OPTIMISED DESIGN METHODOLOGIES FOR ENERGY-EFFICIENT BUILDINGS
INTEGRATED IN THE NEIGHBOURHOOD ENERGY SYSTEMS
eeEmbedded – D10.400
Final Project Report
Responsible Authors:
Peter Katranuschkov and Raimar J. Scherer (eds.)
Contributions: All project partners
Due date: 30.09.2017
Issue date: 17.09.2017
Nature: PU/CO
Coordinator: R. J. Scherer, Institute for Construction Informatics, Technische Universität Dresden, Germany
D10.400 Final Report
Version 2.0
Page 2/105
© eeEmbedded Consortium www.eeEmbedded.eu
Start date of project: 01.10.2013 Duration: 48 months
Organisation name of lead contractor for this deliverable:
Coordinator: TECHNISCHE UNIVERSITAET DRESDEN, Institute of construction informatics.
History
Version Description Lead Author Date
0.1 Deliverable Structure Peter Katranuschkov, Romy Guruz (CIB) 31.05.2017
0.2 Input Chapters 1, 2 and sect. 7.2.1 Romy Guruz (CIB) 14.06.2017
0.3 Contributions to Chapter 7 A. Ton (EPM) 21.06.2017
0.4 Contributions to Chapter 7 G. Dangl (IAB), A. Sukumar (RIB) 25.07.2017
0.5 Contributions to Chapters 4 and 7 M. Löffler (BAM), S. Poloczek (STA) 08.08.2017
0.5 Contributions to Chapter 7 P. Stenzel (EAS), F. Forns-Samso (GRA) 24.08.2017
0.6 Contributions to Chapter 7 R. Schär (SAR), J. Kaiser (IET) 01.09.2017
0.7 Contributions to Part 2 A. Navas (CEM) 01.09.2017
0.8 Contributions to Chapters 4, 5, 8 M. Löffler (BAM), S. Poloczek (STA) 04.09.2017
0.9 Contributions to Chapters 3, 6, 7 K. Baumgärtel, H. Pruvost, T. Grille, P. Katranuschkov (CIB)
05.09.2017
1.0 First complete draft of the report P. Katranuschkov (CIB) 06.09.2017
1.1 Contributions to Chapter 7 E. Mrazek, R. Zellner (NEM), K. Solvik (DDS) 08.09.2017
1.2 Contributions to Chapter 3 G. Calleja-Rodriguez (CEM) 08.09.2017
1.3 Contributions to Part 2 B. Protopsaltis (SOF), P. Katranuschkov (CIB) 11.09.2017
1.4 Full text/gap check and editing P. Katranuschkov, R. Schülbe (CIB) 14.09.2017
1.5 Full final draft P. Katranuschkov, R. Scherer, R. Schülbe (CIB) 15.09.2017
2.0 Approved by Coordinator and uploaded to ECAS
CIB 18.09.2017
Copyright
This report is © eeEmbedded Consortium 2017. Its duplication is restricted to the personal use within
the consortium, the funding agency and the project reviewers. Its duplication is allowed in its integral
form only for anyone's personal use for the purposes of research or education.
Citation
Katranuschkov P. & Scherer R. J. (eds.), (2017): eeEmbedded Deliverable D10.400 - Final Project Report; © eeEmbedded Consortium, TU Dresden, Dresden, Germany.
Acknowledgements
The work presented in this document has been conducted in the context of the seventh framework
programme of the European community project eeEmbedded (n° 609349). eeEmbedded is a 48
month project that started in October 2013 and is funded by the European Commission as well as
by the industrial partners. Their support is gratefully appreciated. The partners in the project are
Technische Universität Dresden (Germany), Fraunhofer-Gesellschaft zur Förderung der
angewandten Forschung E.V (Germany), NEMETSCHEK Slovensko, S.R.O. (Slovakia), Data Design
System ASA (Norway), RIB Information Technologies AG (Germany), Jotne EPM Technology AS
(Norway), Granlund OY (Finland), SOFISTIK HELLAS AE (Greece), Institute for applied Building
D10.400 Final Report
Version 2.0
Page 3/105
© eeEmbedded Consortium www.eeEmbedded.eu
Informatics IABI (Germany), FR. SAUTER AG (Switzerland), Obermeyer Planen + Beraten (Germany),
Centro de Estudios Materiales y Control de Obras S.A. (Spain), STRABAG AG (Austria) and
Koninklijke BAM Group NV (The Netherlands). This report owes to a collaborative effort of the
above organizations.
Project of SEVENTH FRAMEWORK PROGRAMME OF THE EUROPEAN COMMUNITY
Dissemination Level
PU Public X
PP Restricted to other programme participants (including the Commission Services)
RE Restricted to a group specified by the consortium (including the Commission Services)
CO Confidential, only for members of the consortium (including the Commission Services)
D10.400 Final Report
Version 2.0
Page 4/105
© eeEmbedded Consortium www.eeEmbedded.eu
TABLE OF CONTENTS
Executive Summary _______________________________________________________________________5
1. The project on a page _________________________________________________________________6
2. Vision, Mission and Goals of the Project __________________________________________________7
3. Top 10 Project Achievements ___________________________________________________________9
4. The eeEmbedded Holistic Design Methodology __________________________________________ 10
5. Pilot Demonstrators and Usage Scenarios _______________________________________________ 15
6. The eeEmbedded Virtual Lab Platform _________________________________________________ 20
6.1. Software Architecture __________________________________________________________ 20
6.2. Structure of the eeEmbedded Virtual Lab __________________________________________ 21
6.3. The eeEmbedded Multimodel Framework __________________________________________ 22
7. eeEmbedded Products and Findings ___________________________________________________ 24
7.1. Project Setup and Requirements Management Service ________________________________ 24
7.2. Design Tools _________________________________________________________________ 27
7.2.1. Architectural Design ______________________________________________________________ 27
7.2.2. HVAC Design ____________________________________________________________________ 30
7.2.3. BACS Design ____________________________________________________________________ 31
7.2.4. Energy System Modelling (ESIM) ____________________________________________________ 32
7.3. Scenario Manager _____________________________________________________________ 33
7.4. Multimodel Navigator __________________________________________________________ 35
7.5. Collaboration and Resource Management Services and Tools___________________________ 38
7.5.1. BIM—It ________________________________________________________________________ 38
7.5.2. EDM Model Server _______________________________________________________________ 39
7.5.3. Cloud Services __________________________________________________________________ 41
7.6. Model Validation Services _______________________________________________________ 43
7.6.1. Ontology-based Exchange Requirement Checking and Visualisation _______________________ 43
7.6.2. Ontology-based Key Point Checking and Visualisation ___________________________________ 45
7.7. Energy Simulation and Analysis Services and Tools ___________________________________ 47
7.7.1. Input Preparation ________________________________________________________________ 47
7.7.2. Thermal Simulations with TRNSYS___________________________________________________ 50
7.7.3. 3D Wind Analysis in Urban Design __________________________________________________ 52
7.7.4. 3D Therm Analysis in Detailed Design ________________________________________________ 54
7.8. LCA and LCC Analysis ___________________________________________________________ 56
7.9. Risk Assessment Service ________________________________________________________ 58
7.10. Multi Key Point Analysis Tool for Decision Making ____________________________________ 61
8. Evaluation of the eeEmbedded Platform ________________________________________________ 65
9. Exploitation of the eeEmbedded Platform ______________________________________________ 71
10. Conclusions _______________________________________________________________________ 73
Appendix _____________________________________________________________________________ 74
References ________________________________________________________________________ 74
Acronyms _________________________________________________________________________ 77
Partner Abbreviations _______________________________________________________________ 80
D10.400 Final Report
Version 2.0
Page 5/105
© eeEmbedded Consortium www.eeEmbedded.eu
Executive Summary
This deliverable report describes the overall final findings and achievements of the eeEmbedded project.
Publicly accessible via the project’s web site as well as via the EC web services, it gives an overview of the
project, presents the initial vision, mission and goals at the project start and explains the developed new key
point (KP) based holistic design methodology and the real pilot buildings used to validate, evaluate and
demonstrate the project developments and findings. It lists in concise form the main project achievements
and then goes into a more detailed presentation of the developed overall Virtual Energy Lab Platform and its
underlying Multimodel Framework and the component services and tools integrated in the platform for the
purpose of efficient energy-aware building design.
The report contains also a second part which is subject to confidentiality. It comprises a single Chapter
“Potential Impact”, structured in accordance with the predefined FP7 rules and providing an overview of the
project’s impact in terms of dissemination measures and activities, exploitable foreground and societal
implications.
All partners have contributed to the report under the lead of TUD-CIB as follows:
TUD-CIB: Report structuring and overall editing, main input to Chapters 1-5 and 10 as well as contributions
to Chapter 7 and Part 2
BAM: Main input to Chapters 6 and 8 and contributions to Chapter 3
CEM: Contributions to Chapters 3, 4, 7 and 8 and Part 2
SOF: Contributions to Chapters 7, 9 and Part 2
STA: Main input to Chapters 6 and 8
EAS, TUD-IET, NEM, DDS, RIB, EPM, GRA, IABI, SAR and OPB: Contributions to Chapter 7.
The partner abbreviations are shown in the Appendix to this report.
D10.400 Final Report
Version 2.0
Page 6/105
© eeEmbedded Consortium www.eeEmbedded.eu
1. The project on a page
eeEmbedded is an European FP7 industry-driven project established under call EeB.NMP.2013-5 “Optimised
design methodologies for energy-efficient buildings integrated in the neighbourhood energy systems”.
Project Budget: 11.388 M€
Duration: 4 years [01.10.2013 – 30.09.2017]
Main product: Collaborative design and simulation platform and related design methodology
The eeEmbedded consortium features a mix of 15 partners from 9 European countries, covering the whole
knowledge transfer chain and all key areas of research and development relevant to the project goals.
They represent 4 types of market segments:
End-users including construction, architectural and engineering companies as well as control systems
and equipment provider (Koninklijke BAM Groep NV, Netherlands; STRABAG AG, Austria; Centro de
Estudios Materiales y Control de Obras S.A., Spain; Obermeyer Planen + Beraten GmbH, Germany; Fr.
Sauter AG, Switzerland).
Software developers (Nemetschek ALLPLAN Slovensko SRO, Slovakia; Data Design System ASA, Norway;
Jotne EPM Technology AS, Norway; Granlund Oy, Finland; SOFiSTiK Hellas, Greece; Fr. Sauter AG,
Switzerland).
Research institutes with knowledge on BIM/IFC management and interoperability (Institute For Applied
Building Informatics, Germany) and control system modelling, numerical analysis and user activity
modelling (Fraunhofer-Gesellschaft zur Förderung der angewandten Forschung e.V., Germany).
Academic organization (TU Dresden, Germany, with the institutes Construction Informatics and Power
Engineering), specialized in BIM, SOA, ontologies, interoperability, cloud computing and related
orchestration management and in energy system modelling and numerical simulation of any related
system.
Coordinator of the project is the Institute of Construction Informatics of the TU Dresden.
Project Website:
eeEmbedded.eu
Project Career:
linkedin.com/company/eeEmbedded
Project YouTube Channel:
youtube.com/channel/UCkgcav2Q9Zbh
PzAY2a2sYwA
EC Contribution:
7.649 M€
D10.400 Final Report
Version 2.0
Page 7/105
© eeEmbedded Consortium www.eeEmbedded.eu
2. Vision, Mission and Goals of the Project
Already at the outset, when the proposal was prepared, clear vision, mission and goals of the eeEmbedded
project had been identified.
VISION
The project consortium set out to develop an open BIM-based holistic collaborative design and simulation
platform, a related holistic design methodology, an energy system information model and an integrated
information management framework for designing energy-efficient buildings and their optimal energetic
embedding in the neighbourhood of surrounding buildings and energy systems. In this environment, a new
design control and monitoring system based on hierarchical Key Performance Indicators (KPI) will support
the complex design collaboration process. Knowledge-based detailing templates will allow energy simula-
tions as soon as in the urban design phase, and BIM-enabled interoperability will provide for a seamless
holistic design process with distributed experts, and a seamless integration of simulations in the virtual
design office (energy performance, CO2, CFD, control system, energy system, climate change, user
behaviour, construction, facility operation), thus extending it to a real virtual design lab.
MISSION
The main products eeEmbedded (eeE) develops are:
A holistic design methodology based on a hierarchically structured dynamically evolving KPI system which
guides and monitors the progress of the multi-disciplinary, multi-model and multi-physics design process.
A collaborative, holistic design platform comprising a virtual energy design lab and a virtual multi-
disciplinary collaborative design office for the design and evaluation of new or retrofit buildings
embedded in their energetic environment and covering their energetic performance, their constructa-
bility and their energetic vulnerability on different levels of detail.
A new reference model schema for the Energy System Information Model (ESIM) structured according to
BIM-IFC (ISO 16739) and incorporating the topography structure of the energetic environment in
accordance with cityGML. This will complement BIM concerning the internal and external energy
systems, built on and subsuming the various proprietary data structures existing for energy systems.
An ontology-based open interoperability system as the baseline for managing the information and cross-
dependencies of the multi information models, BIM, ESIM and BACS, and the related multi-physics
problems and their computational analyses.
The vision of eeEmbedded was to increase, by an order of magnitude, the quality of energy-efficiency in
building design through the development of an In-Silico Energy Simulator Laboratory.
The mission of eeEmbedded was to develop ICT products and services that will provide for an efficient,
functional and easily configurable Virtual Energy Lab Platform based on an ontology-supported
interoperable BIM implementing established information management standards.
D10.400 Final Report
Version 2.0
Page 8/105
© eeEmbedded Consortium www.eeEmbedded.eu
A multi-model information management method and related management services enabling the
integration of the separately maintained domain models, combining them to multi-models wherever
needed, filtering out the right views with minimal amount of information, mapping the eeeBIM data to
the appropriate computational models and taking care of the interactions and feedback cycles for the
multi-physical interdependencies of the computational models with prototype implementation of the
building thermal energy system, the neighbourhood energy systems, natural ventilation and building-
wind interactions (cool out and wind tunnel effects).
A knowledge management system for fast and grounded design decision-making with characteristic design
detailing templates enabling quantitative analyses and simulations as soon as in the early design phases.
GOALS
Specifically, the project work was focused on the following 7 research and development objectives:
Interoperability of the design objectives as baseline for collaborative holistic design using a new KPI-
based design methodology; the new developed Key Points (KPs) shall act as guidelines for milestones
and control of the collaborative design process, providing the interoperability and monitoring the
progress of the design during its different phases.
Interoperability of the information for heterogeneous distributed information resources and services on
the basis of system and domain ontology schemas and tools
A knowledge structure over the information domain models providing the mapping information needed
to transform the domain information models to computational engineering models, as well as the
knowledge needed to decide on the necessary level of detail and the respective cross-model structure.
Holistic collaborative virtual design office based on collaborative and virtual enterprise methods to
manage people, tools and information, including a change management component to properly handle
the various changes arising during design and enabling to find, retrieve and compare multiple different
design alternatives with the help of an advanced BIM-based visualization system.
Holistic virtual design lab providing quantitative computational support based on efficient cloud computing
methods; the tools and services integrated in the virtual design lab will provide the computer power for the
various required engineering analysis and simulation tasks and will support the feedback cycles for the
interrelationships between the computational models, based on the interoperability of system information.
Stochastic approach as part of the overall virtual design lab approach, extending current deterministic
models and approaches to cope with the uncertainties in the lifecycle concerning climate, energy
provision, as well as the usage of the building and the human behaviour.
Knowledge-supported design methods enabling fast preliminary detailing in the early design phase. This
is a mandatory issue to be able to carry out computational analysis and simulations and to obtain
conclusive quantitative results about the energetic performance of the building and about the
vulnerability of the energy systems already at the early design stages, when fundamental energetic
design decisions have to be made that are hardly alterable later on.
The main objective of the project was to develop ICT building blocks based on standardised Building
Information Models that will integrate, complement and empower existing tools for design and
operation management to the envisaged Virtual Energy Lab.
D10.400 Final Report
Version 2.0
Page 9/105
© eeEmbedded Consortium www.eeEmbedded.eu
3. Top 10 Project Achievements
We consider the following results as Top 10 achievements of the eeEmbedded project:
Key Point based design method supporting the control of the collaborative design work and the
monitoring of the progress against the design objectives.
Open ICT platform incorporating the Scenario Manager for process management, the Multi-Model
Navigator for checking the models and assigning templates, and an extensible number of simulation and
analysis services and a KP analysis tool for decision making grouped in interlinked configurable Virtual
Energy Labs for each role and domain in the design process.
Structured Key Point setup enabling definition of performance objectives and requirements in holistic
and automated manner for verification and validation of the design objectives continuously, at all key
points throughout the design process.
Scenario Manager (ScM): This brand new prototype application supports the collaborative project
process by dynamically assigning and monitoring project tasks and attaching the required data and
actions to them. In this way, project work can proceed in coordinated manner with clearly allocated
responsibilities, work items and interdependencies for each member of the project team.
Project collaboration via consistent use of the BIM Collaboration Format (BCF): The integration of the
BCF platform in the ScM ensures effective communication in the project team. The successor in the
process is informed about the finalisation of the previous task and receives links to all the data
necessary for his/her task.
Easy creation and evaluation of variants: The eeEmbedded platform incorporates generic climate,
occupancy, construction, HVAC, BACS and maintenance templates which can be assigned to element
types, to analyse the impact of various parameters on the sustainable performance of a building.
Multi-Model approach: For most of the simulation tools a Multi-Model Container (MMC) was imple-
mented, which means that only one IFC file is needed per alternative, whereas various external information
sources and various variants are linked to elements in the IFC file using a variation matrix. E.g. for 50 design
variants there is no need to create 50 IFC models but only one model with 50 different variants linked to it.
Exchange Requirements (ER) checking: The Exchange Requirements which are crucial for collaboration
in the project team can be checked via the Ontology Verification Service (OVS) and missing information
highlighted in red in the BIM model. The service is directly integrated in the Scenario Manager, where
ER are linked to the specific tasks in the process.
BIM-based Interoperability APIs: In the eeEmbedded platform simulations and analyses run as services.
This means that the results of various variants are processed without interaction with the end user.
Manual work is significantly reduced via the developed APIs. The coupling of data and tools becomes
feasible and the pre-processing time for model preparation is brought to minimum, thereby enabling
affordable variant examination.
Just-in-time result evaluation and decision-making: The developed new decision-making tool analyses
the impact of Key Design Parameter (KDP) on sustainable Key Performance Indicators (KPI) such as
energy, emissions, thermal comfort and Life Cycle Costs (LCC). In addition, the impact of risks can be
analysed. The results are weighted based on the preferences and visualized in a decision value graph,
which makes the comparison of alternatives and variants very efficient and transparent.
D10.400 Final Report
Version 2.0
Page 10/105
© eeEmbedded Consortium www.eeEmbedded.eu
4. The eeEmbedded Holistic Design Methodology
eeEmbedded has developed a new ICT based intelligent methodology to design energy efficient buildings
integrated in their neighbourhood. It extends existing BIM developments with a multi-model approach for
modelling and analysing the building architecture and its systems (HVAC, BACS) considering facility
management strategies and integrating sophisticated simulations to optimise energy, costs and
environmental impact along the life-cycle of the building.
The design methodology was specified by the end-users of eeEmbedded at the beginning of the project
within the Deliverables D1.2 (Geissler et al., 2014), D2.1 (Guruz et al., 2015a, b). These specifications were
used by eeEmbedded developers as basis to implement the supported tools and services integrated in the
platform. After the implementation of the supported tools and services, the end-users have used them for
the design of two pilot buildings (Sprenger & Poloczek, 2017a, b). Finally, the developed methodology for
holistic energy efficient building design has been updated taking into account the implemented tools and
services and the experience from the performed pilot projects where the implemented tools and services
and the design methodology were used.
The eeEmbedded Methodology features a clear BIM-based approach. It uses Key Points to drive the design,
and Templates to facilitate and accelerate the process. The Key Points are measurable target values that
represent requirements coming from clients, regulations, site and designers. They are used as basis for
taking informed decisions on design solutions. The Templates contain valuable information to speed-up and
streamline the design process while sophisticated analysis methods are applied to a large number of design
variants and alternatives making use of cloud technology.
The major aspects of the developed methodology that distinguish it from state-of-the-art design work are as
follows:
Investing time on project setup
A comprehensive project setup is required to ensure integrated process, information flow and software in
BIM-based collaborative design and to avoid problems due to differences in working cultures, work
processes and software applications.
The more detailed the project setup is, the more straight forward the design process will be later on and the
more problems can be avoided in advance.
The project setup must precisely define:
Project Type in terms of building type, project address, contract type, budget and duration apart from
the project name and its description.
Project structure, i.e. the teams that will be involved and their roles.
Project infrastructure including the software that will be used and the required format of inputs and
outputs (IFC4, CSV, etc.).
Project requirements coming from sites, regulations and building owners; they must be described,
classified and aligned per domain and cross-domain as well as prioritized.
Key Points. The requirements must be translated into four types of measurable target values, also
known as Key Points: (1) Decision Values, (2) Key Performance Indicators, (3) Key Risk Indicators and
(4) Key Design Parameters. After detailing the Key Points, they must be linked to specific instants or
milestones of the design process (check points).
D10.400 Final Report
Version 2.0
Page 11/105
© eeEmbedded Consortium www.eeEmbedded.eu
Process setup, i.e. the definition and interrelationship of the major design tasks and their sequences as
well as the responsible actors.
Exchange Requirements, i.e. the information to be exchanged between the actors (inputs and outputs of
tasks).
The added value for AEC companies is the structured monitoring of all essential project requirements, which
requirements are verified and by whom. In this way it is possible to know whether the project is progressing
within the sustainable requirements and the budget which is an enormous support for quality control in
complex projects. The added value for the client is that s/he has continuous and transparent proof that all
the requirements are met in the project.
Using Key Points in structured ICT supported manner
The eeEmbedded methodology defines a comprehensive framework including rating scale and rules with the
end targets in mind. The basis is translating requirements and design criteria into Key Points which provide
verifiable design check points in form of target values. Key Points have two main missions. On the one hand,
they integrate all design criteria and requirements. On the other hand, they guarantee easy and fast
evaluation and comparison of design options based on relevant well-defined metrics.
Figure 1: Top down decomposition of requirements into Key Points and bottom up verification of Key Points
This means that already in the project brief of a project we need to develop the requirements and the major
design criteria top down according to the following steps:
Choose a Decision Value (DV) and set a target; e.g. sustainable score 85 or Internal Rate of Return of 5 %.
The Decision Value represents the preferences of the decision makers related to the project goals. It allows
prioritizing Key Performance Indicators by means of weighting factors (e.g., Passive House).
Define Key Performance Indicators (KPI) influencing the DV in order to be able to comprehensively
validate if the building is defined according to the clients’ needs. Prioritize those by weighting factors
and set targets based on a requirements analysis. Key Performance Indicators (KPIs) are numeric metrics
of building performance related to energy usage. They are influenced by Key Design Parameters and are
additionally the basis values for evaluation via Decision Values (e.g. cooling demand ≤ 15 kWh/m2a).
D10.400 Final Report
Version 2.0
Page 12/105
© eeEmbedded Consortium www.eeEmbedded.eu
Define Key Risk Indicators (KRI) and set target values that represent deviation of the building
performance due to the stochastic nature of various parameters such as risks related to energy use or to
the reliability of the energy system.
Define Key Design Parameters (KDP), and set targets based on a requirements analysis. Some Key Design
Parameters are already defined and act as constraints in the design process, whilst other parameters can
be adapted to optimise sustainable targets. Key Design Parameters (KDP) represent the required building
properties and usually have a limited value range (e.g. Uwall ≤0,15 W/m2K).
Figure 2: Overall procedure for the use of Key Points
Structured arrangement of processes, tasks, roles and information exchanges
Implementing the Building Information Modelling approach requires a clear arrangement of processes, tasks,
roles and information exchanges. The following questions must thereby be answered.
Who needs the information extracted from the building information model?
At which point in time this information is needed?
Which minimal amount of data has to be exchanged?
eeEmbedded recommends to digitally capture the information exchanges according to the IDM approach
(ISO 29481) and to steer and track them during the project.
To carry out this recommendation, exchange requirements are defined for the various BIM uses/phases and
configured for the specific project at hand in its digital environment. The developed Scenario Manager (ScM)
provides the functionality to setup and run the exchange requirements verification with the help of the
integrated Ontology Verification Service (OVS) and/or the externally used IfcDoc tool from buildingSMART.
Using Design Templates
Speeding up and streamlining the design process while integrating sophisticated analysis methods applied to
a higher number of design variants and alternatives within a shorter time works only when smart re-usable
templates are integrated into the design process. These templates are dividable into two types, (1) design
content templates and (2) process templates.
Main target of the template usage is the higher level of formalisation and the reproducible quality of design
and analysis results across projects and domains, the higher productivity of the involved design team, and
the highly improved capability to define and examine different design variants.
D10.400 Final Report
Version 2.0
Page 13/105
© eeEmbedded Consortium www.eeEmbedded.eu
Integration of both template types into design process starts with the setup of the project while using
process templates covering the step-by-step workflow including the targeted output quality and covering the
related exchange requirements between the process steps. The project setup should also cover the
agreement between the involved project partners about content templates. Typical examples for content
templates are pre-defined construction templates for building elements (walls, slabs, windows) and
equipment (HVAC, sensors and other building automation devices), and/or occupancy profiles as inputs for
both, the design and the analysis steps.
Figure 3: Content templates
Planning an urban design phase focused on energy
Urban design is crucial to take advantage of energy saving potential by using passive heating, photovoltaic
potential or natural ventilation. For example, it is widely known that the level of solar exposure which is
strongly linked to orientation and surrounding shadows influences heating, cooling and artificial lighting
needs of buildings.
In this line, it is important to create a trend to incorporate urban design and planning concepts into the building
design process in order to integrate them energy efficiently in their neighbourhood. That is why we
recommend having a first design phase focus on the urban design that takes into account energy
considerations. On the other hand, it is also crucial to include simulations and precise calculations as much as
possible into this first phase to increase the reliability of the decisions taken in the early stage of the design,
which are considered as the most influential decisions on the building performance (McArthur et al. 2014).
The urban design phase should thereby be focused on the development and evaluation of several building
cubature and energy supply concepts taking in consideration the integration into the neighbourhood and
the use of renewable or conventional resource on site and on district level. To this end it should include:
CFD simulations related to the climatic conditions (wind) to optimise thermal comfort and analyse the
integration of the building into the neighbourhood.
Energy building simulation to rank cubature variants in order to find the optimal energy demand
Taking into account uncertainties when ranking combinations of cubature and energy supply variants that
optimise energy consumption and use renewable or conventional resources on site and district level.
Life Cycle Cost analyses to also compare building cubature variants in combination with energy system
variants and the life cycle costs.
D10.400 Final Report
Version 2.0
Page 14/105
© eeEmbedded Consortium www.eeEmbedded.eu
Involving FM experts in the early phases of design
Traditionally, facilities management and property management (FM/PM) has been regarded with a poor
relation to the architecture, engineering and construction (AEC) industry. The eeEmbedded methodology
acknowledges that the role of FM is much wider than being involved only in the operational phase.
Therefore, FM/PM professionals’ involvement in the early phases of design and knowledge sharing
strengthens the integrated design process developed in the eeEmbedded project.
The involvement of FM professionals is perceived of high value for the entire facility lifecycle. Benefits are
seen in ensuring less rework, emphasizing value for money by taking into consideration life cycle aspects
such as LCC, LCA, investment costs, maintenance cost, flexibility, adaptability and environmental policies.
To date the use of BIM is not common for FM/PM professionals. However BIM tools are capable of
simulating and predicting different performance parameters that are very useful for the decision making
process at a strategic and operational level. FM/PM professionals do not need to necessarily know how to
perform the simulations but should be able to interpret and evaluate the results in form of key performance
indicators (KPIs) for making informed decisions in the long term. Potential KPIs generated for FM are related
to cost of maintenance and operation, revenue, space management, and environmental and safety issues.
These KPIs are integrated in the decision making methodology and supportive decision making tools used
during the design phases.
The methodology was elaborated for 3 design phases:
The urban design phase is focused on the development and evaluation of several building cubature and
energy supply concepts taking in consideration the integration into the neighbourhood and the use of
renewable or conventional resources on site and on district level. It comprises 7 tasks: project setup, design
cubature, CFD wind simulation, energy concept, lifecycle costing, energy simulations and overall decision
making.
The early design phase is focused on the modelling and analysis of combinations of construction types - for
rooms and building elements - and concepts for the HVAC system, the Building Automaton and Control
Systems (BACS) and Facility Management to optimise energy, environmental impact and costs along the life
cycle of the building. It encompasses 9 tasks: update project setup, develop construction types, develop
HVAC types, develop BACS types, FM concept, energy simulation, Lifecycle assessment analysis, LCC
calculation and overall decision making.
The detailed design phase is focused on the accurate development and analysis of room layout, combined
with the detailed design in terms of location and product features of HVAC systems, BACS systems and FM
strategies to optimise energy, environmental impact and costs along the life cycle of the building. It
encompasses 10 tasks: update project setup, create architecture product alternatives, create HVAC product
and location alternatives, design sensor and actuators network, enrich product alternatives with FM
information, energy simulation, CFD simulation, LCC calculation, LCA calculation and overall decision making.
A comprehensive description of the various aspects of the methodology and the developed design scenarios
is presented in Deliverable D2.5 “New ways of holistic working for energy optimized and embedded
building” (Calleja-Rodriguez et al. 2017).
D10.400 Final Report
Version 2.0
Page 15/105
© eeEmbedded Consortium www.eeEmbedded.eu
5. Pilot Demonstrators and Usage Scenarios
Two different pilot models of real buildings – W2 Leidsche Rijn (Figure 4) and Z3 (Figure 5) have been used to
verify and validate the platform and the KP methodology. Both pilots are office buildings, but with different
surroundings, architectural alignment with respect to other buildings and different working space inside as
well as different energy demand. The prepared initial CAD models were exported in the standard Industry
Foundation Classes (IFC) format and reflected as much as possible the necessary exchange requirements
specified in the Project Setup. The surroundings were modelled for the purpose of wind analysis using
computational fluid dynamics (CFD) and thermodynamic energy simulations.
Figure 4: eeEmbedded Pilot Demonstrator: W2 Building, Leidsche Rijn, BAM, Netherlands
Figure 5: eeEmbedded Pilot Demonstrator: Z3 Building, Züblin, Stuttgart, Germany)
D10.400 Final Report
Version 2.0
Page 16/105
© eeEmbedded Consortium www.eeEmbedded.eu
In accordance with the developed design methodology the two models were used to test and evaluate the
eeEmbedded virtual lab platform for the three targeted design phases: Urban Design, Early Design and Detailed
Design. Most comprehensive tests have thereby been performed for the Urban Design phase in order to verify
the holistic design goal of combining architectural and energy system (neighbourhood) design and the use of
energy and life cycle analyses and simulations as early as possible in order to facilitate optimal decision making.
Urban Design
In the Urban Design phase, the models are prepared as simple shapes. They consist of simplified spaces as
office, garage, staircase and slabs indicating the floors. The envelope is defined with external walls and a roof.
The end users proposed also three geometrical alternatives for each model. These differ with regard to shape,
orientation and/or size. Each of the alternatives was simulated with different variants of architecture and
energy systems. The specified variants are shown in Figure 6 below. They ensure that the evaluation is done
based on diverse configurations to have rich and diverse visual outcome demonstrating the flexibility, the
efficiency and the added value of the eeEmbedded methodology and the implemented ICT platform. The result
of the Urban Design phase reveals the best alternative to be further detailed and used for Early Design.
Figure 6: Urban design variants (Left: W2 Building Leidsche Rijn, Right: Z3 Building, Züblin, Stuttgart)
The design scenario for Urban Design is presented in Figure 7. During the first step of this scenario, setup for
the particular project within the Scenario Manager (ScM) of the eeEmbedded platform is prepared. The
project manager introduces information about the project, sets up the project process maps and assigns
project partners to the particular tasks. Decision Values (DV), Key Performance Indicators (KPI) and Key
Alternatives-IFCs
A1 (H Shape) WWR (NE & SW side) Heating System
40% District heating
60% Heat pump
U-Value Wall
Heavy - Brick: 0,19 W/m2.K
Leightweight - Steel: 0,15 W/m2.K
U-Value Window
2-pane: 1,10 W/m2.K
3-pane: 0,66 W/m2.K
A2 (U Shape) WWR (NE & SW side) Heating System
40% District heating
60% Heat pump
U-Value Wall
Heavy - Brick: 0,19 W/m2.K
Leightweight - Steel: 0,15 W/m2.K
Shell
2-pane: 1,10 W/m2.K
3-pane: 0,66 W/m2.K
A3 (Rectangular) WWR (NE & SW side) Heating System
40% District heating
60% Heat pump
U-Value Wall
Heavy - Brick: 0,19 W/m2.K
Leightweight - Steel: 0,15 W/m2.K
Shell
2-pane: 1,10 W/m2.K
3-pane: 0,66 W/m2.K
D10.400 Final Report
Version 2.0
Page 17/105
© eeEmbedded Consortium www.eeEmbedded.eu
Design Parameters (KDPs) are defined within the ScM. Architectural BIM models with alternatives are
created and uploaded as IFC files to the ScM. An Ontology Verification Service (OVS) is used to verify the
exchange requirements for the models and detect deviations. In addition, KDPs are checked visually in the
Multimodel Navigator (MMNav) accessible to all design team members via the Internet. End users assign
building occupancy and climate templates in MMNav and create variants by using construction and energy
system templates. Such templates can be assigned automatically using OmniClass classification or manually
to each building element. The next step is the CFD wind simulation, where wind flows are analysed and
alternatives which do not meet the set KPIs are either discarded or a message is sent to the designer to
optimise. Simulations are optionally done on stochastic scenarios in order to check design variable ranges
and uncertainties. The results from this process are sent further to the energy expert using the platform’s
services and the building collaboration format BCF (see Chapter 6 below).
Figure 7: Urban Design Scenario
Thermal simulation is performed using the same templates and variants as the CFD simulation. Energy
systems are analysed in TRNSYS for each alternative, including uncertainty analysis. The results are
transferred as BCF message with attached Multimodel Container (MMC) to the merging tool developed as
add-on of the EDM model server where all the information from templates and simulations is incorporated
into one BIM-IFC file. This file is transferred to the cost expert for the purpose of LCC calculation. In
iTWO/LCC cost templates are respectively selected and results are automatically generated from the data in
the IFC model. Finally, KPIs are checked and the information is forwarded for decision making. Granlund’s
Key Point Analysis (KPA) tool compiles all the results and presents them in a graphical way which provides
the designers with a clear overview of the best combination of a model alternative and a system or
construction variants that are the most suitable to use for energy-efficient design of an embedded building.
D10.400 Final Report
Version 2.0
Page 18/105
© eeEmbedded Consortium www.eeEmbedded.eu
Early Design
In the Early Design phase, the Level of Detail (LoD) of the selected best Urban Design alternative is increased.
Detailing of rooms and windows, exterior and interior doors is done and the space use and names of the
rooms as well as occupancy profiles are input. Materials of walls and floor construction are specified and
more detailed variants for exterior wall insulation, construction, glazing, HVAC and BACS were defined with
the aim to examine and evaluate the differences in energy performance, Life Cycle Costing (LCC) and Life
Cycle Assessment (LCA).
Selected Alternative Selected Alternative
Figure 8: Early design variants (Left: W2 Building Leidsche Rijn, Right: Z3 Building, Züblin, Stuttgart)
The design scenario is basically the same as for Urban Design (see Figure 9). However, after the thermal
simulation with TRNSYS, the HVAC concept is elaborated with successive ER and KP checks. Consequently, in
the MMNav, HVAC maintenance variants are set up and the eeBACS wizard is used to define the building
Alternatives-IFC Architecture HVAC BACS
A3 Exterior Walls_Insulation Material Heating & Cooling System Classification
Concrete block: 20 cm,
Mineral wool: 26 cm - 0,15 W/m2.K
Ceiling Induction A- High energy performance building automation
and control system (BACS) and technical building
management (TBM)
Concrete block 20 cm, Vacuum
panels + EPS: 8 cm - 0,15 W/m2.K
Concrete Core Activation B- Advanced BACS and TBM
Exterior Walls_Cladding Ventilation System
External cladding material: Stone
(Granite)
Ceiling Induction Unit
External cladding material: Metal Floor diffusors
20
cm
8 c
m
Ext
ern
al
Fin
ish
20
cm
26
cm
Ext
ern
al
Fin
ish
6 c
m A
ir g
ap
4 c
m G
ran
ite
20
cm
8 c
m
6 c
m A
ir g
ap
0,50
cm M
eta
l
20
cm
8 c
m
D10.400 Final Report
Version 2.0
Page 19/105
© eeEmbedded Consortium www.eeEmbedded.eu
automation and control systems. After that, energy simulations are performed, the results are merged by
the EDM server and LCC and LCA calculations are undertaken. Ultimately, all results are compiled and
evaluated with the help of Granlund’s KPA tool.
Figure 9: Early Design scenario
Detailed Design
Detailed Design follows the same steps as Urban and Early Design. It includes additionally thermal comfort
conditions estimation based on CFD simulation which follows the energy simulations. Comfort simulation is
done by using the 3DThermCFD tool developed in the project. The detailed geometry data is imported from
the enhanced BIM-IFC model. Operation points of the HVAC system and airflow conditions are specified
taking into account the desired usage scenarios, e.g. hot day during summer or the coldest day in winter.
Among others thermal and cooling loads are included from the templates. Energy simulation provides the
wall temperatures and solar gains from glazing surfaces. Also, BACS aspects are included. Detailed results
from the CFD simulation are presented via videos and 3D representations of suitable flow quantities are
shown as stream lines. These can be further attached to the IFC model in the MMNav.
The next Chapter 6 gives an overview of the overall eeEmbedded Virtual Lab Platform and its underlying
Multimodel Framework. Chapter 7 describes the integrated new or extended ICT services and tools and the
related major project findings enabling the use of the developed methodology in the industry context.
D10.400 Final Report
Version 2.0
Page 20/105
© eeEmbedded Consortium www.eeEmbedded.eu
6. The eeEmbedded Virtual Lab Platform
The eeEmbedded ICT platform comprises many end-user applications and service components which support
the design methodology in different ways. The combination of design tools, analysis tools, data tools and result
evaluation tools together with data servers led to the concept of an eeE Virtual Laboratory that can be
configured for the different goals and technical domains of the different members of the design team.
Combining such laboratories in a flexible environment encompassing data and compute cloud servers linked
together via a common service bus enables performing holistic energy studies about the designed buildings in
different design phases, starting already from the urban and early design stage.
6.1. Software Architecture
Some tools and components of each Virtual Lab are local software applications which import and export data
files like CAD or FM design. Some others are web components which provide REST-APIs. Therefore, the
software architecture is arranged as a service-oriented architecture (SOA) as shown in Figure 10. It is divided
in multiple layers:
User Layer: The eeEmbedded platform supports users from different domains. Each user has a specific
view on her/his data. The data are created and prepared for further usage in such views. Therefore, on this
layer role/domain specific tools are configured individually.
Virtual Lab Layer: The Virtual Lab Layer is responsible for providing the data connection among the
platform’s users, services and tools. This layer provides also interfaces to additional external tools which
are currently not compliant with tools from the user layer. Advanced BIM Tools like the Scenario
Manager (see Section 7.3) are aligned here to enable BIM workflows, data imports, file management and
building analyses.
Communication Layer: The communication layer provides the overall collaboration infrastructure. All
information and data files are shared within a Multimodel Container with the BIM—it collaboration
server via the Internet using the BCF approach (see Section 7.5.1).
Shared Service Layer: This layer manages the BIM workflows with its messages, events and tasks.
Workflow definitions created in the Scenario Manager are analysed by a workflow engine. This engine
informs the users when they have to do their work and what they have to do.
Service Component Layer: All external applications that help to handle data are aligned in that layer.
They can be called within the Scenario Manager workflows. Furthermore, the clients to web data
repositories and simulations are provided.
Repository Layer: The repository layer includes all data servers like BIM servers and template
repositories. While storage clouds are used to upload and download files to BIM servers, all simulations
run in compute clouds (Section 7.5.3) in order to allow analysing and evaluating hundreds of design
variants in parallel for the time of a little more than a single one.
The advantage of this layered SOA approach for the eeE Virtual Lab is the possibility to exchange
components in each layer without affecting components of other layers. Therefore, it is possible to use e.g.
D10.400 Final Report
Version 2.0
Page 21/105
© eeEmbedded Consortium www.eeEmbedded.eu
other BIM servers than the EDM model server (Section 7.5.2), other simulation tools than TRNSYS (Section
7.7.2) or another BIM management server than BIM—it (Section 7.5.1). This guarantees a fully flexible
system without relying on some special tools.
Figure 10: The eeE software architecture
6.2. Structure of the eeEmbedded Virtual Lab
As shown in Figure 10 the Virtual Lab Layer of the eeEmbedded platform comprises multiple virtual labs
which can be configured specifically for the needs of the separate domains and roles in the holistic design
process. In the scope of eeEmbedded the following views and virtual lab configurations have been
implemented:
Project Manager / Decision Maker
Architect
HVAC Designer
BACS Designer
Energy System Expert
CFD Simulation Expert
LCC Expert
D10.400 Final Report
Version 2.0
Page 22/105
© eeEmbedded Consortium www.eeEmbedded.eu
Further roles can be added using the developed architecture and methodology. Therefore, as a whole a
Virtual Design Office is established. One of its important features is that, while differently configured, all
virtual lab instances follow the same principal structure which enables their seamless integration into a
coherent overall platform. This unified structure comprises three layers:
User Layer, featuring general purpose or domain-specific authoring CAD tools, any other local domain
tools that require user interaction and the mandatory Scenario Manager (ScM) and Multimodel
Navigator (MMNav)
Analysis Layer, which bundles the interfaces to simulation and analysis services allocated on the
compute cloud of the platform
Core Layer, encompassing the needed collaboration, model validation and model management services
which are the same for all Virtual Lab instances and provide the functionality for their proper functioning
and interoperability within a consistent overall system. This layer includes also the APIs enabling the
interaction with the Service Bus and the underlying shared service layer of the platform (see Figure 10).
The next Chapter 7 describes the individual services and tools in the current realisation of the eeEmbedded
platform. With the exception of Section 7.5, which focuses on the infrastructure services “below” the service
bus, it presents the major exploitable components of the implemented Virtual Labs comprising the
eeEmbedded Virtual Design Office. The following Table 1 provides and overview.
Table 1: Implemented Virtual Lab tools and services by role and domain
Task / Tool / Service Virtual Lab Configurations
Project/BIM Manager
Architect HVAC Designer
BACS Designer
Energy Expert
CFD Simul. Expert
LCC Expert
Project Setup Service + (+) (+) (+) (+) (+) (+)
Arch. Design (Revit, Allplan … ) +
HVAC Design (DDS-CAD … ) +
BACS Design (eeBACS Wizard … ) +
BIM Checking (FZK, EDM, Solibri Viewers … ) + + + + +
ESIM Design Tools +
Scenario Manager (ScM) + + + + + + +
Multimodel Navigator (MMNav) + + + + + + +
ER / KDP Checking Services + + (+) (+) + + +
Thermal Simulation (TRNSYS) +
CFD Wind Simulation (3D Wind) +
CFD Thermal Simulation (3D Therm) +
LCA / LCC Analysis (iTWO LCA/LCC Plugin) +
Decision Making (Multi KPA Tool) + (+) (+) (+) (+) (+) (+)
6.3. The eeEmbedded Multimodel Framework
The outlined eeE Virtual Lab platform provides a flexible data concept, which allows sharing any needed
information in any data format using a concept called Multimodel Container (see Figure 11). Such a container
defines a structure that links different kinds of domain models via connections specified in Link Models.
Domain models are treated as independent information resources with their potentially own application
domain, data schema and data formalization. In this way Multimodels can be applied on any domain.
D10.400 Final Report
Version 2.0
Page 23/105
© eeEmbedded Consortium www.eeEmbedded.eu
There are several ways to realize the Multimodel Container (MMC). It can be implemented as compressed
archive file which contains all models or as a Multimodel that contains only the links to the actual resources.
In principal, Multimodel containers contain domain models from different domains and each model can be
independently processed by the project partners and their respective domain tools. Each partner can
thereby create or develop her/his own domain models and link them with existing models. This enables the
design partners to recombine the Multimodels based on their demands and the requirements of the project.
In eeEmbedded we have chosen this
concept because of the many
different proprietary data models the
involved tools need. The advantage is
that not all necessary data is added
to a single data model. This prohibits
redundant information in the overall
workflow, reduces model complexity
and minimizes the shared and stored
data. Hence, the eeE concept is not
to save all information in one huge
overarching model, more precisely
the building information model
expressed via IFC.
Figure 11: Multimodel container concept
We keep each file format as it is and interlink them with each other. Every user of such a Multimodel
container selects the domain models which are needed for her/his work. The tool which consumes the
Multimodel has to parse the link models to retrieve the expressed information space. Basically, in the
context of eeEmbedded a MMC provides the following structure with directories and files:
Multimodel [directory] - root directory
o bpmn [directory] - directory for BPMN workflows
MetaProcess.bpmn - BPMN workflow for the eeEmbedded meta process UrbanDesign.bpmn - BPMN workflow for the urban design phase EarlyDesign.bpmn - BPMN workflow for the early design phase DetailedDesign.bpmn - BPMN workflow for the detailed design phase
o keypoints [directory] - directory including the key point setup files
o links [directory] - directory including the link model files
o models [directory] - directory for all domain model files (BIM-IFC alternatives
templates, stochastic samples, occupancy profiles, climate
profiles)
o Multimodel.xml - meta information of all content in the Multimodel
o VariationModel.xml - information about all defined variants of a specific task.
The Multimodel is packed in ZIP format and attached as BIM snippet to BCF topics as explained in section
7.5.1. It is distributed via the ScM and most information is collected through services of the service
component layer (see Figure 10) from user applications like the Multimodel Navigator (MMNav), presented
in Section 7.4 below. The way how to retrieve information out of a MMC is described in more detail in
Section 7.3. During the eeE workflow the Multimodel information is increasing and all data files are stored
on BIM servers to be able to restore previous versions of BIM information.
D10.400 Final Report
Version 2.0
Page 24/105
© eeEmbedded Consortium www.eeEmbedded.eu
7. eeEmbedded Products and Findings
7.1. Project Setup and Requirements Management Service
The definition of all requirements is performed in accordance with the developed new design methodology.
It is supported by a newly developed user interface providing a front-end to the underlying ontology
framework of the eeEmbedded platform. Utilising VBA, XML, RDF/OWL and JAVA technologies, this
Microsoft Excel based user interface functions as editor for the generation and management of the ontology
models. The choice for Excel has as main reason that it is the best known and accessible spreadsheet tool
people use in general in their working environment. In that way, any project manager, BIM manager,
decision maker or owner can start using the interface and can easily and rapidly get into it.
Figure 12 shows schematically
the main parts of the interface
and the main steps to follow for
accomplishing a complete
project setup. The interface is
composed of several spread-
sheets, each related to some
requirement category and
representing a specific setting.
These categories decompose
requirements into:
Qualitative requirements
i. e. building functions de-
fined and selected using
the OmniClass classifica-
tion system,
Selection of generic pro-
duct libraries used conco-
mitantly for both building
design configuration and
for simulations,
Quantitative requirements
expressed in terms of Key
Point TO-BE values,
Design process settings for
establishing phases and
tasks,
Exchange requirements for
specification of mandatory
eeBIM data exchanges.
Figure 12: Workflow for the overall project requirement setup
Type categories, which are important for later automated template assignments and data filtering, are defined in
a first step. They are organized in five abstraction levels: District, Site, Construction, Space and Element.
D10.400 Final Report
Version 2.0
Page 25/105
© eeEmbedded Consortium www.eeEmbedded.eu
The District Level describes the available internal and external energy supply for the planned building.
This includes power plants as well as energy storages and the related values for energy consumption and
energy generation.
On the Site Level the building site of the planned building is described. The different areas, like parking
areas and areas for energy generation (e.g. area for solar panels), are detailed on this level.
The Construction Level contains the description of the different construction types like the type of the
building (e.g. High School, Police Station, Hospital, etc.) and other constructions.
On the Space Level the different spaces within the building are typified. This way certain Ifc space
elements can be related to a Restroom, Office Room, Corridor, etc.
The Elements Level represents the lowest level and contains various building element types.
By the definition of Key Point requirements the end user can address the four KP types introduced in the
methodology, i.e. decision value (DV), key performance indicators (KPI), key design parameters (KDP) and
key risk indicators (KRI). Figure 13 shows the DV setup view allowing to evaluate the designed building with
regard to owner’s preferences or to targeted certification schemes like LEED, BREEAM, DGNB, etc. (Guruz et
al. 2015b). More details about the DV definition are available in (Forns-Samso et al., 2015).
Figure 13: Spreadsheet dedicated to the configuration of the decision value (DV)
Figure 14 below shows the configuration sheet for the next setup level where all KPIs used in the project for
assessing performance criteria can be configured. These KP definitions are commonly used by certification
schemes and as usual metrics in civil engineering. For the pilots a fixed list of KP definitions was used, but it
is foreseen that in other practical applications such definitions would be extended and used as part of
companies’ knowledge. The same layout has been used for the three KP levels i.e. KPIs, KDPs and KRIs.
Figure 14: View of the sheet used for entering and setting KPI requirements.
D10.400 Final Report
Version 2.0
Page 26/105
© eeEmbedded Consortium www.eeEmbedded.eu
The specification of Exchange Requirements represents the last step of the overall project setup and is the
basis for all later quality check and model validation services (see Section 7.6). Therefore, Exchange
Requirements are specified for each domain as shown on the example in Figure 15.
Once the domain-specific ERs and the check rules have been defined by a BIM expert, the end users (designers)
can finish the ER setup for their project. As shown in Figure 16, a user can then (1) Load Selected Tasks from the
preceding “Design process setup”, (2) Select for each task a related domain-specific ER that shall be checked with
regard to the future eeBIM model, and (3) Load the corresponding check rules, so that during the design
workflow all rules are ready for use for the ER check which are performed on demand.
Figure 15: Exchange Requirement Table for the architectural domain
Figure 16: 3-Step Exchange Requirement Setup
D10.400 Final Report
Version 2.0
Page 27/105
© eeEmbedded Consortium www.eeEmbedded.eu
7.2. Design Tools
Design tools integrated in the eeEmbedded platform are on the user layer of the Virtual Lab. They are either
off-the-shelve CAD systems like Autodesk’s Revit®, or software products of the consortium partners that
have been extended or developed during the project (DDS-CAD - for HVAC Design, and eeBACS Wizard – new
tool developed for BACS design). Their purpose in the eeEmbedded methodology is to provide the initial
design input for analysis at the respective steps of the urban, early and detail design phases.
7.2.1. Architectural Design
Architectural design is accomplished by using a CAD tool that is certified to export standard BIM-IFC
files. In eeEmbedded predominantly Revit® has been used but Nemetschek’s ALLPLAN® is another possible
option. The emphasis of the project in that regard has been on the specific modelling and exchange
requirements that need to be fulfilled to ensure correct energy and LCC analyses.
Architecture Modelling and Exchange Requirements
Ensuring the quality of the model is essential for a streamlined process and the delivery of the
schedule analysis services and design steps. The most important factor for modelling is to use software
which supports the open IFC standard and enables tool-neutral information validation. The IFC model is one
of the main sources for analysing each step in the overall design workflow and it allows transferring different
exchange information within and between the different design domains. The most important model
investigations are as follows:
IFC Object Structure
The structure shown on Figure 17 needs to be observed for each IFC model as an input for all
subsequent information exchanges and mappings to/from design, analysis and simulation services and tools.
Figure 17: Principal IFC model structure on the example of the W2 pilot
D10.400 Final Report
Version 2.0
Page 28/105
© eeEmbedded Consortium www.eeEmbedded.eu
The IFC Model includes project, site, topography, surrounding neighbourhood buildings, storeys, spaces and
construction elements. The latter comprise walls, windows, doors, slabs, roofs etc. Terrain geometry and mass
models of neighbourhood buildings are modelled as different object but connected to IfcSite. Normally, IfcSite
means the construction site in closed sense. However, tor energy-related analysis the geometry of
neighbourhood buildings should be available within the IFC model as mass models whereas the neighbourhood
buildings are normally located outside the construction site in the closed project-specific sense.
Exchange information
This comprises:
Project Information, such as postal address of the site, project attributes (ID, name etc.), units of
measure, global measures (length, area etc.), decomposition type
Site Information, including site identification, spatial composition, spatial containment and various
site-related quantities. If the existing terrain contains several types of land use, e.g. parking areas,
streets, walkways etc., each of these types of land use should be modelled and named separately as
special types of terrain.
Building Information, including the building identification (ID, name, description etc.), various building
quantities, spatial composition and envelope geometry. Minimum one building per site has to be
defined with its reference point, orientation and building classification according to the applicable
national building codes. This data should be contained in instances of IfcClassificationReference,
Pset_BuildingCommon and Pset_BuildingUse in the BIM-IFC model.
Building storeys, including storey identification, various quantities and the spatial composition of each
storey.
Space related information including the space name, the space usage, specific space-related attributes
and quantities, the space occupancy and the geometric second level space boundaries defining the
complete physical or virtual delimiters of each space via instances of the IfcRelSpaceBoundary2ndLevel
relationship class in IFC.
Exporting IFC with Revit Plugin
For easier IFC export, a Revit plug-in called OneClickRevitToIFCExport has been developed by STRABAG.
All relevant settings are configured in advance within IFC export settings as shown in Figure 18.
Figure 18: IFC 4 Coordination View 2.0 for IFC4 export
The user runs the plug-in with a single click, which provides a comfortable and time-saving approach for
creating numerous IFC models with the same export settings. This solution minimizes errors which users may
make during the export configuration.
D10.400 Final Report
Version 2.0
Page 29/105
© eeEmbedded Consortium www.eeEmbedded.eu
Figure 19: Revit IFC export plug-in developed by STRABAG
Quality Checks
For the validation and quality check of IFC the following software tools can be used:
EDMmodelChecker/EDMstandAlone – stand-alone command line tool of partner EPM which validates
a model according to the IFC schema and the exchange requirements
FZK Viewer 4.7 (KIT) – powerful IFC viewer which incorporates model validation functions according to
the model schema
iTWO BIM Qualifier – validates the model specifically for iTWO requirements
Solibri Model Checker – established legacy tool for code checking of the model for different design
domains (architecture, fire safety, fire escapes etc.)
The ER and KP checking and model validation services developed in eeEmbedded (see Section 7.6).
Figure 20: Screenshots from the validation of the IFC model of the Z3 pilot building using the FZK Viewer 4.7 (left)
Challenges in generating an IFC file
Generating an IFC file that fits for all the software applications is not a straightforward task. Despite
following the outlined modelling and exchange requirements and recommendations there are still a number
of challenging issues regarding the correct generation of IFC data for the purpose of energy-related analyses
and simulations, which are not yet fulfilled by legacy authoring tools. They are discussed in the project
deliverable report D9.4 regarding the validation of the eeEmbedded platform on the example and
experience obtained from the performed tests and pilot studies (Sprenger & Poloczek, 2017b). Furthermore,
the possible specifications in the export functions of the legal CAD systems (even if they would work) are not
sufficient for some of the IFC contents. The MVD approach of buildingSMART does not yet solve this issue.
D10.400 Final Report
Version 2.0
Page 30/105
© eeEmbedded Consortium www.eeEmbedded.eu
7.2.2. HVAC Design
HVAC design software (DDS-CAD) facilitates complete design and calculation of pipe and duct systems.
Based on the intelligence information extracted from the architectural BIM-IFC, integrated calculations like
air flow requirements, heat/cooling loads etc. enable developing optimal HVAC systems for the building and
its usage. With DDS-CAD’s openBIM commitment, all types of available open construction library elements
can be used, even though the components must be enriched with technical data.
The role of HVAC design software in the early design stage is to import and analyse Space/Zone client
requirements like occupancy, schedules, room temperature, activity, level of comfort etc. in addition to the
spatial variants like area/volume, shape, location, glazing properties, sun blinds and so on. When these
requirements are collected, and the external climatic conditions such as winter/summer temperature,
humidity, solar radiation (ESIM) etc. are taken into account, a set of design criteria is applied to build up one
or several variants of the HVAC systems. The different variants provide for comparing options with regard to
to different building cost, physical space requirements, operating expenses and so on. All HVAC system
variants will have enough information in itself to transfer operational demands to BACS.
It is expected to read all Space/Zone requirements, except from the external climatic conditions, from an
architectural BIM-IFC model, where object properties such as Pset_SpaceThermalRequirements,
Pset_SpaceOccupancyRequrements etc. are correctly filled, and the design criteria like Pset_SpaceThermalDesign
are either provided from energy or CFD simulation tools, or by the HVAC design tool itself, which will use this data
to determine HVAC demands such as the size of air diffusers.
All variants of the HVAC model should have a minimum of information contents for the BACS to use, and all
components must be assigned to an IfcDistributionSystem with correct enumerated type. Components like
Air Terminal, Damper, Air Handling Unit (AHU) etc., where there is a direct link to the BACS software must
obligatorily contain this information.
Using the knowledge obtained from the HVAC design allows meeting TO-BE KPIs and KDPs quicker and
better. DDS-CAD’s approach to this information flow is to use standardized „openBIM“ knowledge templates
to all disciplines.
Figure 21: Example of the pre-dimensioning and modelling of one HVAC alternative with floor
heating (DDS Tool)
Figure 22: Example of the visualization of one alternative for ventilation with AHUs and ceiling induction in the Multimodel
Navigator of eeEmbedded (see Section 7.4)
D10.400 Final Report
Version 2.0
Page 31/105
© eeEmbedded Consortium www.eeEmbedded.eu
7.2.3. BACS Design
Including building automation and control systems (BACS) design into the holistic eeEmbedded
methodology is a new finding of the project which goes clearly beyond the current state-of-the-art process.
It has been figured out that the energy efficiency
classes according to EN15232 provide a suitable
guideline for such a design because this beings
different equipment such as AHUs, heating units
etc. down to a formal, computer-interpretable
categorisation.
In order to perform the BACS design, several underlying steps have to be performed in advance:
Proper IFC based BIM model of all spaces/zones of interest
Definition of functional relationships within the HVAC design as well as the usage of proper IFC standard
functional descriptions (such as IfcValve, IfcBoiler etc.)
The first and most important added value by using this approach is that energy efficient solutions are
designed in an early phase based on the provided models. In addition, the developed solutions are
comparable with previous projects and templates can be reused in other projects.
Figure 23 shows a screenshot of the developed eeBACS Wizard of the eeEmbedded project which supports
designing BACS consistently using BIM-IFC data and interacting with architectural and HVAC design using the
shared model data and the collaboration and resource management tools of the eeEmbedded platform. The
beta version of the eeBACS Wizard developed during the project supports the user in creating energy
efficient solutions from the beginning. It starts by analysing the available HVAC model and suggests a
minimal setup of control strategies based on the desired energy efficiency class according to EN15232. The
user can then customize the solution according to additional key points. The tool provides templates for
products including costs and approximated energy usage over the life time.
Figure 23: Screenshot of the developed eeBACS Wizard
D10.400 Final Report
Version 2.0
Page 32/105
© eeEmbedded Consortium www.eeEmbedded.eu
7.2.4. Energy System Modelling (ESIM)
Especially within the Urban Design stage architects and clients are interested in elaborating and
comparing different system approaches of energy system concepts on a general systemic level. The analysis
of current design steps involved in the creation of an energy system showed the informational gaps and the
need for a unified description of energy systems. In that regard, the identification of core parts within the
energy system in combination with a cross-domain-oriented set of properties was the starting point for a
concept targeting the development of a unified modelling approach.
Systems Engineering with its related modelling languages UML and SysML is the approach used for the
description of energy systems. A wide range of standards are available or currently under construction for
this topic. The achieved project results have to be interpreted as a snapshot of the current cross-domain-
driven movement towards the formalization of a common energy system description.
Figure 24: ESIM core parts and link model approach connecting related elementary models
Based on the analysis of existing approaches, a formal specification and conceptualization of the ESIM
ontology was achieved. The development of that ontology comprised five main steps, namely (1) require-
ment analysis, (2) vocabulary definition, (3) ontology conceptualization, (4) ontology search, selection and
reuse, and (5) ontology implementation.
Modelling environments supporting the system and requirement engineering approach by using the System
Modelling Language (SysML) are predestined to support a formalized system-oriented modeling approach.
In eeEmbedded, the need of different services for ESIM on knowledge level was clearly defined and the
functional requirements and intention of a set of related services were identified. This includes: (1) Converter
services, (2) Filter and query services, (3) Simulation mapper services as well as (4) Template management
services.
D10.400 Final Report
Version 2.0
Page 33/105
© eeEmbedded Consortium www.eeEmbedded.eu
Currently experts of several different domains such as ‘Smart City’, ‘Smart Grid’, ‘Smart Home’, BIM and
others are working intensively on the standardized modelling of several parts of the energy system as well as
the more formulized description of buildings and their neighbourhood. Within this topic a highly dynamic
development is recognisable resulting in completely new or re-worked standards and ‘best practice’
guidelines with high impact on the introduced approach of ESIM. Therefore, all findings regarding this topic
have to be understood as a starting point. The work on ESIM - especially the implementation - is an ongoing
task which goes beyond the timeframe of the eeEmbedded project while considering actual developments
within the external standardization activities.
7.3. Scenario Manager
The Scenario Manager (ScM) is a new product developed within eeEmbedded following the holistic design
methodology based on the IDM approach. It can support any BIM project in different design phases and it
was developed as a general tool which supports team management, process management and data
management for every project participant as mandatory part of the User Layer of every Virtual Lab
configuration (see Figure 10). Its features comprise:
Team management
o Define BIM teams
o Assign users to teams
o Define team roles for users (BIM manager, architect, energy expert, …)
Process management
o Define workflows for different design phases (urban design, early design, detailed design)
o Create tasks, gateways and flows following the BPMN standard
o Specify control points and design loops
o Assign users to tasks
o Assign exchange requirements (ERs) to tasks
o Issue notifications when users have to work on tasks
Data management
o Setup requirements for information levels, define target values and select possible building entities
o Share files with other users using Multimodel Containers and BCF topics
o Check data quality based on ERs
o Automatically upload/download files to/from servers on the cloud
o Merge data from different sources
o Help to prepare data for analyses
o Help to prepare results for KPI visualization.
Figure 25 shows the communication of multiple Scenario Managers within the eeEmbedded platform
(ScM A & ScM B). The applications are connected with the central BCF server, BIM—it (see Section 7.5.1) and
both are using the same workflow management engine (WFM Engine). This engine is responsible to load
D10.400 Final Report
Version 2.0
Page 34/105
© eeEmbedded Consortium www.eeEmbedded.eu
process models (BPMN diagrams) and to verify the status of the current running process. It notifies the
Scenario Managers about changes in the workflow, for example when a task was completed or a problem like
failed ER checks or failed key design parameter checks occur. Users can upload any file to the workspace and
can download all files from other users where they have access rights. The workspaces are synchronized each
time a handover to the next user in the workflow is done. The data which will be synchronized is held in
Multimodel Containers (see Section 6.3). A receiving application of a Multimodel Container selects the domain
models which are needed in its workspace and has to look into the Link Models to retrieve the information. The
Multimodel Container is attached as BIM snippet to the communicated BCF topic. This is an enhanced
approach for BIM—it (Section 7.5.1) which previously was focusing only on IFC data.
Figure 25: Communication between multiple ScMs on the eeEmbedded Virtual Lab platform
A BPMN editor included in the ScM supports the major BPMN elements like user task, flow, exclusive and
parallel gateway, start event and end event. The project manager models the workflow and uses tasks which
are specified in the key point setup table. S/he can assign to every task one user and some ERs. The ScM
emphasizes in every task which actions are supported in that workflow stage. Figure 26 shows the task level
view. User actions which are currently not possible are greyed out. Possible user actions are in bold black
colour. Each button is connected to applications like the EDM model server, the KPA tool or the Multimodel
Navigator. The data is transferred to and from those tools automatically. Hence, the user does not have to care
about how to store the data. Task files can be imported in the ScM via Drag&Drop. Once the user has
completed a task he can finish it and the handover to the next user will be done automatically as defined in the
BPMN diagram.
D10.400 Final Report
Version 2.0
Page 35/105
© eeEmbedded Consortium www.eeEmbedded.eu
Figure 26: Task level view in the ScM with emphasized user task (red colour) and possible user actions
7.4. Multimodel Navigator
The Multimodel Navigator (MMNav) is the second mandatory tool in each Virtual Lab configuration on the
User Layer of the eeEmbedded platform. It enables the user to check key design results arising in the various
domains of the design process. It provides also advanced functionality to set up new construction conditions
and to execute various simulations of proposed design variations and alternatives by the design team.
The Multimodel Navigator was developed on top of the bim+ platform of Nemetschek. It is a multi-media-
based navigation and visualization application that allows users combination of different graphical
representations of results elaborated in the eeEmbedded design scenarios. The tool runs on standard
Internet browsers and does not require software installation. For this reason, the MMNav is available
everywhere and on any device, which could be decisive for decision makers. The following Figure 27
provides a graphical overview of the most relevant functional units of the MMNav.
The application features:
Identification of graphical and numerical deviations, such as comparison of pre-set TO-BE design values
with actual AS-IS Values
Assignment of new construction templates, space use templates, or other numerical settings such as
climate data, latitude or longitude, north direction etc.; this allows users to run simulations as early as
possible and to examine different materials and construction variants
Ordering the execution of different simulations under variant conditions - Energy, Wind, Life cycle costs etc.
Storing design decisions and corresponding construction conditions
Support of communication issues.
D10.400 Final Report
Version 2.0
Page 36/105
© eeEmbedded Consortium www.eeEmbedded.eu
Figure 27: Functional Units of the MMNav (blue: developed or enhanced by eeE)
The following figures present some of the main features of the MMNav developed during the eeEmbedded
project. Figure 28 shows the use of the MMNav during the verification of Key Design Parameters (KDP). The user
is able to control the KDPs by opening and activating the nodes of the break-down structure. Each KDP is assigned
a traffic-light colour which indicates the deviation of the AS-IS to TO-BE Value (fulfilled, critical, not fulfilled). In the
presented example, all outer walls, which do not fulfil the Window-Wall-Ratio, are shown in red.
Figure 28: Verification of the Key Design Parameter “Window Wall Ratio (WWR)”.
3. ADMINISTERING PROJECT MEMBERS
Inviting persons to projects
Managing member roles
2. ADMINISTRATION OF BIM MODELS
Import of models via web service
Creating model revisions
Filtering of models
5. ADMINISTRATION OF PROPERTIES
Definition of project/model/objects
properties sets
4. PROJECT ATTACHMENTS
Simulation attachments
Filtering of attachments
Attachment of properties to BIM objects
1. ADMINISTRATION OF PROJECTS
Project views
Project selection
Filtering of projects
Multimodel Navigator’s functional Units
6. MMNav VIEW CONTROL OPTIONS
Basic Visualization options
Federated Model views
Object Explorer & Filtering by attributes
Information detail panel and attachments
Visualization of KPIs and KDPs
Definition of Multi-Model Structures
Definition of construction variants
Collaboration in eeE Scenarios
Visualization of Simulation results
D10.400 Final Report
Version 2.0
Page 37/105
© eeEmbedded Consortium www.eeEmbedded.eu
Figure 29 shows the construction templates break-down structure (left menu), which allows users to define
different Construction Variants. The assignment of objects to specific construction templates is supported by the
menu on the right. The navigation window is highlighting the walls in different colours, which corresponds to
individually selected construction templates. The linking of objects to construction templates is stored on the
cloud and can be easily recalled by the MMNav with the help of the Scenario Manager.
Figure 29: Assignment of objects having the same construction type for a given design variant
Figure 30 presents an example of the visualization of simulation results. Simulation results are automatically
attached to respective individual objects via the ScM after the simulation service is run. These results are
accessible for the user by clicking on the attachments in the menu on the right side.
Figure 30: Room simulation results attached to the related space object
D10.400 Final Report
Version 2.0
Page 38/105
© eeEmbedded Consortium www.eeEmbedded.eu
7.5. Collaboration and Resource Management Services and Tools
Collaboration and resource management services and tools are in the core of the Virtual Lab environment.
They are responsible for the common use of the eeEmbedded service bus (Communication Layer) and for the
intelligent access to the Repository Layer (Storage Cloud) and the analysis and simulation services (Compute
Cloud). In the current eeEmbedded platform realisation these services include BIM–It, supporting the BCF-
based communication, the EDM Model Server, providing a number of BIM-related data management
services, and a set of Cloud Services facilitating the parallel analysis of multiple design variants.
7.5.1. BIM—It
IABI’s BIM--It web application is a modern collaboration platform built for easy interoperability and
exchange between partners in all project types of the AEC industry. While it is fully useable with any modern
web browser, BIM--It is also built with an accessible API to allow the integration of external tools. In
eeEmbedded, the Scenario Manager utilizes the developed BCF API to connect multiple platform services
with BIM—It (see Figure 25).
The platform was originally developed to be a BCF capable collaboration server but has since evolved into a
tool that also offers services for project management and model analysis. It was the first available product to
support the BCF API, shortly after it has been officially released by buildingSMART International in early
2015. Multiple software companies use BIM--It as a reference implementation for a BCF Server and have
developed test suites against the platform.
BIM--It is extensively described in the eeEmbedded Deliverable D8.2. Its main use case is to coordinate
multiple project participants and to visualize building models for further checking and analysis. As a web
application, BIM--It is hosted in the Microsoft Azure Cloud. It’s an Asp.Net Core web application backed by a
relational SQL Server database. Some compute-intensive functionalities, such as converting building models,
is outsourced to a micro service architecture accessed via http.
Figure 31: Detailed view of a single issue in BIM--it
D10.400 Final Report
Version 2.0
Page 39/105
© eeEmbedded Consortium www.eeEmbedded.eu
7.5.2. EDM Model Server
The EDMmodelServer (EDM) provides a full featured repository for storing and manipulating ISO
10303 STEP EXPRESS based data, of which IFC 2x3 and IFC4 are two implementations. A fully featured EDM
server provides services adapted to both thin clients like web browsers and smart phones, and fat clients like
CAD systems and other full IFC data handling clients.
Opposed to the more common file based storage for IFC BIM data, EDM stores data as models, where each
model can logically refer to other models. While a model can be exported and imported in its entirety as a file, it is
often necessary to export and import subsets of a model with operations like extraction and merging. The
database system is designed to hold any number of models and each model has no size or instance number limit.
EDM can also store as part of the model data files (BLOBs) in the same way as any other attribute.
Supported file and transfer formats
The EDM can natively import and export data in several formats, including:
ISO10303 Part 21 Step Physical File Format (SPFF) and Part 28 XML format (P28)
IfcXml, an implementation of P28 XML
For Web Services: SOAP xml (Simple Object Access Protocol) and JSON (JavaScript Object Notation).
EDM supports any data defined by ISO10303 Part 11 EXPRESS Schema (P11) on full semantic level.
Applications, services and utilities are available for several important industrial standards like ISO 12006-3
(used for BuildingSMART Data Dictionary bSDD) , IFC2x3 and IFC4. As long as data is defined according to a
P11 Schema, import and export of this data are automatic processes. All data can be sent / received in the
P21 and P28 (XML) format. In addition, any other data formats like e.g. Comma Separated Values (CSV) can
also be accepted, but will require mapping. Traditionally, defining schema for and interfacing with such
legacy data is called „adaptation” and is done by implementation of „adapters“. For simpler data structures,
setting up an EXPRESS schema and adapters for the data is usually a relatively simple task.
Basic Functionality
EDM supports validation and integrity checks against the employed EXPRESS schema, in case of
eeEmbedded IFC4. The function layer checks automatically all data that are imported to the system against
constraints defined by the target schema. Express-X can be used to add user-defined rules for additional checking.
Merge / extract are powerful options for adding, replacing and extracting subsets of data, for example
domain models (HVAC, BACS, EL) in an IFC file, or embedded “non-traditional” data like lease areas or
maintenance data.
Extended Functionality
In those cases where the XPX language is not sufficient for implementing the requested functionality,
EDM supports the use of Server Side Plug-ins (SSPs) written in a generic programming language like C# or
VB.NET. A typical scenario for use of SSPs occurs when data and services provided by other nodes need to
be accessed, for example when:
Data validation requires the server to read ontology data from an external source
A workflow requires the server to send a mail to a particular user.
Such functionality can be implemented using SSPs. The effect is that the EDMmodelServer will both act as a
service provider and a service consumer on the service bus.
D10.400 Final Report
Version 2.0
Page 40/105
© eeEmbedded Consortium www.eeEmbedded.eu
Accessing server-side functionality in the EDMmodelServer
There are two main approaches for accessing data and functions in the EDMmodelServer:
Using an API, utilizing a binary protocol between client and EDM. This implies that the client links
to an EDM library for accessing the functions. The API functions hide the data transfer layer
between client and server. APIs called language bindings are available for several programming
languages like C# and Java.
Using a Web Service interface like http/SOAP or http/REST, utilizing a general “text based”
protocol between client and EDM. In this case there is no direct software dependency between
client and server. Access is provided via XPX queries. This means that as soon as a database query
is defined using XPX, it is also available on the web, provided that the client has the necessary
trust level. This mode is well adapted to “thin clients” like web browser applications.
Management of the EDMmodelServer-ifc and its data
As a companion to the EDMmodelServer, EPM delivers also the EDMmodelServerManager (MSM),
which provides access and user interface to a vast set of functions like
Model management (import and export, merge, extract, versioning etc.)
User and access management
Defining and running reports
Browsing and manipulating models (2D and 3D graphical viewer, user definable tree breakdowns,
property filtering and editing and much more).
Typical applications of EDM in the AEC industry are shown in Figure 32 below.
Figure 32: EDM Server Applications
D10.400 Final Report
Version 2.0
Page 41/105
© eeEmbedded Consortium www.eeEmbedded.eu
7.5.3. Cloud Services
Calculations involved in energy simulations demand large computing resources and thus deployment in the
cloud is an inevitable prerequisite for efficient exploration of design options towards achievement of optimal
building performance. Development work on cloud services exploited prior availability of all analysis tools as cloud
enabled applications and delivered a cloud framework abstraction that provides plug-ins for major existing cloud
frameworks and can easily cope with future cloud frameworks with minimal developer effort. The resulting cloud
services comprise: (1) a Broker Service that translates requests from the eeEmbedded service bus to various
cloud frameworks, and (2) Plug-ins to implement different cloud engine interfaces.
Figure 33: The eeE Cloud Framework
The Cloud Broker Service encapsulates all the details of the underlying cloud infrastructure masking
differences and implementation details (like hosting server location or specific cloud system details) thereby
providing a uniform eeEmbedded Cloud API. To guarantee that the Cloud Broker Service is globally accessible,
in the eeEmbedded service bus an advertisement/registration mechanism is used to publish service availability.
In particular, the Broker Service has been used to perform energy simulations with TRNSYS (Section 7.7.2) and
CFD simulations with the 3D Wind and 3D Therm applications (Sections 7.7.3, 7.7.4) using the developed API.
Figure 34: Energy Analysis running on a private cloud
D10.400 Final Report
Version 2.0
Page 42/105
© eeEmbedded Consortium www.eeEmbedded.eu
Figure 35: CFD Simulation Running on the HPC cloud system offered by a European Research Institute
The use of cloud based computing resources enables the management of simulations running in parallel.
However, this leads also to certain requirements regarding the simulation management concept which are
an inherent part of the overall simulation and optimization framework.
The simulation management is enabled by a Simulation Model Mapper which is part of the analysis domain
reflecting special needs of the used analysis tools as well as the used cloud environment.
The required capabilities can
be differentiated into (1) non-
functional, (2) functional and
(3) workflow-related.
Non-functional capabilities
are scalability, maintaina-
bility and adaptability
Functional capabilities are
related to infrastructure and
access management, self-
management or health-
control and information
acquisition and delivery
Workflow-related capabi-
lities are input management,
job-analysis-tracking, output
management and, as optio-
nal part, data archiving.
Figure 36: Example showing the information flow
D10.400 Final Report
Version 2.0
Page 43/105
© eeEmbedded Consortium www.eeEmbedded.eu
7.6. Model Validation Services
The model validation services are another important part of the core layer of the Virtual Lab environment.
While not mandatory for the functioning of the overall system, they are crucial for the achievement of
efficient high quality design because they ensure that modelling errors and gaps are largely avoided by the
exchange of model data within the design team, requirements are met and key points are appropriately
observed or deviations identified as early as possible. Therefore, the use of these services are highly
recommended by all end user partners in the eeEmbedded consortium.
7.6.1. Ontology-based Exchange Requirement Checking and Visualisation
The ontology-based Exchange Requirement Checking enables capturing the information exchanges
according to the buildingSMART Information Delivery Manual (IDM) as well as steering and tracking them
during the design process. It helps to systematize design tasks, level of information agreements and
exchange requirements (ER) for the various BIM uses/phases and configure them for each specific project in
a digital environment.
Implemented as a service the ontology-based ER Checking is available via the Scenario Manager (ScM). It
provides the functionality to setup and run ontology-based exchange requirements verification and
visualization. The added value is in insuring the model quality and the compliance with the information
requirements of the successor in the design process.
The overall ER Checking approach is outlined on Figure 37 below. It comprises the following steps:
(1) Exchange Requirement Setup: Exchange Requirement Specification as part of the Project Setup
(2) Exchange Requirement Setup: Defining Multi-Model View Definitions regarding the exchange
requirements by implementing ontology-based ER Checks using SPARQL queries
(3) Exchange Requirement Checking: Preparing the ER Checking by selecting relevant data models (e.g. IFC
and ESIM) as input data
(4) Exchange Requirement Checking: Performing the ER Checking on the basis of the input data
(5) Exchange Requirement Visualization: Generating a validation report for the end-user and result file for
the following Key Point Checking.
Figure 37: Overview of the ontology-based ER Checking
D10.400 Final Report
Version 2.0
Page 44/105
© eeEmbedded Consortium www.eeEmbedded.eu
Exchange Requirement Setup (Steps 1 & 2)
The specification of the Exchange Requirements and the corresponding mapping to a specific data schema is
part of the overall project setup (see Section 7.1). The setup of the ontology-based Exchange Requirement
Checking is also part of the project setup. However, in order to prepare for later ER checks some additional
preparation work is necessary. The tables used for detailed ER specification shown in Section 7.1 are thereby
extended by an additional column providing the links to the ER check definitions, which are specified
separately in advance using SPARQL queries. Figure 38 shows as example the SPARQL query to check if an
IFC model contains an IfcSite object which is decomposed by at least one IfcBuilding object.
Figure 38: Definition of an ER check based on the data schema mapping using SPARQL
Exchange Requirement Checking (Steps 3 & 4)
In order to warrant the quality of the data models of a design alternative within the eeEmbedded design
process, an iterative process of model creation (authoring tool) and ontology-based ER checking has to be
performed. After each design task (e.g. Create Design Cubature Options) the ER checking service can be
invoked through the ScM. By clicking the ER/LOD check button the task-related ER table including ontology-
based ER check is started and validates the quality of the elaborated design (see Figure 39).
Figure 39: Screenshot of the Exchange Requirement Checking Service for ER-1.10 ARCH
D10.400 Final Report
Version 2.0
Page 45/105
© eeEmbedded Consortium www.eeEmbedded.eu
Exchange Requirement Visualization (Step 5)
After the ER check has validated the data model input the result file highlights all information gaps in the
provided design alternative. Depending on the Exchange Requirement specification the ER check validates a
single data source or a multi-model. In the following Figure 40 the result of the ER check is visualized for the
Exchange Requirements that specify the needed information from architectural design. The colours in the
first column of the ER specification indicate whether information is available (green), not present (red) or
calculated/derived from other information (orange).
Figure 40: Visualization of the ER Checking results indicates in the first column whether the required information is available (green), not present (red) or calculated/derived from other information (orange).
7.6.2. Ontology-based Key Point Checking and Visualisation
While ER Checking is responsible for the quality of the input models, the KDP Check aims to check the
quality of the results of a certain design task. The requirements for KDP checking are defined during the
project set up phase (see Section 7.1). The KDPs can thereby be interpreted as extension of the ERs: ERs
define that an entity and respective entity attribute(s) should exist in the input model, while KDPs define the
ranges in which the attribute values are valid.
Before the KDP check can be triggered, similar to the ER Checking, the Multimodel Container and its content
has to be transferred to the KP ontology. This transformation is realized in several steps. In the first step the
relevant element types are transformed into OWL. This is realized by transforming the types from the Excel
sheets into SPARUL as an intermediate step. The SPARUL code is then interpreted by the Ontology
Verification Service (OVS) and the types are then mapped into OWL and linked with the predefined Link
D10.400 Final Report
Version 2.0
Page 46/105
© eeEmbedded Consortium www.eeEmbedded.eu
Ontology. After this step, the predefined Ontology Schemas of the KP ontology and the IFC ontology are
linked together with the types. The result is a linked schema of KPs, types and IFC elements.
Figure 41: OWL Representation of the Multimodel
After the schemata are created in OWL, the instances are generated. The target values of the KPs and the
types are defined in the project setup (see Section 7.1) where the specific links between KPs and types are
defined. Similar to the schema generation, instance generation also uses SPARUL code. For the comparison
of the set TO-BE and the actual AS-IS Key Point values the IFC model is transformed into IfcOWL using the
mapping tool from buildingSMART (http:// http://ifcowl.openbimstandards.org/IFC4_ADD1/index.html). The
final result is a complete ontology consisting of KP, type and IFC schemata and instances. Figure 42 shows
how the process is prompted within the project setup by a corresponding Excel-based GUI.
Figure 42: Multimodel generation in the project setup phase via the Excel-based GUI
TARGET VALUES ASIS VALUES
TYPE
ONTOLOGY
SCHEMA
IFC OWLSCHEMA
TYPE
ONTOLOGY
INSTANCES
KPONTOLOGY
SCHEMA
IFC OWLINSTANCES
KPONTOLOGY
INSTANCES
Link Ontology
KPValues
SelectedTypes
IFC Step Model
SPA
RQ
LR
ule
s
On
tolo
gy L
eve
l D
ata
Leve
l
Configurations for Model Generation
C:\Users\makad\Desktop\20170717_ScM_Project-Setup_MASTER-file_v24C:\Users\makad\Desktop\20170717_ScM_Project-Setup_MASTER-file_v24
Multi Model Selection
Select Multi Model C:\Users\makad\Desktop\20170502_eeE_Multimodel\20170502_eeEC:\Users\makad\Desktop\20170502_eeE_Multimodel\20170502_eeE
Select Variant
Start Model Creation
OWL Model Generation Parameters
SPARUL for Generate Entity Types
SPARUL for Entity Types to IFC Schema
OWL for KP Ontology
SPARUL for KPs to Entity Types
Yes
Yes
Yes
Yes
SPARUL for Entity Types to IFC
OWL for IFC Yes
Yes
Workspace Folder
D10.400 Final Report
Version 2.0
Page 47/105
© eeEmbedded Consortium www.eeEmbedded.eu
Both the TO-BE model and the AS-IS model are encoded in OWL. To check for the correct results, the
relationship between both models is described via SPARUL. The checking can then be triggered by the
Ontology Verification Service. In order to start the KP checking via the ScM the different SPARUL rules have to
be related to the different tasks. This information is included in the KP spreadsheets. Figure 43 shows an
example for the task/KP relation.
Figure 43: KP – Task Relation
The KP checking itself produces tabular results in a similar manner as the ER check service. Additionally, the
results can be visualised in the MMNav via automatically generated colour codes, which show the level of
fulfilment of a selected design parameter for all BIM elements associated to it. This is a very useful feature
since it allows quickly identifying gaps and critical points in the design. An example is shown in Section 7.4
which outlines the features of the MMNav (cf. Figure 28).
7.7. Energy Simulation and Analysis Services and Tools
Energy simulation and analysis applications are required to properly assess energy performance and enable
objective evaluation of various design variants. In the scope of eeEmbedded three such applications have
been integrated: (1) TRNSYS, providing for comprehensive thermal analyses/simulations in all targeted
design phases, (2) 3D Wind, providing for simulation of wind influence to assess building location and
orientation with regard to the neighbourhood and verify key parameters already in the urban design phase,
and (3) 3D Therm, providing for deep CFD simulation of selected critical zones/spaces to evaluate thermal
comfort in the detailed design phase.
7.7.1. Input Preparation
Typically, energy simulation analysis tools imply sophisticated mathematical models and therefore
require complex preparation of the input models, which is mostly done manually by an energy expert to
ensure that the simulation model reflects the design intent correctly. However, as energy performance is
affected by a high number of design parameters, whose influence is not easy to predict, today’s design
process calculate only a very few variants. This often leads to suboptimal solutions.
The eeEmbedded methodology suggests an approach to improve that situation by re-engineering the
simulation and analysis tools and thereby splitting the pre-processing, analysis/simulation and post-
processing steps into separate processes. This enables preparing a large number of parameter variations by
the end users (architect, HVAC designer or energy expert), which are then executed in parallel on a compute
cloud and compared and evaluated on the basis of the computed KPIs by a specialised Multi KPA Tool.
KP ID KP type KP group KP sub-category Name Task-ID Task-NameKDP01 KDP design geometry Building Height 20-10 20 01 Create design cubature options
KDP02 KDP design geometry Floor to floor height groundfloor 20-10 20 01 Create design cubature options
KDP03 KDP design geometry Number of floors 20-10 20 01 Create design cubature options
KDP04 KDP design geometry Gross floor area (GFA) 20-10 20 01 Create design cubature options
KDP07 KDP design energy U-Value Wall 20-10 40 01 Create energy system concepts
KDP08 KDP design energy U-Value Base Slab 20-10 40 01 Create energy system concepts
KDP09 KDP design energy U-Value Roof 20-10 40 01 Create energy system concepts
KDP12 KDP design energy Air tightness 20-10 40 01 Create energy system concepts
KDP13 KDP design comfort temperatures winter (perimeter) 20-10 40 01 Create energy system concepts
KDP14 KDP design comfort design temperatures winter (core) 20-10 40 01 Create energy system concepts
KDP15 KDP design comfort design temperature summer 20-10 40 01 Create energy system concepts
KDP16 KDP design geometry Window Wall Ratio (WWR) 20-10 40 01 Create energy system concepts
KDP18 KDP design energy systems Energy system cooling 20-10 40 01 Create energy system concepts
KDP19 KDP design daylight Area of regularly occupied spaces within 7.5m of exterior windows or atrium 20-10 40 01 Create energy system concepts
(1) Load KDPs and selected tasks (2) Setup KDP Check
D10.400 Final Report
Version 2.0
Page 48/105
© eeEmbedded Consortium www.eeEmbedded.eu
Crucial in that regard is the achievement of a high degree of automation in the input preparation. This
involves the following steps:
(1) Semi-automated assignment of design variants in the MMNav
(2) Automated generation of stochastic parameter variations to enable optional uncertainty analysis in
order to better estimate lifecycle risks
(3) Automatic generation of a Variation Model, linking the defined parameter variations to the base BIM-
IFC design model
(4) Using BIM2SIM plug-ins for the simulation tools to perform the transformation of the data from the
BIM model to the analytical simulation input models; here the most difficult part is the proper
interpretation of the geometry and the topology of the building and the respective generation of 2nd
level space boundaries, which are needed for the thermal simulations
(5) Using the developed cloud API to provide for fast parallel computation of all generated variants.
The first two of these steps are performed by tools embedded in the ScM on the User Layer, whereas the
subsequent three are performed automatically with the help of the support services on the Core and the
Analysis Virtual Lab layers.
In Step (1) design variants are created on BIM level using the MMNav. The process is facilitated by the use of
a library of templates for various climate and occupancy profiles as well as various element construction
types (for walls, slabs, roofs, ground plates, windows, doors) and the associated materials. Essential in that
regard is the association of element types to standard OmniClass items which can be done in the project
setup phase and enables initial fully automatic template assignment (see Figure 44).
Figure 44: Automatic element-template assignment in the Multimodel Navigator
Using templates, parameter variations can be easily done in the MMNav user interface, shown schematically
in the following Figure 45. Creating a design variant only requires the input of the desired parameter
D10.400 Final Report
Version 2.0
Page 49/105
© eeEmbedded Consortium www.eeEmbedded.eu
changes, whereas all other data is automatically interlinked to the new variant from the imported base BIM-
IFC model.
Figure 45: The user interface for template assignment in the Multimodel Navigator
In Step (2), performed in the case of a desired Uncertainty Analysis, a special input preparation tool called
Sampling Service is additionally used. It can be launched from the ScM. However, before the sampling can be
performed, some parameters have to be configured. These are the chosen number of samples, the time
interval for the output time series, the building location and the number of days each sample should
comprise (see Figure 46).
Figure 46: Sampling Service GUI
When the sampling service is performed, it produces required occupancy and/or climate samples and saves the
generated data in the multi-model. In addition, the Link Model is updated with the new stochastic variants.
D10.400 Final Report
Version 2.0
Page 50/105
© eeEmbedded Consortium www.eeEmbedded.eu
Thus, not only architectural and engineering design variants can be examined but also parameter ranges,
reflecting the uncertainty of the design values at a certain project stage can be taken in consideration to enable
better informed design decisions and better understanding of the designed building’s performance.
7.7.2. Thermal Simulations with TRNSYS
Energy analysis is included in each part of the design process. Following the intended overall
approach, sophisticated analysis tools modelling the thermal as well as operational behaviour of the building
as well as main components of the energy systems need to be integrated into the workflow to support the
decision-making process. In eeEmbedded, the software system TRNSYS-TUD is used for this kind of analysis.
TRNSYS is the abbreviation for TRaNsient SYstem Simulation program which was initially developed by the
University of Wisconsin in Madison, USA before approximately 35 years. The software is on sale as
commercial software package targeting energy experts. It is continuously updated whereby parts of the
software code are distributed in source form but the main core parts are available only as binaries.
The project partner TUD-IET started the development of its own individual software modules for TRNSYS in 1994.
Since this time more and more new simulation modules were added or existing modules were re-shaped
respectively adapted to support the special tasks within research projects. Because of the high rate of newly
developed software modules and approaches which are unique compared to the software setup which is
available as commercial solution, the suffix TUD was added to the original trademark TRNSYS to indicate the
difference between the commercial tool and the research-orientated solution TRNSYS-TUD. The additional or
modified software modules developed by TUD-IET are not available for purchase or free distribution.
The simulation package in eeEmbedded is adapted and configured for modelling energy systems and related
buildings. It is based on a modularised concept which provides a high level of flexibility when analysing
various kinds of energy systems while involving peripheral conditions and related phenomena. Because of
the modularised approach of the software design experienced users have the possibility to add their own
software code to the core software parts to process simulations according to their individual tasks.
Overall role of TRNSYS-TUD
In the eeEmbedded context TRNSYS-TUD acts as a common placeholder for similar software systems
used for transient thermal building and energy system simulation. In a productive environment, a
comparable tool with similar functionality such as EnergyPlus could be used too.
Figure 47: Workflow within the energy analysis domain, embedding the simulation tool into the Analysis Framework
D10.400 Final Report
Version 2.0
Page 51/105
© eeEmbedded Consortium www.eeEmbedded.eu
In general, the integration of the sophisticated analysis task on the eeEmbedded platform can be divided
into three main sub-steps: (1) pre-processing, (2) analysis processing and (3) post-processing (see Figure 47
above). TRNSYS-TUD covers components which are designed for pre-processing purposes, e.g. to transfer the
building model provided by the architectural domain into a simulation model covering the building
geometry, energy system components (depending on the design stage) as well as user behaviour and climate
conditions. This complements the assignment of design variants in the MMNav providing for BIM2SIM model
transformation and some additional input features. On Figure 48 and Figure 49 the results of transferring the
architectural model into the geometrical part of the simulation model is presented based on the level of
detail used in the Early Design stage. In the Urban Design phase the whole analysis process covering pre-
processing, processing and post-processing is almost fully automated.
Figure 48: Pilot building STR Z3: Architectural model (IFC, left) and simulation model (TRNSYS-TUD, right)
Figure 49: Pilot building BAM W2: Architectural model (IFC, left) and simulation model (TRNSYS-TUD, right)
Interdependencies and constraints with regard to other domains
The quality of the geometrical model provided by the architectural domain plays an important role to
automatically run the analysis process as a service. The analysis software benefits from the output of the
architectural domain (Urban, Early and Detailed Design) as well as the HVAC and BACS domain (Early and
D10.400 Final Report
Version 2.0
Page 52/105
© eeEmbedded Consortium www.eeEmbedded.eu
Detailed design). Other inputs can be included as well like stochastic samples (see Section 7.7.1). If inputs are
missing, default templates or default values can be used based on client requirements or an internal
template library. However, with regard to the quality of the BIM models generated by authoring systems
there are many challenges that have yet to be overcome as outlined in the eeEmbedded validation report –
see Deliverable D9.4 (Sprenger & Poloczek, 2017).
7.7.3. 3D Wind Analysis in Urban Design
3DWind is an end-user application for the aerodynamic analysis of a building embedded in its urban
environment to obtain the best building cubature (shape and orientation) regarding wind comfort indices,
local wind potential for renewable energy use and natural ventilation design (as a result of the combination
of solar radiation and wind flow). 3DWind can be used as complementary tool to Energy Simulation
applications in the Urban Design phase.
In the context of eeEmbedded, CFD analysis utilizes IFC files for the description of the neighborhood
geometries (buildings and terrain), templates and Link Models that empower collaboration and coupling of
CFD with other simulation applications critical to Urban Design phase. Architects continuously receive
feedback from the CFD analysis and can easily make decisions about the building cubature which are critical
for all the consequent design phases.
Automations have been developed for the construction of suitable models for CFD simulations from IFC
building model of any LoD and any design phase. The translation of weather wind data to proper boundary
conditions for the atmospheric boundary layer has been developed and automated.
For the wind analysis around the building at hand, wind-rose data are used which describe the mean wind
velocities, the magnitude, the direction and the duration of the wind at a specific site within a typical year
(see Figure 50 below for the sites of the two pilot projects used in the validation phase).
W2 Pilot, Utrecht, NL. Prevailing directions SW, SSW. Prevailing wind speed 4.5m/s and significant time
intervals with 6-7m/s
Z3 Pilot, Stuttgart, DE. Prevailing directions WSW, SW. Prevailing wind speed 3.3m/s
Figure 50: Wind rose data for the two pilot demonstrators
The wind speed distribution described by wind rose refers to mean hourly wind speeds measured at 10m
above the ground. Radial distances indicate percentage of time (or exact number of hours) of wind events.
In the context of eeEmbedded, a CFD analysis is conducted at Urban Design and Detailed Design phases. At
UD phase, the CFD analysis provides wind comfort KPIs for KPA decision support process. The two predicted
D10.400 Final Report
Version 2.0
Page 53/105
© eeEmbedded Consortium www.eeEmbedded.eu
KPIs concern two representative wind velocities, the first one is the velocity at the building entrance and the
second one the velocity at city canyons around the building (Figure 51 below).
Figure 51: Wind speed at human height, resulting speeds at all points of interest organized in the form of wind rose and wind stream lines around the Z3 building (top) and around the W2 building (bottom).
According to site wind data, a number of significant directions and magnitudes of wind speeds are
considered in order to compose a simulation matrix for the CFD analysis, (see Figure 52 below).
Figure 52: Simulation matrix for prevailing wind for the Z3 building, (left) and the W2 building (right)
Simulation results are synthesized by applying frequencies (fij) of occurrence to each of the wind directions
and wind speed magnitudes, as weighting factors:
�̅�(𝑥, 𝑦, 𝑧) = ∑ ∑ 𝑉𝑖𝑗(𝑥, 𝑦, 𝑧) ∙ 𝑓𝑖𝑗
𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑡 𝑤𝑖𝑛𝑑 𝑚𝑎𝑔𝑛𝑖𝑡𝑢𝑑𝑒𝑠
𝑗=1
𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑤𝑖𝑛𝑑 𝑑𝑖𝑟𝑒𝑐𝑡𝑖𝑜𝑛𝑠
𝑖=1
-3.00
-2.50
-2.00
-1.50
-1.00
-0.50
0.00
0.50
1.00
1.50
2.00
2.50
3.00
-3.00 -2.50 -2.00 -1.50 -1.00 -0.50 0.00 0.50 1.00 1.50 2.00 2.50 3.00
Wind Velocities 3m/sec
POINT 1
POINT 2
POINT 3
POINT 4
POINT 5
POINT 6
POINT 7
POINT 8
Rotation around Z
Wind Direction
Wind Velocities - Occurence
>60% <30% <10%
0 N 3m/s
45 NW 3m/s
67.5 WNW 3m/s
90 W 3m/s 5m/s 7m/s
112.5 WSW 3m/s 5m/s 7m/s
135 SW 3m/s 5m/s 7m/s
180 S 3m/s
202.5 SSE 3m/s
225 SE 3m/s
247.5 ESE 3m/s
270 E 3m/s
292.5 ENE 3m/s 5m/s
315 NE 3m/s
Rotation around Z
Wind Direction
Wind Velocities - Occurence
>60% <30% <10%
0 N 4.5m/s
45 NW 4.5m/s 6.5m/s
67.5 WNW 4.5m/s 6.5m/s
90 W 4.5m/s 6.5m/s
112.5 WSW 4.5m/s 6.5m/s 9.5m/s
135 SW 4.5m/s 6.5m/s 9.5m/s
157.5 SSW 4.5m/s 6.5m/s 9.5m/s
180 S 4.5m/s 6.5m/s
202.5 SSE 4.5m/s
225 SE 4.5m/s
247.5 ESE 4.5m/s
270 E 4.5m/s
292.5 ENE 4.5m/s 6.5m/s
315 NE 4.5m/s
D10.400 Final Report
Version 2.0
Page 54/105
© eeEmbedded Consortium www.eeEmbedded.eu
CFD analysis workflow
Separate IFC models for each cubature alternative and variant are received for the CFD analysis. The CFD
analysis proceeds according to the following steps:
The global site coordinates are determined by the IfcSite entity of the IFC model and the wind rose data
are consequently obtained for each location
Geometry extraction from IFC file (SOF’s application)
Model simplifications for reasonable CFD analysis (SOF’s modeler)
Imposition of CFD boundary conditions and definition of the KPIs to be estimated. Construction of a
simulation matrix according to the prevailing wind directions and wind speeds (SOF’s modeler)
Assignment of CFD runs for execution in the HPC cloud or our private parallel cluster
Summing-up of the results for the estimation of suitable KPIs (2 KPIs per alternative per variant). The
KPIs are delivered via CSV files to KPA tool.
CFD detailed analysis results presentation through videos and 3D representations of suitable flow
quantities (stream lines, pressure isosurfaces etc.) attached to IFC model in MMNav.
7.7.4. 3D Therm Analysis in Detailed Design
CFD analysis for the prediction of microclimate conditions inside buildings provides the capability for
accurate estimation of thermal comfort conditions in buildings and the optimization of HVAC layouts
ensuring that:
interrelated and dynamic aspects of building performance (passive and active elements – energy
demand and supply reduction options) are adequately considered and reflected in the predictions of
energy performance, finally resulting in indoor comfort
the building design performs as close as possible to what is anticipated
not only energy consumption needs are addressed but also the risk of overheating, peak loads and
indoor air quality are assessed
improved decision making is provided so that designers can achieve the optimum and most cost-
effective combination for reduced energy consumption and improved indoor comfort.
3DThermalCFD is a CFD application enhanced with heat transfer equation and buoyancy terms in Navier-
Stokes equations. It is used coupled with Energy Simulations in order to provide detailed data in spaces of
particular interest.
Currently, the coupling of Energy Analysis with the CFD analysis algorithm is a subject of ongoing research
work and a significant amount of manual work is required in order to exchange data/results between the
two types of simulations. This manual work within eeEmbedded is significantly reduced and the coupling
becomes feasible.
The CFD model includes all the HVAC and BACS installation alternatives in order to evaluate the effectiveness
of HVAC systems under both energy performance and thermal comfort criteria. The special characteristics
and the installation of the chosen HVAC systems are taken into consideration and alternative scenarios can
be examined.
D10.400 Final Report
Version 2.0
Page 55/105
© eeEmbedded Consortium www.eeEmbedded.eu
In the Detailed Design phase the thermal comfort KPIs concern the percentage of the occupied space where
thermal comfort requirements are fulfilled.
Examples of suitable KPIs are the Predicted mean vote (PMV), the percentage of people dissatisfied (PPD)
due to discomfort, the percentage dissatisfied (PD) due to draft, and ventilation effectiveness (EN
7730:2005, EN 15251:2007).
CFD detailed results provide answers for:
What parts of the room exposes occupants to the most uncomfortable conditions?
What parts of the room are responsible for wasteful heat gains or losses?
What parts of the room exposes occupants to the highest levels of CO2 and other harmful gases?
Users can easily follow path lines and flow mixing resulting from mechanical or natural ventilation in
order to evaluate the effectiveness of natural or mechanical ventilation systems.
Apart from spatial and temporal 3D representation of KPIs, results interpretation is based on 3D stream lines
“coloured” with temperature (Figure 53 below), spatial distribution of air temperature and air speed and
turbulence intensity distribution in 3D space or at levels of occupants head and legs.
Stream lines coloured with temperature and pressure
Figure 53: CFD results representation for evaluation of KPIs efficiency purposes (Z3 pilot, Stuttgart)
D10.400 Final Report
Version 2.0
Page 56/105
© eeEmbedded Consortium www.eeEmbedded.eu
CFD analysis workflow
Separate IFC model for each alternative which concern the type and the installation of the HVAC systems,
are received for the CFD analysis. The CFD analysis proceeds according to the following steps:
Data import:
i. Space/room geometry (from IFC file)
ii. Operation point of HVAC systems and airflow conditions (flow rate, cross sectional area, point on the
psychrometric diagram) for the scenario of interest (i.t. the coldest of winter or hottest fay in summer)
iii. Thermal and cooling loads, such as occupant loads, infiltration loads, equipment and lighting loads from
templates
iv. Wall temperatures (from Energy Simulations)
v. Solar gains from glazing surfaces (W/m2 from Energy Simulations)
vi. BACS function
Model simplifications for reasonable CFD analysis (SOF’s modeler)
Imposition of CFD boundary conditions and definition of the KPIs to be estimated. Formulation of
suitable boundary conditions according to HVAC type and operating point (SOF’s modeler)
Assignment of CFD runs for execution in the HPC cloud or our private parallel cluster
Summing-up of the results for the estimation of suitable KPIs. Examples of suitable KPIs are: Predicted
mean vote (PMV), the percentage of people dissatisfied (PPD) due to discomfort, the percentage
dissatisfied (PD) due to draft, and ventilation effectiveness. The KPIs are delivered via CSV files to KPA tool.
CFD detailed analysis results presentation through videos and 3D representations of suitable flow
quantities (stream lines, pressure isosurfaces etc.) attached to IFC model in MMNav.
7.8. LCA and LCC Analysis
The LCC/LCA tool using iTWO® helps in implementations of activity/time-based considerations for a sequence
of alternatives in the project. The LCC/LCA workflow is processed within different modules in iTWO such as
Element Planning; Bill of Quantities (BoQ), Job Estimation, Activity Model, thereby transferring results to each
of these activities to generate the whole life cycle cost and assessment of different alternative within the
project. TWO’s LCC/LCA process is important to identify the key performance indicators (KPI) at each stage over
a period and providing practical guidance on the application of LCC for each use case.
The LCC/LCA model is a link between the CAD model and cost accounting model. The BIM Qualifier provides
users with functions that allow you to check the IFC4 data and correct it, if necessary, or to improve the
quality of the data. Element planning calculates the quantity estimation for different CAD models. The Bill of
Quantities (BoQ) a structured document, using a hierarchy for collecting and summarizing values at each
level in the structure. The Bill of Quantities (BOQ) contains all the works to be cost/ecological assessment in
project alternative. For a project, different BOQs can be defined, structure and referenced with respect to
Model detailing. The job estimation model is used to produce the cost of the BOQ item using the cost code
or commodities. Estimate details are parameterized so that detail resource quantities, productivities and
cost factor are calculated. The activity model links the estimate or BOQ to activity schedule. This allows
estimation using the time dependence variable by linking with the calendar catalogue. This transforms into
activity schedule, which is an important tool for life cycle analysis. The activity model is interlinked with the
resources, which is linked with the cost codes and commodities.
D10.400 Final Report
Version 2.0
Page 57/105
© eeEmbedded Consortium www.eeEmbedded.eu
Figure 54: BIM Qualifier for importing IFC4 files
Figure 55: Element Planning different IFC model
Figure 56: Job estimation for estimation of cost using resources (Cost code/ commodity)
D10.400 Final Report
Version 2.0
Page 58/105
© eeEmbedded Consortium www.eeEmbedded.eu
Figure 57: Activity model inside iTWO for time scheduling
Figure 58: LCC result for KPI Tool for decision making
7.9. Risk Assessment Service
The goal of the risk assessment service is to analyze the effects of uncertainty on a buildings performance.
The focus in eeEmbedded was especially set on energy-related risks. In this context, main contributing
uncertainties have been described in (Gnüchtel et al., 2015) and encompass categories of variables like
thermo-physical properties (e.g. climate and material properties), occupancy and occupant behavior as well
as energy system reliability. The assessment of the resulting energy risk has a large impact for the decision
making process, as the risk has direct influence on the exploitation and maintenance costs. In the pilot
projects and for the proof of concept, the focus has been on climate and occupancy uncertainty, but the
developed approach can also be applied to other types of uncertainty.
In the context of the eeBIM framework, a crucial challenge was the integration of uncertainty information
into the eeBIM Multimodel. The newly developed variation model described in (Pruvost et al., 2017) has
been established with this purpose in mind. In addition to enabling the description of numerous design
alternatives and variants, it also describes stochastic realizations thereof. Stochastic realizations are
generated by the dedicated Sampling Service (SaS) and thus can be applied for each design variant. They
describe several scenarios for the building life cycle that are dependent on aleatory uncertainties, e.g.
climate conditions and occupancy. Unlike design variants, which are configured manually by an end user in
the Multimodel Navigator (MMNav), the stochastic realizations and their respective data variations are
generated automatically by the Sampling Service and are afterwards stored into the Multimodel Container
(MMC). For the sake of the TRNSYS energy simulation, defined within the use case scenarios (Sukumar et al.,
2015) and applied by the pilot projects, each stochastic realization consists of a data sample, which is
D10.400 Final Report
Version 2.0
Page 59/105
© eeEmbedded Consortium www.eeEmbedded.eu
constituted by time series of climate and occupancy variables and thus reflects varying climatic and building
usage conditions over time. After the export of the Multimodel Container from the MMNav, the dedicated
sampling service is functioning as an on-demand service for the preparation of samples for the energy
simulation and can be started directly from the Scenario Manager (ScM). Once started the SaS imports the
MMC and produces data samples. Finally, those are then exported back into the MMC. The samples are
generated on the basis of the background stochastic models described in (Gnüchtel et al., 2015) and
implemented via specific algorithms. In the following we are giving a brief explanation about the modeling
approaches followed for the climate and occupancy variables.
For occupancy sampling, a first-order Markov chain technique has been applied. This technique has been
chosen for its flexibility as well as moderate computational cost. The sampling operates at zone level, where
zone is a flexible term that can reflect a room, a storey or the whole building. As input data functions one
transition matrix per zone type that consists of probabilities, which describe that at a certain point in time,
the number of occupants changes from one amount to another (see Figure 59). The generation of this matrix
is realized from the existing occupancy data of a comparable zone. The sampling itself generates a time
series for each zone, consisting of an occupants number for each time step. Figure 60 shows a graphical
representation of such an output of one day.
Figure 59: Transition matrix for occupancy sampling
Figure 60: Graphical representation of one output from occupancy sampling
For the eeE climate sampling method performed prior to the energy simulation, there were three challenges:
D10.400 Final Report
Version 2.0
Page 60/105
© eeEmbedded Consortium www.eeEmbedded.eu
The first was to generate realistic high-resolution climate samples, consisting of multiple parameters each
(outdoor temperature, wind speed, solar radiation, etc.) and for a time span of up to 30 years. This
disqualifies pure mathematical methods for time series prediction like ARIMA.
Secondly, to use these samples for uncertainty analysis, they need to reflect the natural uncertainty of future
weather events. This disqualifies the artificial averaged data sets typically used in energy simulation (e.g. TRY).
Thirdly, computing time has to be in line with a workflow approach centered on information gain and possible
reevaluation. This disqualifies complicated atmospheric models used by meteorologists for weather prediction.
In view of that, the following approach satisfies all three demands:
For locations of interest a database with the measured weather data of the last years is being created. It is
important that the data sets comply with the requirement for fine resolution of all required parameters,
which means that a time interval of 10 minutes is desired. Any missing data points are filled in with average
values. Additionally, a compromise between high number of data sets and their actuality has to be made.
When performing the targeted uncertainty analysis, each energy simulation run is supplemented with one of
these data sets, chosen randomly from all available sets for the location.
After the simulation of all samples in TRNSYS-TUD (Forns-Samso et al., 2015), the simulation engine provides a set
of KPI values as required by the variation model. In the example of Figure 61 below, the computed KPI was the
energy demand for heating (kWh/m2/year). The figure shows the uncertainty analysis view of the KPA tool in
which the distribution of KPI values for three different design variants are plotted. For each variant a set of around
fifty weather and occupancy samples were used. The figure shows substantial differences between the three
variants, which differ in their energy system technology (district heating, natural gas boiler and biomass boiler
respectively), window-to-wall ratio and other architectural properties. The second example shows less robustness
with regard to uncertainty and has consequently a higher standard deviation. Despite higher mean energy
consumption, the two other alternatives show less volatility in the yearly use of energy.
Figure 61: Visualization of simulation results from performed uncertainty analysis in terms of energy demand for heating by three different design variants (KPA tool)
D10.400 Final Report
Version 2.0
Page 61/105
© eeEmbedded Consortium www.eeEmbedded.eu
On the basis of such a KPI output data set, certain KRIs can be derived in post-processing on the basis of the
value distribution of each KPI, which results from uncertainty for the simulation input. The KRI derived from
the previous data set in the example above is the standard deviation of the heating energy demand.
Following the same approach and using other specific input data and simulation tools, additional KRIs can be
computed. Such KRI can be defined as statistical indicators, deduced from the value distribution of a KPI.
Examples are energy system reliability, energy system maintainability, energy system availability, investment
costs, revenue and so on.
7.10. Multi Key Point Analysis Tool for Decision Making
Decision making, broadly defined, is a combination of interconnected activities that include gathering,
interpreting and exchanging information; creating and identifying alternative courses of action; choosing
among alternatives by integrating the often differing perspectives and opinions of stakeholders; and
implementing a choice and monitoring its consequences. In eeEmbedded we acknowledge the multi-
disciplinary nature of a construction project: it employs several experts performing different types of
analyses, simulations and thus creating a large number of results to be explored and analysed. The most
general case of decision-making within a building design process can be expressed as an end decision that is
the product of a whole series of domain decisions (i.e. financial, environmental, functional and physical) and
the interaction of the interested parties.
In construction projects, group decision making is always preferable compared with individual decision
making for increased effectiveness. However, working in such inhomogeneous group/collaborative
environments is not common and requires the use of methods, methodologies and tools that facilitate a
holistic and collaborative design process. One of the main outcomes of the eeEmbedded project is the
developed Key Point Methodology and the supporting software tools, such as the Scenario Manager,
Multimodel Navigator and the Multi Key Point Analysis (KPA) tool. The combination of the methodologies
and tools will allow project teams to work in a more collaborative and structured way and thus allow them
to making better informed decisions during each the design phase. In the following we describe the
developed Multi Key Point Analysis Tool used to support the decision making process.
The Idea
Due to the complexity of construction projects and the large amount of information created during a design
process, the integration and visualization of data is critical for well-founded decision making. The intention is
to develop a tool that supports multidisciplinary work and enhances collaboration between projects teams.
Additionally, it should help the experts and decision makers in analyzing and evaluating the impacts of Key
Performance Indicators (KPIs) from different design domains. A weighing factor can be added to each KPI or
different KPIs, corresponding to the same evaluation criteria (e.g. environmental or financial), can be
grouped together and receive a shared weighting factor. This process will result in the calculation and
visualization of a Decision Value (DV). The process will give us a better understanding of the analyzed
variants and present a more holistic view of the evaluated criteria as well as the involved variables. The KPA
tool supports teams to work in a more structured way, while also enabling flexibility and interaction within
the analysis of variants and thus facilitating the decision making process. The tool is critical for rapid
comparison of different evaluation criteria.
D10.400 Final Report
Version 2.0
Page 62/105
© eeEmbedded Consortium www.eeEmbedded.eu
The Innovation
The KPA tool is developed as a web-based decision making application that uses a graphical multi-attribute
utility analysis to evaluate and compare alternatives based on Key Performance Indicators. Most of the
calculations and all of the visualizations are computed and rendered in the browser, while only some minor
touches are done on the server side. The tool contains three main modules: The first module is the
simulation synthesis, which performs sensitivity and uncertainty analysis. The sensitivity analysis calculates
and visualizes the standardized coefficients for each design parameter in relation to each KPI and is used to
prioritize decisions for the design parameters that have stronger influence on the KPIs. Uncertainty analysis
is used to visualize the fluctuation of the KPIs in the presence of uncertain parameters, such as weather data
or user profiles. The employed sensitivity analysis was developed in the previously funded EU project ISES. In
eeEmbedded we added the uncertainty analysis visualization as shown in Figure 61 in section 7.9.
The second module is the KPI analysis, which uses advanced plotting graphics for multi-dimensional data
visualization, such as hyper radial visualization, parallel coordinate plot and radar charts. All the plots are
developed and used for analysis purposes, thus allowing the user to investigate the relationship between the
various variables in depth. By using these plots the user has the option to thoroughly investigate a wide
range of alternatives and data used to create those alternatives. Figure 62 shows the KPIs and design
parameters in one plot, visualized as a parallel plot. Each polyline is the representation of one design variant.
The example case shows a large number of variants represented by the polylines. However, the capability of
the parallel coordinate plot in the tool allows for making a criteria selection based on different requirements
for each KPI, reducing the number of alternatives based on these requirements. The bolded polylines on
Figure 63 represent alternatives that could be analyzed in more detail as they fall within the project
requirements and represent the most optimal solutions.
Figure 62: Parallel coordinate plot showing all possible alternatives and relationships between KPIs and design parameters
D10.400 Final Report
Version 2.0
Page 63/105
© eeEmbedded Consortium www.eeEmbedded.eu
Figure 63: Filtered parallel coordinate plot representing a reduced number of alternatives based on criteria selection and highlighting the better one (thick curves)
The third module is the Decision Value (DV) analysis which graphically represents the preferences of the
decision makers related to the project goals. The Decision Value is calculated as a weighted sum of the
results of fitness functions over each KPI. This allows prioritizing KPIs by means of a weighting factor. The
user can set up their requirements and group the KPIs with a weighing factor within the Scenario Manager or
through the requirements setup in the KPA tool. The main purpose of the tool is to reduce the wide range of
variants to the ones that better represent the stakeholder preferences of the initial project setup. However,
this does not mean that the highest DV alternative has to be chosen, stakeholders can choose a reduced
number of alternatives that could be analyzed in further detail using an iterative process.
Figure 64: Decision value representation
D10.400 Final Report
Version 2.0
Page 64/105
© eeEmbedded Consortium www.eeEmbedded.eu
Benefits to end users
Integrating results from analysis and simulations from different software tools and having these results
represented with advanced graphics facilitates the decision making process. Consequently, it creates better
understanding of the influence of different design parameters towards the design variants and offers a
comprehensive way to manage them. Calculating and visualizing the Decision Values benefits end users for
having a holistic view of the project priorities.
D10.400 Final Report
Version 2.0
Page 65/105
© eeEmbedded Consortium www.eeEmbedded.eu
8. Evaluation of the eeEmbedded Platform
The platform is evaluated employing the validation and verification steps as has been detailed in the
Deliverable D9.4 (Sprenger & Poloczek, 2017). The qualitative and quantitative parameters have been
gathered during the assessment of the platform and the evaluation has is based on the developed
prototypes, the availability of data, the working methods, the business and social impacts, the future
perspectives as well as possible standardization steps.
There are two methods used for the platform evaluation. The first method is the Cost Benefit Analysis (CBA)
presented in Table 2 below. Its purpose is to investigate the integrity of the platform and the methodology
with regard to their balance of costs against the provided benefits. The benefits from the development and application of the platform are compared to the potential risks, which may occur during a project using the eeEmbedded platform. The CBA focuses mainly on the efficiency and quality of the process and the quality and costs of the resulting design. To measure these, the targeted and design results, i.e. TO-BE and AS-IS KPIs, KDPs and DV, of the pilot projects are used. The improvements towards the processing time is
measured by comparing the different phases of the design process and comparing them to the pilot projects’ results produced by the eeE platform. The second method is the Strength, Weaknesses, Opportunities, Threats (SWOT) analysis summarized in the Table 3. It investigates each component of the platform and is
thereby helping to define the strengths and weaknesses that it offers to the platforms’ users as well as the opportunities to enhance each product and to give it a competitive value. Finally, an insight regarding possible threats involving the usage and development of the components is provided.
Table 2: Cost Benefit Analysis based on the performed scenario validation
Note: steps marked with an asterisk and shown on green background are valid for all phases but were most thoroughly investigated in the Urban Design phase and are therefore shown within this part of the table
Process steps Difference to current practice Benefits Costs
Basis: Urban Design Validation
Project setup and management*
Process management optimization
Process time: No reduction in time regarding BEP
setup, but time saved for coordination in later
stages by elimination of ‘manual’ coordination.
Achieves increased process efficiency.
Process quality: Clear roles, responsibilities and
information exchanges are defined.
Building quality: Ensures building design quality at each milestone. The building fulfils the client
and regulation requirements more closely.
Building costs: Ensures costs remain within budget.
Development of templates
Training for correct handling
Create Design cubature
One standard IFC model and setup for all BIM users, that is maintained throughout the entire duration of the project
Process time: eeE workflow does not require
complicated model in early phases, since the
templates are assigned to wall elements. If many variants shall be analysed, separate models have
to be created for each variant. Out of one variant,
many alternatives can be generated.
Process quality: One common IFC file per alternative for the entire process and shared by all
tools ensures a smooth design process.
Building quality: IFC model is validated by using the ER checks. This provides excellent quality of an
architectural 3D model at an early design stage
ensuring the quality at the later design stages.
Building costs: The IFC model is used for LCC calculations within the cost estimation tool. Costs
of the building and the materials can be predicted
at an early stage of design.
Depending on the complexity
of variants, not all exchange
requirements can currently be
met. Models created in Revit
and exported to IFC4 tend to
fail some ER checks due to
export quality.
D10.400 Final Report
Version 2.0
Page 66/105
© eeEmbedded Consortium www.eeEmbedded.eu
Process steps Difference to current practice Benefits Costs
Create
Variants*
Visual and immediate creation
of building variants per element
type.
Process time: The standard variant creation needs
each element to be designed and therefore expert
knowledge is needed for creating the complete
model in Revit. In eeE, predefined energy
templates are ready for assignment for a simple model and automatic template assignment is
possible.
Process quality: Clear visualization of elements with variant data.
Building quality: Quick evaluation of building
energy behaviours subjected to different energy settings.
Building costs: Best quality vs. cost building options can be evaluated by creating many
variants.
A standard naming convention
is needed
Differences of the variants need to be tracked manually
Libraries need constant refinement to be up-to-date
(for materials, countries, costs, etc.)
Quality check –
Exchange
requirements*
Automated model-based
checking of the information
requirements and visual feedback of deviations.
Process time: Compact verification of the model
and all variants saves time. Communication is
more efficient, due to automatically receiving
made-to-measure information in each task,
instead of defining and requesting the needed information.
Process quality: Each variant is checked against exchange requirements. ER checks make the
process smoother since many errors are detected
at an early stage.
Building quality: Ensures wholeness of the building’s BIM model for the purpose of the
simulations. Increases the quality and reliability of
simulations, which in turn assess building quality.
Building costs: Supports by providing a complete
model for cost analysis.
As long as IFC standards are
developing and the software
tools used are changing their
requirements, ER Checks need
to be updated.
A programmer is needed to formulate the ER checks (e.g.
SPARQL)
Quality check –
KDP check*
Automated model-based
requirements check. Visualises the deviations from KDP.
Process time: Quick setup and management of
KDPs within one table. Variant management is
easier and faster: those that do not fulfil the
requirements are discarded and the time that would be used to simulate them is saved.
Process quality: Structured database and documentation with all KDPs, which can be
checked anytime during the design process.
Visualization of KDPs in the MMNav.
Building quality: Advanced and early management of the requirements towards the building. KDP
check guarantees that requirements are fulfilled or
that deviations are being flagged.
Building costs: Limitations can be introduced for
KDPs that will later influence the LCC costs simulation.
Requires lots of initial input
before the design process
starts. However, tables can be
reused.
Changes in the requirements need changes in the setup.
Extension for additional checks needs expert knowledge.
CFD Wind simulation
Continuous feedback from the CFD analysis to the architect
and therefore easy decision-
making about the cubature,
which are critical for all the consequent design phases.
Process time: The pre-processing time for the
preparation of models for the CFD analysis is
drastically reduced and becomes feasible even for
non-CFD-experts. CFD analysis becomes accessible to architects from a very early design phase on.
Computing time is also reduced by performing
simulation runs in the cloud.
Process quality: The accuracy of the results is improved due to the consideration of construction
details and the building’s surrounding environment.
The capability for automatic formulation of the CFD
model via the incorporation of templates in the
Detailed Design phase and the coupling with Energy Analysis significantly improves the quality and the
efficiency of the simulation.
Extension and automation of
the coupling of CFD analysis
with Energy simulation is
needed for a more accurate analysis and to render the
coupled analysis feasible for the
whole building.
D10.400 Final Report
Version 2.0
Page 67/105
© eeEmbedded Consortium www.eeEmbedded.eu
Process steps Difference to current practice Benefits Costs
Building quality: Supports the decision for the best
architectural alternative: CFD analysis in the
Detailed Design phase incorporates the energy analysis detailed thermal comfort criteria. The
selected KPIs will act as metrics to measure a
building’s absolute energy use performance, in
order to benchmark against similar buildings or with best-practices and assess energy efficiency
measures within buildings.
Building costs: Improved decision making is
provided and designers can achieve the optimum
and most cost-effective combination for reduced energy consumption as well as improved indoor
and outdoor comfort.
Stochastic Sampling*
Currently the process is done as a stand-alone. In the eeE
workflow the stochastic
sampling is based on and transferred together with the
simulation results. It enables
the use of stochastic based
variable ranges to enhance design variant options.
Process time: One-click analysis.
Process quality: Stochastic sampling covers (1)
occupancy profiles related to the space types as well as (2) weather data related to the location of
the building. Because of the integration of the
sampling service in the Scenario Manager
accessing the sampling service is easy to handle. The results of the sampling services will be
automatically integrated in the job description
handed over via Multimodel Container. The
preparation of the energy analysis will include the generated samplings.
Building quality: Thanks to the risk analysis, the influence of comfort and quality parameters can
be evaluated.
Building costs: Risk analysis supports more reliable calculation of costs, thus better decision values can
be achieved.
The more samples are analysed,
the longer the simulation takes.
Energy simulation*
Currently the standard approach is to develop a
completely new 3D energy
model. In the eeE workflow, energy simulation is based on
the existing IFC model provided
by an architect.
Process time: Depends on the complexity of the model and time intervals used within the simulation. The time is significantly shortened due to the cloud environment. Simulation results are automatically incorporated. The results are summarized in KPIs making decision making easier and faster. The utilization of an existing IFC model makes the process faster comparing to create an entirely new 3D energy model.
Process quality: No expert knowledge is required to
develop the energy analysis model, since it is based on the IFC model and MMC content. In current practice the exchange between the architectural and simulation software are often not working very well, here the IFC model is transferred almost without a problem.
Building quality: Energy analysis is included at a very early design stage and applied for different variants. Many factors, e.g. wall construction materials, window-wall ratio, CFD simulation, are taken into account to provide the most reliable energy results for the building.
Building costs: Energy analysis enhances LCC cal-culations in predicting the best cost-efficient variant.
The Energy Simulation has
specific demands toward ER and therefore towards
modelling (e.g. 2nd level space
boundaries are required).
Life Cycle Cost
Analysis*
All chosen construction types,
energy system types and
simulation results for an alternative-variant combination
are merged into one IFC, which
allows automation and inte-
gration of LCC in a very early design stage.
Process time: LCC simulation results and domain
decisions are much quicker due to storing the
results in KPIs. The automation saves time in
alternative-variant processing and comparison.
Process quality: Variants can be filtered.
Building quality: Supports identifying the alternative-variant combination meeting the
sustainable criteria and the budget.
Initial iTWO template setup
requires lots of manual work
inside the software.
D10.400 Final Report
Version 2.0
Page 68/105
© eeEmbedded Consortium www.eeEmbedded.eu
Process steps Difference to current practice Benefits Costs
Building costs: Supports identifying the alternative-
variant combination with the optimized LCC.
Decision making*
Weighted decisions from all the analyses and simulations based
on compiled Decision Values,
which have been defined by the decision maker at project start
within the KP setup.
Process time: Much faster and compact overview
of all the variants and their quality. Faster cross-domain analysis and cross-domain decisions.
Increased cost-effectiveness of evaluation of the
alternatives and variants.
Process quality: All results are clearly visualized.
Building quality: Provides a clear indication of a building with best quality with regard to the
integrated and prioritized design quality goals
coming from all domains.
Building costs: Supports to identify a building with best quality and cost combination.
Weighting needs to be checked
to ensure the right priorities are correctly represented
throughout the decision making
process.
Basis: Early Design Validation
HVAC Design Feasibility study of more va-riants can be made than in the
current practise possible.
Process time: More variants can be analysed in the
same time.
Process quality: Design issues are easily com-municated with the other design members via BCF.
Building quality: Energy and comfort optimisation by interactive consideration of building and
systems variants.
Building costs: Balanced life cycle costs
Setup of generic HVAC
templates
BACS Design BACS engineer is involved
earlier in the design process. Process time: Knowledge-based design support
fastens the early concepts.
Process quality: Knowledge-based support for the
BACS designer to comply with EN15232.
Building quality: Optimised energy efficiency and comfort based on early analysis of control
strategies.
Building costs: Balanced LCC for the clients’ needs
based on integrated costs.
Setup a database with control
strategies, components and
costs or invest in the eeBACS
Wizard once the product is ready for the market.
FM Strategy FM is involved earlier in the design process.
Process time: Knowledge-based support allows for
earlier analysis of maintenance strategies.
Process quality: Integrated analysis of
maintenance strategy and LCC.
Building quality: Optimised quality over the whole
life cycle.
Building costs: Optimised costs based on
clients/users’ needs over the whole life cycle
Setup a generic database of
maintenance cycles, service lives and maintenance
strategies.
Basis: Detailed Design Validation
Comfort simulation
In Detailed Design, currently the coupling of Energy Analysis with
the CFD analysis algorithm is
subject of ongoing research and a
significant amount of manual work is required to exchange
results between the two types of
simulations. This manual work is
significantly reduced within eeEmbedded and the coupling
becomes feasible.
Process time: The pre-processing time for the
preparation of models for the CFD analysis is
drastically reduced and becomes feasible even for non-CFD experts. CFD analysis becomes accessible
to architects in a very early design phase.
Computing time is reduced by assigning simulation
runs in the cloud. The capability for automatic formulation of the CFD model and the coupling
with Energy Analysis significantly improves the
quality and the efficiency of the simulation
Building quality: CFD analysis in the Detailed
Design phase incorporates the energy analysis detailed thermal comfort criteria. Not only energy
consumption needs are addressed but also the risk
of overheating, peak loads and indoor air quality is
assessed (Detailed Design).
Building costs: Improved decision making is
provided: designers can achieve the optimum and most cost-effective combination for reduced
energy consumption and improved indoor and
outdoor comfort.
Extension and automation of
the coupling of CFD analysis
with Energy simulation needs a more accurate analysis to
render the coupled analysis
feasible for the whole building
(Detailed Design).
D10.400 Final Report
Version 2.0
Page 69/105
© eeEmbedded Consortium www.eeEmbedded.eu
Table 3: SWOT Analysis
SWOT / VDL components
Strengths Weaknesses Opportunities Threats
Basis: Urban and Early Design Validation
Scenario
Manager
Well-structured set up of a BIM
Execution Plan. BIM process
coordination and information
management. Accessible for
users at any time. The updating
of the information occurs
automatically since all the tools
are connected with ScM. The
workflow is tracked across the
design steps & analyses. Access
to all project/task messages.
Lack of data exchange flexibi-
lity with the tools as it de-
pends on the Project Setup.
Once the process workflow is
setup and the process is
started, there is no possibility
to amend the process.
Design a process with tasks that
can be done in parallel can be
developed. Process templating
can be developed for the ability
to reuse processes or sub-
processes.
Security issues of the
software. Maintenance,
administration and secu-
rity care is required.
MMNav Graphical user interface for
clear analysis of KDP. Quick
generation of variants based
on a single 3D model through
easy access to predefined
templates. It is possible to
include and link external data
to the model. Offers Web-
based presentation of a 3D
model and automatic assign-
ment of element types based
on Omni Classes defined
within the Project Setup.
It is not possible for end users
to integrate new templates
within MMNav. Not possible to
instantly change properties
within a template in MMNav.
Reviewing the model in MMNav
is flexible and clients have the
possibility to access the model
at any time. It is possible to
extend the template access to a
template management system
for end users, which is
integrated in the Project Setup.
This should allow for the
creation and updating of
templates.
Large size projects require
a reliable and fast internet
connection as well as fast
server.
KDP and
ER Checking
Automatic checks for KDPs and
exchange requirements, saves
time and manual work. This
automatic check detects more
errors than a manual analysis of
the model.
Without detailed IFC know-
ledge, it is not possible to
specify the checks from scratch.
User-friendliness needs to be
improved
Setup can be improved to be
more user-friendly. The checks
for the geometry could be
expanded and further deve-
loped. An appropriate graphical
user interface could be a
solution to avoid using expert
knowledge and setup KDPs and
ERs can be reused.
Defining the wrong rules
could lead to
misinterpretation of the
results.
TRNSYS Automated pre-processing
covers the transfer of the IFC
model to the simulation model,
by enhancing the model with
additional information, inclu-
ding assigned templates.
IFC model does currently not
include construction templates
chosen. They are loaded sepa-
rately as a .csv file as an input
of the analysis.
Enhancing the capabilities of
the IFC model interpretation
and thus, for example, omit the
additional .csv file.
IFC standards are influ-
encing the interpretation
of the IFC model need to
be adjusted to updates.
3DWind Completely integrated into
the workflow and uses the
shared BIM model. Produces
simulation data as KPIs and
returns those back to the
process workflow. Usage of
the KPI allows for easier
interpretation of the analysis
results and the classification
of the building.
Automatic import of IFC
model saves manual work for
the preparation of the CFD
model.
Simulation takes a significant
amount of time, which slows
the entire design process.
Tool can only be used by a CFD
expert. There is a lack of
visualisation of the results
within MMNav as results can
be only attached in it.
Enhanced automation of the
CFD model generation from the
IFC model in the CFD geome-
trical modelling environment.
This includes geometry
modifications in order to fulfil
the requirements for a feasible
CFD analysis.
Improving the speed and
robustness of CFD simulations
is an ongoing research field.
Not suitable for cases of
rapid urban development,
where the topography
changes drastically around
the building of interest.
D10.400 Final Report
Version 2.0
Page 70/105
© eeEmbedded Consortium www.eeEmbedded.eu
SWOT / VDL components
Strengths Weaknesses Opportunities Threats
iTWO -
LCC/LCA
Automated life cycle cost and
life cycle analysis for each
variant.
With minor exceptions, the
data within iTWO cannot be
reused with other BIM
software programs. The initial setup of iTWO
templates is a complicated
manual process.
Until now, iTWO does not provide any user interface for
LCC and LCA calculation.
The generated data could be
provided using an open schema
and be treated independently of
the program’s functionalities, to enable back-end data com-
munication. Providing a user-
interface for the LCC and LCA
calculation would highly simplify the procedure for the end users.
The MMC approach should be
integrated into the iTWO process
to increase the automation of recognition of templates, vari-
ants, contents, materials etc.
Shared data management
is considered to be the
ongoing trend in develop-
ments, which the tool is lacking.
No implementation of
LCC/LCA user interface is
foreseen in the immediate future.
Multi-KP
tool
Easy and transparent decision
making and visual analysis of
alternatives and variants. User-friendly: supports cross-
domain analysis, decision
making and multi-criteria
analysis.
Since it is a web-based tool,
there is no direct connection
to the data or the results: It needs a connection to the
internet to function.
The visualisation depends on
the accuracy of the data provided and the format
specified.
The tool is not BIM com-
patible: Data is agnostic, which could also be a benefit.
For someone who is not aware
of KDPs, KPIs are a better guide
for result interpretation and could be added. Plotting and
analysis types can be expanded.
Algorithms to automatically
optimize the selection of alternatives and narrow the
number of alternatives can be
implemented.
The software has security
issues.
Basis: Early Design Validation
eeBACS
Wizard
Control strategies based on an
Early Design model.
Incorporates the IFC/HVAC
IfcDistributionSystem, specific
enumeration and relation of
HVAC components to spaces.
Proposes BACS equipment
(sensors, actors) and their costs.
There is no 3D representation
within the tool and it is limited
to EN15252 energy efficiency
classes in the current proto-
type.
Enhancing and expanding the
database and involve the BACS
designer early in the process
Depends on a correct
HVAC model.
Basis: Detailed Design Validation
3DTherm Completely integrated into the
workflow and uses the shared
BIM model. Produces simu-lation data as KPIs and returns
these back to the design work-
flow. Automatic import of the
enhanced IFC model with leads to the saving of manual work.
The most important strength of
the CFD analysis lies in the
automatic coupling with energy
analysis application, which provides a great technological
and scientific advantage for the
detailed energy analysis of
buildings.
Simulation takes a significant
amount of time that slows the
entire design process down.
In order to formulate a fea-
sible geometrical model and
boundary conditions, manual
work is needed for the proper simplification of HVAC, BACS,
furniture and other devices
that are considered for energy
balance of each space.
Increase automations for both
the preparation of suitable
models for CFD analysis and the knowledge-based interpretation
of analysis results to make it more
accessible for non-expert end
users (architects, HVAC designers)
The AEC market has continuously
increasing needs for a combined
CFD and Energy Analysis.
New energy saving
technologies and zero
energy buildings require continuous adaptation of
the techniques for the
generation of suitable CFD
models.
The results show that the workflow and most tools are very useful and beneficial for the process quality and
help to shorten the time needed to perform such a process. Furthermore, most of them have an
advantageous influence on the building costs and quality. The prototypical state of the tools means that
many tools have the need to improve their user interface for easier access and that some may be only be
operated by experts or after extensive training.
D10.400 Final Report
Version 2.0
Page 71/105
© eeEmbedded Consortium www.eeEmbedded.eu
9. Exploitation of the eeEmbedded Platform
The main goal of the eeEmbedded project was the development of a stochastic and model-based Virtual
Energy Lab Platform and virtual design office for integrated engineering design and the development of new
products and components facilitating energy-efficient planning. The developed ICT system is a modular
platform, from which each eeEmbedded partner did develop and configured specific modules or
combinations of modules, as required for their individual exploitation needs. The platform will therefore be
the main exploitable prototype and each eeEmbedded partner and any other interested party can exploit the
platform in their own configuration as well as with third-party software exploiting the eeEmbedded data
models and interfaces, as long as the third-party software complies to the established BIM-related
information management standards (IFC, BCF) and some specific energy-related modelling requirements.
The integrated eeEmbedded platform will be exploited:
as a technical Virtual Energy Lab to study new products (building components, technical components)
and services before their realization and to perform an in-depth analysis of poor performance under
lifecycle conditions in order to undertake the right tuning decisions,
as a holistic virtual engineering design office for the design and redesign of facilities and buildings to
study alternatives in depth and under various life-cycle conditions, in order to come up with the best
balanced design decision for the facility owner,
as a system analysis tool to analyze the energy and emission behavior of existing facilities and buildings,
in order to find out their weak components or instances of degraded operation and to make suggestions
to the owner for the redesign, retrofitting or reengineering of the operational processes.
The individual components will be used as standalone tools or in a bundle with other tools providing BIM-
based interoperability infrastructure. They will be exploited and marketed separately by each eeEmbedded
partner as they deem suitable for their individual exploitation needs.
Achieved Commercially Exploitable Results
Open BIM Platform Services
Scenario Manager and Multimodel Navigator
User Interface and Workflow Management of the eeEmbedded Virtual Lab Platform enabling to assign tasks, actions and data, deadlines and dependencies; Navigation and control of all project variants and displaying the results from all analysis tools, thereby supporting an informed decision making; Free of charge basic functionalities of MMNav including a SDK for 3rd parties and an open API.
Ontology (OVS), ER Check, KDP Check
Fast validation of Key Point values and rules of standard design codes of an eeBIM Model according to pre-defined rule sets.
Templates
Construction types, Materials with physical properties, future integration of Libraries, definition of alternative sub-processes to the pre-defined scenarios via Business Process Modelling Notations (BPMN) that may contain a lot of conflicts
D10.400 Final Report
Version 2.0
Page 72/105
© eeEmbedded Consortium www.eeEmbedded.eu
Commercial End User Applications or Plug-In Modules
3D Wind CFD Analysis Tool
Aerodynamic analysis of buildings to optimize shape and position of a building according to criteria such as energy consumption, wind comfort, wind potential, natural ventilation design
3DThermal CFD Analysis Tool
Detailed energy analysis in buildings for the prediction of indoor climate conditions toward the fulfilment of user-defined thermal comfort require-ments
iTWO LCC/LCA Life cycle cost and analysis estimation for all investment and running costs regarding even environmental impacts, like energy and CO2 consumption
Multi KPA Tool Comparing different design alternatives to find the best solution; Display of user-definable performance values (Key Points); Various visualizations within the tool or via the Multimodel Navigator
TRNSYS Energy simulation for calculation of the thermal behavior of buildings taking into account energy systems and HVAC components
eeBACS Wizard Determining correct BACS variant(s) according to already calculated Key Design Parameters
EDM Model Server BIM server which can merge IFC Files from different disciplines with application in energy analyses, HVAC design and lifecycle cost calculations
Extensions to existing Commercial Applications
Allplan (NEM) General Architectural Design CAD Software, capable to manage multiple configurations using parametric modelling
DDS-CAD MEP (DDS) HVAC Design capable to generate multiple configurations using parametric modelling and to produce domain BIM models according to various LOD/LoD agreements
Case Builder BACS (SAR)
Software for handling building automation projects; contains energy-efficient strategies and methods
Granlund Designer (GRA)
Designing the MEP equipment in a construction project taking into consideration FM requirements
D10.400 Final Report
Version 2.0
Page 73/105
© eeEmbedded Consortium www.eeEmbedded.eu
10. Conclusions
This report described the essential results of the eeEmbedded project which have been thoroughly validated
and evaluated by end users from the design (architecture, HVAC, energy), construction and FM domains. The
results showed that the goals of the project set up at the outset have been successfully achieved. A new
design methodology building upon the use of a comprehensive hierarchy of Key Points (DVs, KDPs, KPIs,
KRIs), advanced ICT technologies and standardised data models has been developed and a consistent
adaptable and extensible Virtual Design Office platform has been implemented. Much of the realized
software tools and services are thereby well prepared for short-term practical exploitation in AEC industry
context. Through the use of both storage and compute cloud facilities scalability problems have been
successfully solved. By applying templates, filtering and advanced multimodel techniques a possibility of
investigating a large number of design variants has been found, which can be used not only by large
companies but also by SMEs which are typical for the design landscape in the AEC domain.
However, while the results are overall positive, there is still research and development work needed to
achieve even better design solutions with regard to optimal energy use (especially with regard to renewable
energy), sustainability and cost effectiveness. Various modelling issues need yet to be solved as the related
data standards and the respective market and academic tools have not yet reached full maturity. For
example, the transformation of BIM data to the computational input models needed by analysis and
simulation tools is still a challenging problem for many complex practical cases. Interoperability of tools and
services also remains an issue, especially when detailed data is addressed, as for example by sophisticated
simulations or in detailed design. Last but not least, issues related to the BIMification of the existing building
stock need to be addressed to be able to apply the eeEmbedded methodology efficiently in retrofitting and
refurbishment projects.
Concluding, it has to be noted that this report only provides an overview of the major project findings.
Detailed results are documented in a rich set of public deliverable reports which will be available via the
project’s web site (http://www.eeembedded.eu). More importantly, commercial exploitable results are
expected to emerge soon as outlined shortly in the preceding chapter.
D10.400 Final Report
Version 2.0
Page 74/105
© eeEmbedded Consortium www.eeEmbedded.eu
Appendix
References
Aish R. & Woodbury R. (2005): Multi-level Interaction in Parametric Design. Lecture Notes in Computer
Science, Springer Berlin / Heidelberg. Volume 3638/2005: 151-162
Alwaera H., Clements-Croomeb D.J. (2010): Key performance indicators (KPIs) and priority setting in using
the multi-attribute approach for assessing sustainable intelligent buildings, Building and Environment
4(45), Pages 799–807, DOI:10.1016/j.buildenv.2009.08.019.
Autodesk Inc. (2017): Autodesk Revit® 2017.2, San Rafael, USA.
Baumgärtel K., Katranuschkov P. & Scherer R.J. (2017): An intelligent platform for thermal energy analyses,
to appear in: Automation in Construction (2018), Elsevier
Borrmann A., König M., Koch C. & Beetz J. (2015): Building Information Modeling: Technologische Grund-
lagen und industrielle Praxis (Building Information Modelling: Technological Basis and Industrial Prac-
tice), Springer Vieweg, DOI 10.1007/978-3-658-05606-3, ISBN 978-3-658-05606-3 (eBook)
Brohus H., Frier C., Heiselberg P. & Haghighat F. (2012): Quantification of uncertainty in predicting building
energy consumption: A stochastic approach. Energy and Buildings, Elsevier
buildingSMART: BCF [Online], http://www.buildingsmart-tech.org/specifications/bcf-releases
buildingSMART/ifcXML [Online], http://www.buildingsmart-tech.org/specifications/ifcxml-releases
buildingSMART International Ltd. (2017): Industry Foundation Classes Release 4 (IFC4) [Online]
http://www.buildingsmart-tech.org/ifc/IFC4/final/html/
buildingSMART/MMC [Online]: Multimodel Container to exchange combined models
https://github.com/BuildingSMART/MMC.
Calleja-Rodriguez G., Guruz R. & Loeffler M.-C. (2017): Automated Alternatives Analysis Procedure using Key
Points Method for multidisciplinary energy efficient building design projects, to appear in: Automation
in Construction (2018), Elsevier
DDS-Viewer Version 10 Win32 build 8/5-2014 [Online], www.dds-cad-com, 2014.
Demharter, J., Fuchs S., Schapke, S.-E. and Scherer, R. J. (2014): Multimodell und Multimodellcontainer, IN
Informationssysteme im Bauwesen – Modelle, Methoden und Prozesse (information Systems in
Building Construction – Models, Methods and Processes), Springer Vieweg, DOI 10.1007/978-3-642-
40883-0_2, 39 – 64 p.
DIN EN 15232 - Energy performance of buildings – Impact of Building Automation, Controls and Building
Management. German version FprEN 15232:2011.
DIN EN ISO 16484 - Building automation and control systems (BACS) -- Part 3: Functions.
eu.bac – Certifying Energy Efficiency of Building Automation and Control Systems, a first delivery and during
the lifetime – Part 4: Specification of Key Performance Indicators.
German BMBF project MEFISTO [Online], http://www.mefisto-bau.de
Grierson D. E. (2008): Pareto multi-criteria decision making, Advanced Engineering Informatics 22(3), pp.
371- 384.
D10.400 Final Report
Version 2.0
Page 75/105
© eeEmbedded Consortium www.eeEmbedded.eu
Grille T, Pruvost H. & Scherer R.J. (2016): Stochastic Analysis for Design Space Exploration and Building
Performance Optimisation, Proc. CESBP Central European Symposium on Building Physics and BauSIM
2016, pp. 369-375, http://www.cesbp2016.de/cesbp
Gudnasson G., Balaras C., Dascalaki E., Katranuschkov P., Laine T., Grunewald J., Protopsaltis B., Mansperger
T., (2012): ISES Deliverable D4.1: Technical specification of the overall framework and the principal
energy profile and consumption patterns, © ISES Consortium, Brussels.
Guruz R. & Scherer R.J. (2014): Sustainable energy entrepreneurship through architectural design: a key
point controlled method, Entrepreneurship and sustainability issues, Vol. 2, pp. 60-73,
Entrepreneurship and sustainability center, Lithuania, http://jssidoi.org/jesi/aims-and-scope-of-
research/
Häfele, K.-H., Brenner, J., FZKViewer V 4.7 (Build 905, 2017-02-10), Karlsruhe, Germany.
Hollingsworth D. (1994): The Workflow Reference Model, © Workflow Management Coalition.
ifcDoc Tool [Online], http://www.buildingsmart-tech.org/specifications/specification-tools/ifcdoc-tool
ISO 16739 (2013): Industry Foundation Classes (IFC) for data sharing in the construction and facility
management industries, International Organization for Standardization, Geneva.
ISO 29481-1 (2016): Building information models -- Information delivery manual -- Part 1: Methodology and
format, International Organization for Standardization, Geneva.
ISO 29481-2 (2012): Building information models -- Information delivery manual -- Part 2: Interaction
framework, International Organization for Standardization, Geneva.
ISO/IEC 19510 (2013): Information technology -- Object Management Group Business Process Model and
Notation, International Organization for Standardization, Geneva.
Jaunzens D., Warriner D., Garner U. & Waterman A. (2001): Applying facilities expertise in building design,
Construction Research Communications Ltd. by permission of Building Research Establishment Ltd.,
London, UK
Jensen, P. A. (2009) Design Integration of Facilities Management: A Challenge of Knowledge Transfer.
Architectural, Engineering and Design Management, 5, pp. 124-135.
Laine T., Forns-Samso F. & Kukkonen V. (2016): Visual support for multi-criteria decision making, Proc.
ECPPM 2016, pp. 371-376, CRC Press, UK
McArthur J., Herrera N. & Mantha P. (2014): International Sustainability Systems Comparison - Key Inter-
national Sustainability Systems: Energy and Water Conservation Requirements, CoreNet Global by Ove
Arup & Partners Ltd., March 2014.
OmniClass (2017): OmniClass, a strategy for classifying the built environment, http://www.omniclass.org/
Pruvost H., Grille T. & Scherer R.J. (2016): An IT-based holistic methodology for analysing and managing
building lifecycle risk, Proc. ECPPM 2016, pp. 377-386, CRC Press, UK
Pruvost H., Katranuschkov P. & Scherer R.J. (2017): Multimodel-based exploration of the building design
space and its uncertainty, Proc. Sustainable Places 2017, Middlesborough, UK
Scherer R.J., Katranuschkov P. & Baumgärtel K. (2016): Open eeBIM Platform for Energy-Efficient Building
Design, Proc. ECPPM 2016, pp. 387-395, CRC Press, UK
Scherer R.J., Katranuschkov P. & Guruz (2015): Energy-Efficient BIM Lab, Proc. Lake Constance 5D
Conference, pp. 391-405, Hochschule Konstanz, Germany
D10.400 Final Report
Version 2.0
Page 76/105
© eeEmbedded Consortium www.eeEmbedded.eu
Scherer, R. J. & Schapke, S.-E. A distributed multi-model-based management information system for
simulation and decision making on construction projects. In: Advanced Engineering Informatics, 25
(2011), pp. 582-599. Elsevier, The Netherlands, 2011.
Shao Y., Geyer P., Lang W. (2014): Integrating requirement analysis and multi-objective optimization for
office building energy retrofit strategies, http://dx.doi.org/10.1016/j.enbuild.2014.07.030, Elsevier.
Solibri Model Viewer version 9.6.21 [Online], https://www.solibri.com/products/solibri-model-viewer/
Todinov M. T. (2006): Risk-based reliability analysis and generic principles for risk reduction, Elsevier Science.
Related eeEmbedded Deliverables
Calleja-Rodríguez G. (2017): eeEmbedded Deliverable D2.5: New ways of holistic working for energy
optimized and embedded building, 100 p., © eeEmbedded Consortium, Brussels.
Dangl G., Linhard K. & Katranuschkov, P. (2016): eeEmbedded D8.2: Collaborative Methods, 62 p., ©
eeEmbedded Consortium, Brussels.
Forns-Samso, F., Sukumar, A., Kroner, M., Geissler, M.-C., Calleja-Rodríguez, G., Kaiser, J., Pruvost, H., Grille,
T. & Schär, R. (2015): eeEmbedded D3.2: Sustainability prognosis, quality and ROI methods, 100 p.,
eeEmbedded Consortium, Brussels.
Geißler M.-C., Guruz R. & van Woudenberg W. (2014): eeEmbedded D1.2: Use case scenarios and
requirements specification, 78 p., © eeEmbedded Consortium, Brussels.
Gnüchtel S., Kaiser J., Pruvost H., Stenzel P. Grille, T. & Schär R. (2015): eeEmbedded D3.1: Stochastic, risk
and vulnerability models and control strategies, 127 p., © eeEmbedded Consortium, Brussels.
Guruz R., Calleja-Rodriguez G. & Geißler M.-C. (2015a): eeEmbedded D2.1 Holistic multi-disciplinary Key
Point-based design framework, 85 p., © eeEmbedded Consortium, Brussels.
Guruz R., Calleja-Rodríguez G. & Geißler M.-C. (2015b): eeEmbedded D2.1 Holistic KPI-based design metho-
dology, 87 p., © eeEmbedded Consortium, Brussels.
Kaiser J. & Stenzel P. (2015): eeEmbedded D4.2: Energy System Information Model - ESIM, © eeEmbedded
Consortium, Brussels.
Pruvost, H., Grille, T., Baumgärtel, K., Schülbe, R. & Kadolsky, M. (2017): eeEmbedded D6.5: Optimization of
multi-model criteria, © eeEmbedded Consortium, Brussels.
Sprenger W. & Poloczek S. (2017a): eeEmbedded D9.2: Validation Test Sites Model, 34 p., © eeEmbedded
Consortium, Brussels.
Sprenger W. & Poloczek S. (2017b): eeEmbedded D9.4: Validation and verification of the KPI design
methodology, 60 p., © eeEmbedded Consortium, Brussels.
Sukumar A., Tøn A., Linhard K., Mrazek E., Mosch M. & Katranuschkov P. (2015): eeEmbedded D8.1: SOA
Platform Architecture, © eeEmbedded Consortium, Brussels.
Zellner R. & Kaiser J. (2015): eeEmbedded D2.2: Templates for fast semi-automatic detailing, 48 p.,
© eeEmbedded Consortium, Brussels.
Zellner R. & Mrazek E. (2017): eeEmbedded D7.4: Multi‐model navigation and visualization service, 54 p., ©
eeEmbedded Consortium, Brussels.
D10.400 Final Report
Version 2.0
Page 77/105
© eeEmbedded Consortium www.eeEmbedded.eu
Acronyms
AEC Architecture, Engineering and Construction
API Application Programming Interface – a set of clearly defined methods of communication
between various software components
ARCH Architectural – Most often used to shorten descriptions, i.e. ARCH model
ARIMA Autoregressive integrated moving average – a statistic model to better understand the data or
to predict future points in the series
BACS Building Automation and Control System
BCF BIM Collaboration Format, a data standard to exchange communications about building models
BIM Building Information Modelling/Model – describes either the method of BIM, i.e. the all-
encompassing workflows and processes for a digital design process, or the BIM model, i.e. all
the files that make up the complete building model
BoQ Bill of Quantities
BPMN Business Process Model and Notation – a graphical representation for specifying business
processes in a business process model
BREEAM Building Research Establishment Environmental Assessment Methodology – a method of
assessing, rating, and certifying the sustainability of buildings
CAD Computer-Aided Design
CBA Cost Benefit Analysis
CFD Computational Fluid Dynamics – a branch of fluid mechanics that uses numerical analysis and
data structures to solve and analyse problems that involve fluid flows
CSV Comma-Separated Values
DGNB Deutsche Gesellschaft für Nachhaltiges Bauen e.V. – The German Sustainable Building Council
was founded to promote sustainable and economically efficient building
DV Decision Value – subcategory of the eeEmbedded Key Points, relates to aggregated values,
which support and facilitate a decision
eeE eeEmbedded – official shortcut acronym for the project
eeBIM energy enhanced BIM – either describes BIM data that has been enriched with energy data or
the general modelling method, which includes energy considerations
eeeBIM energy efficient enhanced BIM – either describes BIM data that has been enriched with energy
data or the general modelling method, which includes energy considerations
ER Exchange Requirement – defines data, values and attributes that are required to be available or
to fulfil certain criteria, so that exchange between two software tools or actors can happen
without errors
ESIM Energy System Information Model – the newly developed system model in eeE for the energy
systems
FM Facility Management
HPC High Performance Computing – describes computer or in general computing above the average
computing power of personal computers
D10.400 Final Report
Version 2.0
Page 78/105
© eeEmbedded Consortium www.eeEmbedded.eu
HVAC Heating, Ventilation and Air Conditioning
ICT Information and Communications Technology
ID Identifier – mostly refers to identifiers within software
IDM Information Delivery Manual – refers to ISO 29481-1:2010, specifying a methodology and
format for the development of an information delivery manual (IDM)
IFC Industry Foundation Classes
JSON JavaScript Object Notation – an open-standard file format
KDP Key Design Parameter – one subcategory of Key Point in the eeEmbedded framework, generally
describes mandatory design features for a building
KP Key Point – main aspect of the eeEmbedded design methodology, comprehensible and
aggregated indicators for a buildings performance
KPA Key Point Analysis tool – a software tool developed by the eeEmbedded partner GRA, provides
features to visualize the performance (KP) of a building
KPI Key Performance Indicator – one subcategory of Key Point in the eeEmbedded framework,
generally depicts performance values of a building that are not explicitly visible, i.e. simulation
results
KRI Key Risk Indicator – a subcategory of Key Point in the eeEmbedded framework, generally depicts
uncertainties and risks and is used for the stochastically expression of building performance
LCA Life Cycle Assessment – the domain and process to assess the life cycle of a building
LCC Life Cycle Costing – closely tied to LCA above; calculates the costs corresponding to the life
cycle(s) of a building
LEED Leadership in Energy and Environmental Design – a standard for green building design
LoD Level of Detail
LOD Level of Development
MEP Mechanical, Electrical and Plumbing – a domain of a building and the building design process
MMC Multimodel Container
MMNav Multimodel Navigator – a software tool developed by the partner NEM, main purpose is the
visualisation and navigation of the eeEmbedded Multimodel
MSM EDMmodelServerManager – the management component of the EDM server
MTTF Mean Time To Failure
MTTR Mean Time To Repair
MVD Model View Definition – MVD are subsets (subformats) of a BIM model format and do allow for
certain “views” upon a BIM model
OVS Ontology Verification Service – a software component and service of the eeEmbedded platform
developed by TUD-CIB, the OVS validates the BIM model with regard to data integrity as well as
calculates and checks the Key Points for a building design
OWL Web Ontology Language – a family of knowledge representation languages
PD Percentage Dissatisfied – a term used for comfort analysis within a building
PM Property Management
D10.400 Final Report
Version 2.0
Page 79/105
© eeEmbedded Consortium www.eeEmbedded.eu
PMV Predicted Mean Vote
PPD Percentage of People Dissatisfied
RDF Resource Description Framework – a semantic web data model
ScM Scenario Manager – a software tool of the eeEmbedded platform, which is orchestrating and
managing the overall design process and the data transfer
SDK Software Development Kit
SOA Service Oriented Architecture – a set of principles and methodologies for designing and
developing software in the form of interoperable services
SOAP Simple Object Access Protocol – a protocol specification for exchanging structured information
in the implementation of web services in computer networks
SQL Structured Query Language – a domain-specific language designed for managing data held in a
relational database management system or for stream processing in a relational data stream
management system
SPARQL SPARQL Protocol and RDF Query Language – a RDF query language
SPARUL declarative data manipulation language that is an extension to SPARQL; it provides the ability to
insert, delete and update RDF data held within a triple store or quad store.
SPFF STEP Physical File Format – see STEP
SSP Server Side Plug-in
STEP Standard for the Exchange of Product model data – The ISO 10303 family of standards for the
computer-interpretable representation and exchange of product manufacturing information
SWOT Strengths, Weaknesses, Opportunities and Threats analysis – a structured planning method that
evaluates those four elements of an organization, project or business venture
SysML Systems Modelling Language – a general-purpose modelling language for systems engineering
applications
TRNSYS Transient System Simulation – a simulation program primarily used in the fields of renewable
energy engineering and building simulation, here it refers to the development of the Technische
Universität Dresden
TRY Test Reference Year
UML Unified Modelling Language – a widely spread software modelling language
WWR Window(-to-)Wall Ratio – describes the ration between walls and the windows in it, most often
relates to the (outer) surface area of the wall and window respectivly
XML Extensible Markup Language
XPX EXPRESS-X – query and mapping language for EXPRESS models (ISO 10303-11)
D10.400 Final Report
Version 2.0
Page 80/105
© eeEmbedded Consortium www.eeEmbedded.eu
Partner Abbreviations
TUD-CIB Technische Universität Dresden – Institute of Construction Informatics, Germany (coordinator)
TUD-IEC Technische Universität Dresden – Institute of Power Engineering, Germany
BAM Koninklijke BAM Groep NV, The Netherlands
BDE BAM Deutschland AG, BAM subsidiary in Germany
BNL BAM Utiliteitsbouw b.v., BAM subsidiary in the Netherlands
CEM Centro de Estudios Materiales y Control de Obras S.A. (CEMOSA), Spain
DDS Data Design System ASA, Norway / Germany
EAS Fraunhofer Gesellschaft zur Förderung der Angewandten Forschung e.V. – Institute for
Integrated Circuits, Germany
EPM Jotne EPM Technology AS, Norway
GRA Granlund Oy, Finland
IAB iabi – Institute for Applied Building Informatics, Germany
NEM Nemetschek Allplan Slovensko S.R.O., Slovakia
OPB OBERMEYER Planen + Beraten GmbH, Germany
RIB RIB Information Technologies AG, Germany
SAR Fr. SAUTER AG, Switzerland
SOF SOFiSTiK Hellas AE, Greece
STA STRABAG AG, Austria
ZUE Ed. Züblin AG, STA subsidiary in Germany
D10.400 Final Report
Version 2.0
Page 81/105
© eeEmbedded Consortium www.eeEmbedded.eu
PART 2 – subject to confidentiality –
D10.400 Final Report
Version 2.0
Page 82/105
© eeEmbedded Consortium www.eeEmbedded.eu
Potential impact
The requirements of the EC regarding the reporting of the project’s potential impact are defined
as follows:
A plan for use and dissemination of foreground (including socio-economic impact and target groups for the
results of the research) shall be established at the end of the project. It should, where appropriate, be an
update of the initial plan in Annex I for use and dissemination of foreground and be consistent with the report
on societal implications on the use and dissemination of foreground.
The plan should consist of:
Section A
This section should describe the dissemination measures, including any scientific publications relating to
foreground. Its content will be made available in the public domain thus demonstrating the added-value
and positive impact of the project on the European Union.
Section B
This section should specify the exploitable foreground and provide the plans for exploitation. All these data
can be public or confidential; the report must clearly mark non-publishable (confidential) parts that will be
treated as such by the Commission. Information under Section B that is not marked as confidential will be
made available in the public domain thus demonstrating the added-value and positive impact of the project
on the European Union.
In addition a report section regarding the societal implications of the project has to be included accorind to a
predefined template.
These sections are presented on the following pages completing the Final Project Report.
D2.2 Templates for fast semi-automatic detailing
Version 1.2
Page 83/105
© eeEmbedded Consortium www.eeEmbedded.eu
Section A (public)
This section includes two tables:
Table A1: List of all scientific (peer reviewed) publications relating to the foreground of the project sorted by year (from oldest to newest).
Table A2: List of all dissemination activities (publications, conferences, workshops, web sites/applications, press releases, flyers, articles published in the
popular press, videos, media briefings, presentations, exhibitions, thesis, interviews, films, TV clips, posters).
TABLE A1: LIST OF SCIENTIFIC (PEER REVIEWED) PUBLICATIONS
No. Title Main author Title of the periodical
or the series
Number, date or
frequency Publisher
Place of publication
Year of publication
Relevant pages
Permanent identifiers1 (if available)
Is/Will open access2 provided to this publication?
1 Sustainable energy entrepreneurship through architectural design: a key point controlled method
Guruz R., Scherer R. J.
Entrepreneurship and sustainability issues
Vol. 2 Entrepreneurship and sustainability center
Lithuania 2014 pp. 60-73 http://jssidoi.org/jesi/aims-and-scope-of-research/
yes
2 Building Requirements as Basis for a Key Point controlled Design Method
Guruz R., Scherer R.J.
2nd Int. Conference on ICT for Sustainable Places (ICT4SP2014) - 2nd EeB KPIs Workshop
Nice, France 2014 pp. 58 http://sustainable-places.eu/wp-content/uploads/2014/10/SP14_Proceedings_281014.pdf
no
3 Processes and Requirements for an eeEmbedded Virtual
Geißler M. C., van Woudenberg W., Guruz R.
eWork and eBusiness in Architecture, Engineering and Construction
CRC Press Vienna, Austria
2014 pp. 887-892 http://www.crcnetbase.com/doi/book/10.1201/b17396
no
1 A permanent identifier should be a persistent link to the published version full text if open access or abstract if article is pay per view) or to the final manuscript accepted for publication
(link to article in repository). 2
Open Access is defined as free of charge access for anyone via Internet. Please answer "yes" if the open access to the publication is already established and also if the embargo period for open access is not yet over but you intend to establish open access afterwards.
D2.2 Templates for fast semi-automatic detailing
Version 1.2
Page 84/105
© eeEmbedded Consortium www.eeEmbedded.eu
No. Title Main author Title of the periodical
or the series
Number, date or
frequency Publisher
Place of publication
Year of publication
Relevant pages
Permanent identifiers1 (if available)
Is/Will open access2 provided to this publication?
Design Laboratory
4 Towards a KPI-controlled holistic design method for eeBuildings
R. J. Scherer, R. Guruz, G. Calleja-Rodriguez, M.-C. Geißler
eWork and eBusiness in Architecture, Engineering and Construction
CRC Press Vienna, Austria
2014 pp. 879-885 http://www.crcnetbase.com/doi/book/10.1201/b17396 no
5 An ontology framework for improving building energy performance by utilizing energy saving regulations
K. Baumgärtel , M. Kadolsky , R. Scherer
eWork and eBusiness in Architecture, Engineering and Construction
CRC Press Vienna, Austria
2014 pp. 519-528 http://www.crcnetbase.com/doi/book/10.1201/b17396
no
6 BIM-based Virtual Design Laboratory for energy-efficient embedded buildings
Geißler M.C., van Woudenberg W.
Lake Constance 5D-Conference 2015 Proceedings
Hochschule Konstanz. University of applied sciences
Konstanz, Germany
2015 pp. 380-390
no
7 Energy-Efficient BIM Lab
Scherer R.J., Katranuschkov P., Guruz R.
Lake Constance 5D-Conference 2015 Proceedings
Hochschule Konstanz. University of applied sciences
Konstanz, Germany
2015 pp. 391-405
no
8 Ontology-controlled Energy Simulation Workflow
K. Baumgärtel, M. Kadolsky, R.J. Scherer
Sustainable Places 2015 Proceedings
Savona, Italy 2015 http://sustainable-places.eu/wp-content/uploads/2015/09/FP2_Ken_B.pdf
no
9 Knowledge management framework for monitoring systems improving building energy efficiency
Mathias Kadolsky, Ronny Windisch, Raimar J. Scherer
2015 IEEE Workshop on Environmental, Energy, and Structural Monitoring Systems (EESMS) Proceedings
IEEE 2015 pp. 33-38 http://ieeexplore.ieee.org/xpl/articleDetails.jsp?arnumber=7175848
no
10 Model based processes at large
RIB BBB Booklet University of Aachen
Aachen, Germany
2015 no
D2.2 Templates for fast semi-automatic detailing
Version 1.2
Page 85/105
© eeEmbedded Consortium www.eeEmbedded.eu
No. Title Main author Title of the periodical
or the series
Number, date or
frequency Publisher
Place of publication
Year of publication
Relevant pages
Permanent identifiers1 (if available)
Is/Will open access2 provided to this publication?
infrastructure projects
11 Towards a Workflow-Driven Multi-model BIM Collaboration Platform
Mario Gürtler, Ken Baumgärtel, Raimar J. Scherer
Risks and Resilience of Collaborative Networks
463 Springer International Publishing
Cham, Germany
2015 pp. 235-242 http://link.springer.com/chapter/10.1007/978-3-319-24141-8_21 no
12 Visualization of Facilities Management KPIs during Early Design Using BIM
Forns-Samso F., Laine T., Geissler M.-C.
Proceedings of the CIB World Building Congress 2016
TUT - Tampere University of Technology
Tampere, Finland
2016 pp. 1001-1011
https://tutcris.tut.fi/portal/files/6187048/WBC16_Vol_5.pdf yes
13 Optimizing Energy-Efficient Building Design Using BIM
Katranuschkov P., Scherer R.J., Hoch R.
Proceedings of the 16th International Conference on Computing in Civil and Building Engineering ICCCBE 2016
Osaka University Osaka, Japan 2016 pp. 1765-1772
http://www.see.eng.osaka-u.ac.jp/seeit/icccbe2016/Proceedings yes
14 Stochastic Analysis for Design Space Exploration and Building Performance Optimisation
Grille T, Pruvost H., Scherer R.J.
Proceedings of the CESBP Central European Symposium on Building Physics and BauSIM 2016
Fraunhofer IRB Dresden, Germany
2016 pp. 369-375 http://www.cesbp2016.de/cesbp
no
15 eeBIM LAB – Towards a coherent green building design process
Guruz R., Katranuschkov P., Scherer R.J.
Proceedings of the CESBP Central European Symposium on Building Physics and BauSIM 2016
Fraunhofer IRB Dresden, Germany
2016 pp. 391-395 http://www.cesbp2016.de/cesbp
no
16 KPI visualisation supporting the involvement of facility managers in early
Forns-Samso F., Laine T
Proceedings of CFM’S Second Nordic Conference
Polyteknisk Forlag
Copenhagen Denmark
2016 pp. 68-77 http://orbit.dtu.dk/files/125899567/CFM_Nordic_Conference_2016_proceedings_1.pdf
yes
D2.2 Templates for fast semi-automatic detailing
Version 1.2
Page 86/105
© eeEmbedded Consortium www.eeEmbedded.eu
No. Title Main author Title of the periodical
or the series
Number, date or
frequency Publisher
Place of publication
Year of publication
Relevant pages
Permanent identifiers1 (if available)
Is/Will open access2 provided to this publication?
design
17 Collaboration requirements and interoperability fundamentals in BIM based multi-disciplinary building design processes
Calleja-Rodriguez G., Guruz R., Geißler M.C., Steinmann R., Linhard K. Dangl G.
eWork and eBusiness in Architecture, Engineering and Construction
CRC Press London, UK 2016 pp. 349-354 https://www.crcpress.com/eWork-and-eBusiness-in-Architecture-Engineering-and-Construction-ECPPM/Christodoulo18u-herer/p/book/9781138032804
no
18 Task-Specific Linking for Generating an eeBIM Model based on an Ontology Framework
Kadolsky M., Scherer R.J.
eWork and eBusiness in Architecture, Engineering and Construction
CRC Press London, UK 2016 pp. 363-370 https://www.crcpress.com/eWork-and-eBusiness-in-Architecture-Engineering-and-Construction-ECPPM/Christodoulou-Scherer/p/book/9781138032804
no
19 Visual support for multi-criteria decision making
Laine T., Forns-Samso F., Kukkonen V.
eWork and eBusiness in Architecture, Engineering and Construction
CRC Press London, UK 2016 pp. 371-376 https://www.crcpress.com/eWork-and-eBusiness-in-Architecture-Engineering-and-Construction-ECPPM/Christodoulou-Scherer/p/book/9781138032804
no
20 An IT-based holistic methodology for analysing and managing building lifecycle risk
Pruvost H., Grille T., Scherer R.J
eWork and eBusiness in Architecture, Engineering and Construction
CRC Press London, UK 2016 pp. 377-386 https://www.crcpress.com/eWork-and-eBusiness-in-Architecture-Engineering-and-Construction-
no
D2.2 Templates for fast semi-automatic detailing
Version 1.2
Page 87/105
© eeEmbedded Consortium www.eeEmbedded.eu
No. Title Main author Title of the periodical
or the series
Number, date or
frequency Publisher
Place of publication
Year of publication
Relevant pages
Permanent identifiers1 (if available)
Is/Will open access2 provided to this publication?
ECPPM/Christodoulou-Scherer/p/book/9781138032804
21 Open eeBIM Platform for Energy-Efficient Building Design
Scherer R.J., Katranuschkov P., Baumgärtel K.
eWork and eBusiness in Architecture, Engineering and Construction
CRC Press London, UK 2016 pp. 387-395 https://www.crcpress.com/eWork-and-eBusiness-in-Architecture-Engineering-and-Construction-ECPPM /Christodoulou-Scherer /p/book/9781138032804
no
22 Automatic ontology-based green building design parameter vari-ation and evaluation in thermal energy buil-ding performance analyses
Baumgärtel K., Scherer R.J.
eWork and eBusiness in Architecture, Engineering and Construction
CRC Press London, UK 2016 pp. 667-672 see 21 above
no
23 Automated alternatives analysis procedure using key points me-thod for multidiscipli-nary energy efficient building design projects
G. Calleja-Rodriguez, R. Guruz, M.-C. Loeffler
Automation in Construction
Elsevier Germany 2017
yes
24 An intelligent platform for thermal energy analyses
K. Baumgärtel, P. Katranuschkov, R.J. Scherer
Automation in Construction
Elsevier Germany 2017 yes
25 Scenario Manager: In-tegrated and innova-tive concept for pro-cess and information management based on BIM execution plan
M.-C. Loeffler, G. Calleja-Rodriguez, R. Guruz
Proceedings of the International Research Conference
Salford, UK 2017 http://conference.org.uk/international-research-week/
D2.2 Templates for fast semi-automatic detailing
Version 1.2
Page 88/105
© eeEmbedded Consortium www.eeEmbedded.eu
No. Title Main author Title of the periodical
or the series
Number, date or
frequency Publisher
Place of publication
Year of publication
Relevant pages
Permanent identifiers1 (if available)
Is/Will open access2 provided to this publication?
digitalization and key points
26 Analysis of risk in building life cycle coupling BIM-based energy simulation and semantic modelling
Pruvost, H., Scherer, R.J.
Proc. Creative Construction Conference 2017
Procedia Engineering, Elsevier
Primošten, Croatia
2017
no
27 Multimodel-based exploration of the building design space and its uncertainty
Pruvost, H., Katranuschkov, P., Scherer, R.J.
Sustainable Places 2017 Proceedings
Teesside University
Middles-brough, UK
2017
yes
28 Entwicklung eines Informationsmanagementsystems und einer Entscheidungsplattform für die Zusammen-arbeit aller Projekt-beteiligten
Löffler, M.C. BBB Booklet Stuttgart, Germany
2017
no
D2.2 Templates for fast semi-automatic detailing
Version 1.2
Page 89/105
© eeEmbedded Consortium www.eeEmbedded.eu
TABLE A2: LIST OF DISSEMINATION ACTIVITIES IN CHRONOLOGICAL ORDER
No. Type of activities Main leader Title Date/Period Place Type of audience Size of
audience Countries addressed
1 Web sites/ Applications
TECHNISCHE UNIVERSITAET DRESDEN
Project Web Site 01/12/2013 Internet - www.eeembedded.eu
Scientific community (higher education, Research) - Industry - Civil society - Policy makers - Medias
n/a World
2 Web sites/ Applications
TECHNISCHE UNIVERSITAET DRESDEN
SharePoint 31/10/2013 Internet - https://eembd.cib.bau. tu-dresden.de
Scientific community (higher education, Research) - Industry
n/a Consortium countries
3 Flyers CENTRO DE ESTUDIOS DE MATERIALES Y CONTROL DE OBRA SA
Project flyer 15/05/2014 Europe Scientific community (higher education, Research) - Industry - Civil society - Policy makers - Medias
>200 Europe
4 Oral presentation to a wider public
KONINKLIJKE BAM GROEP NV
BAM Internal Event 27/03/2014 Stuttgart, Germany Industry 30 Germany
5 Press releases CENTRO DE ESTUDIOS DE MATERIALES Y CONTROL DE OBRA SA
eeEmbedded Newsletter Nr.1
31/03/2014 Europe Scientific community (higher education, Research) - Industry - Civil society - Policy makers - Medias
n/a Europe
6 Oral presentation to a wider public
KONINKLIJKE BAM GROEP NV
Presentations from prac-tice for BIM project study
10/04/2014 Stuttgart University, Germany
Scientific community (higher education, Research)
20 Germany
7 Oral presentation to a scientific event
TECHNISCHE UNIVERSITAET DRESDEN
An ontology framework for improving building energy performance by utilizing energy saving regulations
18/09/2014 10th European Conference on Product & Process Modelling (ECPPM2014)
Scientific community (higher education, Research) - Industry
130 Europe
8 Oral presentation to a scientific event
KONINKLIJKE BAM GROEP NV
Processes and Requirements for an eeEmbedded Virtual Design Laboratory
19/09/2014 10th European Conference on Product & Process Modelling (ECPPM2014)
Scientific community (higher education, Research) - Industry
153 Europe
9 Oral presentation to TECHNISCHE Towards a KPI-controlled 19/09/2014 10th European Scientific community (higher 130 Europe
D2.2 Templates for fast semi-automatic detailing
Version 1.2
Page 90/105
© eeEmbedded Consortium www.eeEmbedded.eu
No. Type of activities Main leader Title Date/Period Place Type of audience Size of
audience Countries addressed
a scientific event UNIVERSITAET DRESDEN
holistic design method for eeBuildings
Conference on Product & Process Modelling (ECPPM2014)
education, Research) - Industry
10 Oral presentation to a wider public
NEMETSCHEK ALLPLAN SLOVENSKO SRO
Nemetschek BIM Meeting
19/09/2014 Munich Industry 7 Germany
11 Oral presentation to a wider public
NEMETSCHEK ALLPLAN SLOVENSKO SRO
Nemetschek Development Department Meeting in Bratislava
22/09/2014 Bratislava, Slovakia Industry 73 Europe
12 Oral presentation to a scientific event
TECHNISCHE UNIVERSITAET DRESDEN
Building Requirements as Basis for a Key Point controlled Design Method
01/10/2014 2nd International Conference on ICT for Sustainable Places (ICT4SP2014)
Scientific community (higher education, Research) - Industry
200 World
13 Press releases CENTRO DE ESTUDIOS DE MATERIALES Y CONTROL DE OBRA SA
eeEmbedded Newsletter Nr.2
01/10/2014 Europe Scientific community (higher education, Research) - Industry - Civil society - Policy makers - Medias
n/a Europe
14 Web sites/ Applications
KONINKLIJKE BAM GROEP NV
Virtuelles Planungslabor für nachhaltige Stadtquartiere
22/10/2014 Internet - https://www.bam-deutschland.de/news/883?page=1
Industry n/a Germany
15 Press releases CENTRO DE ESTUDIOS DE MATERIALES Y CONTROL DE OBRA SA
eeEmbedded Newsletter Nr.3
31/03/2015 Europe Scientific community (higher education, Research) - Industry - Civil society - Policy makers - Medias
n/a Europe
16 Oral presentation to a wider public
GRANLUND OY Design methodology, optimization of energy usage
14/04/2015 Innovation Platform, Brussels, Belgium
Industry 15 Europe
17 Oral presentation to a wider public
GRANLUND OY Design methodology, BIM systems
17/04/2015 Switzerland Industry 10 Switzerland
18 Press releases NEMETSCHEK ALLPLAN SLOVENSKO SRO
eeEmbedded Methodology/mmNavigator
22/04/2015 ZUG Schweiz Industry 11 Suiss Germany
D2.2 Templates for fast semi-automatic detailing
Version 1.2
Page 91/105
© eeEmbedded Consortium www.eeEmbedded.eu
No. Type of activities Main leader Title Date/Period Place Type of audience Size of
audience Countries addressed
19 Oral presentation to a wider public
GRANLUND OY Granlund Designer, overview
24/04/2015 Energy Seminar organized by Granlund
Industry 200 Finland
20 Organisation of Workshops
CENTRO DE ESTUDIOS DE MATERIALES Y CONTROL DE OBRA SA
1st eeEmbedded Expert Seminar
05/05/2015 Lake Constance 5D-Conference 2015. Constance, Germany
Scientific community (higher education, Research) - Industry
n/a Europe
21 Posters CENTRO DE ESTUDIOS DE MATERIALES Y CONTROL DE OBRA SA
Project Overview 05/05/2015 5D Lake Constance Conference. Constance, Germany
Scientific community (higher education, Research) - Industry
300 Europe
22 Posters TECHNISCHE UNIVERSITAET DRESDEN
Virtual Energy Lab Concept
05/05/2015 5D Lake Constance Conference. Constance, Germany
Scientific community (higher education, Research) - Industry
300 Europe
23 Posters KONINKLIJKE BAM GROEP NV
Generic Use Cases to Facilitate Collaboration
05/05/2015 5D Lake Constance Conference. Constance, Germany
Scientific community (higher education, Research) - Industry
300 Europe
24 Posters CENTRO DE ESTUDIOS DE MATERIALES Y CONTROL DE OBRA SA
Key Points to Support Design Optimization
05/05/2015 5D Lake Constance Conference. Constance, Germany
Scientific community (higher education, Research) - Industry
300 Europe
25 Posters TECHNISCHE UNIVERSITAET DRESDEN
Software Platform Realization
05/05/2015 5D Lake Constance Conference. Constance, Germany
Scientific community (higher education, Research) - Industry
300 Europe
26 Videos SOFISTIK HELLAS AE Impact & Business Cases
05/05/2015 5D Lake Constance Conference. Constance, Germany
Scientific community (higher education, Research) - Industry
300 Europe
27 Videos TECHNISCHE UNIVERSITAET DRESDEN
nD Navigator - CIB 05/05/2015 5D Lake Constance Conference. Constance, Germany
Scientific community (higher education, Research) - Industry
300 Europe
28 Videos GRANLUND OY Multi-KP Decision Support Tool
05/05/2015 5D Lake Constance Conference. Constance, Germany
Scientific community (higher education, Research) - Industry
300 Europe
29 Videos RIB INFORMATION TECHNOLOGIES AG
Life Cycle Simulation 05/05/2015 5D Lake Constance Conference. Constance, Germany
Scientific community (higher education, Research) - Industry
300 Europe
30 Videos INSTITUTE FOR BCF Collaboration 05/05/2015 5D Lake Constance Scientific community (higher 300 Europe
D2.2 Templates for fast semi-automatic detailing
Version 1.2
Page 92/105
© eeEmbedded Consortium www.eeEmbedded.eu
No. Type of activities Main leader Title Date/Period Place Type of audience Size of
audience Countries addressed
APPLIED BUILDING INFORMATICS IABI
Conference. Constance, Germany
education, Research) - Industry
31 Videos SOFISTIK HELLAS AE CFD Simulation 05/05/2015 5D Lake Constance Conference. Constance, Germany
Scientific community (higher education, Research) - Industry
20 Europe
32 Oral presentation to a scientific event
TECHNISCHE UNIVERSITAET DRESDEN
Overview of the eeEmbedded project
05/05/2015 5D Lake Constance Conference. Constance, Germany
Scientific community (higher education, Research) - Industry
20 Europe
33 Oral presentation to a scientific event
KONINKLIJKE BAM GROEP NV
Design Methodology. Requirements and Use Cases
05/05/2015 5D Lake Constance Conference. Constance, Germany
Scientific community (higher education, Research) - Industry
20 Europe
34 Oral presentation to a scientific event
CENTRO DE ESTUDIOS DE MATERIALES Y CONTROL DE OBRA SA
Design Methodology. Key Point Methodology
05/05/2015 5D Lake Constance Conference. Constance, Germany
Scientific community (higher education, Research) - Industry
20 Europe
35 Oral presentation to a scientific event
NEMETSCHEK ALLPLAN SLOVENSKO SRO
Software Architecture and Components
05/05/2015 5D Lake Constance Conference. Constance, Germany
Scientific community (higher education, Research) - Industry
20 Europe
36 Oral presentation to a scientific event
FRAUNHOFER GESELLSCHAFT ZUR FORDERUNG DER ANGEWANDTEN FORSCHUNG EV
Energy System Information Model
05/05/2015 5D Lake Constance Conference. Constance, Germany
Scientific community (higher education, Research) - Industry
20 Europe
37 Oral presentation to a scientific event
RIB INFORMATION TECHNOLOGIES AG
Main Sponsor Presentation
05/05/2015 5D Lake Constance Conference. Constance, Germany
Scientific community (higher education, Research) - Industry
300 Europe
38 Oral presentation to a scientific event
KONINKLIJKE BAM GROEP NV
BIM-based Virtual Design Laboratory for energy-efficient embedded buildings
05/05/2015 5D Lake Constance Conference. Constance, Germany
Scientific community (higher education, Research) - Industry
Europe
39 Oral presentation to a scientific event
TECHNISCHE UNIVERSITAET DRESDEN
Energy-Efficient BIM Lab 05/05/2015 5D Lake Constance Conference. Constance, Germany
Scientific community (higher education, Research) - Industry
300 Europe
D2.2 Templates for fast semi-automatic detailing
Version 1.2
Page 93/105
© eeEmbedded Consortium www.eeEmbedded.eu
No. Type of activities Main leader Title Date/Period Place Type of audience Size of
audience Countries addressed
40 Organisation of Workshops
KONINKLIJKE BAM GROEP NV
BAM Crossing Boundaries
20/05/2015 BAM SharePoint Industry n/a Europe
41 Oral presentation to a wider public
GRANLUND OY Working at Bigroom, usecase of Energy Optimization
28/05/2015 Metropolia University of Applied Sciences, Helsinki
Scientific community (higher education, Research) - Industry
30 Finland
42 Oral presentation to a scientific event
TECHNISCHE UNIVERSITAET DRESDEN
Knowledge Management Framework for Monitoring Systems improving Building Energy Efficiency
09/07/2015 EESMS 2015-Environmental, Energy and Structural Monitoring Systems
Scientific community (higher education, Research) - Industry
n/a World
43 Thesis Fr. Sauter AG Lösungs-Bibliothek Assistent
14/08/2015 FHNW Brugg-Windisch Scientific community (higher education, Research)
n/a Switzerland
44 Oral presentation to a scientific event
TECHNISCHE UNIVERSITAET DRESDEN
Ontology-controlled Energy Simulation Workflow
16/09/2015 Sustainable Places 2015
Scientific community (higher education, Research) - Industry
>200 World
45 Oral presentation to a scientific event
RIB INFORMATION TECHNOLOGIES AG
Model based processes at large infrastructure projects
17/09/2015 BBB Construction Congress, Aachen
Scientific community (higher education, Research) - Industry
100 Europe
46 Oral presentation to a wider public
GRANLUND OY Project overview 21/09/2015 Innovation Platform, San Francisco, USA
Industry 15 World
47 Oral presentation to a scientific event
RIB INFORMATION TECHNOLOGIES AG
Sustainability of construction projects
29/09/2015 RIB Americas Conference at Georgia Tech, Atlanta
Industry 120 World
48 Press releases NEMETSCHEK ALLPLAN SLOVENSKO SRO
Green Building 30/09/2015 Mail/Letter Scientific community (higher education, Research) - Industry
> 5000 Europe
49 Press releases NEMETSCHEK ALLPLAN SLOVENSKO SRO
eeEmbedded 30/09/2015 Munich Industry 5 Germany
50 Press releases CENTRO DE ESTUDIOS DE MATERIALES Y
eeEmbedded Newsletter Nr.4
30/09/2015 Europe Scientific community (higher education, Research) - Industry -
n/a Europe
D2.2 Templates for fast semi-automatic detailing
Version 1.2
Page 94/105
© eeEmbedded Consortium www.eeEmbedded.eu
No. Type of activities Main leader Title Date/Period Place Type of audience Size of
audience Countries addressed
CONTROL DE OBRA SA Civil society - Policy makers - Medias
51 Web sites/ Applications
KONINKLIJKE BAM GROEP NV
Ein Jahr BIM-Forschung mit eeEmbedded und Selfie
01/10/2015 Internet - http://www.bam.eu/
Industry n/a Germany
52 Web sites/ Applications
CENTRO DE ESTUDIOS DE MATERIALES Y CONTROL DE OBRA SA
eeEmbedded LinkedIn Page
05/10/2015 Internet - https://www.linkedin.com/company/eeembedded
Scientific community (higher education, Research) - Industry - Civil society - Medias
n/a World
53 Oral presentation to a scientific event
TECHNISCHE UNIVERSITAET DRESDEN
Towards a workflow-driven multi-model BIM collaboration platform
06/10/2015 PRO-VE'15 (16th IFIP WG 5.5 Working Conference on Virtual Enterprises)
Scientific community (higher education, Research) - Industry
50 World
54 Posters NEMETSCHEK ALLPLAN SLOVENSKO SRO
eeEmbedded: Software Platform Realization
08/10/2015 Eventreihe ALLPLAN 2016. The Way BIM Works. Leipzig, Germany
Scientific community (higher education, Research) - Industry
150 Germany
55 Posters NEMETSCHEK ALLPLAN SLOVENSKO SRO
eeEmbedded: Impact and Business Cases
08/10/2015 Eventreihe ALLPLAN 2016. The Way BIM Works. Leipzig, Germany
Scientific community (higher education, Research) - Industry
150 Germany
56 Posters NEMETSCHEK ALLPLAN SLOVENSKO SRO
eeEmbedded: Software Platform Realization
28/10/2015 Eventreihe ALLPLAN 2016. The Way BIM Works. Stuttgart, Germany
Scientific community (higher education, Research) - Industry
150 Germany
57 Posters NEMETSCHEK ALLPLAN SLOVENSKO SRO
eeEmbedded: Impact and Business Cases
28/10/2015 Eventreihe ALLPLAN 2016. The Way BIM Works. Stuttgart, Germany
Scientific community (higher education, Research) - Industry
150 Germany
58 Posters NEMETSCHEK ALLPLAN SLOVENSKO SRO
eeEmbedded: Software Platform Realization
29/10/2015 Eventreihe ALLPLAN 2016. The Way BIM Works, Munich , DE
Scientific community (higher education, Research) - Industry
180 Germany
59 Posters NEMETSCHEK ALLPLAN SLOVENSKO
eeEmbedded: Impact 29/10/2015 Eventreihe ALLPLAN 2016. The Way BIM
Scientific community (higher 180 Germany
D2.2 Templates for fast semi-automatic detailing
Version 1.2
Page 95/105
© eeEmbedded Consortium www.eeEmbedded.eu
No. Type of activities Main leader Title Date/Period Place Type of audience Size of
audience Countries addressed
SRO and Business Cases Works. Munich, DE education, Research) - Industry
60 Organisation of Workshops
KONINKLIJKE BAM GROEP NV
eeEmbedded - 1st Conference and Road show
01/10/2015-01/11/2015
Series of webinars, webex
Scientific community (higher education, Research) - Industry
> 60 Europe
61 Oral presentation to a scientific event
TECHNISCHE UNIVERSITAET DRESDEN
eeEmbedded: Link Model
23/03/2016 Linked Data Workshop, Dubln
Scientific community (higher education, Research) - Industry
40 World
62 Press releases CENTRO DE ESTUDIOS DE MATERIALES Y CONTROL DE OBRA SA
eeEmbedded Newsletter Nr.5
31/03/2016 Europe Scientific community (higher education, Research) - Industry - Civil society - Policy makers - Medias
n/a Europe
63 Oral presentation to a scientific event
TECHNISCHE UNIVERSITAET DRESDEN
eeEmbedded: multi model
11/04/2016 Building Smart International Summit, Rotterdam
Scientific community (higher education, Research) - Industry
200 World
64 Oral presentation to a scientific event
NEMETSCHEK ALLPLAN SLOVENSKO SRO
eeEmbedded Methodology an mmNavigator
28/04/2016 Technische Universität München
Industry 19 Germany
65 Oral presentation to a scientific event
NEMETSCHEK ALLPLAN SLOVENSKO SRO
eeEmbedded Methodology an mmNavigator
29/04/2016 Technische Universität München
Scientific community (higher education, Research) - Industry
15 Germany
66 Organisation of Workshops
CENTRO DE ESTUDIOS DE MATERIALES Y CONTROL DE OBRA SA
2nd eeEmbedded Expert Seminar
01/06/2016 CIB World Building Congress 2016. Tampere, Finland
Scientific community (higher education, Research) - Industry
20 World
67 Exhibitions CENTRO DE ESTUDIOS DE MATERIALES Y CONTROL DE OBRA SA
Booth in the WBC16 01/06/2016 CIB World Building Congress 2016. Tampere, Finland
Scientific community (higher education, Research) - Industry
n/a World
68 Oral presentation to a scientific event
GRANLUND OY Visualization of Facilities Management KPIs during Early Design Using BIM
02/06/2016 CIB World Building Congress 2016. Tampere, Finland
Scientific community (higher education, Research) - Industry
> 60 World
69 Oral presentation to TECHNISCHE eeEmbedded: 29/06/2016 SUSTAINABLE Scientific community (higher 200 World
D2.2 Templates for fast semi-automatic detailing
Version 1.2
Page 96/105
© eeEmbedded Consortium www.eeEmbedded.eu
No. Type of activities Main leader Title Date/Period Place Type of audience Size of
audience Countries addressed
a scientific event UNIVERSITAET DRESDEN
presentation of project results
PLACES 2016 – UNIVERSITY OF PAU AND BASQUE COUNTRY, Anglet
education, Research) - Industry
70 Oral presentation to a scientific event
TECHNISCHE UNIVERSITAET DRESDEN
Building Requirements as Basis for a Key Point controlled Design Method
30/06/2016 ID@50 Integrated Design Conference. Bath, England
Scientific community (higher education, Research) - Industry
>100 Europe
71 Oral presentation to a scientific event
KONINKLIJKE BAM GROEP NV
eeEmbedded - Fasttrack 19/07/2016 The Edge, Deloitte, Amsterdam
Industry > 30 Europe
72 Oral presentation to a scientific event
FRAUNHOFER GESELLSCHAFT ZUR FORDERUNG DER ANGEWANDTEN FORSCHUNG EV
Potentiale des BIM-basierten Entwurfs und Betrieb in der Gebäudeautomation
09/08/2016 Automation 2016 / VDI-Konferenz Gebäudeautomation 2016
Scientific community (higher education, Research) - Industry
100 Germany
73 Oral presentation to a scientific event
GRANLUND OY KPI visualisation suporting the involvement of facility managers in early design
29-30/08/2016
CFM’S 2nd Nordic Conference
Scientific community (higher education, Research) - Industry
> 60 Europe
74 Oral presentation to a scientific event
TECHNISCHE UNIVERSITAET DRESDEN
eeBIM LAB – Towards a coherent green building design process
16/09/2016 CESBP/ BauSIM 2016. Dresden, Germany
Scientific community (higher education, Research) - Industry
Europe
75 Organisation of Workshops
TECHNISCHE UNIVERSITAET DRESDEN
Modeling , Information Managament and Simu-lation for Energy Efficient Design Embedded in the Neighbourhood, 6 papers
08/09/2016 ECPPM 2016 Limassol, Cyprus
Scientific community (higher education, Research) - Industry
40 Europe
76 Oral presentation to a scientific event
INSTITUTE FOR APPLIED BUILDING INFORMATICS - IABI
Collaboration require-ments and interopera-bility fundamentals in BIM based multi-disciplinary building design processes
08/09/2016 ECPPM 2016 Limassol, Cyprus
Scientific community (higher education, Research) - Industry
30 Europe
77 Oral presentation to GRANLUND OY Visual support for multi- 09/09/2016 ECPPM 2016 Scientific community (higher 40 Europe
D2.2 Templates for fast semi-automatic detailing
Version 1.2
Page 97/105
© eeEmbedded Consortium www.eeEmbedded.eu
No. Type of activities Main leader Title Date/Period Place Type of audience Size of
audience Countries addressed
a scientific event criteria decision making Limassol, Cyprus education, Research) - Industry
78 Oral presentation to a scientific event
TECHNISCHE UNIVERSITAET DRESDEN
Automatic ontology-based Green Building design Parameter Variation and Evaluation in Thermal Energy Building Perfor-mance Analyses
09/09/2016 ECPPM 2016 Limassol, Cyprus
Scientific community (higher education, Research) - Industry
150 Europe
79 Exhibitions KONINKLIJKE BAM GROEP NV
Booth at the Royal BAM Autumn Meeting
13/09/2016 BAM Autumn Meeting Industry 200 Europe and International
80 Oral presentation to a scientific event
TECHNISCHE UNIVERSITAET DRESDEN
Automatische Prüfung und Filterung in BIM mit Model View Definitions
19/09/2016 Forum Bauinformatik 2016, Hannover, Deutschland
Scientific community (higher education, Research)
80 Germany
81 Press releases CENTRO DE ESTUDIOS DE MATERIALES Y CONTROL DE OBRA SA
eeEmbedded Newsletter Nr.6
30/09/2016 Europe Scientific community (higher education, Research) - Industry - Civil society - Policy makers - Medias
n/a Europe
82 Oral presentation to a scientific event
CENTRO DE ESTUDIOS DE MATERIALES Y CONTROL DE OBRA SA
Workshop on Construction - New Digital Sector
13/10/2016 University of Malaga, Spain
Scientific community (higher education, Research) - Industry
30 Europe
83 Exhibitions FR. SAUTER AG BIM World Munich 29-30/11/2016
Munich, Germany Scientific community, Industry, Policy makers, Media
>2000 Germany
84 Oral presentation to a scientific event
CENTRO DE ESTUDIOS DE MATERIALES Y CONTROL DE OBRA SA
Meeting of the group "City of the Future"
01/03/2017 online Scientific community (higher education, Research) - Industry
23 Spain
85 Organisation of Workshops
STRABAG AG 3rd Conf. and roadshow: buildingSMART International Summit
04/04/2017 buildingSMART International Summit, Barcelona, Spain
Scientific community (higher education, Research) - Industry
30 Europe
86 Oral presentation to a scientific event
KONINKLIJKE BAM GROEP NV
Overview of the whole eeE plattform from a constructions company view
04/04/2017 buildingSMART Workshop in Barcelona
Scientific community - industry 200 Europe
87 Press releases CENTRO DE ESTUDIOS eeEmbedded Newsletter 21/04/2017 Europe Scientific community (higher Europe
D2.2 Templates for fast semi-automatic detailing
Version 1.2
Page 98/105
© eeEmbedded Consortium www.eeEmbedded.eu
No. Type of activities Main leader Title Date/Period Place Type of audience Size of
audience Countries addressed
DE MATERIALES Y CONTROL DE OBRA SA
Nr.7 education, Research) - Industry - Civil society - Policy makers - Medias
88 Oral presentation to a scientific event
KONINKLIJKE BAM GROEP NV
Process and information management for sustainable project development
08/05/2017 buildingSMART Workshop in Mainz
Scientific community - industry 15 Europe
89 Organisation of Workshops
RIB INFORMATION TECHNOLOGIES AG
4th Conference and roadshow: Workshop in Mainz
08/05/2017 Mainz, Germany Scientific community (higher education, Research) - Industry
50 Germany
90 Press releases NEMETSCHEK ALLPLAN SLOVENSKO SRO
ALLPLAN Supports Three EU Projects for the Future of Building
13/06/2017 online Industry > 100.000
Germany, Swiss, Austria,
Worldwide
91 Organisation of Workshops
TECHNISCHE UNIVERSITAET DRESDEN
Four steps closer to a full set of interoperable tools for designing energy effi-cient buildings workshop"
29/06/2017 Sustainable Places 2017, Middlesbrough, United Kingdom
Scientific community (higher education, Research) - Industry - Policy makers
> 60 Europe
92 Oral presentation to a scientific event
CENTRO DE ESTUDIOS DE MATERIALES Y CONTROL DE OBRA SA
Scenario Manager: In-tegrated and innovative concept for process and information management based on BIM execution plan digitalization and key points
11-12/09/2017
International Research Conference 2017, Salford, UK
Scientific community - industry tbc World
D2.2 Templates for fast semi-automatic detailing
Version 1.2
Page 99/105
© eeEmbedded Consortium www.eeEmbedded.eu
Section B (Confidential3 or public: confidential information to be marked clearly) Part B1 The applications for patents, trademarks, registered designs, etc. shall be listed according to the template B1 provided hereafter. The list should, specify at least one unique identifier e.g. European Patent application reference. For patent applications, only if applicable, contributions to standards should be specified. This table is cumulative, which means that it should always show all applications from the beginning until after the end of the project.
TEMPLATE B1: LIST OF APPLICATIONS FOR PATENTS, TRADEMARKS, REGISTERED DESIGNS, ETC.
Type of IP Rights: Confidential Foreseen embargo date
dd/mm/yyyy Application reference(s)
(e.g. EP123456) Subject or title of application
Applicant(s) (as on the application)
N/A
Note: The products of eeEmbedded are the novel design methodology and software services and tools which cannot be patented. Therefore, this table is
left empty.
3 Not to be confused with the "EU CONFIDENTIAL" classification for some security research projects.
D2.2 Templates for fast semi-automatic detailing
Version 1.2
Page 100/105
© eeEmbedded Consortium www.eeEmbedded.eu
Part B2
Type of Exploitable Foreground
Description of exploitable foreground
Confidential YES/NO
Foreseen embargo
date dd/mm/yyyy
Exploitable product(s) or measure(s)
Sector(s) of application
Timetable, commercial
or any other use
Patents or other IPR
exploitation (licences)
Owner & Other Beneficiary(s)
involved
Commercial exploitation of R&D results
eeE Virtual Lab Platform - BIM-based collaborative design and simulation platform. The Platform supports the novel eeEmbedded key point based design methodology by providing an integrated information management framework including BIM and energy system information models (ESIM) for designing energy-efficient buildings and their optimal energetic embedding in the neighborhood of surrounding buildings and energy systems.
NO NO Software and Consulting
J62.0 - Computer programming, consultancy and related activities
2018 eeE Partners (OWNER)
Commercial exploitation of R&D results
Multimodel Framework - Conceptual Framework, Schemas and Reference Implementation for the integration of heterogeneous design data from distributed information sources for the needs of energy-efficient design, LCC/LCA and facility management
NO NO Software and Consulting
J62.0 - Computer programming, consultancy and related activities
2018 ISO/NP21597 (collaboration with COINS and Mefisto projects)
TU Dresden, eeE Partners (OWNER)
Commercial exploitation of R&D results
Risk Assessment Service - A service related to the eeEmbedded platform and integrated within the eeE Scenario Manager to enable consideration of design and life cycle risks as measurable key indicators for comparing variant designs
NO NO Software and Consulting
J62.0 - Computer programming, consultancy and related activities
2018 R project (free software)
TU Dresden, eeE Partners (OWNER)
Commercial exploitation of R&D results
Scenario Manager - Main user interface to the virtual lab platform for the energy-optimised design and other processes.
NO NO Software J62.0 - Computer programming, consultancy and related activities
2018 TU Dresden (OWNER)
D2.2 Templates for fast semi-automatic detailing
Version 1.2
Page 101/105
© eeEmbedded Consortium www.eeEmbedded.eu
Type of Exploitable Foreground
Description of exploitable foreground
Confidential YES/NO
Foreseen embargo
date dd/mm/yyyy
Exploitable product(s) or measure(s)
Sector(s) of application
Timetable, commercial
or any other use
Patents or other IPR
exploitation (licences)
Owner & Other Beneficiary(s)
involved
Commercial exploitation of R&D results
Multimodel Navigator - Navigation to control all Building Variations and support decisions by proper displaying of results.
NO NO Software J62.0 - Computer programming, consultancy and related activities
2018/2019 Nemetschek (OWNER)
Commercial exploitation of R&D results
Ontology (OVS), ER Check, KDP Check - Fast validation of key point values and rules of standard design codes according to pre-defined rule sets
NO NO Software J62.0 - Computer programming, consultancy and related activities
2018/2019 TU Dresden (OWNER) + eeE Consortium
Commercial exploitation of R&D results
Templates - Construction types, Materials with physical properties, future integration of Libraries, definition of alternative sub-processes to the pre-defined scenarios via Business Process Modelling Notations (BPMN) that may contain a lot of conflicts
NO NO Software J62.0 - Computer programming, consultancy and related activities
2018/2019 TU Dresden (OWNER) + eeE Consortium
Commercial exploitation of R&D results
3DWind - Aerodynamic analysis of buildings to optimise shape and position of a building according to criteria such as energy consumption, wind comfort, wind potential, natural ventilation design
NO NO Software J62.0 - Computer programming, consultancy and related activities
2020 SOFiSTiK (OWNER)
Commercial exploitation of R&D results
3DThermalCFD - CFD End user application /Analysis Tool for the detailed energy analysis in buildings for the prediction of indoor climate conditions toward the fulfilment of user-defined thermal comfort requirements
NO NO Software J62.0 - Computer programming, consultancy and related activities
2020 SOFiSTiK (OWNER)
D2.2 Templates for fast semi-automatic detailing
Version 1.2
Page 102/105
© eeEmbedded Consortium www.eeEmbedded.eu
Type of Exploitable Foreground
Description of exploitable foreground
Confidential YES/NO
Foreseen embargo
date dd/mm/yyyy
Exploitable product(s) or measure(s)
Sector(s) of application
Timetable, commercial
or any other use
Patents or other IPR
exploitation (licences)
Owner & Other Beneficiary(s)
involved
Commercial exploitation of R&D results
iTWO – LCC/LCA - Life cycle cost and analysis estimation for all running costs regarding even environmental impacts, like energy and CO2 consumption
NO NO Software J62.0 - Computer programming, consultancy and related activities
after 2018 RIB (OWNER)
Commercial exploitation of R&D results
Multi-KP Tool - Compare different alternatives to find the best solution. Visualisation can be done in the Multimodel Navigator
NO NO Software J62.0 - Computer programming, consultancy and related activities
after 2018 Granlund (OWNER)
Commercial exploitation of R&D results
TRNSYS - Energy simulation for calculation of the thermal behaviour of buildings taking into account energy systems and HVAC components. Extension of Commercial Applic.
NO NO Software and Consulting
J62.0 - Computer programming, consultancy and related activities
after 2018 TU Dresden (OWNER)
Commercial exploitation of R&D results
EPM BIM server - BIM server which can merge IFC Files from different disciplines, energy analysis, cost calculations
NO NO Software and Consulting
J62.0 - Computer programming, consultancy and related activities
after 2018 Jotne (OWNER)
Commercial exploitation of R&D results
Allplan – Extensions to General Architectural Design CAD Software, able to design multiple configurations using parametric modelling
NO NO Software J62.0 - Computer programming, consultancy and related activities
after 2018 Nemetschek (OWNER)
D2.2 Templates for fast semi-automatic detailing
Version 1.2
Page 103/105
© eeEmbedded Consortium www.eeEmbedded.eu
Type of Exploitable Foreground
Description of exploitable foreground
Confidential YES/NO
Foreseen embargo
date dd/mm/yyyy
Exploitable product(s) or measure(s)
Sector(s) of application
Timetable, commercial
or any other use
Patents or other IPR
exploitation (licences)
Owner & Other Beneficiary(s)
involved
Commercial exploitation of R&D results
eeE Software Services – Software Services offered by NEM enhanced by eeEmbedded functionality
NO NO Software J62.0 - Computer programming, consultancy and related activities
after 2018 Developments of NEM Soft-ware & Partners within the eeE Consortium
Nemetschek Software (OWNER)
Commercial exploitation of R&D results
DDS-CAD MEP – Extensions to HVAC Design able to generate multiple configurations – using parametric modelling and produce models according to LOD/LoD agreements
NO NO Software J62.0 - Computer programming, consultancy and related activities
after 2018 DDS (OWNER)
Commercial exploitation of R&D results
Case Builder BACS – Extensions to Software for handling building automation projects, contains energy-efficient strategies and methods
NO NO Software and Consulting
J62.0 - Computer programming, consultancy and related activities
after 2018 Sauter (OWNER)
Commercial exploitation of R&D results
Granlund Designer – Extensions / Design the MEP equipment in a construction project
NO NO Software and Consulting
J62.0 - Computer programming, consultancy and related activities
after 2018 Granlund (OWNER)
D2.2 Templates for fast semi-automatic detailing
Version 1.2
Page 104/105
© eeEmbedded Consortium www.eeEmbedded.eu
Type of Exploitable Foreground
Description of exploitable foreground
Confidential YES/NO
Foreseen embargo
date dd/mm/yyyy
Exploitable product(s) or measure(s)
Sector(s) of application
Timetable, commercial
or any other use
Patents or other IPR
exploitation (licences)
Owner & Other Beneficiary(s)
involved
Commercial exploitation of R&D results
eeE Design Methodology –Will be integrated to CEMOSA services related to design and refurbishment of singular buildings
Medium Term: eeE Design Methodology will be adopted to integrate it in services related to design and refurbishment of infrastructures
NO NO Consulting F41.1.0 - Development of building projects
after 2018 eeE Consortium CEMOSA (OWNER)
Commercial exploitation of R&D results
Scenario Manager –Will be integrated to CEMOSA design processes
NO NO Consulting F41.1.0 - Development of building projects
after 2018 eeE Consortium CEMOSA (OWNER)
Commercial exploitation of R&D results
Key Point Analysis Tool – Will be integrated to CEMOSA design processes for evaluation of buil-dings and infrastructures designs
NO NO Consulting F41.1.0 - Development of building projects
after 2018 eeE Consortium CEMOSA (OWNER)