Office 1 1 742,40 m 2 Office 2 2 621 m 2 «ORGHIMproject» Design Institute

Transcript of «ORGHIMproject» Design...

Page 1: «ORGHIMproject» Design Instituteorghim.ua/en/services/design/copy2_of_PresentationORGHIMprojectDesignInstitute.pdf2 «FOK PK» Software system engineering of isolated foundations

Office 1

1 742,40 m2

Office 2

2 621 m2

«ORGHIMproject» Design Institute

Page 2: «ORGHIMproject» Design Instituteorghim.ua/en/services/design/copy2_of_PresentationORGHIMprojectDesignInstitute.pdf2 «FOK PK» Software system engineering of isolated foundations

Corporative Structure of Private Joint-Stock Company Severodonetsky ORGHIM

Page 3: «ORGHIMproject» Design Instituteorghim.ua/en/services/design/copy2_of_PresentationORGHIMprojectDesignInstitute.pdf2 «FOK PK» Software system engineering of isolated foundations

About the Institute

ORGHIMproject Design Institute (DI

ORGHIMproject) was established in 2009

based on Special Design Bureau (was

established in 2004).

Activities of the Institute include

practically all system design fields, in

particular:

• Chemical industry

• Oil refining and gas processing

• Oil and gas field development

• Petrochemical industry

• Hydrocarbons storage and trans-

shipment terminals

• Power generating industry

• Environment and infrastructure

protection

Page 4: «ORGHIMproject» Design Instituteorghim.ua/en/services/design/copy2_of_PresentationORGHIMprojectDesignInstitute.pdf2 «FOK PK» Software system engineering of isolated foundations

Types of activities

Activities of production departments:

- Technical and economic assessment;

- Technical and economic calculations;

- Feasibility studies;

- Business plan;

- Projects (design documentation for foreign Customers);

- Basic and detail design adaptation to the Customer country

standards;

- General design engineering;

- Preparation of design assignment and technical attachments thereto;

- Preparation of technical requirements for Customer tenders;

- Detailed design engineering;

- As-built documents;

- Cost estimate documents;

- Equipment manufacturing supervision;

- Equipment acceptance;

- Construction supervision;

- Project supporting during expert examination;

- Service Package for construction management;

- Project adaptation to infrastructure of the Customer production site;

- Survey and inspection of production facilities;

- Project implementation risk assessment;

- Development of recommendations and procedures;

- Other.

Activities of auxiliary departments:

- Hardware and software providing;

- Providing with standards and norms;

- Development of 3D design data base;

- Work planning;

- Marketing and PR;

- Project issuing

Page 5: «ORGHIMproject» Design Instituteorghim.ua/en/services/design/copy2_of_PresentationORGHIMprojectDesignInstitute.pdf2 «FOK PK» Software system engineering of isolated foundations

Organizational chart of ORGHIMproject Design Institute

Page 6: «ORGHIMproject» Design Instituteorghim.ua/en/services/design/copy2_of_PresentationORGHIMprojectDesignInstitute.pdf2 «FOK PK» Software system engineering of isolated foundations

Personnel of ORGHIMproject Design Institute

0 5 10 15 20 25 30 35 40

Group for computer-aided design

Equipment purchasing group

Translation group

Planning department

Archives

Marketing and PR department

Technical department

Environment protection group

Plot plan group

Interconnections group

Group for low-voltage electric devices

Engineering documentation development group

Heat insulation group

Cost estimation department

Civil department No. 2

Civil department No. 1

HVAC and dust cleaning department

Water supply and sewage department

Electrical department

Instrumentation department

Process department No. 4

Process department No. 3

Process department No. 2

Process department No. 1

Project managers

Main specialists

Administration

Total Number of the Design Institute employees – 359 persons

Average age of the employees – 43 years old

Page 7: «ORGHIMproject» Design Instituteorghim.ua/en/services/design/copy2_of_PresentationORGHIMprojectDesignInstitute.pdf2 «FOK PK» Software system engineering of isolated foundations

Authorization documents

Ukraine Russian Federation Republic of Kazakhstan

Republic of Belarus Republic of Uzbekistan

Page 8: «ORGHIMproject» Design Instituteorghim.ua/en/services/design/copy2_of_PresentationORGHIMprojectDesignInstitute.pdf2 «FOK PK» Software system engineering of isolated foundations

Quality management system

Page 9: «ORGHIMproject» Design Instituteorghim.ua/en/services/design/copy2_of_PresentationORGHIMprojectDesignInstitute.pdf2 «FOK PK» Software system engineering of isolated foundations

Software

Item No SOFTWARE description SOFTWARE assignment

1 2 3

1 «Start Prof» Pipe strength calculation

2 «FOK PK» Software system engineering of isolated foundations for frame building columns on soil and pile sub foundation

3 PK «Ecolog»

Air pollution estimates (Unified Program of air pollution estimation ). It implements the provision « Analysis of air pollutant

concentration found in the industrial emissions (General reference documentation - 86). State Committee for

Hydrometeorology

4 «ProTreat» Tools for virtual reality modeling and calculation of facilities in the gas purification industry

5 «GidrV»Program for hydraulic ducts calculation. It is provided for computer calculation of ventilation and mechanical forced

aspiration systems as well as for free ventilation systems

6 «ACCORD» POS –subsystem АВС Development of the project design and work execution plan

7 «AutoCAD» Graphic editor

8 «Passat» Stability and strength design of tanks, vessels and their elements

9«Primavera P6 Enterprise Project

Portfolio Management» Project management

10 «Pro/II» Comprehensive process simulation

11«Autodesk Robot Structural Analysis

Professional 2018»Software package for structural calculation and engineering

12«Autodesk Building Design Suite

Premium 2019 Russian»Software complex for 3D design, modeling visualization

13 «Ecolog Noise» Noise impact assessment on environment and evaluation of noise exposure outgoing from area sources at any point

14 «IS PARAGRAPH» Information and reference searching system of Kazakhstan regulatory documents (Codes and Specifications )

Page 10: «ORGHIMproject» Design Instituteorghim.ua/en/services/design/copy2_of_PresentationORGHIMprojectDesignInstitute.pdf2 «FOK PK» Software system engineering of isolated foundations

Software (continued)

Item No Software description Software assignment

1 2 3

15 «LIRA» Software system for automated civil structure engineering

16 «FOK COMPLEKS» Software system engineering of isolated foundations for frame building and facilities columns as well as strip foundations

17 «Dym» Calculation of smoke forced and exhaust ventilation systems

18 «Potoк» Heating system engineering

19 «VSV» Ventilation system calculation

20 «RTI» Calculation of building heat loss

21 «KALOR» Calculation of calorific installations

22 «ERA» Air emission calculation (according to the Norms of the Republic of Kazakhstan)

23 «Stroi-Inform PRO» Information and reference searching system of Ukrainian regulatory documents

24 «Mining works» Program for hazardous emission calculation for the equipment used in the open pit mining

25 «Isolation» Optimum choice of heat insulating structures and materials, calculation of minimum required heat insulating layer,

selection of product size, estimation of work scope and total amount of materials, design documentation release

26 «Flowmeter ISO»

Software system for calculation of media flow rate according to GOST8.586.(1, 2, 3, 4, 5) – 2005, to ISO 5167 (1, 2,

3:2003) and AGA-3 REPORT No 3 (for natural gas) as well as for flow rate calculation by means of special flow

restrictors under Regulatory document 50-411-83

27 «Grand-Smeta» (Russia) Software system for cost estimating and checking as well as for creating report of completed works according to various

certificate forms, making up of estimate documents in full range to estimate the construction cost

28 «NormaCS» Information and reference searching system of RF regulatory documents

29 «PIR System» (Russia) Computer system to estimate design and survey work cost

Page 11: «ORGHIMproject» Design Instituteorghim.ua/en/services/design/copy2_of_PresentationORGHIMprojectDesignInstitute.pdf2 «FOK PK» Software system engineering of isolated foundations

Software (continued)

Item No. Software deswcription Software assignment

1 2 3

30 «АВС 4» (Kazakhstan) To develop estimate and life documentation by all members of investment process

31 «IBK» Program for computer cost assessment of new construction, debottlenecking, modernization and retrofitting

32 «Toksy+ RISK» Software system to estimate the accident consequences involving emission release and risk values

33 «WinSteel 7 Prof» Electronic international steel grade translator which is provided for prompt and easy search of analogue of foreign steel

type

34 «Start Prof» Pipe strength calculation

35 «Prevalve» Calculate and select types of direct action safety valves (and safety valve manifolds equipped with switching devices)

which are installed on vessels, tanks and in process pipelines

36 «Hydrosystem» To perform thermal and hydraulic calculations as well as to select diameters of the pipelines which are used to pump

liquid or gaseous products and gas-liquid mixtures

37 «Fire SAFETY» Explosion and fire safety design and reference system

38 «Bentley AutoPLANT 3D» 3D design system for pipelines, equipment, steel structures

39 «АTP-ECOLOG» Program for emission amount released by fleet vehicles and vehicles production plants

40 «VANISH PAINT» Program is designed to calculate emission release while applying vanish paint materials

41 «WELDING» Provided for calculation of emission release during welding

42 «Hazard class calculation» Calculation of waste hazard class for the environment according to “Criteria”

43 «MPE-ECOLOG» Program for development and formation of maximum permissible emission draft standard matrix

44 «WASTES» Program for preparation of standard drafts for waste production and limits

45 «VetCAD» AutoCad utility set is targeted at the engineers that are involved into industrial and civil building design

Besides Specialists perform some works connected with software PDMS AVEVA and Tekla Structures

Page 12: «ORGHIMproject» Design Instituteorghim.ua/en/services/design/copy2_of_PresentationORGHIMprojectDesignInstitute.pdf2 «FOK PK» Software system engineering of isolated foundations

COMPLETED PROJECTS OF NOTE

(SINCE 2014)

Page 13: «ORGHIMproject» Design Instituteorghim.ua/en/services/design/copy2_of_PresentationORGHIMprojectDesignInstitute.pdf2 «FOK PK» Software system engineering of isolated foundations

AMMONIA/METHANOL/UREA COMPLEX, UNIT FOR RAW

(RIVER) WATER TRATMENT

PRODUCTION CAPACITY: 1,200 m3/hr.

Client: Ammoni OJSC (Kazan, Russian Federation)

Phase: Design (Stage P) & Detailed Design

Year of completion: 2014

Page 14: «ORGHIMproject» Design Instituteorghim.ua/en/services/design/copy2_of_PresentationORGHIMprojectDesignInstitute.pdf2 «FOK PK» Software system engineering of isolated foundations

COMPLEX FOR VGO HIGH CONVERSION AT

KHABAROVSK OIL REFINERY

Client:

Technicas Reunidas (Madrid, Spain)

Phase:

Detailed documents (adaptation to existing Russian Federation

norms and regulations)

Year of completion: 2014

Page 15: «ORGHIMproject» Design Instituteorghim.ua/en/services/design/copy2_of_PresentationORGHIMprojectDesignInstitute.pdf2 «FOK PK» Software system engineering of isolated foundations

SECOND TRAIN OF LOW-TONNAGE UNIT (MTU) FOR MOTOR

FUELS OF EURO-5 EMISSION STANDARD

Client: Condensate JSC (Aksay, Republic of Kazakhstan)

Phase: Design & Detailed documents

Year of completion: 2015

Page 16: «ORGHIMproject» Design Instituteorghim.ua/en/services/design/copy2_of_PresentationORGHIMprojectDesignInstitute.pdf2 «FOK PK» Software system engineering of isolated foundations

M-3 UREA PLANT. TECHNICAL REVAMP TO INCREASE

CAPACITY UP TO 1,600 T/DAY AT

PrJSC SEVERODONETSK AZOT ASSOCIATION

Client: Casale SA (Lugano, Switzerland)

Phase: Design & Detailed documents

Year of completion: 2015

Page 17: «ORGHIMproject» Design Instituteorghim.ua/en/services/design/copy2_of_PresentationORGHIMprojectDesignInstitute.pdf2 «FOK PK» Software system engineering of isolated foundations

Construction of Complex for gas extraction, treatment and

liquefaction, offloading of LNG and gas condensate at

South Tambey Gas Condensate Field

Client: BRANCH OF GENERAL PERTNERSHIP "SOUTH TAMBEY

LNG“

(Sabetta Settlement, Yamal District, Yamalo-Nenets Autonomous

District, Russian Federation)

Rendering services in field of engineering and technical management

and supporting documents preparation meeting SRO norms and

regulations as well as RF norms and regulations in course of

construction works

Year of completion: 2016

Page 18: «ORGHIMproject» Design Instituteorghim.ua/en/services/design/copy2_of_PresentationORGHIMprojectDesignInstitute.pdf2 «FOK PK» Software system engineering of isolated foundations

METHANOL AND AMMONIA PLANT COMPLEX WITH CAPACITY

OF 450,000 TPY AND 135,000 TPY RESPECTIVELY

Client: JSC Shchekinoazot (Shchekino, Russian Federation)

Rendered complex of works:

- FEED;

- Investment feasibility study;

- Technical maintenance, acceptance and examination of Licensor

basic design;

- Development of design documents;

- Development of detailed documents;

Including General Designer functions.

Year of completion: 2017

Page 19: «ORGHIMproject» Design Instituteorghim.ua/en/services/design/copy2_of_PresentationORGHIMprojectDesignInstitute.pdf2 «FOK PK» Software system engineering of isolated foundations

POLYETHYLENE PRODUCTION PLANT CONSTRUCTION

PROJECT (ASTRAKHAN REG, RUSSIAN FEDERATION)

Client: FINPROM LLC

(Moscow, Russian Federation )

Phase: Feasibility study

year of completion : 2018

Page 20: «ORGHIMproject» Design Instituteorghim.ua/en/services/design/copy2_of_PresentationORGHIMprojectDesignInstitute.pdf2 «FOK PK» Software system engineering of isolated foundations

Revamping Project of Water Treatment units of Electrical

stations k.94, k.94/1, k.94/3, k.199a, Water Supply facility of

Power Production.

Client: Shchekinoazot UCC (Shchekino, Russian Federation)

Stage: Design (Stage P)

Year of completion: 2018

Page 21: «ORGHIMproject» Design Instituteorghim.ua/en/services/design/copy2_of_PresentationORGHIMprojectDesignInstitute.pdf2 «FOK PK» Software system engineering of isolated foundations

REVAMPING OF C.5026 OF NON-CONCENTRATED NITRIC ACID

PRODUCTION FACILITY FOR PRODUCTION RATE INCREASE

Заказчик: "KuibyshevАzot" PJSC (Togliatti, Russian Federation)

Stage: Design (Stage P) & Detailed Design

Year of Completion : 2018

Page 22: «ORGHIMproject» Design Instituteorghim.ua/en/services/design/copy2_of_PresentationORGHIMprojectDesignInstitute.pdf2 «FOK PK» Software system engineering of isolated foundations

Projects in Progress

No. Client Region Works

1 Zhaikmunai LLP

Uralsk,

Republic of

Kazakhstan,

Framework agreement on "Cooperation in implementation of Client projects associated

with construction of new process units, reconstruction and modernization of existing

process units (facilities), site facilities, utilities and infrastructure of Client"

2 FINPROM LLCMoscow,

Russian Federation

Feasibility study

Astrakhan Polyethylene Plant

3 "KuibyshevАzot" PJSCTogliatti,

Russian Federation

-Technical Inspection of existing constructions

-Design Documentation Package development and Authority Engineering for State

Expertise Examination

-Detail design and engineering survey for

Revamping of k.502b Weak Nitric Acid production plant with capacity increasing

4 "KuibyshevАzot" PJSCTogliatti,

Russian Federation

-Technical Inspection of existing constructions

-Design Documentation Package development and Authority Engineering for State

Expertise Examination

Revamping of UKL-7 Weak Nitric Acid production plant based on, capacity 120 000 tpy

5 Shchekinoazot UCC Shchekino,

Russian Federation

Detailed Design for the Revamping Project of Water Treatment units of М-450 к.956/07,

Water Supply facility of Power Production

6 Shchekinoazot UCCShchekino,

Russian Federation

Detailed Design for Revamping Project of Water Treatment units of Electrical stations

k.94, k.94/1, k.94/3, k.199a, Water Supply facility of Power Production

7 Shchekinoazot UCCShchekino,

Russian FederationDetailed Design for construction of the new piperack p.M-1

8 Kemerovo Azot JSCKemerovo,

Russian Federation

Detail Design for the Revamping of Ammonia Plant with installation of Flash Gases

Treatment Unit

9IMPaC Offshore Engineering

GmbHGermany, Hamburg

Basic&Detail Design

LPG Loading Jetty, Iran

10 Condensate JSC

Aksay,

Republic of

Kazakhstan

Detail Design for the Reactive power compensation unit in 6 KV power grid ЭП-1502

and others

Page 23: «ORGHIMproject» Design Instituteorghim.ua/en/services/design/copy2_of_PresentationORGHIMprojectDesignInstitute.pdf2 «FOK PK» Software system engineering of isolated foundations

Health and Safety Policy

Priority of employees life and health, strict observance of industrial safety requirements are fundamental principles in the activity of

society.

There is an occupational health and safety management system functioning in Private Joint-Stock Company Severodonetsky

ORGHIM.

The Administration undertakes to seek constantly to improve working conditions and safety of all employees of the Company, failure-

free operation.

Employees are obliged to know and follow the requirements of regulatory and legal acts on occupational health and safety, take care

of personal safety and health, as well as the safety and health of others in the course of work performance.

The Company's policy in the field of occupational health and safety is aimed at :

- providing complex solution of tasks and problems of work safety in system of professional, industrial and environmental safety;

- providing the employees with special clothing, safety shoes, other means of individual and collective protection as prescribed by

law;

- informing employees about working conditions, availability of hazardous and harmful factors in the workplace;

- controlling of impact of hazardous and harmful production factors on the health of workers performing work in conditions of

increased danger, as prescribed by law, not allowing persons having medical contra-indications to work ;

- applying methods of economic incentives and other forms of motivational regulation;

- improving the culture of production, forming and supporting the competence of employees of all levels in the field of occupational

health and safety through awareness-raising activities and regular training.

The main purpose of labor safety is to minimize the impact of production process on human health and environment, to eliminate

accidents and occupational diseases and, on this basis, ensure occupationally safe working conditions at the enterprise, attractive to

business partners.

The Administration undertakes to finance as needed the activities aimed at improving working conditions, preventing occupational

injuries, occupational diseases and accident rate.

Page 24: «ORGHIMproject» Design Instituteorghim.ua/en/services/design/copy2_of_PresentationORGHIMprojectDesignInstitute.pdf2 «FOK PK» Software system engineering of isolated foundations

Clients and Partners

Page 25: «ORGHIMproject» Design Instituteorghim.ua/en/services/design/copy2_of_PresentationORGHIMprojectDesignInstitute.pdf2 «FOK PK» Software system engineering of isolated foundations

Contact information

Head Office of Private Joint-Stock Company "Severodonetsky ORGHIM“

Location / Mailing address: 32, prospect Gvardeisky, Severodonetsk,

Lugansk Region, 93411, Ukraine

Tel.: +38 (06452) 2-85-25

Fax: +38 (06452) 2-85-19

e-mail: [email protected]

Design Institute «ORGHIMproject»

Location / Mailing address: 6, Nauki St., Severodinetsk,

Lugansk Region, 93406, Ukraine

Tel.: +38 (0645) 70-14-56

Fax: +38 (06452) 5-49-30

e-mail: [email protected]