OUR URBAN WATER SUPPLY … THE PLAN FOR MEETING OUR FUTURE WATER SUPPLY NEEDS LAWRENCE C. TROPEA, JR., P.E.,DEE EXECUTIVE DIRECTOR RIVANNA WATER & SEWER AUTHORITY NOVEMBER 25, 2002

Transcript of OUR URBAN WATER SUPPLY … THE PLAN FOR MEETING OUR FUTURE WATER SUPPLY NEEDS LAWRENCE C. TROPEA,...

Page 1: OUR URBAN WATER SUPPLY … THE PLAN FOR MEETING OUR FUTURE WATER SUPPLY NEEDS LAWRENCE C. TROPEA, JR., P.E.,DEE EXECUTIVE DIRECTOR RIVANNA WATER & SEWER.

OUR URBAN WATER SUPPLY …

THE PLAN FOR MEETING OUR FUTURE WATER SUPPLY NEEDS

LAWRENCE C. TROPEA, JR., P.E.,DEEEXECUTIVE DIRECTOR

RIVANNA WATER & SEWER AUTHORITY

NOVEMBER 25, 2002

Page 2: OUR URBAN WATER SUPPLY … THE PLAN FOR MEETING OUR FUTURE WATER SUPPLY NEEDS LAWRENCE C. TROPEA, JR., P.E.,DEE EXECUTIVE DIRECTOR RIVANNA WATER & SEWER.

OBJECTIVES:

• Drought of 2002

• Approved Plan For The Future

• Costs and Time Table

• Answers to Questions

Page 3: OUR URBAN WATER SUPPLY … THE PLAN FOR MEETING OUR FUTURE WATER SUPPLY NEEDS LAWRENCE C. TROPEA, JR., P.E.,DEE EXECUTIVE DIRECTOR RIVANNA WATER & SEWER.

RIVANNA WATER & SEWER AUTHORITY

MISSION

• Provide an adequate supply of safe drinking water for our community.

• Balance our water supply role and our environmental responsibilities.

The Rivanna Water & Sewer Authority does not control growth … our water supply should not be a pawn in the debate over growth.

Page 4: OUR URBAN WATER SUPPLY … THE PLAN FOR MEETING OUR FUTURE WATER SUPPLY NEEDS LAWRENCE C. TROPEA, JR., P.E.,DEE EXECUTIVE DIRECTOR RIVANNA WATER & SEWER.

DROUGHT OF 2002

• Reservoirs full in June 2002 – 1.67 billion gallons

• Precipitation and stream flow fell to zero.

• August was a drought “accelerator.”

• Reservoirs fell to 785,000 gallons – or 88 days supply.

• Mandatory water use restrictions worked.

• Community support was fantastic.

• Reservoirs now recovered to 1.55 billion gallons

THE DROUGHT OF 2002 WILL BE PROVEN MORE SEVERE FOR OUR AREA THAN THE DROUGHT OF THE 1930’s.

Page 5: OUR URBAN WATER SUPPLY … THE PLAN FOR MEETING OUR FUTURE WATER SUPPLY NEEDS LAWRENCE C. TROPEA, JR., P.E.,DEE EXECUTIVE DIRECTOR RIVANNA WATER & SEWER.

Urban Raw Water Storage*

0

200

400

600

800

1000

1200

1400

1600

1/1/012/1/013/1/014/1/015/1/016/1/017/1/018/1/019/1/0110/1/0111/1/0112/1/01

1/1/022/1/023/1/024/1/025/1/026/1/027/1/028/1/029/1/0210/1/0211/1/02

Million Gallons

1676

11/25/0292.0%

* Includes South Fork Rivanna, Sugar Hollow, and Ragged Mountain Reservoirs.

Page 6: OUR URBAN WATER SUPPLY … THE PLAN FOR MEETING OUR FUTURE WATER SUPPLY NEEDS LAWRENCE C. TROPEA, JR., P.E.,DEE EXECUTIVE DIRECTOR RIVANNA WATER & SEWER.

Daily Water Consumption

5

6

7

8

9

10

11

12

13

8/23/028/26/028/29/029/1/029/4/029/7/029/10/029/13/029/16/029/19/029/22/029/25/029/28/0210/1/0210/4/0210/7/0210/10/0210/13/0210/16/0210/19/0210/22/0210/25/0210/28/0210/31/02

11/3/0211/6/0211/9/0211/12/0211/15/0211/18/0211/21/0211/24/02

Million Gallons

Labor Day

Weekend

PHASE 1 RESTRICTIONS ENACTED

PHASE 2 RESTRICTIONS ENACTED

Page 7: OUR URBAN WATER SUPPLY … THE PLAN FOR MEETING OUR FUTURE WATER SUPPLY NEEDS LAWRENCE C. TROPEA, JR., P.E.,DEE EXECUTIVE DIRECTOR RIVANNA WATER & SEWER.

WATER SUPPLY MYTHS

• Water demand has been steadily increasing.

• No future water supply plan exists.

• Buck Mountain Reservoir is the water supply panacea.

• RWSA controls area growth.

Page 8: OUR URBAN WATER SUPPLY … THE PLAN FOR MEETING OUR FUTURE WATER SUPPLY NEEDS LAWRENCE C. TROPEA, JR., P.E.,DEE EXECUTIVE DIRECTOR RIVANNA WATER & SEWER.

URBAN AREAWATER CONSUMPTION

YEAR DAILY AVERAGE

1999 11.93 MGD

2000 11.22 MGD

2001 11.18 MGD

2002 10.75 MGD

AREA WATER CONSUMPTION WAS GREATER THAN 10 MGD IN 1987.

Page 9: OUR URBAN WATER SUPPLY … THE PLAN FOR MEETING OUR FUTURE WATER SUPPLY NEEDS LAWRENCE C. TROPEA, JR., P.E.,DEE EXECUTIVE DIRECTOR RIVANNA WATER & SEWER.

RIVANNA WATER SUPPLY PLANThis plan is approved and being

implemented• Continue Water Conservation.• Add More Water Storage Capacity.• Maintenance Dredging of the South Fork Rivanna Reservoir.• Rebuild Mechums Pump Station.• Improve Water Treatment Facilities .. Gain Operating

Flexibility.• Control Sediments in the Watershed. Plus watershed

leadership.• Better Drought Management.

PLAN ADDS 630 MILLION GALLONS OR 38 PERCENT TO OUR STORAGE CAPACITY.

Page 10: OUR URBAN WATER SUPPLY … THE PLAN FOR MEETING OUR FUTURE WATER SUPPLY NEEDS LAWRENCE C. TROPEA, JR., P.E.,DEE EXECUTIVE DIRECTOR RIVANNA WATER & SEWER.

GROWTH AND OUR AREA WATER SUPPLY

By 2030• Plan allows for 5.3 MGD of Growth.• 45 percent increase from FY 2001 water demand.

By 2050• Plan allows for 8.2 MGD of growth.• 75 percent increase from FY 2001 water demand.

THE RIVANNA PLAN COMMITS TO PERIODIC REASSESSMENTS OF WATER SUPPLY NEEDS.

Page 11: OUR URBAN WATER SUPPLY … THE PLAN FOR MEETING OUR FUTURE WATER SUPPLY NEEDS LAWRENCE C. TROPEA, JR., P.E.,DEE EXECUTIVE DIRECTOR RIVANNA WATER & SEWER.

FAST TRACKING THE WATER SUPPLY PLAN

• Initially focusing on:

– Raising height of Dam on South Fork Rivanna Reservoir

– Dredging Project

– Mechums River Pump Station

• Regulatory Approvals moving forward quickly

THE TIME FOR PLANNING IS OVER … RIVANNA IS TAKING ACTION!

Page 12: OUR URBAN WATER SUPPLY … THE PLAN FOR MEETING OUR FUTURE WATER SUPPLY NEEDS LAWRENCE C. TROPEA, JR., P.E.,DEE EXECUTIVE DIRECTOR RIVANNA WATER & SEWER.

REGULATORY APPROVAL SUMMARY

• Four-Foot Crest Control Project– Wetlands delineation– Permit Application approximately 12/31/02

• Mechums River Pump Station Project– PCN submitted– Permit in one week

• Dredging of South Fork Rivanna Reservoir– PCN submitted– Permit in two weeks

• Key Future Interactions– VDOT Meeting– FERC Analysis– Wetlands Mitigation– Aerial Photography — Define reservoir footprint

Page 13: OUR URBAN WATER SUPPLY … THE PLAN FOR MEETING OUR FUTURE WATER SUPPLY NEEDS LAWRENCE C. TROPEA, JR., P.E.,DEE EXECUTIVE DIRECTOR RIVANNA WATER & SEWER.

FUTURE WATER SUPPLY COSTS

• Water Supply Plan — $13.2 million

• Rehabilitation of Ragged Mountain Dam — under study

• Other infrastructure

improvements — under study

Targets – • Major South Fork Rivanna improvements in 24 months to 4.5 years.

• Mechums River Pump Station by early to late 2003.

WATER RATES MUST INCREASE TO ADDRESS FUTURE WATER SUPPLY NEEDS.

Page 14: OUR URBAN WATER SUPPLY … THE PLAN FOR MEETING OUR FUTURE WATER SUPPLY NEEDS LAWRENCE C. TROPEA, JR., P.E.,DEE EXECUTIVE DIRECTOR RIVANNA WATER & SEWER.

PROPOSED BUCK MOUNTAIN RESERVOIR

• Part of 2050 Water Supply Strategy.

– 14.4 MGD of safe yield

• Not currently a preferred option:

– South Fork Rivanna Reservoir is better option (cheaper, faster, less environmental

impact).

– Expected long lead time.

– Environmental concerns (59 acre wetlands impact).

• James Spiny Mussel present

– Very expensive ($57 million for project).THE BUCK MOUNTAIN RESERVOIR IS NOT A “LITMUS TEST” OF OUR WATER SUPPLY PLAN.

Page 15: OUR URBAN WATER SUPPLY … THE PLAN FOR MEETING OUR FUTURE WATER SUPPLY NEEDS LAWRENCE C. TROPEA, JR., P.E.,DEE EXECUTIVE DIRECTOR RIVANNA WATER & SEWER.

CLOSING COMMENTS

• Our approved water supply plan is sound.

• No plan is totally “drought proof.”

• Our focus must now be on action.

• RWSA committed to periodic reassessments of strategy.

• Let’s coalesce behind the approved plan!