Outline - Telsoc · 4/28/2015  · Mobile Cellular Small Cells Macrocells using 700MHz out to 35km...

37
8/9/2014 (C) Mark A Gregory 1 National Broadband Network by Dr Mark A Gregory FIEAust, SMIEEE A nation building project Outline 8/9/2014 (C) Mark A Gregory 2 1 National Broadband Network 2 Technologies 3 Alternate Technologies 4 NBN related issues 5 Universal Service

Transcript of Outline - Telsoc · 4/28/2015  · Mobile Cellular Small Cells Macrocells using 700MHz out to 35km...

  • 8/9/2014

    (C) Mark A Gregory 1

    National Broadband Network

    by Dr Mark A Gregory FIEAust, SMIEEE

    A nation building project

    Outline

    8/9/2014 (C) Mark A Gregory 2

    1 National Broadband Network

    2 Technologies

    3 Alternate Technologies

    4 NBN related issues

    5 Universal Service

  • 8/9/2014

    (C) Mark A Gregory 2

    National Broadband Network

    There can be no greater goal today, for this nation, than to strive to

    become a leader in the global digital economy and when this is

    achieved to maintain this position in the decades to come.

    A National Broadband Network that utilises FTTP, Wireless and

    Satellite to connect Australians to the NBN is an instrumental

    requirement if this nation is to succeed.

    8/9/2014 (C) Mark A Gregory 3

    History

    NBN I – 2007 - FTTN

    NBN II – 2009 – FTTP 93%, wireless+satellite 7%

    NBN III – 2014 – FTTN, FTTdp, HFC, FTTP,

    wireless+satellite

    8/9/2014 (C) Mark A Gregory 4

  • 8/9/2014

    (C) Mark A Gregory 3

    What is the NBN really about?

    The NBN is about more than connection speed.

    • Connection speed

    • Capacity – NBN, national and international

    • Traffic Class Management

    • Congestion – peak hour

    • Staying ahead of our competitors – global digital economy

    8/9/2014 (C) Mark A Gregory 5

    Definitions

    CIR – Committed Information Rate defines a level of data throughput for

    which service frames are delivered according to the performance

    objectives of the applicable traffic class.

    PIR – Peak Information Rate is defined as the maximum data throughput

    that may be delivered by the service. Note that traffic capacity in excess

    of the CIR and within the PIR will be carried through the NBN Co

    Network without any performance objectives. Traffic that exceeds the

    PIR will be discarded at ingress to the NBN Co Network.

    8/9/2014 (C) Mark A Gregory 6

  • 8/9/2014

    (C) Mark A Gregory 4

    Definitions - Costs

    “Access Virtual Circuit” (AVC), which identifies a customers traffic within the NBN – AVC is

    one cost

    Access Seekers purchase a “Connectivity Virtual Circuit” (CVC) for each Connectivity

    Serving Area they wish to cover. The CVC is essentially a bandwidth pipe, the size

    determined by the cost. The larger the CVC, the better the service to subscribers within the

    Connectivity Serving Area – CVC is another cost

    Access Seekers connect to NBN PoIs and there is a monthly charge for every PoI

    connection and an initial one off charge for every PoI connection

    And now there are green field and Fibre on Demand costs

    8/9/2014 (C) Mark A Gregory 7

    Technologies

    Fixed Line

    Fixed Wireless

    Satellite

    8/9/2014 (C) Mark A Gregory 8

  • 8/9/2014

    (C) Mark A Gregory 5

    Source: NBN Co

    8/9/2014 (C) Mark A Gregory 9

    121 Points of Interconnect

    Transit

    Minimum of two backhaul

    providers at each PoI

    At some PoI backhaul

    providers are Telstra and

    government

    Source: NBN Co

    8/9/2014 (C) Mark A Gregory 10

  • 8/9/2014

    (C) Mark A Gregory 6

    Fibre

    Source: Schink, H.

    8/9/2014 (C) Mark A Gregory 11

    Long Reach PON

    Source: R Ram, MIT

    8/9/2014 (C) Mark A Gregory 12

  • 8/9/2014

    (C) Mark A Gregory 7

    PON Trends

    Source: Kani and Davey, NTT

    8/9/2014 (C) Mark A Gregory 13

    Passive Optical Network – Active Architecture

    8/9/2014 (C) Mark A Gregory 14

  • 8/9/2014

    (C) Mark A Gregory 8

    Network Termination Unit

    Source: Alcatel Lucent

    8/9/2014 (C) Mark A Gregory 15

    Property Connection Point

    Source: NBN Co

    8/9/2014 (C) Mark A Gregory 16

    http://www.computerworld.com.au/article/352822/coming_wall_near_meet_nbn_ont

  • 8/9/2014

    (C) Mark A Gregory 9

    Distribution Network

    Source: NBN Co

    8/9/2014 (C) Mark A Gregory 17

    8/9/2014 (C) Mark A Gregory 18

    http://www.nbnco.com.au/wps/wcm/connect/80c0d68043a2015c8d09fdc5166da634/Network_and_Operations_Information_Session_Presentation.pdf?MOD=AJPERES&CACHEID=80c0d68043a2015c8d09fdc5166da634

  • 8/9/2014

    (C) Mark A Gregory 10

    8/9/2014 (C) Mark A Gregory 19

    8/9/2014 (C) Mark A Gregory 20

  • 8/9/2014

    (C) Mark A Gregory 11

    8/9/2014 (C) Mark A Gregory 21

    Point of Interconnect to Premises

    8/9/2014 (C) Mark A Gregory 22

  • 8/9/2014

    (C) Mark A Gregory 12

    Cabinet and pit

    Source: NBN Co

    8/9/2014 (C) Mark A Gregory 23

    Copper Advances

    But the length gets shorter and

    shorter and shorter….

    Source: newelectronics

    8/9/2014 (C) Mark A Gregory 24

  • 8/9/2014

    (C) Mark A Gregory 13

    FTTN with VDSL2

    Source: AT&T

    8/9/2014 (C) Mark A Gregory 25

    VDSL2 Vectoring

    Copper pairs from one cable cannot be connected to different ISAM

    8/9/2014 (C) Mark A Gregory 26

  • 8/9/2014

    (C) Mark A Gregory 14

    FTTdp Architecture

    Source: itNews

    8/9/2014 (C) Mark A Gregory 27

    8/9/2014 (C) Mark A Gregory 28

    http://www.google.com.au/url?sa=i&source=images&cd=&cad=rja&uact=8&docid=-_2_LwonzguB_M&tbnid=OGnVBnOFz-RQDM:&ved=0CAgQjRw&url=http://www.itnews.com.au/News/348820,copper-broadband-beats-1gbps-speeds-in-trial.aspx&ei=K9cOVIuSNpX48AWC04CIAQ&psig=AFQjCNHrNbK61KY95mZ63CXUJNfsWC0y6Q&ust=1410345131994393

  • 8/9/2014

    (C) Mark A Gregory 15

    Hybrid Fibre Coax

    Source: linebroker.co.uk

    8/9/2014 (C) Mark A Gregory 29

    Fixed Wireless Block Diagram

    Source: NBN Co

    8/9/2014 (C) Mark A Gregory 30

  • 8/9/2014

    (C) Mark A Gregory 16

    Fixed Wireless

    2.3 GHz spectrum – not as good as 700 MHz for regional

    use

    http://web.acma.gov.au/pls/radcom/client_search.client_lookup?pCLIENT_NO=1104329

    http://web.acma.gov.au/pls/radcom/client_search.client_lookup?pCLIENT_NO=8129031

    8/9/2014 (C) Mark A Gregory 31

    Fixed Wireless eNodeB Base Station

    Each eNodeB has three sectors and is sited according to a site specific radio

    coverage plan to provide optimised coverage.

    Each sector supports on average 60 premises, with an approximate CIR for the

    eNodeB of 100Mbps.

    • 3 RF Antennae

    • GPS Antenna

    • Remote Radio Unit

    • Digital Baseband Unit

    • Power Supply

    • Battery Backup

    8/9/2014 (C) Mark A Gregory 32

    http://web.acma.gov.au/pls/radcom/client_search.client_lookup?pCLIENT_NO=1104329http://web.acma.gov.au/pls/radcom/client_search.client_lookup?pCLIENT_NO=1104329http://web.acma.gov.au/pls/radcom/client_search.client_lookup?pCLIENT_NO=8129031http://web.acma.gov.au/pls/radcom/client_search.client_lookup?pCLIENT_NO=8129031

  • 8/9/2014

    (C) Mark A Gregory 17

    Fixed Wireless Microwave Transit

    Source: NBN Co

    8/9/2014 (C) Mark A Gregory 33

    Fixed Wireless Aggregation

    The three sectors of an eNodeB (maximum of 180 end users) typically

    provide an aggregated CIR throughout of approximately 100 Mbps. This

    determines the Microwave Transport backhaul capacity required.

    The maximum bandwidth planned for the Microwave Hub Site back to a FAN

    site is 900Mbps, allowing for the aggregation of up to 8 eNodeBs, with a

    maximum of 1440 end users.

    Source: NBN Co

    8/9/2014 (C) Mark A Gregory 34

  • 8/9/2014

    (C) Mark A Gregory 18

    Fixed Wireless Serving Area

    The largest WSA will have up to 24 WSAM connecting to

    a FAN.

    8/9/2014 (C) Mark A Gregory 35

    Fixed Wireless Access Aggregation Region

    The third module is the Access Aggregation Region (AAR). The

    wireless area served by a single POI is an AAR. The maximum

    number of WSAs in an AAR is determined by the number of FANs

    that connect back to the POI. For the purposes of wireless

    dimensioning, the size of an AAR is based on the maximum number

    of end users, rather than the maximum number of WSAs, with a

    maximum of 25000 end users in an AAR.

    8/9/2014 (C) Mark A Gregory 36

  • 8/9/2014

    (C) Mark A Gregory 19

    Satellite Block Diagram

    Source: NBN Co

    8/9/2014 (C) Mark A Gregory 37

    Satellite NTD

    The ODU key components include: • Parabolic satellite terminal antenna

    • Ka-Band VSAT transceiver

    • Interface to the IDU

    The IDU key components include: • 4 UNI-D ports,

    • Layer 2 Ethernet Switch

    • Embedded Transparent Performance Enhancing Proxy (TPEP) software client

    • Interface to the ODU

    A standard AC power supply is used to power the IDU and through that the ODU

    8/9/2014 (C) Mark A Gregory 38

  • 8/9/2014

    (C) Mark A Gregory 20

    Satellites

    NBN Co is building two, multi-spot beam, geostationary, "bent-pipe”, Ka-band,

    telecommunications satellites for the Satellite Access Solution with the following

    characteristics:

    Two satellites to enable service redundancy and load balancing of users.

    Multi-spot beam design on each satellite enabling 70Gbps forward path and

    20Gbps return path system capacity to best support the regional and remote

    Australian population and utilise the optimum broadband user experience from

    the amount of RF spectrum available.

    8/9/2014 (C) Mark A Gregory 39

    Satellite Spot Beams

    Source: NBN Co

    8/9/2014 (C) Mark A Gregory 40

  • 8/9/2014

    (C) Mark A Gregory 21

    Satellite RF Gateways

    To achieve the optimum RFGW trunk link performance, the following design criteria are optimised:

    • Maximum gateway to gateway geographical separation,

    • Location of gateways away from projected user high density areas,

    • Services available at gateway locations (highly reliable power, transit network connectivity,

    ACMA TX and RX license approvals, Australian security agency approvals, etc)

    • Gateway to User beam RF interference characteristics

    • Frequency and polarity reuse strategy for gateway and user beams,

    • the satellite’s antenna specifications and RF filter design capabilities, and

    • the VSAT system’s advanced RF channel adaptive power management and modulation

    schemes.

    8/9/2014 (C) Mark A Gregory 41

    Spectrum and Orbital Slots

    RFGW to Satellite Uplink 27.0 – 28.5 GHz

    Satellite to VSAT Downlink 17.7 ‐18.2 GHz, 18.8 ‐19.3 GHz and 19.7 ‐ 20.2 GHz

    VSAT to Satellite Uplink 28.5 – 29.1 GHz

    Satellite to RFGW Downlink 18.2‐ 18.8 GHz

    RF Auto Tracking Downlink 29.5 – 29.54 GHz

    Uplink Power Control 19.3 – 19.35 GHz

    Designed to operate at the orbital slots of 140 deg E and 145 deg E.

    8/9/2014 (C) Mark A Gregory 42

  • 8/9/2014

    (C) Mark A Gregory 22

    Trends

    Private operator licenses for spectrum are available

    ABS: Aussies spend about 13 hours per week watching

    Television

    For a household with Netflix and a 4K Ultra HD TV a 500-

    600 GB per month plan is recommended

    8/9/2014 (C) Mark A Gregory 43

    Nielsen

    What do we need

    and when?

    8/9/2014 (C) Mark A Gregory 44

  • 8/9/2014

    (C) Mark A Gregory 23

    HFC Trend

    Utilise existing HFC

    What happens after

    DOCSIS 3.1?

    Total upgrade cost is

    unknown

    8/9/2014 (C) Mark A Gregory 45

    Alternate Technologies

    8/9/2014 (C) Mark A Gregory 46

  • 8/9/2014

    (C) Mark A Gregory 24

    Telco and Community Wi-Fi

    NBN should include Wi-Fi, two ATA and 4 Data Ports in NTD

    Source: Telstra

    8/9/2014 (C) Mark A Gregory 47

    Mobile Cellular

    2020 – 5G

    But handsets will support UHD

    Congestion still an issue, so Wi-Fi

    data handoff is important.

    Source: Bilodeau, JDSU

    8/9/2014 (C) Mark A Gregory 48

  • 8/9/2014

    (C) Mark A Gregory 25

    Mobile Cellular Small Cells Macrocells using 700MHz out to 35km cell size – shared towers?

    Small cells for high user numbers – size of cell depends on frequency and transmit power

    pico (200m) femtocells (10-30m)

    Installation Operator Customer

    Transmission to

    operators network Operator Customer

    Frequency Centrally planned Locally determined

    Site rental Operator Customer

    8/9/2014 (C) Mark A Gregory 49

    Telstra RF Network

    Significant national RF microwave

    network

    In some areas being decommissioned

    Can this network be incorporated into

    the NBN to provide additional 100

    Mbps links for various local wireless

    solutions?

    8/9/2014 (C) Mark A Gregory 50

  • 8/9/2014

    (C) Mark A Gregory 26

    Self-Install Fibre

    FTTdp provides options

    Self-install fibre kits available for premises to pits

    FTTdp supports G.Fast as an alternative

    8/9/2014 (C) Mark A Gregory 51

    NBN related issues

    Telstra – wholesale and retail – should Telstra be split?

    Legislation and Regulation

    Multi-Technology Mix (FTTP, FTTB, FTTdp, FTTN, HFC, Fixed Wireless, Satellite)

    Construction

    Backhaul charges

    Universal service

    8/9/2014 (C) Mark A Gregory 52

  • 8/9/2014

    (C) Mark A Gregory 27

    What went wrong?

    Telstra was privatised as one entity – is this the greatest anti-competitive arrangement

    in Australian history?

    Labor had the right idea, but the wrong implementation

    Threatened Telstra with no access to spectrum auction to get 2011 NBN agreement

    and 2012 SSU and put in place government owned NBN Co.

    Should have forced Telstra to own and operate NBN Co from the outset. NBN Co

    would absorb the rest of Telstra wholesale as the SSU was implemented between

    2010 and 2020. In 2020 NBN Co to be separated from Telstra retail in a two for one

    share issue.

    8/9/2014 (C) Mark A Gregory 53

    Teething problems and delays

    1. Telstra agreement

    2. Telstra Asbestos +

    construction interaction

    Source: NBN Co and Rod Tucker

    8/9/2014 (C) Mark A Gregory 54

  • 8/9/2014

    (C) Mark A Gregory 28

    Caused this

    At least a one year delay on initial

    projections. But worse was to

    come in early 2013 before the

    rollout finally gathered steam just

    in time for the September

    election.

    Source: NBN Co and Rod Tucker

    8/9/2014 (C) Mark A Gregory 55

    Yet another delay

    The second Telstra agreement caused another 18-24

    month delay

    And increased the cost of the project significantly over a

    30 year life time

    8/9/2014 (C) Mark A Gregory 56

  • 8/9/2014

    (C) Mark A Gregory 29

    Failed project?

    On Aug 21 iiNet CEO Mr Buckingham said he was “furious”

    about the national broadband network’s slow rollout and

    delayed renegotiations with Telstra.

    “NBN needs to get on with the rollout because we’re sick of

    waiting. They really need to start unleashing the plan they

    keep putting in front of us.”

    Source: AFR Aug 21, 2014

    8/9/2014 (C) Mark A Gregory 57

    Government Intervention

    Knowing when it is time to intervene is an insight

    Knowing how to intervene without making a situation

    worse is a gift

    1997 – 2015 and counting…

    8/9/2014 (C) Mark A Gregory 58

  • 8/9/2014

    (C) Mark A Gregory 30

    Should the government build the NBN?

    What do you think?

    1. Political interference

    2. Election cycle

    3. Lack of vision + ideology

    4. Failure to involve the community

    5. Attacking government regulators to get their way

    8/9/2014 (C) Mark A Gregory 59

    6. Must have a policy difference going into the next election

    7. Failure to consult widely

    8. Adopting a Yes Minister approach by hand-picking review and audit panels

    9. Backloading costs to leave debt for incoming governments

    10. Attacking anyone that does not agree with them

    Should Telcos build the NBN

    Yes.

    1. Telstra SSU completed before 2015

    2. Minimum three backhaul to 36 PoI

    3. Rollout plan to 2025

    4. FTTP, FTTdp, HFC, Wireless, Wi-Fi, Satellite

    8/9/2014 (C) Mark A Gregory 60

    5. 2010 HFC regulated with

    wholesale access

    6. Agreed design with

    Connection speeds, QoS, Traffic Class Management, capacity, congestion, utilisation < 70%

    7. Telstra separated into two

    companies in 2020

  • 8/9/2014

    (C) Mark A Gregory 31

    Key Agreements and Regulation

    2011 NBN Co Telstra agreement – infrastructure, construction?

    2012 Telstra Structural Separation Undertaking - add this to the

    recent structural separation regulation - level playing field?

    2014 NBN Co Telstra agreement - technology?

    Sell NBN Co to Telstra a soon as possible and force Telstra to

    separate into two companies with a one to one share offer?

    Is there the political will to do what the nation needs?

    8/9/2014 (C) Mark A Gregory 61

    Multi-Technology Mix

    Classic argument - overbuild versus incremental upgrade

    Overbuild must have strong technical justification,

    overwhelming RoI for operators and consumer support

    Incremental upgrade is the safe traditional approach that

    minimises risk and maximises RoI for vendors and

    operators but can fall behind consumer expectations

    8/9/2014 (C) Mark A Gregory 62

  • 8/9/2014

    (C) Mark A Gregory 32

    FTTP versus FTTN and HFC

    In 2000 to 2005 FTTN was justified with a 10 year life – copper reaching end of life

    By 2010 FTTN could not be justified as it would fall behind customer expectations well

    before end of life

    HFC remains a justifiable technology that can be replaced by FTTP over time as it becomes

    due for rebuild.

    Consumers demand change - FTTN and HFC are not justified if there is no QoS, traffic class

    management and utilisation < 70%

    2012 NBN Co network design rules released.

    Post Sept. 2013 NBN Co has failed to release updated network design rules.

    8/9/2014 (C) Mark A Gregory 63

    Dump FTTN/VDSL2

    Use FTTdp

    self-install fibre from premises to pit

    G.Fast/Vectoring

    Other technologies

    But really just get on with FTTP in non-HFC areas

    8/9/2014 (C) Mark A Gregory 64

  • 8/9/2014

    (C) Mark A Gregory 33

    Construction

    Classic argument. Create one subsidiary construction

    company for the rollout or outsource.

    NBN Co managing construction directly in Northern Territory

    Construction is not meeting targets everywhere

    There does not appear to be sufficient construction teams to

    meet targets – why?

    8/9/2014 (C) Mark A Gregory 65

    Construction approach

    On-demand connection led to significant problems when

    copper access network was turned off

    Must connect premises immediately after fibre passes

    premises

    Can the community help with building to street

    connection?

    8/9/2014 (C) Mark A Gregory 66

  • 8/9/2014

    (C) Mark A Gregory 34

    Backhaul

    Not part of NBN Co’s mandate

    If two backhaul providers it is regulated by ACCC

    If three backhaul providers it is not regulated

    8/9/2014 (C) Mark A Gregory 67

    8/9/2014 (C) Mark A Gregory 68

    Version date: June 2012

    Change the blue cells to generate price

    output in the green cell

    Route category Route between Tasmania and mainland

    Data rate (Mbps) 500

    Protected Yes

    Distance (km) 600

    Output ($) 629,563$

    U se o f t his calculat o r

    This calculator does not replace the Price Terms set out in Schedule 1 of the DTCS FAD and is intended to be a guide only.

    The Explanatory Statement to the DTCS FAD explains the ACCC’s decision on the Price Terms.

    Valid ranges for data rate are between 2 and 1000 M bps.

    Valid distances are greater than 0 km and up to 4000 km. Distance is measured based on the point to point radial distance of the ent ire service.

    All tail end routes are forced to equal 2 km and are not protected.

    Routes that traverse the Bass Strait must be greater than the not ional length of the under-sea cable (300 km) to generate output.

    A protected service includes geographic path diversity for the interexchange component of the service only.

    Output is the regulated annual price (ex-GST) for the service specif ied in the blue cells.

    DTCS FAD Pricing calculator

  • 8/9/2014

    (C) Mark A Gregory 35

    8/9/2014 (C) Mark A Gregory 69

    Version date: June 2012

    Change the blue cells to generate price

    output in the green cell

    Route category Regional

    Data rate (Mbps) 500

    Protected Yes

    Distance (km) 600

    Output ($) 466,875$

    U se o f t his calculat o r

    This calculator does not replace the Price Terms set out in Schedule 1 of the DTCS FAD and is intended to be a guide only.

    The Explanatory Statement to the DTCS FAD explains the ACCC’s decision on the Price Terms.

    Valid ranges for data rate are between 2 and 1000 M bps.

    Valid distances are greater than 0 km and up to 4000 km. Distance is measured based on the point to point radial distance of the ent ire service.

    All tail end routes are forced to equal 2 km and are not protected.

    Routes that traverse the Bass Strait must be greater than the not ional length of the under-sea cable (300 km) to generate output.

    A protected service includes geographic path diversity for the interexchange component of the service only.

    Output is the regulated annual price (ex-GST) for the service specif ied in the blue cells.

    DTCS FAD Pricing calculator

    8/9/2014 (C) Mark A Gregory 70

    Version date: June 2012

    Change the blue cells to generate price

    output in the green cell

    Route category Route to or from Darwin

    Data rate (Mbps) 500

    Protected Yes

    Distance (km) 4000

    Output ($) 681,018$

    U se o f t his calculat o r

    This calculator does not replace the Price Terms set out in Schedule 1 of the DTCS FAD and is intended to be a guide only.

    The Explanatory Statement to the DTCS FAD explains the ACCC’s decision on the Price Terms.

    Valid ranges for data rate are between 2 and 1000 M bps.

    Valid distances are greater than 0 km and up to 4000 km. Distance is measured based on the point to point radial distance of the ent ire service.

    All tail end routes are forced to equal 2 km and are not protected.

    Routes that traverse the Bass Strait must be greater than the not ional length of the under-sea cable (300 km) to generate output.

    A protected service includes geographic path diversity for the interexchange component of the service only.

    Output is the regulated annual price (ex-GST) for the service specif ied in the blue cells.

    DTCS FAD Pricing calculator

  • 8/9/2014

    (C) Mark A Gregory 36

    8/9/2014 (C) Mark A Gregory 71

    Version date: June 2012

    Change the blue cells to generate price

    output in the green cell

    Route category Regional

    Data rate (Mbps) 500

    Protected Yes

    Distance (km) 4000

    Output ($) 681,018$

    U se o f t his calculat o r

    This calculator does not replace the Price Terms set out in Schedule 1 of the DTCS FAD and is intended to be a guide only.

    The Explanatory Statement to the DTCS FAD explains the ACCC’s decision on the Price Terms.

    Valid ranges for data rate are between 2 and 1000 M bps.

    Valid distances are greater than 0 km and up to 4000 km. Distance is measured based on the point to point radial distance of the ent ire service.

    All tail end routes are forced to equal 2 km and are not protected.

    Routes that traverse the Bass Strait must be greater than the not ional length of the under-sea cable (300 km) to generate output.

    A protected service includes geographic path diversity for the interexchange component of the service only.

    Output is the regulated annual price (ex-GST) for the service specif ied in the blue cells.

    DTCS FAD Pricing calculator

    8/9/2014 (C) Mark A Gregory 72

    Source: Delimiter

  • 8/9/2014

    (C) Mark A Gregory 37

    Should Backhaul Costs be Equalised?

    8/9/2014 (C) Mark A Gregory 73

    Backhaul to Tasmania costs about 40% more than backhaul to

    other state and territory capitals

    Backhaul costs increase as you move away from Sydney

    How to fix this?

    Increase backhaul competition

    Update the Universal Service Obligation

    Universal Service Obligation

    Telecommunications is an essential service

    The Universal Service Obligation should be updated to include

    wholesale data and backhaul

    • Wi-Fi infrastructure

    • Telstra’s national RF network

    Government announces review at ACCAN USO Forum in March

    2015

    8/9/2014 (C) Mark A Gregory 74