OPG and the Opportunities for New Generation in Ontario Emad Elsayed Vice President Hydroelectric...
-
Upload
brian-sutton -
Category
Documents
-
view
214 -
download
1
Transcript of OPG and the Opportunities for New Generation in Ontario Emad Elsayed Vice President Hydroelectric...
OPG and the Opportunities for
New Generation in Ontario Emad Elsayed
Vice President Hydroelectric Development Ontario Power Generation
to the Electricity Distributors Association
Thunder Bay, Ontario
September 7, 2006
2
OPG Profile
Generated 108.5 TWh in 2005 53.9 TWh in first 6 months 2006
Produces approx. 70% of Ontario’s electricity generation Employs approx. 11,000 employees Operates:
Three nuclear stations (10 operating units, total) Five fossil-fuelled stations 64 hydroelectric stations
Beck 2 GS Lambton GS Pickering B GS
3
Improving Financial Performance
2005 2004
500
450
400
350
300
250
200
150
100
50
Net Income ($millions)
$366$342
$42
Q1-Q2 2006
In May, 2006 OPG’s Credit rating was upgraded by Standard & Poor’s -- short-term commercial paper debt rating upgraded to “A-1 (low)” from A-2.”
4
OPG Helps Moderate Electricity Prices
5
Source: IESO/OPG, January 2006
Ontario Capacity: 30,631 MW OPG Capacity: 22,173 MW (72%)
Coal – 21.4%
Ontario Electricity Supply MixOntario Energy: 156,000 GWh/yr OPG Energy: 109,000 GWh/yr (70%)
Capacity Mix In Ontario
Coal21.0%
Nuclear36.0%
Hydro26.0%
Oil/Gas17%
OPG = 7%
OPG = 22.7%
OPG = 21.6%
OPG = 21%
Energy Mix In Ontario
Oil/Gas8.0%
Hydro22.0%
Nuclear51.0%
Coal19%
OPG = 1%
OPG = 21.0%
OPG = 29%
OPG = 19%
6
Station Location Map
7
OPG’s Hydroelectric Assets
STATIONS PROFILE
NO. OF STATIONS 64
AVERAGE ENERGY 34.0 TWh
CAPACITY 6947 MW
AVERAGE AGE 71 yrs.
NO. OF GENERATING UNITS 240
NO OF RIVER SYSTEMS 26
NO. OF DAMS 232
PLANT GROUPS / WORK CENTRES
PLANT GROUPS 5
WORK CENTRES 22
CONTROL CENTRES 7
Ragged Rapids GS
8
OPG Mandate
Memorandum of Agreement between OPG and Shareholder (Ontario Government), signed August 17, 2005, states in part:
“With respect to investment in new generation capacity, OPG’s priority will be hydro-electric generation capacity.
OPG will seek to expand, develop and/or improve its hydro-electric generation capacity.
This will include expansion and redevelopment on its existing sites as well as the pursuit of new projects where feasible.
These investments will be taken by OPG through partnerships or on its own, as appropriate.”
9
Hydroelectric Development Potential in Ontario
Theoretical potential ~ 12,000 MW Practical/economic potential ~ 5,000
MW Most potential sites are in Northern
Ontario and are restricted by existing government commitments
Need to address key issues: First Nations participation Transmission requirements Restrictions on Northern &
Moose Rivers development Environmental considerations
10
First Nations Participation
Active involvement by First Nations in hydroelectric developments includes potential equity
participation. Memoranda of Understanding/Final
Settlement Agreements signed with: Mattagami FN to explore the
development of the Mattagami Lake Control Dam
Taykwa Tagamou Nation to explore developments on the Abitibi River
Significant involvement by FN’s in the proposed Lower Mattagami River development.
Goal is to create framework for all future developments in the Northern Rivers and Moose River Basin.
Mattagami First Nation Council and OPG representatives
11
Transmission Requirements
Significant development in northern Ontario will require new transmission lines to southern Ontario.
Interim measure necessary for some projects (e.g. Lower Mattagami development).
Longer term requirements to be addressed as part of OPA’s Integrated Power System Plan (IPSP).
12
Restrictions on Northern & Moose Rivers Development
Site release commitments on Northern and Moose Rivers (4,500 MW): Commitment restricts developments greater than 25MW in
four Northern Rivers (Albany, Attawapiskat, Winisk and Severn)
No new development within Moose River basin north of Highway 11 without co-planning with First Nations (exception, Lower Mattagami Project)
Parks designations in North restricts additional 1,500MW (Bill11)
13
Environmental Considerations
Some flooding required for Northern Rivers/Moose River Basin developments
Need harmonization of Federal and Provincial environmental approval
14
Current Active Hydroelectric Development Projects in Northern Ontario
Lac Seul Development 12.5 MW addition to existing Ear
Falls station Construction started in Jan/06 Expected completion Nov/07
Upper Mattagami River Development Replacing 3 existing old stations
(Wawaitin, Sandy Falls, Lower Sturgeon) with 3 larger stations producing 35 MW
Started pre-qualification process for equipment suppliers and contractors
Construction expected to start in mid 2007
Lac Seul: Rock Drilling at the Intake, March 2006
15
Current Active Hydroelectric Development Projects in Northern Ontario (Con’t)
Hound Chute Redevelopment (near Cobalt) Replace an existing 95-year
old station (Hound Chute) with a new larger (9 MW) station
Started pre-qualification process for equipment suppliers and contractors
Construction expected to start in mid 2007
16
Current Active Hydroelectric Development Projects in Northern Ontario (Con’t)
Lower Mattagami River Development Replace existing 75-year old
Smoky Falls station with a new larger station
add an extra generating unit to each of three existing stations (Little Long, Harmon and Kipling)
Net increase in generating capacity is 450 MW
Construction expected to start in late 2007
Little Long
Smoky Falls
Harmon
Kipling
17
Current Active Hydroelectric Development Projects in Northern Ontario (Con’t)
Other Projects Mattagami Lake Control
Dam (5 MW) with Mattagami First Nation
Abitibi River sites with Taykwa Tagamou Nation
Long Lake Control Dam (5-6 MW)
Little Jackfish River Development (132 MW)
Mattagami Lake Control Dam
Long Lake Control Dam
18
Recap
OPG continues to invest in Northern Ontario. OPG will pursue all economically viable hydroelectric developments in the
Province, mostly in Northern Ontario. OPG will seek involvement and partnerships with First Nations. OPG will continue to work with the appropriate government agencies and
stakeholders to address existing development restrictions, transmission constraints and environmental considerations.
19
Other Supply Initiatives: Niagara Tunnel
Sir Adam Beck GS No.1
Sir Adam Beck GS No.2
Sir Adam Beck Pump Generating Station
Outlet
Intake
20
Other Supply Initiatives: Niagara Tunnel (cont’d)
Diverts additional water to Beck hydroelectric stations 500 cubic metres of water per
second 1.6 billion KWh average per
year 10.4 km long
Construction work underway Expected completion: late
2009 90 year life-expectancy Project is on schedule and
within budget OPG is project manager
Niagara Tunnel Boring Machine, “Big Becky”
21
Other Supply Initiatives: Portlands Energy Centre
IESO reports Toronto needs additional 500 MW by 2010
PEC is a 550 MW high efficiency combined-cycle: co-generation capable fuelled by natural gas
Located in Toronto’s Portlands area OPG and TransCanada Energy Ltd.
are partnering to build PEC Environmental assessment and
approvals in place Site clearing is underway in
preparation for construction First power in 2008; fully operational
by 2009
PEC: Artist’s Conception
Site Clearing Underway
22
Nuclear Refurbishment In June, Ont. Govt. Directed OPG to
Undertake feasibility studies re. refurbishment of units at Pickering B & Darlington sites
Begin Environmental Assessment (EA) on Pickering B refurbishment as part of this process
OPG is now assessing the business case for refurbishing Pickering B OPG’s Plant Life Extension Project
Division created in February 2006 On June 15, OPG submitted letter of intent
and project description to CNSC re. potential Pickering B refurbishment
EA for potential Pickering B refurbishment is proceeding as part of business case
Business case study to be reviewed by OPG management and Board in 2008
Solid business case must exist before any decision to refurbish Pickering B (and eventually Darlington) is made
Pickering B
23
New Nuclear
In June, Ont. Govt. has also Directed OPG to: Begin federal approvals process for
new nuclear units at an existing facility• Includes an environmental
assessment
OPG is developing plan of action to meet this directive
OPG believes Darlington is best site for new build Experienced workforce Best-performing multi-unit CANDU
station in Canada in 2004 and 2005 Strong community support Room to build on site
Darlington
Darlington Nuclear Generating Station
24
OPG’s Fossil-Fuelled Stations
Ontario Govt. responded in June to the OPA’s Supply Mix Report (Dec. 2005) The Govt. has asked OPA to determine
how best to replace coal-fired generation
in Ontario at the earliest possible time As a result…OPG’s coal-fired
stations to continue operating beyond 2009
OPG to meet all environmental regulations governing the operation of its coal-fired stations
OPG will make additional, prudent investments in environmental equipment and systems to further improve environmental performance of its coal-fired plants
Lambton GS
Nanticoke GS
25
Lakeview Stack Demolition
Lakeview Generating Station in Mississauga: in service:1961 capacity 1,140 MW lifetime output: 214 TWh 275 employees permanently shut down in April 2005
June 12, 2006: stack demolition Site now being cleared of
remaining equipment Potential for future high-efficiency
gas plant at the site
26
The Trust and Confidence of Communities is Essential to our Operations
Kakabeka Falls GS, 100th Anniversary Open House
Pickering Neighbourhood Walk Employee Volunteers
Darlington Bird houses OPG receives Pickering 2005 Local Business Award
27
OPG: The Big Picture
Contributing to Ontario’s Electricity supply
Continuous improvement Meeting our
commitments Open, transparent and
accountable Reliable Providing value to our
shareholders -- the people of Ontario
OPG and the Opportunities for
New Generation in Ontario Emad Elsayed
Vice President Hydroelectric Development Ontario Power Generation
to the Electricity Distributors Association
Thunder Bay, Ontario
September 7, 2006