Orcst - Variation and Final Acc1
-
Upload
daniel-evans -
Category
Documents
-
view
14 -
download
4
description
Transcript of Orcst - Variation and Final Acc1
OMISSION ADDITIONAL
ITEM DESCRIPTION UNIT RATE TOTAL RATE TOTAL
CONTRACT SUM $20,854,880.00
REMEASURED WORKS BILL NO. 3 - Pile Caps
C
120 M2 $3,600.00 $432,000.00
D
3.6 M2 $13,000.00 $46,800.00
E
1.92 M3 $58,000.00 $111,360.00
QUANTITY
Allow for the replacement of corroded rebar where required with 16mm diameter bars x 1m, bent and welded to existing rebar as per drawing sheet 2a and as instructed by the Engineer and coated with epoxy zinc chromate primer to exposed surfaces
Supply and install wrought formwork to soffit and sides of pile cap. (for minimum concrete thickness of 150mm) inclusive of supports and bracing and striking on completion
Place design concrete mix containing chloride inhibitors and super plastisizers having a 28 day cube strength of 30 Mpa
OMISSION ADDITIONAL
ITEM DESCRIPTION UNIT RATE TOTAL RATE TOTAL QUANTITY
H
56.929 M $11,000.00 $626,219.00
J
2 $112,000.00 $224,000.00
H
PS $600,000.00
Chase cracks to minimum depth fo 30mm by 60mm wide and repair with approved masonary repair concrete such Phoscrete supplied by PowerGen Limited (or similar product approved by the Engineer)
Clean during low tide exposed concrete and steel reinforcement to 2no. Pile Head supporting Pile Cap D appox 0.4 x 0.45m x 2no at splash zone by water blasting with potable water and apply layers of phoscrete concrete as per manufacturer instruction to ac
BILL NO. 4- Repairs to Deck Support Beams
Include Provisional Sum of $600,000.00 to be used as instructed by the Engineer. To be deducted in whole or part if unused.
OMISSION ADDITIONAL
ITEM DESCRIPTION UNIT RATE TOTAL RATE TOTAL QUANTITY
D
192 M2 $1,000.00
E
PS $300,000.00
BILL NO. 6 = Repairs to T-Pier
K
PS $650,000.00
BILL NO. 7
VARIATION No. 1
Dowel 25mm rebars into existing slab 24 No. $3,271.25 Eng. Estimate @ $2,972.21 $78,510.00
removespalling concrete from additional t-pier cap 0.5 M3 $140,000.00 Rate is as per BQ/6 - ITEM A $70,000.00
BILL NO. 5 - Painting and Protective Coatings
Repaint exterior surfaces (sides and soffit) of 8no. pile caps with approved exterior marine grade paint finish, colour to match existing
Allow Provisional Sum of $300,000.00 to be used as instructed by Engineer. To be removed in whole or part if not used
Include the PROVISIONAL SUM of $650,000.00 for Contingencies to be used as directed by the Engineer and to be deducted in whole or in part if not required:-
OMISSION ADDITIONAL
ITEM DESCRIPTION UNIT RATE TOTAL RATE TOTAL QUANTITY
VARIATION No. 2
replace barrier on T-Pier 5 no. $20,000.00 Eng. Estimate @ $85,000.00 $100,000.00
70 M $7,000.00 $490,000.00
Apply Nitobond to deck support beam item $19,375.00
additional work to widen Gate as Directed Sum Relocation of Gate Posts $20,000.00
VARIATION No. 3
Repair to Stem of Deck Beams
8 item $37,500.00 $300,000.00
A7 M2 $9,250.00 $64,750.00
B
10 M $8,000.00 $80,000.00
Chase crack to a minimum depth of 30mm x 60mm wide and repair with approved masonry repair concrete
( Rendoroc)
Allow for relocating the pantoon between span of pile clusters.
Remove delaminated and spalling concrete to a depth ( > 10 MM) so as to expose reinforcement
and clean with potable water .
Allow for cleaning of rebars with wire brush to remove all corrosion and wash with potable water.
(Corroded portion of rebar exposed to damaged face of stem)
OMISSION ADDITIONAL
ITEM DESCRIPTION UNIT RATE TOTAL RATE TOTAL QUANTITY
C
0.069 M3 $39,600.00 $2,732.40
D
5 M $4,000.00 $20,000.00
E
240 No. $300.00 $72,000.00
Repair to the Soffit of Beams
A
10 No. $1,562.50 $15,625.00
B1 M2 $15,625.00 $15,625.00
C2 M2 $1,375.00 $2,750.00
Place design masonary repair concrete such Renderoc HB (or similar product approved by the
Engineer) to a thickiness no less than 12mm
Chase cracks to minimum depth fo 12mm and 30 mm wide; repair with approved masonary repair
concrete such Renderoc (or similar product approved by the Engineer)
Allow for removing concrete from defective area (0.07 sq. m) of beam stem, clean rebars with wire
brush to remove all corrosion and treat with zinc chromate. Repair using Renderoc HB (Corroded
portion of rebar exposed to damaged face of stem). apply Nitobond SBR as per manufacturer's
specification.
Remove 0.2 m2 delaminated and spalling concrete to a minimum depth of 12mm so as to
expose rebars of the soffit of deck beam.
Wire brush rebars to remove corrosion, wash with potable water and coat with zinc chromate
To apply Nitobond SBR as bonding agent to deck beams
OMISSION ADDITIONAL
ITEM DESCRIPTION UNIT RATE TOTAL RATE TOTAL QUANTITY
D
0.02 M3 $820,000.00 $16,400.00
REPAIR TO PILE CAPS
A
3 M $28,200.00 $84,600.00
B 8 M2 $6,750.00 $54,000.00
C6 item $4,229.00 $25,374.00
D0.2 M2 $41,000.00 $8,200.00
E
0.5 M $70,250.00 $35,125.00
TOTAL OMISSION $2,400,219.00 TOTAL ADDITION $2,165,226.40
NET VARIATION -$234,992.60
CONTRACT SUM $20,854,880.00
Place design masonary repair concrete such Renderoc HB ( similar product approved by the
Engineer) to a thickiness no less than 12mm
Chase cracks to minimum depth fo 30mm by 60mm wide and repair with approved masonary
repair concrete such as Renderoc (or similar product approved by the Engineer)
Remove delaminated and spalling concrete to a minimum depth so as to expose rebars
Allow for cleaning of rebars with wire brush to remove all corrosion and wash with potable water.
Place design masonary repair concrete such Renderoc HB ( similar product approved by the
Engineer) .
Effect repairs to one corner ( 1M X1MX 0.5M) of a a pile cap, remove spalling concrete, clean
corrosion from bars using wire brush , treat with zinc chromate , shuttering and apply apply deisgn concrete with chloride inhibitor of design strength
no less than 30 Mpa.
OMISSION ADDITIONAL
ITEM DESCRIPTION UNIT RATE TOTAL RATE TOTAL QUANTITY
REVISED CONTRACT SUM $20,619,887.40
OMISSION ADDITIONAL
ITEM DESCRIPTION UNIT RATE TOTAL RATE TOTAL
CONTRACT SUM $20,854,880.00
VARIATION No. 4
A
4 Eng. Estimate @ $47,000.00 $55,000.00 $220,000.00
B
4 Rate is as per BQ/6 Item B $8,500.00 $34,000.00
C
5 Kg Rate is as per BQ/6 Item C $3,600.00 $18,000.00
D7.6 Eng. Estimate @ $13,000.00 $10,000.00 $76,000.00
E 1.5 Rate is as per BQ/6 Item E $58,000.00 $87,000.00
F Allow for Nitobond as per Manufacture's Instructions 4 Eng. Estimate @ $1,400.00 $1,375.00 $5,500.00
G 1.5 Eng. Estimate @ $7,700.00 $7,000.00 $10,500.00
H8 Rate is as per BQ/8 Item C $7,100.00 $56,800.00
SUB-TOTAL $507,800.00
OMISSION
BILL NO. 3 - Pile Caps
FPS $120,773.60
BILL NO. 6 - Repairs to T-Pier
HPS $387,026.40
SUB-TOTAL $507,800.00
Summary
CONTRACT SUM $20,854,880.00
VARIATIONS No. 4 $507,800.00
OMISSION ($507,800.00)
GRAND TOTAL $20,854,880.00
QUANTITY
Complete repairs as outlined to Pile Caps and concrete pile muff protection over water depth between 1m
Remove delaminated and spalling concrete to sides and base of pile cap to depth of 100mm below reinforcement and clean with potable water using high pressure water jet equipment during low tide level m2
Allow for cleaning of rebars with wet sand blasting, high pressure potable water jet and mechanical cleaning to White Metal (SSPC-SP5) (NACE1). (Corroded portion of rebar exposed to damaged face of pile caps)
m2
Allow for the replacement of corroded rebar where required with 16mm diameter bars x 1m, bent and welded to existing rebar as per drawing sheet 2a and as instructed by the Engineer and coated with epoxy zinc chromate primer to exposed surfaces
Supply and install wrought formwork to soffit and sides of pile cap. (for minimum concrete thickness of 150mm) inclusive of supports and bracing and striking on completion
m2
Place design concrete mix containing chloride inhibitors and super plastisizers having a 28 day cube strength of 30 Mpa m3
m2
Allow for the application of Renderoc to surface of repaired concrete beam to seal and close any cracks which may appear. m2
Apply two coats of the approved protective coating to match exterior colour. m2
Allow Provisional Sum of $150,000.00 for supply and installation of sacrificial anodes ( to be used as directed by the Engineer and to removed in whole or part if unused)
Include Provisional Sum of $650,000.00 to be used as instructed by the Engineer. To be deducted in whole or part if unused.
OMISSION ADDITIONAL
DESCRIPTION UNIT RATE TOTAL RATE TOTAL
CONTRACT SUM $20,854,880.00
REMEASURED WORKS - All rates are as per contract
BILL NO. 3 - Pile Caps
120 M2 $3,600.00 $432,000.00
3.6 M2 $13,000.00 $46,800.00
1.92 M3 $58,000.00 $111,360.00
SUB-TOTAL $590,160.00VARIATIONS
VARIATION No. 1
Dowel 25mm rebars into existing slab
24 No. Eng. Estimate @ $2,900.00 $3,271.25 $78,510.00
removespalling concrete from additional t-pier cap 0.5 M3 Rate is as per BQ/6 - ITEM A $140,000.00 $70,000.00
VARIATION No. 2
replace barrier on T-Pier
5 no. Eng. Estimate @ $18,500.00 $20,000.00 $100,000.00
70 M Eng. Estimate @ $7,700.00 $7,000.00 $490,000.00
Apply Nitobond to deck support beamITEM Eng. Estimate @ $17,000.00 $19,375.00
additional work to widen Gate as Directed Sum Eng. Estimate @ $ 20,000.00 $20,000.00
QUANTITY
Allow for the replacement of corroded rebar where required with 16mm diameter bars x 1m, bent and welded to existing rebar as per drawing sheet 2a and as instructed by the Engineer and coated with epoxy zinc chromate primer to exposed surfaces
Supply and install wrought formwork to soffit and sides of pile cap. (for minimum concrete thickness of 150mm) inclusive of supports and bracing and striking on completion
Place design concrete mix containing chloride inhibitors and super plastisizers having a 28 day cube strength of 30 Mpa
Chase crack to a minimum depth of 30mm x 60mm wide and repair with approved masonry repair concrete ( Rendoroc)
OMISSION ADDITIONAL
DESCRIPTION UNIT RATE TOTAL RATE TOTAL QUANTITY
VARIATION No. 3
Repair to Stem of Deck BeamsAllow for relocating the pantoon between span of pile clusters. 8 item Eng. Estimate @ $ 32,500.00 $37,500.00 $300,000.00
7 M2 Eng. Estimate @ $ 14,000.00 $9,250.00 $64,750.00
10 M Rate in the contract is $8,500. $8,000.00 $80,000.00
0.069 M3 Eng. Estimate @ $ 49,000.00 $39,600.00 $2,732.40
5 M Eng. Estimate @ $2,700.00 $4,000.00 $20,000.00
240 No. Eng. Estimate @ $287.00 $300.00 $72,000.00
Repair to the Soffit of Beams
10 No. Eng. Estimate @ $1,600.00 $1,562.50 $15,625.00
1 M2 Eng. Estimate @ $11,900.00 $15,625.00 $15,625.00
To apply Nitobond SBR as bonding agent to deck beams 2 M2 Eng. Estimate @ $3,500.00 $1,375.00 $2,750.00
Eng. Estimate @ $17,680.00 Item $16,400.00
Remove delaminated and spalling concrete to a depth ( > 10 MM) so as to expose reinforcement and clean with potable
water .
Allow for cleaning of rebars with wire brush to remove all corrosion and wash with potable water. (Corroded portion
of rebar exposed to damaged face of stem)
Place design masonary repair concrete such Renderoc HB (or similar product approved by the Engineer) to a thickiness no
less than 12mm
Chase cracks to minimum depth fo 12mm and 30 mm wide; repair with approved masonary repair concrete such Renderoc
(or similar product approved by the Engineer)
Allow for removing concrete from defective area (0.07 sq. m) of beam stem, clean rebars with wire brush to remove all corrosion
and treat with zinc chromate. Repair using Renderoc HB (Corroded portion of rebar exposed to damaged face of stem).
apply Nitobond SBR as per manufacturer's specification.
Remove 0.2 m2 delaminated and spalling concrete to a minimum depth of 12mm so as to expose rebars of the soffit of deck
beam.
Wire brush rebars to remove corrosion, wash with potable water and coat with zinc chromate
Place design masonary repair concrete such Renderoc HB ( similar product approved by the Engineer) to a thickiness no
less than 12mm
OMISSION ADDITIONAL
DESCRIPTION UNIT RATE TOTAL RATE TOTAL QUANTITY
Repairs to Pile Cap
3 M Eng. Estimate @ $11,000.00 $28,200.00 $84,600.00
8 M2 Eng. Estimate @ $20,000.00 $6,750.00 $54,000.00
6 item Eng. Estimate @ $2,500.00 $4,229.00 $25,374.00
0.2 M2 Eng. Estimate @ $49,000.00 $41,000.00 $8,200.00
0.5 M Eng. Estimate @ $80,000.00 $70,250.00 $35,125.00
VARIATION No. 4
4
Eng. Estimate @ $47,000.00 $55,000.00 $220,000.00
4
Rate is as per BQ/6 Item B $8,500.00 $34,000.00
5 Kg
Rate is as per BQ/6 Item C $3,600.00 $18,000.00
7.6Eng. Estimate @ $13,000.00 $10,000.00 $76,000.00
1.5 Rate is as per BQ/6 Item E $58,000.00 $87,000.00
Allow for Nitobond as per Manufacture's Instructions 4 Eng. Estimate @ $1,400.00 $1,375.00 $5,500.00
1.5 Eng. Estimate @ $7,700.00 $7,000.00 $10,500.00
8Rate is as per BQ/8 Item C $7,100.00 $56,800.00
SUB-TOTAL $2,082,866.40
OMISSION
General & Preliminary Items
PS $50,000.00
BILL NO. 3 - Pile Caps
PS $150,000.00
70 M $11,000.00 $770,000.00
Chase cracks to minimum depth fo 30mm by 60mm wide and repair with approved masonary repair concrete such as
Renderoc (or similar product approved by the Engineer)
Remove delaminated and spalling concrete to a minimum depth so as to expose rebars
Allow for cleaning of rebars with wire brush to remove all corrosion and wash with potable water.
Place design masonary repair concrete such Renderoc HB ( similar product approved by the Engineer) .
Effect repairs to one corner ( 1M X1MX 0.5M) of a a pile cap, remove spalling concrete, clean corrosion from bars using wire
brush , treat with zinc chromate , shuttering and apply apply deisgn concrete with chloride inhibitor of design strength no less
than 30 Mpa.
Complete repairs as outlined to Pile Caps and concrete pile muff protection over water depth between 1m
Remove delaminated and spalling concrete to sides and base of pile cap to depth of 100mm below reinforcement and clean with potable water using high pressure water jet equipment during low tide level
m2
Allow for cleaning of rebars with wet sand blasting, high pressure potable water jet and mechanical cleaning to White Metal (SSPC-SP5) (NACE1). (Corroded portion of rebar exposed to damaged face of pile caps)
m2
Allow for the replacement of corroded rebar where required with 16mm diameter bars x 1m, bent and welded to existing rebar as per drawing sheet 2a and as instructed by the Engineer and coated with epoxy zinc chromate primer to exposed surfaces
Supply and install wrought formwork to soffit and sides of pile cap. (for minimum concrete thickness of 150mm) inclusive of supports and bracing and striking on completion
m2
Place design concrete mix containing chloride inhibitors and super plastisizers having a 28 day cube strength of 30 Mpa
m3
m2
Allow for the application of Renderoc to surface of repaired concrete beam to seal and close any cracks which may appear.
m2
Apply two coats of the approved protective coating to match exterior colour.
m2
Allow Provisional Sum of $50,000.00 for the supply and installation of signs as per Engineers instructions
Allow Provisional Sum of $150,000.00 for supply and installation of sacrificial anodes ( to be used as directed by the Engineer and to removed in whole or part if unused)
Chase cracks to minimum depth fo 30mm by 60mm wide and repair with approved masonary repair concrete such Phoscrete supplied by PowerGen Limited (or similar product approved by the Engineer)
OMISSION ADDITIONAL
DESCRIPTION UNIT RATE TOTAL RATE TOTAL QUANTITY
2 $112,000.00 $224,000.00
BILL NO. 4- Repairs to Deck Support Beams
PS $600,000.00
BILL NO. 5 - Painting and Protective Coatings
192 M2 $1,000.00 $192,000.00
PS $300,000.00
BILL NO. 6 - Repairs to Damaged T-Pier
PS 387,025.20
SUB-TOTAL $2,673,026.40 $2,673,026.40
Summary
CONTRACT SUM $20,854,880.00
REMEASURED WORKS $590,160.00
VARIATIONS $2,082,866.40
OMISSION ($2,165,226.40)
GRAND TOTAL $21,362,680.00
Clean during low tide exposed concrete and steel reinforcement to 2no. Pile Head supporting Pile Cap D appox 0.4 x 0.45m x 2no at splash zone by water blasting with potable water and apply layers of phoscrete concrete as per manufacturer instruction to ac
Include Provisional Sum of $600,000.00 to be used as instructed by the Engineer. To be deducted in whole or part if unused.
Repaint exterior surfaces (sides and soffit) of 8no. pile caps with approved exterior marine grade paint finish, colour to match existing
Allow Provisional Sum of $300,000.00 to be used as instructed by Engineer. To be removed in whole or part if not used
Include Provisional Sum of $600,000.00 to be used as instructed by the Engineer. To be deducted in whole or part if unused.
OCHO RIOS PILE CAP REPAIRS - VARIATION
Page 13 of 147
OMISSION ADDITIONAL
ITEM DESCRIPTION UNIT RATE TOTAL RATE
CONTRACT SUM $20,854,880.00
General & Preliminary ItemsK
PS $50,000.00
BILL NO. 3 - Pile CapsC
120 M2 $3,600.00
D
3.6 M2 $13,000.00
E
1.92 M3 $58,000.00
QUANTITY
Allow Provisional Sum of $50,000.00 for the supply and installation of signs as per Engineers instructions
Allow for the replacement of corroded rebar where required with 16mm diameter bars x 1m, bent and welded to existing rebar as per drawing sheet 2a and as instructed by the Engineer and coated with epoxy zinc chromate primer to exposed surfaces
Supply and install wrought formwork to soffit and sides of pile cap. (for minimum concrete thickness of 150mm) inclusive of supports and bracing and striking on completion
Place design concrete mix containing chloride inhibitors and super plastisizers having a 28 day cube strength of 30 Mpa
OCHO RIOS PILE CAP REPAIRS - VARIATION
Page 14 of 147
OMISSION ADDITIONAL
ITEM DESCRIPTION UNIT RATE TOTAL RATEQUANTITY
F
PS $150,000.00
H
70 M $11,000.00 $770,000.00
J
2 $112,000.00 $224,000.00
H
PS $600,000.00
Allow Provisional Sum of $150,000.00 for supply and installation of sacrificial anodes ( to be used as directed by the Engineer and to removed in whole or part if unused)
Chase cracks to minimum depth fo 30mm by 60mm wide and repair with approved masonary repair concrete such Phoscrete supplied by PowerGen Limited (or similar product approved by the Engineer)
Clean during low tide exposed concrete and steel reinforcement to 2no. Pile Head supporting Pile Cap D appox 0.4 x 0.45m x 2no at splash zone by water blasting with potable water and apply layers of phoscrete concrete as per manufacturer instruction to ac
BILL NO. 4- Repairs to Deck Support Beams
Include Provisional Sum of $600,000.00 to be used as instructed by the Engineer. To be deducted in whole or part if unused.
OCHO RIOS PILE CAP REPAIRS - VARIATION
Page 15 of 147
OMISSION ADDITIONAL
ITEM DESCRIPTION UNIT RATE TOTAL RATEQUANTITY
D
192 M2 $1,000.00 $192,000.00
E
PS $300,000.00
BILL NO. 6 = Repairs to T-Pier
K
PS $650,000.00
F 16 mm diameter high tensile rod reinforced 212 KG $300.00 $63,600.00
G 25 mm diameter high tensile rod reinforced 364 KG $350.00 $127,400.00
BILL NO. 7
F 10 mm diameter mild steel rod reinforced 450.00 KG $260.00 $117,000.00
VARIATION No. 1
Dowel 25mm rebars into existing slab
removespalling concrete from additional t-pier cap
BILL NO. 5 - Painting and Protective Coatings
Repaint exterior surfaces (sides and soffit) of 8no. pile caps with approved exterior marine grade paint finish, colour to match existing
Allow Provisional Sum of $300,000.00 to be used as instructed by Engineer. To be removed in whole or part if not used
Include the PROVISIONAL SUM of $650,000.00 for Contingencies to be used as directed by the Engineer and to be deducted in whole or in part if not required:-
OCHO RIOS PILE CAP REPAIRS - VARIATION
Page 16 of 147
OMISSION ADDITIONAL
ITEM DESCRIPTION UNIT RATE TOTAL RATEQUANTITY
VARIATION No. 2
replace barrier on T-Pier
70 M $7,000.00
Apply Nitobond to deck support beam
additional work to widen Gate as Directed
VARIATION No. 3
Repair to Stem of Deck Beams
8 item $37,500.00
A7 M2 $9,250.00
B
10 M $8,000.00
Chase crack to a minimum depth of 30mm x 60mm wide and repair with approved masonry repair concrete
( Rendoroc)
Allow for relocating the pantoon between span of pile clusters.
Remove delaminated and spalling concrete to a depth ( > 10 MM) so as to expose reinforcement
and clean with potable water .
Allow for cleaning of rebars with wire brush to remove all corrosion and wash with potable water.
(Corroded portion of rebar exposed to damaged face of stem)
OCHO RIOS PILE CAP REPAIRS - VARIATION
Page 17 of 147
OMISSION ADDITIONAL
ITEM DESCRIPTION UNIT RATE TOTAL RATEQUANTITY
C
0.069 M3 $39,600.00
D
5 M $4,000.00
E
240 No. $300.00
Repair to the Soffit of Beams
A
10 No. $1,562.50
B1 M2 $15,625.00
C2 M2 $1,375.00
Place design masonary repair concrete such Renderoc HB (or similar product approved by the
Engineer) to a thickiness no less than 12mm
Chase cracks to minimum depth fo 12mm and 30 mm wide; repair with approved masonary repair
concrete such Renderoc (or similar product approved by the Engineer)
Allow for removing concrete from defective area (0.07 sq. m) of beam stem, clean rebars with wire
brush to remove all corrosion and treat with zinc chromate. Repair using Renderoc HB (Corroded
portion of rebar exposed to damaged face of stem). apply Nitobond SBR as per manufacturer's
specification.
Remove 0.2 m2 delaminated and spalling concrete to a minimum depth of 12mm so as to
expose rebars of the soffit of deck beam.
Wire brush rebars to remove corrosion, wash with potable water and coat with zinc chromate
To apply Nitobond SBR as bonding agent to deck beams
OCHO RIOS PILE CAP REPAIRS - VARIATION
Page 18 of 147
OMISSION ADDITIONAL
ITEM DESCRIPTION UNIT RATE TOTAL RATEQUANTITY
D
0.02 M3 $820,000.00
REPAIR TO PILE CAPS
A
3 M $28,200.00
B 8 M2 $6,750.00
C6 item $4,229.00
D0.2 M2 $41,000.00
E
0.5 M $70,250.00
TOTAL OMISSION $3,244,000.00 TOTAL ADDITION
NET VARIATION -$1,078,773.60
CONTRACT SUM $20,854,880.00
Place design masonary repair concrete such Renderoc HB ( similar product approved by the
Engineer) to a thickiness no less than 12mm
Chase cracks to minimum depth fo 30mm by 60mm wide and repair with approved masonary
repair concrete such as Renderoc (or similar product approved by the Engineer)
Remove delaminated and spalling concrete to a minimum depth so as to expose rebars
Allow for cleaning of rebars with wire brush to remove all corrosion and wash with potable water.
Place design masonary repair concrete such Renderoc HB ( similar product approved by the
Engineer) .
Effect repairs to one corner ( 1M X1MX 0.5M) of a a pile cap, remove spalling concrete, clean
corrosion from bars using wire brush , treat with zinc chromate , shuttering and apply apply deisgn concrete with chloride inhibitor of design strength
no less than 30 Mpa.
OCHO RIOS PILE CAP REPAIRS - VARIATION
Page 19 of 147
OMISSION ADDITIONAL
ITEM DESCRIPTION UNIT RATE TOTAL RATEQUANTITY
REVISED CONTRACT SUM $19,776,106.40
OCHO RIOS PILE CAP REPAIRS - VARIATION
Page 20 of 147
ADDITIONAL
TOTAL
$20,854,880.00
$432,000.00
$46,800.00
$111,360.00
OCHO RIOS PILE CAP REPAIRS - VARIATION
Page 21 of 147
ADDITIONAL
TOTAL
OCHO RIOS PILE CAP REPAIRS - VARIATION
Page 22 of 147
ADDITIONAL
TOTAL
$78,510.00
$70,000.00
OCHO RIOS PILE CAP REPAIRS - VARIATION
Page 23 of 147
ADDITIONAL
TOTAL
$100,000.00
$490,000.00
$19,375.00
$20,000.00
$300,000.00
$64,750.00
$80,000.00
OCHO RIOS PILE CAP REPAIRS - VARIATION
Page 24 of 147
ADDITIONAL
TOTAL
$2,732.40
$20,000.00
$72,000.00
$15,625.00
$15,625.00
$2,750.00
OCHO RIOS PILE CAP REPAIRS - VARIATION
Page 25 of 147
ADDITIONAL
TOTAL
$16,400.00
$84,600.00
$54,000.00
$25,374.00
$8,200.00
$35,125.00
$2,165,226.40
PORT AUTHORITY OF JAMAICA
ITEM DESCRIPTION CONTRACT
QUANTITY
General & Preliminary Items
A a) Contractors All Risk
B b) Public LiabilityC c) Employers Liability
D
E
F Allow for mobilisation of equipment and site personnel
G Programme
H Setting Out
Listed under this bill are items for which, in opinion of the Engineer, a separate charge is appropriate and becomes due at the times stated. The sums are entered against these items shall be fixed lumps sums not subject to works. All extra costs requir
Allow for the provision of the following insurances for the works in accordance with the Condition of Contracts
Allow for provisons of Performance Bond of 10% for duration of construction of the works
Allow for mobilisation of all necessary tools, equipment and personnel site, inclusive of working platform or pontoon barge and necessary mooring or anchoring equipment for safe operation
J
K
L
M
N
O
BILL NO. 1 Cont'd
A
B Allow for the working, curing and testing of concrete test cubes.
C
Allow for all safety and Personal Protective Equipment required for the workforce including that required for working over water
Allow Provisional Sum of $50,000.00 for the supply and installation of signs as per Engineers instructions
Welfare and sanitary facilities, installation of temporary services, false work, platforms, boat, tenting for protection of works and removal on completion of contract.
Allow for modification to property fence and entrance canopy so as to create access for equipment & make good on completion
Allow for taking all precaution to avoid any damage whatsoever to existing infrastructures services.
Allow for providing samples of material proposed to be used in the Contract which when requested by the Engineer shall be furnished without delay.
TOTAL BILL NO. 1 - FIXED PRELIMINARIES Add#3 - BQ/2 carried forward
Allow for providing and erecting in approved locations proper sheds for use of the workmen, storage and protection of materials (those for cement having floor raised at least 12" from the ground) and for clearing same away upon completion of construction.
The Contractor shall enter in the spaces below the clause numbers of the conditions of Contract or Specification against which to cover any special risk, liabilities and obligations not described above and which cannot be included in the rates. The amoun
BILL NO. 2
Time Dependent Preliminaries
A Temporary Services (eg. water, power, phone etc) 10
B Lighting, site security and keeping site clean at all times 10
Site Supervsion and management.
C List made up of total figure below: 10
Item Amt/Week
EngineerSupervisor
REPAIR TO PILE CAPS
BILL NO. 3 Pile Caps
Repair to Pile Caps on Grid Lines B, C and E
A 4
B 4
TOTAL BILL NO. 1 - FIXED PRELIMINARIES Add#3 - BQ/2 - brought forward
TOTAL BILL NO. 1 - FIXED PRELIMINARIES carried to summary
TOTAL BILL NO. 2 - TIME DEPENDENT PRELIMINARIES
Complete repairs as outlined to Pile Caps and concrete pile muff protection over water depth between 1m and 6m
Remove delaminated and spalling concrete to sides of pile cap to depth of 100mm below reinforcement and clean with potable water using high pressure water jet equipment during low tide level
Allow for cleaning of rebars with wet sand blasting, high pressure potable water jet and mechanical cleaning to White Metal (SSPC-SP5) (NACE1). (Corroded portion of rebar exposed to damaged face of pile caps)
C 30
D 4
E 0.6
F
G 4
Repair to Pile Caps on Grid Lines B, CD, , E, N, P and V
H 100
J 2
REPAIR TO PILE CAPSBILL NO. 4
Allow for the replacement of corroded rebar where required with 16mm diameter bars x 1m, bent and welded to existing rebar as per drawing sheet 2a and as instructed by the Engineer and coated with epoxy zinc chromate primer to exposed surfaces
Supply and install wrought formwork to soffit and sides of pile cap. (for minimum concrete thickness of 150mm) inclusive of supports and bracing and striking on completion
Place design concrete mix containing chloride inhibitors and super plastisizers having a 28 day cube strength of 30 Mpa
Allow Provisional Sum of $150,000.00 for supply and installation of sacrificial anodes ( to be used as directed by the Engineer and to removed in whole or part if unused)
Allow for the application of repair mortor to surface of repaired concrete beam to seal and close any cracks which may appear.
Chase cracks to minimum depth fo 30mm by 60mm wide and repair with approved masonary repair concrete such Phoscrete supplied by PowerGen Limited (or similar product approved by the Engineer)
Clean during low tide exposed concrete and steel reinforcement to 2no. Pile Head supporting Pile Cap D appox 0.4 x 0.45m x 2no at splash zone by water blasting with potable water and apply layers of phoscrete concrete as per manufacturer instruction to ac
TOTAL BILL NO. 3 - REPAIRS TO PILE CAP carried to summary
Repairs to Deck Support Beams
A 8
B 8
C 36
D Supply and install wrought fromwork to soffit and side of beam. 84
E 3
F 42
G 8
H
3
REPAIR TO PILE CAPS
Repair/Reinstatement of damage to Precast Double Tees on Grid Lines 5, 6, 7 & 8
Allow for temporary support and work access to each Double Tee sections (approx. 14m length) in water depth varing between 1m and 6m deep, during beam repairs
Remove 0.5 m2 delaminated and spalling concrete to expose at least 150mm of tendon on either side of damaged double Tee beam
Sandblast reinforcement tendons to remove corrosion and apply zinc chromate primer to exposed tendons
Place design concrete mix containing chloride inhibitors etc having a 28 day cube strength of 30 Mpa
Allow for the application of repair mortor to surface of repaired concrete beam to complete repairs and seal any cracks which may appear on surface of ccncrete.
Allow for the temporary work access platform to complete repairs to cracks in Double Tee beams in water depths 1m to 6m
Include Provisional Sum of $600,000.00 to be used as instructed by the Engineer. To be deducted in whole or part if unused.
Alternative (Rate Only)
Apply shot crete or build up concrete having a 28 day cube strength of 30 Mpa to complete beam repair around reinforcement tendons inclusive of final surface render finish.
TOTAL BILL NO. 4 - REPAIRS TO DECK SUPPORT BEAMS
BILL NO. 5
Painting and Protective Coatings
A
B 192
C 192
D 192
.E
REPAIR TO DAMAGED T PIERBILL NO. 6
DEMOLITION AND ALTERATION
Allow for the installation of protective drop cloth or equivalent method to facilitate the collection of sand and debris at each location resulting from the sandblasting of the concrete surface (measured seperately)
Remove existing paint finish to to sides and soffit of 8 no. pile caps by wet sand blasting or water blasting as required
Apply approved corrosion inhibiting coating to the previously prepared and new concrete surfaces of 8no. Pile caps as per manufacturers instruction
Repaint exterior surfaces (sides and soffit) of 8no. pile caps with approved exterior marine grade paint finish, colour to match existing
Allow Provisional Sum of $300,000.00 to be used as instructed by Engineer. To be removed in whole or part if not used
TOTAL BILL NO. 5 - PAINTING & PROTECTIVE COATINGS carried to summary
The demolition of existing in-situ slab between centre lines 3-4 and A-B . The removal and replacement of two "L" -shaped beams and repair one pile cap at 3B.
Carefully remove following damaged concrete section of pier inclusive of all false work and safety measures
A 25.00
B 13.50
C Cart away spoil
PRE-CAST REINFORCED CONCRETE
Reinforced Concrete 4500 PSI in:
D 3.00
Steel Reinforcement
E 10 mm diameter Mild steel rod reinforced 415.00
F 16 mm diameter high tensile rod reinforced 322.00
G 25 mm diameter high tensile rod reinforced 660.00
Formwork and support to:-
H Side of beam 23.00
J Ditto bottom of beam 6.00
K
22'-0" x 12'-0" x 8" section of reinforced concrete slab supported on 8" thick precast concrete slabs (to be reused) mounted on damaged reinforced concrete beams (measured seperately)
Damaged 18"x16"x22' reinforced concrete beams mounted on pile caps as supports to precast slab and insitu slab. Insitu slab to be removed and measured seprately.
This section covers the replacement of 2 No. Pre-cast reinforced concrete beam and in-situ 200mm concrete slab. Prices should include for all costs involved in order to fulfill every requirement of the design specification and any particular site conditio
Precast Reinforced Concrete Beam fixed to top of piles as per drawing
Include the PROVISIONAL SUM of $650,000.00 for Contingencies to be used as directed by the Engineer and to be deducted in whole or in part if not required:-
REPAIR TO DAMAGED T PIER
BILL NO. 7
IN-SITU REINFORCED CONCRETE
Reinforced Concrete Pile Cap
A Pile Cap - Concrete 431 M.Pa 0.30
B 12 mm diameter mild steel rod reinforced 21.00
C 16 mm diameter high tensile rod reinforced 97.00
D Sides of pile cap 2.00
In-situ Reinforced Concrete Slab
E 8.00
F 10 mm diameter mild steel rod reinforced 514.00
REPAIR TO DAMAGED T PIER
BILL NO. 8
SHORE PROTECTION - BOULDERS
A 600
B Ditto with boulder 0.3m - 0.8m diameter ( Provisional) 40
TOTAL BILL NO. 6 - REPAIR TO DAMAGED T PIER carried to summary
200 mm thick slab laid on Pre-Cast slab (measured seperately) finished with broom finish.
TOTAL BILL NO. 7 - IN-SITU REINFORCED CONCRETE carried to summary
To supply material , labour to place boulders 0.9m and 1.2m in diameter as rock armouring to shoreline in accordance with specifications (Provisional)
C 80
VARIATION
1 VARIATION No. 12
Dowel 25mm rebars into existing slab34 Remove spalling concrete from additional t-pier cap5
6 VARIATION No. 278 replace barrier on T-Pier
Apply Nitobond to deck support beam
additional work to widen Gate as Directed
VARIATION No. 3
Repair to Stem of Deck BeamsAllow for relocating the pantoon between span of pile clusters.
Carefully reclaim boulders(0.9m and 1.2m in diameter) from seabed in a depth of water not exceeding 1.5m for repacking in rock armouring (Provisional)
TOTAL BILL NO. 8 - SHORE PROTECTION - BOULDERS carried to summary
Chase crack to a minimum depth of 30mm x 60mm wide and repair with approved masonry repair concrete ( Rendoroc)
Remove delaminated and spalling concrete to a depth ( > 10 MM) so as to expose reinforcement and clean with potable water .
Repair to the Soffit of Beams
To apply Nitobond SBR as bonding agent to deck beams
REPAIR TO PILE CAPS
Allow for cleaning of rebars with wire brush to remove all corrosion and wash with potable water. (Corroded portion of rebar exposed to damaged face of stem)
Place design masonary repair concrete such Renderoc HB (or similar product approved by the Engineer) to a thickiness no less than 12mm
Chase cracks to minimum depth fo 12mm and 30 mm wide; repair with approved masonary repair concrete such Renderoc (or similar product approved by the Engineer)
Allow for removing concrete from defective area (0.07 sq. m) of beam stem, clean rebars with wire brush to remove all corrosion and treat with zinc chromate. Repair using Renderoc HB (Corroded portion of rebar exposed to damaged face of stem). apply Nitobond SBR as per manufacturer's specification.
Remove 0.2 m2 delaminated and spalling concrete to a minimum depth of 12mm so as to expose rebars of the soffit of deck beam.
Wire brush rebars to remove corrosion, wash with potable water and coat with zinc chromate
Place design masonary repair concrete such Renderoc HB ( similar product approved by the Engineer) to a thickiness no less than 12mm
Chase cracks to minimum depth fo 30mm by 60mm wide and repair with approved masonary repair concrete such as Renderoc (or similar product approved by the Engineer)
VARIATION No. 4
Remove delaminated and spalling concrete to a minimum depth so as to expose rebars
Allow for cleaning of rebars with wire brush to remove all corrosion and wash with potable water.
Place design masonary repair concrete such Renderoc HB ( similar product approved by the Engineer) .
Effect repairs to one corner ( 1M X1MX 0.5M) of a a pile cap, remove spalling concrete, clean corrosion from bars using wire brush , treat with zinc chromate , shuttering and apply apply deisgn concrete with chloride inhibitor of design strength no less than 30 Mpa.
Complete repairs as outlined to Pile Caps and concrete pile muff protection over water depth between 1m
Remove delaminated and spalling concrete to sides and base of pile cap to depth of 100mm below reinforcement and clean with potable water using high pressure water jet equipment during low tide level
Allow for cleaning of rebars with wet sand blasting, high pressure potable water jet and mechanical cleaning to White Metal (SSPC-SP5) (NACE1). (Corroded portion of rebar exposed to damaged face of pile caps)
Allow for the replacement of corroded rebar where required with 16mm diameter bars x 1m, bent and welded to existing rebar as per drawing sheet 2a and as instructed by the Engineer and coated with epoxy zinc chromate primer to exposed surfaces
Allow for Nitobond as per Manufacture's Instructions
Supply and install wrought formwork to soffit and sides of pile cap. (for minimum concrete thickness of 150mm) inclusive of supports and bracing and striking on completion
Place design concrete mix containing chloride inhibitors and super plastisizers having a 28 day cube strength of 30 Mpa
Allow for the application of Renderoc to surface of repaired concrete beam to seal and close any cracks which may appear.
Apply two coats of the approved protective coating to match exterior colour.
CONTRACT ADDITION
UNIT RATE TOTAL QUNTITY RATE
Sum -
SumSum $600,000.00
Sum $100,000.00 -
Sum $550,000.00 -
Sum $400,000.00 -
Sum $40,000.00 -
Sum $10,000.00 -
Sum $250,000.00 -
PS $50,000.00
Sum $250,000.00 -
Sum $200,000.00 -
Sum $80,000.00 -
Sum $50,000.00 -
-
Sum $200,000.00
Sum $80,000.00
Week 6,000.00 $60,000.00
Week 6,000.00 $60,000.00
Week 50,000.00 $500,000.00
140,000.00 $560,000.00
8,500.00 $34,000.00
m2
m2
Kg 3,600.00 $108,000.00 120.00 3600.00
13,000.00 $52,000.00 3.60 13000.00
58,000.00 $34,800.00 1.92 58000.00
PS $150,000.00
2,000.00 $8,000.00
m 11,000.00 $1,100,000.00
no. 112,000.00 $224,000.00
m2
m3
m2
no. 235000 $1,880,000.00
no. 31,500.00 $252,000.00
8,500.00 $306,000.00
13,000.00 $1,092,000.00
58,000.00 $174,000.00
2,000.00 $84,000.00
no. 50,000.00 $400,000.00
PS $600,000.00
m2
m2
m3
m2
m3
item $100,000.00
8,500.00 $1,632,000.00
7,100.00 $1,363,200.00
1,000.00 $192,000.00
PS $300,000.00
m2
m2
m2
4000 $100,000.00
m 46000 $621,000.00
SUM $100,000.00
Cub. M 240,000.00 $720,000.00
Kg. 260.00 $107,900.00
Kg. 300.00 $96,600.00
Kg. 350.00 $231,000.00
Sq. M 4,000.00 $92,000.00
Sq. M 3,000.00 $18,000.00
PS $650,000.00
m2
Cub. M 38,000.00 $11,400.00
Kg. 300.00 $6,300.00
Kg. 320.00 $31,040.00
Sq. M 13,000.00 $26,000.00
Cub. M 33,000.00 $264,000.00
Kg. 260.00 $133,640.00
Cub. M 5,000.00 $3,000,000.00
Cub. M 5,000.00 $200,000.00
Cub. M 4,000.00 $320,000.00
No. 24 $3,271.25
M3 0.5 $140,000.00
no. 5 $20,000.00
M 70 $7,000.00
ITEM
Sum
item 8 $37,500.00
M2 7 $9,250.00
M 10 $8,000.00
M3 0.069 $39,600.00
M 5 $4,000.00
No. 240 $300.00
No. 10 $1,562.50
M2 1 $15,625.00
M2 2 $1,375.00
Item
M 3 $28,200.00
M2 8 $6,750.00
item 6 $4,229.00
M2 0.2 $41,000.00
M 0.5 $70,250.00
4 $55,000.00
4 $8,500.00
Kg 5 $3,600.00
m2
m2
7.6 $10,000.00
1.5 $58,000.00
4 $1,375.00
1.5 $7,000.00
8 $7,100.00
$20,854,880.00
m2
m3
m2
m2
m2
ADDITION OMISSION
TOTAL QUNTITY RATE TOTAL
-
-
-
-
-
-
-
$50,000.00
432000.00
46800.00
111360.00
$150,000.00
70.00 11000 $770,000.00
$600,000.00
192.00 1000.00 $192,000.00
$300,000.00
$650,000.00
78510.00
70000.00
100000.00
490000.00
$19,375.00
$20,000.00
$ 300,000.00
$ 64,750.00
$ 80,000.00
$ 2,732.40
$ 20,000.00
$ 72,000.00
$ 15,625.00
$ 15,625.00
$ 2,750.00
$ 84,600.00
$ 54,000.00
$ 25,374.00
$ 8,200.00
$ 35,125.00
$ 220,000.00
$ 34,000.00
$ 18,000.00
$ 76,000.00
$ 87,000.00
$ 5,500.00
$ 10,500.00
$ 56,800.00
$2,656,626.40 $2,712,000.00
A
B
C
D
E
F
G
H
J
A
B
C
D
E
F
G
H
A
B
C
D
E
A
B
C
D
E
F
G
H
J
K
A
B
C
D
E
F
A
B
C
1
2
3
4
5
6
7
8
REPAIR TO PILE CAPS
BILL NO. 3
Pile Caps
Repair to Pile Caps on Grid Lines B, C and E
Kg
PS
Repair to Pile Caps on Grid Lines B, CD, , E, N, P and V
m
no.
Complete repairs as outlined to Pile Caps and concrete pile muff protection over water depth between 1m and 6m
Remove delaminated and spalling concrete to sides of pile cap to depth of 100mm below reinforcement and clean with potable water using high pressure water jet equipment during low tide level
m2
Allow for cleaning of rebars with wet sand blasting, high pressure potable water jet and mechanical cleaning to White Metal (SSPC-SP5) (NACE1). (Corroded portion of rebar exposed to damaged face of pile caps)
m2
Allow for the replacement of corroded rebar where required with 16mm diameter bars x 1m, bent and welded to existing rebar as per drawing sheet 2a and as instructed by the Engineer and coated with epoxy zinc chromate primer to exposed surfaces
Supply and install wrought formwork to soffit and sides of pile cap. (for minimum concrete thickness of 150mm) inclusive of supports and bracing and striking on completion
m2
Place design concrete mix containing chloride inhibitors and super plastisizers having a 28 day cube strength of 30 Mpa
m3
Allow Provisional Sum of $150,000.00 for supply and installation of sacrificial anodes ( to be used as directed by the Engineer and to removed in whole or part if unused)
Allow for the application of repair mortor to surface of repaired concrete beam to seal and close any cracks which may appear.
m2
Chase cracks to minimum depth fo 30mm by 60mm wide and repair with approved masonary repair concrete such Phoscrete supplied by PowerGen Limited (or similar product approved by the Engineer)
Clean during low tide exposed concrete and steel reinforcement to 2no. Pile Head supporting Pile Cap D appox 0.4 x 0.45m x 2no at splash zone by water blasting with potable water and apply layers of phoscrete concrete as per manufacturer instruction to ac
REPAIR TO PILE CAPSBILL NO. 4
Repairs to Deck Support Beams
no.
no.
Supply and install wrought fromwork to soffit and side of beam.
no.
PS
TOTAL BILL NO. 4 - REPAIRS TO DECK SUPPORT BEAMS
REPAIR TO PILE CAPS
BILL NO. 5
Painting and Protective Coatings
TOTAL BILL NO. 3 - REPAIRS TO PILE CAP carried to summary
Repair/Reinstatement of damage to Precast Double Tees on Grid Lines 5, 6, 7 & 8
Allow for temporary support and work access to each Double Tee sections (approx. 14m length) in water depth varing between 1m and 6m deep, during beam repairs
Remove 0.5 m2 delaminated and spalling concrete to expose at least 150mm of tendon on either side of damaged double Tee beam
Sandblast reinforcement tendons to remove corrosion and apply zinc chromate primer to exposed tendons
m2
m2
Place design concrete mix containing chloride inhibitors etc having a 28 day cube strength of 30 Mpa
m3
Allow for the application of repair mortor to surface of repaired concrete beam to complete repairs and seal any cracks which may appear on surface of ccncrete.
m2
Allow for the temporary work access platform to complete repairs to cracks in Double Tee beams in water depths 1m to 6m
Include Provisional Sum of $600,000.00 to be used as instructed by the Engineer. To be deducted in whole or part if unused.
Alternative (Rate Only)
Apply shot crete or build up concrete having a 28 day cube strength of 30 Mpa to complete beam repair around reinforcement tendons inclusive of final surface render finish.
m3
item
PS
REPAIR TO DAMAGED T PIER
BILL NO. 6DEMOLITION AND ALTERATION
m
Cart away spoil SUM
PRE-CAST REINFORCED CONCRETE
Reinforced Concrete 4500 PSI in:
Precast Reinforced Concrete Beam fixed to top of piles as per drawing Cub. M
Allow for the installation of protective drop cloth or equivalent method to facilitate the collection of sand and debris at each location resulting from the sandblasting of the concrete surface (measured seperately)
Remove existing paint finish to to sides and soffit of 8 no. pile caps by wet sand blasting or water blasting as required
m2
Apply approved corrosion inhibiting coating to the previously prepared and new concrete surfaces of 8no. Pile caps as per manufacturers instruction
m2
Repaint exterior surfaces (sides and soffit) of 8no. pile caps with approved exterior marine grade paint finish, colour to match existing
m2
Allow Provisional Sum of $300,000.00 to be used as instructed by Engineer. To be removed in whole or part if not used
TOTAL BILL NO. 5 - PAINTING & PROTECTIVE COATINGS carried to summary
The demolition of existing in-situ slab between centre lines 3-4 and A-B . The removal and replacement of two "L" -shaped beams and repair one pile cap at 3B.
Carefully remove following damaged concrete section of pier inclusive of all false work and safety measures
22'-0" x 12'-0" x 8" section of reinforced concrete slab supported on 8" thick precast concrete slabs (to be reused) mounted on damaged reinforced concrete beams (measured seperately)
m2
Damaged 18"x16"x22' reinforced concrete beams mounted on pile caps as supports to precast slab and insitu slab. Insitu slab to be removed and measured seprately.
This section covers the replacement of 2 No. Pre-cast reinforced concrete beam and in-situ 200mm concrete slab. Prices should include for all costs involved in order to fulfill every requirement of the design specification and any particular site conditio
Steel Reinforcement
10 mm diameter Mild steel rod reinforced Kg.
16 mm diameter high tensile rod reinforced Kg.
25 mm diameter high tensile rod reinforced Kg.
Formwork and support to:-
Side of beam Sq. M
Ditto bottom of beam Sq. M
PS
REPAIR TO DAMAGED T PIER
BILL NO. 7
Include the PROVISIONAL SUM of $650,000.00 for Contingencies to be used
as directed by the Engineer and to be deducted in whole or in part if not
required:-
TOTAL BILL NO. 6 - REPAIR TO DAMAGED T PIER carried to summary
IN-SITU REINFORCED CONCRETE
Reinforced Concrete Pile Cap
Pile Cap - Concrete 431 M.Pa Cub. M
12 mm diameter mild steel rod reinforced Kg.
16 mm diameter high tensile rod reinforced Kg.
Sides of pile cap Sq. M
In-situ Reinforced Concrete Slab
Cub. M
10 mm diameter mild steel rod reinforced Kg.
200 mm thick slab laid on Pre-Cast slab (measured seperately) finished with broom finish.
TOTAL BILL NO. 7 - IN-SITU REINFORCED CONCRETE carried to summary
REPAIR TO DAMAGED T PIER
BILL NO. 8
SHORE PROTECTION - BOULDERS
Cub. M
Ditto with boulder 0.3m - 0.8m diameter ( Provisional) Cub. M
Cub. M
To supply material , labour to place boulders 0.9m and 1.2m in diameter as rock armouring to shoreline in accordance with specifications (Provisional)
Carefully reclaim boulders(0.9m and 1.2m in diameter) from seabed in a depth of water not exceeding 1.5m for repacking in rock armouring (Provisional)
SUMMARY
PRELIMINARIES
Bill No.1 - FIXED PRELIMINARIES
Bill No.2 - TIME DEPENDENT PRELIMINARIES
TOTAL BILL NO. 8 - SHORE PROTECTION - BOULDERS carried to summary
REPAIRS TO PILE CAPS
Bill No.3 - REPAIRS TO PILE CAPS
Bill No.4 - REPAIRS TO DECK SUPPORT BEAMS
Bill No.5 - PAINTING & PROTECTIVE COATINGS
REPAIR TO DAMAGED T PIER
Bill No.6 - DEMOLITION AND ALTERATION
Bill No.7 - IN-SITU REINFORCED CONCRETE
Bill No.8 - SHORE PROTECTION - BOULDERS
GRAND TOTAL
PRELIMINARIES
REPAIRS TO PILE CAPS
REPAIR TO DAMAGED T PIER
GRAND TOTAL - TO STANDARD FORM: CONTRACTORS BID
D&S
20,500.00 82,000.00 130,600.00 560,000.00 48600.00
15,900.00 63,600.00 18,500.00 34,000.00 (45100.00)
16,000.00 480,000.00 18,750.00 108,000.00 (461250.00)
15,000.00 60,000.00 58,000.00 52,000.00 (2000.00)
48,000.00 28,800.00 25,500.00 34,800.00 (3300.00)
150,000.00 150,000.00 150,000.00 0.00
15,500.00 62,000.00 136,840.00 8,000.00 74840.00
3,500.00 350,000.00 155,000.00 1,100,000.00 (195000.00)
120,000.00 240,000.00 125,040.00 224,000.00 (114960.00)
1,516,400.00 818,230.00 2,270,800.00 (698170.00)
100000 800,000.00 494,560.00 1,880,000.00 (305440.00)
15,500.00 124,000.00 386,600.00 252,000.00 262600.00
10,900.00 392,400.00 189,540.00 306,000.00 (202860.00)
15,000.00 1,260,000.00 1,218,000.00 1,092,000.00 (42000.00)
48,000.00 144,000.00 127,500.00 174,000.00 (16500.00)
15,500.00 651,000.00 1,436,820.00 84,000.00 785820.00
60,000.00 480,000.00 494,560.00 400,000.00 14560.00
600,000.00 600,000.00 600,000.00
- 750,000.00 750000.00
4,451,400.00 5,697,580.00 4,788,000.00 1246180.00
350,000.00 550,000.00 100,000.00 200000.00
8,900.00 1,708,800.00 630,720.00 1,632,000.00 (1078080.00)
3,500.00 672,000.00 680,064.00 1,363,200.00 8064.00
2,500.00 480,000.00 893,760.00 192,000.00 413760.00
300,000.00 300,000.00 300,000.00
3,510,800.00 3,054,544.00 3,587,200.00 (456256.00)
80,000.00 1,850,000.00 100,000.00 1770000.00
53,000.00 587,250.00 621,000.00 534250.00
10,000.00 245,000.00 100,000.00 235000.00
31,250.00 93,750.00 165,000.00 720,000.00 71250.00
82.00 34,030.00 134,875.00 107,900.00 100845.00
82.00 26,404.00 123,970.00 96,600.00 97566.00
82.00 54,120.00 254,100.00 231,000.00 199980.00
300.00 6,900.00 241,500.00 92,000.00 234600.00
300.00 1,800.00 87,000.00 18,000.00 85200.00
650,000.00 650,000.00 650,000.00
1,010,004.00 4,338,695.00 2,736,500.00 3328691.00
26,500.00 7,950.00 16,500.00 11,400.00 8550.00
82.00 1,722.00 6,825.00 6,300.00 5103.00
82.00 7,954.00 37,345.00 31,040.00 29391.00
3,300.00 6,600.00 21,000.00 26,000.00 14400.00
26,500.00 212,000.00 440,000.00 264,000.00 228000.00
82.00 42,148.00 167,050.00 133,640.00 124902.00
278,374.00 688,720.00 472,380.00 410346.00
4,000.00 2,400,000.00 6,900,000.00 3,000,000.00 4500000.00
3,800.00 152,000.00 460,000.00 200,000.00 308000.00
1,500.00 120,000.00 600,000.00 320,000.00 480000.00
2,672,000.00 7,960,000.00 3,520,000.00 5288000.00
3,900,000.00 15,056,100.00 2,810,000.00 11156100.00
1,942,500.00 6,306,300.00 620,000.00 4363800.00
1,516,400.00 818,230.00 2,270,800.00 (698170.00)
4,451,400.00 5,697,580.00 4,788,000.00 1246180.00
3,510,800.00 3,054,544.00 3,587,200.00 (456256.00)
1,010,004.00 4,338,695.00 2,736,500.00 3328691.00
278,374.00 688,720.00 472,380.00 410346.00
2,672,000.00 7,960,000.00 3,520,000.00 5288000.00
19,281,478.00 43,920,169.00 20,804,880.00 24638691.00
5,842,500.00 21,362,400.00 3,430,000.00 15519900.00
9,478,600.00 9,570,354.00 10,646,000.00 91754.00
3,960,378.00 12,987,415.00 6,728,880.00 9027037.00
19,281,478.00 43,920,169.00 20,804,880.00 24638691.00
P&S
478000.00
(29600.00)
(372000.00)
(8000.00)
6000.00
0.00
(54000.00)
750000.00
(16000.00)
754400.00
1080000.00
128000.00
(86400.00)
(168000.00)
30000.00
(567000.00)
(80000.00)
336600.00
(250000.00)
(76800.00)
691200.00
(288000.00)
76400.00
20000.00
568000.00
90000.00
626250.00
73870.00
70196.00
176880.00
85100.00
16200.00
1726496.00
3450.00
4578.00
23086.00
19400.00
52000.00
91492.00
194006.00
600000.00
48000.00
200000.00
848000.00
(1090000.00)
(1322500.00)
754400.00
336600.00
76400.00
1726496.00
194006.00
848000.00
1523402.00
(2412500.00)
1167400.00
2768502.00
1523402.00
SELECTED RATES- T-PIER REPAIRS
Description unit Engineer's Est Diving & Salvage
m² 3200 74,000.0 4,000.0
m 3926 43,500.0 46,000.0
10 mm diameter Mild steel rod reinforced kg 220 325.0 260.0
16 mm diameter high tensile rod reinforced kg 220 385.0 300.0
25 mm diameter high tensile rod reinforced kg 220 385.0 350.0
Formwork and support
Side of beam Sq. M 3000 10,500.0 4,000.0
Bottom of beam Sq. M 3000 14,500.0 3,000.0
200 mm thick slab laid on Pre-Cast slab (measured seperately) finished with broom finish. m³ 26500 55,000.0 33,000.0
PERCENTAGE DIFFERENCE BETWEEN THE TENDERED RATES AND THE ENG.'S ESTIMATE
Description unit Engineer's Est Diving & Salvage
m² 3200 2212.5% 25.0%
m 3926 1008.0% 1071.7%
10 mm diameter Mild steel rod reinforced kg 220 47.7% 18.2%
16 mm diameter high tensile rod reinforced kg 220 75.0% 36.4%
25 mm diameter high tensile rod reinforced kg 220 75.0% 59.1%
Formwork and support
Side of beam Sq. M 3000 250.0% 33.3%
Bottom of beam Sq. M 3000 383.3% 0.0%
200 mm thick slab laid on Pre-Cast slab (measured seperately) finished with broom finish. m³ 26500 107.5% 24.5%
TENDERED AMOUNT COMPARED WITH THE ENG.'S ESTIMATE FOR SELECTED ITEMS.
Description unit Engineer's Est Diving & Salvage
m² 80,000.00 $1,850,000.0 $100,000.0
m 53,000.00 $5,872.5 $621,000.00
10 mm diameter Mild steel rod reinforced kg 91,300.00 $134,875.0 $107,900.0
16 mm diameter high tensile rod reinforced kg 70,840.00 $123,970.0 $96,000.0
25 mm diameter high tensile rod reinforcedkg 145,200.00 $254,100.0 $231,000.0
Formwork and support
Side of beam Sq. M 69,000.00 $241,500.0 $92,000.0
Bottom of beam Sq. M 18,000.00 $87,000.0 $18,000.0
200 mm thick slab laid on Pre-Cast slab (measured seperately) finished with broom finish. m³ 256,000.00 $440,000.0 $264,000.0
Pavement & Structures
22'-0" x 12'-0" x 8" section of reinforced concrete slab supported on 8" thick precast concrete slabs (to be reused) mounted on damaged reinforced concrete beams (measured seperately)
Damaged 18"x16"x22' reinforced concrete beams mounted on pile caps as supports to precast slab and insitu slab. Insitu slab to be removed and measured seprately.
Pavement & Structures
22'-0" x 12'-0" x 8" section of reinforced concrete slab supported on 8" thick precast concrete slabs (to be reused) mounted on damaged reinforced concrete beams (measured seperately)
Damaged 18"x16"x22' reinforced concrete beams mounted on pile caps as supports to precast slab and insitu slab. Insitu slab to be removed and measured seprately.
Pavement & Structures
22'-0" x 12'-0" x 8" section of reinforced concrete slab supported on 8" thick precast concrete slabs (to be reused) mounted on damaged reinforced concrete beams (measured seperately)
Damaged 18"x16"x22' reinforced concrete beams mounted on pile caps as supports to precast slab and insitu slab. Insitu slab to be removed and measured seprately.
SELECTED TASKS- %DIFF. BETWEEN ENG.'S EST. AND BID AMOUNT
Description unit
20,500.00 32,650.00 140,000.00
15,900.00 4,625.00 8,500.00
kg 16,000.00 625.00 3,600.00
15,000.00 14,500.00 13,000.00
48,000.00 42,500.00 58,000.00
15,500.00 34,210.00 2,000.00
m 3,500.00 1,550.00 11,000.00
no 120,000.00 62,520.00 112,000.00
no 100,000.00 61,820.00 235,000.00
no 15,500.00 48,325.00 31,500.00
10,900.00 5,265.00 8,500.00
Supply and install wrought fromwork to soffit and side of beam. 15,000.00 14,500.00 13,000.00
48,000.00 42,500.00 58,000.00
15,500.00 34,210.00 2,000.00
no 60,000.00 61,820.00 50,000.00
Item 350,000.00 550,000.00 100,000.00
8,900.00 3,285.00 8,500.00
3,500.00 3,542.00 7,100.00
2,500.00 4,655.00 1,000.00
Engineer's Est
Diving & Salvage
Pavement & Structures
Remove delaminated and spalling concrete to sides of pile cap to depth of 100mm below reinforcement and clean with potable water using high pressure water jet equipment during low tide level
m²
Allow for cleaning of rebars with wet sand blasting, high pressure potable water jet and mechanical cleaning to White Metal (SSPC-SP5) (NACE1). (Corroded portion of rebar exposed to damaged face of pile caps) m²
Allow for the replacement of corroded rebar where required with 16mm diameter bars x 1m, bent and welded to existing rebar as per drawing sheet 2a and as instructed by the Engineer and coated with epoxy zinc chromate primer to exposed surfaces
Supply and install wrought formwork to soffit and sides of pile cap. (for minimum concrete thickness of 150mm) inclusive of supports and bracing and striking on completion m²
Place design concrete mix containing chloride inhibitors and super plastisizers having a 28 day cube strength of 30 Mpa m³
Allow for the application of repair mortor to surface of repaired concrete beam to seal and close any cracks which may appear. m²
Chase cracks to minimum depth fo 30mm by 60mm wide and repair with approved masonary repair concrete such Phoscrete supplied by PowerGen Limited (or similar product approved by the Engineer)
Clean during low tide exposed concrete and steel reinforcement to 2no. Pile Head supporting Pile Cap D appox 0.4 x 0.45m x 2no at splash zone by water blasting with potable water and apply layers of phoscrete concrete as per manufacturer instruction to ac
Allow for temporary support and work access to each Double Tee sections (approx. 14m length) in water depth varing between 1m and 6m deep, during beam repairs
Remove 0.5 m2 delaminated and spalling concrete to expose at least 150mm of tendon on either side of damaged double Tee beam
Sandblast reinforcement tendons to remove corrosion and apply zinc chromate primer to exposed tendons
m²
m²
Place design concrete mix containing chloride inhibitors etc having a 28 day cube strength of 30 Mpa
m³
Allow for the application of repair mortor to surface of repaired concrete beam to complete repairs and seal any cracks which may appear on surface of ccncrete.
m²
Allow for the temporary work access platform to complete repairs to cracks in Double Tee beams in water depths 1m to 6m
Allow for the installation of protective drop cloth or equivalent method to facilitate the collection of sand and debris at each location resulting from the sandblasting of the concrete surface
Remove existing paint finish to to sides and soffit of 8 no. pile caps by wet sand blasting or water blasting as required
m²
Apply approved corrosion inhibiting coating to the previously prepared and new concrete surfaces of 8no. Pile caps as per manufacturers instruction
m²
Repaint exterior surfaces (sides and soffit) of 8no. pile caps with approved exterior marine grade paint finish, colour to match existing
m²
Description unit
82,000.00 59.27%
m² 63,600.00 -70.91%
kg 480,000.00 -96.09%
m³ 28,800.00 -11.46%
m² 62,000.00 120.71%
m 350,000.00 -55.71%
no 240,000.00 -47.90%
no 800,000.00 -38.18%
no 124,000.00 211.77%
m² 392,400.00 -51.70%
Item 350,000.00 57.14%
m² 1,708,800.00 -63.09%
m² 480,000.00 86.20%
Engineer's Est
Diving & Salvage
% DIFF. BETWEEN ENGINEER'S EST. & BID SUM
Remove delaminated and spalling concrete to sides of pile cap to depth of 100mm below reinforcement and clean with potable water using high pressure water jet equipment during low tide level
m²Allow for cleaning of rebars with wet sand blasting, high pressure potable water jet and mechanical cleaning to White Metal (SSPC-SP5) (NACE1). (Corroded portion of rebar exposed to damaged face of pile caps)
Allow for the replacement of corroded rebar where required with 16mm diameter bars x 1m, bent and welded to existing rebar as per drawing sheet 2a and as instructed by the Engineer and coated with epoxy zinc chromate primer to exposed surfaces
Place design concrete mix containing chloride inhibitors and super plastisizers having a 28 day cube strength of 30 Mpa
Allow for the application of repair mortor to surface of repaired concrete beam to seal and close any cracks which may appear.
Chase cracks to minimum depth fo 30mm by 60mm wide and repair with approved masonary repair concrete such Phoscrete supplied by PowerGen Limited (or similar product approved by the Engineer)
Clean during low tide exposed concrete and steel reinforcement to 2no. Pile Head supporting Pile Cap D appox 0.4 x 0.45m x 2no at splash zone by water blasting with potable water and apply layers of phoscrete concrete as per manufacturer instruction to ac
Allow for temporary support and work access to each Double Tee sections (approx. 14m length) in water depth varing between 1m and 6m deep, during beam repairs
Remove 0.5 m2 delaminated and spalling concrete to expose at least 150mm of tendon on either side of damaged double Tee beam
Sandblast reinforcement tendons to remove corrosion and apply zinc chromate primer to exposed tendons
Allow for the installation of protective drop cloth or equivalent method to facilitate the collection of sand and debris at each location resulting from the sandblasting of the concrete surface
Remove existing paint finish to to sides and soffit of 8 no. pile caps by wet sand blasting or water blasting as required
Repaint exterior surfaces (sides and soffit) of 8no. pile caps with approved exterior marine grade paint finish, colour to match existing
CONTRACT
ITEM DESCRIPTION QUANTITY UNIT
CONTRACT SUM
REMEASURED WORKS - All rates are as per contract
BILL NO. 3 - Pile CapsC
30 KG
D
4 M2
E0.8 M3
VARIATIONS
VARIATION No. 1
Dowel 25mm rebars into existing slab
24 No.
removespalling concrete from additional t-pier cap 0.5 M3
VARIATION No. 2
replace barrier on T-Pier
5 no.
70 M
Apply Nitobond to deck support beamITEM
Allow for the replacement of corroded rebar where required with 16mm diameter bars x 1m, bent and welded to existing rebar as per drawing sheet 2a and as instructed by the Engineer and coated with epoxy zinc chromate primer to exposed surfaces
Supply and install wrought formwork to soffit and sides of pile cap. (for minimum concrete thickness of 150mm) inclusive of supports and bracing and striking on completion
Place design concrete mix containing chloride inhibitors and super plastisizers having a 28 day cube strength of 30 Mpa
Chase crack to a minimum depth of 30mm x 60mm wide and repair with approved masonry repair concrete ( Rendoroc)
additional work to widen Gate as Directed Sum
VARIATION No. 3
Repair to Stem of Deck BeamsAllow for relocating the pantoon between span of pile clusters. 8 item
A7 M2
B10 M
C0.069 M3
D5 M
E
240 No.
Repair to the Soffit of Beams
A10 No.
B 1 M2
C To apply Nitobond SBR as bonding agent to deck beams 2 M2
D
Remove delaminated and spalling concrete to a depth ( > 10 MM) so as to expose reinforcement and clean with potable
water .
Allow for cleaning of rebars with wire brush to remove all corrosion and wash with potable water. (Corroded portion
of rebar exposed to damaged face of stem)
Place design masonary repair concrete such Renderoc HB (or similar product approved by the Engineer) to a thickiness no
less than 12mm
Chase cracks to minimum depth fo 12mm and 30 mm wide; repair with approved masonary repair concrete such Renderoc
(or similar product approved by the Engineer)
Allow for removing concrete from defective area (0.07 sq. m) of beam stem, clean rebars with wire brush to remove all corrosion
and treat with zinc chromate. Repair using Renderoc HB (Corroded portion of rebar exposed to damaged face of stem).
apply Nitobond SBR as per manufacturer's specification.
Remove 0.2 m2 delaminated and spalling concrete to a minimum depth of 12mm so as to expose rebars of the soffit of deck
beam.
Wire brush rebars to remove corrosion, wash with potable water and coat with zinc chromate
Place design masonary repair concrete such Renderoc HB ( similar product approved by the Engineer) to a thickiness no
less than 12mm
Repairs to Pile Cap
A3 M
B 8 M2
C 6 item
D 0.2 M2
E
0.5 M
VARIATION No. 4
A 4
B 4
C 5 Kg
D 7.6
Chase cracks to minimum depth fo 30mm by 60mm wide and repair with approved masonary repair concrete such as
Renderoc (or similar product approved by the Engineer)
Remove delaminated and spalling concrete to a minimum depth so as to expose rebars
Allow for cleaning of rebars with wire brush to remove all corrosion and wash with potable water.
Place design masonary repair concrete such Renderoc HB ( similar product approved by the Engineer) .
Effect repairs to one corner ( 1M X1MX 0.5M) of a a pile cap, remove spalling concrete, clean corrosion from bars using wire
brush , treat with zinc chromate , shuttering and apply apply deisgn concrete with chloride inhibitor of design strength no less
than 30 Mpa.
Complete repairs as outlined to Pile Caps and concrete pile muff protection over water depth between 1m
Remove delaminated and spalling concrete to sides and base of pile cap to depth of 100mm below reinforcement and clean with potable water using high pressure water jet equipment during low tide level
m2
Allow for cleaning of rebars with wet sand blasting, high pressure potable water jet and mechanical cleaning to White Metal (SSPC-SP5) (NACE1). (Corroded portion of rebar exposed to damaged face of pile caps)
m2
Allow for the replacement of corroded rebar where required with 16mm diameter bars x 1m, bent and welded to existing rebar as per drawing sheet 2a and as instructed by the Engineer and coated with epoxy zinc chromate primer to exposed surfaces
Supply and install wrought formwork to soffit and sides of pile cap. (for minimum concrete thickness of 150mm) inclusive of supports and bracing and striking on completion
m2
E 1.5
F Allow for Nitobond as per Manufacture's Instructions 4
G 1.5
H 8
OMISSION
General & Preliminary Items
K PS
BILL NO. 3 - Pile Caps
FPS
H 100 M
J
2
BILL NO. 4- Repairs to Deck Support Beams
H PS
BILL NO. 5 - Painting and Protective Coatings
D192 M2
E PS
BILL NO. 6 - Repairs to Damaged T-Pier
Place design concrete mix containing chloride inhibitors and super plastisizers having a 28 day cube strength of 30 Mpa
m3
m2
Allow for the application of Renderoc to surface of repaired concrete beam to seal and close any cracks which may appear.
m2
Apply two coats of the approved protective coating to match exterior colour.
m2
Allow Provisional Sum of $50,000.00 for the supply and installation of signs as per Engineers instructions
Allow Provisional Sum of $150,000.00 for supply and installation of sacrificial anodes ( to be used as directed by the Engineer and to removed in whole or part if unused)
Chase cracks to minimum depth fo 30mm by 60mm wide and repair with approved masonary repair concrete such Phoscrete supplied by PowerGen Limited (or similar product approved by the Engineer)Clean during low tide exposed concrete and steel reinforcement to 2no. Pile Head supporting Pile Cap D appox 0.4 x 0.45m x 2no at splash zone by water blasting with potable water and apply layers of phoscrete concrete as per manufacturer instruction to ac
Include Provisional Sum of $600,000.00 to be used as instructed by the Engineer. To be deducted in whole or part if unused.
Repaint exterior surfaces (sides and soffit) of 8no. pile caps with approved exterior marine grade paint finish, colour to match existing
Allow Provisional Sum of $300,000.00 to be used as instructed by Engineer. To be removed in whole or part if not used
H PS
Summary
CONTRACT SUM $20,854,880.00
REMEASURED WORKS $590,160.00
VARIATIONS $2,082,866.40
OMISSION ($2,886,001.20)
GRAND TOTAL $20,641,905.20
Include Provisional Sum of $600,000.00 to be used as instructed by the Engineer. To be deducted in whole or part if unused.
OMISSION ADDITIONAL
RATE QUANTITY TOTAL RATE QUANTITY TOTAL
$20,854,880.00
$3,600.00 $120.00 $432,000.00
$13,000.00 $3.60 $46,800.00
$58,000.00 $1.92 $111,360.00
SUB-TOTAL $590,160.00
Eng. Estimate @ $2,900.00 $3,271.25 $78,510.00
Rate is as per BQ/6 - ITEM A $140,000.00 $70,000.00
Eng. Estimate @ $18,500.00 $20,000.00 $100,000.00
Eng. Estimate @ $7,700.00 $7,000.00 $490,000.00
Eng. Estimate @ $17,000.00 $19,375.00
Eng. Estimate @ $ 20,000.00 $20,000.00
Eng. Estimate @ $ 32,500.00 $37,500.00 $300,000.00
Eng. Estimate @ $ 14,000.00 $9,250.00 $64,750.00
Rate in the contract is $8,500.00 $8,000.00 $80,000.00
Eng. Estimate @ $ 49,000.00 $39,600.00 $2,732.40
Eng. Estimate @ $2,700.00 $4,000.00 $20,000.00
Eng. Estimate @ $287.00 $300.00 $72,000.00
Eng. Estimate @ $1,600.00 $1,562.50 $15,625.00
Eng. Estimate @ $11,900.00 $15,625.00 $15,625.00
Eng. Estimate @ $3,500.00 $1,375.00 $2,750.00
Eng. Estimate @ $17,680.00 Item $16,400.00
Eng. Estimate @ $11,000.00 $28,200.00 $84,600.00
Eng. Estimate @ $20,000.00 $6,750.00 $54,000.00
Eng. Estimate @ $2,500.00 $4,229.00 $25,374.00
Eng. Estimate @ $49,000.00 $41,000.00 $8,200.00
Eng. Estimate @ $80,000.00 $70,250.00 $35,125.00
Eng. Estimate @ $47,000.00 $55,000.00 $220,000.00
Rate is as per BQ/6 Item B $8,500.00 $34,000.00
Rate is as per BQ/6 Item C $3,600.00 $18,000.00
Eng. Estimate @ $13,000.00 $10,000.00 $76,000.00
Rate is as per BQ/6 Item E $58,000.00 $87,000.00
Eng. Estimate @ $1,400.00 $1,375.00 $5,500.00
Eng. Estimate @ $7,700.00 $7,000.00 $10,500.00
Rate is as per BQ/8 Item C $7,100.00 $56,800.00
SUB-TOTAL $2,082,866.40
$50,000.00
$150,000.00
$11,000.00 70.00 $770,000.00
$112,000.00 2.00 $224,000.00
$600,000.00
$1,000.00 192.00 $192,000.00
$300,000.00
600,000.00
SUB-TOTAL $2,886,001.20 $2,673,026.40
COMMENT
Discrepancies were identified and rate negotiate down
Discrepancies were identified and rate negotiated down
Item not originally included in the contract but revised spec related new rate.
Rate was negotiate down and agreed on
$2,165,226.40$5,772,001.20
The Eng. Est. is based on a figure in the contract, however the contractor revised the rate up.
The Eng. Est. is based on a Pro-rated figure already in the contract, however the contractor revised the rate down.
-$3,606,774.80
-$212,974.80
-$2,956,774.80
-$212,974.80
VARIATION 1
TASK PAJ PSLSTEEL $9,500.00 $11,185.00DRILL BIT $28,000.00 $28,000.00EPOXY $10,668.28 $12,000.00HAMMER DRILL $3,088.09 $4,000.00GENERATOR $4,019.81 $5,000.00CHOP SAW $1,828.05 $2,000.00MASON $4,500.00 $5,000.00LABOURER $3,125.00 $3,125.00DISPENSING KIT $5,054.14 $6,000.00TRANSPORTATION $2,000.00 $2,200.00
$71,783.38 $78,510.00rate for each dowel $2,990.97 $3,271.25
TO REMOVE DAMAGED WEDGES OF FOUR PILE CAPS OF THE T-PIER AND MAKE GOOD
TASK PAJ PSLBOAT $50,000.00HILTI HAMMER $10,000.00GENERATOR $10,000.00FALSEWORK $10,000.00LABOURER $10,000.00
$90,000.00
VARIATION 2
TO APPLY BONDING AGENT (NITOBOND SBR) TO MAIN PIER DECK
TASK PAJ PSLLABOURERS $12,500.00 $25,000.00BRUSHES $1,875.00 $1,875.00CEMENT $3,000.00 $3,000.00TRANSPORT $2,000.00 $2,000.00
$19,375.00 $31,875.00
DOWELLING INTO EXISTING IN-SITU SLAB USING 1" HT REBARS 2'-0 IN LENGTH AND AFFIXED WITH E22 EPOXY
The BQ rate was used as a
basis.
TO REPLACE DISPLACE BARRIER OF THE T-PIER
TASK PAJ PSLGENERATOR $4,600.00 $5,000.00HILTI HAMMER $4,600.00 $5,000.00CHOP SAW $1,725.00 $2,000.00EPOSY $3,450.00 $5,250.006" PVC $23,032.50 $22,023.405/8" REBAR $3,277.50 $3,343.202"X8"X14' LUMBER $10,120.00 $17,913.00BOLTSAND NUTS $4,370.00 $6,596.80PAINT & PAINTER $19,550.00 $19,123.60TRANSPORTATION $4,025.00 $7,500.00LABOURERS $6,250.00 $6,250.00
$85,000.00 $100,000.00