Ortiz.james
-
Upload
nasapmc -
Category
Technology
-
view
13.768 -
download
0
Transcript of Ortiz.james
Page 1
Connect the Dots
Dr. James Ortiz, Director Independent Program Assessment Office
Seventh Annual NASA Program Management Challenge 2010
February 10, 2010Used with Permission
Page 2
Introduction
• The Independent Program Assessment Office (IPAO) manages the independent review of the Agency's Programs and projects at life-cycle milestones to ensure the highest probability of mission success.
•This presentation provides an overview of the Agency’s policy context for the Agency Independent Life Cycle Review process (The “Why”, the “What”, and the “How”).
Page 3
Outline
• Connecting the dots on the Agency policy context – The “Why”
» NPD 1000.0; NPD 1000.5 – The “What”
» NPR 7120.5D NID; NPR 7123.1 – The “How”
» SRB Handbook » IPAO System Operating Procedures
• Summary
Page 4
Agency Policy Context for Independent Review
Page 5
Policy Flow-down
NPD 1000.0NPD 1000.3NPD 1000.5
NPD 7120.4
NPR 7123.1A NPR 7120.5Dand NID
IPAO 1000IPAO MANAGEMENT
PLAN
NASA -SP 2009 -10 -015 -HQ SRB HANDBOOK
IPAO 2000STANDARD OPERATING
PROCEDURE
NPD 8700.1 NPD 8900.5A Mission Support Office
OSMA Directives OCHMO Directives Support OrganizationDirectives
21 3 4 5
LEGEND:
1: ENGINEERING REQUIREMENTS2: PROGRAM/PROJECT MANAGEMENT REQUIREMENTS3. SAFETY AND MISSIONASSURANCE REQUIREMENTS4. HEALTH AND MEDICAL REQTS5. MSO FUNCTIONAL REQTS6. MD REQUIREMENTS7. CENTER REQUIREMENTS
NASA -SP -6105SYSTEMS ENGINEERING
HANDBOOK
Center EngineeringRequirements
Mission DirectorateRequirements
7 6
DIRECT
INDIRECT
Page 6
The “Why”
Page 7
The Governance and Strategic Management Handbook (NPD 1000.0A)
“NASA governance and strategic management provide the discipline and rigor to enable success of NASA’s Mission- …. Mission success delivers on our commitment to be good stewards of the resources entrusted to us by the taxpayer. To enable Agency-wide accomplishments, NASA’s governance framework is founded on the following tenets: • …..NASA’s governance principles that provide this framework are:• Lean governance. • Clear roles, responsibility and decision making. • Strategic acquisition.
• Checks and balances. ……There are many process-related checks and balances built into NASA’s way of doing business. They range from peer reviews conducted at the lowest level to oversight reviews conducted by the Agency’s Program Management Council. Three checks and balances of particular importance at the program or project level are: the independent life-cycle review process, the process for tailoring a specific prescribed requirement, and the Dissenting Opinion process.”
Page 8
Why Independent Review The Governance and Strategic Management
Handbook (NPD 1000.0A)
The independent life-cycle review process provides a comprehensive review of programs and projects at each life-cycle milestone by competent, independent individuals. The purpose of these reviews is to provide:
1. Agency wants P/p to receive independent assurance that they are on-track
2. NASA senior management wants: – Independent validation at key decision points of the
Program/project’s readiness to proceed into the next phase of its life-cycle
– Externally-imposed impediments to Program/project success to be removed
3. Agency needs to give external stakeholders assurance we can deliver to our commitments
4. Significant additional benefit is that preparation for the review milestone allows for a holistic examination by the Program/project and the review team
Page 9
9
Policy for NASA AcquisitionNPD 1000.5
• NPD 1000.5A calling for the Joint Confidence Level (JCL) analysis became effective in January 2009
• Policy is directed to ensure appropriate level of funding is provided and maintained to increase probability of success of the Agency’s Programs and Projects
• Requirements – (a) Programs are to be baselined or rebaselined and budgeted at a confidence level
of 70% or the level approved by the decision authority of the responsible Agency-level management council. For a 70% confidence level, this is the point on the joint cost and schedule probability distribution where there is a 70% probability that the project will be completed at or lower than the estimated amount and at or before the projected schedule. The basis for a confidence level less than 70% is to be formally documented.
– (b) Projects are to be baselined or rebaselined and budgeted at a confidence level consistent with the program’s confidence level.
– The program's or project's proposed cost and schedule baseline are to be assessed by an independent review team. The program or project is to present and justify its resulting cost and schedule to the decision authority of the responsible Agency-level management council. The independent review team is to discuss with the decision authority its key concerns with the plans and baselines proposed by the program or project.
Page 10
The “What”
Page 1111
NPR 7120.5D NIDIndependent Review Requirements
• Provides the basis for how NASA execute its space flight programs and projects.
• Provided a standardized life cycle review process that is built around Key Decision Points (KDP).
• Formalized the Technical Authority, Dissenting Opinion Resolution, and Waiver processes.
• Defines the Independent review policy requirements Standardizes the Standing Review Board concept across NASA Combines technical (7123) and programmatic reviews into one Boardthe Standing Review Board (SRB)
One independent review board for each program or project Conducts all 7120.5-required independent reviews for that
program or project throughout its life cycle Implemented by the IPAO for all Programs, Category 1 Projects
and Category 2 projects with a life-cycle cost > $250M
Page 12
Project Life Cycle (NPR 7120.5)
Page 13
Project Life Cycle (NPR 7120.5)
Page 14
NPR 7123.1 Systems Engineering Technical Review Requirements
• NPR 7123.1A – Systems Engineering Processes and Requirements Articulates and establishes the requirements on the implementing
organization for performing, supporting, and evaluating systems engineering
This systems approach is applied to all elements of a system and all hierarchical levels of a system over the complete project life cycle
• 5.2.1.3 A technical review is an evaluation of the project, or element thereof, by a knowledgeable group for the purposes of: Assessing status of and progress toward accomplishing planned activities. Validating technical tradeoffs explored and design solutions proposed. Identifying technical weaknesses or marginal design and potential
problems (risks) and recommending improvements and corrective actions. Making judgments on activities’ readiness for follow-on events, incl
additional future evaluation milestones to improve likelihood of successful outcome.
Making assessments and recommendations to project team, Center, and Agency management.
Providing historical record that can be referenced of decisions that were made during these formal reviews.
• Entrance and Success criteria for each life-cycle milestone are contained in Appendix G.
Page 15
The “How”
Page 16
The SRB HandbookThe How
• The SRB is written to provide guidance to the NASA Program and project (P/p) community and the Standing Review Boards (SRBs) regarding expectations, processes, products, timelines, and working interfaces with Mission Directorates, P/p, Centers, other review organizations, and the Management Councils.
• The SRB handbook was published by PA&E/IPAO with concurrence from OCE
IR-16
Page 17
SRB Handbook Contents
• The SRB Handbook consist of six sections – Section 1: Context for Independent Lifecycle Review (ILCR) Process. Objectives,
intent, and governance of the Standing Review Boards (SRB).– Section 2: High level principles that govern the SRBs. Independence and issue
resolution. Points to Annex with Agency policy for “Review Board Composition, Balance and Conflict of Interest”.
– Section 3: Scope and expectations of ILCR. Provides guidelines (roadmaps) for application of review criteria in NPR 7120.5 as a function of the lifecycle stage of P/p, the types of mission (Robotics versus Human Spaceflight), and type of Program ( tightly coupled or loosely coupled).
– Section 4: SRB Initiation process. Roles and responsibilities for Chair/RM nomination, team composition and staffing, and Terms of Reference (TOR).
– Section 5: SRB Products. Technical and programmatic assessments, findings and recommendation, briefings and reports.
– Section 6: Notional review timeline. Describes the review phases for a typical review. – Appendices: Agency Independence Policy, PIR guidance
IR-17
Page 18
Example of Section 3(SRB engagement roadmap)
IR-18
Operations
Pre-Phase A Phase B Phase E
SDR PDR
(PNAR) (NAR)
Key Decision Points KDP A KDP B KDP C KDP D KDP E
SRB Participation Case-by-case
Full Board Full Board Full Board Full Board Chair and Member
Subset 3
Full Board Chair and Member
Subset 3
Chair and Member
Subset 3
Chair and Member
Subset 3
Chair and Member
Subset 3
Chair and Member
Subset 3
Sample Assessments
Requirements
Preliminary Functional and Performance Baseline ; Requirements Traceability Report; SEMP
Flowdown to Functional Elements; System Requirements Document
Flowdown to Functional Elements, Descope Plans
Any Changes, Flowdown to Functional Elements, Descope Plans
Production processes , certified design
Integration Plan and Procedures
System meets acceptance criteria and has been verified and validated
Phase E, Descope plans
Flight operations are certified to proceed
Launch system and spacecraft/ payloads readiness for launch
Flight performance reporting
Technical 5
Key Technolgies,TRL, MOEs, MOPs
Preliminary Approach, TRL, Technology Devlpt. Maturity Assessment Plan (TDMAP), Software Devlpt. Plan (SDP)
Mission System Architecture, TRL, TDMAP, SEMP, SDP
Baseline: Systems Engineeering Mgt Plan, Design meets performance
Design meets performance, TRL
Design documentation, Production Plans
Previous component, subsystem and system tests have been verified to support integration
Technical data package, Certification package
All waivers and anomalies have been closed; Operational procedures and contingency planning
Hardware and software systems are configured for flight
Launch system and spacecraft/ payloads readiness for launch
Performance report and Anomaly resolution
Integrated cost and
schedule 6
ROM Cost Schedule Estimates
ROM Integrated Cost Schedule Estimates
Preliminary: BOEs IMS Cost/Budget UFE, CADRe WBS ICE
Baseline: BOEs IMS Cost/Budget UFE, CADRe JCL , Detail schedules, ICE
Performance against plans, EVM, UFE , LLIL
Production Plans
Performance against plans, EVM, UFE, JCL
Remaining liens or open items and plans for closure
Performance against plans, EVM, UFE
Performance against plans, EVM, UFE
Resources
Preliminary: Facilities Workforce
Preliminary: Facilities Workforce
Preliminary: Facilities Workforce
Baseline: Facilities Workforce
Facilities Workforce
Facilities Workforce
Facilities Workforce
Facilities Workforce
Facilities Workforce
Facilities Workforce
Risk
Preliminary Risks
Preliminary Risks
Preliminary: Risk Mgt Plan Risk list Mitigation
Baseline: Risk Mgt Plan Risk list Mitigation
Risk List Mitigation
Risk List Mitigation
Risk List Mitigation
Risk List Mitigation
Risk List Mitigation
Risk List Mitigation
Management
Preliminary: Approach
Preliminary: Plans
Preliminary: Project Plans
Baseline: Project Plans
Performance against plans
Production Engineering and Planning
Performance against plans
Performance against Plans
Phase E Mgt Plan
Performance against plans
Reporting Venues
Project x x x x x x x x
Program 4 x x x x x x x x
CMC 4 x x x x x x x x
DPMC x x x 4 x 4 x x x 4 x
APMC Cat 1 Cat 1 Cat 1 Cat 1
6. Compliance with NPR 1000.5.
NASA Life Cycle Phases
Formulation ImplementationPre-Systems Acquisition Systems Acquisition
Phase A
SIR ORR FRR 2 LRR 2
5. Compliance with NPR 7123.1 review entrance and success criteria will be assessed.
SAR
Notes:
1. PRRs are only needed when multiple flight system copies are being developed; timing is discretionary.
Reviews MCR 1 SRR CDR PRR 1 PFAR 2
Phase C Phase D
4. The SRB chair and RM will make themselves available to support these interim briefings.
3. Chair determines which members should attend, including themselves.
2. LRRs, FRRs, PFARs are performed by the Mission Management Team (MMT); the SRB Chair (and/or Designee) attend as non-voting observers.
Page 19
Example from Section 4 (SRB Formulation )
IR-19
SRB Initiation Schedule prepared monthly for the APMC
MDAANominates Chair
IPAO RMAssignment
Nominations vetted with all Approval Authorities (MDAA, DA, TA, PA&E)
Chair/RM developSRB Membership List
Chair/RM develop ToRand review with DA and TA
Proceed with SRB Reviews
* For Programs, Cat.1 and Cat 2 (LCC>$250M) Projects only
CDNominates Chair
Center RMassignment
ProgramsCat 1 &
Cat 2 Projects>$250M
Cat 3 &Cat 2 Projects
<$250M
IPAO RMAssignment
CDNominates Chair
MDAA/DA/TA/PA&E*Approval/Concurrence ?
Reiterateselection stepswith new Chair
nomination
MDAA/DA/TA/PA&E*Approval/Concurrence ?
Reiterate asnecessary to
obtain Approvals
Mission Directorate Host Center
IPAO SRB
Joint Effort
No
No
Yes
YesParticipating Organizations
Selection of the SRB Chair and RM
SRB Staffing and ToR Preparation
SRB Initiation Schedule prepared monthly for the BPR
MDAANominates Chair
IPAO RMAssignment
Nominations vetted with all Approval Authorities (MDAA, DA, TA, PA&E) and cleared for OCI/PCI.
Chair/RM developSRB Membership List
Chair/RM develop ToRand review with DA and TA
Proceed with SRB Reviews
* For Programs, Cat.1 and Cat 2 (LCC>$250M) Projects only
CDNominates Chair
Center RMassignment
ProgramsCat 1 &
Cat 2 Projects>$250M
Cat 3 &Cat 2 Projects
<$250M
IPAO RMAssignment
CDNominates Chair
MDAA/DA/TA/PA&E*Approval/Concurrence ?
Reiterateselection stepswith new Chair
nomination
MDAA/DA/TA/PA&E*Approval/Concurrence ?
Reiterate asnecessary to
obtain Approvals
Mission Directorate Host Center
IPAO SRB
Joint Effort
No
No
Yes
YesParticipating Organizations
Selection of the SRB Chair and RM
SRB Staffing and ToR Preparation
and cleared for OCI/PCI.
Nominations vetted with all Approval Authorities
Page 20
Handbook Status
• Initial version of Standing Review Board (SRB) Handbook (HB) developed October 2007 by Agency team (IPAO lead and representative from each Center).
• SRB HB on hold pending review of Federal Advisory Committee Act (FACA) regulations and independence policy requirements.
• SRB HB on hold for completion of NPR 7120.5D NID (~February 2009).• NID-aligned version of the SRB Handbook released for PPMB review on Sept
25, 2009 ( 2 week review).• Baseline version of SRB HB published ( December 2009)• Next revision to be published with NPR 7120.5E
IR-20
Page 21
IPAO
The NASA organization responsible for the agency independent life cycle review process
• Enables independent review of programs and projects to ensure highest probability of mission success.
• Ensures objectivity, quality, integrity and consistency of independent review process per NPRs 7120.5D and 7123.1A.
Works with SRB Chair and Convening Authorities Reviews SRB products to ensure they meet Agency
expectations• Provides Review Manager, cost, schedule and other
programmatic analysis SRB members• Provides advice and recommendations to Agency
on program and project policies Book Manager for Agency’s SRB Handbook
Page 22
IPAO Standard Operating ProcedureDetail processes
• The Standard Operating Procedure (SOP) documents the Independent Program Assessment Office (IPAO) process for conducting Independent Life-Cycle Reviews (ILCRs).
• The SOP is a guide for the IPAO personnel when conducting ILCRs of the Agency’s programs and projects.
• The purpose of this document is to ensure ILCR quality and efficiency through the development of common definitions and processes.
Page 23
Individual Review BudgetToR, Cost Plan, Schedule PlanChair and Team Nomination and Guidance Letters Review Schedule Contract Task Statement R&R for SRB
Monitor AgencyBaseline Program/
Project Review Determine IPAO
Review Budget Review Assignments
PLANNING PREPARING REPORTING CLOSING-OUT
Continuous 1- Month2-3 Months2- Months 1-3 Months
ICE/ICA/ISA SRB Findings RFA Recommendations
Receive CADRe Inputs SRB Kick-Off Meetings Attend Reviews Attend Site Visit Develop ICE/ICA/ISA
Verbal Pre-Briefings to P/p Write one-page summary Write the Report Prepare the Summary
Briefings Present the Briefings:
- Program/ project - CMC- MD PMC- APMC (if required)
RM/CA/SA Assignments One Page Summary SRB Report RRD ReportSRB Briefings
Review Summary Contracts Close-out by COTR Review Records RRD Report Process improvements
REVIEWING
Review Closeout Customer
Feedback Develop Lessons Learned Process Review and Improvement Administrative Close-out Team Recognition
P/p Documentation Cost & Schedule
Documentation Program/Project Briefings
Agency Review Schedule Review Chair Nomination
Minutes/Decisions/Actions Agency/Directorate/CentersDocumentation & Requirements
Initiate Contact and Determine Review Budget Identify and obtain approval of SRB Chair/RM/SRB members Determine funding mechanism Develop the TOR Develop Schedule/Logistics
of the Review Develop the Cost Plan Develop the Schedule Plan
P R O D U C T S
I N P U T S
SRB Briefings to Program/Project
Individual Review BudgetToR, Cost Plan, Schedule PlanChair and Team Nomination and Guidance Letters Review Schedule Contract Task Statement R&R for SRB
Monitor AgencyBaseline Program/
Project Review Determine IPAO
Review Budget Review Assignments
PLANNING PREPARING REPORTING CLOSING-OUT
Continuous 1- Month2-3 Months2- Months 1-3 Months
ICE/ICA/ISA SRB Findings RFA Recommendations
Receive CADRe Inputs SRB Kick-Off Meetings Attend Reviews Attend Site Visit Develop ICE/ICA/ISA
Verbal Pre-Briefings to P/p Write one-page summary Write the Report Prepare the Summary
Briefings Present the Briefings:
- Program/ project - CMC- MD PMC- APMC (if required)
RM/CA/SA Assignments One Page Summary SRB Report RRD ReportSRB Briefings
Review Summary Contracts Close-out by COTR Review Records RRD Report Process improvements
REVIEWING
Review Closeout Customer
Feedback Develop Lessons Learned Process Review and Improvement Administrative Close-out Team Recognition
P/p Documentation Cost & Schedule
Documentation Program/Project Briefings
Agency Review Schedule Review Chair Nomination
Minutes/Decisions/Actions Agency/Directorate/CentersDocumentation & Requirements
Initiate Contact and Determine Review Budget Identify and obtain approval of SRB Chair/RM/SRB members Determine funding mechanism Develop the TOR Develop Schedule/Logistics
of the Review Develop the Cost Plan Develop the Schedule Plan
P R O D U C T S
I N P U T S
SRB Briefings to Program/Project
How is it done? (IPAO Process)
Page 24
SOP:Sample SRB Engagement Timeline
PDR: 2/11/10 Site Visit: 5/11/10 - 5/21/10 KDP: 6/11/10 - 6/21/10SRB KO: 10/14/09
PDR KO:12/1/09
24
Page 25
• The independent life cycle review process is an integral part of the Agency’s check and balances built into the NASA governance structure and complements the programmatic and technical lines of command and authority.
• The independent lifecycle review process is encoded as part of NASA policy direction; its requirements are stipulated in policy requirements; and guidance to reviews team and implementing personnel is provided in handbooks and operating procedures.
• Its processes are continuously assessed for improvement by IPAO and its stakeholders.
• The independent lifecycle review process helps ensure the highest probability of success of the Agency’s program and projects.
Summary