Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been...

58
September 21, 2016 Oversight Committee

Transcript of Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been...

Page 1: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

Oversight Committee

Page 2: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

AGENDA

As required, please be advised that a copy of the rules of the Open Meeting Act as amended is located in the folder on the north wall of Jesse Lowe Conference Room and assistance will be provided for anyone needing help.

●●●

○■

○○

■○○○

■■

○○○

●○○

●●●

Page 3: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

IT Service Management(Julie Stangl)

Page 4: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

2018 Cost Model

Project progressing as planned. Creation of 2018 Budget is underway; Allocation metrics collected for Aug. 31.

Page 5: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

2016 Hours by CategoryTime spent by category has only fluctuated

slightly throughout the year

Page 6: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

The split of DOTComm direct support hours between the City and County for August was 38% / 62%, and 43% / 57% for the year*

Direct Support Hours Allocation

* vs. the 2015 cost model split of 46% City / 54% County

62%

43%

57%

38%

Page 7: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 2016

1. Service Maturity - Current State

2. Operational Performance - PMO Functions & KPIs

3. Competitiveness - Ranking our structure, functions,& performance to similar organizations

Project Management Office (PMO) Benchmark - Overview

Page 8: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 2016

PMO - Org Structure

Director, Business Services(PMO, Finance, HR)

Tracy Svevad

PMO/Project Manager

Kelly Gray

IT Project Manager

Randy Pauley

IT Project Manager

John Rivera

PM Responsibilities*Bavitha Govindarajulu

Steve JacobsenJason HainesSean Powers

*Dotted line accountability to the PMO for project management process & execution

Purpose StatementEnsure project alignment to strategic plans and consistently deliver

high quality outcomes on schedule, budget and scope.

Page 9: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 2016

Project Management Office - Service Maturity

● Maturity Assessment Completed - Project & Portfolio Management ○ 44 Questions○ 5 Domains○ 29 Participants

● Created a maturity baseline○ Shows links between desired changes and improvement efforts○ Supports on-going conversations about our PPM capabilities

Sample question

Page 10: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 2016

Project Management Office - Service Maturity

Page 11: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 2016

People(2.95) Closing in on Level 3: Defined - Initial Integration. At this level of maturity we are increasingly managing complex projects and programs in-house. The role of a PPM leader becomes more defined. Project staffing/resource capacity issues begin to be addressed.

PPM Process & Practice(2.94) Closing in on Level 3: Defined - Initial Integration. At this level of maturity we have established project delivery processes. The PMO is a recognized part of the organization. Project and portfolio risks are reviewed. Project proposals begin to be approved on a portfolio basis.

Financial Management (2.33) Squarely in Level 2: Developing - Emerging Disciple. At this level of maturity projects have budgetary estimates. Actual costs are estimated. Some project proposals include benefit statements.

Technology (2.06) Arriving at Level 2: Developing - Emerging Disciple. At this level of maturity project scheduling tools and milestone reporting are adopted. The need for project collaboration spaces intensifies. The recognition that enhanced capabilities to detect cross-project relationships emerges.

Relationships (2.74) Moving towards Level 3: Developing - Emerging Disciple. The role of the relationship manager emerges. IT and the business attempt to work together to improved communications via the relationship manager, business analysts and project manager updates. The efforts exerted at this level is to be viewed as trusted advisors.

Reference Materials - PPM Assessment Definitions

Page 12: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

Gartner PPM Maturity Model

Page 13: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 2016

PMO - Functional Areas

Project Management● Project Managers ● Process Improvements● Standards

Portfolio Management● Strategic Alignment ● Governance Support

Performance Reporting● Project tracking● Metrics Collection

PM Development● Community of Practice● Coaching/mentoring

PMs

PMO

Page 14: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 2016

PMO - Functional Areas - KPIs

Project Management● # of process improvements

implemented● % of overdue tasks

Portfolio Management● % of projects aligned with

strategic objectives● % of high priority projects fully

resourced

Performance Reporting● % of closed projects within hours

and duration variance targets● % of projects completed on time

PM Development● # of community of practice

sessions conducted● % of PMs that are certified

Project Management Professionals (PMP)

PMO

Page 15: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

Projects - Completed 2Q 2016

Page 16: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 2016

PMO - Competitiveness

Structure

Functions

Performance

● % PMO/PM Staff to IT Budget and/or Total Budget

● PM Turnover Ratio - 0 (Since Jan 2016)

● PM Hourly Rates● % Hours on Project Mgmt Duties (80% for

Full-Time PM’s)

● Ratio of PM hours to Total Project Hours● % Project Delivered that Meet Customer

Expectations

Page 17: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

Projects(Tracy Svevad)

Page 18: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

April 20, 2016

Project Bucket Hour SummaryAt the end of August, total project hours were at 80% of

forecast, significantly ahead of projections.

County = 30 Projects

GTL = 313 HD Health Data Website = 225 BOE = 199 Assessor / ROD:Landmark = 107

Shared = 15 Projects AWS Migration = 497 Oracle OBIEE Reporting = 361 Salesforce = 384

2,775 (8%) City = 19 Projects

OCVB Move = 173 OPD Video Storage = 99 Fin ECM Phase 2 = 76

3,310 (10%)

3,861 (11%)

3,196 (9%)3,109

(9%)

3,507 (10%)

3,215(10%)

3,952(12%)

Page 19: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

Projects Update

County Shared City

2016 Total Forecast Bucket Hours:

9,302 11,865 12,531

YTD Bucket Hour Actuals: 6,290 10,533 10,102

% Bucket Hour Actuals: 68% 89% 81%

Project Bucket Hour Summary by Portfolio YTD - thru August 2016

Page 20: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

Pending = Pending Initiation which is generally due to resource constraints (excludes Pending Project Requests)

Projects - Summary

Page 21: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

Pending = Pending Initiation which is generally due to resource constraints (excludes Pending Project Requests)

Projects - Summary

Page 22: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

Projects Update - Shared Services Portfolio

Active Phase Highlights Status

Amazon Web Migration Executing & Controlling

Several dates have moved due to Customer resource availability for testing. Continuing to move forward by starting work on other websites.

Oracle OBIEE Reporting Executing & Controlling

Work continues on reports. Reports are migrated to production as they completed and accepted.

SQL/Infrastructure Upgrade Executing & Controlling

No new completions from the last report. Good work continues on planning w/several scheduled to be completed this next month.

Windows 2003 Server Upgrades and Decommissioning

Executing & Controlling

Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery.

Faster Upgrade Executing & Controlling

Vendor continues to build the installer package.

City/County Attorney - CMS upgraded for NE eFiling

Planning Vendor continuing to work on the coding for eFile.

2018 Cost Model Planning Review of cost model allocations completed with only minor changes. Inventories are being gathered and DOTComm budget is in-progress.

Oracle Testing Suite Implementation

Initiation AP script is completed and the AR script is in process.

Enterprise Security Enhancement (RFP)

Planning Project Charter completed and approved. Kick-off meetings with stakeholders are being held. RFP is tentatively scheduled to go out by the end of the year.

Page 23: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

Amazon Web Migration (2015-2018)Project Manager: Bavitha Govindarajulu

Page 24: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

CIP Project Updates - SQL UpgradeProject Manager: Kelly Gray

In Planning

County Applications:● eJurer● Airvision● ANSOS● Victim CMS● Corr - Access DB’s● Atty Payment● Saddlebrook

City Applications:● SEB App● Fuelmaster● PW Inhouse App● Foray● Maximo● Accela● FlowLink● US Bank Card

Shared Applications:● 2 Virtual Servers● Picture Link● Faster

Page 25: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

Salesforce Program Manager: Julie Stangl

Phase 1 of the CMDB recently Closed; Service Cloud project on track for October launch.

Page 26: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

Shoretel VoIP Projects UpdateProject Manager: Randy Pauley

Page 27: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

Projects Update - Douglas County PortfolioActive Phase Highlights Status

DC County Clerk VoIP Closing Project completed.

GTL Implementation Executing & Controlling

Vendor is upgrading hardware/OS/database environment. DOTComm providing support as needed and requested.

ECM - Land Book Scan & Store

Executing & Controlling

Preparing closing documents and reviewing final invoices. Project should be closed by next meeting.

Health Data Website Phase 2 (DCHD)

Executing & Controlling

Client user acceptance testing has started. DOTComm QA also in process.

DCSO-Records Mgmt Executing & Controlling

Scheduled go-live is being set for March 2017 with the vendor and DCSO assigning resources to meet that date.

DCROD-Landmark Implementation

Planning Working on image storage solution and loading of images from Filebound to the internal new storage service.

DCTRES - Oracle Treasury Implementation

Initiating Continuing to discuss roles and responsibilities with customers.

DC Youth Center VoIP Planning Charter completed and approved. Planning and ordering equipment is underway. Tentatively scheduled for an early November implementation.

Additional Active Projects Various Phases

Includes several year-end projects, Court Room 50, 2016 Open Enrollment, and HD File Server Replacement.

Page 28: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

Projects Update - City of Omaha PortfolioActive Phase Highlights Status

CIPW-Fleet Mgmt VoIP Closing Phone system deployed.

OCVB Move Executing & Controlling

VoIP migration completed. PC’s moved and being installed. Project will be closing within the next couple of weeks.

CiPlan - EPA Superfund Executing & Controlling

Continuing to make changes and adjustments to application as requested by customer.

CIHR&R CC1 Online Form Submission

Executing & Controlling

Resolving technical issue with loading some code for Filebound.

CIHR&R-SEB Enhance Executing & Controlling

Customer has requested to perform another full User Acceptance Testing prior to going live. Targeting early October for completion.

CIOPD - Video Storage Executing & Controlling

Completed full video and image migration testing. OPD validated data. Preparing to go-live in mid-late September.

CIRec/GolfTrac Upgrade Executing & Controlling

User training has started on schedule. Working through some technical connectivity issue with user provisioning and load balancing.

CIFIN-Phase 2 Invoice Process in Filebound

Executing & Controlling

POC completed successfully. Actively working with five departments on implementation. Completing site surveys for remaining departments.

Page 29: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

Capital Improvement ProjectsUpdate(Bob Nord)

Page 30: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

2016 Capital Status

Requesting approval for the items in red below last June

Page 31: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

EXPENDITURES

Quote 2016 2017 2018 DESCRIPTION CATEGORY

Microsoft Renewals $79,370.61 $21,646.53 $28,862.04 $28,862.04

Software Assurance Renewals for Active

Directory and SCCM with Operational User licenses Security and User Productivity

Microsoft Renewal $147,636.06 $51,034.72 $51,034.72 $45,566.62

Server Datacenter licensing for virtual server

environment Application Modernization

VM License Renewals $165,649.53 $55,216.51 $55,216.51 $55,216.51

VMWare Licensing for virtual server environment Application Modernization

Total $392,656.20 $127,897.76 $135,113.27 $129,645.17

Estimated Capital Requested/Approved $152,222.00 $152,222.00 $152,222.00

Summed total from licensing renewals attributed to Security, User Productivity and Application Modernization ($5,500, $32,667 and $114,055 respectfully)

Remaining Balance $24,324.24 $17,108.73 $22,576.83

2016 Capital StatusJune Approvals

● Storage Maintenance● Network Hardware Routers and Switches Maintenance and Refresh● Second Core Switch● Java Upgrade

4Q - Anticipated Submissions for Approval:

Page 32: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

Operations Update(Bob Nord)

Page 33: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

Tech Center Hosting Total Invoiceable: 7

Operations Service Update

MF Operations

● MF upgrade and update efforts○ Preparing to replace the z114 with a

zBC12 - 46MIPS to 50MIPS ○ Replaced obsolete HW and

Eliminate Physical Tape○ Upgrade OS

● PSeries update and upgrade efforts○ Replace obsolete HW and

Eliminate Physical Tape○ Move second Pseries to Lincoln

● Analysis of Pseries Database Needs● Analysis of MF Applications

Page 34: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

IT Service Management Update

Incidentand

Service RequestSLAs

Page 35: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

Operations Service Update

AugustPriority 2Service Outages

Ticket Summary

*Breached SLA

➢ 172535 ShoreTel - Lost Outbound Dialing - Cox Service Restored

Page 36: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

Incident Resolution SLA by Priority

Page 37: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

May 2016

Service Request Resolution by Priority

Page 38: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

May 2016

August Ticket Summary - P3

Page 39: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

May 2016

August Ticket Summary - P4

Page 40: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

May 2016

August Ticket Summary - P5

Page 41: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

Tech Support Statistics and Customer Satisfaction Survey

Results

Page 42: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

May 2016

Tech Support Call Statistics

August

Average Speed of Answer 19 Seconds

Average Call Duration 5:35 (Min:Sec)

Page 43: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

May 2016

Tech Support Call Statistics

Weekdays Monday - Friday 6PM - 6AM

Calls Accepted

Calls Answered

Abandoned Calls

Longest Wait Time in Queue

Avg Duration of Calls

Longest Call

Avg Hold Time

99 95 4 5:55 4:19 21:051 0:04

Weekends Friday 6PM - Monday 6AM

Calls Accepted

Calls Answered

Abandoned Calls

Longest Wait Time in Queue

Avg Duration of Calls

Longest Call

Avg Hold Time

118 114 3 27:07 5:12 27:57 1:21

Extended Hours - August

Page 44: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

May 2016

Customer Satisfaction Survey Results

August

Incident Survey Response Rate at 27.3%

Service Request Survey Response Rate at 26.1%

Industry Survey Response Rate

Page 45: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

Applications SupportServices Update(Vijay Badal / Tom Olson)

NO UPDATE FOR SEPTEMBER

Page 46: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

IT Security

(Greg Andersen)

Page 47: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

IT Security - September Update

Compliance Update▪ Project 1762: Security Enhancements RFP

▪ Charter drafted and signed by steering committee

▪ Kickoff meeting with stakeholders hosted at DOTComm

▪ Currently in requirements gathering phase

▪ Next step is creating a draft RFP and limiting scope

▪ On-track

Cyber Security Awareness Month (next month!)▪ Poster and Calendars

▪ Quick FYI Emails with Social Media and Website Updates

▪ Cyber Security Speaker at DOTComm Tech Fair - Kevin Russell from Sirius

▪ An interactive activity for the departments, that will be educational and fun

Upcoming Policy▪ Draft new policy created for data destruction

▪ Reviewing with peers and departments that use DOTComm’s policy▪ Will have up for approval next month

Page 48: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

Financials(Tracy Svevad)

Page 49: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

Financials - Operating Income Statement

Page 50: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

Financials - Funds Restricted for Capital

Page 51: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

Financials - Outstanding Receivables

.

Page 52: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

Financials - Cash Projections

Page 53: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

Financials - Chargebacks 2016 (as of 09/09/2016)

Page 54: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

Organizational Update

(Derek Kruse)

Page 55: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

New Business

Page 56: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

2017 Tech Fair

Page 57: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

2017 Proposed Oversight Meeting Calendar

Page 58: Oversight Committee · Customer apps/servers are in progress. 77 of 146 servers have been completed. Four (4) servers remain that need research / discovery. Faster Upgrade Executing

September 21, 2016

▪ PUBLIC COMMENTS

▪ NEXT MEETING: October 19, 2016 @ 2:30 p.m. in Jesse Lowe Conference Room

▪ ADJOURN (to Executive Session as needed)