
61
APAR Layouts in the MN MUTCD
62
2014 Temporary Traffic Control Zone Layouts Field Manual
Alternate Pedestrian Access Routes