Date: August 18,2016Dontaye Brooks
Intern Final Presentation
- Company Private -
![Page 2: Otis Elevator Summer 2016 final Presentation](https://reader031.fdocuments.in/reader031/viewer/2022021506/5886ce0c1a28abcc7d8b7c51/html5/thumbnails/2.jpg)
*Intern Bio*Summer Objectives*Results*Observations/ Recommendations *Q&A
Agenda
2
![Page 3: Otis Elevator Summer 2016 final Presentation](https://reader031.fdocuments.in/reader031/viewer/2022021506/5886ce0c1a28abcc7d8b7c51/html5/thumbnails/3.jpg)
Bio
3
Hometown: Hartford, CTSchool: Central Connecticut State UniversityMajor: AccountingYear: Rising JuniorSupervisor: Lisa Blanton; Colleen Parkhurst
Your picture
![Page 4: Otis Elevator Summer 2016 final Presentation](https://reader031.fdocuments.in/reader031/viewer/2022021506/5886ce0c1a28abcc7d8b7c51/html5/thumbnails/4.jpg)
*Objective 1: Track one year worth of returned mail for billing team
*Objective 2: Track daily invoices for billing team
*Objective 3: Track change order returns for booking team
Summer Objectives
4
![Page 5: Otis Elevator Summer 2016 final Presentation](https://reader031.fdocuments.in/reader031/viewer/2022021506/5886ce0c1a28abcc7d8b7c51/html5/thumbnails/5.jpg)
Objective 1 Deliverable
* July 2015- 117 turnbacks were made
* July 2016-122 turnbacks were made
*Majority of the turnbacks were made due to:
* Incomplete CBIS forms(common error)
* Unclear CBIS forms* Invalid Info in JDE* Unable to load
Turnbacks Made(July 2015- July 2016)
5Source: GP Otis NE Mod Billing CBIS
![Page 6: Otis Elevator Summer 2016 final Presentation](https://reader031.fdocuments.in/reader031/viewer/2022021506/5886ce0c1a28abcc7d8b7c51/html5/thumbnails/6.jpg)
Objective 2 Deliverable
* June had the highest invoice count of 3067*August Invoice count
in process
Monthly New Equipment Billing Invoice Count(2016)
6Source: Daily Print Out
![Page 7: Otis Elevator Summer 2016 final Presentation](https://reader031.fdocuments.in/reader031/viewer/2022021506/5886ce0c1a28abcc7d8b7c51/html5/thumbnails/7.jpg)
Objective 3 Deliverable
* June 2016- There were 238 total turnbacks made
* July 2016- 219 total turnbacks were made
Change Order Turnbacks (June 2016-July 2016)
7Source: GP OTIS NAA Estimating
![Page 8: Otis Elevator Summer 2016 final Presentation](https://reader031.fdocuments.in/reader031/viewer/2022021506/5886ce0c1a28abcc7d8b7c51/html5/thumbnails/8.jpg)
Observations*Otis values customer care and employee opportunity* Everyone is family: Makes work environment efficient and easy to work in* Team work is key to accomplishing company goalsRecommendations* Having the opportunity to work with a newer software* I was looking forward to working with other interns but later found out the company is in transition to relocating* Feedback: I enjoyed every moment of my internship experience. Never had a dull moment with my managers and colleagues.
Observations/Recommendations