OTC HOUSTON 2015 diretora Solange ... - Agência Petrobras€¦ · The presentation may contain...
Transcript of OTC HOUSTON 2015 diretora Solange ... - Agência Petrobras€¦ · The presentation may contain...
PRE-SALT —Achievements and Legacy
OTC 2015MAY 5th, 2015 • HOUSTON, TEXAS, USA
Solange da Silva GuedesE&P Director
1
FORWARD-LOOKING STATEMENTS:
DISCLAIMER
The presentation may contain forward-looking statements about future
events within the meaning of Section 27A of the Securities Act of 1933, as
amended, and Section 21E of the Securities Exchange Act of 1934, as
amended, that are not based on historical facts and are not assurances of
future results. Such forward-looking statements merely reflect the
Company’s current views and estimates of future economic
circumstances, industry conditions, company performance and financial
results. Such terms as "anticipate", "believe", "expect", "forecast", "intend",
"plan", "project", "seek", "should", along with similar or analogous
expressions, are used to identify such forward-looking statements.
Readers are cautioned that these statements are only projections and may
differ materially from actual future results or events. Readers are referred
to the documents filed by the Company with the SEC, specifically the
Company’s most recent Annual Report on Form 20-F, which identify
important risk factors that could cause actual results to differ from those
contained in the forward-looking statements, including, among other
things, risks relating to general economic and business conditions,
including crude oil and other commodity prices, refining margins and
prevailing exchange rates, uncertainties inherent in making estimates of
our oil and gas reserves including recently discovered oil and gas
reserves, international and Brazilian political, economic and social
developments, receipt of governmental approvals and licenses and our
ability to obtain financing.
We undertake no obligation to publicly update or revise any
forward-looking statements, whether as a result of new
information or future events or for any other reason. Figures for
2014 on are estimates or targets.
All forward-looking statements are expressly qualified in their
entirety by this cautionary statement, and you should not place
reliance on any forward-looking statement contained in this
presentation.
NON-SEC COMPLIANT OIL AND GAS RESERVES:
CAUTIONARY STATEMENT FOR US INVESTORS
We present certain data in this presentation, such as oil and gas
resources, that we are not permitted to present in documents filed
with the United States Securities and Exchange Commission
(SEC) under new Subpart 1200 to Regulation S-K because such
terms do not qualify as proved, probable or possible reserves
under Rule 4-10(a) of Regulation S-X.
Disclaimer
2
As known, the Brazilian Pre-Salt was discovered in 2006 and covers an area of 149,000 square kilometers—
Concession blocks
Transfer of rights area
Production sharing contract5
The pre-salt is managed in an harmonic way, with several partners and three regulatory models—
Santos Basin - Concession Model
BMS-8
BMS-9
BMS-11
BMS-21
BMS-24
BMS-50
(66%) (10%) (10%) (14%)
(45%) (30%) (25%)
(65%) (25%) (10%)
(80%) (20%)
(80%) (20%)
(60%) (20%) (20%)
Santos Basin
Production Sharing AgreementModel
(40%)
(20%)
(20%)
(10%)
(10%)
Santos Basin Transfer of Rights Contract
(100%)
Concession blocks
Transfer of rights area
Production sharing contract6
Campos Basin - Concession Model
(100%)
Xerelete
Alb. Leste
BM-C-33
(41,175%) (41,175%) (17,65%)
(90%)
(35%) (35%)
(10%)
(30%)
Other concessions
Mount Everest
8,8 km
Since the 80’s, Petrobras has been innovating in ultra-deepwater—
1st oil fieldfound in
Campos Basin
OTC
Award
1992
1st FPSO Production
System
OTC
Award
2001
1st comercial discovery from
Pre-Salt
OTC
Award
2015
Deepest
flexible riser
water depth
8
8 km
0 km
K2 MOUNTAIN(8,6 km)
Source: iStock/Petrobras images
Today, the Pre-salt production is already supported by 12 production systems and 55 wells—
Concession contracts
Transfer of rights contract
Production sharing contract
FPSO Cid. ParatyLula
FPSO Cid. Angra dos ReisLula
FPSO Cid. MangaratibaLula
FPSO Cid. São PauloSapinhoá
FPSO Cid. IlhabelaSapinhoá
FPSO Dynamic ProducerExtended Well Tests
Petrobras 48Carimbé
Petrobras 53Tracajá
FPSO Cid. AnchietaBaleia Azul
Petrobras 58Parque das Baleias
FPSO CapixabaBaleia Franca
FPSO Cid. NiteróiMarlim Leste
9
OTC 2015Solange da Silva Guedes
OTC 2011José Miranda Formigli
OTC 2013Carlos Tadeu da Costa Fraga
OTC 2009José Miranda Formigli
The development strategy has been accomplished over the years and shared with the industry through OTC—
11
To take advantage of all Pre-Salt potential, a long-term vision for planning was required—
Phase 0:
Information
Gathering
Phase 1a:
Production
Development
Phase 1b:
Technological
Innovation
12
A specific methodology and a new integrated workflow in characterizing the reservoir were developed…
—
In the earlier 2000’s, Petrobras and partners
decided to acquire
20,000 km2 of 3Dover the main Pre-salt
areas
Better algorithmic and velocity models
Improvement in Pre-Salt reservoir
imaging
13
Seismic AcquisitionSeismic
ProcessingSeismic
Interpretation
117 exploratory wells drilled from 2005 to March 2015
Pre-Salt Exploratory Success Rate: > 90%
10 EWTs from Apr/2009 to Mar/2015
FPSO Cidade de São Vicente FPSO Dynamic Producer
Pilot Project:
First supergiant Field, LulaOn stream since Oct/2010
FPSO Cidade de Angra dos Reis (Lula Pilot)
… which allowed important exploratory results, setting the path to production development
—
���
14
As mentioned in OTC 2011, the first project in Phase 1a was the Sapinhoá Pilot that was put on stream in 2013—
Sapinhoá ProjectFPSO Cidade de São Paulo
1st Oil: Q1 / 2013
Project on stream.
15
���
Lula NE ProjectFPSO Cidade de Paraty
As mentioned in 2011, we planned to put on stream others mega projects through 2014. The Pre-Salt production by June 2013 was about 310 kbpd—
As announced at OTC 2011…
1st Oil: Q2 / 201316
���…project on stream.
1st Oil: Q2 / 2013
On March 2014, the average production was about 395 kbpd—
17
Norte Parque das Baleias ProjectFPSO Petrobras 58
As announced at OTC 2013…
1st Oil: Q4 / 2013
���…project on stream.
1st Oil: Q1 / 2014
With these 5 new units, production achieved an average of 666 kbpd on December 2014—
18
Iracema Sul ProjectFPSO Cidade de Mangaratiba
As announced at OTC 2011…
1st Oil: Q4 / 2014
���…project on stream.
1st Oil: Q4 / 2014
On November 2014, the average production was over 600 kbpd. It nearly doubled in less than 8 months—
19
Sapinhoá Norte ProjectFPSO Cidade de Ilhabela
As announced at OTC 2011…
1st Oil: Q3 / 2014
���…project on stream.
1st Oil: Q4 / 2014
September/08Jubarte field - EWT P-34
May/09Lula field (Tupi lead) - EWTFPSO BW Cid. São Vicente
July/10Cachalote FieldFPSO Capixaba
October/10Lula field pilotFPSO Cid. Angra dos Reis
December/10Caratinga FieldP-48
February/11
Marlim Leste Field
P-53
September/12Pirambu and Baleia Azul fieldsFPSO Cid. de Anchieta
January/13Sapinhoá Field FPSO Cid. São Paulo
June/13Lula NE Field FPSO Cid. Paraty
July/13
Marlim Leste Field
FPSO Cidade de Niterói
March/14Baleia Azul, Baleia Franca andJubarte fieldsP-58
October/14Iracema Sul AreaFPSO Cid. Mangaratiba
November/14Sapinhoá Norte FieldFPSO Cid. Ilhabela
The pre-salt layer daily production record was 737 kbpd in Feb 2015 —
� ���Daily record (Feb 26th): 737
Thousand bpd
20
Average monthly production (kbpd)
Reservoir Well Construction Subsea Topside and Processing Facilities
Deepest Offshore Well 2,173 m Water Depth –
Injecting Gas with CO2
Dec/2014
Water Alternating GasInjection Method (WAG) in Ultra-deepwatersDec/2012
Water depth record for a
Subsea Well Drilled with
Pressured Mud-Cap DrillingJun/2014
Intelligent Completion in Ultra-deepwater Satellite Wells with High
Potencial for Carbonate ScalingMar/2011
Buoy SupportingRisers Jan/2014
First Steel Catenary Risers with lined pipesJan/2014
Deepest Steel LazyWave RiserMar/2015
Deepest FlexibleRisers - 2,220 m WD Dec/2014
First Application of FlexibleRisers with Integrated TensileArmor Wire MonitoringSystem2nd semester/2015
First CO2 Separation from Associated Natural Gas in Ultra-deepwater with CO2
Re-injectionSep/2011
���Daily record (Feb 26th): 737
Thousand bpd
Those results were supported by innovative technologies… —
21
Average monthly production (kbpd)
… and above average well productivity… —
Top 5 productive wells: all over 30 kbpd
Top Wells - Sapinhoá Field
1. SPH-7: 42 kbpd
2. SPH-5: 36 kbpd
3. SPH-1: 36 kbpd
Top Wells - Lula Field
4. LL-27: 35 kbpd
5. RJS-681: 34 kbpd
���
22
… all to support the production goal of 1 MM bpd by 2017, as mentioned in OTC 2009—
The Production more than doubled in 24 months
feb/13 jun/14 feb/15
300 kbpd
520 kbpd
737 kbpd (peak)
2,5 x2,5 x
���
23
Slide 25All the strategies and efforts pursued so far gave Petrobras strong competitive advantages related to cost reduction and productivity improvement
—
Competitive advantage
on lower oil price scenario
New
Technologies
Learning Curve
AccelerationStandardization
Cost Reduction Productivity Improvement
25
26
RESERVOIRCHARACTERIZATION
RESERVOIRCHARACTERIZATION
HIGH PRESSURE
SEPARATION
LOWERCOMPLETIONDECOUPLING
LOWERCOMPLETIONDECOUPLINGH2S REMOVAL
SYSTEMS
FPUs PROCESSING
CAPACITYFPUs PROCESSING
CAPACITY
INTELLIGENT COMPLETIONINTELLIGENT COMPLETION
OCEAN BOTTOM SENSORS
OCEAN BOTTOM SENSORS
NANO-TECHNOLOGY
CONTROLED SALINITY WATER
INJECTION
CO2 SEPARATION SYSTEMS
New technologies are already under evaluation—
27
Accelerated Learning Curve will continue to be applied …—
The importance of these optimization programswill continue as the Pre-salt campaign moves forward
Structured assessment of Learning Curves ...
... to identify optimization initiatives ...
Objective: accelerateexperience effects
Optimization dimensions
Sourcing strategy
New technologies
Improved planning, processes & design
Metrics & incentives
Scope: most criticalwells & subsea items
... that were the basis for optimization programs
Initial cost optimizationprogram …
... expanded into specificprograms for wells &
subsea systems 40+ initiatives
Cumulative Volume
Unit
Cost
…. once we achieved an impressive result at a massive campaign of offshore well construction. —
54% of time reduction from 2010 to 2014
54% of time reduction from 2010 to 2014
0%
20%
40%
60%
80%
100%
2010 2011 2012 2013 2014
Drilling Completion
Time reduction in well construction through
Accelerated Learning Curve
Lula and Sapinhoá Fields
28
25 drilling rigs130 wells drilled
Standardized equipment are the key for Cost optimization and effective Risk Management
Pre-Salt scale provides optimization through standardization—
Based on the successful experience in Campos Basin, Petrobras has been continuously investing in equipment standardization for Pre-salt development
29
Subsea tree standardization Subsea manifolds standardization Flexible pipes standardization
30
Drop in oil prices puts pressure on suppliers—
5566 73
99
6380
111 112 10999
40
90
140
Brent
Industry CAPEX and OPEX behavior compared to Brent prices
(US$/bbl)
126
167
198
221201 209
220230 232 229
132151
168 172 171 174184 192 198 199
100
150
200
250
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014
Infl
ati
on
index
Capex / Investimento Opex / Operação
Source: Bloomberg
Source: IHS Energy - Upstream Capital Costs Index (UCCI) e Upstream Operating Costs Index (UOCI)
31
Petrobras has an unique combination of costs, productivity and efficiency. As a consequence, a very competitive portfolio. —
9.1
14.6
15.0
Pre-salt
Petrobras Average
Other Operators
Source: Evaluate Energy
Current projects’ average return2014 Lifting Cost* (US$/boe)
Inte
rna
lR
ate
of
Re
turn
(%)
Other Operators
Petrobras
2014 Operational Efficiency (%)
Source: Wood Mackenzie Corporate Benchmarking Tool -
Publicly Traded Companies (04/28/15)
Pre-salt last three years average: 92.4%
* without government take
32
Petrobras and its partners have a phenomenal portfolio which puts Brazil in a leading position in ultra-deepwater development—
“The enormous amount of knowledge already gained allowed Petrobras and its partners to overcome the challenges which the pre-salt brought to the development of the production.”
- Carlos Alves, Petrogal Brasil CEO
“It is a privilege to count with a solid partner like Petrobras, a leading specialist and true reference in deep and ultra deep water.”
- Nelson Silva, BG Brasil Chairman
“Petrobras is a first rate operator and what the company is doing in the pre-salt could not be accomplished by any other company in the world on its own.”
- Tomas Blanco, Repsol Sinopec Brasil CEO