    OUTAGE PREPAREDNESS INDEX (OPI-00) for Fin. Yea

    (Target cum Monitoring sheet-Part-A)

    Station : Unchahar Scheduled from - 25/05/09 to 13/06/09

    OH Completed from - 25/05/09 to 15/06/

    Unit: 4 Type of O/H : BOILER O

    S. No. Activity / Description Max Months Before O/HMarks 24 18 12 6

    01.0 Formation of Outage Committee 20 * 20

    02.0 30

    03.0 30 * 20 * 05 * 05

    04.0 100 * 60 * 20 * 20

    Boiler & Aux.

    Steam Turbine Aux.

    Turbo Generator Aux. Electrical

    Control & Instrumentation

    Miscellaneous

    05.0 50 * 30 * 10 * 10

    BTL reduction plan

    APH efficiency revival plan

    Turbine efficiency plan

    Condenser tube replacement

    Obsolescence (R&M for DAS)

    06.0 30 * 30

    07.0 30 * 10 * 10 * 10

    08.0 Resource Analysis 50 * 30 * 10 *10Spares & Material identification

    Contracts identification

    Procurement status

    Contract Award

    09.0 Estimated Budget Requirement 30 * 10 * 10 * 10

    10.0 PERT & Bar Charts 30 * 10 * 10 * 10

    Engineering Declarationsubmission in required format(Revision No.-3) Overhaul Date(Proposed)

    *R020

    *R105

    *R205

    Outage period & duration:justification of outage duration &time period

    Identification of Equipments &Scope of Work for Overhaul.Standard Scope of work

    Plant betterment Action Plan(AI/RI/EI/TO/LF) Examples

    Defects/Shutdown/Pending PMJobs included in Scope

    Incorporation ofrecommendations / comments ofKTs/COS/RHQ-OS

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    2/183

    11.0 QCP Readiness 50 * 30 * 10 * 10

    Number of QCP identified

    Number of QCP prepared (%)

    12.0 20 * 20

    13.0 30 * 20 * 10

    Number of RCS idintified

    Number of RCS prepared (%)

    Total of applicable activities500 200 110 110 80

    OUTAGE PREPAREDNESS INDEX (OPI- 01 ) for Fin. Ye

    (Target cum Monitoring sheet-Part-A)Station : Unchahar Scheduled from - 06/10/09 to 14/11/09

    Unit: 2 Type of O/H : BOILER + R&M WORK LIKE- DDCMIS +U

    S. No. Activity / Description Max Months Before O/H

    Marks

    24 (R0) 18 (R1) 12 (2) 6

    01.0 Formation of Outage Committee 20 20

    02.0 30 20 5 5

    03.0 30 20 5 5

    04.0 100 60 20 20

    Boiler & Aux.

    Steam Turbine Aux.

    Turbo Generator Aux. & Electrical

    Control & Instrumentation

    Miscellaneous

    05.0 50 30 10 10

    BTL reduction plan

    Isolation Plan readinessChecking of tools

    Re-commissioning ChecksSheets (RCS) Readiness :

    Engineering Declaration

    submission in required format(Revision No.-3) Overhaul Date(Proposed)

    Outage period & duration:justification of outage duration &time period

    Identification of Equipments &Scope of Work for Overhaul.Standard Scope of work

    Plant betterment Action Plan(AI/RI/EI/TO/LF) Examples

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    3/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    4/183

    02.0 30 20 5 5

    03.0 30 20 5 5

    04.0 100 60 20 20

    Boiler & Aux.

    Steam Turbine Aux.

    Turbo Generator Aux. & Electrical

    Control & Instrumentation

    Miscellaneous

    05.0 50 30 10 10

    BTL reduction planAPH efficiency revival plan

    Turbine efficiency plan

    Condenser tube replacement

    Obsolescence (R&M for DAS)

    06.0 30 30

    07.0 30 10 10 10

    08.0 Resource Analysis 50 30 10 10

    Spares & Material identification

    Contracts identificationProcurement status

    Contract Award

    09.0 Estimated Budget Requirement 30 10 10 10

    10.0 PERT & Bar Charts 30 10 10 10

    11.0 QCP Readiness 50 30 10 10

    Number of QCP identified

    Number of QCP prepared (%)

    12.0 20 20

    13.0 30 20 10

    Number of RCS idintified

    Number of RCS prepared (%)

    Total of applicable activities 500 200 110 110 80

    Engineering Declarationsubmission in required format(Revision No.-3) Overhaul Date(Proposed)

    Outage period & duration:justification of outage duration &

    time periodIdentification of Equipments &Scope of Work for Overhaul.Standard Scope of work

    Plant betterment Action Plan(AI/RI/EI/TO/LF) Examples

    Defects/Shutdown/Pending PMJobs included in Scope

    Incorporation ofrecommendations / comments ofKTs/COS/RHQ-OS

    Isolation Plan readinessChecking of tools

    Re-commissioning ChecksSheets (RCS) Readiness :

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    5/183

    OUTAGE PREPAREDNESS INDEX (OPI-11) for Fin. Yea

    (Target cum Monitoring sheet-Part-A)

    Station : Unchahar Scheduled from - 25/08/10 to 18/09/10

    Unit: 1 Type of O/H : BOILER

    Max Months Before O/HS. No. Activity / Description Marks 24 (R0) 18 (R1) 12 (2) 6

    01.0 Formation of Outage Committee 20 20

    02.0 30 20 5 5

    03.0 30 20 5 5

    04.0 100 60 20 20

    Boiler & Aux.

    Steam Turbine Aux.

    Turbo Generator Aux. Electrical

    Control & Instrumentation

    Miscellaneous

    05.0 50 30 10 10

    BTL reduction plan

    APH efficiency revival plan

    Turbine efficiency planCondenser tube replacement

    Obsolescence (R&M for DAS)

    06.0 30

    07.0 30 10 10 10

    08.0 Resource Analysis 50 30 10 8

    Spares & Material identification

    Contracts identification

    Procurement status

    Contract Award09.0 Estimated Budget Requirement 30 10 10 10

    10.0 PERT & Bar Charts 30 10 10

    11.0 QCP Readiness 50 30 30

    Number of QCP identified

    Number of QCP prepared (%)

    12.0 20

    Engineering Declarationsubmission in required format(Revision No.-3) Overhaul Date(Proposed)

    Outage period & duration:justification of outage duration &time period

    Identification of Equipments &

    Scope of Work for Overhaul.Standard Scope of work

    Plant betterment Action Plan(AI/RI/EI/TO/LF) Examples

    Defects/Shutdown/Pending PMJobs included in Scope

    Incorporation ofrecommendations / comments ofKTs/COS/RHQ-OS

    Isolation Plan readinessChecking of tools

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    6/183

    13.0 30

    Number of RCS idintified

    Number of RCS prepared (%)

    Total of applicable activities 500 200 110 108 0

    OUTAGE PREPAREDNESS INDEX (OPI-13) for Fin. Yea

    (Target cum Monitoring sheet-Part-A)

    Station : Unchahar Scheduled from - 20/10/10 to 13/11/10

    Unit: 5 Type of O/H : OH of LP turbine & Boiler

    Max Months Before O/H

    S. No. Activity / Description Marks 24 (R0) 18 (R1) 12 6

    01.0 Formation of Outage Committee 20 20

    02.0 30 20 5

    03.0 30 20 5

    04.0 100 60 20

    Boiler & Aux.

    Steam Turbine Aux.Turbo Generator Aux. & Electrical

    Control & Instrumentation

    Miscellaneous

    05.0 50 30 10

    BTL reduction plan

    APH efficiency revival plan

    Turbine efficiency plan

    Condenser tube replacement

    Obsolescence (R&M for DAS)06.0 30

    07.0 30 10 10

    08.0 Resource Analysis 50 30 10

    Spares & Material identification

    Contracts identification

    Re-commissioning ChecksSheets (RCS) Readiness :

    Engineering Declaration

    submission in required format(Revision No.-3) Overhaul Date(Proposed)

    Outage period & duration:justification of outage duration &time period

    Identification of Equipments &Scope of Work for Overhaul.Standard Scope of work

    Plant betterment Action Plan(AI/RI/EI/TO/LF) Examples

    Defects/Shutdown/Pending PMJobs included in Scope

    Incorporation ofrecommendations / comments ofKTs/COS/RHQ-OS

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    7/183

    Procurement status

    Contract Award

    09.0 Estimated Budget Requirement 30 10 10

    10.0 PERT & Bar Charts 30 10

    11.0 QCP Readiness 50 30

    Number of QCP identifiedNumber of QCP prepared (%)

    12.0 Isolation Plan readiness 20

    13.0 30

    Number of RCS idintified

    Number of RCS prepared (%)

    Total of applicable activities 500 200 110

    Re-commissioning ChecksSheets (RCS) Readiness :

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    8/183

    UNCHAHAR

    r:-2009-10

    Date- 31/08/2009

    9ERHAUL

    OPI-Remarks

    Formed

    Submitted.

    Provided

    As per part-B

    Done

    * Boiler & boiler aux.* Turbine aux.

    * Generator aux.* Electrical system.

    * Control & Instrumentationsystem.

    * Mill liner replacement of Mill 4AB* Material Mix-up & thickness survey

    of critical TG pipings, drains & bends.* Mounting of

    thermocouples for monitoring highenergy drains passing with alarm inUCB. *TGBearing-4 bearing inspection/ repair

    Pending defect list being updatedregularly. Available on line.

    Recommendations incorporated in O/Hscope ot work.

    Provided with Engg declaration

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    9/183

    Identified

    QCP prepared (100%)

    Identified

    RCS prepared (100 %)

    r:-2009-10

    B,DAS,CER CIVIL WORK etc.

    OPI-Remarks

    Formed

    Submitted.

    Provided

    36 175

    Thickness survey, radiography & DPTtests as per old pactice.

    Identified (As per SAP PM Module)

    Identified (As per practice)

    * Boiler & boiler aux. *Turbine aux.

    * Generator aux. *Electrical system. *Control & Instrumentation system.

    * Repl. of Gen. stator* Material Mix-up & thickness survey ofcritical pipings, drains & bends.

    * Mounting ofthermocouples for monitoring highenergy drains passing with alarm in

    *

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    10/183

    As per part-B

    Done

    Identified

    QCP prepared (100%)

    Identified

    RCS prepared (100 %)

    r:-2009-10

    OPI-Remarks

    Formed

    in C & I area- DDCMIS, ASLD,Actuators of ID,FD,PA fans, DAS &CER etc.* R & M works in electrical area- HTbreakers, DAVR etc.* R & M works in turbine area-

    replacement of HP heater, TSI etc.* R & M works in ash handling system-Bottom ash hopper hydraulic gate* R & M work in Mill area- Mill hot airgate *Replacement of control room floor &roof

    Pending defect list being updatedregularly. Available on line.

    Recommendations incorporated in O/Hscope ot work.

    Provided with Engg declaration

    Thickness survey, radiography & DPTtests as per old pactice.

    Identified (As per SAP PM Module)

    Identified (As per practice)

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    11/183

    Submitted.

    Provided

    As per part-B

    Done

    Identified

    QCP prepared (100%)

    Identified

    RCS prepared (100 %)

    * Boiler & boiler aux. *Turbine aux & Turbine aux.

    * Generator aux &Generator aux. *Electrical system. *Control & Instru

    * Material Mix-up & thickness survey ofcritical pipings, drains & bends.

    * Mounting ofthermocouples for monitoring highenergy drains passing with alarm inUCB.

    Pending defect list being updatedregularly. Available on line.

    Recommendations incorporated in O/Hscope ot work.

    Provided with Engg declaration

    Thickness survey, radiography & DPTtests as per old pactice.

    Identified (As per SAP PM Module)

    Identified (As per practice)

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    12/183

    r:-2010-11

    VERHAUL

    OPI-Remarks

    Formed

    Submitted.

    Provided

    As per part-B

    Done

    Identified

    QCP prepared (100%)

    * Boiler & boiler aux.

    *Turbine aux.* Generator aux.

    * Electrical system.* Control & Instrumentation system.

    Before 12 month of overhauling finalOH Scope will be decided by CC-OS

    Pending defect list being updatedregularly. Available on line.

    Recommendations incorporated in O/Hscope ot work.

    Provided with Engg declaration

    Thickness survey, radiography & DPTtests as per old pactice.

    Identified (As per SAP PM Module)

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    13/183

    Identified

    RCS prepared (100 %)

    r:-2010-11

    OPI-Remarks

    Formed

    Submitted.

    Provided

    As per part-B

    Identified (As per practice)

    * Boiler & boiler aux. * LP Turbine & Turbine aux.

    * Generator aux.* Electrical system.

    * Control &Instrumentation system.

    Before 12 month of overhauling finalOH Scope will be decided by CC-OS

    Pending defect list being updatedregularly. Available on line.

    Recommendations incorporated in O/Hscope ot work.

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    14/183

    Done

    IdentifiedQCP prepared (100%)

    Identified

    RCS prepared (100 %)

    Provided with Engg declaration

    Thickness survey, radiography & DPTtests as per old pactice.

    Identified (As per SAP PM Module)

    Identified (As per practice)

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    15/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    16/183

    15 94500

    2625

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    17/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    18/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    19/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    20/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    21/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    22/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    23/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    24/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    25/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    26/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    27/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    28/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    29/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    30/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    31/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    32/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    33/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    34/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    35/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    36/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    37/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    38/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    39/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    40/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    41/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    42/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    43/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    44/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    45/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    46/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    47/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    48/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    49/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    50/183

    OPI PART B CALCULATION F

    FGUTPP UNCHAHAR

    Unit-4(OPI- 00M)

    Part-B Scheduled frOH Completed

    Sno Activity U/M

    1 2 3 3 8 6 7Spares procurement

    1 CRITICAL SPARES

    1.1 Total No of Spares identified 34 34 34 0

    1.2 Purchase Indents Raised 34 34 34 0

    1.3 Purchase Enquiry Issued 34 34 34 0

    1.4 Purchase Order Placed 34 34 34 0

    1.5 Items recd against PO 34 34 34 0

    Total 1.0

    2 NON CRITICAL SPARES

    2.1 Total No of Spares identified 289 289 289 0

    2.2 Purchase Indents Raised 289 289 289 0

    2.3 Purchase Enquiry Issued 289 289 289 0

    2.4 Purchase Order Placed 289 289 289 0

    2.5 Items recd against PO 289 289 289 0

    Total 2.0

    3 CONSUMABLES

    3.1 Total No of items identified 248 248 248 0

    3.2 Purchase Indents Raised 248 248 248 0

    Unit: - 4: O/H Type: BOILE

    TotalQnty

    Expected/Due

    for O/H

    CumulativeTarget for

    OPI

    CumulativeAchieved

    Shortfall, ifany

    No ofItems

    No ofItems

    No ofItems

    No ofItems

    No of

    Items

    No ofItems

    No ofItems

    No ofItems

    No ofItems

    Nosofitems

    No ofItems

    No ofItems

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    51/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    52/183

    FGUTPP UNCHAHAR

    Unit-2 (OPI- 01 M)

    Part-B Scheduled fr

    Sno Activity U/M

    1 2 3 3 8 6 7

    Spares procurement

    1 CRITICAL SPARES1.1 Total No of Spares identified 40 40 40 0

    1.2 Purchase Indents Raised 40 40 40 0

    1.3 Purchase Enquiry Issued 40 40 40 0

    1.4 Purchase Order Placed 40 40 40 0

    1.5 Items recd against PO 40 40 38 2

    Total 1.0

    2 NON CRITICAL SPARES

    2.1 Total No of Spares identified 193 193 193 0

    2.2 Purchase Indents Raised 193 193 193 0

    2.3 Purchase Enquiry Issued 193 193 193 0

    2.4 Purchase Order Placed 193 193 193 0

    2.5 Items recd against PO 193 193 189 4

    Total 2.0

    3 CONSUMABLES

    3.1 Total No of items identified 323 323 323 0

    3.2 Purchase Indents Raised 323 323 323 0

    3.3 Purchase Enquiry Issued 323 323 323 0

    Unit: - 2: O/H Type: BOILER OH + R&M WORK LIKE-DDCMIS+UCB,

    TotalQnty

    Expected/Due for

    O/H

    CumulativeTarget for

    OPI

    CumulativeAchieved

    Shortfall, ifany

    No ofItems

    No ofItems

    No ofItems

    No ofItems

    No ofItems

    No ofItems

    No ofItems

    No ofItems

    No ofItems

    Nosofitems

    No ofItems

    No ofItems

    No ofItems

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    53/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    54/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    55/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    56/183

    Sno Activity U/M

    1 2 3 3 8 6 7Spares procurement

    1 CRITICAL SPARES

    1.1 Total No of Spares identified 28 28 28 0

    1.2 Purchase Indents Raised 28 20 20 0

    1.3 Purchase Enquiry Issued 28 15 14 1

    1.4 Purchase Order Placed 28 10 14 -4

    1.5 Items recd against PO 28 3 14 -11

    Total 1.0

    2 NON CRITICAL SPARES

    2.1 Total No of Spares identified 476 476 476 0

    2.2 Purchase Indents Raised 476 476 440 36

    2.3 Purchase Enquiry Issued 476 476 440 36

    2.4 Purchase Order Placed 476 476 260 216

    2.5 Items recd against PO 476 476 132 344

    Total 2.0

    3 CONSUMABLES

    3.1 Total No of items identified 120 120 120 0

    3.2 Purchase Indents Raised 120 87 87 0

    3.3 Purchase Enquiry Issued 120 76 76 0

    3.4 Purchase Order Placed 120 76 76 0

    3.5 Items recd against PO 120 42 42 0

    Total 3.0

    4 T&P

    4.1 Total No of items identified 0 0 0 0

    4.2 Purchase Indents Raised 0 0 0 0

    TotalQnty

    Expected/Due

    for O/H

    CumulativeTarget for

    OPI

    CumulativeAchieved

    Shortfall, ifany

    No ofItems

    No ofItems

    No ofItems

    No ofItems

    No ofItems

    No ofItems

    No ofItems

    No ofItems

    No ofItems

    Nos

    ofitems

    No ofItems

    No ofItems

    No ofItems

    No ofItems

    Nos ofitems

    No ofItems

    No ofItems

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    57/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    58/183

    1.1 Total No of Spares identified 36 36 36 0

    1.2 Purchase Indents Raised 36 15 12 3

    1.3 Purchase Enquiry Issued 36 6 6 0

    1.4 Purchase Order Placed 36 0 4 -4

    1.5 Items recd against PO 36 0 3 -3

    Total 1.0

    2 NON CRITICAL SPARES

    2.1 Total No of Spares identified 276 276 276 0

    2.2 Purchase Indents Raised 276 150 56 94

    2.3 Purchase Enquiry Issued 276 100 27 73

    2.4 Purchase Order Placed 276 50 13 37

    2.5 Items recd against PO 276 0 107 -107

    Total 2.0

    3 CONSUMABLES

    3.1 Total No of items identified 111 111 111 0

    3.2 Purchase Indents Raised 111 90 60 30

    3.3 Purchase Enquiry Issued 111 35 48 -13

    3.4 Purchase Order Placed 111 20 24 -4

    3.5 Items recd against PO 111 0 18 -18

    Total 3.0

    4 T&P

    4.1 Total No of items identified 0 0 0 0

    4.2 Purchase Indents Raised 0 0 0 0

    4.3 Purchase Enquiry Issued 0 0 0 0

    4.4 Purchase Order Placed 0 0 0 0

    4.5 Items recd against PO 0 0 0 0

    Total 4.0

    No ofItems

    No ofItems

    No ofItems

    No ofItems

    No ofItems

    No ofItems

    No ofItems

    No of

    ItemsNo ofItems

    Nosofitems

    No ofItems

    No ofItems

    No ofItems

    No ofItems

    Nos ofitems

    No ofItems

    No of

    ItemsNo ofItems

    No ofItems

    Nos ofitems

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    59/183

    5 Contracts for O/H

    5.1 Identification of Contracts 28 28 28 0

    5.2 Contract Proposals initiated 28 0 20 -20

    5.3 Tender Issued 28 0 12 -12

    5.4 Offer received 28 0 12 -12

    5.5 LOA Issued 28 0 9 -9

    Total 5.0

    Grand Total: 1.0+2.0+3.0+4.0+5.0

    No ofContracts

    No ofContracts

    No ofContracts

    No ofContracts

    No ofContracts

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    60/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    61/183

    1015.0 15.0 15.0

    2537.5 37.5 37.5

    5075.0 75.0 75.0

    100 150.0 150 150.0100.0 100.0

    50.0 0.0 0.0

    100.0 0.0 0.0

    100.0 0.0 0.0

    250.0 0.0 0.0

    500.0 0.0 0.0

    100 0.0 0 0.0

    0.0 0.0

    5

    12.5 12.5 12.5

    20

    50.0 50.0 50.0

    15

    37.5 37.5 37.5

    1025.0 25.0 25.0

    50

    125.0 125.0 125.0

    100 250.0 250.0 250.0

    100.0 100.0

    900.0 900.0 900.0

    100.0 100.0

    R OPI 2009-10

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    62/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    63/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    64/183

    m - 01/09/09 to 05/10/09

    gress from 01/09/09

    OPI-(00)

    weightage in % MAX. MARKS

    9 10 11 12 13

    515.0 15.0 15.0

    1030.0 30.0 30.0

    1030.0 30.0 30.0

    2575.0 75.0 75.0

    50150.0 146.6 146.6

    100 300 297 296.6

    98.9 98.9

    5

    10.0 10.0 10.010

    20.0 20.0 20.0

    1020.0 20.0 20.0

    2550.0 50.0 50.0

    50100.0 100.0 100.0

    100 200.0 200 200.0

    100.0 100.0

    57.5 7.5 7.5

    1015.0 15.0 15.0

    1015.0 15.0 15.0

    2537.5 37.5 37.5

    FY of O/H: 2009-10.

    ACTUALSCORE

    ACTUALSCORE Cum

    ReviewedScore

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    65/183

    5075.0 75.0 75.0

    100 150.0 150 150.0

    100.0 100.0

    5

    0.0 0.0 0.010

    0.0 0.0 0.0

    100.0 0.0 0.0

    250.0 0.0 0.0

    500.0 0.0 0.0

    100 0.0 0 0.0

    0.0 0.0

    512.5 12.5 12.5

    20

    50.0 50.0 50.0

    15

    37.5 37.5 37.5

    10

    25.0 25.0 25.0

    50

    125.0 125.0 125.0100 250.0 250.0 250.0

    100.0 100.0

    900.0 896.6 896.6

    99.6 99.6

    R OPI 2010-11

    UPDATED ON- 31/07/2009

    8/09/10 (25 days) Boiler+RH modfn+AVR

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    66/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    67/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    68/183

    515.0 15.0 15.0

    1030.0 24.0 10.0

    1030.0 30.0 5.0

    250.0 0.0 8.3

    500.0 0.0 12.5

    100 75 69 50.8

    92.0 16.9

    510.0 10.0 10.0

    1020.0 7.5 4.1

    10

    20.0 5.4 2.025

    50.0 13.0 2.4

    500.0 0.0 38.8

    100 100.0 36 57.1

    35.9 28.6

    57.5 7.5 7.5

    1015.0 10.0 8.1

    1015.0 20.6 6.5

    2537.5 45.0 8.1

    500.0 0.0 12.2

    100 75.0 83 42.4

    110.8 28.2

    50.0 0.0 0.0

    100.0 0.0 0.0

    100.0 0.0 0.0

    250.0 0.0 0.0

    500.0 0.0 0.0

    100 0.0 0 0.0

    0.0 0.0

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    69/183

    5

    12.5 12.5 12.5

    20

    0.0 0.0 35.7

    15

    0.0 0.0 16.1

    10

    0.0 0.0 10.7

    50

    0.0 0.0 40.2

    100 12.5 12.5 115.2

    100.0 46.1

    262.5 200.4 265.5

    76.4 29.5

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    70/183

    14.0 PLANNED MAINTENANCE14.2.1 KEY SPARES & CONTRACTS REQUIRED FOR OH

    UNIT NO.4 OVERHAUL DUE IN FINANCIAL YEAR:-20SPARES (CRITICAL)

    S.NO MAT CODE DESCRIPTION MODE OF

    /DEPT PROCURE

    BMD Received All

    1

    TOTAL 0 0 0

    TMD Received All1

    TOTAL 0 0 0

    EMD Received All

    1

    TOTAL 0 0 0

    C&I Received All

    1

    TOTAL 0 0 0

    AHP Received All

    1TOTAL 0 0 0

    G TOTAL 0 0 0

    SPARES (NON - CRITICAL)S.NO MAT CODE DESCRIPTION MODE OF

    /DEPT PROCURE

    BMD Received All

    1TOTAL 0 0 0

    TMD Received All

    1

    TOTAL 0 0 0

    EMD Received All

    1

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    71/183

    TOTAL 0 0 0

    C&I Received All

    1

    TOTAL 0 0 0

    AHP Received All

    1

    TOTAL 0 0 0

    G TOTAL 0 0 0

    T&PS.NO ITEM CODE DESCRIPTION MODE OF

    /DEPT PROCURE

    BMD

    1TOTAL 0 0 0

    TMD

    1

    TOTAL 0 0 0

    EMD

    1

    TOTAL 0 0 0

    C&I

    1

    TOTAL 0 0 0

    AHP

    1

    TOTAL 0 0 0

    G TOTAL 0 0 0

    CONSUMABLESS.NO ITEM CODE DESCRIPTION MODE OF

    /DEPT PROCURE

    BMD

    TOTAL 0 0 0

    TMD

    1

    TOTAL 0 0 0

    EMD

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    72/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    73/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    74/183

    C&I

    1

    TOTAL 0 0 0

    AHP

    1

    TOTAL 0 0 0

    G TOTAL 4 4 4

    T&PS.NO ITEM CODE DESCRIPTION MODE OF

    /DEPT PROCURE

    BMD

    1

    TOTAL 0 0 0TMD

    1

    TOTAL 0 0 0

    EMD

    1

    TOTAL 0 0 0

    C&I

    1

    TOTAL 0 0 0

    AHP

    1

    TOTAL 0 0 0

    G TOTAL 0 0 0

    CONSUMABLESS.NO ITEM CODE DESCRIPTION MODE OF

    /DEPT PROCURE

    BMD1

    TOTAL 0 0 0

    TMD

    1

    M1012014503

    LTWHITE FUSED

    ALUMINA,SIZE-90 GRIT

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    75/183

    1

    TOTAL 0 0 0

    EMD

    1

    TOTAL 0 0 0

    C&I

    1

    TOTAL 0 0 0

    AHP

    1

    TOTAL 0 0 0

    G TOTAL 0 0 0

    CONTRACTSS.NO DESC MODE OF ESTIM

    /DEPT OF JOB TENDER VALUE

    BMD

    1

    TOTAL 0 0 0

    TMD

    TOTAL 1 1 1

    EMD

    TOTAL 1 1 1

    C&I

    1

    TOTAL 0 0 0

    OFFSITE

    1

    TOTAL 0 0 0

    G TOTAL 2 2 2

    UNIT NO.3 OVERHAUL DUE IN FINANCIAL YEAR:-20

    SPARES (CRITICAL)S.NO MAT CODE DESCRIPTION MODE OF

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    76/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    77/183

    /DEPT PROCURE

    BMD

    1

    TOTAL 0 0 0

    TMD

    1

    TOTAL 0 0 0

    EMD

    1

    TOTAL 0 0 0

    C&I

    1

    TOTAL 0 0 0

    AHP1

    TOTAL 0 0 0

    G TOTAL 0 0 0

    CONSUMABLESS.NO ITEM CODE DESCRIPTION MODE OF

    /DEPT PROCURE

    BMD

    TOTAL 1 1 1

    TMD

    TOTAL 1 1 1

    EMD

    1

    TOTAL 0 0 0

    C&I

    1

    TOTAL 0 0 0

    AHP

    1

    TOTAL 0 0 0

    G TOTAL 2 2 2

    CONTRACTS

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    78/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    79/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    80/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    81/183

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    INITIATION BUDGET REG CLEAR CONC BY FIN

    TARGET ACTUAL CERTIF Y/N TARGET ACTUAL

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    9-10

    PR RAISED REG CLEAR CLEARED BY PI NO ENQUIR

    ACTUAL Y/N SC COMM TARGETTARGET(OPI)

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    82/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    83/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    84/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    85/183

    ACTUAL Y/N SC COMM TARGET

    Minus-18M 100008310 Y Y 100008310 Y

    1 1 1 1 1 1

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    1 1 1 1 1 1

    PR RAISED REG CLEAR CLEARED BY PI NO ENQUIR

    ACTUAL Y/N SC COMM TARGET

    1 1 1 1 1 1

    1 1 1 1 1 1

    0 0 0 0 0 0

    1 1 1 1 1 1

    0 0 0 0 0 0

    3 3 3 3 3 3

    PR RAISED REG CLEAR CLEARED BY PI NO ENQUIR

    TARGET(OPI)

    TARGET(OPI)

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    86/183

    ACTUAL Y/N SC COMM TARGET

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    PR RAISED REG CLEAR CLEARED BY PI NO ENQUIR

    ACTUAL Y/N SC COMM TARGET

    1 1 1 1 1 1

    1 1 1 1 1 1

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    2 2 2 2 2 2

    TARGET(OPI)

    TARGET(OPI)

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    87/183

    INITIATION BUDGET REG CLEAR CONC BY FIN

    TARGET ACTUAL CERTIF Y/N TARGET ACTUAL

    0 0 0 0 0 0

    1 1 1 1 1 1

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    1 1 1 1 1 1

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    88/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    89/183

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    ISSUED BOD TECH PO PLACED ITEM

    ACTUAL SUITABLITY TARGET ACTUAL TARGET

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    ISSUED BOD TECH ITEM RECD

    ACTUAL SUITABLITY TARGET ACTUAL TARGET

    0 0 0 0 1 0

    0 0 0 0 1 0

    PO PLACED

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    90/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    91/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    92/183

    0 0 0 0 0 0

    0 0 0 0 0 0

    4 4 4 4 4 4

    ISSUED BOD TECH PO PLACED ITEM

    ACTUAL SUITABLITY TARGET ACTUAL TARGET

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    ISSUED BOD TECH ITEM RECD

    ACTUAL SUITABLITY TARGET ACTUAL TARGET

    0 0 0 0 0 0

    6000102174 6/24/2009 Y Minus-3M

    PO PLACED

    4000028186/00010

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    93/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    94/183

    ACTUAL SUITABLITY TARGET ACTUAL TARGET

    Y Y Y Minus-12M Minus-3M

    1 1 1 1 1 1

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    1 1 1 1 1 1

    ISSUED BOD TECH PO PLACED ITEM

    ACTUAL SUITABLITY TARGET ACTUAL TARGET

    1 1 1 1 1 1

    1 1 1 1 1 1

    0 0 0 0 0 0

    1 1 1 1 1 1

    0 0 0 0 0 0

    3 3 3 3 3 3

    ISSUED BOD TECH PO PLACED ITEM

    4000012574/001304000016827/00070

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    95/183

    ACTUAL SUITABLITY TARGET ACTUAL TARGET

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    ISSUED BOD TECH ITEM RECD

    ACTUAL SUITABLITY TARGET ACTUAL TARGET

    1 1 1 1 1 1

    1 1 1 1 0 1

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    2 2 2 2 #REF! 2

    PO PLACED

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    96/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    97/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    98/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    99/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    100/183

    BHEL

    DOD 30/06/10 Under despatch

    BHEL (T)

    DOD 30/09/10 Under despatch

    2 2 2

    0 0 0

    0 0 0

    0 0 0

    0 0 0

    2 2 2

    RECD VENDOR REMARKS

    ACTUAL NAME

    BHEL DOD 31/03/10 Under despatch

    BHEL DOD 31/05/10 Under despatch

    2 2 2

    BHEL

    BHEL

    2 2 2

    0 0 0

    Expected by30/09/09

    Expected by30/09/09

    Expected by30/09/09

    Expected by30/09/09

    Expected by30/09/09

    DOD: 05.08.2010 Rem. On27.6.09

    Expected by30/09/09

    DOD: 05.08.2010 Rem. On27.6.10

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    101/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    102/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    103/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    104/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    105/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    106/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    107/183

    5 Contracts for O/H

    5.1 Identification of Contracts 26

    5.2 Contract Proposals initiated 26

    5.3 Tender Issued 26

    5.4 Offer received 26

    5.5 LOA Issued 26

    UNIT - 2 Scheduled from - 26/08/09 to 04/10

    TARGET MATRIX UNIT- 2OPI(-24) OPI-(23) OPI-(22) OPI-(21)

    Sno Activi ty

    Spares procurement

    1 CRITICAL SPARES

    1.1 Total No of Spares identified 40 5 12 15 18

    1.2 Purchase Indents Raised 40 5 12

    1.3 Purchase Enquiry Issued 40 51.4 Purchase Order Placed 40

    1.5 Items recd against PO 40

    2 NON CRITICAL SPARES

    2.1 Total No of Spares identified 193 10 12 12 18

    2.2 Purchase Indents Raised 193 10 12

    2.3 Purchase Enquiry Issued 193 10

    2.4 Purchase Order Placed 193

    2.5 Items recd against PO 193

    3 CONSUMABLES

    3.1 Total No of items identified 323 20 50 80 120

    3.2 Purchase Indents Raised 323 20 50

    3.3 Purchase Enquiry Issued 323

    3.4 Purchase Order Placed 323

    3.5 Items recd against PO 323

    Total QntyExpected/Du

    e for O/H

    CumulativeTarget for this

    OPI

    CumulativeTarget for OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    108/183

    4 T&P

    4.1 Total No of items identified 0 0 0 0 0

    4.2 Purchase Indents Raised 0 0 0 0 0

    4.3 Purchase Enquiry Issued 0 0 0 0 0

    4.4 Purchase Order Placed 0 0 0 0 0

    4.5 Items recd against PO 0 0 0 0 0

    5 Contracts for O/H

    5.1 Identification of Contracts 24

    5.2 Contract Proposals initiated 24

    5.3 Tender Issued 24

    5.4 Offer received 24

    5.5 LOA Issued 24

    UNIT - 3 Scheduled from 11/10/09 to 14/11/09

    TARGET MATRIX UNIT- 3OPI(-24) OPI-(23) OPI-(22) OPI-(21)

    Sno Activi ty

    Spares procurement

    1 CRITICAL SPARES

    1.1 Total No of Spares identified 44 5 10 20 32

    1.2 Purchase Indents Raised 44 5 10

    1.3 Purchase Enquiry Issued 44

    1.4 Purchase Order Placed 44

    1.5 Items recd against PO 44

    2 NON CRITICAL SPARES

    2.1 Total No of Spares identified 276 10 30 50 80

    2.2 Purchase Indents Raised 276 10 30

    2.3 Purchase Enquiry Issued 276

    2.4 Purchase Order Placed 276

    Total QntyExpected/Du

    e for O/H

    CumulativeTarget for this

    OPI

    CumulativeTarget for OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    109/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    110/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    111/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    112/183

    4.2 Purchase Indents Raised 0 0 0 0 0

    4.3 Purchase Enquiry Issued 0 0 0 0 0

    4.4 Purchase Order Placed 0 0 0 0 0

    4.5 Items recd against PO 0 0 0 0 0

    5 Contracts for O/H5.1 Identification of Contracts 28

    5.2 Contract Proposals initiated 28

    5.3 Tender Issued 28

    5.4 Offer received 28

    5.5 LOA Issued 28

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    113/183

    31/08/2009

    H Completed)

    OPI-(20) OPI-(19) OPI-(18) OPI-(15) OPI-(12) OPI-(9) OPI-(08) OPI-(07) OPI-(06) OPI-(05)

    15 20 34 34 34 34 34 34 34 3410 15 20 34 34 34 34 34 34 34

    5 10 15 20 34 34 34 34 34 34

    5 10 15 30 34 34 34 34 34

    6 12 18 24 31 31

    50 100 140 175 200 289 289 289 289 289

    30 40 50 100 140 175 200 289 289 289

    10 30 40 50 100 140 175 200 289 289

    10 30 40 50 100 140 175 200 289

    8 10 14 40 75 120 160 273

    60 105 140 175 190 289 289 289 289 289

    16 34 53 86 148 183 200 289 289 289

    10 30 40 50 100 140 175 200 289 289

    10 30 40 50 100 140 175 200 267

    6 14 18 40 75 120 160 222

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    0 0 0 0 0 0

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for OPI

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    114/183

    12 18 24 26 26 26

    6 18 20 20 24 26

    6 18 22 22 26

    6 18 20 24

    6 12 17

    /09

    OPI-(20) OPI-(19) OPI-(18) OPI-(15) OPI-(12) OPI-(9) OPI-(08) OPI-(07) OPI-(06) OPI-(05)

    20 20 30 30 40 40 40 40 40 40

    15 18 20 20 30 40 40 40 40 40

    10 15 18 20 20 30 40 40 40 405 10 15 18 20 20 30 40 40 40

    6 18 28 32 36 36

    52 86 122 142 193 193 193 193 193 193

    12 18 52 86 122 142 193 193 193 193

    12 12 18 52 86 122 142 193 193 193

    10 12 12 18 52 86 122 142 187 187

    18 52 86 140 168 168

    170 220 250 300 323 323 323 323 323 323

    80 120 170 220 250 323 323 323 323 323

    20 50 80 120 170 220 250 323 323 323

    20 50 80 120 170 220 301 301 301

    20 85 160 220 256 256

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for OPI

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    115/183

    0 0 0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0 0 0

    24 24 24 24 24 24

    15 22 24 24 24 24

    8 15 22 24 24 24

    8 12 18 20 20

    8 12 16 16

    OPI-(20) OPI-(19) OPI-(18) OPI-(15) OPI-(12) OPI-(9) OPI-(08) OPI-(07) OPI-(06) OPI-(8)

    38 38 40 40 44 44 44 44 44 44

    20 32 38 38 40 40 44 44 44 44

    5 10 20 32 38 38 40 40 44 44

    5 10 15 18 22 28 30 35 38

    15 18 22 28 33 33

    150 180 222 240 276 276 276 276 276 276

    50 80 150 180 222 240 276 276 276 276

    10 30 50 80 150 180 222 240 276 276

    30 50 80 150 180 222 240 268

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for OPI

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    116/183

    30 50 80 150 180 244

    140 180 205 228 282 282 282 282 282 282

    25 40 75 140 180 205 228 282 282 28210 25 40 75 140 180 205 228 282 282

    10 25 40 75 140 180 205 228 276

    30 75 90 140 220 238

    0 0 0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0 0 0

    12 15 18 25 27 27

    5 8 12 15 18 25

    5 8 12 15 18

    5 8 12 15

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    117/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    118/183

    5 8 11 11

    5 8 11

    /10

    OPI-(20) OPI-(19) OPI-(18) OPI-(15) OPI-(12) OPI-(9) OPI-(08) OPI-(07) OPI-(06) OPI-(05)

    25 30 36 36 36 36 36 36 36 36

    10 15 20 25 30 36 36 36

    4 6 10 15 20 25 30 36 36 36

    6 10 15 20 25 30 36

    6 10 15 20 20 25

    200 276 276 276 276 276 276 276 276 276

    15 50 100 150 200 276 276 276 276 276

    6 15 50 100 150 200 276 276 276 276

    15 50 100 150 200 276 276 276

    15 50 100 150 180 200

    100 111 111 111 111 111 111 111 111 111

    20 35 80 90 100 111 111 111 111 111

    28 20 35 80 90 100 111 111 111

    20 35 80 90 100 111 111

    20 35 50 80 80 90

    0 0 0 0 0 0 0 0 0 0

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for OPI

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    119/183

    0 0 0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0 0 0

    28 28 28 28 28 28

    28 28 28 28 28

    28 28 28 28 28

    20 24 28 28

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    120/183

    OPI-(04) OPI-(03) OPI-(02) OPI-(01) OPI-(00)

    34 34 34 34 3434 34 34 34 34

    34 34 34 34 34

    34 34 34 34 34

    31 34 34 34 34

    289 289 289 289 289

    289 289 289 289 289

    289 289 289 289 289

    289 289 289 289 289

    285 289 289 289 289

    289 289 289 289 289

    289 289 289 289 289

    289 289 289 289 289

    289 289 289 289 289

    222 289 289 289 289

    0 0 0 0 0

    0 0 0 0 0

    0 0 0 0 0

    0 0 0 0 0

    0 0 0 0 0

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    121/183

    26 26 26 26 26

    26 26 26 26 26

    26 26 26 26 26

    26 26 26 26 26

    17 26 26 26 26

    OPI-(04) OPI-(03) OPI-(02) OPI-(01) OPI-(00)

    40 40 40 40 40

    40 40 40 40 40

    40 40 40 40 4040 40 40 40 40

    36 40 40 40 40

    193 193 193 193 193

    193 193 193 193 193

    193 193 193 193 193

    193 193 193 193 193

    168 193 193 193 193

    323 323 323 323 323

    323 323 323 323 323

    323 323 323 323 323

    323 323 323 323 323

    256 323 323 323 323

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    122/183

    0 0 0 0 0

    0 0 0 0 0

    0 0 0 0 0

    0 0 0 0 0

    0 0 0 0 0

    24 24 24 24 24

    24 24 24 24 24

    24 24 24 24 24

    24 24 24 24 24

    16 24 24 24 24

    OPI-(7) OPI-(6) OPI-(5) OPI-(4) OPI-(3) OPI-(2) OPI-(1) OPI-(00)

    44 44 44 44 44 44 44 44

    44 44 44 44 44 44 44 44

    44 44 44 44 44 44 44 44

    38 38 38 44 44 44 44 44

    33 33 33 38 44 44 44 44

    276 276 276 276 276 276 276 276

    276 276 276 276 276 276 276 276

    276 276 276 276 276 276 276 276

    268 268 268 276 276 276 276 276

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for OPI

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    123/183

    244 244 244 268 276 276 276 276

    282 282 282 282 282 282 282 282

    282 282 282 282 282 282 282 282282 282 282 282 282 282 282 282

    276 276 276 282 282 282 282 282

    238 238 238 276 282 282 282 282

    0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0 0

    27 27 27 27 27 27 27 27

    27 27 27 27 27 27 27 27

    25 27 27 27 27 27 27 27

    18 25 27 27 27 27 27 27

    5 8 12 18 23 27 27 27

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    124/183

    OPI-(04) OPI-(03) OPI-(02) OPI-(01) OPI-(00)

    28 28 28 28 28

    28 28 28 28 28

    28 28 28 28 28

    28 28 28 28 28

    28 28 28 28 28

    476 476 476 476 476

    476 476 476 476 476

    476 476 476 476 476

    476 476 476 476 476

    125 476 476 476 476

    120 120 120 120 120

    120 120 120 120 120120 120 120 120 120

    120 120 120 120 120

    120 120 120 120 120

    0 0 0 0 0

    0 0 0 0 0

    0 0 0 0 0

    0 0 0 0 0

    0 0 0 0 0

    21 21 21 21 21

    21 21 21 21 21

    21 21 21 21 21

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    125/183

    21 21 21 21 21

    11 21 21 21 21

    OPI-(04) OPI-(03) OPI-(02) OPI-(01) OPI-(00)

    36 36 36 36 36

    36 36 36 36 36

    36 36 36 36 36

    36 36 36 36 36

    25 30 36 36 36

    276 276 276 276 276

    276 276 276 276 276

    276 276 276 276 276

    276 276 276 276 276

    200 276 276 276 276

    111 111 111 111 111

    111 111 111 111 111

    111 111 111 111 111

    111 111 111 111 111

    95 100 111 111 111

    0 0 0 0 0

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

    CumulativeTarget for

    OPI

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    126/183

    0 0 0 0 0

    0 0 0 0 0

    0 0 0 0 0

    0 0 0 0 0

    28 28 28 28 28

    28 28 28 28 28

    28 28 28 28 28

    28 28 28 28 28

    28 28 28

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    127/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    128/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    129/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    130/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    131/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    132/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    133/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    134/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    135/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    136/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    137/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    138/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    139/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    140/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    141/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    142/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    143/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    144/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    145/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    146/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    147/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    148/183

    14.0 PLANNED MAINTENANCE

    Contents:

    14.3 ORT Summary Sheet-OPI Summ

    Station:. , ORT Month: held on, FY of O/H: Current Year/Next Year/Next to Nex

    Unit-1 Unit-2 Un

    Due Start Date of O/H

    Duration (Days)

    O/H Type

    Activity/OPI No OPI- 03 M OPI-

    Max Actual Max

    Marks Score Marks

    Part-A As per Format A

    1240 239 240

    2 O/H Scope of Work(4+5+6) 180 180 180

    330 30 30

    4 Quality O/H/Commissioning (12+13) 50 50 50

    Total Part-A 500 499 500

    100%

    Part-B As per Format B

    5 Spares 500 494.0 500

    6 General Consumables 150 150 150

    7 T&Ps 100 100 100

    8 Contracts for O/H 250 250 250

    Total Part-B 1000 994 1000

    99%

    Grand Total 1500 1493 1500

    100%

    Spares/Contracts Brief status Total Act Total

    Due Qty Due

    Spares No of items received till this OPI 233 227 458

    No of Indents matured into receipt

    CONTENTS

    14.3 OPI SUMMARY SHEET

    Engg Decl Submission/O/H Proposal(1+2+3+8+9+10+11)

    Incorporation of comments/advice fromCOS/ROS in Engg Decl/ SOW (7)

    http://191.254.11.230/mail/707201.nsf/38d46bf5e8f08834852564b500129b2c/b6ad0bd0c6b1d02965257164003fc08f/$FILE/EEMG-1%20(MOU-ABT-PERF-AVF-PL-OUTAGE).xlshttp://191.254.11.230/mail/707201.nsf/38d46bf5e8f08834852564b500129b2c/b6ad0bd0c6b1d02965257164003fc08f/$FILE/EEMG-1%20(MOU-ABT-PERF-AVF-PL-OUTAGE).xls
  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    149/183

    Contracts No of Contracts for O/H Awarded29 29 30

    Exception/Major Shortfall:

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    150/183

    Date- 31/08/2009

    ry for ORT

    ORT Month: Financial Year of O/H:

    t-3 Unit-4 Unit-5 Unit-6 Unit-7 Unit-8

    04 M OPI- 00 M OPI- OPI- OPI-

    Actual Max Actual Max Actual Max Actual Max Actual

    Score Marks Score Marks Score Marks Score Marks Score

    240 240 240

    180 180 180

    30 30 30

    50 50 50

    500 500 500

    100% 100%

    497 500 500

    150 150 150

    100 100 100

    250 250 250

    997 1000 1000

    100% 100%

    1497 1500 1500

    100% 100%

    Act Total Act Total Act Total Act Total Act

    Qty Due Qty Due Qty Qty Qty Qty Qty

    457 323 323

    Click togo to

    Contents

    Click togo to

    Contents

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    151/183

    30 30 30

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    152/183

    Unit-9 Unit-10 Unit-11 Unit-12

    OPI- OPI- OPI- OPI-

    Max Actual Max Actual Max Actual Max Actual

    Marks Score Marks Score Marks Score Marks Score

    Total Act Total Act Total Act Total Act

    Qty Qty Qty Qty Qty Qty Qty Qty

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    153/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    154/183

    14.0 PLANNED MAINTENANCE

    14.4 MONTHLY EXCEPTION REPORT

    Overhaul Preparedness In

    Station Monthly Exception report

    Overhaul: for FY 2008-09 Sample Sheet

    A) Resource (Material & Contract) Exceptions

    4 Materials Contracts Material Contracts Materials

    1 Indent raisingBMD 0 0 0 0 0

    TMD 0 0 0 0 0

    EMD 0 0 0 0 0

    C&I 0 0 0 0 0

    Offsite Mtnc 0 0 0 0 0

    LTP - MTP 0 0 0 0 0

    C&M 0 0 0 0 0

    O&M 0 0 0 0 0

    PO placement 0 0 0 8 0

    0 0 0 0 0

    0 0 0 0 0

    Negotiations 0 0 4 0 0

    TC 0 0 0 0 0

    Vendor 0 0 0 0 0

    Retendering 0 0 0 0 0

    UnitNo.

    ActivityPending wrtTarget Matrix

    Pending for currentOPI

    Pending sinceprevious OPI Review(more than 1 Month

    of Target)

    Pendinprevious(more tha

    of T

    Issue ofenquiry

    pending

    Non receipt ofbid

    TechnicalEvaluation

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    155/183

    0 0 10 8 22

    B) No. of pending items

    R0 0 0

    R1 0 0

    R2 0 0

    Others: 0 0

    A) Resource (Material & Contract) Exceptions

    Materials Contracts Material Contracts Materials

    2 Indent raising

    BMD 0 0 0 0 0

    TMD 0 0 0 0 0

    EMD 0 0 0 0 0

    C&I 0 0 0 0 0

    Offsite Mtnc 0 0 0 0 0

    LTP - MTP 0 0 0 0 0

    C&M 0 0 0 0 0

    O&M 0 0 0 0 0

    PO placement 0 0 0 0 16

    Receipt ofmaterial

    OPI - PART A

    Exceptions

    Pending since

    previous OPI Review(more than 1 Month

    of Target)

    Pendin

    previous(more tha

    of T

    Engg DeclarationSubmission

    UnitNo.

    ActivityPending wrtTarget Matrix

    Pending for currentOPI

    Pending sinceprevious OPI Review(more than 1 Month

    of Target)

    Pendinprevious(more tha

    of T

    Issue of

    enquirypending

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    156/183

    0 1 0 2 0

    0 0 0 0 7

    Negotiations 0 0 0 0 0

    TC 0 0 0 2 0Vendor 0 0 0 0 0

    Retendering 0 0 0 0 0

    6 0 7 2 16

    B) No. of pending items

    R0 0 0

    R1 0 0

    R2 0 0

    Others: 0 0

    A) Resource (Material & Contract) Exceptions

    Materials Contracts Material Contracts Materials

    3 Indent raising

    BMD 0 0 0 0 0

    TMD 0 0 0 0 0

    EMD 0 0 0 0 0

    C&I 0 0 0 0 0

    Offsite Mtnc 0 0 0 0 0

    Non receipt ofbid

    TechnicalEvaluation

    Receipt ofmaterial

    OPI - PART A

    Exceptions

    Pending since

    previous OPI Review(more than 1 Month

    of Target)

    Pendin

    previous(more tha

    of T

    Engg DeclarationSubmission

    UnitNo.

    ActivityPending wrtTarget Matrix

    Pending for currentOPI

    Pending sinceprevious OPI Review(more than 1 Month

    of Target)

    Pendinprevious(more tha

    of T

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    157/183

    LTP - MTP 0 0 0 0 0

    C&M 0 0 0 0 0

    O&M 0 0 0 0 0

    PO placement 0 0 10 11 13

    0 2 0 2 0

    6 0 9 0 13

    Negotiations 0 0 0 0 0

    TC 0 0 0 0 0

    Vendor 0 0 0 0 0

    Retendering 0 0 0 0 0

    1 0 68 4 76

    B) No. of pending items

    R0 0 0

    R1 0 0

    R2 0 0

    Others: 0 0

    C) OPI ScoresOPI no. Score Scores a

    Current - 1 Current - 2 Current - 3

    4 Part A 100 99.6

    Issue ofenquirypending

    Non receipt ofbid

    TechnicalEvaluation

    Receipt ofmaterial

    OPI - PART AExceptions

    Pending sinceprevious OPI Review

    (more than 1 Monthof Target)

    Pendinprevious

    (more thaof T

    Engg DeclarationSubmission

    Unitno.

    Current OPIscore(in %)

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    158/183

    OPI-00100 95

    100 90

    2

    OPI-01

    Part A 99.5 99.5

    99 99

    98.9 98.9

    3

    OPI-02

    Part A 100 99

    100 97

    100 96.5

    D) Issue details

    GM Station NilED Region Nil

    ED OS Nil

    Nil

    Part Bmonthly

    Part Bcumulative

    Part B

    monthlyPart Bcumulative

    Part Bmonthly

    Part Bcumulative

    FlaggedIssues

    DirectorOperations

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    159/183

    Date- 31/08/2009

    dex (OPI)

    Remarks

    Contracts

    0

    0

    0

    0

    0

    0

    0

    0

    9

    0

    0

    0

    0

    0

    0

    beforePI Review2 Months

    rget)

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    160/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    161/183

    2

    0

    0

    00

    0

    7

    Remarks

    Engg. Declaration R-0 sent to OS

    Engg. Declaration R-0 sent to OS

    Engg. Declaration R-0 sent to OS

    Engg. Declaration R-0 sent to OS

    Remarks

    Contracts

    0

    0

    0

    0

    0

    before

    PI Review2 Months

    rget)

    beforePI Review2 Months

    rget)

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    162/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    163/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    164/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    165/183

    1 Type of Overhaul

    2 Duration 47

    3 Spare Cost + Consumable Cost 5,01

    4 Contract Cost 4,15

    5 Total Cost

    14.9 MAJOR (CAPITAL) SPARES CONSUMED (Recently completed Overhauls

    14.10 PLANNED MAINTENANCE ROLLING PLAN FOR 8 YE

    YEAR UNIT-I UNIT-2

    Schedule S

    2005-06 Boiler Boiler Lic. Renewal

    2006-07 Boiler

    2007-08 Capital

    Rs.9,1

    Rs.17,08,7

    Type ofOH

    Type ofOH

    21-09-0508-10-05

    04-11-05

    17/01/0722/01/07

    03-06-07

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    166/183

    16.7 STRUCTURE CHECKING:

    AREA TG Hall Boiler ESP CHP AHP

    8/18/2008 Dec.-08 Jul-09 Jun-08 Jul-09

    Y Y Y Y Y

    NA NA NA NA NA

    01 year 01 year 01 year 01 year 01 year

    Aug-09 Dec.-09 Jul-10 Jun-09 Jul-10

    Note: ORT Co-ordinator is to affix the relevant Reports along with Action

    16.8 MACHINE FOUNDATIONS:

    Area TG CHP AHP

    Aug-09 Apr-09 Jun-09

    Y Y Y Y Y

    NA NA NA NA NA

    06 Months 06 Months 06 Months 06 Months 06 Months

    Feb-10 Sept.-09 Dec.-09

    Note: ORT Co-ordinator is to affix the relevant Reports along with Action

    16.9 CHIMNEY INSPECTION:

    Last date ofchecking structuresas per Guidelines

    Compliance ofobservationscompleted (Y/N)

    Action Plan for thePendingObservations

    Freq. ofchecking

    Next dateof checking

    Fans,Mills etc. In Blr.

    CompressorHouse

    Last date ofchecking as perguidelines includingspring loadedfoundations

    Stg-I, Stg-II& Stg-IIIMay-09

    Stg-I, Stg-II& Stg-IIIMay-09

    Compliance ofobservationscompleted (Y/N)

    Action Plan for thePendingObservations

    Freq. Ofchecking

    Next date ofchecking

    Stg-I, Stg-II& Stg-IIINov-09

    Stg-I, Stg-II& Stg-IIINov-09

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    167/183

    Unit No. Major Observations

    1 01/10/2002

    201/10/2002

    310/19/2007

    410/19/2007

    5 21/11/2008

    6

    7

    8

    9

    10

    11

    12

    Note: ORT Co-ordinator is to affix the relevant Reports along with Action

    16.10 PAINTING OF STRUCTURES:

    Area TG Hall Boiler ESP CHP

    July'02 May'03 2003 Mar.'04

    Rolling plan for painting of the structure of FGUTPP

    Sl. Description 2005-06 2006-07 2007-08

    PT Plant

    Lastdate of

    checking

    Bunkers& Mill Bay

    Last dateof painting done

    PatiallyDone, in

    06-07

    Frequencyof Painting (year)

    As perrequiremen

    t

    As perrequirement

    As perrequireme

    nt

    As perrequiremen

    t

    As perrequirement

    Next dateof painting

    5 yrsrolling planas under

    covering all

    thestructures.

    5 yrs rollingplan as undercovering all the

    structures.

    Balancein 08-09

    5 yrsrolling planas undercovering

    all thestructures.

    5 yrs rollingplan asunder

    covering all

    thestructures.

    1.Completed

    May-06

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    168/183

    DM Plant

    Trestles

    DG + Compressor house

    ESP + AHP (I)

    ESP + AHP (II)

    Bal CHP-I

    CHP-II

    Boiler I

    Boiler II

    TG Hall I

    TG Hall II

    2.Completed

    May-06

    3.Completed

    May-07

    4.

    5.

    Completed

    6.

    in progresscompleted

    byJune.'2008

    7.

    8.

    9.

    10. PartiallyCompleted

    11. PartiallyCompleted

    12. ESP + AHP + Compressorhouse (TAC)-(II)

    13. Balance of plant (CW, CT,Chem. plant etc.)- I

    14. Balance of plant (CW, CT,Ch. plant etc.)- II

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    169/183

    Date- 31/08/2009

    Bunkers

    Dec.-08 3/31/2009 3/31/2009 10/10/2008

    Y Y Y Y

    NA NA NA NA

    01 year 01 year 01 year 01 year

    Dec.-09 Mar-10 Mar-10 Oct'09

    lan

    Oil Tanks

    Jun-09 Mar-09

    Y Y

    NA NA

    06 Months 06 Months

    Dec.-09 Sep-09

    lan

    DM

    Plant

    CW

    P/ H

    CompHouse

    (St-I to III)

    DMPlant & DMTank

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    170/183

    Proposed Action

    01/10/2003

    01/10/2003

    10/19/2008

    10/19/2008

    21/11/2009

    lan

    AHP

    2005-2006 2005-2006 Dec'07

    2008-09 2009-10 Remarks

    OFS

    Next dateof checking

    Frequencyof checking

    Stage S/DOpportunity

    Stage S/DOpportunity

    Stage S/DOpportunity

    Stage S/DOpportunity

    DMPlant CWPH CompressorHouse

    Patially Done,in 06-07

    As perrequirement

    As perrequirement

    As perrequirement

    As perrequirement

    Balance in08-09

    5 yrs rollingplan as undercovering all the

    structures.

    5 yrs rollingplan as undercovering all the

    structures.

    5 yrs rollingplan asunder

    covering all

    thestructures.

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    171/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    172/183

    15.0 MAINTENANCE MANAGEMENT SYSTEM

    Contents:

    15.1 ANURAKSHNAN SYSTEM: SYSTE

    15.2 EQUIPMENTS NOT AVAILABLE FOR MORE THAN 15 DAYS:DATA AVAILA

    15.3 EQUIPMENTS WHERE REPEATED FAILURES OCCURRED (CURR

    15.4 MAJOR EQUIPMENTS HAVING HIGH VIBRATIONS:DATA AVAILA

    15.5 WOC QUANTITATIVE ANALYSIS: DATA AVAILA

    15.2 EQUIPMENTS NOT AVAILABLE FOR MORE THAN 15 D

    Unit Out since (date)

    CHP S/R-2 (St-II) 8/9/2007

    CHP RB-4. 5/8/2008 High vibration.

    CHP RB-1. 5/1/2008

    CHP Pay loader-13116 9/15/2008

    Note *: Includes the equipments of Main plant, Offsite, CHP, MGR and DM Plant

    15.3 EQUIPMENTS WHERE REPEATED FAILURES OCCURRED (CURRENT FY):

    Unit Equipment Name No. of failures with Details Reason

    AHD-2 Ash Slurry Pump-4 amming, inoperative lve erod

    Equipment Name*

    Reason for non-availability

    Slew bearing notavailable.

    Major over hauling& replacement.

    Under B/D ( sparesnot available)

    09/04/2009&18/04/2009.

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    173/183

    OFS-1 CW Pump-6 Gauge c

    CHP-1 FG-8.

    Unit-1. Generator AVR Sy

    Brushes worn out.

    CHP-2

    S/C-5. High vibration.

    CHP-3

    S/C-3.

    15.4 MAJOR EQUIPMENTS HAVING HIGH VIBRATIONS:

    Unit Equipment Name Date of Measurem Measurement Point Monitorin

    8/1/2009 MOTOR NDE mm/s

    3 TURBINE 8/24/2009 mm/s

    4 TURBINE 8/24/2009 mm/s

    5 BFP-C 8/28/2009 Main Pump-DE mm/s

    07/04/2009,

    16/04/2009

    &24/04/2009

    Tripping on

    discharge valve fail,

    motor DE brg temp

    erratic.01/04/2009

    &05/04/2009

    Flap gate stuck up/

    inoperative.

    FG-8 to

    Conv-

    11

    beam

    broken.

    02/04/2009,

    15/04/2009,

    22/04/2009

    Short

    length

    of

    brush.23/06/2009,

    17/06/2009

    Teeths

    worn

    out.

    03/06/2009

    10/06/2009

    02/07/2009

    16/07/2009

    High vibration.

    Scoop tube control

    machanism jam.

    Teeths

    worn

    out.

    FAN

    LPT rear (BrgNo-4)

    LPT rear (BrgNo-4)

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    174/183

    * Please mention details like Overall vel/Displacement,Spike energy-gSE ,mm/sec pk, mic

    15.5 WOC QUANTITATIVE ANALYSIS:

    Section Break Down Maint. (BD) Preventive Maint.

    Raised (No.) Attended (No.) Raised (No.) ended (BM-PP 88 80 0 0

    BM-RM 4 1 165 112

    TM 67 59 231 222

    BoP 214 175 642 622

    373 315 1038 956

    79 68 371 281EM 140 117 569 448

    0 0 0 0

    C&I 145 111 161 145

    Civil 1 0 0 0

    Total 738 611 2139 1830

    15.6 STATUS OF CRITICAL SPARES AFFECTING ROUTINE PERFORMANCE OF UNI

    ITEMS Avg.Monthly Stock PIPE L

    consumption

    Mill Spares

    4+2Sets 27+2

    4+2Sets 22+5

    MM(Total)

    MM

    (CHP)

    EM(CHP)

    Indent

    Grinding Roll

    St.I+IIIBull ringsegmentsSt.I+III

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    175/183

    120T 160

    CHP

    2+8 sets 2+5

    Conv Belt 500m 100m

    OFF SITE

    MGR Nil

    WTP/ETP Nil

    Turbine

    8000 ltr 10430 ltr

    **NOTE : STATION SHOULD IDENTIFY THE LIST OF SPARES AND MONITOR**NOTE : STATION SHOULD IDENTIFY THE LIST OF SPAR

    GrindingBalls Stg-II

    Ash handling

    Crusherhemmer St-I+II.

    Lube oil -SP-46

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    176/183

    Date- 31/08/2009

    IS NOT BEING USED

    BLE IN ERP (SAP) - ORTOPN2

    ENT FY):

    BLE IN ERP (SAP) - ORTOPN2

    BLE IN ERP (SAP) - ORTOPN2

    YS:

    Action Plan Present status

    DGM(C&M)

    PO Placed. DGM(FM)

    PO placed. DGM(FM)

    DGM(FM)

    Action Plan Target Date Present status

    d. DGM (AMG) Available.

    Responsibility

    TargetDate

    Abnormal sound inslew bearing. POPlaced.

    Slew systemnot available.

    Emergencyavailable.

    Equipmentoutage.

    Pay loader sent

    BEML servicecentre Singrauli on24/09/08 for O/H.LOI issued. To beexpected by 15Sept 2009. Equipment

    outage.

    Responsibility

    09/04/2009&19/04/2009

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    177/183

    alibration required. DGM (C&I) Available.

    DGM (CHP) Available.

    DGM (EMD) Available.

    DGM(CHP)

    6/25/2009

    Available.

    DGM(CHP) Available.

    Parameter Value Limit Action Plan Target Date Present st

    A-10.90 6.5mm/sA-38.10 24 mm/s

    A-64.30 24 mm/s

    HOR-18.10 16mm/s

    09/04/200

    9,

    16/04/200

    9 &

    06/05/200

    902/04/200

    9

    &12/04/2

    009

    02/04/200

    9,

    16/04/200

    9,

    23/04/200

    9

    10/06/200

    9

    10/06/200

    9

    03/07/200

    9

    16/07/200

    9

    Responsibility

    Available.

    Available.

    Available.

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    178/183

    on pp,1*RPM,2*RPM etc.

    Condition Based Maint. (CBM) Total

    Raised (No.) Attended (No. aised (No Attended (No.)0 0 88 80

    0 0 169 113

    0 0 298 281

    0 0 856 797

    0 0 1411 1271

    0 0 450 349 16 14 725 579

    0 0 0 0

    0 0 306 256

    0 0 1 0

    16 14 2893 2455

    S

    INE QUANTITY

    Enquiry PO

    St-III for

    12 sets.St-III for

    12 sets.

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    179/183

    20sets

    6km.

    HE STATUSES AND MONITOR THE STATUS

    250T- part

    delivery.

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    180/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    181/183

    atus

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    182/183

  • 7/27/2019 Opi-overhauling & Maint. Mgmt

    183/183