1 Manhattan Construction Company Dallas Cowboys New Stadium Site Specific Orientation

Transcript of Osha General How To Survive An Inspection For Construction

1

Manhattan Construction

Company

Dallas Cowboys New Stadium Site Specific

Orientation

2

3

This is an OCIP Project.

All injuries will be reported.

1. Your Supervisor

2. Project Safety Director

4

PPE

Hardhat is required at all times with sticker.

Safety glasses is required at all times.

Non-offensive clothing.

Photo ID Badge in View.

Fluorescent Safety vest is required at all times

Fall protection is required for any work over 6’

Manhattan has a Zero Tolerance Policy you will be sent off this project.

5

Parking/Personal Vehicles

Speed Limit is 10 MPH…No faster

Personal vehicles are not permitted

Parking in designated areas only

6

Housekeeping

Eating in designated areas only

Clean up the work area all day and at

the end of shift.

Do not bring glass containers on site

All fuel must be removed out side of

stadium at the end of each work day.

“A CLEAN PROJECT IS A SAFE

PROJECT”

7

Slip Trip and Falls

When walking around the project

keep in mind that it is still a

construction site.

Stop, Look and Listen as you walk.

Stop and see if there is work going

on over head. (if yes go around)

Look for any red laser lights.

Listen for power active tools, drills,

big motors or compressors.

8

Look for

Extension

Cords on

the floors.

Slip Trip and Falls

9

Slip Trip and Falls

Look for Ladders (Do not go under them)

Can you see me

10

Slip Trip and Falls

Look for Scaffolds

(Do not go under them)

11

Emergency Evacuation Areas

Manhattan Construction

Company parking lot.

(1) Primary Evacuation site

Dallas Cowboys Blue Star

(2) Secondary Evacuation site

12

11

5

13

3

Co

llins

Ba

rd F

rom

Rd

.

Division St.

Randol Mill Rd.

13

Areas of focus

Fall Protection Zero tolerance policy

Excavations (access,sloping,shoring,benching….etc)

Extension Cords (Check them)

Ladders (Check them)

Scaffolds

PPE

Sexual Harassment

No recording devices pictures

Barricades-”Red & Yellow tape or chine

Cranes – Signals and rigging

14

Job-wide Safety Meeting

Will be on the third Wednesday of month.

EVERYONE working on site is required to attend.

English is on the south and Spanish is on the north side.

15

Employee Recognition Program

Rewards and awards will be extended to:

Workers who consistently and diligently demonstrate

planning and safe work practices

Supervisors consistently and effectively manage their

work crew’s safety practices

16

Overall Safety

MSDS sheets

Do not take shortcuts – this is how people get

injured and killed

Open door Policy

Each individual on the project is responsible

for safety.

Bring any unsafe acts to our attention

17

Our Goal

Zero Lost time Accidents

Zero OSHA Recordable Accitents

No Property Damage

This to be the SAFEST project you

have ever worked on!