Osomo LBM Factoryfrom Concept to Operational Business

Symposium “Kleinschalige bioraffinage voor en door bedrijven"

Osomo Copyright1

Page 2: Osomo LBM Factory - Acrres€¦ · Title: 6 Jerom van Roosmalen Osomo Osomo LBM Factory from Concept to Operational Business Author: eliss001 Created Date: 4/14/2017 12:36:09 PM

Introduction

� Founded 2009

� Since 2012 (Bio-)LNG/LBM

– Liquefaction of (bio)methane 1st pilot plant in cooperation with Shell and

Gasunie at Waste Water Treatment Plant in Apeldoorn

– Stirling Cryocoolers in two Pilot installations

� Now

– Patent granted for efficient (Bio-)gas-to-LNG process method

– Patent pending for Cryogenic 3-phase-separator

– 2014 upwards: 2nd Bio-LNG pilot plant to validate the patent and other

research goals here at Acrres

– Acquired rights of ZR-LNG technology from Gas Consult Ltd

– Developed combined ZR-iLNG technology

Symposium “Kleinschalige bioraffinage voor en door bedrijven"

Osomo Copyright2

Page 3: Osomo LBM Factory - Acrres€¦ · Title: 6 Jerom van Roosmalen Osomo Osomo LBM Factory from Concept to Operational Business Author: eliss001 Created Date: 4/14/2017 12:36:09 PM

Evolution LBM technology

2nd Demo May 2012

1 day Fundraising demonstration

1st Pilot Plant Oct 2012- May 2013

Prove of concept

2nd Pilot Plant Jan 2015 – Dec 2015

Improved concept, Patent validation, Research

5 ton/day Plant 2017

Econ feasible

Integrated and modulair system

4 million euros

Multiple Plants 5 ton/day

2017-2020

Supply chain of multiple sites

Symposium “Kleinschalige bioraffinage voor en door bedrijven"

1st Demo 2011: Does it work?

Osomo Copyright3

Page 4: Osomo LBM Factory - Acrres€¦ · Title: 6 Jerom van Roosmalen Osomo Osomo LBM Factory from Concept to Operational Business Author: eliss001 Created Date: 4/14/2017 12:36:09 PM

Pilot plant in Lelystad

Symposium “Kleinschalige bioraffinage voor en door bedrijven"

Osomo Copyright4

Page 5: Osomo LBM Factory - Acrres€¦ · Title: 6 Jerom van Roosmalen Osomo Osomo LBM Factory from Concept to Operational Business Author: eliss001 Created Date: 4/14/2017 12:36:09 PM

Working field

Osomo / iLNG

Supply Chain LNG

Symposium “Kleinschalige bioraffinage voor en door bedrijven"

Osomo Copyright5

Page 6: Osomo LBM Factory - Acrres€¦ · Title: 6 Jerom van Roosmalen Osomo Osomo LBM Factory from Concept to Operational Business Author: eliss001 Created Date: 4/14/2017 12:36:09 PM

Valuation of biogas

Osomo Copyright6

Biogas Valuation

CHP

• Heat

• Electricity

Green Gas

• Gridinjection

LBM

• Energy Storage

• Fuel

Page 7: Osomo LBM Factory - Acrres€¦ · Title: 6 Jerom van Roosmalen Osomo Osomo LBM Factory from Concept to Operational Business Author: eliss001 Created Date: 4/14/2017 12:36:09 PM

Glycol- H2O

dewpoint

LTS - HC

dewpoint

Amine CO2

Removal

Water, Hg

removal

Heavy HC

removal

Liquefaction

LNGGas well

pipeline

Heating

medium

Conventional large scale fossil LNG

Fractionation

LNG shipping

How can small scale LBM compete

with large-scale fossil LNG?

Biogas to LBM; iLNG technology

pipeline

LNG truck

Membrane

Removal

Liquefaction

LNGDigester

LNG import

terminal

LNG truck Possible by;

- CO2 tolerant liquefaction

- Integrated with membrane gas treating

Osomo CopyrightSymposium “Kleinschalige bioraffinage voor en door bedrijven"

40 days Cryogenic storage

Simple, short, standard, supply chain

Competitive specific capex

4 days Cryogenic storage

7

Page 8: Osomo LBM Factory - Acrres€¦ · Title: 6 Jerom van Roosmalen Osomo Osomo LBM Factory from Concept to Operational Business Author: eliss001 Created Date: 4/14/2017 12:36:09 PM

Gas treatmentConventional

Membrane

LiquefactionStirling Cryocooler

or ZR-LNG

RawBiogas

BioMethaneTreated

BiogasLBM

CO2

Simplified Process schemeiLNG technology

Unique simplified integrated proces method, non-

obvious combination of proven existing techniques.

Decantor3 phase separation

End-polishing

N2 / CH4 mix recycle

Symposium “Kleinschalige bioraffinage voor en door bedrijven"

Conventional technology with

no risk. Several supplier

available. Fall back is green

gas production.

Stirling: existing technology

and proven in pilot.

ZR-LNG: new technology,

lower capex, wider capacity

bandwidth

Existing technology, proven in

pilot and large peak shavers.

Improved design with patent

pending. No alternative,

unique and essential.

Green

Gas

Osomo Copyright8

Page 9: Osomo LBM Factory - Acrres€¦ · Title: 6 Jerom van Roosmalen Osomo Osomo LBM Factory from Concept to Operational Business Author: eliss001 Created Date: 4/14/2017 12:36:09 PM

Valuation model of LBM

Osomo CopyrightSymposium “Kleinschalige bioraffinage voor en door bedrijven"

9

Biomass-waste

storage

Anaerobic

DigesterField

Liquefaction

Liquid Bio Methane

LBM

Storage

BioGas

Upgrading

CHP power

Generation

Gas grid

Fuel stations

Wind power

Generation

H2 production by

electrolysis

CO2 CO2

Minerals - NPKPower grid

Biological

methanation

CO2

Page 10: Osomo LBM Factory - Acrres€¦ · Title: 6 Jerom van Roosmalen Osomo Osomo LBM Factory from Concept to Operational Business Author: eliss001 Created Date: 4/14/2017 12:36:09 PM

Purpose local LBM/LNG

� Reduce installed base of centralized capacity of conventional

power plants

� Decentralized storage connected to three grids: grid balancing

between supply and demand on daily bases in every and

between the three networks at local basis

� Strategic energy storage: one LNG fuel station storage tank of

60 m3 has the same energy storage as the batteries of 2200

Teslas

Osomo CopyrightSymposium “Kleinschalige bioraffinage voor en door bedrijven"

10

Page 11: Osomo LBM Factory - Acrres€¦ · Title: 6 Jerom van Roosmalen Osomo Osomo LBM Factory from Concept to Operational Business Author: eliss001 Created Date: 4/14/2017 12:36:09 PM

Market Perspective

� New Renewable Energy Directive (2020 upwards) has an

progressive increasing greening policy. This has a major

impact on fuel blending rates.

� LNG is a growing market as substitute for conventional fossil

fuels especially for heavy road transport and inland and

short sea shipping. There is no short term alternative

available to reduce emission then LNG.

� LBM is the green counterpart for LNG, and is necessary for

further growth of the LNG market

Symposium “Kleinschalige bioraffinage voor en door bedrijven"

Osomo Copyright11

Page 12: Osomo LBM Factory - Acrres€¦ · Title: 6 Jerom van Roosmalen Osomo Osomo LBM Factory from Concept to Operational Business Author: eliss001 Created Date: 4/14/2017 12:36:09 PM

Summary

� Smart integration is the key-word

� Energy transition is no revolution, but evulotion

� LBM is a local produced subsitute for three kinds of energy

demands

� LBM can take a central role in this process and make it happen

with the optimal use of existing infrastructure

� More research need to be done on convertion efficiencies and

system interactions

� It can be done now, not a promise like H2

Osomo CopyrightSymposium “Kleinschalige bioraffinage voor en door bedrijven"

12

Page 13: Osomo LBM Factory - Acrres€¦ · Title: 6 Jerom van Roosmalen Osomo Osomo LBM Factory from Concept to Operational Business Author: eliss001 Created Date: 4/14/2017 12:36:09 PM

Questions or remarks?

Osomo Projects BV Deel 1

Osomo Projects BV Deel 2

Osomo Projects BV Deel 3

Osomo Promo algemeen

Osomo CopyrightSymposium “Kleinschalige bioraffinage voor en door bedrijven"

13

More info on our website and youtube channel

Page 14: Osomo LBM Factory - Acrres€¦ · Title: 6 Jerom van Roosmalen Osomo Osomo LBM Factory from Concept to Operational Business Author: eliss001 Created Date: 4/14/2017 12:36:09 PM

Extending the design envelope of standard equipment

Closing the gap and making the link

Osomo CopyrightSymposium “Kleinschalige bioraffinage voor en door bedrijven"

Standard

membrane

[ CO2 ] and [H2O] at inlet or outlet

Cryogenic

section

Standard

membrane

Conventional

Membrane &

LNG technology

Integrated

iLNG technology

Cryogenic

Section

Flash-2-Sweep

Cryo-3-

Flash

14

Page 15: Osomo LBM Factory - Acrres€¦ · Title: 6 Jerom van Roosmalen Osomo Osomo LBM Factory from Concept to Operational Business Author: eliss001 Created Date: 4/14/2017 12:36:09 PM

iLNG USP’s

• Low risk, low equipment count, robust, simple, reliable, simple, N2

tolerant

• Validated process line-up with actual field data that works on very

small scale (< 10 ton/dy)

• Patented process method

• Build up with conventional proven components

• No issues with freeze-out, because of end-flash in three phase

separator => patented component design. Holy Grail also for

competitive liquefaction technologies

• Till now the only problem-free small scale LBM factory. We know

how to make LBM successfully and we know the pitfalls.

Osomo CopyrightSymposium “Kleinschalige bioraffinage voor en door bedrijven"