Opi-overhauling & Maint. Mgmt
Transcript of Opi-overhauling & Maint. Mgmt
-
7/27/2019 Opi-overhauling & Maint. Mgmt
1/183
FGUTPP
OUTAGE PREPAREDNESS INDEX (OPI-00) for Fin. Yea
(Target cum Monitoring sheet-Part-A)
Station : Unchahar Scheduled from - 25/05/09 to 13/06/09
OH Completed from - 25/05/09 to 15/06/
Unit: 4 Type of O/H : BOILER O
S. No. Activity / Description Max Months Before O/HMarks 24 18 12 6
01.0 Formation of Outage Committee 20 * 20
02.0 30
03.0 30 * 20 * 05 * 05
04.0 100 * 60 * 20 * 20
Boiler & Aux.
Steam Turbine Aux.
Turbo Generator Aux. Electrical
Control & Instrumentation
Miscellaneous
05.0 50 * 30 * 10 * 10
BTL reduction plan
APH efficiency revival plan
Turbine efficiency plan
Condenser tube replacement
Obsolescence (R&M for DAS)
06.0 30 * 30
07.0 30 * 10 * 10 * 10
08.0 Resource Analysis 50 * 30 * 10 *10Spares & Material identification
Contracts identification
Procurement status
Contract Award
09.0 Estimated Budget Requirement 30 * 10 * 10 * 10
10.0 PERT & Bar Charts 30 * 10 * 10 * 10
Engineering Declarationsubmission in required format(Revision No.-3) Overhaul Date(Proposed)
*R020
*R105
*R205
Outage period & duration:justification of outage duration &time period
Identification of Equipments &Scope of Work for Overhaul.Standard Scope of work
Plant betterment Action Plan(AI/RI/EI/TO/LF) Examples
Defects/Shutdown/Pending PMJobs included in Scope
Incorporation ofrecommendations / comments ofKTs/COS/RHQ-OS
-
7/27/2019 Opi-overhauling & Maint. Mgmt
2/183
11.0 QCP Readiness 50 * 30 * 10 * 10
Number of QCP identified
Number of QCP prepared (%)
12.0 20 * 20
13.0 30 * 20 * 10
Number of RCS idintified
Number of RCS prepared (%)
Total of applicable activities500 200 110 110 80
OUTAGE PREPAREDNESS INDEX (OPI- 01 ) for Fin. Ye
(Target cum Monitoring sheet-Part-A)Station : Unchahar Scheduled from - 06/10/09 to 14/11/09
Unit: 2 Type of O/H : BOILER + R&M WORK LIKE- DDCMIS +U
S. No. Activity / Description Max Months Before O/H
Marks
24 (R0) 18 (R1) 12 (2) 6
01.0 Formation of Outage Committee 20 20
02.0 30 20 5 5
03.0 30 20 5 5
04.0 100 60 20 20
Boiler & Aux.
Steam Turbine Aux.
Turbo Generator Aux. & Electrical
Control & Instrumentation
Miscellaneous
05.0 50 30 10 10
BTL reduction plan
Isolation Plan readinessChecking of tools
Re-commissioning ChecksSheets (RCS) Readiness :
Engineering Declaration
submission in required format(Revision No.-3) Overhaul Date(Proposed)
Outage period & duration:justification of outage duration &time period
Identification of Equipments &Scope of Work for Overhaul.Standard Scope of work
Plant betterment Action Plan(AI/RI/EI/TO/LF) Examples
-
7/27/2019 Opi-overhauling & Maint. Mgmt
3/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
4/183
02.0 30 20 5 5
03.0 30 20 5 5
04.0 100 60 20 20
Boiler & Aux.
Steam Turbine Aux.
Turbo Generator Aux. & Electrical
Control & Instrumentation
Miscellaneous
05.0 50 30 10 10
BTL reduction planAPH efficiency revival plan
Turbine efficiency plan
Condenser tube replacement
Obsolescence (R&M for DAS)
06.0 30 30
07.0 30 10 10 10
08.0 Resource Analysis 50 30 10 10
Spares & Material identification
Contracts identificationProcurement status
Contract Award
09.0 Estimated Budget Requirement 30 10 10 10
10.0 PERT & Bar Charts 30 10 10 10
11.0 QCP Readiness 50 30 10 10
Number of QCP identified
Number of QCP prepared (%)
12.0 20 20
13.0 30 20 10
Number of RCS idintified
Number of RCS prepared (%)
Total of applicable activities 500 200 110 110 80
Engineering Declarationsubmission in required format(Revision No.-3) Overhaul Date(Proposed)
Outage period & duration:justification of outage duration &
time periodIdentification of Equipments &Scope of Work for Overhaul.Standard Scope of work
Plant betterment Action Plan(AI/RI/EI/TO/LF) Examples
Defects/Shutdown/Pending PMJobs included in Scope
Incorporation ofrecommendations / comments ofKTs/COS/RHQ-OS
Isolation Plan readinessChecking of tools
Re-commissioning ChecksSheets (RCS) Readiness :
-
7/27/2019 Opi-overhauling & Maint. Mgmt
5/183
OUTAGE PREPAREDNESS INDEX (OPI-11) for Fin. Yea
(Target cum Monitoring sheet-Part-A)
Station : Unchahar Scheduled from - 25/08/10 to 18/09/10
Unit: 1 Type of O/H : BOILER
Max Months Before O/HS. No. Activity / Description Marks 24 (R0) 18 (R1) 12 (2) 6
01.0 Formation of Outage Committee 20 20
02.0 30 20 5 5
03.0 30 20 5 5
04.0 100 60 20 20
Boiler & Aux.
Steam Turbine Aux.
Turbo Generator Aux. Electrical
Control & Instrumentation
Miscellaneous
05.0 50 30 10 10
BTL reduction plan
APH efficiency revival plan
Turbine efficiency planCondenser tube replacement
Obsolescence (R&M for DAS)
06.0 30
07.0 30 10 10 10
08.0 Resource Analysis 50 30 10 8
Spares & Material identification
Contracts identification
Procurement status
Contract Award09.0 Estimated Budget Requirement 30 10 10 10
10.0 PERT & Bar Charts 30 10 10
11.0 QCP Readiness 50 30 30
Number of QCP identified
Number of QCP prepared (%)
12.0 20
Engineering Declarationsubmission in required format(Revision No.-3) Overhaul Date(Proposed)
Outage period & duration:justification of outage duration &time period
Identification of Equipments &
Scope of Work for Overhaul.Standard Scope of work
Plant betterment Action Plan(AI/RI/EI/TO/LF) Examples
Defects/Shutdown/Pending PMJobs included in Scope
Incorporation ofrecommendations / comments ofKTs/COS/RHQ-OS
Isolation Plan readinessChecking of tools
-
7/27/2019 Opi-overhauling & Maint. Mgmt
6/183
13.0 30
Number of RCS idintified
Number of RCS prepared (%)
Total of applicable activities 500 200 110 108 0
OUTAGE PREPAREDNESS INDEX (OPI-13) for Fin. Yea
(Target cum Monitoring sheet-Part-A)
Station : Unchahar Scheduled from - 20/10/10 to 13/11/10
Unit: 5 Type of O/H : OH of LP turbine & Boiler
Max Months Before O/H
S. No. Activity / Description Marks 24 (R0) 18 (R1) 12 6
01.0 Formation of Outage Committee 20 20
02.0 30 20 5
03.0 30 20 5
04.0 100 60 20
Boiler & Aux.
Steam Turbine Aux.Turbo Generator Aux. & Electrical
Control & Instrumentation
Miscellaneous
05.0 50 30 10
BTL reduction plan
APH efficiency revival plan
Turbine efficiency plan
Condenser tube replacement
Obsolescence (R&M for DAS)06.0 30
07.0 30 10 10
08.0 Resource Analysis 50 30 10
Spares & Material identification
Contracts identification
Re-commissioning ChecksSheets (RCS) Readiness :
Engineering Declaration
submission in required format(Revision No.-3) Overhaul Date(Proposed)
Outage period & duration:justification of outage duration &time period
Identification of Equipments &Scope of Work for Overhaul.Standard Scope of work
Plant betterment Action Plan(AI/RI/EI/TO/LF) Examples
Defects/Shutdown/Pending PMJobs included in Scope
Incorporation ofrecommendations / comments ofKTs/COS/RHQ-OS
-
7/27/2019 Opi-overhauling & Maint. Mgmt
7/183
Procurement status
Contract Award
09.0 Estimated Budget Requirement 30 10 10
10.0 PERT & Bar Charts 30 10
11.0 QCP Readiness 50 30
Number of QCP identifiedNumber of QCP prepared (%)
12.0 Isolation Plan readiness 20
13.0 30
Number of RCS idintified
Number of RCS prepared (%)
Total of applicable activities 500 200 110
Re-commissioning ChecksSheets (RCS) Readiness :
-
7/27/2019 Opi-overhauling & Maint. Mgmt
8/183
UNCHAHAR
r:-2009-10
Date- 31/08/2009
9ERHAUL
OPI-Remarks
Formed
Submitted.
Provided
As per part-B
Done
* Boiler & boiler aux.* Turbine aux.
* Generator aux.* Electrical system.
* Control & Instrumentationsystem.
* Mill liner replacement of Mill 4AB* Material Mix-up & thickness survey
of critical TG pipings, drains & bends.* Mounting of
thermocouples for monitoring highenergy drains passing with alarm inUCB. *TGBearing-4 bearing inspection/ repair
Pending defect list being updatedregularly. Available on line.
Recommendations incorporated in O/Hscope ot work.
Provided with Engg declaration
-
7/27/2019 Opi-overhauling & Maint. Mgmt
9/183
Identified
QCP prepared (100%)
Identified
RCS prepared (100 %)
r:-2009-10
B,DAS,CER CIVIL WORK etc.
OPI-Remarks
Formed
Submitted.
Provided
36 175
Thickness survey, radiography & DPTtests as per old pactice.
Identified (As per SAP PM Module)
Identified (As per practice)
* Boiler & boiler aux. *Turbine aux.
* Generator aux. *Electrical system. *Control & Instrumentation system.
* Repl. of Gen. stator* Material Mix-up & thickness survey ofcritical pipings, drains & bends.
* Mounting ofthermocouples for monitoring highenergy drains passing with alarm in
*
-
7/27/2019 Opi-overhauling & Maint. Mgmt
10/183
As per part-B
Done
Identified
QCP prepared (100%)
Identified
RCS prepared (100 %)
r:-2009-10
OPI-Remarks
Formed
in C & I area- DDCMIS, ASLD,Actuators of ID,FD,PA fans, DAS &CER etc.* R & M works in electrical area- HTbreakers, DAVR etc.* R & M works in turbine area-
replacement of HP heater, TSI etc.* R & M works in ash handling system-Bottom ash hopper hydraulic gate* R & M work in Mill area- Mill hot airgate *Replacement of control room floor &roof
Pending defect list being updatedregularly. Available on line.
Recommendations incorporated in O/Hscope ot work.
Provided with Engg declaration
Thickness survey, radiography & DPTtests as per old pactice.
Identified (As per SAP PM Module)
Identified (As per practice)
-
7/27/2019 Opi-overhauling & Maint. Mgmt
11/183
Submitted.
Provided
As per part-B
Done
Identified
QCP prepared (100%)
Identified
RCS prepared (100 %)
* Boiler & boiler aux. *Turbine aux & Turbine aux.
* Generator aux &Generator aux. *Electrical system. *Control & Instru
* Material Mix-up & thickness survey ofcritical pipings, drains & bends.
* Mounting ofthermocouples for monitoring highenergy drains passing with alarm inUCB.
Pending defect list being updatedregularly. Available on line.
Recommendations incorporated in O/Hscope ot work.
Provided with Engg declaration
Thickness survey, radiography & DPTtests as per old pactice.
Identified (As per SAP PM Module)
Identified (As per practice)
-
7/27/2019 Opi-overhauling & Maint. Mgmt
12/183
r:-2010-11
VERHAUL
OPI-Remarks
Formed
Submitted.
Provided
As per part-B
Done
Identified
QCP prepared (100%)
* Boiler & boiler aux.
*Turbine aux.* Generator aux.
* Electrical system.* Control & Instrumentation system.
Before 12 month of overhauling finalOH Scope will be decided by CC-OS
Pending defect list being updatedregularly. Available on line.
Recommendations incorporated in O/Hscope ot work.
Provided with Engg declaration
Thickness survey, radiography & DPTtests as per old pactice.
Identified (As per SAP PM Module)
-
7/27/2019 Opi-overhauling & Maint. Mgmt
13/183
Identified
RCS prepared (100 %)
r:-2010-11
OPI-Remarks
Formed
Submitted.
Provided
As per part-B
Identified (As per practice)
* Boiler & boiler aux. * LP Turbine & Turbine aux.
* Generator aux.* Electrical system.
* Control &Instrumentation system.
Before 12 month of overhauling finalOH Scope will be decided by CC-OS
Pending defect list being updatedregularly. Available on line.
Recommendations incorporated in O/Hscope ot work.
-
7/27/2019 Opi-overhauling & Maint. Mgmt
14/183
Done
IdentifiedQCP prepared (100%)
Identified
RCS prepared (100 %)
Provided with Engg declaration
Thickness survey, radiography & DPTtests as per old pactice.
Identified (As per SAP PM Module)
Identified (As per practice)
-
7/27/2019 Opi-overhauling & Maint. Mgmt
15/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
16/183
15 94500
2625
-
7/27/2019 Opi-overhauling & Maint. Mgmt
17/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
18/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
19/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
20/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
21/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
22/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
23/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
24/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
25/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
26/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
27/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
28/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
29/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
30/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
31/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
32/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
33/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
34/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
35/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
36/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
37/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
38/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
39/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
40/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
41/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
42/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
43/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
44/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
45/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
46/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
47/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
48/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
49/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
50/183
OPI PART B CALCULATION F
FGUTPP UNCHAHAR
Unit-4(OPI- 00M)
Part-B Scheduled frOH Completed
Sno Activity U/M
1 2 3 3 8 6 7Spares procurement
1 CRITICAL SPARES
1.1 Total No of Spares identified 34 34 34 0
1.2 Purchase Indents Raised 34 34 34 0
1.3 Purchase Enquiry Issued 34 34 34 0
1.4 Purchase Order Placed 34 34 34 0
1.5 Items recd against PO 34 34 34 0
Total 1.0
2 NON CRITICAL SPARES
2.1 Total No of Spares identified 289 289 289 0
2.2 Purchase Indents Raised 289 289 289 0
2.3 Purchase Enquiry Issued 289 289 289 0
2.4 Purchase Order Placed 289 289 289 0
2.5 Items recd against PO 289 289 289 0
Total 2.0
3 CONSUMABLES
3.1 Total No of items identified 248 248 248 0
3.2 Purchase Indents Raised 248 248 248 0
Unit: - 4: O/H Type: BOILE
TotalQnty
Expected/Due
for O/H
CumulativeTarget for
OPI
CumulativeAchieved
Shortfall, ifany
No ofItems
No ofItems
No ofItems
No ofItems
No of
Items
No ofItems
No ofItems
No ofItems
No ofItems
Nosofitems
No ofItems
No ofItems
-
7/27/2019 Opi-overhauling & Maint. Mgmt
51/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
52/183
FGUTPP UNCHAHAR
Unit-2 (OPI- 01 M)
Part-B Scheduled fr
Sno Activity U/M
1 2 3 3 8 6 7
Spares procurement
1 CRITICAL SPARES1.1 Total No of Spares identified 40 40 40 0
1.2 Purchase Indents Raised 40 40 40 0
1.3 Purchase Enquiry Issued 40 40 40 0
1.4 Purchase Order Placed 40 40 40 0
1.5 Items recd against PO 40 40 38 2
Total 1.0
2 NON CRITICAL SPARES
2.1 Total No of Spares identified 193 193 193 0
2.2 Purchase Indents Raised 193 193 193 0
2.3 Purchase Enquiry Issued 193 193 193 0
2.4 Purchase Order Placed 193 193 193 0
2.5 Items recd against PO 193 193 189 4
Total 2.0
3 CONSUMABLES
3.1 Total No of items identified 323 323 323 0
3.2 Purchase Indents Raised 323 323 323 0
3.3 Purchase Enquiry Issued 323 323 323 0
Unit: - 2: O/H Type: BOILER OH + R&M WORK LIKE-DDCMIS+UCB,
TotalQnty
Expected/Due for
O/H
CumulativeTarget for
OPI
CumulativeAchieved
Shortfall, ifany
No ofItems
No ofItems
No ofItems
No ofItems
No ofItems
No ofItems
No ofItems
No ofItems
No ofItems
Nosofitems
No ofItems
No ofItems
No ofItems
-
7/27/2019 Opi-overhauling & Maint. Mgmt
53/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
54/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
55/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
56/183
Sno Activity U/M
1 2 3 3 8 6 7Spares procurement
1 CRITICAL SPARES
1.1 Total No of Spares identified 28 28 28 0
1.2 Purchase Indents Raised 28 20 20 0
1.3 Purchase Enquiry Issued 28 15 14 1
1.4 Purchase Order Placed 28 10 14 -4
1.5 Items recd against PO 28 3 14 -11
Total 1.0
2 NON CRITICAL SPARES
2.1 Total No of Spares identified 476 476 476 0
2.2 Purchase Indents Raised 476 476 440 36
2.3 Purchase Enquiry Issued 476 476 440 36
2.4 Purchase Order Placed 476 476 260 216
2.5 Items recd against PO 476 476 132 344
Total 2.0
3 CONSUMABLES
3.1 Total No of items identified 120 120 120 0
3.2 Purchase Indents Raised 120 87 87 0
3.3 Purchase Enquiry Issued 120 76 76 0
3.4 Purchase Order Placed 120 76 76 0
3.5 Items recd against PO 120 42 42 0
Total 3.0
4 T&P
4.1 Total No of items identified 0 0 0 0
4.2 Purchase Indents Raised 0 0 0 0
TotalQnty
Expected/Due
for O/H
CumulativeTarget for
OPI
CumulativeAchieved
Shortfall, ifany
No ofItems
No ofItems
No ofItems
No ofItems
No ofItems
No ofItems
No ofItems
No ofItems
No ofItems
Nos
ofitems
No ofItems
No ofItems
No ofItems
No ofItems
Nos ofitems
No ofItems
No ofItems
-
7/27/2019 Opi-overhauling & Maint. Mgmt
57/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
58/183
1.1 Total No of Spares identified 36 36 36 0
1.2 Purchase Indents Raised 36 15 12 3
1.3 Purchase Enquiry Issued 36 6 6 0
1.4 Purchase Order Placed 36 0 4 -4
1.5 Items recd against PO 36 0 3 -3
Total 1.0
2 NON CRITICAL SPARES
2.1 Total No of Spares identified 276 276 276 0
2.2 Purchase Indents Raised 276 150 56 94
2.3 Purchase Enquiry Issued 276 100 27 73
2.4 Purchase Order Placed 276 50 13 37
2.5 Items recd against PO 276 0 107 -107
Total 2.0
3 CONSUMABLES
3.1 Total No of items identified 111 111 111 0
3.2 Purchase Indents Raised 111 90 60 30
3.3 Purchase Enquiry Issued 111 35 48 -13
3.4 Purchase Order Placed 111 20 24 -4
3.5 Items recd against PO 111 0 18 -18
Total 3.0
4 T&P
4.1 Total No of items identified 0 0 0 0
4.2 Purchase Indents Raised 0 0 0 0
4.3 Purchase Enquiry Issued 0 0 0 0
4.4 Purchase Order Placed 0 0 0 0
4.5 Items recd against PO 0 0 0 0
Total 4.0
No ofItems
No ofItems
No ofItems
No ofItems
No ofItems
No ofItems
No ofItems
No of
ItemsNo ofItems
Nosofitems
No ofItems
No ofItems
No ofItems
No ofItems
Nos ofitems
No ofItems
No of
ItemsNo ofItems
No ofItems
Nos ofitems
-
7/27/2019 Opi-overhauling & Maint. Mgmt
59/183
5 Contracts for O/H
5.1 Identification of Contracts 28 28 28 0
5.2 Contract Proposals initiated 28 0 20 -20
5.3 Tender Issued 28 0 12 -12
5.4 Offer received 28 0 12 -12
5.5 LOA Issued 28 0 9 -9
Total 5.0
Grand Total: 1.0+2.0+3.0+4.0+5.0
No ofContracts
No ofContracts
No ofContracts
No ofContracts
No ofContracts
-
7/27/2019 Opi-overhauling & Maint. Mgmt
60/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
61/183
1015.0 15.0 15.0
2537.5 37.5 37.5
5075.0 75.0 75.0
100 150.0 150 150.0100.0 100.0
50.0 0.0 0.0
100.0 0.0 0.0
100.0 0.0 0.0
250.0 0.0 0.0
500.0 0.0 0.0
100 0.0 0 0.0
0.0 0.0
5
12.5 12.5 12.5
20
50.0 50.0 50.0
15
37.5 37.5 37.5
1025.0 25.0 25.0
50
125.0 125.0 125.0
100 250.0 250.0 250.0
100.0 100.0
900.0 900.0 900.0
100.0 100.0
R OPI 2009-10
-
7/27/2019 Opi-overhauling & Maint. Mgmt
62/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
63/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
64/183
m - 01/09/09 to 05/10/09
gress from 01/09/09
OPI-(00)
weightage in % MAX. MARKS
9 10 11 12 13
515.0 15.0 15.0
1030.0 30.0 30.0
1030.0 30.0 30.0
2575.0 75.0 75.0
50150.0 146.6 146.6
100 300 297 296.6
98.9 98.9
5
10.0 10.0 10.010
20.0 20.0 20.0
1020.0 20.0 20.0
2550.0 50.0 50.0
50100.0 100.0 100.0
100 200.0 200 200.0
100.0 100.0
57.5 7.5 7.5
1015.0 15.0 15.0
1015.0 15.0 15.0
2537.5 37.5 37.5
FY of O/H: 2009-10.
ACTUALSCORE
ACTUALSCORE Cum
ReviewedScore
-
7/27/2019 Opi-overhauling & Maint. Mgmt
65/183
5075.0 75.0 75.0
100 150.0 150 150.0
100.0 100.0
5
0.0 0.0 0.010
0.0 0.0 0.0
100.0 0.0 0.0
250.0 0.0 0.0
500.0 0.0 0.0
100 0.0 0 0.0
0.0 0.0
512.5 12.5 12.5
20
50.0 50.0 50.0
15
37.5 37.5 37.5
10
25.0 25.0 25.0
50
125.0 125.0 125.0100 250.0 250.0 250.0
100.0 100.0
900.0 896.6 896.6
99.6 99.6
R OPI 2010-11
UPDATED ON- 31/07/2009
8/09/10 (25 days) Boiler+RH modfn+AVR
-
7/27/2019 Opi-overhauling & Maint. Mgmt
66/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
67/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
68/183
515.0 15.0 15.0
1030.0 24.0 10.0
1030.0 30.0 5.0
250.0 0.0 8.3
500.0 0.0 12.5
100 75 69 50.8
92.0 16.9
510.0 10.0 10.0
1020.0 7.5 4.1
10
20.0 5.4 2.025
50.0 13.0 2.4
500.0 0.0 38.8
100 100.0 36 57.1
35.9 28.6
57.5 7.5 7.5
1015.0 10.0 8.1
1015.0 20.6 6.5
2537.5 45.0 8.1
500.0 0.0 12.2
100 75.0 83 42.4
110.8 28.2
50.0 0.0 0.0
100.0 0.0 0.0
100.0 0.0 0.0
250.0 0.0 0.0
500.0 0.0 0.0
100 0.0 0 0.0
0.0 0.0
-
7/27/2019 Opi-overhauling & Maint. Mgmt
69/183
5
12.5 12.5 12.5
20
0.0 0.0 35.7
15
0.0 0.0 16.1
10
0.0 0.0 10.7
50
0.0 0.0 40.2
100 12.5 12.5 115.2
100.0 46.1
262.5 200.4 265.5
76.4 29.5
-
7/27/2019 Opi-overhauling & Maint. Mgmt
70/183
14.0 PLANNED MAINTENANCE14.2.1 KEY SPARES & CONTRACTS REQUIRED FOR OH
UNIT NO.4 OVERHAUL DUE IN FINANCIAL YEAR:-20SPARES (CRITICAL)
S.NO MAT CODE DESCRIPTION MODE OF
/DEPT PROCURE
BMD Received All
1
TOTAL 0 0 0
TMD Received All1
TOTAL 0 0 0
EMD Received All
1
TOTAL 0 0 0
C&I Received All
1
TOTAL 0 0 0
AHP Received All
1TOTAL 0 0 0
G TOTAL 0 0 0
SPARES (NON - CRITICAL)S.NO MAT CODE DESCRIPTION MODE OF
/DEPT PROCURE
BMD Received All
1TOTAL 0 0 0
TMD Received All
1
TOTAL 0 0 0
EMD Received All
1
-
7/27/2019 Opi-overhauling & Maint. Mgmt
71/183
TOTAL 0 0 0
C&I Received All
1
TOTAL 0 0 0
AHP Received All
1
TOTAL 0 0 0
G TOTAL 0 0 0
T&PS.NO ITEM CODE DESCRIPTION MODE OF
/DEPT PROCURE
BMD
1TOTAL 0 0 0
TMD
1
TOTAL 0 0 0
EMD
1
TOTAL 0 0 0
C&I
1
TOTAL 0 0 0
AHP
1
TOTAL 0 0 0
G TOTAL 0 0 0
CONSUMABLESS.NO ITEM CODE DESCRIPTION MODE OF
/DEPT PROCURE
BMD
TOTAL 0 0 0
TMD
1
TOTAL 0 0 0
EMD
-
7/27/2019 Opi-overhauling & Maint. Mgmt
72/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
73/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
74/183
C&I
1
TOTAL 0 0 0
AHP
1
TOTAL 0 0 0
G TOTAL 4 4 4
T&PS.NO ITEM CODE DESCRIPTION MODE OF
/DEPT PROCURE
BMD
1
TOTAL 0 0 0TMD
1
TOTAL 0 0 0
EMD
1
TOTAL 0 0 0
C&I
1
TOTAL 0 0 0
AHP
1
TOTAL 0 0 0
G TOTAL 0 0 0
CONSUMABLESS.NO ITEM CODE DESCRIPTION MODE OF
/DEPT PROCURE
BMD1
TOTAL 0 0 0
TMD
1
M1012014503
LTWHITE FUSED
ALUMINA,SIZE-90 GRIT
-
7/27/2019 Opi-overhauling & Maint. Mgmt
75/183
1
TOTAL 0 0 0
EMD
1
TOTAL 0 0 0
C&I
1
TOTAL 0 0 0
AHP
1
TOTAL 0 0 0
G TOTAL 0 0 0
CONTRACTSS.NO DESC MODE OF ESTIM
/DEPT OF JOB TENDER VALUE
BMD
1
TOTAL 0 0 0
TMD
TOTAL 1 1 1
EMD
TOTAL 1 1 1
C&I
1
TOTAL 0 0 0
OFFSITE
1
TOTAL 0 0 0
G TOTAL 2 2 2
UNIT NO.3 OVERHAUL DUE IN FINANCIAL YEAR:-20
SPARES (CRITICAL)S.NO MAT CODE DESCRIPTION MODE OF
-
7/27/2019 Opi-overhauling & Maint. Mgmt
76/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
77/183
/DEPT PROCURE
BMD
1
TOTAL 0 0 0
TMD
1
TOTAL 0 0 0
EMD
1
TOTAL 0 0 0
C&I
1
TOTAL 0 0 0
AHP1
TOTAL 0 0 0
G TOTAL 0 0 0
CONSUMABLESS.NO ITEM CODE DESCRIPTION MODE OF
/DEPT PROCURE
BMD
TOTAL 1 1 1
TMD
TOTAL 1 1 1
EMD
1
TOTAL 0 0 0
C&I
1
TOTAL 0 0 0
AHP
1
TOTAL 0 0 0
G TOTAL 2 2 2
CONTRACTS
-
7/27/2019 Opi-overhauling & Maint. Mgmt
78/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
79/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
80/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
81/183
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
INITIATION BUDGET REG CLEAR CONC BY FIN
TARGET ACTUAL CERTIF Y/N TARGET ACTUAL
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
9-10
PR RAISED REG CLEAR CLEARED BY PI NO ENQUIR
ACTUAL Y/N SC COMM TARGETTARGET(OPI)
-
7/27/2019 Opi-overhauling & Maint. Mgmt
82/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
83/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
84/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
85/183
ACTUAL Y/N SC COMM TARGET
Minus-18M 100008310 Y Y 100008310 Y
1 1 1 1 1 1
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
1 1 1 1 1 1
PR RAISED REG CLEAR CLEARED BY PI NO ENQUIR
ACTUAL Y/N SC COMM TARGET
1 1 1 1 1 1
1 1 1 1 1 1
0 0 0 0 0 0
1 1 1 1 1 1
0 0 0 0 0 0
3 3 3 3 3 3
PR RAISED REG CLEAR CLEARED BY PI NO ENQUIR
TARGET(OPI)
TARGET(OPI)
-
7/27/2019 Opi-overhauling & Maint. Mgmt
86/183
ACTUAL Y/N SC COMM TARGET
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
PR RAISED REG CLEAR CLEARED BY PI NO ENQUIR
ACTUAL Y/N SC COMM TARGET
1 1 1 1 1 1
1 1 1 1 1 1
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
2 2 2 2 2 2
TARGET(OPI)
TARGET(OPI)
-
7/27/2019 Opi-overhauling & Maint. Mgmt
87/183
INITIATION BUDGET REG CLEAR CONC BY FIN
TARGET ACTUAL CERTIF Y/N TARGET ACTUAL
0 0 0 0 0 0
1 1 1 1 1 1
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
1 1 1 1 1 1
-
7/27/2019 Opi-overhauling & Maint. Mgmt
88/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
89/183
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
ISSUED BOD TECH PO PLACED ITEM
ACTUAL SUITABLITY TARGET ACTUAL TARGET
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
ISSUED BOD TECH ITEM RECD
ACTUAL SUITABLITY TARGET ACTUAL TARGET
0 0 0 0 1 0
0 0 0 0 1 0
PO PLACED
-
7/27/2019 Opi-overhauling & Maint. Mgmt
90/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
91/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
92/183
0 0 0 0 0 0
0 0 0 0 0 0
4 4 4 4 4 4
ISSUED BOD TECH PO PLACED ITEM
ACTUAL SUITABLITY TARGET ACTUAL TARGET
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
ISSUED BOD TECH ITEM RECD
ACTUAL SUITABLITY TARGET ACTUAL TARGET
0 0 0 0 0 0
6000102174 6/24/2009 Y Minus-3M
PO PLACED
4000028186/00010
-
7/27/2019 Opi-overhauling & Maint. Mgmt
93/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
94/183
ACTUAL SUITABLITY TARGET ACTUAL TARGET
Y Y Y Minus-12M Minus-3M
1 1 1 1 1 1
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
1 1 1 1 1 1
ISSUED BOD TECH PO PLACED ITEM
ACTUAL SUITABLITY TARGET ACTUAL TARGET
1 1 1 1 1 1
1 1 1 1 1 1
0 0 0 0 0 0
1 1 1 1 1 1
0 0 0 0 0 0
3 3 3 3 3 3
ISSUED BOD TECH PO PLACED ITEM
4000012574/001304000016827/00070
-
7/27/2019 Opi-overhauling & Maint. Mgmt
95/183
ACTUAL SUITABLITY TARGET ACTUAL TARGET
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
ISSUED BOD TECH ITEM RECD
ACTUAL SUITABLITY TARGET ACTUAL TARGET
1 1 1 1 1 1
1 1 1 1 0 1
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
2 2 2 2 #REF! 2
PO PLACED
-
7/27/2019 Opi-overhauling & Maint. Mgmt
96/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
97/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
98/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
99/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
100/183
BHEL
DOD 30/06/10 Under despatch
BHEL (T)
DOD 30/09/10 Under despatch
2 2 2
0 0 0
0 0 0
0 0 0
0 0 0
2 2 2
RECD VENDOR REMARKS
ACTUAL NAME
BHEL DOD 31/03/10 Under despatch
BHEL DOD 31/05/10 Under despatch
2 2 2
BHEL
BHEL
2 2 2
0 0 0
Expected by30/09/09
Expected by30/09/09
Expected by30/09/09
Expected by30/09/09
Expected by30/09/09
DOD: 05.08.2010 Rem. On27.6.09
Expected by30/09/09
DOD: 05.08.2010 Rem. On27.6.10
-
7/27/2019 Opi-overhauling & Maint. Mgmt
101/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
102/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
103/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
104/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
105/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
106/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
107/183
5 Contracts for O/H
5.1 Identification of Contracts 26
5.2 Contract Proposals initiated 26
5.3 Tender Issued 26
5.4 Offer received 26
5.5 LOA Issued 26
UNIT - 2 Scheduled from - 26/08/09 to 04/10
TARGET MATRIX UNIT- 2OPI(-24) OPI-(23) OPI-(22) OPI-(21)
Sno Activi ty
Spares procurement
1 CRITICAL SPARES
1.1 Total No of Spares identified 40 5 12 15 18
1.2 Purchase Indents Raised 40 5 12
1.3 Purchase Enquiry Issued 40 51.4 Purchase Order Placed 40
1.5 Items recd against PO 40
2 NON CRITICAL SPARES
2.1 Total No of Spares identified 193 10 12 12 18
2.2 Purchase Indents Raised 193 10 12
2.3 Purchase Enquiry Issued 193 10
2.4 Purchase Order Placed 193
2.5 Items recd against PO 193
3 CONSUMABLES
3.1 Total No of items identified 323 20 50 80 120
3.2 Purchase Indents Raised 323 20 50
3.3 Purchase Enquiry Issued 323
3.4 Purchase Order Placed 323
3.5 Items recd against PO 323
Total QntyExpected/Du
e for O/H
CumulativeTarget for this
OPI
CumulativeTarget for OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
-
7/27/2019 Opi-overhauling & Maint. Mgmt
108/183
4 T&P
4.1 Total No of items identified 0 0 0 0 0
4.2 Purchase Indents Raised 0 0 0 0 0
4.3 Purchase Enquiry Issued 0 0 0 0 0
4.4 Purchase Order Placed 0 0 0 0 0
4.5 Items recd against PO 0 0 0 0 0
5 Contracts for O/H
5.1 Identification of Contracts 24
5.2 Contract Proposals initiated 24
5.3 Tender Issued 24
5.4 Offer received 24
5.5 LOA Issued 24
UNIT - 3 Scheduled from 11/10/09 to 14/11/09
TARGET MATRIX UNIT- 3OPI(-24) OPI-(23) OPI-(22) OPI-(21)
Sno Activi ty
Spares procurement
1 CRITICAL SPARES
1.1 Total No of Spares identified 44 5 10 20 32
1.2 Purchase Indents Raised 44 5 10
1.3 Purchase Enquiry Issued 44
1.4 Purchase Order Placed 44
1.5 Items recd against PO 44
2 NON CRITICAL SPARES
2.1 Total No of Spares identified 276 10 30 50 80
2.2 Purchase Indents Raised 276 10 30
2.3 Purchase Enquiry Issued 276
2.4 Purchase Order Placed 276
Total QntyExpected/Du
e for O/H
CumulativeTarget for this
OPI
CumulativeTarget for OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
-
7/27/2019 Opi-overhauling & Maint. Mgmt
109/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
110/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
111/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
112/183
4.2 Purchase Indents Raised 0 0 0 0 0
4.3 Purchase Enquiry Issued 0 0 0 0 0
4.4 Purchase Order Placed 0 0 0 0 0
4.5 Items recd against PO 0 0 0 0 0
5 Contracts for O/H5.1 Identification of Contracts 28
5.2 Contract Proposals initiated 28
5.3 Tender Issued 28
5.4 Offer received 28
5.5 LOA Issued 28
-
7/27/2019 Opi-overhauling & Maint. Mgmt
113/183
31/08/2009
H Completed)
OPI-(20) OPI-(19) OPI-(18) OPI-(15) OPI-(12) OPI-(9) OPI-(08) OPI-(07) OPI-(06) OPI-(05)
15 20 34 34 34 34 34 34 34 3410 15 20 34 34 34 34 34 34 34
5 10 15 20 34 34 34 34 34 34
5 10 15 30 34 34 34 34 34
6 12 18 24 31 31
50 100 140 175 200 289 289 289 289 289
30 40 50 100 140 175 200 289 289 289
10 30 40 50 100 140 175 200 289 289
10 30 40 50 100 140 175 200 289
8 10 14 40 75 120 160 273
60 105 140 175 190 289 289 289 289 289
16 34 53 86 148 183 200 289 289 289
10 30 40 50 100 140 175 200 289 289
10 30 40 50 100 140 175 200 267
6 14 18 40 75 120 160 222
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for OPI
-
7/27/2019 Opi-overhauling & Maint. Mgmt
114/183
12 18 24 26 26 26
6 18 20 20 24 26
6 18 22 22 26
6 18 20 24
6 12 17
/09
OPI-(20) OPI-(19) OPI-(18) OPI-(15) OPI-(12) OPI-(9) OPI-(08) OPI-(07) OPI-(06) OPI-(05)
20 20 30 30 40 40 40 40 40 40
15 18 20 20 30 40 40 40 40 40
10 15 18 20 20 30 40 40 40 405 10 15 18 20 20 30 40 40 40
6 18 28 32 36 36
52 86 122 142 193 193 193 193 193 193
12 18 52 86 122 142 193 193 193 193
12 12 18 52 86 122 142 193 193 193
10 12 12 18 52 86 122 142 187 187
18 52 86 140 168 168
170 220 250 300 323 323 323 323 323 323
80 120 170 220 250 323 323 323 323 323
20 50 80 120 170 220 250 323 323 323
20 50 80 120 170 220 301 301 301
20 85 160 220 256 256
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for OPI
-
7/27/2019 Opi-overhauling & Maint. Mgmt
115/183
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
24 24 24 24 24 24
15 22 24 24 24 24
8 15 22 24 24 24
8 12 18 20 20
8 12 16 16
OPI-(20) OPI-(19) OPI-(18) OPI-(15) OPI-(12) OPI-(9) OPI-(08) OPI-(07) OPI-(06) OPI-(8)
38 38 40 40 44 44 44 44 44 44
20 32 38 38 40 40 44 44 44 44
5 10 20 32 38 38 40 40 44 44
5 10 15 18 22 28 30 35 38
15 18 22 28 33 33
150 180 222 240 276 276 276 276 276 276
50 80 150 180 222 240 276 276 276 276
10 30 50 80 150 180 222 240 276 276
30 50 80 150 180 222 240 268
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for OPI
-
7/27/2019 Opi-overhauling & Maint. Mgmt
116/183
30 50 80 150 180 244
140 180 205 228 282 282 282 282 282 282
25 40 75 140 180 205 228 282 282 28210 25 40 75 140 180 205 228 282 282
10 25 40 75 140 180 205 228 276
30 75 90 140 220 238
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
12 15 18 25 27 27
5 8 12 15 18 25
5 8 12 15 18
5 8 12 15
-
7/27/2019 Opi-overhauling & Maint. Mgmt
117/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
118/183
5 8 11 11
5 8 11
/10
OPI-(20) OPI-(19) OPI-(18) OPI-(15) OPI-(12) OPI-(9) OPI-(08) OPI-(07) OPI-(06) OPI-(05)
25 30 36 36 36 36 36 36 36 36
10 15 20 25 30 36 36 36
4 6 10 15 20 25 30 36 36 36
6 10 15 20 25 30 36
6 10 15 20 20 25
200 276 276 276 276 276 276 276 276 276
15 50 100 150 200 276 276 276 276 276
6 15 50 100 150 200 276 276 276 276
15 50 100 150 200 276 276 276
15 50 100 150 180 200
100 111 111 111 111 111 111 111 111 111
20 35 80 90 100 111 111 111 111 111
28 20 35 80 90 100 111 111 111
20 35 80 90 100 111 111
20 35 50 80 80 90
0 0 0 0 0 0 0 0 0 0
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for OPI
-
7/27/2019 Opi-overhauling & Maint. Mgmt
119/183
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
28 28 28 28 28 28
28 28 28 28 28
28 28 28 28 28
20 24 28 28
-
7/27/2019 Opi-overhauling & Maint. Mgmt
120/183
OPI-(04) OPI-(03) OPI-(02) OPI-(01) OPI-(00)
34 34 34 34 3434 34 34 34 34
34 34 34 34 34
34 34 34 34 34
31 34 34 34 34
289 289 289 289 289
289 289 289 289 289
289 289 289 289 289
289 289 289 289 289
285 289 289 289 289
289 289 289 289 289
289 289 289 289 289
289 289 289 289 289
289 289 289 289 289
222 289 289 289 289
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
-
7/27/2019 Opi-overhauling & Maint. Mgmt
121/183
26 26 26 26 26
26 26 26 26 26
26 26 26 26 26
26 26 26 26 26
17 26 26 26 26
OPI-(04) OPI-(03) OPI-(02) OPI-(01) OPI-(00)
40 40 40 40 40
40 40 40 40 40
40 40 40 40 4040 40 40 40 40
36 40 40 40 40
193 193 193 193 193
193 193 193 193 193
193 193 193 193 193
193 193 193 193 193
168 193 193 193 193
323 323 323 323 323
323 323 323 323 323
323 323 323 323 323
323 323 323 323 323
256 323 323 323 323
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
-
7/27/2019 Opi-overhauling & Maint. Mgmt
122/183
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
24 24 24 24 24
24 24 24 24 24
24 24 24 24 24
24 24 24 24 24
16 24 24 24 24
OPI-(7) OPI-(6) OPI-(5) OPI-(4) OPI-(3) OPI-(2) OPI-(1) OPI-(00)
44 44 44 44 44 44 44 44
44 44 44 44 44 44 44 44
44 44 44 44 44 44 44 44
38 38 38 44 44 44 44 44
33 33 33 38 44 44 44 44
276 276 276 276 276 276 276 276
276 276 276 276 276 276 276 276
276 276 276 276 276 276 276 276
268 268 268 276 276 276 276 276
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for OPI
-
7/27/2019 Opi-overhauling & Maint. Mgmt
123/183
244 244 244 268 276 276 276 276
282 282 282 282 282 282 282 282
282 282 282 282 282 282 282 282282 282 282 282 282 282 282 282
276 276 276 282 282 282 282 282
238 238 238 276 282 282 282 282
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
27 27 27 27 27 27 27 27
27 27 27 27 27 27 27 27
25 27 27 27 27 27 27 27
18 25 27 27 27 27 27 27
5 8 12 18 23 27 27 27
-
7/27/2019 Opi-overhauling & Maint. Mgmt
124/183
OPI-(04) OPI-(03) OPI-(02) OPI-(01) OPI-(00)
28 28 28 28 28
28 28 28 28 28
28 28 28 28 28
28 28 28 28 28
28 28 28 28 28
476 476 476 476 476
476 476 476 476 476
476 476 476 476 476
476 476 476 476 476
125 476 476 476 476
120 120 120 120 120
120 120 120 120 120120 120 120 120 120
120 120 120 120 120
120 120 120 120 120
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
21 21 21 21 21
21 21 21 21 21
21 21 21 21 21
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
-
7/27/2019 Opi-overhauling & Maint. Mgmt
125/183
21 21 21 21 21
11 21 21 21 21
OPI-(04) OPI-(03) OPI-(02) OPI-(01) OPI-(00)
36 36 36 36 36
36 36 36 36 36
36 36 36 36 36
36 36 36 36 36
25 30 36 36 36
276 276 276 276 276
276 276 276 276 276
276 276 276 276 276
276 276 276 276 276
200 276 276 276 276
111 111 111 111 111
111 111 111 111 111
111 111 111 111 111
111 111 111 111 111
95 100 111 111 111
0 0 0 0 0
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
CumulativeTarget for
OPI
-
7/27/2019 Opi-overhauling & Maint. Mgmt
126/183
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
28 28 28 28 28
28 28 28 28 28
28 28 28 28 28
28 28 28 28 28
28 28 28
-
7/27/2019 Opi-overhauling & Maint. Mgmt
127/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
128/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
129/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
130/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
131/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
132/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
133/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
134/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
135/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
136/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
137/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
138/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
139/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
140/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
141/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
142/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
143/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
144/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
145/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
146/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
147/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
148/183
14.0 PLANNED MAINTENANCE
Contents:
14.3 ORT Summary Sheet-OPI Summ
Station:. , ORT Month: held on, FY of O/H: Current Year/Next Year/Next to Nex
Unit-1 Unit-2 Un
Due Start Date of O/H
Duration (Days)
O/H Type
Activity/OPI No OPI- 03 M OPI-
Max Actual Max
Marks Score Marks
Part-A As per Format A
1240 239 240
2 O/H Scope of Work(4+5+6) 180 180 180
330 30 30
4 Quality O/H/Commissioning (12+13) 50 50 50
Total Part-A 500 499 500
100%
Part-B As per Format B
5 Spares 500 494.0 500
6 General Consumables 150 150 150
7 T&Ps 100 100 100
8 Contracts for O/H 250 250 250
Total Part-B 1000 994 1000
99%
Grand Total 1500 1493 1500
100%
Spares/Contracts Brief status Total Act Total
Due Qty Due
Spares No of items received till this OPI 233 227 458
No of Indents matured into receipt
CONTENTS
14.3 OPI SUMMARY SHEET
Engg Decl Submission/O/H Proposal(1+2+3+8+9+10+11)
Incorporation of comments/advice fromCOS/ROS in Engg Decl/ SOW (7)
http://191.254.11.230/mail/707201.nsf/38d46bf5e8f08834852564b500129b2c/b6ad0bd0c6b1d02965257164003fc08f/$FILE/EEMG-1%20(MOU-ABT-PERF-AVF-PL-OUTAGE).xlshttp://191.254.11.230/mail/707201.nsf/38d46bf5e8f08834852564b500129b2c/b6ad0bd0c6b1d02965257164003fc08f/$FILE/EEMG-1%20(MOU-ABT-PERF-AVF-PL-OUTAGE).xls -
7/27/2019 Opi-overhauling & Maint. Mgmt
149/183
Contracts No of Contracts for O/H Awarded29 29 30
Exception/Major Shortfall:
-
7/27/2019 Opi-overhauling & Maint. Mgmt
150/183
Date- 31/08/2009
ry for ORT
ORT Month: Financial Year of O/H:
t-3 Unit-4 Unit-5 Unit-6 Unit-7 Unit-8
04 M OPI- 00 M OPI- OPI- OPI-
Actual Max Actual Max Actual Max Actual Max Actual
Score Marks Score Marks Score Marks Score Marks Score
240 240 240
180 180 180
30 30 30
50 50 50
500 500 500
100% 100%
497 500 500
150 150 150
100 100 100
250 250 250
997 1000 1000
100% 100%
1497 1500 1500
100% 100%
Act Total Act Total Act Total Act Total Act
Qty Due Qty Due Qty Qty Qty Qty Qty
457 323 323
Click togo to
Contents
Click togo to
Contents
-
7/27/2019 Opi-overhauling & Maint. Mgmt
151/183
30 30 30
-
7/27/2019 Opi-overhauling & Maint. Mgmt
152/183
Unit-9 Unit-10 Unit-11 Unit-12
OPI- OPI- OPI- OPI-
Max Actual Max Actual Max Actual Max Actual
Marks Score Marks Score Marks Score Marks Score
Total Act Total Act Total Act Total Act
Qty Qty Qty Qty Qty Qty Qty Qty
-
7/27/2019 Opi-overhauling & Maint. Mgmt
153/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
154/183
14.0 PLANNED MAINTENANCE
14.4 MONTHLY EXCEPTION REPORT
Overhaul Preparedness In
Station Monthly Exception report
Overhaul: for FY 2008-09 Sample Sheet
A) Resource (Material & Contract) Exceptions
4 Materials Contracts Material Contracts Materials
1 Indent raisingBMD 0 0 0 0 0
TMD 0 0 0 0 0
EMD 0 0 0 0 0
C&I 0 0 0 0 0
Offsite Mtnc 0 0 0 0 0
LTP - MTP 0 0 0 0 0
C&M 0 0 0 0 0
O&M 0 0 0 0 0
PO placement 0 0 0 8 0
0 0 0 0 0
0 0 0 0 0
Negotiations 0 0 4 0 0
TC 0 0 0 0 0
Vendor 0 0 0 0 0
Retendering 0 0 0 0 0
UnitNo.
ActivityPending wrtTarget Matrix
Pending for currentOPI
Pending sinceprevious OPI Review(more than 1 Month
of Target)
Pendinprevious(more tha
of T
Issue ofenquiry
pending
Non receipt ofbid
TechnicalEvaluation
-
7/27/2019 Opi-overhauling & Maint. Mgmt
155/183
0 0 10 8 22
B) No. of pending items
R0 0 0
R1 0 0
R2 0 0
Others: 0 0
A) Resource (Material & Contract) Exceptions
Materials Contracts Material Contracts Materials
2 Indent raising
BMD 0 0 0 0 0
TMD 0 0 0 0 0
EMD 0 0 0 0 0
C&I 0 0 0 0 0
Offsite Mtnc 0 0 0 0 0
LTP - MTP 0 0 0 0 0
C&M 0 0 0 0 0
O&M 0 0 0 0 0
PO placement 0 0 0 0 16
Receipt ofmaterial
OPI - PART A
Exceptions
Pending since
previous OPI Review(more than 1 Month
of Target)
Pendin
previous(more tha
of T
Engg DeclarationSubmission
UnitNo.
ActivityPending wrtTarget Matrix
Pending for currentOPI
Pending sinceprevious OPI Review(more than 1 Month
of Target)
Pendinprevious(more tha
of T
Issue of
enquirypending
-
7/27/2019 Opi-overhauling & Maint. Mgmt
156/183
0 1 0 2 0
0 0 0 0 7
Negotiations 0 0 0 0 0
TC 0 0 0 2 0Vendor 0 0 0 0 0
Retendering 0 0 0 0 0
6 0 7 2 16
B) No. of pending items
R0 0 0
R1 0 0
R2 0 0
Others: 0 0
A) Resource (Material & Contract) Exceptions
Materials Contracts Material Contracts Materials
3 Indent raising
BMD 0 0 0 0 0
TMD 0 0 0 0 0
EMD 0 0 0 0 0
C&I 0 0 0 0 0
Offsite Mtnc 0 0 0 0 0
Non receipt ofbid
TechnicalEvaluation
Receipt ofmaterial
OPI - PART A
Exceptions
Pending since
previous OPI Review(more than 1 Month
of Target)
Pendin
previous(more tha
of T
Engg DeclarationSubmission
UnitNo.
ActivityPending wrtTarget Matrix
Pending for currentOPI
Pending sinceprevious OPI Review(more than 1 Month
of Target)
Pendinprevious(more tha
of T
-
7/27/2019 Opi-overhauling & Maint. Mgmt
157/183
LTP - MTP 0 0 0 0 0
C&M 0 0 0 0 0
O&M 0 0 0 0 0
PO placement 0 0 10 11 13
0 2 0 2 0
6 0 9 0 13
Negotiations 0 0 0 0 0
TC 0 0 0 0 0
Vendor 0 0 0 0 0
Retendering 0 0 0 0 0
1 0 68 4 76
B) No. of pending items
R0 0 0
R1 0 0
R2 0 0
Others: 0 0
C) OPI ScoresOPI no. Score Scores a
Current - 1 Current - 2 Current - 3
4 Part A 100 99.6
Issue ofenquirypending
Non receipt ofbid
TechnicalEvaluation
Receipt ofmaterial
OPI - PART AExceptions
Pending sinceprevious OPI Review
(more than 1 Monthof Target)
Pendinprevious
(more thaof T
Engg DeclarationSubmission
Unitno.
Current OPIscore(in %)
-
7/27/2019 Opi-overhauling & Maint. Mgmt
158/183
OPI-00100 95
100 90
2
OPI-01
Part A 99.5 99.5
99 99
98.9 98.9
3
OPI-02
Part A 100 99
100 97
100 96.5
D) Issue details
GM Station NilED Region Nil
ED OS Nil
Nil
Part Bmonthly
Part Bcumulative
Part B
monthlyPart Bcumulative
Part Bmonthly
Part Bcumulative
FlaggedIssues
DirectorOperations
-
7/27/2019 Opi-overhauling & Maint. Mgmt
159/183
Date- 31/08/2009
dex (OPI)
Remarks
Contracts
0
0
0
0
0
0
0
0
9
0
0
0
0
0
0
beforePI Review2 Months
rget)
-
7/27/2019 Opi-overhauling & Maint. Mgmt
160/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
161/183
2
0
0
00
0
7
Remarks
Engg. Declaration R-0 sent to OS
Engg. Declaration R-0 sent to OS
Engg. Declaration R-0 sent to OS
Engg. Declaration R-0 sent to OS
Remarks
Contracts
0
0
0
0
0
before
PI Review2 Months
rget)
beforePI Review2 Months
rget)
-
7/27/2019 Opi-overhauling & Maint. Mgmt
162/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
163/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
164/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
165/183
1 Type of Overhaul
2 Duration 47
3 Spare Cost + Consumable Cost 5,01
4 Contract Cost 4,15
5 Total Cost
14.9 MAJOR (CAPITAL) SPARES CONSUMED (Recently completed Overhauls
14.10 PLANNED MAINTENANCE ROLLING PLAN FOR 8 YE
YEAR UNIT-I UNIT-2
Schedule S
2005-06 Boiler Boiler Lic. Renewal
2006-07 Boiler
2007-08 Capital
Rs.9,1
Rs.17,08,7
Type ofOH
Type ofOH
21-09-0508-10-05
04-11-05
17/01/0722/01/07
03-06-07
-
7/27/2019 Opi-overhauling & Maint. Mgmt
166/183
16.7 STRUCTURE CHECKING:
AREA TG Hall Boiler ESP CHP AHP
8/18/2008 Dec.-08 Jul-09 Jun-08 Jul-09
Y Y Y Y Y
NA NA NA NA NA
01 year 01 year 01 year 01 year 01 year
Aug-09 Dec.-09 Jul-10 Jun-09 Jul-10
Note: ORT Co-ordinator is to affix the relevant Reports along with Action
16.8 MACHINE FOUNDATIONS:
Area TG CHP AHP
Aug-09 Apr-09 Jun-09
Y Y Y Y Y
NA NA NA NA NA
06 Months 06 Months 06 Months 06 Months 06 Months
Feb-10 Sept.-09 Dec.-09
Note: ORT Co-ordinator is to affix the relevant Reports along with Action
16.9 CHIMNEY INSPECTION:
Last date ofchecking structuresas per Guidelines
Compliance ofobservationscompleted (Y/N)
Action Plan for thePendingObservations
Freq. ofchecking
Next dateof checking
Fans,Mills etc. In Blr.
CompressorHouse
Last date ofchecking as perguidelines includingspring loadedfoundations
Stg-I, Stg-II& Stg-IIIMay-09
Stg-I, Stg-II& Stg-IIIMay-09
Compliance ofobservationscompleted (Y/N)
Action Plan for thePendingObservations
Freq. Ofchecking
Next date ofchecking
Stg-I, Stg-II& Stg-IIINov-09
Stg-I, Stg-II& Stg-IIINov-09
-
7/27/2019 Opi-overhauling & Maint. Mgmt
167/183
Unit No. Major Observations
1 01/10/2002
201/10/2002
310/19/2007
410/19/2007
5 21/11/2008
6
7
8
9
10
11
12
Note: ORT Co-ordinator is to affix the relevant Reports along with Action
16.10 PAINTING OF STRUCTURES:
Area TG Hall Boiler ESP CHP
July'02 May'03 2003 Mar.'04
Rolling plan for painting of the structure of FGUTPP
Sl. Description 2005-06 2006-07 2007-08
PT Plant
Lastdate of
checking
Bunkers& Mill Bay
Last dateof painting done
PatiallyDone, in
06-07
Frequencyof Painting (year)
As perrequiremen
t
As perrequirement
As perrequireme
nt
As perrequiremen
t
As perrequirement
Next dateof painting
5 yrsrolling planas under
covering all
thestructures.
5 yrs rollingplan as undercovering all the
structures.
Balancein 08-09
5 yrsrolling planas undercovering
all thestructures.
5 yrs rollingplan asunder
covering all
thestructures.
1.Completed
May-06
-
7/27/2019 Opi-overhauling & Maint. Mgmt
168/183
DM Plant
Trestles
DG + Compressor house
ESP + AHP (I)
ESP + AHP (II)
Bal CHP-I
CHP-II
Boiler I
Boiler II
TG Hall I
TG Hall II
2.Completed
May-06
3.Completed
May-07
4.
5.
Completed
6.
in progresscompleted
byJune.'2008
7.
8.
9.
10. PartiallyCompleted
11. PartiallyCompleted
12. ESP + AHP + Compressorhouse (TAC)-(II)
13. Balance of plant (CW, CT,Chem. plant etc.)- I
14. Balance of plant (CW, CT,Ch. plant etc.)- II
-
7/27/2019 Opi-overhauling & Maint. Mgmt
169/183
Date- 31/08/2009
Bunkers
Dec.-08 3/31/2009 3/31/2009 10/10/2008
Y Y Y Y
NA NA NA NA
01 year 01 year 01 year 01 year
Dec.-09 Mar-10 Mar-10 Oct'09
lan
Oil Tanks
Jun-09 Mar-09
Y Y
NA NA
06 Months 06 Months
Dec.-09 Sep-09
lan
DM
Plant
CW
P/ H
CompHouse
(St-I to III)
DMPlant & DMTank
-
7/27/2019 Opi-overhauling & Maint. Mgmt
170/183
Proposed Action
01/10/2003
01/10/2003
10/19/2008
10/19/2008
21/11/2009
lan
AHP
2005-2006 2005-2006 Dec'07
2008-09 2009-10 Remarks
OFS
Next dateof checking
Frequencyof checking
Stage S/DOpportunity
Stage S/DOpportunity
Stage S/DOpportunity
Stage S/DOpportunity
DMPlant CWPH CompressorHouse
Patially Done,in 06-07
As perrequirement
As perrequirement
As perrequirement
As perrequirement
Balance in08-09
5 yrs rollingplan as undercovering all the
structures.
5 yrs rollingplan as undercovering all the
structures.
5 yrs rollingplan asunder
covering all
thestructures.
-
7/27/2019 Opi-overhauling & Maint. Mgmt
171/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
172/183
15.0 MAINTENANCE MANAGEMENT SYSTEM
Contents:
15.1 ANURAKSHNAN SYSTEM: SYSTE
15.2 EQUIPMENTS NOT AVAILABLE FOR MORE THAN 15 DAYS:DATA AVAILA
15.3 EQUIPMENTS WHERE REPEATED FAILURES OCCURRED (CURR
15.4 MAJOR EQUIPMENTS HAVING HIGH VIBRATIONS:DATA AVAILA
15.5 WOC QUANTITATIVE ANALYSIS: DATA AVAILA
15.2 EQUIPMENTS NOT AVAILABLE FOR MORE THAN 15 D
Unit Out since (date)
CHP S/R-2 (St-II) 8/9/2007
CHP RB-4. 5/8/2008 High vibration.
CHP RB-1. 5/1/2008
CHP Pay loader-13116 9/15/2008
Note *: Includes the equipments of Main plant, Offsite, CHP, MGR and DM Plant
15.3 EQUIPMENTS WHERE REPEATED FAILURES OCCURRED (CURRENT FY):
Unit Equipment Name No. of failures with Details Reason
AHD-2 Ash Slurry Pump-4 amming, inoperative lve erod
Equipment Name*
Reason for non-availability
Slew bearing notavailable.
Major over hauling& replacement.
Under B/D ( sparesnot available)
09/04/2009&18/04/2009.
-
7/27/2019 Opi-overhauling & Maint. Mgmt
173/183
OFS-1 CW Pump-6 Gauge c
CHP-1 FG-8.
Unit-1. Generator AVR Sy
Brushes worn out.
CHP-2
S/C-5. High vibration.
CHP-3
S/C-3.
15.4 MAJOR EQUIPMENTS HAVING HIGH VIBRATIONS:
Unit Equipment Name Date of Measurem Measurement Point Monitorin
8/1/2009 MOTOR NDE mm/s
3 TURBINE 8/24/2009 mm/s
4 TURBINE 8/24/2009 mm/s
5 BFP-C 8/28/2009 Main Pump-DE mm/s
07/04/2009,
16/04/2009
&24/04/2009
Tripping on
discharge valve fail,
motor DE brg temp
erratic.01/04/2009
&05/04/2009
Flap gate stuck up/
inoperative.
FG-8 to
Conv-
11
beam
broken.
02/04/2009,
15/04/2009,
22/04/2009
Short
length
of
brush.23/06/2009,
17/06/2009
Teeths
worn
out.
03/06/2009
10/06/2009
02/07/2009
16/07/2009
High vibration.
Scoop tube control
machanism jam.
Teeths
worn
out.
FAN
LPT rear (BrgNo-4)
LPT rear (BrgNo-4)
-
7/27/2019 Opi-overhauling & Maint. Mgmt
174/183
* Please mention details like Overall vel/Displacement,Spike energy-gSE ,mm/sec pk, mic
15.5 WOC QUANTITATIVE ANALYSIS:
Section Break Down Maint. (BD) Preventive Maint.
Raised (No.) Attended (No.) Raised (No.) ended (BM-PP 88 80 0 0
BM-RM 4 1 165 112
TM 67 59 231 222
BoP 214 175 642 622
373 315 1038 956
79 68 371 281EM 140 117 569 448
0 0 0 0
C&I 145 111 161 145
Civil 1 0 0 0
Total 738 611 2139 1830
15.6 STATUS OF CRITICAL SPARES AFFECTING ROUTINE PERFORMANCE OF UNI
ITEMS Avg.Monthly Stock PIPE L
consumption
Mill Spares
4+2Sets 27+2
4+2Sets 22+5
MM(Total)
MM
(CHP)
EM(CHP)
Indent
Grinding Roll
St.I+IIIBull ringsegmentsSt.I+III
-
7/27/2019 Opi-overhauling & Maint. Mgmt
175/183
120T 160
CHP
2+8 sets 2+5
Conv Belt 500m 100m
OFF SITE
MGR Nil
WTP/ETP Nil
Turbine
8000 ltr 10430 ltr
**NOTE : STATION SHOULD IDENTIFY THE LIST OF SPARES AND MONITOR**NOTE : STATION SHOULD IDENTIFY THE LIST OF SPAR
GrindingBalls Stg-II
Ash handling
Crusherhemmer St-I+II.
Lube oil -SP-46
-
7/27/2019 Opi-overhauling & Maint. Mgmt
176/183
Date- 31/08/2009
IS NOT BEING USED
BLE IN ERP (SAP) - ORTOPN2
ENT FY):
BLE IN ERP (SAP) - ORTOPN2
BLE IN ERP (SAP) - ORTOPN2
YS:
Action Plan Present status
DGM(C&M)
PO Placed. DGM(FM)
PO placed. DGM(FM)
DGM(FM)
Action Plan Target Date Present status
d. DGM (AMG) Available.
Responsibility
TargetDate
Abnormal sound inslew bearing. POPlaced.
Slew systemnot available.
Emergencyavailable.
Equipmentoutage.
Pay loader sent
BEML servicecentre Singrauli on24/09/08 for O/H.LOI issued. To beexpected by 15Sept 2009. Equipment
outage.
Responsibility
09/04/2009&19/04/2009
-
7/27/2019 Opi-overhauling & Maint. Mgmt
177/183
alibration required. DGM (C&I) Available.
DGM (CHP) Available.
DGM (EMD) Available.
DGM(CHP)
6/25/2009
Available.
DGM(CHP) Available.
Parameter Value Limit Action Plan Target Date Present st
A-10.90 6.5mm/sA-38.10 24 mm/s
A-64.30 24 mm/s
HOR-18.10 16mm/s
09/04/200
9,
16/04/200
9 &
06/05/200
902/04/200
9
&12/04/2
009
02/04/200
9,
16/04/200
9,
23/04/200
9
10/06/200
9
10/06/200
9
03/07/200
9
16/07/200
9
Responsibility
Available.
Available.
Available.
-
7/27/2019 Opi-overhauling & Maint. Mgmt
178/183
on pp,1*RPM,2*RPM etc.
Condition Based Maint. (CBM) Total
Raised (No.) Attended (No. aised (No Attended (No.)0 0 88 80
0 0 169 113
0 0 298 281
0 0 856 797
0 0 1411 1271
0 0 450 349 16 14 725 579
0 0 0 0
0 0 306 256
0 0 1 0
16 14 2893 2455
S
INE QUANTITY
Enquiry PO
St-III for
12 sets.St-III for
12 sets.
-
7/27/2019 Opi-overhauling & Maint. Mgmt
179/183
20sets
6km.
HE STATUSES AND MONITOR THE STATUS
250T- part
delivery.
-
7/27/2019 Opi-overhauling & Maint. Mgmt
180/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
181/183
atus
-
7/27/2019 Opi-overhauling & Maint. Mgmt
182/183
-
7/27/2019 Opi-overhauling & Maint. Mgmt
183/183