On the Road to REDD+: The UN-REDD Programme's Support to REDD+ Readiness 2008-2013
Operational Programme Innovation and Competitiveness …OPIC 2014-2020, 2014BG16RFOP002 March 2015...
Transcript of Operational Programme Innovation and Competitiveness …OPIC 2014-2020, 2014BG16RFOP002 March 2015...
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Operational Programme
„Innovation and
Competitiveness”
2014-2020
March 2015
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page. 2 of 274
TABLE OF CONTENTS
1. Strategy for the operational programme's contribution to the Union strategy for
smart, sustainable and inclusive growth and to the achievement of economic,
social and territorial cohesion ...................................................................................... 7
1.1. Strategy for the operational programme's contribution to the Union strategy for
smart, sustainable and inclusive growth and to the achievement of economic,
social and territorial cohesion ...................................................................................... 7
1.1.1. Description of the programme‘s strategy for contributing to the delivery of the
Europe 2020 strategy and to the achievement of economic, social and territorial
cohesion. ....................................................................................................................... 7
1.1.2. Justification for the selection of thematic objectives and corresponding
investment priorities ................................................................................................... 42
1.2. Justification of financial allocation ............................................................................ 48
2. Proirity Axes .............................................................................................................. 55
2.1. Priority Axis 1: Technological development and Innovation .................................... 56
2.1.1. Investment Priority 1.1. Technological development and innovation ....................... 56
2.1.2. Performance framework of the priority axis .............................................................. 66
Categories of intervention ........................................................................................................ 67
2.2. Priority Axis 2: Entrepreneurship and Capacity for growth of SMEs ....................... 69
2.2.1. Investment Priority 2.1. Access to finance for supporting entrepreneurship ............. 69
2.2.2. Investment Priority 2.2: Capacity for SMEs to grow ................................................. 75
2.2.3. Performance framework for the implementation of the priority axis ........................ 83
Categories of intervention ........................................................................................................ 84
2.3. Priority Axis 3: Energy and Resource Efficiency ...................................................... 86
2.3.1. Investment Priority 3.1: Energy technologies and energy efficiency ........................ 87
2.3.2. Investment Priority 3.2: Resource Efficiency ............................................................ 92
2.3.3. Performance framework for the implementation of the priority axis ........................ 97
Categories of intervention ........................................................................................................ 98
2.4. Priority Axis 4 – Removing bottlenecks in security of gas supplies ........................ 100
2.4.1. Investment priority 4.1: Improving energy efficiency and security of supply
through the development of smart energy transmission systems ............................. 100
2.4.2. Performance framework for the implementation of the priority axis ...................... 104
Categories of intervention (by priority axis) .......................................................................... 105
2.5. Priority Axis 5 – Technical Assistance .................................................................... 106
Categories of intervention (by priority axis) .......................................................................... 112
3. Financial plan OPIC 2014-2020 ............................................................................... 114
4. Integrated approach to territorial development ........................................................ 117
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page. 3 of 274
5. Specific needs of geographical areas most affected by poverty or target groups
at highest risk of discrimination or social exclusion ................................................ 120
6. Specific needs of geographical areas which suffer from severe and permanent
natural or demographic handicaps ........................................................................... 120
7. Authorities and bodies responsible for management, control and audit and the
role of the relevant partners...................................................................................... 121
7.1. The authorities and bodies responsible for management, control and audit. ........... 121
7.2. Involvement of relevant partners ............................................................................. 122
8. Coordination between the funds, EAFRD, EMFF and other Union and national
funding instruments, and EIB .................................................................................. 128
9. Ex-ante conditionalities ............................................................................................ 137
9.1. Description of the actions which will be taken to implement ex-ante
conditionalities, responsible authorities and timeframe of these actions ................. 138
10. Reduction of the administrative burden for the beneficiaries .................................. 264
11. Horizontal principles ................................................................................................ 268
12. Separate Elements .................................................................................................... 272
12.1. Relevant partners involved in preparation of programme ........................................ 272
TABLES
Table 1-1: Macroeconomic projections4F ...................................................................... 10
Table 1-2: Barriers for innovation development in selected sectors ............................... 17
Table 1-3: Enterprises by size, number of employees and value added ......................... 20
Table 1-4: Enterprises by size, sectors, number of employees and value added by sectors
................................................................................................................................. 20
Table 1-5: Distribution of financial instruments for OPC 2007-2013 ............................ 36
Table 1-6: Overview of the justification for the selection of thematic objectives and
investment priorities ................................................................................................ 43
Table 1-7: Overview of the investment strategy of the Operational Programme ........... 53
Table 2-1: Programme-specific result indicators for ERDF ........................................... 57
Table 2-2: Common and programme specific result indicators for the ERDF ............... 63
Table 2-3: Performance framework for the implementation of Priority Axis 1 ............. 66
Table 3-1. Financial plan of the Operational Programme giving the annual commitment
of the European Regional Development Fund (ERDF) in the Operational
Programme (Euro) per category of regions * ........................................................ 114
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page. 4 of 274
Table 3-2 Financial plan of the Operational Programme, showing the amount of the total
financial allocation of each fund in the Operational Programme, national funding
and co-financing by priority axis for the whole programming period (EUR)....... 115
Table 3-3 Breakdown of the financial plan by priority axis, fund, category of region and
thematic objective for the ERDF, the ESF and the Cohesion Fund (Table 18b 19)
(Art. 87 (d) (ii) of the General Regulation) (EUR) ............................................... 116
Table 7-1: Identification and contact details of the relevant competent authorities/bodies
............................................................................................................................... 121
Table 9-1 Applicable ex-ante conditionalities and assessment of their fulfilment ....... 139
Table 9-2 Actions to fulfil applicable general ex-ante conditionalities ........................ 246
Table 9-3 Actions to fulfil applicable thematic ex-ante conditionalities ...................... 249
FIGURES
Fig. 1. Innovative characteristics of SMEs ..................................................................... 15
Fig. 2. Business expenditures on R&D by economic activity (% of total business
expenditure on R&D) .............................................................................................. 16
Fig. 3. Structure of the Bulgarian export by groups of goods for 2011 .......................... 23
Fig. 4. Final energy consumption (FEC) in Bulgaria during the period 2000-2011 by
economic sectors ..................................................................................................... 26
Fig. 5. Primary and final energy intensity 2000-2011 ..................................................... 27
Fig. 6. Protecting and restoring environment costs by sectors (as % of GDP) ............... 29
Fig. 7. Distance from the average values for EU ............................................................ 30
Fig. 8. Resource productivity ......................................................................................... 31
Fig. 9. Areas of support under Operational Programme ―Development of the
Competitiveness of the Bulgarian Economy‖ 2007- 2013 ...................................... 33
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 5 of 274
LIST OF ABBREVIATIONS
BSMEPA Bulgarian Small and Medium Enterprises Promotion Agency
CSF Common Strategic Framework
DAE Digital Agenda for Europe
EFRD European Fund for Regional Development
EMFF European Maritime and Fisheries Fund
ESIF European Structural and Investment Funds
EU European Union
ExEA Executive Environment Agency
FDI Foreign Direct Investment
GDP Gross Domestic Product
GVA Gross Value Added
IP Investment Priority
IP Intellectual Property
RIS 3 Innovation Strategy for Smart Specialization
ICT Information and Communication Technologies
MA Managing Authority
MAF Ministry of Agriculture and Food
MEE Ministry of Economy and Energy
MES Ministry of Education and Science
MEW Ministry of Environment and Water
NSI National Statistics Institute
NIF National Innovation Fund
NSPSMEs National Strategy for Promotion of SMEs
OP Operational Programme
OPDCBE Operational Programme Development of the Competitiveness of Bulgarian
Economy
OPE Operational Programme Environment
OPGG Operational Programme Good Governance
OPHRD Operational Programme Human Resourse Development
OPIC Operational Programme Innovation and Competitiveness
OPRG
OPSEIG
Operational Programme Regions in Growth
Operational Programme Science and Education for Intelligent Growth
OPTTI Operational Programme Transport and Transport Infrastructure
PA Priority Axis
PMAF Program for Maritime Affairs and Fisheries
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 6 of 274
R&D Research and Development
RES Renewable Energy Sources
RDP Rural Development Programme
SEDA Sustainable Energy Development Agency
SME Small and Medium-size Enterprise
TO Thematic Objective
UMIS Unified Management Information System for the EU Structural Instruments
in Bulgaria
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 7 of 274
1. STRATEGY FOR THE OPERATIONAL PROGRAMME'S CONTRIBUTION TO THE
UNION STRATEGY FOR SMART, SUSTAINABLE AND INCLUSIVE GROWTH AND
TO THE ACHIEVEMENT OF ECONOMIC, SOCIAL AND TERRITORIAL COHESION
This chapter contains the description of the strategy of the Operational Programme
―Innovation and Competitiveness‖ (OPIC) and the justification for the financial allocation
to each thematic objective and investment priority.
1.1. Strategy for the operational programme's contribution to the Union
strategy for smart, sustainable and inclusive growth and to the
achievement of economic, social and territorial cohesion
1.1.1. Description of the programme’s strategy for contributing to the delivery of the
Europe 2020 strategy and to the achievement of economic, social and
territorial cohesion.
STRATEGIC CONTRIBUTION OF OPIC 2014-2020
The OPIC 2014-2020 strategy, as a part of the implementation of the EU structural and
investment funds (ESIF) in Bulgaria, according to the Partnership Agreement 2014-
2020, is closely related to the objectives for Growth and Jobs and Bulgaria‘s
contribution to achieving the three complementary types of growth according to the
"Europe 2020":
Smart growth: developing an economy based on knowledge and innovations;
Sustainable growth: promoting a greener and more competitive economy and a
more efficient use of resources;
Inclusive growth: fostering a high-employment economy leading to social and
territorial cohesion.
OPIC 2014-2020 directly engages in smart growth (under priority axes 1, 2) and
sustainable growth (under priority axes 3 and 4), aiming at complementary effect
in terms of inclusive growth.
The support under OPIC 2014-2020 aims at addressing the needs, overcoming the
challenges and seizing the opportunities for development of Bulgarian economy,
defined according to:
Documents0 F
1 Objectives/priorities/needs
The National Development
Programme: Bulgaria 2020 (NDP BG
2020) – the leading strategic and
Strategic Oblective 3: Increasing the
competitiveness of the economy by
providing a favourable business
1 COM(2013) 352 final, Council‘s Recommendation on the National Reform Programme of Bulgaria for 2013 and the
Council‘s Opinion on the convergence programme of Bulgaria for the period 2012-2016 Ref. Ares(2012)1273775 -
26/10/2012, Position of the Commission services on the development of the Partnership Agreement and the
programmes of Bulgaria for the period 2014-2020 , etc.
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 8 of 274
Documents0 F
1 Objectives/priorities/needs
programme document which defines the
objectives of the policies for socio-
economic development of the Republic of
Bulgaria by 2020, as well as the national
decisions for growth in the context of
"Europe 2020" Strategy.
environment, promoting investments,
applying innovative solutions and
increasing resource efficiency
Priority 5 ―Support innovation and
investment activities to increase the
competitiveness of the economy‖
Priority 7 ―Energy security and increasing
resource efficiency‖
The National Reform Programme
(NRP) reflects on an annual basis the
country's progress in implementing the
national targets in the context of Union
Strategy ―Europe 2020‖ and the progress
on the recommendations of the Council
National Objective 2 Investment in R&D
to the amount of 1.5% of the GDP; support
for promoting R&D and innovation
activities of enterprises (in accordance with
the flagship initiative "Innovation Union")
National Objective 3 under ―Climate and
Energy‖ Package – ―Reaching 16% share
of renewable energy sources in the gross
final energy consumption1F
2 and increasing
energy efficiency by 25% till 2020"(in line
with the flagship initiative UResource
Efficient EuropeU)
Position of the Commission services on
the development of the Partnership
Agreement and the programmes of
Bulgaria for the period 2014 – 2020
Priority 2 Innovation-friendly business
environment
Priority 3 Modern infrastructure for
growth and jobs
Priority 4 Environmentally sound and
resource-efficient economy
Recommendation of the Council on the
National Reform Programme of Bulgaria
for 2013 also containing the Council‘s
opinion on the Convergence programme
of Bulgaria 2012-2016
Recommendation 4 ―…by enhancing the
cooperation between education, research
institutes and enterprises"
Recommendaion 5 "... to improve the
access to finance for SMEs and start-ups."
Recommendation 7 ―….Accelerate
electricity and gas interconnector projects
and enhance the capacity to cope with
disruption. Step up efforts to improve
energy efficiency"
Recommendation of the Council on the
National Reform Programme of Bulgaria
for 2014 also containing the Council‘s
Recommendation 6 ―…..Accelerate
interconnector projects with neighbouring
Member States and candidate countries,
2 The target is achieved – in 2012 the share was 16.3%. Currently efforts are focused not on increasing RES but rather
on the need for balancing the energy system.
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 9 of 274
Documents0 F
1 Objectives/priorities/needs
opinion on the Convergence programme
of Bulgaria 2012-2016
in particular for gas, and enhance the
capacity to cope with disruptions.
Partnership Agreement of the Republic
of Bulgaria outlining the support under
the European Structural and Investment
Funds for the period 2014 – 2020
Strategic priority 2: Scientific research,
innovation and investment for smart
growth
Strategic priority 3: Connectivity and
green economy for sustainable growth
OPIC 2014-2020 is an essential tool for the implementation of the policies laid down in
the following national strategies:
The National Strategy for Promotion of Small and Medium–size Enterprises
2014-2020, representing the vision of the Republic of Bulgaria on state support
for SMEs in line with the EU policy. The need to create about 12 000 new SMEs
distributed in the relevant sectors of the economy, especially in the industrial and
knowledge-intensive services, has been taken into account. OPIC 2014-2020
contributes to achieving the objectives in five priority areas of the National
Strategy for Promotion of SMEs – entrepreneurship, access to finance, skills and
innovation, environment and internationalisation.
Innovation Strategy for Smart Specialisation of the Republic of Bulgaria
(RIS3), which has the nature of an ex-ante continionality for OPIC 2014-2020 and
aims at ensuring an effective and coordinated management of innovation
processes; strengthening the innovation system by building a modern innovation
and scientific infrastructure, enhancing human capacity in response to the needs of
science and industry and introduction of specific financial instruments of support;
support for the digital growth and e-government. The strategy deals with the
approach of determining thematic objectives (based on the so-called process of
entrepreneurial discovery) with the potential to become ―generators of growth" for
achieving significant economic impact at regional and national level.
OPIC 2014-2020 has also been developed in line with the objectives of:
The Energy Strategy of the Republic Bulgaria until 2020, representing the
country's vision for the sector in accordance with the current European framework
and the global trends in energy technology. The key challenges are the high
energy intensity of production in Bulgaria, the high dependence on imported
energy resources and the need for environmentally sound development. OPIC is in
line with the strategy priorities for ensuring security of energy supply,
incompliance with the objectives to increase the production of renewable energy
and improving the energy efficiency.
The Strategy for e-Governance in Bulgaria for the period 2014-2020 and The
National Programme "Digital Bulgaria 2015", which recognizes ICT as a
driver of innovation andeconomic growth. The Programme sets the parameters for
the development of the information society (IS) and the digital technologies in
Bulgaria, leading to the implementation of the EU objectives defined in the
Digital Agenda for Europe (DAE).
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 10 of 274
The EU Strategy for the Danube Region in Bulgaria, especially with respect to
entrepreneurship innovation activity, increasing the competitiveness and
efficiency of enterprises.
The Strategy for Sustainable Tourism Development on Bulgaria 2014-2030 which aims at promoting the competitiveness and the efficiency of the Bulgarian
tourism sector through the best usage of natural and antropogenic resources in line
with the market requirements and consumer expectation for sustainable tourism
development.
GENERAL NEEDS AND CHALLENGES IN THE IMPACT AREA OF
OPIC 2014-2020
As a small and open economy with a currency pegged to the euro, Bulgaria is heavily
dependent on foreign markets and foreign investment, as been demonstrated by the
effect of the global financial and economic crisis on the country‘s growth rate. A
characteristic of the Bulgarian economy is also that presently its competitive advantages
are formed on the basis of the low price of the underlying factors – labour, natural
resources and energy, rather than on the basis of special factors such as innovation,
productivity, skilled workforce, research and technological development (which are the
basis for long-term competitiveness). This determines the ambition of the OPIC 2014-
2020 for strengthening the long-term competitiveness of the Bulgarian enterprises in
clear compliance with the European industrial policy:
In the Eurostat projections for the period 2010-2060 the population of Bulgaria will
decrease by nearly 27% and the share of the population over 65 will reach over 32.6% 3F
3,
while that of children aged under 15 will shrink to 13%. According to the World Bank
estimates, from 2012 to 2050 Bulgaria will have the most rapidly shrinking working age
population in the world. The greatest concern is that the population between the ages of
15 and 24 is expected to fall by 41%, which will have a direct impact on the
performance and structure of the education sector and the labour market, and
respectively, on the overall economy.
In this sense, the risks associated with the economic growth in Bulgaria, can be
differentiated as external and internal. The economic activity in the EU, the trends in
energy development and the volume of FDI are key external aspects of the growth
forecast. Increasing the productivity, efficiency and innovation of Bulgarian enterprises
are fundamental internal factors that are able to mitigate to some extent the impact of
the deteriorating demographic processes. In a relatively stable external environment,
growth will depend on a combination of reforms in key sectors with investments under
OPIC 2014-2020, in support of export-oriented economy based on knowledge,
innovation and sectors with high added value.
Table 1-1: Macroeconomic projections4F
4
2013 2013 2014 2015 2016 2017
Indicator
Level
(mln. BGN)
Rate of
change
Rate of
change
Rate of
change
Rate of
change
Rate of
change
3 Eurostat, News Release, 80/2011 - 8 June 2011, Population projections 2010-2060 4 Convergence Programme of the Republic of Bulgaria –2014-2017, updated April 2014
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 11 of 274
2013 2013 2014 2015 2016 2017
Indicator
Level
(mln. BGN)
Rate of
change
Rate of
change
Rate of
change
Rate of
change
Rate of
change
Real GDP (at 2012 prices) 78 762 0.9 2.1 2.6 3.4 3.4
Nominal GDP 78 115 0.0 3.3 4.4 5.2 5.2
Components of real GDP
Private consumption 50 209 -2.3 1.3 3.0 4.3 4.4
Government consumption 12 416 2.5 2.4 2.2 2.4 2.3
Gross fixed capital formation 16 648 -0.3 2.1 4.3 5.4 6.0
Change in inventories and net acquisition of assets (% of the
GDP)
309 0.4 0.4 0.5 0.5 0.5
Export of goods and services 56 701 8.9 6.9 5.9 6.1 6.2
Import of goods and services 57 521 5.7 6.3 6.6 7.1 7.4
Contributions to real GDP growth (p.p.)
Final domestic demand - -1.2 1.7 3.2 4.3 4.5
Change in inventories and net acquisition of assets
- 0.0 0.2 0.0 0.0 0.0
External balance of goods and
services - 2.0 0.3 -0.6 -0.9 -1.1
As specified in the Partnership Agreement 2014-2020, the objectives and priorities
identified in the relevant strategic documents and the results from the previous
programming period, OPIC 2014-2020 will address the following key needs and
challenges, which the Bulgarian economy is facing:
low degree of innovativeness of Bulgarian enterprises as a result of
insufficient cooperation between business, academia and universities, small in
volume and inefficient investment in R&D and innovation, and lack of adequate
infrastructure and environment for innovation
Bulgarian SMEs are at 108th
position among 148 countries in terms of business
sophistication and innovation5. Bulgaria is the last in the EU in innovation performance
and the last but one in the share of SMEs that have marketed new products or services
(17% compared to 39% for the EU). The low level of innovative activity leads to a
strong price competition from countries with lower production costs and a decline in the
market share of Bulgarian exports in a number of leading industries (light industry, food
processing, pharmaceuticals, iron and steel production, etc.). On the other hand, there is
a low degree of fruitful collaboration – development and introduction of innovative
products with a high added value for which there is also a market demand – between
5 The Global Competitiveness Report 2013–2014
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 12 of 274
business (especially SMEs), educational institutions and R&D organisations, which is a
proven prerequisite for the achievement of economic development and sustainability.
difficult access to sources of funding and low investment activity - only
16.766 percent of the Bulgarian SMEs have access to public financial support
including guarantees
Micro, small and medium-sized enterprises have difficulties in ensuring funds for
investments in tangible and intangible assets and the so-called technology transfer, and
as a result of the crisis – even for working capital. Businesses use primarily personal
savings (62%) and bank loans to finance investments7. A huge potential for increase has
those businesses who use retained earnings and the ones that take advantage of the
financial capacity of the EU funds, incl. JEREMIE. In early 2012, access to finance is
very difficult for 69% of the enterprises. Securing funding for their activities depends
heavily on the stage of their development. Credit is available for enterprises with longer
financial history rather than younger ones – only 27% of the enterprises established
after 2010 have used bank loans.
Constrained investment in the economy leads to limiting the opportunities for economic
growth and creates barriers to the development of the innovation potential of enterprises
and achieving rapid growth. On the other hand, the use of obsolete and outdated
equipment seriously deteriorates the efficiency and effectiveness of production with
view of production inputs – raw materials, fuel, energy and labour costs per production
unit, and has negative effect the competitiveness of enterprises.
insufficient entrepreneurial activity and sectoral structure of the economy
considerably different from the EU countries
Traditionally, banks rarely provide resources for start-ups especially in the high- and
medium- technology sectors, sectors of the knowledge-intensive services and of R&D,
where long term assets are few and do not serve as collateral. Thus the necessity for
continued financial instruments in this area is urgently needed on the basis of the
experience with the JEREMIE. Nearly 6% of the SMEs (between 1200 and 1500 in
total) have an annual turnover growth over 20% and constantly seek opportunities to
finance the expansion of their business. They create between 35% and 40% of the added
value generated by SMEs. There is obviously a need for specially modelled financial
instruments to address these demands.
National Strategy for Small and Medium-sized Enterprises 2014-2020 - Small Business
Act shows the main disadvantage of the structure of Bulgarian companies – a sectoral
structure that is significantly different from the one in the EU, namely:
Bulgaria EU-6
High-tech production: 1% 2%
Low-tech production: 10% 8%
Knowledge-intensive services: 14% 23%
6 The National Strategy for Promotion of SMEs 2014-2020.
7 Study of the entrepreneurship and the prospects of innovation development in SMEs 2012 – 2013,
Bulgarian SMEs Promotion Agency, Sofia, 2013
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 13 of 274
Bulgaria EU-6
Low knowledge-intensive services: 68% 51%
Other sectors: 7% 16%
The share of enterprises operating in the "Retail" sector is over 32% of the SMEs; for
comparison, this index in the EU-27 is 17% on average while for the EU-6 it is only
13%.
The following economic activities have the largest contribution to Bulgaria‘s GVA:
production and distribution of electricity, heat and gas (about 20%), food production
(about 10%), clothing (about 7%), manufacture of other non-metallic mineral products
(about 6%), fabricated metal products, except machinery and equipment (6%), mining
of metal ores (about 4%), manufacture of machinery and equipment for general and
special purposes (about 4 %). None of them falls within the classification of high-
technology sectors, which are the main driver of "knowledge-based economy".
low degree of internationalisation – as per data for 2012, only 3.84% of the
Bulgarian SMEs import from outside the EU, while only 1.76% export outside the
EU. 95% of the SMEs are characterised with a low degree of internationalisation
and the country ranks 27th
in the EU.
The limited technological capacity, guarantees for sustainable quality and low
innovation activity of SMEs are the factors for the poor export, which Bulgarian
enterprises realize at the European and international market. In terms of the summary
indicator of technological readiness8F
8 that explores the presence of the latest technology
(99th
), the level of absorption of technologies by companies (113th
), the levels of foreign
investment and technology transfer (107th
), Bulgaria ranks 44th
among 148 countries.
However, the sectors of mechanical engineering, metal products, computers, optics and
electronics, automotive industry, demonstrate growth in the volume and price of
exports, including labour productivity. Additionally, the production of food and
clothing, medical and pharmaceutical product contributes to it as well. In practice, these
are the sectors with potential for significant contribution to export growth, especially in
third markets.
Attracting foreign investments in targeted economic activities would contribute to better
performance of Bulgaria in the ranking and to this end a proactive investment marketing
for promotion of direct investments should be conducted. As a result the possibilities
and services for investors in Bulgaria provided by Bulgarian institutions will become
more popular.
poor export structure (based primarily on export of raw materials and goods
with relatively low added value)
The existing data on foreign trade of Bulgaria outline the export of raw materials with
the largest share: 43.3% of the total exports in 2012, followed by consumer goods -
23.3% and capital goods - 16.7 %. Compared to the same period of 2011, the share of
consumer goods and energy resources has increased while the share of raw materials
has been reduced (by 3.5% less). High-tech industries achieved 6.1% of the total exports
(in average 16% for the EU), which ranks third in exports per employee behind the
8 The Global Competitiveness Report 2013-2014
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 14 of 274
export of petroleum products and base metals. Overall, Bulgaria‘s export consist of
products that are below the average world level of technological development.
high degree of resource- and especially energy intensity of production, low
degree of implementation of new technologies – the SME sector contributes
significantly to the formation of the profile of the Bulgarian economy as the
highest resource-and-energy-intensive economy per unit of output among the
economies of the EU.
Bulgaria ranks first in energy intensity in EU-27, i.e. the Bulgarian economy consumes
the greatest amount of energy needed to produce a unit of GDP, or by 77.34% more
than the average for the EU 27. Despite the long-term trend of improving the energy
efficiency of the Bulgarian economy, measured by the total energy efficiency index
ODEX, in 2011 Bulgaria ranks last in energy efficiency at EU- 27 level, which is one of
the factors limiting the productivity and competitiveness of enterprises in Bulgaria. The
high energy intensity of the industry is due to physically outdated and obsolete
technologies, limited access to new best practices, systems and models for energy and
efficiency production.
The period of the crisis 2008-2009 did not allow for capital investments of strategic
importance and led to a lasting trend of reducing expenditure, both public and private.
Consequently a particularly serious difficulty for the SMEs proves to be the provision of
free resources for investment in improving the energy and resource efficiency of their
operations. According to a case study9 F
9, the evaluation of the Bulgarian entrepreneurs in
terms of the state of technological equipment in their companies according to the EU
standards shows that only in 17% of them it is modern, and for 52% it is at an
acceptable level. Only 27% of the entrepreneurs say they have had the opportunity to
make investments for upgrading the technology in recent years.
The upgrading and improvement of technologies makes production processes more
resource-efficient and more environmentally-friendly, influences the increase of energy
efficiency and enhances business competitiveness by achieving lower production costs
and diminishing the dependence in supply of raw materials.
vulnerability to gas supply disruptions – the Republic of Bulgaria is practically
100% dependent on gas imports from Russia (transited through the territories of
Ukraine, Moldova and Romania) and does not have any alternative sources and
routes for natural gas supply.
Bulgaria was the most affected EU Member State during the gas crisis of January 2009,
when supplies of Russian gas through the territory of Ukraine were interrupted for two
weeks.
The development of adequate infrastructure facilities and gas interconnections with
neighbouring countires in particular would secure uninterruptible and diversified
supplies, as well as secure the necessary conditions for the physical operation of the
regional gas market in South East Europe.
Building sustainable and diversified energy systems, secure energy supplies, efficient
use of resources and innovative solutions are crucial to the long-term sustainable
growth, job creation and quality of life.
9 Study of the entrepreneurship and the prospects of innovation development in SMEs 2012 – 2013,
Bulgarian SMEs Promotion Agency, Sofia, 2013.
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 15 of 274
SPECIFIC AREAS OF IMPACT OF OPIC 2014-2020
Innovation performance
As the Innovation Strategy for Smart Specialisation (RIS3) has identified, Bulgaria is in
the group of ―modest innovators‖ whose performance is more than 50% below the
average for the EU-27 10F
10, and ranks last in innovation performance among EU-27.
Innovation creates sustainable competitive advantages and as a result of promoting
innovation, the Bulgarian economy will be able to move up higher in the value chain. In
this regard OPIC 2014-2020 is aimed at special impact in terms of Bulgarian innovation
performance in the following indicators: number of local providers1F
11, (local business
entities engaged in the process of creating innovation), contribution to the value chain2F
12,
collaboration between business and academia in the field of R&D3F
13, capacity for
innovationF
14, nature of competitive advantages
15F
15.
Fig. 1. Innovative characteristics of SMEs
The innovative characteristics of Bulgarian SMEs compared with those of EU-27 show
most significant distance from the EU-average in indicator ―collaboration‖. The main
recommendation16
of the Council of EU about innovations and competitiveness
concerns namely partnerships between universities, research centres and industry.
Promoting the exchange of ideas, technology transfer and commercialisation of research
results are crucial for the ability of the Bulgarian research system to generate significant
10 According to Innovation Union Scoreboard 2013 11 From 61 place in 2008-2009 to 108 place in 2013-2014 according to the Global Competitiveness report. 12 From 86 place in 2008-2009 to 116 place in 2013-2014 according to the Global Competitiveness report. 13 From 92 place in 2008-2009 to 117 place in 2013-2014 according to the Global Competitiveness report. 14 From 80 place in 2008-2009 to 103 place in 2013-2014 according to the Global Competitiveness report. 15 From 100 place in 2008-2009 to 113 place in 2013-2014 according to the Global Competitiveness report. 16
Recommendation of the Council on the NRP 2013 and the opinion on the Convergence Programme of Bulgaria
2013-2016 from 9th July 2013
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 16 of 274
economic impact. Bulgarian economy has not yet reached the stage of transition from
efficient economy to a higher level of development (―knowledge-based economy‖)17F
17,
which puts it into the position of ―catch-up‖ state. OPIC 2014-2020 will seek
opportunities to accelerate the transition towards a knowledge-based economy by
promoting the high-tech sector and knowledge-intensive services –promotion of
investment in the thematic areas of intense innovation development and innovative
horizontal policies in full compliance with RIS3.
In order to get closer to the EU average, Bulgaria has to make further efforts on
coordinated support, aimed at increasing the efficiency and ―knowledge-based
economy‖ indicators (high level of development). The innovation is seen as an integral
element of the competitiveness. According to an evaluation report for Bulgaria,
commissioned by the EC, most of the Bulgarian companies work under the technology
threshold, and ―their growth is based on improvements in productivity that are neither
related to R&D and dissemination of knowledge, nor generation of knowledge‖ 18F
18. Even
the FDI attracted so far in the economy have a limited contribution to technology
transfer. To improve competitiveness, Bulgaria should emphasize both on the quality of
the workforce and on capacity building to adopt and adapt the European and
international knowledge and technology. This requires that the innovation policy should
be oriented toward specific areas and should combine promotion of R&D-based
innovation activities with those which are not directly related to R&D (such as ICT).
The most serious reason for Bulgaria‘s lagging behind in innovation is the share of the
total amount of investments in R&D and innovations in comparison with the world's
leading economies and those of the other EU Member States.
Fig. 2. Business expenditures on R&D by economic activity (% of total business
expenditure on R&D)
Source, NSI, Bulgaria, http://www.nsi.bg
In the private sector, the majority of enterprises, especially micro and small enterprises,
do not have their own technologies and capabilities to develop innovations which are of
significant importance for specific branch or group of branches. SMEs face number of
17 http://www3.weforum.org/docs/WEF_GlobalCompetitivenessReport_2013-14.pdf 18 Radoshevich, S., Strogilopulus, 2012. Strategies for smart specialization in the field of research and innovation.
Assessment of Bulgaria. European Commission, 2012
Tho
usa
nd
Le
vs
Agriculture, forestry and fishing (% of
total BERD)
Manufacturing (% of total BERD)
Wholesale and retail trade; repair of
motor vehicles and motorcycles (% of
total BERD)
Information and communication (% of
total BERD)
Human health and social work activities
(% of total BERD)
Total BERD, Thousand Lev
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 17 of 274
difficulties associated with the lack of qualified staff for innovation, access to applied
research results and funding for such studies.
In this regard, OPIC 2014-2020 will contribute to increase the investment (public and
private) in R&D and innovation, particularly in the sectors of manufacturing and
services, and with the aim to achieve the national goal of 1.5% share of GDP of R&D
costs. Opportunities will be sought to promote business to business partnerships and
business and academic cooperation, including internationally, to increase the level of
generated and transferred ideas, to achieve better exchange of specialists and extended
investment activity.
Table 1-2: Barriers for innovation development in selected sectors
Sector Specific to the sector barriers for innovation
development
Interrelated
obstacles to
innovation
ICT Inadequate system for protecting ICT‘s assets,
such as innovative services and business process
innovation
Shortage of skilled
labor
Lack of
cooperation
between
businesses,
universities and
research units
Energy
inefficiency
Mechatronics Large number of small players at the base line of
the value chain
Medicine and
pharmacy
Undeveloped system and inappropriate
infrastructure for research at initial stage and
tests.
Knowledge
intensive
services
Inappropriate system for protecting IP assets,
such as innovative services and business process
innovation
Shortage of entrepreneurial skills
Low level of information for funding
opportunities and limited skills and capacity to
access such opportunities
Low level of cooperation between researchers
and business.
Ineffective
implementation of
IPR
Limited access to
funding
OPIC 2014-2020 aims also at overcoming main barriers to innovations in selected areas
(Table 1-2) in accordance with to RIS 3 goals..
The Innovation Strategy for Smart Specialisation addresses the need for synchronisation
of efforts in the field of economic development, research and innovation, and
strengthening the link between science and business. The draft version of RIS3 provides
for vertical thematic areas (mechatronics and clean technologies, ICT and informatics,
industry for healthy life and biotechnologies, new technologies in creative and
recreative industries) and horizontal policies (ICT and resource efficiency), as well as
technological niches, identified through continuous process of entrepreneurial
discovery. In this context, the investments under Thematic objective 1 of OPIC support
activities exclusively within the thematic areas and horizontal policies of RIS3.
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 18 of 274
In accordance with RIS3 draft version, the innovation policy of the Republic of Bulgaria
in the period 2014 - 2020 will be focused on:
• Innovation potential in the identified thematic areas (for creation and
development of new technologies, leading to competitive advantages and increase of
domestic products and services added value of) and
• Supporting innovations for resource efficiency and ICT applications in
enterprises throughout the industry (for accelerated absorption of technologies)
so that until 2020 Bulgaria passes from the group of "modest innovators" to the
group of "moderate innovators". This will be done by:
• Regular analysis to identify market advantages of the country and to create high
quality scientific potential, which serves the national economy and contributes to
ensuring high quality life for citizens;
• Strengthening the innovation potential and restructuring the economy towards
sectors with potential to be integrated into the EU economy with a maximum benefit
both for the country and for the EU as a whole, sectors with export potential outside the
EU;
• Encouraging private investment in research and innovation;
• Encouraging development and use of resource efficient, environmentally
friendly and wasteless technologies that reduce pollution at the source, allowing for
recycling, while reducing carbon emissions;
• Development of financial instruments tailored to company size and expanding
access to finance for micro, small and medium-sized enterprises and innovative large
companies;
• Development and safeguarding of human potential and talent;
• Development of research and innovation infrastructure (including e-
infrastructure);
• Promoting internationalization of enterprises to enter the international market.
The RIS3 approach is combined: it will support activities to establish and develop
strong links between research and business; creating, attracting and retaining quality
human resource; well functioning infrastructure which favours innovations. The focus
will be entirely on promoting development of the thematic areas by supporting specific
activities addressing the specific challenges of each thematic area identified in the
process of in-depth analysis and a wide range of discussions. Horizontally innovations
for resource efficiency and IT applications in enterprises throughout the industry will be
supported.
One of the conditions for stimulating innovation activity of enterprises according to
RIS3 is the development of integral scientific-research and innovation ecosystem. The
key element of building a favourable environment for innovation is the mutual
coordination and complementarity between the interventions covered by ESIF, national
funds and other EU funds which is explained in details in the respective part of the OP.
Effective and sustainable management of innovation processes and continuous
discovery of entrepreneurial potential is guaranteed by commitment at highest level and
institutionalized coordination and partnership with all stakeholders (government, local
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 19 of 274
authorities, industry, science and NGOs). RIS3 governance is structured at several
levels, described in details in Annex 4.
The priorities will be set up by a Council for Smart Growth. It will carry out vertical
coordination with the ministries, which form a peer network at central level. Two
Councils will play a consultative role in the interaction between the peer network at
central level and the peer network at regional level - The National Innovation Council
(NIC) and The National Research and Innovation Council (NRIC). The peer network at
regional level encompasses representatives from all regional administrations in the
country.
Administrative capacity on each of the vertical thematic areas will be developed in the
units of the peer network at central level, through which the activities and initiatives,
related to RIS3 implementation will be promptly and effectively coordinated.
Knowledge on the financial instruments for RIS3 implementation will be spread out and
support will be given to effective interaction with stakeholders.
On the level of the regional peer network and on the level of NIC and NRIC feedback
from stakeholders in the vertical thematic areas, defined in RIS3, will be received and
analyzed on regular basis. That feedback will serve to measure the progress in the
implementation of measures, to analyze current tendencies and to identify innovation
potential and ideas. This information will be used in the process of activities prioritizing
and elaborating new measures to support innovations.
The enterprises face many difficulties to develop their potential and to become
innovators because of limitations on intellectual property protection. The Bulgarian
legislation in this field is in compliance with EU directives, but does not stimulate
sufficiently local innovation activity. Although these measures have reduced the
irregular acquisition of intellectual property, their implementation remains unequal, and
the perception of the private sector is mostly limited to patents, obtained in international
partnerships. That is why OPIC strategy includes also support for stimulation of policy
developments in the area of intellectual property.
Entrepreneurship
The backbone of the economy are the micro, small and medium enterprises (SMEs) and
despite the low performance during the economic and financial crisis, SMEs remain the
main driving force of economic growth in Bulgaria, contributing to 75% of the
employment (68% in the EU) and 62% of the value added (58% in the EU) 21F
19. In 2012
92% of SMEs are micro, 6.6% - small and 1.2% - medium enterprises.
Although the proportion of SMEs types corresponds to that of the EU-28 in terms of
value added, Bulgarian micro-enterprises are significantly behind the EU-28. The
highest value-added have businesses in the ―Manufacturing‖ industry, followed by the
―Transport, repair of motor vehicles and motorcycles‖ industry and the ―Creating and
disseminating information and creative products; telecommunication‖.
19
National Strategy for Promotion of SMEs 2014-2020.
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 20 of 274
Table 1-3: Enterprises by size, number of employees and value added
Source: NSI, Eurostat, 2012
Table 1-4: Enterprises by size, sectors, number of employees and value added by
sectors
Source, NSI, 2011.
The sectoral structure of the Bulgarian economy differs significantly from that of the
other EU countries. The share of SMEs in high-tech industries, knowledge intensive
services and R&D is significantly low and therefore the stimulation of entrepreneurship
and start-ups in these sectors is really important.
Entrepreneurship is a key factor for the development of local economies. In principal,
the more enterprises created on a certain territory, the more the chances for higher
incomes and prosperity of local economy. The viability of the local economy is ensured
by the existence of sufficient number of SMEs. The high number of SMEs ensures
wider diversification as well as resistance of the local economy to dynamic changes.
The largest numbers of enterprises per 1000 inhabitants in Bulgaria are in the regions of
Sofia (capital), Varna, Burgas, Blagoevgrad, Plovdiv, and the most threatened is the
local economic sustainability in the regions of Kardzhali, Targovishte, Montana, Vratsa,
Vidin and Silistra.22F
20
In general the entrepreneurship in Bulgaria is dominated by micro enterprises with less
than 10 employees. Stimulating the entrepreneurial activity is related to a number of
factors. Despite that according to the ―doing business‖ indicator Bulgaria takes sixth
20
Regional Profiles: indicators of development, Institute for Market Economics, Sofia, 2013
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 21 of 274
place among the EU-27, the conditions associated with the funding and provision of risk
for the entrepreneurs remain as a barrier to those who want to start their own business
and choose entrepreneurship as an opportunity.
SMEs, particularly micro and small enterprises face difficulties in access to finance as
the major omissions are related to meeting the financial needs of micro-enterprises.
Microfinance is one of the most popular instruments for smaller companies, start-ups
and entrepreneurs who are experiencing problems accessing the banking system, which
is the main source of corporate finance in the country. Consequently, the main sources
of financing of micro-enterprises are mainly "funds from the owner", followed by
"government grants" and "short-term loans, bank overdrafts and credit lines". It should
be noted that access to basic banking products is limited to micro-enterprises that have
higher turnover and appropriate assets to ensure the collateral. Providers of
microfinance institutions in Bulgaria are not currently able to meet the growing demand
for micro-enterprises, and their presence has gradually decreased, while borrowing costs
remain high for many potential customers. There is therefore a need to promote the
development of microfinance institutions.
Although usually lower, the demand for equity capital in Bulgaria exists among all
categories of SMEs, especially among small and medium enterprises, as observed is the
need in the segment between 1 and 5 million Euro for investment. However, the supply
of equity capital in the country is almost non-existent in the last few years, especially
for small investments up to 5 million Euro, mainly due to the structural limitations of
the financial sector and unstable business environment in the country. In the near future,
only supported by JEREMIE initiatives can be considered as potential sources of equity
capital. Shortage21
of risk capital is estimated to € 30.6 million / year, lack of equity for
companies in a more mature stage of development - € 88 million / year.
Ex-ante analysis of financial instruments concluded that SMEs in the country need
primarily easier access already provided into existing measures and public services,
while they also need methodological, technical assistance in providing the needed
externally leverage finance.
The opportunities for funding in the field of entrepreneurship through financial
instuments provided by OPIC 2014-2020 will stimulate the creation of new enterprises,
the successful implementation of new business ideas, and the successful and accelerated
development of existing entrepreneurs, leading to economic stabilisation and growth,
respectively to the creation of new jobs, partially offset by identified in the ex-ante
evaluation of the implementation of financial instruments financing gap for SMEs.
Innovative entrepreneurship requires strong expertise, specialised platforms and access
to funding mostly through financial instruments. There are serious opportunities for
improvement and extension of current funding instruments for entrepreneurship and
innovation, OPIC 2014-2020 will focus on the implementation of those ones which are
working properly and will address the market needs of developing entrepreneurs to
implement innovations and to support commercialisation of R&D with proven market
demand. With regards to the instruments for support entrepreneurship, Bulgaria has the
chance to prove itself as a regional leader.
Bulgaria supports the overall European policy for SMEs development in new areas
related to European and regional challenges as creative and cultural industries, products
21
Preliminary analysis of ex-ante evaluation of the financial instruments
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 22 of 274
and services aiming to overcome the demographic problems, aging of population, social
entrepreneurship, etc. With this specific range of potential beneficiaries of ERDF funds,
grant funding is a way to encourage participation with quality projects that make a
significant contribution to the implementation of the national and European policies.
According to the ISSS, among the sectors of creative industries most dynamically are
developing information technology and film production, television production and
recording and at a rate higher than the EU average in terms of the number of enterprises,
value added and employment. These sectors are two of the four ones in Bulgaria, that in
the years of the financial and economic crisis have a continuous growth by the
indicators below.
The total share of value added, just for these two sectors, and if the same pace of growth
is retained, is expected to reach in 2020 4% of the added value generated by all
enterprises and overall of creative industries – about 8-9 %. Sectoral links, according to
NSI data, show that these two sectors consume products especially in production of
computer and communication equipment, electronic optical products, which means that
their growth will inevitably affect the growth to one of the high-tech industrial sectors in
the country.
Capacity for Growth
The traditional manufacturing in Bulgaria is facing a strong price competition, from
third parties as well as competition in terms of quality from other EU countries. Despite
that, the manufacturing sectors with potential for growth and export are developed in
Bulgaria, as well as such in specific areas 23F
22, related to the European and regional
challenges.
On the other hand enterprises have limited resources and lower ability to take risks and
considerable volumes of exports on intensively competitive markets. Factors are also:
differences in the applicable law in the specific areas of economic activity; limited
information about potential partners and about the characteristics of the external
demand, despite the numerous traditional connections of the Bulgarian economy with
other country markets.
22 Creative and cultural industries, activities related to the aging population, in accordance with paragraph (8) of the
preamble to Regulation 1301/2013
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 23 of 274
In line with the ―The European Competitiveness Report 2013: toward knowledge-driven
re-industrialisation‖ the restructuring of the Bulgarian economy should be based not
only on the sectors of retail trade and production of raw materials but mainly on
consumer and investment goods and services with a focus on high-tech sectors of
industry and sectors of knowledge intensive services which will be supported by OPIC
2014-2020.
In other words the export determines the competitiveness and the growth potential of
SMEs, especially for a country like Bulgaria, which is characterised by an open
economy and a limited domestic market. The main trade partners of the country are
among the EU-27 (60%). Assuming that European orientation means the realisation of
at least 50% of the total exports of goods of the particular economic activity on the EU-
27 market, the results show that the majority of economic activities meet this criterion.
The Bulgarian trade relations with countries like China, USA, Russia and CIS countries,
and other countries with large market potential, became more active. Significantly high
degree of European orientation is observed in the medium-high technology industries
(electrical equipment, motor vehicles, trailers and semi-trailers; vehicles, but not cars)
and low-tech industries (leather, clothing, furniture), where the share exceeds 75%.
Exception to the general trend is reported in medicinal substances and products (from
the group of high-tech industries), chemical products (medium-high technology
industries), coke and refined petroleum products (medium-low technology industries),
timber and tobacco products (low-tech industries), all of which have found effective
market presence in third countries.
Fig. 3. Structure of the Bulgarian export by groups of goods for 2011
Source: Ministry of Economy and Energy, NSI, 2012
The distribution of economic activities by groups, depending on the extent of their
global technological intensity, offers a different perspective on the structure of the
Bulgarian export, but as to the profile of goods export, mainly the activities are of low
level of processing final products. This statement is supported by significantly higher
share in the total export of medium-low-tech activities (36.0%) and low-tech activities
(21.4%) compared with the high-tech (6.0%) and medium-high technology activities
(19.4%). In this respect, OPIC 2014-2020 will support economic activities with high
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 24 of 274
and medium-high-tech level of development which have the greatest potential for
increasing export, improvement of export advantages of the Bulgarian enterprises on the
international market and more active involvement of the Bulgarian SMEs in value chain
on the international markets. A change in the export structure requires restructuring and
technology modernisation of production, strengthening the application of innovative
knowledge and skills and highly qualified labour, which will position the Bulgarian
products in market niches of higher price range and will help to create long-term
competitive advantages, and will indirectly contribute to attracting foreign direct
investment. Complementary support will be also provided to institutions and
organizations providing direct services for enterprises, especially to export oriented
ones, for attracting investments and for international marketing of Bulgaria as tourist
and investment destination.
OPIC 2014-2020 also supports the capacity of enterprises for easier access, sustainable
development and presence on markets, and effective use of the benefits of growing
markets. Measures which will be implemented in this area will be directed towards
overcoming the limitations which the Bulgarian enterprises face in terms of
competitiveness on the regional, the European and the international markets. The
limitations come from high production costs and the need for optimization of production
chains; the use of obsolete production technologies; lack of sufficient production
capacity which can meet the volumes of market demand; lower quality of products in
some sectors; insufficient information on the attitudes, expectations, and needs of the
consumers; lack of objective guarantee of the quality and use of good manufacturing
practices. As a result, enterprises face higher trade barriers to enter new markets or to
maintain the achieved market positions.
The support for development of the production capacity will contribute to the
stimulation of broader enterprises participation in the value chain and the formation of
competitive advantages based on specific products and processes. Complementary
institutional support will help enterprises to prepare their presence on the regional,
European and international markets, to attract foreign investments and successfully
cooperate with foreign partners.
Institutional support will be provided also for the tourism sector. Although the tourism
is leading and fast growing sector in Bulgaria, with a significant contribution to the
Bulgarian economy, considerable private investments in the last decade and a strong
potential for further growth and positive impact on the regional development and
employment, the tourism enterprises and business associations, lack sufficient capacity
to offer their products independently and to promote themselves at the international
market. One of the main mechanisms to support SMEs in the tourism sector is through
support for establishment and functioning of the touristic regions management
organizations provided in the Tourism Act.
For Bulgarian SMEs ICT are very useful for improvement of integration, expansion of
the range of their capacities and creating competitive advantages. SMEs are growing
twice and three times faster when using ICT, therefore specific actions to promote their
use will be supported.
Approaches towards increasing value added ―on the spot‖, reuse of raw materials (and
utilization of waste and waste products) will be supported. In this context, the flagship
initiative ―Resource-efficient Europe‖ is to be leading, taking into account the current
stage of Bulgarian technology development.
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 25 of 274
The potential of clustering for the implementation of technology transfer, innovations,
sharing of resources and expanding of markets, including through economies of scale
remains unused, which makes it a powerful instrument for enhancing the
competitiveness of the Bulgarian economy. According to the RIS3 association of
enterprises in clusters allows the implementation of new production solutions and
development of innovative potential, which leads to increased productivity, higher
value-added production, access to markets and hence – to enhance the competitiveness
of businesses and expand their capacity for export.
Among the main challenges that clusters face are:
- been created in response to opened calls for proposals under various programs
(PHARE, OP, etc.) they are less focused on solving the specific common
problems of the companies involved,
- lack of specified goals to be achieved in their collaboration,
- weak connections between clusters and science.
- inadequate promotion of Bulgarian clusters abroad,
- insufficient commitment to the regional economical development
- insufficient trainings, awareness and motivation of companies for the benefit of
sustainable existence of clusters.
As a result, the existing clusters are less flexible and adaptable to the rapidly changing
environment. 2
But there are, however, good examples of real existing clusters in the
country in the field of new technologies, textile and furniture industry, marine industry
and renewable energy, etc.
The largest concentration of clusters, which is determined by the presence of the
traditional production, is in the regions of Sofia, Ruse, Varna, Stara Zagora and Sliven,
(such as the clothing industry in Ruse and Sliven, IT / electronics in Sofia and Stara
Zagora) and is also result of proximity to major universities (Sofia, Varna, etc.).
In accordance with the horizontal policies and thematic areas of RIS3, OPIC 2014-2020
will support clusters (according to their needs in line with the stage of development:
newly-created, developing and developed) in order to increase the degree of integration
of local suppliers for maximum use of their capacity to develop competitive innovative
business products and services, and active presence in the regional, national and
international markets. For example, the newly created clusters will be supported
primarily for "soft measures" aimed at strengthening their organizational and
administrative capacity, stimulating cooperation and creating partnerships throughout
the value chain, incl. adoption of good European practices. For developing and
developed clusters support will be directed towards development of shared
infrastructure and innovation know-how, internationalization and participation in
European and international forms of cooperation in order to make the clusters the
driving force for regional smart specialization in Bulgaria.
Energy Efficiency
The achievement of competitiveness of the economy directly depends on the
management and use of the natural resources and energy production and consumption.
Improving energy efficiency contributes to the implementation of all EU policies‘
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 26 of 274
objectives: improved competitiveness; flexibility of supply; sustainability; and shift
towards a low carbon economy26F
23.
There is a close correlation between the development of energy sector and all the other
economic sectors, which determines the important role which the Bulgarian energy
sector plays for the economic development of the country. ―The Bulgarian energy sector
faces challenges like significant dependence on imported resources and energy, rising
energy prices and the climate change. Bulgaria is one of the poorest, most energy
intensive and most dependent on imported energy resources, countries in Europe.‖27F
24
Primary energy production satisfies just above 60% of the gross domestic energy
consumption in the country without significant structural changes: 42% coal; 20.85%
nuclear energy; 19.8% oil and oil products; 13.64% natural gas; 8.46% of energy from
renewable sources. For the period 2000-2011, there was an increase in final energy
consumption (FEC) in absolute terms – from 8436 ktoe in 2000 to 9050 ktoe in 2011.
Fig. 4. Final energy consumption (FEC) in Bulgaria during the period 2000-2011
by economic sectors
Source: „Report on the implementation of the Second National Action Plan for Energy
Efficiency in 2012.“, MEE (April 2013)
The changes in energy consumption and energy intensity of the industrial sector are key
factors affecting the changes in the overall FEC. The share of the "Industry" sector
declined in 2011, compared to 2000, taking up about 30% in the FEC structure.
Energy intensity is the main efficiency indicator in energy use and has a considerable
impact on the competitiveness of the Bulgarian economy. Bulgaria ranks first in energy
intensity compared to the EU 27. The Bulgarian economy has the highest consumption
of energy per unit product of gross domestic product, or with 77.34% more than the
average level within EU 27. The low energy efficiency of the industry is due to the
23 COM/2014/015 ―A policy framework for climate and energy in the period from 2020 to 2030" 24 National Development Programme: Bulgaria 2020―, p. 240
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 27 of 274
outdated technologies and the limited access to new good practices, systems and models
for energy and efficient production. The need for replacement of large production
facilities and systems is indispensable, but it lags behind because of the insufficient
financial resources, and the relatively slow return of investment in such, thus the price
of electricity in the country is still one of the lowest. Nevertheless, there was a trend
towards reducing the energy intensity of the Bulgarian economy for the period 2000-
2011 – an annual average of around 5%. The measures that are part of the energy policy
of the country have a positive role in the ongoing energy efficiency policy, but a
significant impact has also the structural changes in the Bulgarian economy. In 2011
annual growth of 5.4% is reported in primary energy intensity (PEI) and 2.5% in the
final energy intensity (FEI).
Fig. 5. Primary and final energy intensity 2000-2011
Source: „Report on the implementation of the Second National Action Plan for Energy
Efficiency in 2012.“, MEE (April 2013)
FEI of industry decreased twice for the entire period from 2000 to 2011, but in 2010
there is an increase of 10.7% compared to the previous year – 2009. In 2011 the energy
intensity of the sector remains unchanged, which shows no improvement.
Due to the expected economic revival of the industry after the economic crisis, only by
increasing the energy efficiency the growth of energy intensity in the sector could be
limited. The main factor for this increase is the impact of the economic crisis, and the
impact of the accompanying structural changes (about 20%, as a result of the share of
the added value of industry in GDP). The largest effect for the increase in energy
intensity in the sector has the manufacturing industry in which the energy intensity has
increased by 4.2% compared to 2009, while decreasing by 5.5% per year in 2000-2009.
That is the reason why OPIC 2014-2020 will concentrate resources on TO 4 in order to
support the reduction of energy intensity as a priority in manufacturing industry,
respectively – for increase of energy efficiency in industry and commercial buildings.
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 28 of 274
For the period 2005-2012 there is a tendency of increasing the share of energy from
RES in the structure of gross final energy consumption by up to 16.3% in 201225
, which
is above the EU – 28 average – 14,1%26
. By this in practice the national objective of
16% share of energy from RES in the gross energy end consumption by 2020 is
achieved.
Although the renewable energy production contributes to the reduction of emission of
greenhouse gases and allows for diversification of energy sources, for which Bulgaria
still has more to achieve, there are some problems related to the high growth of the
electricity production from renewable sources and the low consumption in the country,
resulting in the need to balance the production and consumption of electrical energy in
the system,take actions for its balancing and additional costs for its management. Also
the introduction of measures to promote energy from renewable sources, such as
preferential prices, accompanied by an obligation to purchase the entire quantity of
electricity produced from renewable sources has a high social cost as it resulted in
increase of the price of electricity for consumers.
Given that at present Bulgaria has exceeded the national target for increasing the share
of renewable energy, and in terms of implementing the national target for energy
efficiency improvement the country lags significantly, the resources of OPIC 2014-2020
focus on support to increase energy efficiency, while the measures related to the use of
renewable energywill be supported in addition to the energy efficiency measures and
will be only for own needs of the enterprises
While simultaneously improving energy efficiency and management mechanisms on
built RES, the national target can be maintained more cheaply and still be significantly
exceeded. Over achieving the target will allow the country to sell "surplus" till 2020,
through the adoption of mechanisms for transfer of certificates of other EU countries.
Energy intensity is directly dependent on the energy efficiency, the fuel mix and the
structure of the economy as the strategy of OPIC 2014-2020 is to address each of these
elements commonly, by supporting interventions in Thematic Objective 4. According to
the Partnership Agreement 2014-2020, promoting energy and resource efficiency is
mandatory in Bulgaria for increasing the competitiveness of the Bulgarian economy. In
this regard and in order to achieve the objectives of the Europe 2020, the PA plans to
invest in "reducing energy inefficiency and energy intensity of production, in limiting
energy dependence and increasing the share of energy for internal consumption from
renewable sources in enterprises".
Bulgaria's Energy Strategy 2020 is the first national strategic document which sets
specific quantitative targets that must be achieved by 2020. The most important of them
is the 50% reduction in the energy intensity of GDP, thereby it‘s expected to achieve the
most rapid and cost-effective path to the security of supply and competitive industry.
Gasification, according to this document, is an essential tool for the ecologization of
energy consumption with the recommendation for gasification and replacement of the
consumption of electricity, fuel oil and coal with natural gas consumption.
Greenhouse gas emissions from all energy activities in the energy sector, industry,
transport, agriculture and households, present 70% of total greenhouse gas emissions in
the country. Approximately 40% of greenhouse gas emissions in Bulgaria are product of
25 Eurostat 26 Eurostat
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 29 of 274
the energy sector. For the period 2000-2010 there is a tendency to reduce greenhouse
gas emissions on the stage of PEC and FEC. The significant contribution of the industry
and transport in the total greenhouse gas emissions (91% of CO2 emissions in the
country, while the share of households is only 5%27
)
) determines the importance of
measures which aim to reduce emissions of hazardous gases from these sectors, as
OPIC will therefore contribute indirectly - through the support of activities leading to
energy savings as a result of which will reduce emissions of hazardous gases
Resource efficiency
The industry costs on protection and restoration of the environment in Bulgaria, are
significantly above the average among the other member-states and in recent years these
costs are increasing on annual basis by an average of about 15%. The manufacturing
industry has the highest expenditures.
Fig. 6. Protecting and restoring environment costs by sectors (as % of GDP)
The highest costs for environmental protection and recuperation of industry are those
for air and waste, and the lowest are for biodiversity, noise and vibration. At the same
time in line with the indicator – environmentally friendly business, the Bulgarian SMEs
are substantially behind the EU average.
27 Policies and measures of energy efficiency in Bulgaria, SEDA
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 30 of 274
Fig. 7. Distance from the average values for EU28
Source: 2013 SBA Fact sheet Bulgaria
Despite the high environmental protection expenditures, the key reason for such poor
performance is that Bulgaria ranks last in the EU indicator for resource productivity,
which threatens the sustainability of the economy.
In relation to the following criteria: innovation for the environment, share of SMEs with
measures of resource efficiency, share of SMEs offering ―green products‖' share of
SMEs received public support for the introduction of measures to resource efficiency or
"green products "and share of SMEs satisfied with public support, Bulgaria ranks
among the last in the EU29
. The main reasons for this are rooted in:
The low cost of resources and as a result - higher share of exports of raw
materials;
Insufficient awareness and promotion of the possible mechanisms to achieve
resource efficiency and poor exchange of information between the partners in
the value chain;
The low level of renewal of the technological park of processing plants due to
lack of financial resources and incentives;
Lack of industrial symbiosis;
Strong administrative burden of the various ordinations and permits relating to
the protection of the environment through which are assessed and authorized
new investment proposals of the enterprises related to achieving resource
efficiency;
28 Source 2013 SBA Fact sheet Bulgaria 29
Source NSPSMEs
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 31 of 274
Fig. 8. Resource productivity 30
Source: Eurostat, 2014
In this regard as additional contribution to the investment of OPT, OPRD and OPE,
OPIC 2014-2020 aims to support SMEs to improve their resource efficiency as a
horizontal priority and to stimulate pilot and demonstration initiatives aimed at
promoting industrial symbiosis and exchange of information between the partners in the
value chain (through separate investment priority), thus contributing to the turnaround
of the national target set in NSPSMEs to increase the share of SMEs with measures to
effectively use our resources31
.
Security of gas supplies
On 28 May 2014 the European Commission adopted its European Energy Security
Strategy providing a comprehensive plan to strengthen Europe‘s security of energy
supply. As a part of the immediate measures to increase EU‘s resilience to a major gas
disruption, the European Council endorsed on 27 July 2014 the Commission‘s proposal
to launch the so-called stress test exercise with the purpose of assessing the resilience of
the European gas system to cope with a severe disruption of gas supply to the EU. Three
focus groups were set up to specifically cover the regions where the impact of
disruptions was likely to be most prominent, one of these groups being for South East
region of the EU, including Bulgaria.
One of the proposed medium term measures (by end 2015) in the Communication from
the Commission to the European Parliament and the Council on the short-term
resilience of the European gas system is to speed up the implementation of key Projects
of Common Interest or Projects of Energy Community Interest, which include
interconnections of Bulgaria with neighboring countries. The Commission will follow
up such projects and also stand ready to facilitate any outstanding negotiations between
parties with a view to push forward all these projects towards an expedited completion.
30 Eurostat, 2014
31
The goal is the share of SMEs with effective use of resources in 2020 to exceed 93%, at the time, the base value is 85%.
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 32 of 274
Projects contribute to ensuring natural gas supply from alternative sources to Bulgaria
(currently totally dependent on Russia), energy security and further balance of the
regional energy mix by increasing natural gas consumption, creation of jobs and support
to economic recovery in the post-recession period; provision of a direct connection of
the gas markets of the four Member States - Bulgaria, Romania, Greece and Hungary to
the gas markets of the other South-East European ones.
In order to ensure uninterruptible gas supply at affordable prices to businesses, OPIC
2014-2020 will support Phase 2 of the project for construction of Bulgaria-Serbia gas
interconnection. Moreover, forecasts show that by 2030 industry will be responsible for
43% of the total consumption of natural gas and electricity production – for about 35%.
At present, the share of natural gas in gross domestic energy consumption (GDEC) of
the country is approximately 70% lower compared to the EU-27 and this proportion has
not changed over the last decade. This makes the project for gas interconnection crucial
for the development of the Bulgarian economy.With the flexibility and the decrease of
the energy dependence which contribute to the reduction of the energy intensity of the
enterprises, Phase 2 of the project will provide new opportunities for the development
and recovery of the economy in the areas along the route, introduction of new energy
technologies, etc. The availability of secure access to natural gas will contribute to the
economic growth and the enterprises that switching from electricity and oil products to
natural gas will realize substantial savings and reduce hazardous emissions.
LESSONS LEARNED 2007-2013
Lessons learned 2007–2013 with regard to the effects and assessing the impact
During the first programming period for Bulgaria under the OP Competitiveness (OP
DCBE) 2007-2013 the amount of 1,162,216 thousand euros has been allocated, out of
which 987 883 thousand (85% of the funds) financed by the EU under ERDF and 174
332 thousand (15% of funds) by national co-financing. Fig. 9 presents areas for support
under OPDCBE 2007-2013 and the amount of the grants provided to the OP‘s
beneficiaries (as of 03/31/2014) (million EUR).
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 33 of 274
Fig. 9. Areas of support under Operational Programme “Development of the
Competitiveness of the Bulgarian Economy” 2007- 2013
Except allocated resources for the financial instruments (30%), the largest is the
percentage of the funds for technology modernisation and management systems (26% of
total allocation), followed by the innovation and R&D support (24%) and energy
efficiency and green economy (15%).
Considering the fact that still the overall impact of EU funds on the Bulgarian economy
cannot be entirely measured, it can be concluded that by September 2012 there is a
positive effect of OP implementation on five of the main macroeconomic indicators
(GDP, employment rate, growth in private consumption and exports of goods and
services), as the most positive impact is on the growth of private investment (Fig. 10)
Fig. 10. Effects from the OPDCBE 2007- 2013”, SIBILA database
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 34 of 274
Evaluating the impact of the Structural and Cohesion Funds on the Bulgarian economy
based on econometric model, SIBILA (in regard to OPDCBE)
The main conclusion is that the effect of the financing under operational programmes
cannot be measured by the amount of available funds and/or financing ―per piece‖, but
by the initial stimulation of projects which the private sector undertakes, develops
further and benefits multiply.
Lessons learned 2007-2013 in terms of administrative capacity and administrative
burden
In the beginning of the programming period 2007-2013, the applicants and beneficiaries
faced a high degree of red type and complicated administrative procedures. The
Bulgarian lack of experience in the implementation of the Structural and Cohesion
Funds should be also considered.
The changing legislation, complex rules and procedures and the large number of
documents required upon application, often discouraged candidates, resulted in
significant delays of project evaluation, which led to risk of undermining project ideas,
especially in respect to projects, related to the development and/or implementation of
innovations. Pre-funding, requirements for implementation by the beneficiaries of the
regimes for the award for the implementation of project activities, requirements for
advance guarantees, complicated reporting, delays in verification and reimbursement
process also impede beneficiaries, increase their costs and often limit their free financial
resources, which makes harder further implementation of the project activities.
These challenges are addressed with a continuous improvement of the administrative
capacity of the MA and the beneficiaries, and with the increasing attention given to the
reduction of administrative burdens and bureaucracy (the so-called ―red tapes‖‖), as the
progress is described more detailed in the relevant section of OPIC 2014-2020. For
example, there is a legal requirement introduced for conduction of an information
campaign for potential beneficiaries after the announcement of the calls for proposals
and also a practice for subsequently training of beneficiaries with grant.
For the programming process of OPIC 2014-2020 the ―lessons learned‖ concern:
close relation between the programming process and the Programme
implementation - even procedures which directly address identified needs of the
business, cannot achieve high interest at application stage or effectiveness at the
implementation stage, if the complication of the procedures does not allow active
participation and focuses on the implementation and benefits instead;
the need to define "successful" project means not only ―well-written‖ or ―well-
reported‖ project. The administration itself should be motivated not only to
minimise the risk of errors, but also to maximise the benefits for the beneficiary
and to achieve the desired objectives both on project and procedure level, as well
as on the level of priority axis and even programme level. Last but not least, a
project has effect as long as it has attracted funding from other sources and thus
ensures sustainable results.
Lessons learned 2007-2013 in terms of structuring Programme’s investments
Specifically in terms of innovation, the OP 2007-2013 defines quite appropriately the
economy based on knowledge and innovation as a separate priority of key importance.
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 35 of 274
After the modification of the Programme in 2012 the total amount of the Priority axis is
€ 210,692,798, including national co-financing. The share of certifited costs till 31st
Dec 2013 is just over 10% , the main reasons for this are: late start of some of the
procedures, complex procedures and restrictions at application stage. After 2012 a
positive development occurs after the modification of the definition for ―innovation‖
according to the Oslo Manualand opening the possibility for funding not only
developed by the innovative enterprise innovation, but also developed by other entities
innovations .
According to a BCCI study almost half of the enterprises (45%) do not believe that in
the next 3-5 years will assign the development of a new product to universities and
research institutes . Only 23% of entrepreneurs say they can independently implement
activities in the field of innovation. The most preferred forms of innovation activities
are partnerships with other companies and universities, which is pointed by 37%.
According to the survey, the two main barriers for collaboration between business and
science, are the insufficient information of the business for scientific researches and the
low activity of the universities. Both barriers need to be overcome and in this regard
will seek synergies of interventions under TO 1 within OPIC and OPSEIG.In regard to
the institutional beneficiaries, in the OP 2007-2013 funding was set aside for them in
separate axis in amount of € 37,656,853. Although Priority axis 4 is the smallest one,
is also characterized by an extremely slow rate of progress of the contracts‘
implementation ( 27% certified funds to 31.12.2013), due to:
significant difficulties in pre-financing projects due to budget constraints;
pre-allocation funding under OP results in the so-called ―crowding out‖ effect,
which means failure to receive funds from other sources and make them
dependable on the implementation and reimbursement of project costs ;
difficulties in implementation and reporting of complex multiannual projects ;
inequality with other beneficiaries in terms of the eligible costs for external
consultancies, management team and other project specific implementation
costs.
Given the analysis of the experience from the 2007-2013 period and the need for
effective orientation of the programmes for 2014-2020, in OPIC the approach to the
institutional beneficiaries has been revised and they are subject to support under the
different PA , which will have the following advantages:
a) it will provide more particular direction and contribution for fulfillment of
the general and specific objectives of the Programme and connect them with
appropriate output and product indicators ;
b) it will ensure the flexibility in planning, financing and implementation of
projects as well as overcoming the difficulties of management;
c) it will help the institutions to open to a wider range of financing sources;
d) it will provide opportunities for equal treatment to the Programme
beneficiaries in terms of eligible costs, activities and etc.
As regards to the financial instruments the OP DCBE is often cited as a good practice at
EU level. The budget of the Priority axis after the last modification of the OP is EUR
350 million, which amounts to 30.11% of the Programme‘s budget.
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 36 of 274
Under JEREMIE initiative in OP Competitiveness two funds for initial funding with a
total budget of EUR 21 million are supported. According to the annual progress report
2013 under JEREMIE initiative ten calls for proposals have been opened, and over
3,000 applications for funding received. Funding for 73 innovative start-ups was
provided, amounting on 4,384,759 Euros. Where 6 million Euros were invested under
the Programme, with subsequent private investments for 4 million Euros reported.
Under JEREMIE Initiative two instruments for facilitatig bank lending – guarantees,
covering losses on portfolios of loans and risk sharing financing - are implemented. The
two instruments are implemented to ease the conditions of bank lending. Since
December 2013 there are over 4 445 guaranteed loans provided under the guarantee
instrument amounting on 275 million Euros, among which 173 million are for new
SMEs‘ investment. For the same period 1 253 loans for approximately 170 million
Euros were granted in pursuance of the low-interest rate instruments (risk sharing
financing). In the process of raising private capital, in this period two more instruments
for equity funding are provided – VC fund and mezzanine fund. At the end of 2013 the
selection of financial intermediaries for the instrument of co-financing is finalised.
There is no doubt about the financial progress achieved. The table below shows the
allocation of funds among the financial instruments and also the progress in absorbing
(investments or loans for final beneficiaries) till 31.12.201332
Table 1-5: Distribution of financial instruments for OPC 2007-2013
Invitation Instrument
Total
value of
the
portfolio
Funds
from
OPC
Invested
funds /
Loans,
guarantees,
million
EUR
Percentage
of
absorption
JER 009/1 Venture capital fund 20.4 14.3 0 0%
JER 009/2
Guarantees covering the
losses on a portfolio of
loans
301 60.2 275 91%
JER 009/4 Mezzanine fund 60 30 0 0%
JER 009/5
Instrument for
promoting
entrepreneurship and
providing initial funding
21.21 21 4.5 23.6%
JER 009/6 Instrument providing
risk sharing financing 400 200 170 42.5%
32 Based on data from the Annual progress report of the JEREMIE initiative. The funding of the Growth fund is
allocated to the risk-sharing financial instrument and also funds for co-investment, for which at the end of 2013, there
are not agreed funds so they are not included in the table.
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 37 of 274
Invitation Instrument
Total
value of
the
portfolio
Funds
from
OPC
Invested
funds /
Loans,
guarantees,
million
EUR
Percentage
of
absorption
Total 802.5 325.5 450 56%
The Holding Fund has contracted more than 93% of the allocated funds under the OP.
The absorption of 56% of the instruments, which means a significant progress,
considering the delayed start of the Programme,. In terms of absorption the most
successful is the guarantee instrument (91% at end of 2013). Given the fact that the
instruments for risk sharing actually began operating in 2013 the rate of 42.5 %
achieved also outlines good perspectives. The actual operations of the VC fund and
Mezzanine funds are about to start. With respect to the Mezzanine fund, the investors
expect future guarantees of the instrument after 2015.
Considering the success of the financial instruments and the fact that aid under OP,
aimed at this type of tools, leads to significant mobilization of private capital, under
OPIC will be provided their operation and in the next programming period, taking into
account the need to ensure a sufficient volume of public information about the progress
of the financial instruments, the selection of financial intermediaries and the level of
achievement of their objectives. The size of the portfolio and type of instruments, which
will continue to be funded are determined based on the results of the use of financial
instruments by OPIC under art. 37 of the (EU) Regulation No.1303 / 2013, which
provides an assessment of market failure or sub-optimal investment situation in the
country and the estimated level and scope of public investment needs.
.
FIs are planned within the different thematic objectives and priority axes, which
follows the overall logic of intervention of the program and ensure the utmost
achievement of the Programme‘s objectives and also the output and result indicators.
LOGIC OF INTERVENTIONS OF OPIC 2014-2020
The contribution of OPIC 2014-2020 to addressing the main needs and challenges of the
Bulgarian economy identified above, in consideration of the lessons learned consists of
the following 6 areas of intervention:
Technological development and innovation – interventions under TO 1
(Investment priority (IP) Art. 5(1) (b) of ERDF Regulation;
Access to finance for supporting entrepreneurship– interventions under TO 3 (IP
Art. 5(3) (a) of ERDF Regulation;
Capacity for SMEs growth– interventions under TO 3 (IP Art. 5(3) (d) of ERDF
Regulation;
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 38 of 274
Energy technologies and energy efficiency – interventions under TO 4 (IP Art.
5(4) (b) of ERDF Regulation;
Resource efficiency – interventions under TO 6 (IP Art. 5(6) (g) of ERDF
Regulation;
Security of gas supplies – interventions under TO 7 (IP Art. 5(7) (e) of ERDF
Regulation.
The first area of intervention (Technological development and innovation) is
committed to the achievement of ―smart growth‖ in the areas of the Innovation Strategy
for Smart Specialisation, particularly in regard to research and innovation. There is a
need to strengthen the innovation capacity of enterprises and foster a favourable
environment for innovation and research by supporting existing and effective
structures/organisations. The implementation of the planned indicative actions will aim
at attracting investment for innovative activities, creating and strengthening the capacity
of Bulgarian enterprises for development, deployment and commercialisation of
innovative products, services and business models, as well as for improving the
conditions for carrying out innovation and developing the cooperation between
businesses and research community. This will, in turn, promote greater integration
between the parties of the ―knowledge triangle‖ (Education-Research-Business) for
developing competitive products/services for which there is demand in the market. The
implementation of this Investment Priority will enable a rise in the value added along
the value chain in relation to the Innovation Strategy for Smart Specialisation (RIS3)
thematic objectives, considering the stage and dynamics of the development of the
Bulgarian economy.
Promoting synergistic cooperation and interaction between all players in the national
innovation system and taking coordinated steps across the entire chain – from the
emergence of the idea, through its laboratory testing to the commercialization of the
results – will allow for mitigating the consequences of market failures associated with
the innovation process.
Regional specialisation could have a further positive contribution to the development of
small and medium-sized enterprises (SMEs) according to the sector-specific initiative,
the Small Business Act (SBA) within the context of RIS3. Developing links between
education, research and businesses at regional level and combining local business
development with creating and attracting skilled human resources will stimulate
enhanced competitiveness and degree of internationalization of enterprises and support
the formation of sustainable competitive advantages, which will render businesses more
competitive in the domestic and international market.
The actions under the first area of intervention will contribute to the implementation of
the following objectives under TO 1:
Contribution to the national target under Europe 2020 for increased expenditure
on R&D as % of the GDP;
Contribution to the following results as per Partnership Agreement:
Growth of the enterprises realizing innovation activity;
Support for companies that cooperate with research institutions / other entities;
Support the development of technology parks and laboratories;
Support for innovation clusters;
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 39 of 274
Increase R & D expenditure of enterprises.
The second area of intervention (support to entrepreneurship, incl. guarantied
portfolio for financial instruments) aims at achieving both smart growth and,
indirectly, inclusive growth by promoting the establishment of new and sustainable
enterprises to create new jobs for the Bulgarian economy. According to the National
Strategy for Promotion of SME (Small Business Act), in Bulgaria there are conditions
for launching and implementing entrepreneurial initiatives but there is a need for further
measures to simplify the requirements for developing new ideas and facilitating the
access to funding for small enterprises and start-ups. The aim of the support under this
area of intervention will be to increase the entrepreneurial activity and to achieve
successful implementation of new business ideas, as well as successful and accelerated
development of existing entrepreneurial companies leading to economic stabilisation
and growth. As part of entrepreneurship and provides targeted support for SMEs
(through Grants) in emerging areas of intervention that address regional and European
challenges.
Contribution to the following results as per Partnership Agreement:
increase in entrepreneurial activity;
The third area of intervention (Capacity for SMEs growth) aims to accelerate the
growth rate (―fast‖ growth) and is expected to create opportunities for increasing the
productivity of enterprises and for diversification of their product portfolios and
distribution of their production in new markets through grant support in compliance
with the National Strategy for Promotion of SMEs, as well through improvement of the
access to finance. The competitiveness of enterprises will be strengthened, their
participation in the value added chain will be enhanced, and their achievement of
market stability in a rapidly changing economic and competitive market environment
will be accelerated. Taking into account these circumstances and the position of the
business and its organisations, the OP foresees continued investment in the period 2014-
2020 aimed at improving the production processes in enterprises and facilitating the
transition to high and knowledge-based technologies for improved production, quality
management and increasing opportunities for export orientation and access to
international markets.
There is significant potential to improve the competitiveness and productivity of
enterprises through development of electronic applications and services and use of
business management systems.
Contribution to the following results as per Partnership Agreement:
Increase of the volume of exports of goods and services generated by SMEs;
Cluster support;
Support for SMEs to participate in promotional activities:
Support for SMEs for the introduction of certificates;
Support for projects of SMEs for growth and export;
Increase of the share of exports in total turnover of SMEs.
The fourth area of intervention (Energy technologies and energy efficiency) will
support sustainable uses of energy and improving the energy efficiency of enterprises.
Compared to the other European countries Bulgaria‘s economy is the most energy
intensive and one of the most heavily dependent on imported energy. Therefore,
improving the energy efficiency of enterprises and promoting the production and use of
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 40 of 274
energy from renewable sources for their own consumption (especially in manufacturing
enterprises, which have the largest contribution to the high energy intensity of the
national economy) are crucial to ensure the reduction of the energy intensity of the
Bulgarian economy, and thereby reduction of the distances of the national energy
efficiency target. The actions under the fourth area of intervention will contribute to the
implementation of the following objectives under TO 4:
Contribution to the national targets under Europe 2020:
Increase energy efficiency by 25% by 202033
Contribution to the following results as per Partnership Agreement:
Reduction of the energy intensity of the economy;
Increase of the energy savings in enteroprises;
Reduction of greenhouse gas emissions.
The fifth area of intervention (Resource efficiency) builds on the need to invest in
achieving a resource efficient economy as a horizontal priority and complementing it
with a pilot and demonstration initiatives focused on promoting industrial symbiosis and
exchange of information between the partners in the value chain.
The introduction of resource-efficient technologies and processes in enterprises is a
prerequisite for enhancing both competitiveness and the quality of life. Given that
increasing the resource effectiveness of enterprises will be addressed by the
interventions under Thematic Objectives 1, 3 and 4 with the help of horizontal principle,
the actions under the present area of intervention will be to a large extent complemented
by the other areas of intervention.
The actions under this area of intervention will contribute to the implementation of the
following objectives under TO 6:
Contribution to the following results as per Partnership Agreement:
Reduced generation of waste and increased reuse and recycling;
Improved environment and air quality, including in settlements.
The sixth area of intervention (Security of gas supplies) will support the construction
of adequate energy infrastructure as a prerequisite for improving the security of supply
situation in Bulgaria.
Developing interconnections with the energy systems of the neighbouring states will be
of key significance to increasing security and flexibility of energy supply for
enterprises.
With a view to overcoming the main challenges related to the need for compensatory
growth and addressing the areas of intervention described above, the following four
priority axes with relevant investment priorities have been identified:
PRIORITY 1. Technological development and innovations
1.1. Technological development and innovations (―smart‖ growth) – Thematic
33
The target share of renewable energy in the gross final energy consumption has been achieved – in 2012 the share
was 16.3%. At present, efforts are focused on the need to balance the electricity system rather than increase
renewable energy.
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 41 of 274
Objective 1 of the Common Strategic Framework;
PRIORITY 2. Entrepreneurship and Capacity for SMEs growth;
2.1. Access to finance for supporting entrepreneurship – Thematic Objective 3 of the
Common Strategic Framework
2.2. Capacity for SMEs to grow – Thematic Objective 3 of the Common Strategic
Framework;
PRIORITY 3. Energy and resource efficiency
3.1. Energy technologies and energy efficiency – Thematic Objective 4 of the Common
Strategic Framework;
3.2. Resource efficiency – Thematic Objective 6 of the Common Strategic Framework.
PRIORITY 4. Removing bottlenecks in security of gas supplies
4.1. Improving energy efficiency and security of supply through the development of
smart energy transmission systems - Thematic Objective 7 of the Common Strategic
Framework
The aim of these four priority axes is to provide a joint support for creating sustainable
and long-lasting competitive advantages for Bulgarian enterprises and accelerating the
transition to a knowledge-based economy, while improving the country‘s performance
under the indicators financial market development, technological readiness, market size,
business sophistication and innovation, as well as to improve security of gas supplies to
enterprises.
With a view to ensuring effective and efficient allocation of ERDF funding, the
determination of the priority axes and investment priorities has been based on the
approach of concentration of resources. Compared to the challenges faced by the
national economy, ESI financial allocations seem very limited. This requires that clear
and attainable objectives should be set to achieve significant impacts on the condition of
enterprises. Furthermore, the funding will complement parallel national efforts in this
area and it is expected that more private expenditure will be leveraged to act as a
catalyst of economic development rather than an end source of funding.
The lessons learned from the current programming period show the critical importance
of access to funding, including for the implementation of grant projects. The application
of financial engineering instruments will aim to leverage more private funding.
Application of financial instruments subject to the specific characteristics of the
different types of projects has been envisaged. Financial engineering instruments will
aim to facilitate access to funding for enterprises and higher rate of utilization and more
flexibility in the implementation of activities at the enterprise level. The main strengths
of financial instruments lie in the option to reuse funding in the long run, speedy
selection and flexibility of implementation for final recipients, including reduced
timeframes and administrative burden of procedures and potential to leverage additional
public or private investment to overcome market deficiencies in accordance with
Europe 2020 and Cohesion Policy priorities.
Investment directed at creating and developing effective and sustainable support and
expertise systems in new and/or existing agencies, organisations and institutions
through development of modern and innovative services has been identified as an
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page 42 of 274
integral part of the first three priority axes that will directly contribute to enhancing the
innovation and competitiveness of enterprises in the country.
Investment for technical assistance has been identified as a horizontal priority axis. The
goal is to ensure proper management, implementation, monitoring, evaluation,
information and control for the OP and thus to guarantee not only high absorption rates
for ERDF and budget funding but also good performance of OPIC 2014-2020 strategy.
Due to the scope and high number of potential beneficiaries, publicity and awareness
raising measures are also essential – not only in terms of meeting regulatory
requirements, but also as a prerequisite for active participation in the OP, project
maturity, tangible impacts and timely implementation.
1.1.2. Justification for the selection of thematic objectives and corresponding
investment priorities
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page. 43 of 274
Table 1-6: Overview of the justification for the selection of thematic objectives and investment priorities
Selected thematic objective Selected investment
priority
Justification for selection
TO 1. Strengthening
research, technological
development and innovation
Investment priority
1.1. Technological
development and
innovation
Council Recommendation on the National Reform Programme of Bulgaria in 2013 and
containing an opinion on the Convergence program of Bulgaria for the period 2012 to
2016:
Recommendation 5 ―... to improve the access of SMEs and start-ups to finance:
Recommendation 4 ―... by strengthening cooperation between education, research
institutes and enterprises‖.
National targets
National targets set out in the National Reform Programme to increase R & D
investment from 0.6% of GDP in 2012. to 1.5% of GDP by 2020;
In the National Development Programme: Bulgaria 2020 foresees actions for
developing innovative infrastructure and ecosystem and increasing the innovative
activity of Bulgarian enterprises.
Identified needs:
Poor cooperation of different actors in R &D;
Low innovation activity and low value-added innovation
Poorly developed innovation infrastructure and insufficiently attractive
environment for innovation
TO 3. Enhancing the
competitiveness of small and
medium-sized enterprises
Investment Priority
2.1. Access to finance
for supporting
entrepreneurship
Council Recommendation on the National Reform Programme 2013 of Bulgaria as
well as in other European countries and containing an opinion on the Convergence
program of Bulgaria for the period 2012 to 2016:
Recommendation 5. ― … Improve the access to finance for SMEs and start-ups.‖
In NSPSMEs a national target is the need to strengthen the entrepreneurial activity of
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page. 44 of 274
Selected thematic objective Selected investment
priority
Justification for selection
10% in 2012 to at least 12% by 2020
Identified needs:
Difficult acces to sources of financing - although under the access to finance
indicator Bulgaria occupies 10th place in the EU for 2012, only 16.7 percent34
of
Bulgarian SMEs have access to public financial support including guarantees;
Unsatisfactory conditions, especially among young people, improved conditions,
particularly those that create security environment for the realization of
entrepreneurial opportunities and those related to culture and education to develop
an entrepreneurial spirit.
Investment Priority
2.2. Capacity for
SMEs to grow
Council Recommendation on the National Reform Programme of Bulgaria in 2013 and
the Council opinion on the Convergence Programme of Bulgaria 2012-2016
Recommendation 5 "... to improve the access of SMEs and start-ups to finance"
National targets:
In NSPSMEs has set national targets for :
Increasing the share of Bulgarian SMEs that export goods and services to other
Member States. (from 3.15% in 2012 to > 7% in 2020 )
increasing the share of Bulgarian SMEs exporting outside the EU ( 1.76 % in 2012
to > 3.06% in 2020)
Identified needs:
Poor export structure with emphasis on goods and services with low value added;
Low degree of internationalization : 95% of SMEs have a low degree of
34
NSPSMEs 2014-2020
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page. 45 of 274
Selected thematic objective Selected investment
priority
Justification for selection
internationalization and the country ranks 27 in the EU in 2012.
Low rate of introduction of improved production technologies, optimisation of
production processes and production chains, reduction of used resources and,
respectively of product costs - establishing competitive advantages and sustainable
market presence for Bulgarian SMEs.
TO 4. Supporting the shift
towards a low-carbon
economy in all sectors
Investment Priority
3.1. Energy
technologies and
energy efficiency
National targets:
In the National Reform Programme in the implementation of the Strategy "Europe
2020" a national target has been set to increase energy efficiency by 25% by 2020
The National Development Programme: Bulgaria 2020: activities to
improve energy efficiency in enterprises have been foreseen
National needs:
Low energy efficiency in enterprises - Bulgarian economy consumes with 77.34%
more energy per unit of GDP than the average for EU-27, which is one of the
factors limiting the productivity and competitiveness of enterprises in Bulgaria.
Lack of funds for investments in improving energy and resource efficiency.
TO 6. Protecting the
environment and promoting
resource efficiency
Investment Priority
3.2. Resource
efficiency
National targets:
National Development Programme: Bulgaria 2020 and the NSPSMEs activities are
provided to enhance resource efficiency in SMEs, incl. pilot and demonstration
initiatives , as in NSPSMEs is set a specific target for increase of the share of SMEs
with measures of resource efficiency (from 85% during 2012 to more than 93% in
2020)
National needs:
Bulgarian SMEs have the lowest performance resource efficiency among EU
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page. 46 of 274
Selected thematic objective Selected investment
priority
Justification for selection
Member states, which is one of the factors limiting the productivity and
competitiveness of the SMEs in Bulgaria.
Lack of activity, processes and products for enhancing the resources efficiency.
Insufficient and inefficient investments for environmental protection.
TO 7. Promoting sustainable
transport and removing
bottlenecks in key network
infrastructures
Investment Priority
4.1 Improving energy
efficiency and
security of supply
through the
development of smart
energy transmission
systems
National targets:
Electricity and Gas Interconnector Projects and Capacity to Deal with
Disruptions fall under Country Specific Recommendation No 7 (2013) and
Recommendation No 6 (2014) in the National Reform Programme.
Energy independence on the gas market in Bulgaria continues to be among the main
priorities of the country, especially with a view to the recent political and economic
events triggered by the crisis in Ukraine. In order to provide cheaper gas for Bulgarian
producers and improve their competitiveness, and especially in order to guarantee the
energy independence and security of supplies of natural gas, extensive work is
undertaken on all infrastructure projects. Special attention is being paid to the
construction of the reverse gas interconnectors with the neighbouring countries
(Greece, Serbia, Romania and Turkey).
Diversification of gas supplies is one of the main priorities of Bulgaria's Energy
Strategy to 2020.
National needs:
Improving security and flexibility of gas supplies. Bulgaria is an important
transit hub. The strategic geographic location of the country determines the
significant potential for diversification of sources and routes of gas and oil
supplies. National dimensions and efforts are focused on attracting future gas
pipeline routes from Russia, the Caspian region, the Middle East and North
Africa to pass via Bulgaria. The construction of the planned pipelines through
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page. 47 of 274
Selected thematic objective Selected investment
priority
Justification for selection
Bulgaria will increase the security of supply and the development of the natural
gas market in the region.
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page. 48 of 274
1.2. Justification of financial allocation
The justification for the financial allocation (Union support) to each thematic objective
and, where appropriate, investment priority is in accordance with the thematic
concentration requirements, taking into account the ex-ante evaluation.
The allocation of financial resources from the ESI Funds to the different operational
programmes that will be implemented in Bulgaria in 2014-2020 programming period
takes account of the national priorities and needs and is based on a preliminary
allocation of resources by thematic objective in accordance with a specially designed
national model. The allocation is underpinned by criteria that provide a basis for
objective and justifiable financial allocation in line with the national priorities set out in
the National Development Programme: Bulgaria 2020 and the targets of the National
Reform Programme, the needs identified in the analysis of the Partnership Agreement
and the Position of the Commission Services of October 2012 on funding priorities, the
specific Council recommendations on the National Reform Programme, the national
capacity for absorption of funding in the period 2007-2013. The indicative allocations to
the different operational programmes and thematic objectives are based on the final
allocation of EU funding for the implementation of Cohesion Policy in Bulgaria. The
country has been allocated a total of 3,628,667,612 euros from the ERDF, of which a
total of 1 181,615,516 euros is dedicated to OPIC. In accordance with the established
co-financing rate of 85% (Art. 20(3) (b) of Regulation 1303/2013), the national co-
financing of the Programme will amount to 208,520,385 euros (15% of the total budget
of the Programme), in view of which the total budget will be 1, 390,135, 901 euros.
In accordance with the Partnership Agreement, OPIC 2014-2020 will support
investment priorities under five thematic objectives as follows:
Thematic Objective (TO)
Budget allocated to OPIC 2014-2020 by
thematic objective, based on the national
model for financial allocation of ESI
funds
TO 1. Strengthening research,
technological development and
innovation
21,24%
TO 3. Enhancing the competitiveness of
small and medium-sized enterprises 50, 17%
TO 4. Supporting the shift towards a low-
carbon economy in all sectors 19.71%
TO 6. Protecting the environment and
promoting resource efficiency 2,64%
TO 7. Promoting sustainable transport
and removing bottlenecks in key network
infrastructures
3.24%
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page. 49 of 274
Thematic Objective (TO)
Budget allocated to OPIC 2014-2020 by
thematic objective, based on the national
model for financial allocation of ESI
funds
Technical Assistance 3,00%
For each thematic objective OPIC 2014-2020 will be complemented by other ESI-
funded programmes that will address the identified national needs in observance of the
principles of complementary and demarcation and will jointly meet the results of the
different thematic objectives set out in the Partnership Agreement.
Given the focus on clear results and the limited OP budget for each thematic objective,
the adopted approach has been to concentrate resources on those programme-applicable
investment priorities of Regulation 1301/2013 that best address the identified needs,
attract other resources, and allow for the highest integration of measures, including from
different thematic objectives, where this is justifiable and will lead to achieving
synergies..
The relatively low share of the OPIC budget allocated to Thematic Objective 6 is due to
several factors:
The main national needs within the scope of TO 6, including resource
efficiency, will be addressed (in observance of the principle of demarcation) by
five operational programmes: OP Environment (with funding from the ERDF
and the CF), OP Regions in Growth (with funding from the ERDF), Rural
Development Programme (with funding from the EAFRD), OP Innovation and
Competitiveness (with funding from the ERDF) and Programme for Maritime
Affairs and Fisheries (with funding from the EMFF), where the highest share
will be that of OP Environment.
What is relevant to OPIC 2014-2020 from the scope of Thematic Objective 6, is
resource effectiveness of enterprises, which, at the same time, constitutes part of
the horizontal principle of sustainable development. As such it will be
addressed by the guidelines for project selection under other investment
priorities (Technical development and innovation, Capacity for growth of
SMEs, Energy efficiency).
Considering the above, as well as the fact that industry costs for restoration and
protection of the environment in Bulgaria are above the EU average, is the reason for
the relatively low share of the OPIC budget of Thematic Objective 6.
The breakdown by investment priority of the allocations to thematic objectives is as
follows:
Thematic
Objective
Investment
priority
under ERDF
Regulation
Addressed
challenges
Investment
priority under
OPIC 2014-
2020
Financial
allocation to
correspondi
ng axis
TO 1.
Strengthening
research,
Art. 5(1) (b);
Integration of
measures in
Innovation
capacity of
enterprises, incl.
Technological
development
and innovation
100% of the
funding for
TO 1 or
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page. 50 of 274
Thematic
Objective
Investment
priority
under ERDF
Regulation
Addressed
challenges
Investment
priority under
OPIC 2014-
2020
Financial
allocation to
correspondi
ng axis
technological
development
and innovation
accordance
with Art. 5(4)
(f), Art. 5(6)
(f) and Art.
5(6) (g)
through
horizontal
principles
capacity to
develop,
introduce and
distribute eco-
innovation and
innovation
related to
energy
efficiency
21,24% of
the funding
for OPIC
2014-2020
TO 3.
Enhancing the
competitiveness
of SMEs
Art. 5(3) (a) Entrepreneurial
potential
SMEs in new
spheres
Access to
finance for
supporting
entrepreneurshi
p
Covers
16.4% of the
funding for
TO 3 of
OPIC 2014-
2020 or
8.23% of the
programme
budget
Art. 5(3) (d);
Integration of
measures in
accordance
with Art. 5(4)
(f) and Art.
5(6) (g) –
horizontal
principles
Labour
productivity,
production
capacity, export
Capacity for
SMEs to grow
Covers
83.6% of the
funding for
TO 3 of
OPIC 2014-
2020 or
41.95% of
the
programme
budget
TO 4.
Supporting the
shift towards a
low-carbon
economy in all
sectors
Art. 5(4) (b) –
energy
efficiency
Integration of
measures Art.
5 para. 4 c)
Energy
efficiency of
enterprises
Energy
technologies
and energy
efficiency
100% of
OPIC 2014-
2020 funding
for TO 4 or
19.71% of
the
programme
budget
TO 6.
Protecting the
environment and
promoting
resource
Part of the
measures in
accordance
with Art. 5(6)
(g) – efficient
use of
Efficient use of
resources
Resource
efficiency
100% of
OPIC 2014-
2020 funding
for TO 6 or
2.64% of the
programme
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page. 51 of 274
Thematic
Objective
Investment
priority
under ERDF
Regulation
Addressed
challenges
Investment
priority under
OPIC 2014-
2020
Financial
allocation to
correspondi
ng axis
efficiency resources budget
TO 7.
Promoting
sustainable
transport and
removing
bottlenecks in
key network
infrastructures
Art. 5(7) (e) –
improving
energy
efficiency and
security of
supply
Vulnerability to
gas supply
disruptions
Improving
energy
efficiency and
security of
supply through
the
development of
smart energy
transmission
systems
100% of
OPIC 2014-
2020 funding
for TO 7 or
3.24% of the
programme
budget
Technical
Assistance
100% of
OPIC 2014-
2020 funding
for technical
assistance or
3.00% of the
programme
budget
Considering the national specifics, the need to focus interventions on the most pressing
needs and the most important goals, while at the same time ensuring integration of
measures to achieve a synergistic effect of the support, in accordance with the rules for
internal coherence and complementarity, the above-listed OPIC investment priorities
have been grouped in the following five (5) priority axes as follows:
Priority Axis Investment Priority of
OPIC 2014-2020
Budget of
Investment Priority
Budget of
Priority Axis
Technological
development and
innovation
Technological
development and
innovation (Thematic
Objective 1)
21.24% of OPIC
2014-2020 funding 21.24% of the
programme
budget
Entrepreneurship
and Capacity for
growth
Access to finance for
supporting
entrepreneurship
(Thematic Objective 3)
8.22 % of the
programme budget
50.17% of the
programme
budget Capacity for SMEs to
grow (Thematic
Objective 3)
41.95% of the
programme budget
Energy and Energy technologies 19.71 % of the total 22.35 % of the
OPIC 2014-2020, 2014BG16RFOP002 – March 2015
Page. 52 of 274
Priority Axis Investment Priority of
OPIC 2014-2020
Budget of
Investment Priority
Budget of
Priority Axis
resource
efficiency
and energy efficiency
(Thematic Objective 4)
programme funding programme
budget
Resource efficiency
(Thematic Objective 6)
2.64% of the total
programme funding
Removing
bottlenecks in
security of gas
supplies
Improving energy
efficiency and security
of supply through the
development of smart
energy transmission
systems
3.24% of the total
programme funding 3.24% of the
programme
budget
Technical
Assistance
3.00% of the total
programme funding
3.00% of the
total
programme
funding
OPIC 2014-2020, 2014 BG16RFOP002 – September 2014
Page. 53 of 274
Table 1-7: Overview of the investment strategy of the Operational Programme
Priority Axis Fund
Union
Support
(EUR)
Proportion
of total
Union
support for
the OP
Thematic
Objective
Investment
Priority
Specific objectives
corresponding to the
investment priority
Common and programme-specific
result indicators
Technological
development and
innovation
ERDF 250,990,169 85%
TO 1 Strengthening
research and
development,
technological
development and
innovations
Technological
development and
innovations
Increased innovation
activity of enterprises
Share of innovative enterprises;
Non-R&D innovation expenditure
Entrepreneurship
and Capacity for
growth
ERDF 97,217,060 85%
TO 3 Enhancing
the competitiveness
of SMEs
Access to finance
for supporting
entrepreneurship
Improving the survival
rate of SMEs
including through
stimulating
entrepreneurship
Number of enterprise survivals up to two
years
Entrepreneurship
and Capacity for
growth
ERDF 495,651,181 85%
TO 3 Enhancing
the competitiveness
of SMEs
Capacity for
SMEs to grow
Strengthening
productivity and
export potential of
Bulgarian SMEs
Export volume of goods and services
achieved bySMEs
Productivity of SMEs
Energy and
resource
efficiency
ERDF 232,947,006 85%
TO 4 Supporting
the shift towards a
low carbon
economy in all
sectors
Energy
technologies and
resource
efficiency
Reducing energy
intensity of the
economy
Reduced energy intensity
Energy and
resource ERDF 31,136,631 85%
TO 6 Protecting the
environment and
promoting resource
Resource
efficiency Increased share of
SMEs with measures
Increased share of SMEs with measures of
resource efficiency
OPIC 2014-2020, 2014 BG16RFOP002 – September 2014
Page. 54 of 274
Priority Axis Fund
Union
Support
(EUR)
Proportion
of total
Union
support for
the OP
Thematic
Objective
Investment
Priority
Specific objectives
corresponding to the
investment priority
Common and programme-specific
result indicators
efficiency efficiency of resource efficiency
Removing
bottlenecks in
security of gas
supplies
ERDF 38,250,000 85%
TO 7. Promoting
sustainable
transport and
removing
bottlenecks in key
network
infrastructures
Improving
energy efficiency
and security of
supply through
the development
of smart energy
transmission
systems
Better
interconnectivity with
neighbouring gas
transmission systems
N – 1 standard for infrastructure
Technical
Assistance ERDF 35,423,468 85%
TOTAL: ERDF 1,181,615,516 85%
OPIC 2014-2020, 2014 BG16RFOP002 – September 2014
Page 55 of 274
2. PROIRITY AXES
The priority axes described below are structured through an integrated approach to
maximize support. Indicative activites for implementing the investment priorities are
shown. These activities are indicative and the list is not exhaustive, both in terms of
number and of opportunities for impact. In accordance with their procedures, the
Managing Authority can add new ones or modify the activities described below in case
that such a change or a new activity correspond to the thematic objectives and the
investment priorities in the priority axis .
Description of the Priority Axes
OPIC
2014-2020
Technological Development
and Innovation
Entrepreneurship
Capacity for growth of
SMEs
Security of gas supplies
Energy technologies and energy efficiency
Resource efficiency
GROWTH AND JOBS
INVESTMENT
PRIORITY 1.1.
PRIORITY AXIS 1:
TECHNOLOGICAL
DEVELOPMENT AND
INNOVATION
INVESTMENT
PRIORITY 4.1
PRIORITY AXIS 4: REMOVING
BOTTLENECKS IN SECURITY OF GAS
SUPPLIES
INVESTMENT
PRIORITY 2.1.
INVESTMENT
PRIORITY 2.2.
PRIORITY AXIS 2:
ENTREPRENEURSHIP AND
CAPACITY FOR GROWTH
INVESTMENT
PRIORITY 3.1
INVESTMENT
PRIORITY 3.2.
PRIORITY AXIS 3: ENERGY
AND RESOURCE EFFICIENCY
OPIC 2014-2020, 2014 BG16RFOP002 – September 2014
Page 56 of 274
The focus of the priority axes 1 and 2 ―Technologic Development and Innovation‖ and
―Entrepreneurship and Capacity for Growth of SMEs‖ has two mutually complementary
aspects – acceleration of growth (providing "catch up" growth) and supporting the
development of innovation (such as the opportunity of "smart" growth). The production
capacity of enterprises and the technological development and transfer of knowledge
and technology need to be strengthened in parallel with the development and
introduction of innovations and promotion of sustainable entrepreneurship through
financial instruments which synergistically leads to increased competitiveness and
productivity of enterprises, and creates new opportunities on European and international
markets.
A need for three investment priorities has been identified: 1/ tehnological development
and innovation, 2/ access to funding in support of entrepreneurship, and 3/ capacity for
growth of SMEs, which only integrated can address the key challenges for innovation
and competitiveness of the Bulgarian enterprises.
Compliance with the national strategic policies is required in order to achieve maximum
focus and enhanced effect of investments :
Priority axis 1: ‖Technological Development and Innovation" (TO1), is in line
with the Innovation Strategy for Smart Specialisation (RIS3);
Priority axis 2: ‖Entrepreneurship and Capacity for Growth of SMEs ― (TO3), is
in line with the National Strategy for Promotion of SMEs.
Priority Axis "Energy and resource efficiency" also addresses two inter-related aspects
(efficient use of resources and energy efficiency of enterprises), which are the basis of
"sustainable" growth. Integrated approach towards resource and energy efficiency is the
only option for addressing the complex challenges which Bulgarian enterprises face in
terms of their resource inefficiency. It is also necessary to improve efficient use of
resources in companies and increase their energy efficiency and flexibility, which can
lead to sustainable competitiveness of the Bulgarian economy.
This priority axis consists of two investment priorities: 1/ Energy technologies and
energy efficiency and 2/ Resource efficiency.
With aim to achieve maximum focus and impact of investments made under Priority
Axis 3 "Energy and resource efficiency", in Thematic Objective 4 trade and services
sectors are excluded from grant support and under Thematic Objective 6 only pilot and
demonstration project for resource efficiency will be supported.
Priority axis ―Removing bottlenecks in security of gas supplies‖ supports the main
priorities of the Bulgarian energy policy aimed at ensuring energy security,
diversification of sources and routes, energy efficiency, liberalized energy market and
protection of consumers‘ rights.
2.1. Priority Axis 1: Technological development and Innovation
2.1.1. Investment Priority 1.1. Technological development and innovation
In accordance with Thematic Objective 1 "Strengthening research and development,
technological development and innovation", Investment priority 1b/, Regulation
OPIC 2014-2020, 2014 BG16RFOP002 – September 2014
Page 57 of 274
1301/2013, "encouraging business investment in R&D, development of relations and
cooperation between enterprises, R&D centers and the university sector, in particular
the promotion of investment in the development of products and services, technology
transfer ... " and according to the needs identified at national level within OPIC 2014-
2020, this priority axis includes support for technological development and innovation
in order to increase innovation activities of enterprises. The Council Recommendations
for 2013 highlight the importance of linking education with the needs of businesses as
well as strengthening the cooperation between education-science-businesses
(Recommendation 4); and access to finance for SMEs and start-ups (Recommendation
5).
The Investment priority aims at directly contributing to promotion of innovation activity
of enterprises in the thematic areas identified in RIS3:
a) fostering partnership between innovative enterprises and academia;
b) introducing specific measures for support of innovation activities in enterprises;
c) further development of existing or introducing new financial instruments for
funding innovation activities;
d) support for research and innovation infrastructure for business needs;
e) internationalisation of innovation process;
f) popularisation of good practises of innovation activities.
Specific Objective 1.1.: Increased innovation activity of enterprises
Expected results
The indicative activities in support of that specific objective will lead to increased
innovation activity of the Bulgarian enterprises by creating the necessary innovation
environment and infrastructure for development of innovation; stimulating R&D
activities and innovation in and for enterprises, incl. through cooperationbetween
enterprises or between enterprises and research institutes and universities. The
enhancing of the innovation activity of the enterprises is achieved both by stimulating
investment (both public and private) in R&D and through increased investment in
product, process, marketing and/or organizational innovation. Eco-innovations as well
as innovation in the field of low carbon economy are integral part of OPICapproach to
innovation. This creates prerequisites for building an integrated innovation capacity,
movement up the value chain and creating long-term competitive advantages, incl. into
the ecology and low carbon tehnologies.
Table 2-1: Programme-specific result indicators for ERDF
N
о Indicator
Measuremen
t Unit
Categor
y of
region
Base
value
Base
year
Target value
(2023)
Data
source
Frequency
of
reporting
OPIC 2014-2020, 2014 BG16RFOP002 – September 2014
Page 58 of 274
1 Share of
innovative
enterprises35
% of the
total number
of
enterprises
Less
develop
ed
regions
27.4 2012 30.4
NSI
Every two
years
2 Non-R&D
innovation
expenditure
% of
turnover
Less
develop
ed
regions
0.49 2012 0.63 NSI Every
even year
Action to be supported under the investment priority:
The support provided within the priority axis is envisaged to be focused on, but not
limited to the following indicative sets of activities:
development of cooperation for innovation between enterprises, between
business and academia incl. internationalisation of the innovation process.
support for innovation in enterprises, incl. development and introduction of new
products, processes and business models in enterprises;
support for development of environment and research and innovation
infrastructure for business needs.
The development of cooperation for innovation between enterprises and, between
business and academia, incl. internationalisation of the innovation process will be
encouraged through implementation of cooperation projects, including clustering and
participation in pro-innovative EU networks and platforms. Opportunities will be
created for companies and leading national and/or European academic and research
groups to collaborate, which will lead to the creation/development of innovative
capacity and sharing resources for the development and implementation of innovative
processes and products, protection and transfer of copywright and license royalties,
commercialization of the results.
On the other hand, mostly for high technology, cluster approach could be applied for
identification and structuring of partnershipswith the aim of technology transfer needed
for introducing innovations in individual companies within the cluster
Furthermore, mutual cooperation could be supported also through the development of
technology transfer offices and technology centers. Support will focus on science-
business relationship management, intellectual property rights, commercialization
through licenses and start-ups, researchers‘ awareness about intellectual property rights
and commercialization.
The Strategy for the Danube Region also contains a priority that OPIC will support
within the development of the "knowledge society" (more specificly, innovation and
ICT). Examples of activities in this regard include the creation of Living Labs for the
development, validation and implementation of new products and services through joint
participation of consumers, the academia and the businesses in the innovation process
(according to the Danube Strategy, the Action Plan for the Danube strategy, PA7), as
well as facilitation of creative knowledge transfer through establishing new design
35 NSI - Innovative enterprises,
as a share of all enterprises. Innovative enterprises include enterprises with
technological and non-technological innovation from the industry (NACE sections B, C, D and E) and
services (NACE sections Н, J and К, and NACE divisions 46, 71, 72 and 73).
OPIC 2014-2020, 2014 BG16RFOP002 – September 2014
Page 59 of 274
centers and transfer of knowledge from the creative industries to the traditional
enterprises (according to the Danube Strategy, the Action Plan for the Danube strategy,
PA8).
The expected contribution of these supported actions is raising the innovation activity
of enterprises due to the createdopportunities for cooperation, exchange and sharing of
ideas and resources. As a result, the share of companies developing and introducing
innovation in partnership with other participants in the innovation chain will increase,
leading to establishing innovation capacity in the areas set in objectives 1 and 2 of RIS3
and creating long-term competitive advantages for the country. Contribution is expected
also to the objectives and results of the Danube Strategy.
The target group includes Bulgarian enterprises in cooperation with other Bulgarian or
European companies, universities and/or research organizations; Bulgarian start-up
(spin-off) companies based on intellectual property transferred by the Bulgarian or
European universities/research organizations; clusters with potential for high value
added, consortia of enterprises designed to create new products and services.
Support for innovation in enterprises, incl. development and introduction of new
products, processes and business models is associated with investment support,
advisory and support services for development and implementation of innovation in
enterprises.
The expected contribution of these supported activities is expressed mainly in the
increased share of companies which by themselves carry out innovation activities,
develop and disseminate innovation, and as a result, their own innovative capacity and
competitiveness will increase.
The target group includes enterprises developing/introducing innovation incl. existing
enterprises.
Support for development of favourable environment and research and innovation
infrastructure for business needs includes:
construction, equipment and accreditation of thematically focused laboratories
necessary to meet business needs of certification, standardised testing and
technical verification, proof of concept, test models and utility models,
prototyping and other shared infrastructure to support innovation activities of
enterprises, including support for TTOs with constructed basic infrastructure,
technology centres, completion and upgrade of Technology Park ―Sofia Tech
Park‖ .
The supported laboratories are thematically focused laboratories and high-tech
labs for testing and technical verification that provide access to tehnology
options and tools, education and training and mentoring for prototyping and
digital production of innovative ideas and products. This will reduce the risk
associated with the launch of new products and ideas to market prior to proof of
return. Targeted support for Sofia Tech Park aims at up-grading of the existing
innovation environment which embraces all aspects of researches, technological
development and innovations where they can identify, promote and develop
innovative ideas and projects. The aim is to increase the competitiveness of the
science and the entrepreneurship in Bulgaria through improvement of
knowledge exchange between academia and business community supporting
start-ups and innovative ideas catalyzing the process of commercialization of
OPIC 2014-2020, 2014 BG16RFOP002 – September 2014
Page 60 of 274
R&D activities. The conditions for promotion of projects that create new
knowledge will be improved as well as a potential will be created for innovative
products, processes and services stimulating sectors from the economy with high
added value falling in the scope of the thematic areas and horizontal policies of
RIS3 and will lead to an increase of the competitveness and creation of
additional employment. Support for the development of modern and new for the
country business services related to the management of intellectual property
system, the Bulgarian standardization system and the system for accreditation of
laboratories and new products.
A national environment for world level innovation will be established in order to
stimulate the development of thematic areas defined in RIS3.
The expected contribution of these supported activities is expressed in increased
innovation activity by improving the environment and infrastructure for development
and dissemination of innovations - innovative environment that will support the
development of innovative capacity and create long-term competitive advantages of the
Bulgarian economy by moving up the value chain.
The target group is Sofia Tech Park with the aim to create an eco-system of vertically
integrated enterprises, clusters with potential for high value added, new and already
existing technology transfer offices, associations of companies as well as associations of
companies with scientific organizations, institutions of direct benefit to the innovation
activity of the enterprises.
Specific targeted territories: the territory of the whole country.
Types of Beneficiaries: enterprises or group of enterprises, including partnerships with
research organizations36
(legal entities as well as other forms of partnerships), agencies,
institutions, business organizations and other entities providing services for support of
R&D and innovation in enterprises, Sofia Tech Park, technology transfer offices and
technology centers, clusters.
Guiding principles for the selection of operations
In the selection of operations within the investment priority, the following leading
principles should be followed:
Provision of funding will be made in accordance with the procedures laid down
in national legislation and the internal rules of the MA;
Coordination and synergy - coordination between ESIF programmes at national
level, the horizontal programmes and other instruments of the Union with the
aim to achieve maximum s synergy effect and avoid double funding;
Thematic concentration – support will be provided for operations/investments
falling exclusively within the areas of smart specialization set in objectives 1 and
2 of RIS3;
Need-based funding – the selected operations are supposed to meet key
challenges to the business/economy identified in the Partnership Agreement,
OPIC 2014-2020 Strategy, the relevant strategic documents and documents in
implementation of specific ex-ante conditionality;
36
incl. scientific research institutes of the Bulgaria Academy of Sciences (BAS)
OPIC 2014-2020, 2014 BG16RFOP002 – September 2014
Page 61 of 274
Promoting operations which end result will contribute to improving resource
efficiency and the respective mitigation of climate change37
;
Supporting operations promoting and contributing to the implementation of
policies in the field of R & D and innovation;
Principle of sustainable development (art. 8 of Regulation 1303/2013) – when
funding operations under OP will be pursued sustainability of the results and
long-term effect on the target groups;
Effectiveness and efficiency of the investments - selected operations should
comply fully with the goals of the OP at the adequate ratio between the
estimated costs and benefits. In the selection of projects will ensure that
investments are directed towards the most sustainable options with the most
efficient use of resources;
Provision of funding in reducing the administrative burden for potential
beneficiaries;
Relevance - selected operations should contribute to the implementation of the
output and result indicators and outcome of the programme;
Sustainability of the investments – ensure sustainability of the achieved results
after project/operation completion;
Principle of partnership and transparency - the criteria for selecting the
operations are subject to approval by the Monitoring Committee of the
Operational Programme;
Principle of equal opportunities - promoting equal opportunities for all,
including accessibility for people with disabilities by mainstreaming the
principle of non-discrimination.
According to the Guide to synergies between the Structural Funds and Horizon 2020
and other research programmes related to innovation and competitiveness (Ref. Ares
(2014) 755 621 - 17.03.2014) despite the increased budget in the area of research,
innovation and competitiveness, what is crucial is to ensure optimal synergy between
the various funds and instruments for addressing global competitive pressures and to
maximize the results and effectiveness of public resources. The European Parliament
and the Council clearly demonstrate that the approach has changed from "it is nice to
have" to "it should have" synergistic effect between ESIF and the Framework
Programmes in the period 2014-2020, Horizon 2020 and COSME. The guide provides
for three main features:
Parallel complementary projects with good timing;
Co-financing under the same project with clear demarcation of expenditure;
Building on the results of the projects under the Framework Programmes, where
the OPIC 2014-2020 strategy envisages to include this opportunity, given the
proximity of the possibilities for reducing the administrative burden. Project
37 According to Guidelines for mainstreaming EP and CCP in the funds for Cohesion Policy, the Common Agricultural Policy and
the Common Fisheries Policy for the 2014-2020
OPIC 2014-2020, 2014 BG16RFOP002 – September 2014
Page 62 of 274
proposals involving building on the results under 5, 6, 7 Framework Programme
and Horizon 2020 and ECSEL Joint Undertaking, will be advantagously
encouraged under the principle of bonus points in the assessment.
When providing any kind of funding the European state aid legislation will be respected
and checks for the absence of double funding will be carried out.
OPIC 2014-2020, 2014 BG16RFOP002 – September 2014
Page 63 of 274
Table 2-2: Common and programme specific result indicators for the ERDF
I
D
Indicator Measurement
unit Unit
Fund Category of
Region (where
relevant
Target value (2023) Source of data Frequency of
reporting
М W Total
1 Number of enterprises
cooperating with research
institutions (Activites 1 &
3)
Enterprises ERDF Less
developed
regions
14138
UMIS 2020
Annually
2 Number of enterprises
supported to introduce new
to the firm products
Enterprises ERDF Less
developed
regions
302 UMIS 2020
Annually
3 Number of enterprises
supported to introduce new
to the market products
Enterprises ERDF Less
developed
regions
30 UMIS 2020
Annually
4 Private investment
matching public support
for innovation or R&D
projects (all activities)
EUR ERDF Less
developed
regions
169,239,766
UMIS 2020
Annually
5 Number of enterprises
supported by the Sofia
Tech Park
Number ERDF Less
developed
regions
26 UMIS 2020
Annually
6 Number of enterprises
receiving support
Enterprises ERDF Less
developed
regions
504 UMIS 2020
Annually
38 Incl. enterprises in the supported clusters.
OPIC 2014-2020, 2014 BG16RFOP002 – September 2014
Page 64 of 274
UPlanned financial instruments
Within investment priority 1.1. it is envisaged the use of financial instruments as in
order to increase the investments in innovations new funding models are needed
especially in the areas of commercialization and transfer of knowledge. Of great
importance in that respect is the direct support for technology transfer, for active
commercialization of intellectual property and its management as basic instruments for
knowledge transfer and revenue generation.
The use of financial instruments under the present investment priority is justified also
with the existing constraints for the enterprises related with the limited access to
external sources of funding for innovation (such as development of prototypes or pilot
production), the lack of experience, mentoring, quality consultancy services, and
innovation culture as a whole.
The implementation of financial instruments for encouraging open innovation and
technology transfer will increase the effectiveness and the efficiency of funding due to
the application of market oriented approach to the assessment of the innovativeness and
the economic relevance of funded activities. Additionally this approach will provide
opportunities for attracting foreign direct investments for support of innovation and
stimulation of the demand for innovative products.
The use of financial instruments within this investment priority will focus on, but will
not be limited to the following indicative groups of financial instruments:
• equity and/or quasi equity investments in technology transfer, commercialization
of scientific results, intellectual property rights, new ideas and products;
• support through debt instruments for innovation in enterprises, including
development and launch of new products, processes and business models in
enterprises.
Equity and/or quasi equity investments in technology transfer, commercialization
of scientific results, intellectual property rights, new ideas and products: this
activity envisages the development of an equity instrument (such as technology transfer
fund), that to invest in new innovative enterprises, high technology enterprises,
knowledge-based companies, new or existing spin-offs, innovative infrastructure and
other participants in the innovation ecosystem. Significant part of the investments will
support technology transfer, transformation of scientific works into market oriented
products, processes, technologies, commercialization and management of intellectual
property. It is envisaged the instrument to be managed/implemented in collaboration
with research organizations, managers of research infrastructure, innovation
infrastructure, innovation intermediaries, including the Sofia Tech Park.
It is envisaged to combine the instrument with a grant under Priority Axis 1, providing
funding for technical assistance for specialized assessment of investments, mentoring
and consultancy for intellectual property rights, market analysis and commercialization
of the activities being subject of the investment.
The expected contribution of the instrument results in reducing the gap between
science and business, commercial application of the research results, development of a
favourable innovation environment, attraction of foreign investments and know –how,
the introduction of the Bulgarian enterprises and innovators on the international market.
The target group includes enterprises, Bulgarian enterprises in collaboration with other
Bulgarian or European companies, universities and/or research organizations; research
OPIC 2014-2020, 2014 BG16RFOP002 – September 2014
Page 65 of 274
and innovation infrastructures, innovation intermediaries, spin-off companies; high
technology enterprises, enterprises specialized in R&D, knowledge-based companies
and other participants in the innovation ecosystem. Support will be provided for
investements falling exclusively within the areas of smart specialization set in
objectives 1 and 2 of RIS3.
Support through debt instruments for innovation in enterprises, including
development and launch of new products, processes and business models in
enterprises: it is a part of the budget of a debt instrument (such as first loss portfolio
guarantee) or it is implemented separately by providing loans and/or leases for
investment in assets and/or working capital for development, and/or launching, and/or
marketing of a new or significantly improved product, service or production process, or
a new marketing approach, or a new organization method. Due to the form of funding it
is envisaged that the support will be focused towards already developed or existing
enterprises (including large enterprises) that need financial resource, but do not dispose
of the necessary collateral. In case the support is provided as part of the budget of a
single guarantee instrument, covering also Thematic objective 3, under the instrument
would be provided minimum criteria for percentage of the allocation of the resources
among the thematic objectives as well as specific requirements for compliance with the
EU legislation regarding the relevant thematic objective.
The expected contribution of these activities results in addressing one of the key
constraints of enterprises in the innovation process namely their access to finance and
the significant costs for the implementation of the innovation projects. Envisaged
activities will influence positively the following barriers: the lack of credit history of
enterprises and the high collateral requirements of the credit institutions.
The target group covers enterprises that develop/launch/introduce innovations,
including existing companies, enterprises engaged with R&D, other knowledge-based
companies. Support will be provided for investements falling exclusively within the
areas of smart specialization set in objectives 1 and 2 of RIS3.
Specific targeted territories: the territory of the whole country.
Types of Beneficiaries: fund of funds, credit and financial institutions, fund managers,
etc.
The instruments described in this priority axis are indicative and they may be
supplemented and /or replaced. This may be undertaken especially during reviewing and
updating the ex-ante assessment according to the provisions of the CPR during the
implementation of any financial instrument which has been implemented based upon
such assessment, where during the implementation phase, the managing authority
considers that the ex ante assessment may no longer accurately represent the market
conditions existing at the time of implementation. (Art. 37 par. 2 "g" of Regulation
1303/2013).
Cross-financing: Up to 10% of costs under this priority axis can be funded under
eligibility rules applicable for the European Social Fund (ESF), provided that such costs
are necessary for the proper execution of the operation and are directly related to it.
OPIC 2014-2020, 2014 BG16RFOP002 – September 2014
Page 66 of 274
2.1.2. Performance framework of the priority axis
Table 2-3: Performance framework for the implementation of Priority Axis 1
Priority
Axis
Indicator
type Name of Indicator
Measu
rement
unit,
where
appropr
iate
Fund
Catego
ry of
region
Milestone
for (2018)
Final target
(2023)51F39
Source of data
Explanation
of relevance
of indicator,
where
appropriate
M W Tot
al
PA 1 Financial Certified expenditure EUR ERD
F
Less
develo
ped
40,826,510 295,282,552 UMIS 2020
Applicable
for the whole
axis
PA 1 Output Number of enterprises receiving
support
Enterpr
ises
ERD
F
Less
develo
ped
57 504 UMIS 2020
Applicable
for the whole
axis
Additional information on the performance framework:
Interim values of the financial indicators and the output indicators are set, based on the experience and lessons learned gained during the
programming period 2007-2013.
39 Target values must be represented in total (M + W) or broken down by gender.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 67 от 274
Categories of intervention
(Reference: point (b)(vi) of Article 96(2) of Regulation (EU) No 1303/2013)
Categories of intervention corresponding to the content of the priority axis based on a
nomenclature adopted by the Commission, and indicative breakdown of Union support.
Tables 2-4, 2-5, 2-6, 2-7: Categories of intervention40
(by Fund and category of region, if the priority axis covers more than one)
Tables 2-4: Dimension 1 – Intervention field
Fund ERDF
Category of region Less developed
Priority axis Code Amount (EUR)
1 056 Investment in
infrastructure, capacities and
equipment in SMEs directly
linked to research and
innovation activities
110,867,669
1 057 Investment in
infrastructure, capacities and
equipment in large companies
directly linked to research and
innovation activities
52,275,000
1 059 Research and innovation
infrastructure (private,
including science parks)
22,652,500
1 062 Technology transfer and
university-enterprise
cooperation primarily
benefiting SMEs
34,170,000
1 063 Cluster support and
business networks primarily
benefiting SMEs
13,005,000
1 065 Research and innovation
infrastructure, processes,
technology transfer and
cooperation in enterprises
focusing on the low carbon
economy and on resilience to
climate change
14,195,000
1 096 Institutional capacity of
public administrations and
public services related to
implementation of the ERDF
or actions supporting ESF
institutional capacity
3,825,000
40
Amounts include total Union support (the main allocation and the allocation from the
performance reserve).
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 68 от 274
initiatives
Table 2-5: Dimension 2 – Form of finance
Fund ERDF
Category of region Less developed
Priority axis Code Amount (EUR)
1 01 Non-repayable grant 199,990,169
1 03 Support through financial
instruments: venture and
equity capital or equivalent
25,500,000
1 05 Support through financial
instruments: guarantee or
equivalent
25,500,000
Table 2-6: Dimension 3 – Territory type
Fund ERDF
Category of region Less developed
Priority axis Code Amount (EUR)
1 07 Not applicable 250,990,169
Table 2-7: Dimension 4 – Territorial delivery mechanisms
Fund ERDF
Category of region Less developed
Priority axis Code Amount (EUR)
1 06 Community-led local
development initiatives 27,858,750
1 07 Not applicable 223,131,419
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 69 от 274
2.2. Priority Axis 2: Entrepreneurship and Capacity for growth of SMEs
2.2.1. Investment Priority 2.1. Access to finance for supporting entrepreneurship
In accordance with Thematic Objective 3, Investment Priority 3a/Regulation 1301/2013
"promoting entrepreneurship, in particular by facilitating the economic exploitation of
new ideas and fostering the creation of new businesses ..." and according to the
identified needs at the national level within OPIC 2014-2020 and Recommendation No
5 (to improve access to finance for SMEs and start-ups) of the Council for 2013, this
investment priority provides for support to promote entrepreneurship and facilitate
access to financing for enterprises (both existing and newly created) under priority area
"Entrepreneurship " and "Access to Funding" of the National Strategy for Promotion of
SMEs 2014-2020.
Specific objective 2.1: Improving the survival rate of SMEs including through
stimulating entrepreneurship
UExpected results:
The implementation of the indicative activities under this investment priority aims at
achieving positive effect on the sustainability of the newly created enterprises.
According to SBA Fact Sheet for Bulgaria reviewing the demographic data for the
business, the latest available data (2011) show high level of dynamic. In the same year
37 000 SMEs are closed and more than 36 000 are created. The reasons for the high
level of dynamic according to the cited document are numerous, incl. financial defects
of the Bulgarian sector of the SMEs, incl. with the access to finance.
Table 2-8: Programme specific result indicators for the ERDF
No Indicator
Meas
urem
ent
unit
Category
of region
Baseline
value
Baseline
year
Target
value
(2023)
Source of
data
Frequen
cy of
reportin
g
1 Number of
enterprise
survivals up to
2 years 41
% Less
develope
d regions
74.5 2012 77.0 NSI/
Eurostat
Once in
two
years
Action to be supported under the investment priority:
Financial instruments in support of entrepreneurship incl. financial instruments
combined with grants;
Encouraging entrepreneurial ideas in areas related to European and regional
challenges and sectors defined in the National Strategy for Promotion of SMEs.
41
For calculating the base and target value of the indicator are used NSI‘s data. Enterprises with 0
employees are not included.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 70 от 274
Financial instruments in support of the entrepreneurship, incl. financial
instruments combined with grant: the indicative activities, their contribution to the
specific objective, planned target groups, target areas and type of beneficiaries are
described in the part ―Planned use of financial instruments‖.
Encouraging entrepreneurial ideas in areas related to European and regional
challenges47
42 and sectors defined in the National Strategy for Promotion of SMEs is
envisaged as an integral part of the entrepreneurship as an investment priority of the
OPIC strategy funded with grants. Given the particular importance for the EU of certain
specific areas43
related to European and regional challenges, support will be provided
for enterprises in specific areas48F, e.g. creative and cultural industries, companies
developing new products and services related to an ageing population, care and health,
including social entrepreneurship. Support of ideas that will be implemented by social
entrepreneurs and cooperatives of people with disabilities, women-entrepreneurs, start-
up entrepreneurs – persons up to 29 years and for persons aged over 50, starting new
business is also envisaged.
According to the Partnership Agreement the focus will be on regions with specific
demographic features. Entrepreneurship within the Strategy for the Danube Region can
also get support under this investment priority.
The expected contribution of these activities is development of new businesses and
enhancing competitiveness of the existing ones and the creation and sustainability of
jobs therewith in order to achieve growth in emerging areas related to European and
regional challenges.
The target group of this set of measures are: enterprises willing to implement
entrepreneurial ideas in the field of healthcare, the processes associated with population
aging, demographic issues, cultural and creative industries and others.
Territorial scope: all measures and activities within this investment priority will be
implemented throughout the country.
Types of Beneficiaries: start-ups (newly registered) and existing enterprises in the
sectors defined in the National Strategy for Promotion of SMEs and in the area of
creative and cultural industries, enterprises developing new products and services
related to an ageing population, care and health, social entrepeneurship, etc.
UGuiding proinciples for the selection of operations U:
The following guiding principles should be observed in the selection of operations
within investment priority 2.1:
Provision of funding will be made in accordance with the procedures laid down
in national legislation and the internal rules of the MA;
Coordination and synergy - coordination between ESIF programmes at national
level, the horizontal programmes and other instruments of the Union with the
aim to achieve maximum s synergy effect and avoid double funding;
42
Under paragraph (8) of the Preamble to Regulation 1301/2013 43
Creative and cultural industries, healthcare, activities related to the aging of the population, in
accordance with paragraph (8) of the Preamble to Regulation 1301/2013 with up to 2% of the
Programme‘s budget
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 71 от 274
Need-based funding – the selected operations are supposed to meet key
challenges to the business/economy identified in the Partnership Agreement,
OPIC 2014-2020 Strategy, the relevant strategic documents and documents in
implementation of specific ex-ante conditionalities;
Promoting operations whereby the end result will contribute to mitigate or abate
climate change44
;
Projects in RIS3 areas of smart specialization will be given priority;
Principle of sustainable development (art. 8 of Regulation 1303/2013) -
Managing Authority will ensure compliance with the principle of sustainable
development on the funding of operations under OP;
Effectiveness and efficiency of the investments - selected operations should fully
comply with the goals of the OP at adequate ratio between the estimated costs
and benefits. In the selection of projects it will be ensured that investments are
directed towards the most sustainable options with the most efficient use of
resources;
Relevance - selected operations should contribute to the implementation of the
output and result indicators and outcome of the programme;
Sustainability of investments – ensure sustainability of the achieved results after
project/operation completion;
Principle of partnership and transparency - the criteria for selection of operations
are subject to approval by the Monitoring Committee of the Operational
Programme;
Principle of equal opportunities - promoting equal opportunities for all,
including accessibility for people with disabilities by mainstreaming the
principle of non-discrimination;
Specific thematic focus - financed through grants will be operations in areas
related to European and regional challenges and sectors defined in the "National
Strategy for the Promotion of Small and Medium Enterprises" 2014 to 2020.
When providing any kind of support, the European state aid rules will be complied with
and checks for the absence of double funding will be carried out.
UPlanned financial instruments
According to Communication from the Commission to the European Parliament, The
Council, The European Economic and Social Committee and the Committee of the
Rregions ―Entrepreneurship 2020‖ Action plan, the access to finance constitutes one of
the most significant constraints on growth and entrepreneurship in Europe.
Entrepreneurs particularly have difficulties raising finance in the early stages of their
businesses. It is also important to increase the quality and financial returns of start-up
projects.
44 According to Guidelines for mainstreaming EP and CCP in the funds for Cohesion Policy, the Common Agricultural Policy and
the Common Fisheries Policy for the 2014-2020
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 72 от 274
An important component of a successful entrepreneurial ecosystem consist of an array
of early stage investors that provide seed and first round equity investments. These
investors use an extensive network of peers and provide valuable knowledge and
support about the market and the development of the venture "smart money".
In relation to this the planned use of financial instruments within the present investment
priority includes without limiting to the following indicative groups of financial
instruments:
• Equity and quasi-equity investments in seed capital;
• Equity and quasi-equity investments in start-up capital and early stages of
development.
Equity and quasi-equity investments in seed capital: the activities will be
implemented through equity instrument (e.g. Acceleration and Seed fund), that
combines two interrelated components: acceleration component, which provides initial
financing, supplemented by mentorship, and this stage ends up with a final product
concept, prototype or beta version; the seed component provides funding to successful
graduates from the acceleration component as well as supports other start-ups.
The instrument is envisaged to be combined with grants for ensuring a technical
assistance support for some of the activities of the funds.
The expected contribution of these activities is to create new sustainable businesses
and jobs therewith, by increasing entrepreneurial activity as well as successful
implementation of new business ideas.
The target group of this set of measures is: starting entrepreneurs, newly registered
companies wishing to implement a business idea amounting more than € 25,000; start-
up companies;
Equity and quasi-equity investments, providing capital for start-ups and
companies in the early stages of development: the activities will be implemented
through equity instrument (eg. Risk Capital Fund), the instrument is focused primarily
on micro, small and medium-sized enterprises (SMEs) in the field of high technologies
and at the stage of early development, which often have difficulties finding additional
capital to support their growth, as they are considered too risky.
The expected contribution: A considerable part of the newly created enterprises cease
their activity during the first five years from their establishment. The companies usually
do not have access to adequate ecosystem supporting their growth. Providing
appropriate support can significantly increase the success of the new enterprises.
Target group: SMSs in their early stages of development, innovative SMEs, high-tech
SMEs, SMEs with high risk profile.
Territorial scope: all measures and activities will be implemented throughout the
country.
Types of Beneficiaries: fund of funds, fund managers, etc.
The instruments described in this priority axis are indicative and they may be
supplemented and /or replaced. This may be undertaken especially during reviewing and
updating the ex-ante assessment according to the provisions of the CPR during the
implementation of any financial instrument which has been implemented based upon
such assessment, where during the implementation phase, the managing authority
considers that the ex ante assessment may no longer accurately represent the market
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 73 от 274
conditions existing at the time of implementation. (Art. 37 par. 2 "g" of Regulation
1303/2013).
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 74 от 274
Table 2-9: Common and programme specific output indicators for the ERDF
ID Indicator Measurement unit Unit Fund Category of
Region (where
applicable)
Target value (2023)49F45
Data source Frequency
of reporting
М W Total
1 Number of new enterprises
supported (all activities)
Enterprises ERDF Less developed
regions
390 UMIS 2020
Annually
2 Number of enterprises receiving
support (all activities)
Enterprises ERDF Less developed
regions
564 UMIS 2020
Annually
3
Number of enterprises receiving
financial support other than grants
(Activity 1)
Enterprises ERDF Less developed
regions
392
UMIS 2020
Annually
4 Number of enterprises receiving
grants
Enterprises ERDF Less developed
regions
172 UMIS 2020
Annually
5 Private investment matching public
support to enterprises (grants)
EUR ERDF Less developed
regions
5,155,952 UMIS 2020
Annually
6 Private investment matching public
support to enterprises (non-grants)
EUR
ERDF
Less developed
regions
7,140,000 UMIS 2020
Annually
7 Employment increase in supported
enterprises
full-time equivalents ERDF Less developed
regions
390 UMIS 2020
Annually
45
For the ESF, this list includes common output indicators for which a target value has been set. Target values may be presented as a total (men+women) or broken down by
gender. For the ERDF and the Cohesion Fund, gender breakdown is in most cases not relevant. ―M‖ = men, ―W‖=women, ―T‖= total.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 75 от 274
2.2.2. Investment Priority 2.2: Capacity for SMEs to grow
In accordance with Thematic Objective 3 Investment Priority 3d/Regulation 1301/2013
"support the capacity for growth of SMEs at regional, national and international markets
and participation in the innovation process" and according to the identified needs at
national level within the OPIC 2014-2020 and Recommendation No. 5 (to improve
access for SMEs and start-ups to finance) of the Council for 2013, under this investment
priority support is to be provided for strengthening the competitiveness of the Bulgarian
enterprises, including meeting the criteria for priority areas "Access to Finance",
"Internationalization" and "Skills and innovation" of the National Strategy for
Promotion of SMEs 2014-2020.
Specific Objective 2.2.: Strengthening productivity and export potential of Bulgarian
SMEs
UExpected results
The implementation of the indicative measures under this investment priority aims at
achieving a positive effect on the development of a sustainable market competitiveness
of the Bulgarian SMEs, in order to increase their productivity and export potential.
Particular emphasis is placed on the quality of products and services to businesses, their
potential to realize higher performance in the value chain and rapid provision of market
stability in a highly dynamic and competitive environment. The expected results are
related to the creation and development of competitiveness of the enterprises based on
improved efficiency and effectiveness of the production processes, incl. by improving
resource efficiency, increased production capacity and quality of products, improved
capacity to manage and implement new business models and practices. By accessing the
technology and innovative resource, the Bulgarian SMEs will realize the opportunities
offered by the global market and thus improve their market position.
Table 2-10: Programme specific result indicators for the ERDF
N
o Indicator
Measuremen
t unit
Category
of region
Baseline
value
Baselin
e year
Target
value
(2023)
Sourc
e of
data
Frequenc
y of
reporting
1 Export
volume of
goods and
services
achieved by
SMEs
Billion Euro Less
develope
d regions
8.1 2012 9.18 NSI Every
two years
2 Productivity
of SMEs
value added
at factor
costs (BGN
in
thousand)/e
mployed
person
Less
develope
d regions
16.8 2012 19.3 NSI Every
two years
Description of the types and indicative activities to be financed and their expected
contribution to the relevant specific objectives:
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 76 от 274
The support under this investment priority is envisaged to be focused on, but not limited
to the following indicative groups of activities and combinations thereof:
general productive investments for enhancing the production capacity for growth
through effective and efficient use of the factors of production and through
creation of opportunities for adoption and adaptation of European and
international knowledge and technology;
support for specialized services to SMEs to develop and strengthen the
management capacity;
support for the growth of businesses by improving the quality and by promoting
the use of ICT and services;
support for the implementation of activities and services for direct benefit of the
business development and opportunities for SMEs export.
The general productive investments for improving the production capacity for
growth and creating competitive advantage through the effective and efficient use
of the factors of production and through creation of opportunities for adoption
and adaptation of European and international knowledge and technology will
include measures to increase productivity, effective and efficient use of the factors of
production (human capital, natural resources and technology), improvement of
production processes through investments in tangible and intangible assets, introduction
of leading technology solutions and/or reengineering of processes to expand production
by adding new features or improving the existing products and services and
diversification of operations by diversifying the portfolio of businesses and the access to
markets.
Efficiency and competitiveness of enterprises will be improved through measures for
implementation of new technologies / practices / methods / systems to improve resource
efficiency and effectiveness in the production process, implementation of best practices
/technological methods / technologies / processes to reduce consumption of natural
resources, waste technologies, recycling of secondary raw materials and production
waste, regeneration etc.
The expected contribution from the implementation of this set of measures relates to
improving competitiveness and creating potential for export and as a result - improving
market presence of Bulgarian SMEs - through embedded technology to improve the
manufacturing process to achieve higher performance, reduce production costs and
optimize the production chain, respectively, increase the added value and actively
involve in all stages of the added value chain.
The target group of indicative measures is: SMEs under NSPSMEs.
Support for specialized services to SMEs to develop and strengthen the
management capacity will be directed to the management of the production factors
with an emphasis on building the capacity for adoption and adaptation of the European
and international knowledge and best practices. To increase competitiveness and as a
result - the export potential of Bulgarian SMEs through investment will be encouraged:
development, implementation and certification of quality management, environmental
protection, eco labeling, energy management, information security and others under
international, European and national standards; development, transfer, implementation
and certification of good manufacturing practices; services for processes reengineering
in enterprises; transfer of new models for managing change and quick adaptation to
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 77 от 274
them; develop strategies for marketing, research and transfer tools to enter new markets
to satisfy market demand and diversification of supply.
This set of measures also includes support to improve the conditions and processes for
the functioning and development of SMEs and to ensure fair competition and a
favorable business environment for economic operators (eg. metrological and technical
supervision, quality control and notification to conformity assessment bodies) -
monitoring of compliance with the legal obligations of producers and economic
operators to avoid doing business in the "informal sector"; completion and accreditation
of laboratories for checking and validation the conformity of national and EU quality
standards and brands recognition of national product. Additional support will be
provided in the implementation of the overall policy to ensure compliance of Bulgarian
products with international quality standards to support growth of enterprises.
The expected contribution of the implementation of this measures is related to
improving the capacity of Bulgarian SMEs to work in intense competitive markets,
increasing competitiveness and respectively the stable presence of Bulgarian SMEs on
the foreign markets by improving, maintaining and ensuring the quality of products /
processes / services and provision of objective guarantee for the quality and use of good
manufacturing practices, and by developing and strengthening management capacity.
The target group of indicative measures is: SMEs under NSPSMEs, organizations,
institutions, agencies for business support and improvement of business environment.
Support the growth of enterprises by promoting the use of ICT and services – the
support aims at improving the quality of existing processes, products and services
through the development and implementation of ICT-based systems and applications,
including "virtualised", "cloud" and "mobile": for business management, including
those for integration of various units and locations of a company, computer aided
design, engineering and production; for transformation of business and operating
processes that lead to increased productivity and competitiveness; electronic business
platforms to improve access to foreign markets. Support will be also provided through
introduction of pilot voucher schemes, including innovation vouchers in the ICT field.
The expected contribution of the implementation of this measures is related to
improving the capacity of SMEs for doing a competitive and sustainable business in
dynamic emerging markets, as well as to providing faster and easier access to foreign
markets through increasing and improving the use of ICT, and optimization of business
process management.
The target group of the indicative measures is: SMEs under NSPSMEs, organizations,
institutions, agencies for business support and improvement of the business
environment.
Support for the implementation of activities and services for direct benefit to
business development and opportunities for SMEs export – investment will be made
for improvement of entrepreneurial culture on unification of SMEs in clusters;
promoting international activities of Bulgarian SMEs by providing information and
advices about European and third country markets, organizing trainings for
internationalization and export management of SMEs, organization of showrooms and
information events in Bulgaria, of business forums in the country and abroad,
supporting the participation of enterprises in trade missions abroad, as well as in
national and international exhibitions to promote Bulgarian production; information,
business statistics, databases and etc.; investment and export-oriented activities,
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 78 от 274
including support to export-focused associations, organizing visits to potential investors
and partners of SMEs in the country; programmes to attract foreign investments in
targeted sectors and countries through proactive investement marketing.
In the field of tourism the support for SMEs will be realized through institutional
support for establishment and operation of organizations for management of tourist
areas regulated by the Law on Tourism, including activities aimed at: capacity building
of the enterprises for easier access and presence on the national and international
markets; for establishment of a unity system for tourist information at national level as a
platform for networking tourism business, tourism organizations and institutions;
support for the introduction of ICT and provision of ICT services; conducting market
studies, analyzes and forecasts; developing product, marketing and investment concepts,
strategies, plans, etc.; organizing business forums in the country and abroad, supporting
participation in events and exhibitions, (regional, national and international).
The expected contribution from the implementation of these measures relates to the
development of export orientation, awareness, partnership and international market
presence of Bulgarian SMEs and as a result increase in the export of Bulgarian SMEs
by creating opportunities for the Bulgarian SMEs for realization on foreign markets,
promotion of production, expanding access to and provision of information for foreign
markets.
The target group of the indicative measures is: SMEs under NSPSMEs, associations
and business associations as well as organizations and institutions that are associated
with the implementation of activities and provision of services in support of business
and improvement of business environment.
Territorial scope: measures and activities within this investment priority will be
implemented throughout the country, and some limited activities abroad are also
possible.
Types of Beneficiaries: existing micro, small and medium-sized enterprises according
to the National Strategy for Promotion of SMEs 2014-2020 for operations financed
through grants, clusters (including new and existing clusters within the Strategy for the
Danube region, the Action Plan, PA 3), business associations as well as organizations
and institutions that are associated with implementation of activities and provision of
services in support of business and improvement of business environment.
UGuiding principles for the selection of operationsU:
The following guiding principles should be observed in the selection of operations
within the investment priority:
Provision of funding will be made in accordance with the procedures laid down
in national legislation and the internal rules of MA;
Coordination and synergy - coordination between ESIF programmes at national
level, the horizontal programmes and other instruments of the Union with the
aim to achieve maximum synergy effect and avoid double funding;
Projects in RIS3 areas of smart specialization will be given priority;
Need-based funding – the selected operations are supposed to meet key
challenges to the business/economy identified in the Partnership Agreement,
OPIC 2014-2020 Strategy, the relevant strategic documents and documents in
implementation of specific ex-ante conditionality;
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 79 от 274
Promoting operations whereby the end result will contribute to mitigate or abate
climate change46
;
Principle of sustainable development (art. 8 of Regulation 1303/2013) -
Managing Authority will ensure compliance with the principle of sustainable
development on the funding of operations under OP;
Effectiveness and efficiency of the investments – the- selected operations should
fully comply with OP goals at adequate ratio between the estimated costs and
benefits. In the selection of projects it will be ensured that investments are
directed towards the most sustainable options with the most efficient use of
resources;
Relevance - selected operations should contribute to the implementation of the
output and result indicators and outcome of the programme;
Sustainability of investments – ensure sustainability of the achieved results after
project/operation completion;
Principle of partnership and transparency - the criteria for selecting the
operations are subject to approval by the Monitoring Committee of the
Operational Programme;
Principle of equal opportunities - promoting equal opportunities for all,
including accessibility for people with disabilities by mainstreaming the
principle of non-discrimination;
Specific thematic focus - in the selection of operations financed through grants
key importance will be given to the "National Strategy for the Promotion of
Small and Medium Enterprises" 2014 - 2020.
When providing any kind of support, the European state aid rules will be complied with
and checks for the absence of double funding will be carried out.
46 According to Guidelines for mainstreaming EP and CCP in the funds for Cohesion Policy, the Common Agricultural Policy and
the Common Fisheries Policy for the 2014-2020
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 80 от 274
Table 2-11: Common and programme specific output indicators for the ERDF
ID Indicator Measurement unit Fund Category of
Region (where
applicable)
Target value
(2023)50F47
Source of data Frequency of
reporting
M W Total
1 Number of enterprises receiving
support (all activities)
Enterprises ERDF Less developed
regions
7,411 UMIS 2020
Annually
2 Number of enterprises receiving
grants
Enterprises ERDF Less developed
regions
1,464 UMIS 2020
Annually
3 Number of enterprises receiving
financial support other than grants
Enterprises ERDF Less developed
regions
3,447 UMIS 2020
Annually
4 Number of enterprises receiving
non-financial support
Enterprises ERDF Less developed
regions
2,500 UMIS 2020
Annually
5 Private investment matching public
support to enterprises (grants)
EUR ERDF Less developed
regions
153,047,615
UMIS 2020
Annually
6 Private investment matching public
support to enterprises (non-grants)
EUR ERDF Less developed
regions
438,000,000
UMIS 2020
Annually
47
For the ESF, this list includes common output indicators for which a target value has been set. Target values may be presented as a total (men+women) or broken down by gender.
For the ERDF and the Cohesion Fund, gender breakdown is in most cases not relevant. ―M‖ = men, ―W‖=women, ―T‖= total.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 81 от 274
UPlanned financial instruments
High importance for the strengthening of the export potential of the SMEs represents:
decrease of the constraints among the enterprises related with difficult access to finance
due to the high collateral and interest rates; improve of the access to SMEs to the
markets for risk capital, as well as increase of the level of awareness of the investors
concerning the capacity of the SMEs.
In relation to the above mentioned the planned application of financial instruments
under this investment priority is envisaged to be focused on, but not limited to the
following indicative groups of financial instruments:
equity and/or quasi equity investments for support of enterprises with high
potential to grow;
support through debt instruments for growth and development, facilitating
improvement of the access to finance of the enterprises;
support through debt instruments for microfinance tailored to needs for finance
for growth of micro enterprises;
Equity and/or quasi equity investments for support of enterprises with high
potential to grow: the activities will consist of investments in the development of
SMEs and they may include and mezzanine capital, as well. The instrument will
focus on enterprises in their growth stage or mature stage of development, which
need additional investments in order to implement their strategy for growth..
The expected contribution of the instrument is to increase the capacity for growth
of the SMEs, to support the internationalization of the enterprises through the
expansion of their capacity for growth on international markets. The instrument will
lead to improvement of the management capacity and the organization of the
enterprise activity, as a result of the attracted investments. That will lead to the
development of their capacity to participate in the innovation process.
The target groups of this set of measures are: SMEs in phase of growth or mature
stage of development, other relevant SMEs.
Support through debt instruments for growth and development, facilitating
access to finance for enterprises: will be provided as part of the budget of the debt
instrument (e.g. First Loss Portfolio Guarantee) under Thematic Objective 1 or as a
single debt instrument. The support will cover loans and / or leases for investments
and / or working capital for growth and development of SMEs.
Expected contribution: the instrument will contribute to increased competitiveness
and respectively to the sustainable presence of Bulgarian SMEs in national and
international markets by improving, maintaining the quality of the delivered
products / processes /services, and will allow the credit and financial institutions to
extend the portfolio of the funded SMEs and will facilitate the access to debt
financing ofr many small and medium-sized enterprises which are facing difficulties
in accessing traditional banking system.
The target group: SMEs at the stage of their growth or maturity; other relevant SMEs.
Support through debt instruments for microfinance tailored to needs for finance
for growth of micro enterprises: will be implemented through an instrument for micro
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 82 от 274
loans mainly for micro enterprises at preferential interest rates and collateral
requirements. The instrument may be implemented as a portfolio risk sharing loan.
The expected contribution of the implementation of this instrument is to fill the
existing gap in the Bulgarian market, where currently the micro funding is not well
developed, while focusing on the problems of micro enterprises related with the access
of finance and barriers for growth.
The target group of the indicative measures is notably micro enterprises.
Territorial scope: all measures and activities will be implemented throughout the
country.
Types of Beneficiaries: fund of funds, credit and financial institutions and other entities
entitled to grant credits on the territory of the Republic of Bulgaria, fund managers, etc.
The instruments described in this priority axis are indicative and they may be
supplemented and /or replaced. This may be undertaken especially during reviewing and
updating the ex-ante assessment according to the provisions of the CPR during the
implementation of any financial instrument which has been implemented based upon
such assessment, where during the implementation phase, the managing authority
considers that the ex ante assessment may no longer accurately represent the market
conditions existing at the time of implementation. (Art. 37 par. 2 "g" of Regulation
1303/2013).
Cross-financing: Up to 10% of costs under this priority axis can be funded under
eligibility rules applicable for the European Social Fund (ESF), provided that such costs
are necessary for the proper execution of the operation and are directly related to it.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 83 от 274
2.2.3. Performance framework for the implementation of the priority axis
Table 2-12: Performance framework for the implementation of Priority Axis 2
Priority
Axis
Type of
Indicator Name of Indicator
Measur
ement
unit,
where
appropr
iate
Fund
Categor
y of
region
Milestone for
(2018)
Final target
(2023)51F48
Source of data
Explanation
of relevance
of indicator,
where
appropriate M W Tot
al
PA 2 Financial Certified expenditure EUR ERD
F
Less
develop
ed
188,847,615 697,492,050 UMIS 2020
Applicable
for the whole
axis
PA 2 Output Private investment matching
public support to enterprises
(grants and non-grants)
EUR ERD
F
Less
develop
ed
63,093,284 603,343,567 UMIS 2020
Applicable
for the whole
axis
Additional information on the implementation framework:
Interim values of the financial indicators and the output indicators are set, based on the experience and lessons learned gained during the
programming period 2007-2013..
48
Target values must be represented in total (M + W) or broken down by gender.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 84 от 274
Categories of intervention
(Reference: point (b)(vi) of Article 96(2) of Regulation (EU) No 1303/2013)
Categories of intervention corresponding to the content of the priority axis based on a
nomenclature adopted by the Commission, and indicative breakdown of Union support.
Tables 2-13, 2-14, 2-15, 2-16: Categories of intervention49
(by Fund and category of region, if the priority axis covers more than one)
Tables 2-13: Dimension 1 – Intervention field
Fund ERDF
Category of region Less developed
Priority axis Code Amount (EUR)
2 001 Generic productive
investment in small and
medium – sized enterprises
(‗SMEs‘)
370,170,945
2 063 Cluster support and
business networks primarily
benefiting SMEs
32,512,500
2 066 Advanced support
services for SMEs and groups
of SMEs (including
management, marketing and
design services)
42,021,368
067 SME business
development, support to
entrepreneurship and
incubation (including support
to spin offs and spin outs)
68,000,000
2 073 Support to social
enterprises (SMEs) 14,608,530
2 076 Development and
promotion of cultural and
creative assets in SMEs
2,921,706
2 077 Development and
promotion of cultural and
creative services in or for
SMEs
2,921,706
2 082 ICT Services and
applications for SMEs
(including e-Commerce, e-
Business and networked
business processes), living
labs, web entrepreneurs and
ICT start-ups)
30,036,486
49
Amounts include total Union support (the main allocation and the allocation from the
performance reserve).
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 85 от 274
2 096 Institutional capacity of
public administrations and
public services related to
implementation of the ERDF
or actions supporting ESF
institutional capacity
initiatives
21,675,000
Table 2-14: Dimension 2 – Form of finance
Fund ERDF
Category of region Less developed
Priority axis Code Amount (EUR)
2 01 Non-repayable grant 376,118,242
2 03 Support through financial
instruments: venture and
equity capital or equivalent 102,000,000
2 04 Support through financial
instruments: loan or
equivalent 12,750,000
2 05 Support through financial
instruments: guarantee or
equivalent 102,000,000
Table 2-15: Dimension 3 – Territory type
Fund ERDF
Category of region Less developed
Priority axis Code Amount (EUR)
2 07 Not applicable 592,868,242
Table 2-16: Dimension 4 – Territorial delivery mechanisms
Fund ERDF
Category of region Less developed
Priority axis Code Amount (EUR)
2 06 Community-led local
development initiatives 31,222,026
2 07 Not applicable 561,646,216
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 86 от 274
URationale for Priority Axis 3
Bulgarian enterprises rank first in energy and resource intensity per unit of output and
somewhere in the last positions in environmental performance, which are the main
prerequisites for the creation of sustainable competitiveness. High levels of
consumption and cost of raw materials and energy in the production and the low level
of environmental performance are related to depreciated and outdated technologies
and limited access to new practices, systems and production patterns. Renewal of the
existing production equipment is indispensable, but is delayed due to lack of financial
resources and relatively slow return on investment in new ones, as the prices of
electricity and resources in the country are still some of the lowest. It‘s necessary to
encourage businesses to undertake investments to increase the resource and energy
efficiency, which will reduce the cost of production per unit of output, will contribute
to the introduction and development of eco-industries and increase sustainable
competitiveness of enterprises.
Priority Axis 3 "Energy and Resource Efficiency" will provide targeted support for the
transition to a low carbon economy in all sectors of production (Thematic Objective 4 )
and promote efficient use of resources (Thematic Objectivel 6 ).
Promoting energy efficiency and resource efficiency in eneterprises, especially those
from the manufacturing industry, is a important and imperative process since these
companies contribute in the greatest extent to the low productivity of resources and the
low energy efficiency of the economy. According to the framework proposed by the
European Commission52F
50, energy efficiency is a key component of resource efficiency
and the integrated guidelines of the Commission indicate that a decoupling of economic
growth from use of resources is necessary; and the environmental challenges turn into
opportunities for growth through efficient use of natural resources. The desired and
expected effect of the targeted support for improving energy efficiency and
environmental performance in the economy can only be achieved through joint
implementation under one priority axis of measures to introduce energy efficient
technologies and productions for effective use of resources in the companies, in
compliance with:
4.b/of Art. 5 of Regulation 1301/2013 "Promotion of energy efficiency and use
of renewable energy in enterprises";
6.g/ of Art. 5 of Regulation 1301/2013 "Support for industrial shift towards a
resource efficient ecomomy, through promoting green growth, eco-innovation
and environmental performance management in the public and private sector" -
in the part on effective use of resources.
In line with this framework, and seeking a synergistic result, interventions under
Priority Axis 3 are grouped into two investment priorities
Investment Priority 3.1: Energy technology and energy efficiency;
Investment priority 3.2: Resource efficiency.
50
Resource Efficient Europe flagship initiative и Resource Efficiency Scoreboard
2.3. Priority Axis 3: Energy and Resource Efficiency
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 87 от 274
2.3.1. Investment Priority 3.1: Energy technologies and energy efficiency
In accordance with Thematic Objective 4 "Supporting the shift towards a low carbon
economy in all sectors" and according to the identified needs at national level within the
OPIC 2014-2020, this investment priority provides for support for reducing the energy
intensity of the economy, primarily through increased energy efficiency and flexibility
of the enterprises, and hence of the country's economy in line with the Energy Strategy
of R. Bulgaria till 2020 and National Energy Efficiency Action Plan 2014-2020. The
enterprises are to be supported for measures with energy saving potential on the basis of
energy audit and thereby their implementation is expected to contribute with more than
7 % to the national objective for additional energy savings in EEP51
set in the Plan and
more than 40% of the objective for additional energy savings by the industry.
Specific Objective 3.1.: Reducing energy intensity of the economy
UExpected results
As a result of the implementation of the activities envisaged under this priority
investment, an improvement of the energy efficiency of the enterprises is excpected,
which shall result in reduction of the energy intensity both at the level of separate
production enterprises and for the entire economy.
Table 2-17: Programme specific result indicators for the ERDF
N
o
Indicat
or Measurement Unit
Category
of region
Baselin
e
value
Baseline
year
Target
value
(2023)
Sour
ce of
data
Frequency
of reporting
1 Energ
y
intensi
ty of
the
econo
my
t.o.e. per 1000 euro
GDP
Less
develope
d regions
0.671 2012 0.604 NSI Four times
for the
implementat
ion period
of OPIC
UActions to be supported under the investment priority:
Support within the investment priority will be focused, but not limited to the following
indicative sets of activities:
support for increasing the energy efficiency in enterprises;
institutional support for sustainable energy development.
Support for increased energy efficiency in enterprises - includes preparing and
conducting audits for energy efficiency in enterprises52
and subsequent implementation
51
National objective fir additional energy savings in EEP is 230 ktoe/y as the objective for the industry is
calculated at 33.97 ktoe/y. 52
to perform energy audits will be supported only enterprises that do not fall under the mandatory regime
under the Energy Efficiency Directive
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 88 от 274
of the recommended measures in the audit reports. The support includes investments in
tangible and intangible assets, energy management and implementation of technologies
and production lines, ICT-based systems to manage energy efficiency, waste heat
recovery in the industry, support of highly efficient small-scale and micro-co-
generations and rehabilitation of district heating networks, etc that increase the energy
efficiency in the supported enterprises. leading to increased energy efficiency in the
supported enterprises. As additional activities will be supported the use of RES energy
for own needs (electric and heat energy and cooling energy). Given that buildings have
a significant contribution to improving the energy efficiency, complementary support
for construction works to improve the energy and thermal performance of the
production buildings of enterprises will also be provided once their effect and the
relation to such activities is proven. Support will also be possible for projects in the field
of "blue" growth if proven the demand and the potential for development of "blue"
energy (energy of waves, currents, tides, using the difference between the salt
concentration in the water, etc.). The realized energy savings will result in reduction of
greenhouse gas emissions.
The expected contribution of these supported activities relates to increasing the energy
efficiency of the supported enterprises, which will reduce their production costs,
improve their environmental performance and increase their competitiveness. In turn,
this will have a positive effect not only on the specific enterprises supported, but also on
the entire economy.
Target group – existing enterprises (with the exception of of trade and services
sectors).
The institutional support for sustainable energy development aims at providing the
necessary institutional prerequisites for an integrated approach to energy efficiency and
renewable energy, for example by supporting the capacity building of SEDA to improve
the quality and quantity of services provided to Bulgarian enterprises, as well as
increased opportunities for energy management of enterprises. The support is mainly
aimed at the introduction of the mechanism for trade of ―white‖ certificates elaborated
within the 2007-2013 period project or energy efficiency obligation scheme and the
related activities for the popularization and training of the participants in the process.
The ―tradable white certificates‖ ор energy efficiency obligation scheme are a new
financial mechanism in the EU an are envisaged to support the efforts for the increase of
the energy efficiency by complementing the existing policies and measures and
contributing to the achievement of the energy efficiency objectives.
The expected contribution of this support is improved coordination and synergy of the
measures in the field of energy efficiency.
Types of beneficiaries: existing enterprises (except grant support for trade and services
sectors); Sustainable Energy Development Agency (SEDA).
Territorial scope: throughout the country
UGuiding principles for the selection of operationsU:
The following guiding principles should be observed in the selection of operations
within the investment priority:
Provision of funding will be made in accordance with the procedures laid down
in national legislation and the internal ones of the MA;
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 89 от 274
Coordination and synergy - coordination between ESIF programmes at national
level, the horizontal programmes and other instruments of the Union with the
aim to achieve maximum s synergy effect and avoid double funding;
Need-based funding – the selected operations are supposed to meet key
challenges to the business/economy identified in the Partnership Agreement,
OPIC 2014-2020 Strategy, the relevant strategic documents and documents in
implementation of specific ex-ante conditionality;
Promoting operations whereby the end result will contribute to improve resource
efficiency and/or to mitigate or abate climate change53
;
Principle of sustainable development (art. 8 of Regulation 1303/2013) -
Managing Authority to ensure compliance with the principle of sustainable
development on the funding of operations under OP;
Effectiveness and efficiency of the investments - selected operations should
comply fully with the goals of the OP at the adequate ratio between the
estimated costs and benefits. In the selection of projects will ensure that
investments are directed towards the most sustainable options with the most
efficient use of resources;
Relevance - selected operations should contribute to the implementation of the
output and result indicators and outcome of the programme;
Sustainability of the investments – ensure sustainability of the achieved results
after project/operation completion;
Principle of partnership and transparency - the criteria for selecting the
operations are subject to approval by the Monitoring Committee of the
Operational Programme;
Principle of equal opportunities - promoting equal opportunities for all,
including accessibility for people with disabilities by mainstreaming the
principle of non-discrimination;
Specific thematic focus - in the selection of operations with the key importance
will be the ―Energy Strategy of R. Bulgaria‖ till 2020 and National Energy
Efficiency Action Plan 2014-2020;
In accordance with art.3, (3), b of Regulation (EU) 1301/2013 there will be no
support for investments to achieve the reduction of the greenhouse gas emissions
for activities listed in Annex I of Directive 2003/87/EC
53 According to Guidelines for mainstreaming EP and CCP in the funds for Cohesion Policy, the Common Agricultural Policy and
the Common Fisheries Policy for the 2014-2020
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 90 от 274
Table 2-18 Common and programme specific output indicators for the ERDF
ID Indicator Measurement unit Fund Category of
Region (where
applicable)
Target value
(2023)
Source of data Frequency of
reporting
1 Number of enterprises
receiving support Enterprises ERDF Less developed
regions
719 UMIS 2020
annually
2 Number of enterprises
receiving grants Enterprises ERDF Less developed
regions
528 UMIS 2020
annually
3 Energy audits performed Enterprises
ERDF Less developed
regions
662 UMIS 2020
annually
4 Expected energy savings in
enterprises as a result of
completed projects
МWh/y
ERDF Less developed
regions
179,794 UMIS 2020
annually
5 GHG reduction tons CO2 equiv.
ERDF Less developed
regions
55,017 UMIS 2020
annually
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 91 от 274
UPlanned financial support
Type of beneficiary Type of support
Existing enterprises Grants
SEDA Grants
Upon providing any kind of support, the European state aid rules will be complied with
and checks for the absence of double funding will be carried out.
Planned financial instruments
In the implementation of the instrument under this investment priority will be taken into
account both the higher potential for energy savings of the projects implemented by
large enterprises and major difficulties faced by SMEs in access to information and
finance.
According to the National Action Plan for Energy Efficiency 2014-2020, reduction of
energy consumption in the buildings sector is important measure, needed to reduce
greenhouse gas emissions, for this reason the support through the financial instrument
under this investment priority will focus on energy efficiency of industrial buildings and
buildings / premises, used primarily for economic activities. Under this investment
priority will not be suported the energy efficiency of administrative buildings, student
dormitories and residential buildings covered by Operational Programme ―Regions in
Growth‖ 2014 - 2020.
Under this investment priority the following financial instrument is planned:
Debt instrument for energy efficiency measures in enterprises - the support will be
provided through a debt instrument (e.g. First Loss Portfolio Guarantee) providing
investment loans / leases to increase energy efficiency of enterprises. Under the
instrument is envisaged focus on energy efficiency of industrial buildings and buildings
/ premises, used primarily for economic activies including these forming parts of an
industrial system. Under mentioned instrument may be attracted financial resources
from international financial institutions under condition that an interest is expressed
from their side and they offer acceptable conditions for participation in the
implementation of the instrument.
The instrument may be combined with grants for technical support with the aim to
support the enterprises in identification and assessment of investment opportunities
from a technical perspective for the implementation of energy efficiency measures, as
well as for the preparation of bankable energy efficiency projects.
The expected contribution of this support is related with increase of energy efficiency
in supported enterprises, which will result in reduction of the their production costs,
increase of their environmental integrity and enhancing of their competitiveness.
Because of the possible participation of international financial institution, the instrument
may also lead to increase of the capacity of enterprises and of the administrative
capacity for the implementation of energy efficiency measures.
Target group are existing enterprises implementing energy efficiency measures.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 92 от 274
Types of beneficiaries: fund of funds, financial and credit institutions, other similar
organizations.
Territorial scope: throughout the country.
The instrument described in this priority axis is indicative and it may be supplemented
and /or replaced. This may be undertaken especially during reviewing and updating the
ex-ante assessment according to the provisions of the CPR during the implementation
of any financial instrument which has been implemented based upon such assessment,
where during the implementation phase, the managing authority considers that the ex
ante assessment may no longer accurately represent the market conditions existing at the
time of implementation. (Art. 37 par. 2 "g" of Regulation 1303/2013).
Upon providing any kind of support, the European state aid rules will be complied with
and checks for the absence of double funding will be carried out.
2.3.2. Investment Priority 3.2: Resource Efficiency
In accordance with Thematic Objective 6 "Environmental protection and promotion of
the efficient use of resources" and according to the identified needs at national level
within OPIC 2014-2020, this investment priority provides support for increasing the
resource efficiency of businesses, including a contribution to the criteria in the priority
area "Environment" of the National Strategy for Promotion of SMEs 2014-2020.
Specific Objective 3.2.: Increase the share of SMEs with introduced resource
efficiency measures
UExpected results
This investment priority is aimed at improving resource efficiency and raise awareness
for enterprises in relation to the available opportunities by supporting the activities
related to increased waste recovery and reduced waste generetaion, reduced costs of raw
materials through pilot and demonstration innitiatives. The expected results are directly
related to improving the resource efficiency of the supported enterprises, and hence the
production sectors and the economy as a whole, thus contributing to the implementation
of the respective target by NSPSMEs54
.
Table 2-19: Programme specific result indicators for the ERDF
No Indicator
Measur
ement
Unit
Category of
region
Baseline
value
Baseline
year
Target
value
(2023)
Source
of data
Frequenc
y of
reporting
1 Share of SMEs
with measures
of resource
% Less
developed
regions
85% 2012 93%55
SBA
Fact
sheets
Every
two
years
54
In NSPSMEs is set at specific target for increase of the share of SMEs with measures of resource
efficiency from 85% to more than 93%.
55 According NSPSMEs: 2020 the share of SMEs with effective use of resources should exceed 93%. Support by IP
2.2 under OPIC 2014-2020 will contribute to the national target set in NSPSMEs.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 93 от 274
efficiency
UActions to be supported under the investment priority
The support within the investment priority will focus on, but will not be limited to:
support for pilot and demonstration innitiatives to increase the resource
efficiency in enterprises or group of enterprises.
To increase the efficient use of resources in enterprises or group of enterprises
measures will be supported to improve the resource efficiency and sustainable use of
raw materials, incl industrial symbiosis: introduction of high-tech and ICT solutions for
optimizing the production processes and reducing the use of raw materials;
implementation of modern technologies for use of waste as a raw material in new
production and/or other alternative uses; implementation of modern wastefree
technologies, incl. replacement of obsolete and resource-intensive equipment;
implementation of innovative production materials and increasing the use of recycable
materials, incl. investing to adapt the existing equipment to the characteristics of new
products; introduction of turnover cycles for water use in production processes. The
results will be applied to the distribution requirement in order to achieve multiplier
effect and the effect of capitalization (capitalization).
The expected contribution of these activities results in improving the awareness about
the efficient use of resources in the supported SMEs, increasing symbiosis between
enterprises along the value chain, which gradually will improve the efficiency of the
production processes, reduce the cost of their production and increase their
competitiveness, and thus of the overall economy.
Main target groups: SMEs, organizations of SMEs, clusters, industrial zones, LAGs.
Type of beneficiaries: SMEs in the manufacturing industry.
Territorial scope: Measures and activities within this investment priority will be
implemented throughout the country.
Guiding principles for the selection of operationsU:
The following guiding principles should be observed in the selection of operations
within the investment priority:
Provision of funding will be made in accordance with the procedures laid down
in national legislation and the internal rules of the MA;
Coordination and synergy - coordination between ESIF programmes at national
level, the horizontal programmes and other instruments of the Union with the
aim to achieve maximum s synergy effect and avoid double funding;
Need-based funding – the selected operations are supposed to meet key
challenges to the business/economy identified in the Partnership Agreement,
OPIC 2014-2020 Strategy, the relevant strategic documents and documents in
implementation of specific ex-ante conditionality;
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 94 от 274
Promoting operations whereby the end result will contribute to improve resource
efficiency and/or mitigate or abate climate change56
;
Principle of sustainable development (art. 8 of Regulation 1303/2013) -
Managing Authority to ensure compliance with the principle of sustainable
development on the funding of operations under OP;
Effectiveness and efficiency of the investments - selected operations should
comply fully with the goals of the OP at the adequate ratio between the
estimated costs and benefits. In the selection of projects will ensure that
investments are directed towards the most sustainable options with the most
efficient use of resources;
Relevance - selected operations should contribute to the implementation of the
output and result indicators and outcome of the programme;
Sustainability of the investments – ensure sustainability of the achieved results
after project completion;
Principle of partnership and transparency - the criteria for selecting the
operations are subject to approval by the Monitoring Committee of the
Operational Programme;
Principle of equal opportunities - promoting equal opportunities for all,
including accessibility for people with disabilities by mainstreaming the
principle of non-discrimination;
Specific thematic focus - in the selection of operations with the key importance
will be the ―Energy Strategy of R. Bulgaria‖ till 2020 and NSPSMEs- Priority
axis ‖Environment‖.
56 According to Guidelines for mainstreaming EP and CCP in the funds for Cohesion Policy, the Common Agricultural Policy and
the Common Fisheries Policy for the 2014-2020
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 95 от 274
Table 2-20: Common and programme specific output indicators for the ERDF
ID Indicator Measurement unit Fund Category of
Region
(where
applicable)
Target
value
(2023)
Data source Frequency of
reporting
1 Implemented pilot
and demonstration
innitiatives
Number ERDF Less
developed
regions
24 UMIS 2020
Annually
2 Number of
enterprises
receiving grants
Enterprises ERDF Less
developed
regions
49 UMIS 2020
Annually
3 Supported projects
related to industrial
waste management
% of the supported
projects under IP
3.2
ERDF Less
developed
regions
18 %
UMIS 2020
Annually
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Стр. 96 от 274
UPlanned financial support
Type of beneficiary Type of support:
SMEs Grants
When providing any kind of support, the European state aid rules will be complied with
and checks for the absence of double-funding will be carried out.
Cross-financing: Up to 10% of costs under this priority axis can be funded under
eligibility rules applicable for the European Social Fund, provided that such costs are
necessary for the proper performance of the operation and are directly linked to it.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 97 of 274
2.3.3. Performance framework for the implementation of the priority axis
Table 2-21: Performance framework for the implementation of priority axis 3
Priority
Axis
Type of
Indicator Name of Indicator
Measure
ment
unit,
where
appropri
ate
Fund
Categ
ory of
region
Interim value
(2018)
Target value
(2023)54F57
Source of data
Explanation
of relevance
of indicator,
where
appropriate
M W Tot
al
PA 3 Financial Certified expenditure mln.
Euro
ERDF Less
develo
ped
68,416,590 310,686,632 UMIS 2020
Applicable
for the whole
axis
PA 3 Output Number of enterprises receiving
grants (IP 3.1)
Enterpris
es
ERDF Less
develo
ped
185 528 UMIS 2020
Applicable
for the whole
axis
Additional information on the implementation framework:
Interim values of the financial indicators and the output indicators are set, based on the experience and lessons learned gained during the
programming period 2007-2013
57 Target values must be represented in total (M + W) or broken down by gender.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
98
Categories of intervention
(Reference: point (b)(vi) of Article 96(2) of Regulation (EU) No 1303/2013)
Categories of intervention corresponding to the content of the priority axis based on a
nomenclature adopted by the Commission, and indicative breakdown of Union support.
Tables 2-22, 2-23, 2-24, 2-25: Categories of intervention58
(by Fund and category of region, if the priority axis covers more than one)
Tables 2-22: Dimension 1 – Intervention field
Fund ERDF
Category of region Less developed
Priority axis Code Amount (EUR)
3 003 Productive investment in
large enterprises linked to the
low-carbon economy
44,200,000
3 068 Energy efficiency and
demonstration projects in
SMEs and supporting
measures
183,647,006
3 069 Support to
environmentally-friendly
production processes and
resource efficiency in SMEs
31,136,631
3 096 Institutional capacity of
public administrations and
public services related to
implementation of the ERDF
or actions supporting ESF
institutional capacity
initiatives
5,100,000
Table 2-23: Dimension 2 – Form of finance
Fund ERDF
Category of region Less developed
Priority axis Code Amount (EUR)
3 01 Non-repayable grant 230,083,637
3 05 Support through financial
instruments: guarantee or
equivalent
34,000,000
58
Amounts include total Union support (the main allocation and the allocation from the
performance reserve).
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
99
Table 2-24: Dimension 3 – Territory type
Fund ERDF
Category of region Less developed
Priority axis Code Amount (EUR)
3 07 Not applicable 264,083,637
Table 2-25: Dimension 4 – Territorial delivery mechanisms
Fund ERDF
Category of region Less developed
Priority axis Code Amount (EUR)
3 07 Not applicable 264,083,637
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
100
Justification of Priority Axis 4
Bulgaria supports the efforts of the European Commission to develop a common energy
policy of the European Union, taking into account global challenges and national
specificities. The main priorities of the Bulgarian energy policy are aimed at ensuring
energy security, diversification of sources and routes, energy efficiency, liberalized
energy market and protection of consumers‘ rights.
2.4.1. Investment priority 4.1: Improving energy efficiency and security of supply
through the development of smart energy transmission systems
Modernization and expansion of energy infrastructure is a prerequisite for enhancing
energy security and optimization of the energy mix in the transition to a low carbon
economy. An important point in this regard is the inclusion of 11 projects (out of 248)
with the participation of Bulgaria, out of which 4 in the field of electricity and 7 in the
field of natural gas, in the first list of Projects of Common Interest (PCIs) of the EU.
Some of the projects are of special importance for the security of the energy supplies
not only for Bulgaria but also for the region and the EU. The most important of them are
the projects for interconnections with the neighbouring gas systems (Greece, Turkey,
Serbia and Romania) and South Stream.
Specific objective 4.1.: Better interconnectivity with neighbouring gas transmission systems
Expected results
To meet the EU N-1 infrastructure standard Bulgaria will have to develop
interconnections with the neighbouring countries. The gas interconnector with Serbia
will contribute to increasing the value of the standard (in %) and reaching the required
100%.
In the event of disruption of the single largest gas infrastructure, the capacity of the
remaining infrastructure should be able to supply the required volume of gas to satisfy
total gas demand in the calculated area for a day of exceptionally high gas demand
occurring with a statistical probability of once in 20 years, i.e. N-1>100%.
The interconnector with Serbia, when constructed and put into operation, will contribute
to increase of the infrastructure standard by 23% in 2017, respectively by 20% in 2022
(presumably the same per cent in 2023) as it will have the capacity to transport 4.9
million cubic meters of gas per day in the direction form Serbia to Bulgaria, which
represents respectively 23% and 20% of projected total gas demand in the country for a
day of exceptionally high gas demand (21.7 million cubic meters per day in 2017 and
24.9 million cubic meters per day in 2022).
Table 2- 26: Programme-specific result indicators for ERDF
N
o Indicator
Measurem
ent unit
Category of
region
Baseline
value
Baselin
e year
Target
value
(2023)
Source
of data
Frequenc
y of
reporting
2.4. Priority Axis 4 – Removing bottlenecks in security of gas supplies
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
101
1 N – 1 standard
for
infrastructure59
% Bulgaria 40,6% 2014 >100%
Contributi
on of IBS
20%
Prevent
ive
Action
Plan
Every
two years
Action to be supported under the investment priority:
Construction of the section on Bulgarian territory of the gas interconnector between
Bulgaria and Serbia - Phase 2 of "Construction of Gas Interconnection Bulgaria-Serbia"
project. Preparatory activities under the project, all research and design are included in
the current OP ―Development of the Competitiveness of the Bulgarian Economy 2007-
2013‖, as Phase 1. All other activities related to land acquisition procedures,
construction, supervision and audit with the aim to implement the project will be co-
funded under the OPIC 2014-2020.
The expected contribution of this action is reliability and flexibility of gas supplies
supporting the main priorities of the Energy Strategy of Republic of Bulgaria till 2020
and meeting the EU N-1 infrastructure standard.
The target group are the natural gas consumers, incl. enterprises throughout the
country.
Types of Beneficiaries: Ministry of Energy
Specific targeted territories: the territory of the whole country.
Guiding principles for the selection of operations:
In the selection of operations within the investment priority, the following leading
principles should be followed:
Provision of funding will be made in accordance with the procedures laid down
in national legislation and the internal rules of the MA;
Coordination and synergy - coordination between ESIF programmes at national
level, the horizontal programmes and other instruments of the Union with the
aim to achieve maximum s synergy effect and avoid double funding;
Need-based funding – the selected operations are supposed to meet key
challenges to the business/economy identified in the Partnership Agreement,
OPIC 2014-2020 Strategy, the relevant strategic documents and documents in
implementation of specific ex-ante conditionality;
Principle of sustainable development (art. 8 of Regulation 1303/2013) -
Managing Authority to ensure compliance with the principle of sustainable
development on the funding of operations under OP;
59
The N – 1 formula describes the ability of the technical capacity of the gas infrastructure to satisfy total
gas demand in the calculated area in the event of disruption of the single largest gas infrastructure during
a day of exceptionally high gas demand occurring with a statistical probability of once in 20 years -
Regulation (EU) 994/2010.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
102
Effectiveness and efficiency of the investments - selected operations should
comply fully with the goals of the OP at the adequate ratio between the
estimated costs and benefits. In the selection of projects will ensure that
investments are directed towards the most sustainable options with the most
efficient use of resources;
Relevance - selected operations should contribute to the implementation of the
output and result indicators and outcome of the programme;
Sustainability of the investments – ensure sustainability of the achieved results
after project completion;
Principle of partnership and transparency - the criteria for selecting the
operations are subject to approval by the Monitoring Committee of the
Operational Programme;
Specific thematic focus - in the selection of operations with key importance will
be projects of energy's common interest.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
103
Table 2- 27 Common and programme specific output indicators for the ERDF
ID Indicator Unit Fund Category of Region
(where relevant)
Target value (2023) Source of data Frequency of reporting
М F Total
1 Gas Interconnection Bulgaria-
Serbia built
km ERDF Less developed
regions
61.1 UMIS 2020
Twice in the course of
implementation
UPlanned financial support
Type of beneficiary Type of support:
МЕ Grant
When providing any kind of support, the European state aid rules will be complied with and checks for the absence of double-funding will be
carried out.
Planned financial instruments
No financial instruments are planned.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
104
2.4.2. Performance framework for the implementation of the priority axis
Table 2-28: Performance framework of the PA 4
ID Indicator Name of Indicator Measurement
unit
Fund Category of
region
Milestone for
(2018)
Final target (2023)51F Source of data Explanation of
relevance of
indicator, where
appropriate М F Total
PA 4 Financial Certified
expenditure
EUR ERDF Less
developed
22,500,000 45,000,000 UMIS 2020
Applicable for
the whole axis
PA 4 Output Gas Interconnection
Bulgaria-Serbia
built
km ERDF Less
developed
regions
41 61.1 UMIS 2020
Applicable for
the whole axis
Additional information on the performance framework:
Interim values of the financial indicator and the output indicator are set taking into consideration the implementation of the project on the territory of
Serbia, as start of construction on Serbian territory is a precondition for start of construction on Bulgarian territory.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
105
Categories of intervention (by priority axis)
(Reference: points (c)(v) of the first subparagraph of Article 96(2) of Regulation (EU)
No 1303/2013)
Corresponding categories of intervention based on a nomenclature adopted by the
Commission, and an indicative breakdown of Union support
Tables 2- 29, 2-30, 2- 31, 2- 32: Categories of intervention60
Table 2-29: Dimension 1 – Intervention field
Fund ERDF
Category of region Less developed
Priority Axis Code Amount (EUR)
4 008 Natural gas (TEN-E) 38,250,000
Table 2-30: Dimension 2 – Form of finance
Fund ERDF
Category of region Less developed
Priority Axis Code Amount (EUR)
4 01 Non-repayable grant 38,250,000
Table 2-31: Dimension 3 – Territory type
Fund ERDF
Category of region Less developed
Priority Axis Code Amount (EUR)
3 07 Not applicable 38,250,000
Table 2-32: Dimension 4 – Territorial delivery mechanisms
Fund ERDF
Category of region Less developed
Priority Axis Code Amount (EUR)
3 07 Not applicable 38,250,000
60
Amounts include total Union support (the main allocation and the allocation from the
performance reserve)
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
106
During 2007-2013 programming period Priority Axis 5 Technical Assistance of the
Operational Programme ―Development of the Competitiveness of the Bulgarian
Economy 2007-2013‖ supported the management, implementation, monitoring and
control of the programme activities, as well as the work of the Monitoring Committee,
including by carrying out studies and surveys for the needs of the evaluation of the OP
and promotional campaigns to ensure transparency and awareness. The Priority Axis
covered the following areas of intervention:
Area of intervention 5.1. Support for the management, implementation,
monitoring and evaluation of the OP;
Area of intervention 5.2. Other activities for the implementation of the OP.
During the programming period 2014-2020 the Priority Axis will provide even more
targeted support for the successful management of interventions under the OP and will
continue building on the capacity of the MA and the beneficiaries. The implementation
of this support will be streamlined through measures to achieve the following specific
objectives:
1. Support for effective and efficient implementation of actions related to the
programming, management, monitoring, evaluation and control of OPIC in accordance
with the current legislation and existing best practices;
2. Provision of adequate and timely information and raising the public awareness of
funding opportunities under OPIC and the criteria, rules and procedures for participation
in its implementation;
3. Strengthening the capacity of the beneficiaries of OPIC for participation in the
programme implementation and better use of its financial resources.
– SPECIFIC OBJECTIVE 5.1.: Support for effective and efficient
implementation of actions related to the programming, management,
monitoring, evaluation and control of OPIC in accordance with the current
legislation and existing best practices
A major challenge will be to maintain and further strengthen the capacity of the MA
given the need for parallel management, by 2015, of the OPDCBE 2007-2013 and the
follow-up responsibilities related to the programme closure on the one hand, and the
need for launching the implementation of the OPIC 2014-2020 as early as possible, on
the other. The activities related to the closure of the current programme are significant
and time-consuming and Bulgaria has no relevant experience dating before the 2007-
2013 period. This necessitates continued investment in the human resources of the
system. Some further strengthening of the qualification and motivation of MA staff will
be required, as well as seeking for sustainability and stability of the structures and the
developed capacity, including though measures for reducing the turnover of human
resources.
2.5. Priority Axis 5 – Technical Assistance
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
107
In the period 2007-2013 certain weaknesses in public procurement and state aids at
national level were identified, which will also have an effect on OPIC 2014-2020 and
will require technical assistance funds. The gaps identified in the capacity for
programme monitoring and evaluation in the current period in turn resulted in a delay of
the necessary re-programming actions. In the period 2014-2020 similar processes would
cause a loss of implementation reserves, i.e. an actual reduction of the planned funding
outside the n+3 rule. Another closely linked element is the completion of a reliable
framework for feeding statistical information under set indicators and ensuring the
integrity of the system of indicators, including clear sources of information and methods
of calculation, valuation etc. In the new period it will also be necessary to support
actions arising from the ex-ante conditionalities.
In order for technical assistance to be able to adequately meet the changing needs of the
MA and the Monitoring Committee in accordance with new challenges and
requirements, it has been foreseen to apply a more flexible approach to the planning of
actions over the previous programming period. The indicative types of actions include:
Actions to be supported and their expected contribution to the specific objectives:
Actions for management, completion and post evaluation of OPDCBE 2007-
2013 according to the requirement of art. 59 of the General regulation for ESIF;
Logistic and technical support of the functioning of the Monitoring Committee;
General and specialised training for MA staff, including development and
sustaining capacity in the field of state aid (workshops, seminars, exchange of
best practices and experience etc.) as well as trainings for staff from the common
MEE administration, supporting the functioning of the MA;
Financing basic and additional remuneration for MA staff (incl. wage costs,
health and social payments and all other related costs according to the Bulgarian
legislation);
Perfoming evaluations during the programming period, incl. preparation and
execution of plan for evaluation and post evaluation of the OP ;
Provision and implementation of technical support, consultancy, research,
analyses and studies for proper programming, management, monitoring,
evaluation and control of OPIC;
Support for the process of evaluation and selection of projects (organisation of
evaluating committees, database of independent experts having appropriate
technical expertise, contracting of experts etc.), independent evaluation of
projects;
Support for ongoing monitoring, financial control and audit, as well as risk
assessment, anti-fraud/irregularities/corruption measures;
Delivery/rent, repair, maintenance and insurance of movable and immovable
property used by the MA (incl. premises, furniture, equipment, cars, etc.);
Business trips of MA staff and other persons, participating in the management of
the OP;
Delivery, elaboration and maintenance of computerised information system
(hardware and software) for the needs of the MA;
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
108
Support for costs for activities of OP‘s completion (closure);
Support for preparation of the next programming period
Other activities related to the resource and technical support of the OP
implementation.
UExpected results
The implementation of the activities will ensure an effective, efficient and proper
management of the OP in accordance with the principle of sound financial management
and the regulations of the European and national legislation. Performance will be
ensured by the good structuring and organisation of the work of the programme MA and
its regional units (including risk assessment system) and the high qualifications,
motivation and commitment of staff on the one hand, and by the proper functioning of
the programme Monitoring Committee on the other.
SPECIFIC OBJECTIVE 5.2.: Supporting the Managing Authority for provision
of adequate and timely information and raising the public awareness of funding
opportunities under OPIC and the criteria, rules and procedures for participation
in its implementation
The so far conducted studies have shown that the potential beneficiaries need more
targeted and timely information about the practical aspects of using EU funds in
Bulgaria, more specifically about application procedures, funding opportunities, project
preparation and other similar issues concerning the programme specifics. Special
attention should be paid to the conclusions of the studies conducted under Priority Axis
5 of the OPDCBE in the period 2007-2013. According to a recent study55F
61, the
continuous communication efforts of the MA of OPDCBE in 2012 have led to
significant positive results: compared to all other operational programmes, the
OPDCBE has experienced the greatest growth in recognition among the general public
in the past year – 16%, i.e. information and awareness raising activities have covered a
further 340,000 people. Yet, the level of awareness of particular programme aspects
among the population, remains low. There is a clear profiling of informational needs,
based on which three main groups can be defined: with general interest in the
Programme, companies with project ideas, groups of companies (or consortia thereof) in
actual interaction with the Programme (including beneficiaries with completed
projects). The degree of programme commitment should be taken into account, as well
as the content of the selected information, in order to achieve a higher level of
communication efficiency.
There is an increase in the estimates of the institutions associated with the management
of the OP. Data suggest that there has been a significant positive change in the
interaction between the administration and beneficiaries. The most probable reason for
that could be the closure of the Intermediate Body, simplification of communication,
shortening response times and reduced document flows. Estimates are even higher
among beneficiaries with ongoing or completed projects. This indicates that much of the
negative attitude is a reflection of the overall mistrust of institutions rather than some
form of critic of the MEE and DG European Funds for Competitiveness in particular.
What is needed is additional communication directly related to management
61
The study was carried out by ESTAT OOD in 2013
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
109
mechanisms, so as to create an impression of transparency of operations and explain
that, in fact, both parties work towards the same common goal – to improve the
condition of the business in Bulgaria and hence the general standard of the population.
Despite the registered increase in the interest in the internet website of the OP among
the general public, the visitors share – 10.7% of the population (approx. 673,000 people,
compared to approx. 267,000 people by 2012) is rather low. This not only suggests a
need for greater integration of this channel of communication in information and
awareness raising processes, but also a need for joint action and involvement of actual
and potential beneficiaries.
The outlook for the next programming period is rather positive. The proportion of
companies having declared an intention to submit projects in the period 2014-2020 is
52%, accordingly 80% among ICT and other organisations, of those aware of the
OPDCBE 2007-2013. There is a growing confidence in Euro-funding opportunities
among businesses, as well as overcoming initial fears.
Regrding OPIC 2014-2020, the potential beneficiaries have specific requirements
concerning simplification of procedures, support to the business to secure the necessary
co-financing, and prospect for development in the form of focus on sectors of potential.
Fulfilling those requirements would result in increasing the number of candidates and
successfully completed projects.
Most likely to apply subject to fulfillment of the above conditions are companies that
are currently in interaction with the Programme in one way or another. As regards
communication, this means that in the next period one of the main target groups of the
OP should be organisations that have in some way been involved in the OPDCBI,
regardless of whether they have actually implemented a project or have just applied and
been turned down.
Actions to be supported and their expected contribution to the specific objectives:
Organisation of public and promotional events – promotional campaigns,
seminars, round tables, conferences, exhibitions, presentations, seminars to
promote public support and responsibility for the proposed investment;
Distribution of documentation, information and materials, related to the
implementation of OPIC;
Update and maintenance of an internet website as a key communication channel;
Participation in programmes, preparation and distribution of promotional films
and videos, commercials and other media events;
Publications, bulletins, brochures, banners, manuals etc.;
Analyses and opinion polls – focus groups, surveys, sociological studies etc.
UExpected results
The implementation of the activities will ensure transparency of OPIC implementation
and its promotion among the widest stakeholder range, physical persons and legal
entities alike. Opportunities will be created for raising public awareness of the ERDF
(as well as of funding from the state budget and other sources of funding, including
multifund investments IFIs, EU programmes such as Horizon 2020, COSME etc.) and
OPIC in the period 2014-2020, attracting public interest, stimulating project
participation, explaining the opportunities and benefits of participation in the
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
110
Programme and complementary financial resources, ensuring equality and transparency
in its implementation.
Efforts to promote the Competitiveness OP in the period 2007-2013 have significantly
improved the visibility of the OP among the general public. The national promotional
campaigns can be considered successful and of significant use to the participants.
Events, however, tended to attract mainly companies that have a specific intention to
participate, as well as certain project experience. Therefore the coverage of such events
should be expanded. At the same time, since greater awareness is more often than not
concomitant with greater criticism, special attention should be paid to the selection of
the content and the form of promotional events.
– SPECIFIC OBJECTIVE 5.3.: Strengthening the capacity of the beneficiaries
of OPIC for participation in the programme implementation and better
(quantitative and qualitative) use of its financial resources
According to an analysis of the OPDCBE of March 2014, a large part of beneficiaries
mention serious problems in the preparation and implementation of projects. At the
present moment, the end of the programming period, beneficiaries are still unable to
prepare and manage projects on their own and often resort to consulting services. On the
one hand, this indicates a need to further reduce the administrative burden of the OP
and, on the other, the substantial experience gained by the consulting sector in Bulgaria.
In this regard, another indicator of beneficiaries‘ capacity is the fact that only 13% of all
completed grant contracts have finished within the established timeframes. The data are
indicative enough to conclude that the beneficiaries still lack the capacity to plan and
implement projects within set periods.
In view of the current experience of the MA in planning and support provision to
develop the capacity of beneficiaries in the period 2007-2013, the following main
challenges can be identified:
1) Achieve a balance between the supply and demand, i.e. address the specific needs of
both current and potential beneficiaries. A key prerequisite for this will be the
preliminary preparation, study and systematisation of needs and most of all
expectations.
2) Identify, take into account and make targeted efforts to minimise ―typical‖ mistakes,
irregularities, faults and gaps admitted by beneficiaries both at the stage of the
preparation of the project and during the implementation and reporting. An important
guiding principle will be to approach ―typical‖ mistakes in a systematic manner, initiate
and maintain proper and regular external communication and internal coordination
within the MA to standardise the methods of operation, fully unify the approach in case
of precedents, and answer enquiries and requests for clarification in a straightforward
and understandable manner.
3) Consider the specific actual needs and capacities of the different groups of
beneficiaries (micro-enterprises, small and medium-sized enterprises, large enterprises,
institutional beneficiaries) and key partners (other MAs, public institutions, business
organisations etc.), and, where applicable, even take sectoral specifics into account.
Streamlining the OP and shifting the focus to performance will require a strictly
differentiated approach. There is a need to support actions to address the difficulties of
the different groups of OPIC beneficiaries in prioritising their needs, as well as during
the identification, justification, preparation and implementation of projects.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
111
Actions to be supported and their expected contribution to the specific objectives:
Organisation and implementation of trainings in support of the capacity of the
candidates and beneficiaries in order to facilitate the implementation of OPIC
incl identifying, adaptation and implementation of good practices from other EU
member-states, joint initiatives and models.;
Preparation and implementation of evaluations, analyses and action plans to
strengthen the administrative capacity of OPIC applicants /beneficiaries;
Analysis of the needs and expectations of different groups of applicants /
beneficiaries of OPIC in order to better focusing of the Programme on the
difficulties and challenges which they are facing.
UExpected results
Developing beneficiaries‘ capacity will contribute to making significant progress in
terms of resource absorption and, last but not least, attaining OPIC objectives.
Table 2-39: Programme-specific result indicators (by specific objective)
ID Indicator Measurement
unit
Baseline
value
Baseline
year
Target
value
(2023)*
Source
of data
Frequency of
reporting
TO1 Average time
for a project
approval
(between
submission of a
project‘s
application and
signing of a
contract
days 215 2007-2013 183 UMIS Every two
years
TO1 Average time
required to pay
the beneficiary
from the
submission date
of the
reimbursement
application;
Days 112 2007-2013 90 UMIS Every two years
TO2 Degree of
public
awareness of
OPIC, overall
and with regard
to the particular
procedures
% 41.662
2013 51 % Survey Four times for
period of
implementation
of OPIC
TO3 Terminated
contracts
% 16.81% 2007-2013 13% UMIS Every two years
62
According ot data firom the Evaluation report on implementation of the 2013 Communication Plan of
OPC, performed by ESTAT
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
112
ID Indicator Measurement
unit
Baseline
value
Baseline
year
Target
value
(2023)*
Source
of data
Frequency of
reporting
TO3 Level of
satisfaction of
OPIC
beneficiaries
with training
and technical
support
% 41.8 2013 75% Survey Four times for
period of
implementation
of OPIC
*Target values may be qualitative or quantitative
Table 2-40: Output indicators ERDF (by priority axis)
ID Indicator Measurement unit Target value
(2023)*
Source of data
1 MA staff, including in regional
offices, having received training
Number 250 Annual reports
2 Trained beneficiaries/applicants Number 1500 Annual reports
3 Analyses, studies and other
consultancy support
Number 50 Annual reports
4 Promotional campaigns and
public events held
Number 30 Annual reports
5 Monitoring Committee meetings
held
Number 18 Annual reports
6 Internal and external evaluations
performed
Number 6 Annual reports
7 Number of on the spot
verifications
Number 6 150 Annual reports
8 Number of employees (Full-time
equivalents, FTEs) whose salaries
are co-financed by technical
assistance.
Number 228 Annual reports
* Target values for output indicators under technical assistance are optional
Categories of intervention (by priority axis)
Reference: points (c)(v) of the first subparagraph of Article 96(2) of Regulation (EU)
No 1303/2013)
Corresponding categories of intervention based on a nomenclature adopted by the
Commission, and an indicative breakdown of Union support
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
113
Tables 2-41, 2-42, 2-43: Categories of intervention63
Table 2-41: Dimension 1 – Intervention field
Category of region: Less developed
Priority axis Code Amount (EUR)
5 121 Preparation,
implementation, monitoring
and inspection
30,109,426
5 122 Evaluation and studies 1,771,714
5 123 Information and
communication
3,542,348
Table 2-42: Dimension 2 – Form of finance
Category of region: Less developed
Priority axis Code Amount (EUR)
5 01 Non-repayable grant 35,423,468
Table 2-43: Dimension 3 – Territory type
Category of region: Less developed
Priority axis Code Amount (EUR)
5 07 Not applicable 35,423,468
63
Amounts include total Union support (the main allocation and the allocation from the
performance reserve).
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
114
3. FINANCIAL PLAN OPIC 2014-2020
Table 3-1. Financial plan of the Operational Programme giving the annual commitment of the European Regional Development Fund
(ERDF) in the Operational Programme (Euro) per category of regions *
Fund Category of
region
2014 2015 2016 2017 2018 2019 2020 Total
Main
allocation
Perfor
mance
reserve
Main
allocatio
n
Perfor
mance
reserve
Main
allocatio
n
Perfor
mance
reserve
Main
allocatio
n
Performa
nce
reserve
Main
allocatio
n
Performa
nce
reserve
Main
allocatio
n
Performa
nce
reserve
Main
allocatio
n
Performa
nce
reserve
Main
allocation
Performa
nce
reserve
ERDF Less
developed
regions
138 173 101 8 819 560 145 250 508 9 271 309 152 997 456 9 765 795 159 359 742 10 171 898 165 607 234 10 570 674 171 706 601 10 959 996 177 623 943 11 337 699 1 110 718 585 70 896 931
Total 138 173 101 8 819 560 145 250 508 9 271 309 152 997 456 9 765 795 159 359 742 10 171 898 165 607 234 10 570 674 171 706 601 10 959 996 177 623 943 11 337 699 1 110 718 585 70 896 931
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 115 of 274
Table 3-2 Financial plan of the Operational Programme, showing the amount of the total financial allocation of each fund in the
Operational Programme, national funding and co-financing by priority axis for the whole programming period (EUR)
Financing plan
Priorit
y axis
Fund Category
of region
Basis
for
calcula
tion of
Union
suppor
t
(Total
eligible
cost or
public
eligible
cost)
Union
suppor
t
National
counterpart
Indicative breakdown
of national counterpart
Total funding Co-
financi
ng rate
For
inform
ation
EIB
contrib
utions
Main allocation (total
funding less performance
reserve)
Performance reserve Perform
ance
reserve
amount
as
proporti
on of
total
Union
support
National
public
funding
Nation
al
private
fundin
g
Union
support
National
counterpart
Union support National counterpart
(a)
(c) (d)
(g)
(j)
PA 1 ERDF Less
developed
Public
costs 250,990,16
9 44,292,383 44,292,383 - 295,282,552 85.00% - 235,465,343 41,552,708 15,524,826 2,739,675 6.185%
PA 2 ERDF Less
developed
Public
costs 592,868,24
2 104,623,808 104,623,808 - 697,492,050 85.00% - 556,196,779 98,152,373 36,671,463 6,471,435 6.185%
PA 3 ERDF Less
developed
Public
costs 264,083,63
7 46,602,995 46,602,995 - 310,686,632 85.00% - 247,748,923 43,720,398 16,334,714 2,882,597 6.185%
PA 4 ERDF Less
developed
Public
costs 38,250,000 6,750,000 6,750,000 - 45,000,000 85.00% - 35,884,072 6,332,483 2,365,928 417,517 6.185%
PA 5 ERDF Less developed
Public costs 35,423,468 6,251,201 6,251,201 - 41,674,669 85.00% - 35,423,468 6,251,201 - -
Total ERDF Less developed
1,181,615,5
16 208,520,385 208,520,385
1,390,135,903 85.00%
1,110,718,585 196,009,162 70,896,931 12,511,224 6.000%
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 116 of 274
Table 3-3 Breakdown of the financial plan by priority axis, fund, category of region and thematic objective for the ERDF, the ESF and
the Cohesion Fund (Table 18b 19) (Art. 87 (d) (ii) of the General Regulation) (EUR)
Priority axis Fund Category of region Thematic objective Union support National counterpart Total funding
PA 1: Technological development
and innovation
ERDF Less developed TO 1 Strengthening research,
technological development and
innovations
250,990,169 44,292,383 295,282,552
PA 2: Entrepreneurship and
capacity for growth
ERDF Less developed TO 3 Enhancing the
competitiveness of SMEs 592,868,242 104,623,808 697,492,050
PA 3: Energy and resource
efficiency
ERDF Less developed TO 4 Supporting the shift towards a
low carbon economy in all sectors 232,947,006 41,108,295 274,055,301
ERDF Less developed TO 6 Preserving and protecting the
environment and promoting
resource efficiency
31,136,631 5,494,700 36,631,331
PA4: Removing bottlenecks in
security of gas supplies
ERDF Less developed TO 7. Promoting sustainable
transport and removing bottlenecks
in key network infrastructures
38,250,000 6,750,000 45,000,000
PA 5: Technical Assistance ERDF Less developed NA 35,423,468 6,251,201 41,674,669
TOTAL 1,181,615,516 208,520,387 1,390,135,903
Note: The guidelines for the integration of environmental policy and policy on climate change in the funds for Cohesion Policy, the Common
Agricultural Policy and the Common Fisheries Policy for the period 2014-2020 provide for each programme to be identified adequate number of
objectives oriented to fulfillment of the requirements for the integration of environmental policy and policy on climate change in five ESIF,
ensuring that they contain the necessary quantitative indicators, which measure the subsequent progress. According to the methodology by codes
for determining the amount of funds in support of the objectives related to climate change, OPIC calculated 15%.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 117 of 274
4. INTEGRATED APPROACH TO TERRITORIAL DEVELOPMENT
In coordination and compliance with the Partnership Agreement OPIC 2014-2020 will
contribute to the implementation of the integrated territorial development. Through their
use OPIC 2014-2020 will aim to achieve a competitive and sustainable economy in
territories in which, according to the PA, there is a need to address bottlenecks, as well
as development needs related to creating sustainable employment, increasing the
income of the local population, and using the local potential for growth.
The application of the integrated approach to territorial development will support
targeted development, i.e. development that is to a maximum degree consistent with the
specific local needs and possibilities for growth and sustainable investment of OPIC
resources, in accordance with the principles of complementarity, concentration,
effectiveness and efficiency of resources. This approach will provide a better access to
funding opportunities for local businesses and contribute to the promotion of
partnerships and the development of multi level governance.
In line with PA, for the period 2014-2020 Bulgaria will implement the following
instruments for integrated territorial development to address territorial challenges:
Community-Led Local Development (CLLD), including CLLD with multi-
funding approach;
Investment to promote sustainable urban development on the basis of integrated
plans for urban regeneration and development;
European territorial cooperation, including under the Danube Strategy.
The contribution of OPIC 2014-2020 to the implementation of the above listed
instruments will be consistent with the thematic objectives as well as the priorities,
objectives and performance indicators of the OPon one hand and the specific features of
the identified territories on the other for achieving successful smart, sustainable and
inclusive growth
UCommunity-led local development
In line with the PA, the designation of territories for targeted support through the CLLD
instrument is based on geographic characteristics and identified socio-economic
disbalances and include:
Territories at risk (demographic, economic, environmental risks) with
progressive decrease of population and unrealised economic potential;
Mountainous, border and rural territories;
Territories for conservation of landscape, natural and cultural values;
Black Sea and Danube coastal areas.
The CLLD will be implemented using the ―bottom-up‖ approach based on local
strategies for integrated development to be elaborated by 31 December at latest 2017.
OPIC 2014-2020 envisages support to the implementation of these strategies through:
Participation of representatives of the MA in the committee evaluating local
development strategies submitted by the Local Action Groups (LAG);
financing projects within the approved local development strategies that
are prepared in accordance with the specifics of the particular territory
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 118 of 274
and in line with the priorities and objectives of OPIC 2014-2020 and
have set priorities, objectives and measures for implementation in the
following areas:Promoting innovation development and
commercialization (Thematic Objective 1);
Enhancing the competitiveness of local economies and the opportunities
for local business start-ups, including through diversification and
alternative activities (Thematic objective 3);
The expected results from the support under the CLLD instrumentat local levelare:
Transfer of knowledge and technologies at local level through investments to
enhance SMEs‘ capacity for market development, labour productivity and
reduction of energy and resource intensity of production in these areas;
Promotion of innovation activity, development and introductionof innovations
inthese areas and stimulating private investments in research and innovation;
Improving access to funding for SMEs and promoting the creation of new
enterprises to provide opportunities for local employment and increased
incomes.
In line with the Partnership Agreement OPIC 2014-2020 will contribute up to 5% of its
budget to multi-funding under the CLLD instrument.
The full implementation of the CLLD instrument will be laid out in a dedicated
regulatory act, that is to be adopted within three months after the approval of the
Partnership Agreement. Projects within the local development strategies that OPIC
2014 - 2020 will finance shall be implemented according to the rules and procedures for
implementation of the OP.
USustainable urban development
OPIC 2014-2020 will seek opportunities to complement actions in the designated
economic impact zones, based on developed and approved Integrated plans for urban
regenerationand development (IPURD) in urban areas out of the scope of the definition
for rural areas.
UIntegrated territorial investment
Currently the application of the approach for integrated territorial investment under
Regulation 1303/2013 is not envisaged.
Nevertheless, in line with the PA territorial approach for targeted support of North-West
Region (Severozapaden raion) is envisaged. The approach will be based on the strategy
for targeted support of the NWR. The focus will be on using the local potential taking
into account the main challenges and problems in the region.
The investment priorities that will be supported by OPIC give opportunities for
interventions leading to decreasing the intensity of economic problems and combating
unfavourable demographic tendencies in the region. More specifically the interventions
will be within the scope of OPIC priorities focusing on development and increasing
SME competitiveness by stimulating innovation activity, creating opportunities for local
business start-ups, supporting energy and resource efficiency measures. Based on the
defined priorities in the strategy for targeted support of NWR, OPIC will support project
either by designing a separate grant procedure for the NWR region or by giving priority
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 119 of 274
to projects from this region in the more general grant procedures covering all the
regions.
UInterregional and transnational actions
In line with the PA, in the period 2014-2020 OPIC will cover the following priority
areas for territorial cooperation:
Promotion of entrepreneurship, overcoming structural problems and enhancing
competitiveness by entrepreneurship promotion – new technologies and business
models to stimulate innovation, networking between research and technological
centres in the business sector, cooperation in support of SMEs and human
capital;
Preservation of natural and cultural heritage, especially in connection with
―green‖ growth economy and sustainable tourism;
Development of joint plans, coordinated investment, operations and systems for
resource efficiency, promotion of adaptation to climate change and risk
prevention and management.
The interventions to be supported by OPIC 2014-2020 under the goals ―Investment for
growth and jobs‖ and ―European territorial cooperation‖ will be programmed and
implemented in a manner so as to ensure their synergy and complementarity.
UMacro-regional and sea-basin strategies
OPIC 2014-2020 will seek opportunities for complementary operations for the
implementation of the EU macro-regional strategy for development of the Danube
Region. The relevant priorities for cooperation between OPIC 2014-2020 and the
Danube strategy are:
Encouraging more sustainable energy (Priority Axis 2);
Developing the Knowledge Society (research, education and ICT) (Priority Axis
7);
Supporting the competitiveness of enterprises (Priority Axis 8).
Two of Bulgaria‘s NUTS II regions – Severoiztochen and Yugoiztochen – fall within
the territorial scope of the Black Sea Basin Joint Operational Programme. The
Programme will be synergistic with the EU Blue Growth Strategy and the Convention
on the Protection of the Black Sea from Pollution (Bucharest Convention).
Bulgaria, and in particular OPIC 2014-2020, attributes importance to the
implementation of the objectives of the Integrated Maritime Policy and EU‘s Blue
Growth Strategy. Being a Black Sea and a Danube country, Bulgaria has certain
potential to implement ―blue‖ policies and it is OPIC‘s strategy to support such policies
in areas of applicable investment priorities. Moreover, the MEE takes part in the
specially established coordination mechanism under the MTITC. A special joint inter-
departmental working group for integrated maritime policy has been set up to bring
together all players in the process of planning and implementation of blue policies.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 120 of 274
5. SPECIFIC NEEDS OF GEOGRAPHICAL AREAS MOST AFFECTED BY POVERTY OR
TARGET GROUPS AT HIGHEST RISK OF DISCRIMINATION OR SOCIAL
EXCLUSION
As an element of the integrated approach the Partnership Agreement envisages
addressing the specific needs of geographical areas most affected by poverty or at
highest risk of social exclusion.
OPIC 2014-2020 will contribute to addressing the identified problems indirectly
through:
Support for creation of new enterprises and development of existing ones to
provide sustainable jobs, including for economically inactive and long-term
unemployed persons;
Implementation of measures leading to increased income of the population and
improved quality of life;
Implementation of the equality principle in the selection of operations –
promoting equality for all, including accessibility for people with disabilities,
and observance of the principle of accessibility (prevention of any
discrimination on the basis of disability);
Support for implementation of integrated local development strategies under the
CLLD tool and the strategy of targeted support for Severozapaden Region.
6. SPECIFIC NEEDS OF GEOGRAPHICAL AREAS WHICH SUFFER FROM SEVERE
AND PERMANENT NATURAL OR DEMOGRAPHIC HANDICAPS
In line with the Partnership Agreement, targeted support will be provided for two types
of areas:
Areas which suffer from extremely negative demographic trends (depopulation
and ageing);
Areas which suffer from severe natural handicaps and difficult accessibility (in
particular mountainous areas).
OPIC contributions in such areas will be through support for measures and operations
arising from the integrated local development strategies under the CLLD tool and the
strategy of targeted support for Severozapaden Region.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 121 of 274
7. AUTHORITIES AND BODIES RESPONSIBLE FOR MANAGEMENT, CONTROL AND
AUDIT AND THE ROLE OF THE RELEVANT PARTNERS
7.1. The authorities and bodies responsible for management, control and audit.
Table 7-1: Identification and contact details of the relevant competent
authorities/bodies
Authority/body Name of authority/body and
department or unit
Head of authority/body
(position or post)
Managing Authority Directorate-General European
Funds for Competitiveness (DG
EFC), ME
Minister of Economy
Certifying Authority
(if applicable)
National Fund Directorate,
Ministry of Finance
Director of National Fund
Directorate, MF
Audit Authority Executive Agency Audit of EU
Funds (EA AEUF)
Executive Director of EA
AEUF
Body to whom
payments will be made
by the Commission
National Fund Directorate,
Ministry of Finance
Director of National Fund
Directorate, MF
In line with the principle of shared management, the Member State and the Commission
will be responsible for the management and control of the operational programmes. The
Member State will take the lead role in the process concerning the implementation and
control of operational programmes through management and control systems. To
enhance the effectiveness of the control on the selection and implementation of
operations and the functioning of management and control systems, the functions and
rules of procedure of the MA will be laid out in detail by the MA of the OP in
accordance with the regulations of the EC for the period 2014-2020.
The MA will have primary responsibility for the effective and efficient implementation
of OPIC and will thus perform a number of functions related to the preparation,
management and monitoring of the OPIC, financial management and control, selection
of operations and implementation of promotion and publicity measures for the OP in
line with the relevant requirements and regulations of the EC. In accordance with
Decision Nr. 328 dated 25th April 2012 of the Council of Ministers and the Rules of
Organisation of the Ministry of Economy and Energy, the functions of Managing
Authority of the Operational Programme ―Innovation and Competitiveness‖ in the
period 2014-2020 will be performed by Directorate-General European Funds for
Competitiveness (DG EFC) at the MEE.
The Monitoring Committee will monitor the implementation of the OP. The functions
and procedural rules of operation will be prepared by the MA of the OP in accordance
with the Common Provisions Regulation on CSF funds in the period 2014-2020. The
MA will also act as Secretariat.
The Certifying Authority will be responsible for preparing and submitting to the EC
certified statements of expenditure and claims for payment. The National Fund
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 122 of 274
Directorate at the Ministry of Finance will act as Certifying Authority for OPIC 2014-
2020.
The Audit Authority will be responsible for ensuring that audit is carried out to verify
the efficient functioning of the management and control system of the Operational
Programme. The Executive Agency Audit of EU Funds will act as Audit Authority for
OPIC 2014-2020.
7.2. Involvement of relevant partners
Actions taken to involve the relevant partners in the preparation of the operational
programme and the role of those partners in the implementation, monitoring and
evaluation of the programme
Preparation of the operational program
By Decision № 328/25.04.2012 of the Council of Ministers, the Ministry of Economy
and Energy is defined as the leading institution for the development of new operational
program in innovation and entrepreneurship.
According to Article 32 , Paragraph 1, Item 5 of the Rules of MEE, General Directorate
"European Funds for Competitiveness" (DG "EFC") is responsible for the preparation of
the operational program for the programming period 2014-2020, and the accompanying
documents . According to Art. 32, paragraph 1, item 6 the Directorate coordinates the
work of the Thematic Working Group (TWG) for the preparation of the operational
program and serve as the secretariat to it under existing regulations. Thus in the
development of Operational Programme for ―Innovation and Competitiveness‖ 2014-
2020 the past experience of the department in development, management and
implementation of Operational Programme ―Development of the Competitiveness of
Bulgarian Economy 2007-2013"is used, in its capacity of Managing Authority.
The main coordinating body at the national level, responsible for the development and
negotiation of the Partnership Agreement and the operational programs for the
programming period 2014-2020 is Central Coordination Unit (CCU) in the
administration of the Council of Ministers.
The new OP Competitiveness and Innovation (OPIC) has been developed based on
evolving documents (Bulgarian and European) and in accordance with the needs of
business and the results of preliminary consultations with all stakeholders, incl. EC
services. In this regard , the flexible approach is the only possible one, because OPIC
(as each OP) is closely related to other planning and programming documents and any
change in one of the parameters can lead to significant changes in other parameters or
parts of the program.
The main stages in the programming of OPIC, activities that are performed in parallel
and coordinated can be defined as follows:
Preparatory stage - development of strategic documents, identifying the stakeholders
(partners), collection and processing of raw data/information
The process of preparing strategic and programming documents for EU funds
management for the programming period 2014-2020 was launched in late 2011. In
January 2012 were approved procedures for their development (Decree №
5/18.01.2012). Decision № 328 / 25.04.2012 of the Council of Ministers has approved a
list of thematic objectives, operational programs and departments responsible for their
preparation.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 123 of 274
In accordance with the provisions of Article 5, paragraph 3 of the Decree №
5/18.01.2012 on identified key partners to participate in the programming process and
set up a working group to develop the Operational Programme for Competitiveness and
Innovation (OPIC). Besides representatives of line ministries and departments in the
working group are also the socio-economic partners, regional and local authorities, civil
society, and academia.
Identified are strategic documents and analyses that are necessary to prepare the new
OP, including applicable ex ante conditionalities (National Strategy for Promotion of
SMEs 2013-2020, Innovation strategy for smart specialization, analysis of the current
programming period, analytical data on the distribution of the Bulgarian economy in
regions and sectors, strategic documents in the field of tourism, strategic analysis for
attracting foreign direct investment, Energy strategy, etc.).
In July 2012, an Agreement was signed with the World Bank for the provision of
consultancy services for providing support for the improvement of the institutional and
legal framework to support the national innovation system of Bulgaria and improve
innovation projects funded by the European Union.
The World Bank assistance under the Agreement is essential for the programming
period 2014-2020. The main activity of the agreement was the development of
Innovative strategy for smart specialization as one of the essential prerequisites for
providing support from by ESIF 2014-2020. A report by the World Bank was prepared
and submitted for the Innovation strategies for smart specialization, on the base of
which in May 2013 the first draft of the Strategy was developed.
Under the Agreement, the World Bank actively cooperated in the development of the
innovative component of OPIC - A review on the support for innovation through OP
"Development of the Competitiveness of the Bulgarian Economy" 2007-2013 was
conducted and opportunities identified for improving performance in 2014-2020, mainly
through financial engineering mechanisms to provide easier access to finance in general,
and specifically to ensure implementation of key activities in the field of innovation in
combination with grants.
In parallel, under the Agreement separate meetings and consultations with businesses
were held, including focus groups in the sectors: ICT, pharmaceuticals, mechatronics
and electronics, food, protection and commercialization of intellectual property, and
creative industries. Concrete recommendations were received from the Association of
Business Clusters, ARI (Association of the recycling industry) and Bulgarian Recycling
Association (BRA), the Association of Industrial Capital in Bulgaria (BICA), Bulgarian
Chamber of Commerce and Industry (BCCI) and others.
In November 2012 the "Position of the Commission Services on the development of
Partnership Agreement and programmess in Bulgaria for the period 2014-2020" was
presented containing specific recommendations of the European Commission and key
priority areas that the Commission would like Bulgaria to focus EU funding for the next
programming period, which served as a base for developing the concept of OPIC 2014-
2020.
At the end of 2012 a qualitative study was conducted through in-depth interviews or
focus groups among beneficiaries and other stakeholders (business organizations,
research institutes, consultants, etc.) in respect to their experience with the current
operational program aimingto outline the main difficulties and to formulate concrete
proposals or guidelines for changes in the next programming period. During the period
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 124 of 274
March - May 2013 nationally representative survey was conducted using quantitative
methods to the general group of potential beneficiaries (non-applicants, participated and
rejected, completed / implementing projects under the OP).
With Decision of the Council of Ministers from 09.01.2013 the list of operational
programs was supplemented by OP "Science and Education for Smart Growth", which
triggered a broad and lengthy discussion on the differentiation and complementarities of
the measures in both programs relating to the innovation system in the country and in
particular the aim for synergy in the implementation of innovative activities of business
and academia, and supporting cooperation between the business and science to achieve
an overall positive impact on the Bulgarian economy.
In September 2013 a tender for an external consultant to support the programming
process was opened, including the analysis of the results of the operational program for
the period 2007-2013, the formulation of recommendations for the next programming
period 2014-2020 and support the development of the new OP.
Preparation of concept for OPIC 2014-2020, consultation with stakeholders, and
reaching agreement on key issues.
On 6th
February 2013, at a meeting with representatives of the European Commission
(EC) the scope and indicative priority areas for funding under OPIC were agreed upon.
On this basis, in the context of relevant strategic documents, conducted research and
analysis, the results of ongoing discussions to date within the coordination mechanism
for the development of strategic documents for the next programming period
(workshops to determine the mechanisms of differentiation and complementarities
between OP working group meetings for the Partnership Agreement, several informal
meetings at senior management level to achieve common understanding and agreement
on issues of national importance, the preliminary negotiations with the EC services
since November 2012 and February 2013) and the expertise of the World Bank in April
2013 the first version of the Concept of OPIC 2014-2020 was developed.
The first version of the Concept of OPIC 2014-2020 was presented for discussion at the
first meeting of the Thematic Working Group (TWG ) held on 04.26.2013. The
proposed scope, priority axis, indicative activities and tools for financingwere
discussed. The majority of opinions expressed disagreement with the general approach
of the concept of promoting the development of innovation infrastructure, clusters and
application of new models (tools) to support businesses with proven efficiency
worldwide but not in Bulgaria .
In order to deepen the dialogue and achieve a common understanding on the opinions
and suggestions of the business and its organizations, NGOs, regional and local
authorities and other stakeholders, as well as to better reflect the actual needs of
Bulgarian economy next workshops was initiated to be held in June 2013.
In meantime, the first version of the concept from April 2013 has been evaluated in non-
official paper of the Commission of 22 July 2013 (non paper) as insufficiently mature to
become the basis for Technical Talks. However, the first observation is that: there is
lack of solid justification for the selection of priorities and therefore the study of the
World Bank on the Strategy for smart specialization should be used to broaden the
possibilities for supporting SME‘s and start-ups through financial engineering in
combination with grants.
Based on the comments received and consultations held in June 2013, a second version
of the concept of OPIC 2014-2020 was developed, which was then presented for
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 125 of 274
discussion at the second meeting of the Thematic Working Group on 11.07.2013, where
reached a significant level of approval by the stakeholders.
After the meeting of the TWG additional bilateral meetings were conducted between
DG "EFC" the Ministry of Economy and Energy and the Ministry of Education, the
Association of Business Clusters(ABC) and MOEW. Meetings with the Ministry of
Education and MOEW aimed at determing the demarcation lines and complementary
between the programs, and the meeting with ABC aimed at discussing the position of
the ABC on the second version of the concept of OPIC and the indicative activities and
rules of the new operational program in particular the support for clusters.
As a result of the second meeting of the TWG additional comments from 13
organizations were received: MEE -"Innovations, investments and entrepreneurship"
Directorate, Council of Ministers - "Programming of EU Funds" Directorate, Ministry
of Finance, BCCI, BAS and academics, Association of district heating companies in
Bulgaria, NAMB, ABC, Branch Chamber of Wood processing and Furniture Industry,
Bulgarian Association of Producers of aggregates, members of the business and
consulting organizations, MTITC .
The main challenge in the development of the program is to reach consensus among all
stakeholders and balance on the measures which will have quick and immediate impact
on the business (technological upgrading – support for the modernization will be
provided mainly through improved access to finance based on JEREMIE experience,
the introduction of international standards and certification, internationalization, etc.),
and those that require a longer period to achieve certain results and larger investments
(infrastructure for innovation and research; development and commercialization of
innovations, etc.). The key innovation activities will be supported adequately on the
basis of lessons learned from previous schemes for incubators and offices for
technology transfer.
The third TWG meeting was held on 24 April 2014 and the expressed (in dialogue or
written) opinions of stakeholders were taken into account – the comments of NSI,
Bulgarian Academy of Science (BAS), Ministry of Finance (MF), MOEW, MRD, line
departments in the Ministry of Economy and Energy (MEE), MTITC, State Agency for
Metrological and Technical Surveillance , organizations of people with disabilities, the
Association of banks in Bulgaria, CEIBG, BICA, Bulgarian Chamber of Commerce and
Industry (BCCI), Council of Ministers Administration and others. OPIC is published for
public consultations on http://www.strategy.bg.
Developing a comprehensive draft version of OPIC 2014-2020
Based on the broadly accepted by socio-economic partners second version of the
concept of OPIC 2014-2020, the comments received and the results of the meetings and
discussions, the MA elaborated the draft version of the Operational Programme
covering the details with regard to program strategy, priority setting to achieve it in
accordance with the thematic objectives and investment priorities under the draft ERDF
Regulation, indicative support activities, the expected results and indicators to measure
them.
In August 2013 a letter was received from the European Commission on the indicative
allocation of ESI Funds for Bulgaria for the period 2014-2020 on the basis of which at
national level the indicative allocation of financial resources among operational
programs and thematic objectives was finalized. Thus the invisaged priority areas for
support in the overall design of the operational program received their financial terms.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 126 of 274
In October 2013 MA sent a draft OPIC 2014-2020 to the European Commission within
the informal dialogue and technical advice in order to achieve timely consensus on the
scope and planned investments and results of the program. Constructive comments and
remarks were received by the Commission, used in the partnership process to improve
the focus and quality of the operational program.
In December 2013 with the Council of Ministers decision are defined Managing
Authorities (MA) of all operational programs for 2014-2020. OPIC Managing Authority
is the Ministry of Economy and Energy and Directorate General ―European Funds for
Competitiveness". In March 2014 the Council of Ministers approved the Partnership
Agreement 2014-2020 as a base to launch formal negotiations with the European
Commission.
Two rounds of informal consultations with the EC services were held, on which were
discussed and addressed potential "white spots" and problematic areas ("bottlenecks"),
which may arise in the implementation process of the Programme. Also, the Ministry of
Environment and Waters has issued a statement on the environmental assessment,
which is consistent OPIC.
On the 21st of May, 2014 the draft version Operational Programme "Innovation and
Competitiveness" 2014-2020 was approved at a meeting of the Council of Ministers.
The program was sent via the SFC system starting formal negotiations with the EC
services on 31st of May 2014. The EC official comments were received on 07.08.2014.
Additional technical meetings with EC services representatives were held to discuss the
open issues related to ensuring synergy and complementarity of interventions under
TO1 between OPIC and OPSESG and fulfilment of ex ante conditionalites 1.1. and 1.2;
planned use of financial instruments under TO1, TO3 and TO4 in accordance with the
results of the ex ante assessment of applicability of financial instruments under OPIC
and proposed investment strategy; decision on financing of 2-nd phase of the project for
gas interconnector ―Bulgaria – Serbia‖ and including new theamitc objective 7 and new
ex ante conditionality 7.4 in OPIC respectively; development of detailed methodlogy
and criteria for selection of indicators of OPIC. The revised version of OPIC was
resubmitted officialy on 17.11.2014. Upcoming is finalization of the negotiation process
for adoption of OPIC and starting the implementation of programmes‘ objectives and
priorities.
Involvement of partners in the preparation of the Operational Program
In accordance with Article 5 of the draft General Regulation, Operational Programme
―Innovation and Competitiveness " 2014-2020 was developed with the Principle of
Partnership. The members list of the thematic working group for its preparation is
formed in accordance with the provisions of Article 5, paragraph 3 of the Decree №
5/18.01.2012. The participating Bodies and organizations listed in Article 5 (3) ensure
coverage of the views of all stakeholders on the development of OPIC 2014-2020, as
well as use of the expertise of the members for the best possible development of the
document. The members of the thematic working groups, responsibilities and tasks are
defined by Order RD-16-1396/19.10.2013 of the Minister of Economy, Energy and
Tourism (see attached list of partners as an annex to this document).
To ensure the widest possible active participation of stakeholders, civil society
organizations are represented by the most reputable and active business organizations in
the country. A place in the group found representatives of nationally represented
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 127 of 274
organizations for people with disabilities, organizations from the thematic groups
"Social Organizations", "Environmental organizations" and ―Development Policy".
Participation of NGOs in the TWG‘s election was conducted according to the
Mechanism for selection of NGOs approved by the Minister on the Management of EU
funds. There was an election of representatives of the academics, in accordance with the
Mechanism and the support of the Ministry of Education and Science.
TWG partners are included in overall preparation, review and approval of the drafts and
final version of the OPIC, as all their rights and obligations as members of the group are
defined in the rules of operation of the TWG adopted by a vote on its first meeting.
To facilitate the involvement of partners from across the country, the venue for the
TWG meetings are selected at best accessible communication facilities, incl.
accessibility for people with disabilities. All decisions of the TWG are being taken by
consensus when possible. In case of disagreement, additional meetings are held. There
is also an availability to create sub-groups for the development of parts of the draft OP /
to discuss specific questions and solve problems related to the functions and tasks of the
working group or the draft operational program). In order to correctly reflect all the
views and comments received, the Secretariat shall prepare minutes of each meeting and
ordination chart, on which are recorded the reflected opinions and given reasons for the
rejection of items.
With a view to enabling the introduction to the draft OPIC and reflecting the views of
the broaden possible group of stakeholders, the website of the 2007-2013 OPDCBE
(Uhttp://www.opcompetitiveness.bg ) were created sections named " New Programming
period 2014-2020‖ and ―Suggestions, opinions and recommendations‖. Under section
―New programming period 2014-2020 " are published minutes of the meetings of the
TWG and the section " Suggestions , opinions , recommendations " allows businesses to
send their suggestions, comments and recommendations for the new programming
period 2014-2020. All submitted proposals, opinions and recommendations are
reviewed by the Managing Authority of OP ―Competitiveness" and received a response.
To promote the project of OPIC 2014-2020, and receive feedback from an even broader
range of individuals and organizations, MA experts participated in a number of
information events to present the project programme.
After the final development of the program and its approval by the EC, cooperation with
the partners will continue in future on the Monitoring Committee, in which majority of
the organizations from the TWG will be represented.
Organization of the ex-ante evaluation and environmental assessment processes
The OPIC was also informed and developed in response to the Ex-ante Evaluation and
the Strategic Environmental Assessment (SEA) and consultation responses to this in
June 2014.
The ex-ante evaluation and environmental assessment have been performed by external
consultants selected through public procurement procedures. During the development of
the programme the MA engaged extensively with both consultants. Discussions and
meetings were held throughout the process as the programme was further improved.
Their comments and proposals were also used to develop the final programme
document.
The consultation documents on the SEA Report were sent to all interested parties
represented in the Thematic working group for the development of OPIC (incl.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 128 of 274
participating NGOs), as well as to those defined in the Ordinance on the Conditions and
Procedures for Environmental Assessment of Plans and Programmes (Ministry of
Environment and Water, Ministry of Health, the Regional Inspectorates of the
Environment and Water and the Basin Water Management Directorates). The
documents were also made available online on the MA‘s official website. Response on
the documents was not obligatory.
8. COORDINATION BETWEEN THE FUNDS, EAFRD, EMFF AND OTHER UNION
AND NATIONAL FUNDING INSTRUMENTS, AND EIB
Demarcation and complementarity between the Operational Programme ―Innovation
and Competitiveness‖ (OPIC) and the other Operational Programmes at national level.
One of the challenges to the effective and efficient absorption of the ESI Funds is
achieving a synergistic effect of the various actions under the different operational
programmes at national level. At the same time, it is necessary to draw a clear
demarcation line between operational programmes to avoid overlapping measures and
double funding. The overall mechanism and the bodies to ensure the coordination
between the ESI Funds and the other national and European financing tools are
described in a separate section in Bulgaria‘s Partnership Agreement. At OPIC level the
following areas of demarcation and complementarity with the other operational
programmes in Bulgaria have been identified:
OPIC and Operational Programme “Science, Education and Smart Growth”
(OPSESG)
OPIC and OPSESG are aimed at achieving smart growth of the Bulgarian economy.
Each of them through mutually complementing interventions contribute to the
development of R&D activities, technological development and innovation, which is
defined as Thematic objective 1 of the Common Strategic Framework of ESIF.
The support under OPSESG is aimed at the creation of the necessary infrastructural and
human resources for conduction of applied research in the thematic areas of RIS3. In the
newly created research and innovation infrastructure (centers of excellence and centers
of competence) as well as in the modernized one (research institutes and schools of
higher education) applied research will be conducted, leading to creation and
dissemination of publicly accessible knowledge in RIS3 thematic areas, which, by its
side will serve as an insentive and scientific base for business innovation activity. At the
same time, through financing of applied research, specialization of researchers and
training of PhD and post-PhD students will be accomplished with the aim to build up
and develop the necessary scientific and research capacity in those areas. In addition,
the regional needs for specialization in the RIS3 temathic areas will be addressed by
regional alignment of the centers of competence and by support for infrastructure
modernization in research institutes and schools of higher education whose activity is of
a greater interest for the local business.
OPIC by its side will intervene in support for conduction of applied research and
innovation aimed at creation or improvement of particular products and services in the
enterprises, and their commercialization, while benefiting from the built up capacity and
applied research results within the centers of excellence and centers of competence,
schools of higher education and research organisations
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 129 of 274
In support of the innovation activity of the enterprises funding will be provided for
construction, equipment and accreditation of thematically focused laboratories and other
similar infrastructure, necessary for the needs of enterprises for certification,
standartized testing, technical verification, proof of concept, test models and utility
models, prototyping and other similar activities, which are not related to creation of new
knowledge, but are aimed at development and introduction of innovations, including
support for TTOs with constructed basic infrastructure (out of the centers of excellence
and centers of competence).
Thus OPSESG will support activities laying a stable base, in terms of capacity and
applied research, for development of innovative activity of Bulgarian enterprise, as the
quality of research and innovation infrastructure, the creation of a new generation of
researchers and, consequently, the advanced level of education and R&D activity, form
the basis of the innovation capacity of each country. On the other hand, OPIC will focus
on encouraging business to use the results of the created conditions for conducting
innovation activity and transforming those results into marketable products and
processes, which create economic growth.
Special attention will be focused on the achievement of synergy effect of the support for
Sofia Tech Park (STP) by the two OPs. Under OPSESG funding will be provided for
applied research by researchers teams in the framework of the consortium to the
laboratory complex in STP. This includes funding of applied research projects, incl.
expenditure for consumables, hiring and training of researchers, equipment
maintenance, knowledge dissemination and other similar expenditure. OPIC will
intervene in investment expenditure for infrastructure, which has not been financed by
OP Competitiveness 2007-2014 .
At the start of the implementation of the programmes an interinstitutional working
group for the coordination of the demarcations and complementarity issues between the
two programmes in all phases of the project cycle (selection of operations,
programming, monitoring and evaluation of the implementation) will be created. The
discussion and approval of the selection criteria and the specific parameters of the
proposed schemes will be also carried out within the MC of the operational programmes
where the managing authorities are represented with a status of full members.
The implementation of both OPs and the expected complementing effect ought to have
a major contribution to the achievement of the determined national objective for R&D
investment of 1,5% of GDP by 2020.
OPIC and Operational Programme “Regions in Growth” (OPRG)
The strategy of OPRG focuses on improving the quality of life with a view to
overcoming negative demographic trends and using city potential to achieve a balanced
development across the entire national territory. Emphasis will be laid on sustainable
and integrated urban development (Priority 1) by adopting an approach of concentration
of resources by focusing investment in certain cities (identified eligible cities as per
National Concept for Spatial Development for the period 2013-2015), and in particular
within the impact zones of relevant Integrated Plan for Urban Regeneration and
Development (IPURD). The latter will aim to achieve a synergistic effect of the
coordinated implementation of different local sectoral policies and investment at
regional level so that the overall solution would exceed the value added if such policies
and investment were to be implemented separately.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 130 of 274
Coordination between the two operational programmes will be sought within areas of
potential for economic development as per the Integrated Plans for Urban Regeneration
and Development. OPRG will support modernisation and reconstruction of existing or
construction of new technical infrastructure relating to promotion of business and
entrepreneurship, as well as construction, rehabilitation and reconstruction of
commercial and industrial zones, including buildings in areas of potential for economic
development as per IPURD. Extra priority under OPIC can be given to eligible
enterprises developing economic activities or having an intention to invest in an eligible
area of potential for economic development as per IPURD outside the scope of the
definition of ―rural areas‖.
Nearly 1/3 of the OPRG resources will be allocated to Thematic Objective 4.
Supporting the shift towards a low-carbon economy in all sectors, with almost 20%
designated to the implementation of measures for energy efficiency in administrative
and residential buildings and 9% to investing in the development of integrated urban
transport. At the same time, OPIC envisages measures to improve energy efficiency in
enterprises (production processes, heating/cooling, energy performance of buildings). In
this way, the two operational programmes will cover two separate, but also
complementary areas of intervention. The high energy intensity of the Bulgarian
economy compared to the average EU level and the main identified related problems
necessitate implementation of measures to increase energy efficiency along the
production-transfer-energy consumption chain. There is a need to improve the
efficiency of energy consumption in all sectors of the national economy in order to
reach the ambitious national target to increase energy efficiency by 25% by 2020.
By way of complementing the Priority Axis 5 ―Regional Tourism‖ under OPRG, aimed
at preserving and developing cultural heritage of national and world significance, OPIC
envisages support in favour of SMEs through institutional support for the establishment
and operation of management organizations in tourist areas.
In addition to the thematic objectives that will be the focus of the respective operational
programme, the main demarcation between OPIC and OPRG can be sought in terms of
the potential beneficiaries of the two programmes: OPIC will support micro-, small,
medium-sized and large enterprises and agencies and other organisations and
institutions associated with the provision of services for the business and for
improvement of the business environment, while OPRG will support - municipalities
in accordance with IPURD, the Housing Policy Directorate at the MRD, and financial
institutions in connection with the implementation of financial tools for the needs of the
OPIC.
OPIC and Operational Programme “Environment” (OP Environment)
OPIC and OP Environment will simultaneously address one of the aspects of the main
goal of Europe 2020 – smart, sustainable and inclusive growth, namely sustainability.
Both programmes envisage actions in support of the implementation of Thematic
Objective 6. Protecting the environment and promoting resource efficiency of the CSF
of the ESI Funds. OP Environment foresees measures for protection, restoration and
maintenance of biodiversity within the National Ecological Network including protected
areas and territories (PA ―Natura 2000 and Biodiversity‖); improvement of municipal
waste management systems and ensuring proper treatment, recovery and disposal of
municipal waste in observance of waste management hierarchies and with a focus on
meeting the objectives set by the national and Union legislation (PA ―Waste‖);
improvement of water management through the provision of wastewater treatment in
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 131 of 274
agglomerations in which wastewater sewage is discharged without proper treatment,
provision of clean and safe drinking water to the population, improvement of the water
monitoring system, and development of information systems and water management
models. The planned measures will be implemented by organisations of or units within
the MoEW, ExEA, municipalities, profit and non-profit legal entities, science institutes,
authorities/bodies/units responsible for the management of Natura 2000 sites in the
country and protected areas,etc.
At the same time, OPIC envisages implementation of eco-innovation in enterprises by
means of a horizontal approach. Support will be offered for implementation of high-tech
solutions for optimisation of production processes and reduced use of raw materials;
implementation of modern technologies for use of waste as raw material in new
production and/or other alternative uses; implementation of zero-waste technologies,
innovative production materials, green production technologies etc. in all sectors of the
economy. In this regard, OPIC will concentrate on introducing eco-innovation to foster
better uses of resources and energy and enhance enterprise productivity, while the focus
of OP Environment will be the protection of the environment. OP Environment does not
envisage actions to support the use of innovative solutions in the field of the
environment. Hence, no overlap/duplication of interventions between the two
programmes can be expected.
OPIC and Operational Programme “Human Resources Development” (OPHRD)
The strategy of OPHRD is based on three pillars – Achieving of higher rates of and
quality employment; Reducing poverty and promoting social inclusion; Modernisation
of public policies, as well as on the identified basic needs of the target groups of the
Programme. OPHRD addresses the social element of the main goal of Europe 2020 –
smart, sustainable and inclusive growth, namely fostering the economy through high
rates of employment leading to social and territorial cohesion.
The complementarity of the measures of the two operational programmes will help
ensure higher effectiveness for ESI funding. On the one hand, OPIC will support
entrepreneurship and enhancing the export and production potential of enterprises,
which is a prerequisite for creation of new jobs. On the other, OPHRD will implement
measures to promote easier adaptation for employed people, enterprises and
entrepreneurs to the changing needs of the economy and the labour market, including
through development of the knowledge and skills of the employed in accordance with
the qualifications and competences required by enterprises, introduction of new forms
of labour organisation and promotion of geographic and professional mobility.
The programmes will be complementary in terms of measures for promotion of
entrepreneurship. OPIC foresees to promote entrepreneurship mainly through financial
engineering instruments pursuant to Thematic Objective 3. The relevant OPHRD
actions in this regard will aim to improve access to employment through promotion of
entrepreneurship and starting own economic activity or self-employment under
Thematic Objective 8. OPIC will support eneterprises with more significant investment
needs while OPHRD will support newly established enterprises with minor investment
needs (up to 50 000 lv.).
With regard to the beneficiaries OPHRD will support measures for employment of
individuals that want to start their own business and don‘t have registered legal entity or
newly established enterprises registered by those individuals. OPIC will promote the
establishment of new enterprises mainly in the high- and medium-technology and
―knowledge based services‖ sectors as per NSPSMEs, development of new ideas, new
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 132 of 274
products/services and enterpreunireship in specific areas as cultural and creative
industries, enterprises developing new products or services related to an ageing
population, care and health, social entrepreneurship, and cooperatives of people with
disabilities.
Complementarity between the two programmes will be sought through possibilities for
coordinated implementation of schemes supporting the beginning of independent
activity, as well as social entrepreneurship. In these cases start-ups supported under
OPHRD, incl. social enterprises. will have access to schemes supporting their further
development under OPIC. Under OPHRD will be supported start-up social enterprises
by funding activities in the area of social marketing, the promotion of the social
economy and social entrepreneurship, social and professional integration of members of
vulnerable groups, equipment and adapting of jobs, improvement of the capacity and
human resources for effective management etc. Subsequently, OPIC support for social
enterprises that are legal entities will be carried out through the promotion of
entrepreneurial ideas in areas related to European and regional challenges, funded with
grants, as well as financial instruments for development, support to improve production
capacity and quality, use of ICT, consulting services etc.
OPIC and Operational Programme “Transport and Transport Infrastructure”
(OPTTI)
OPTTI is aimed at developing sustainable transport and transport systems. The
Programme envisages promotion of a multi-modal Single European Transport Area
through investment in Trans-European Transport Networks, development of
environmentally-friendly low-carbon transport systems, and promotion of sustainable
urban mobility, including river and sea transport, ports and multimodal connections
(under Thematic Objective 7). Ensuring good road infrastructure is one of the impact
factors of business development, however, there are no overlapping areas of investment
between the two programmes.
OPIC and Operational Programme “Good Governance” (OPGG)
OPIC envisages support to businesses in designated areas of intervention in accordance
with the programme priorities (innovation, entrepreneurship and competitive SMEs,
energy and resource efficiency). A key element will be the provision of direct support to
enterprises (vouchers, grants and financial instruments). The effectiveness of this
investment is directly dependent on the support that will be offered under OPGG
towards a more favourable overall business environment and competitiveness,
especially through good regulation and focus on quality and timeliness of public service
provision, including follow-up development of e-government.
Moreover, OPIC will allow for implementation of a limited number of quality projects
of national level institutions (agencies and other institutions) or projects in partnership
(e.g. with business organisations) of direct benefit to business development – awareness
raising, e-applications, international presence, investment or export operations etc.
Among others, eligible actions will include: targeted investment for standardisation and
accreditation, peer review, technological equipment and facilities for laboratories and
control units, innovation capacity and capacity in the field of patents and enforcement of
intellectual property legislation, monitoring and evaluation systems in the area of energy
and resource efficiency of enterprises, strictly specialised professional qualification in
eligible areas for financing under OPIC.
OPIC and Rural Development Programme (RDP)
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 133 of 274
The support under OP "Innovation and Competitiveness" and the Rural Development
Programme (RDP) is mutually complementing in terms of innovation, development of
SMEs sector and energy efficiency, the demarcation between the two programmes is
based on the territorial scope, eligible sectors, target groups and beneficiaries and the
types of activities included in the scope of the relevant priorities.
The support for innovation under PA 1 of OPIC is in line with the thematic areas and
horizontal policies identified in RIS3 except those covered by the RDP (e.g. Production
of organic food). The support for innovation under RDP is horizontal and is provided
for sectors of agriculture and food industry for processing and marketing of products
from Annex I to the TFEU, with the exception of fish and fishery products. Within the
European Innovation Partnership "Agricultural Productivity and Sustainability" support
will be provided for the establishment and functioning of the operating groups that will
implement specific innovative project.
In terms of support for SMEs and start-ups under PA 2 of OPIC SMEs from the sectors
defined in NSPSMEs (high, medium and low technology sectors) will be supported,
with the exception of sub-sectors of the food industry for the processing and marketing
of products from Annex I to the TFEU, covered by RDP and with the exception of fish
and fishery products. Investment support and initial aid for non-agricultural activities is
provided to small and medium enterprises throughout the entire territory of the country
and to micro enterprises outside rural areas.
RDP provides investment support for modernization of farms and enterprises,
processing and adding value to agricultural products, incl. food industry for processing
and marketing of product from Annex I to the TFEU, with the exception of fish and
fishery products. Investment support and initial aid for non-agricultural activities is
given to micro enterprises in rural areas.
In terms of energy efficiency OPIC (PA 3) addresses problems of high energy intensity
of manufacturing enterprises, with the exception of farmers and enterprises from food
industry for processing and marketing of products from Annex I to the TFEU, subject of
support under RDP. Both programmes will provide support for use of energy from
renewable sources for own consumption. Enterprises – beneficiaries of OPIC will have
the opportunity to implement measures for use of biomass, including primary and
secondary biomass of products from Annex I. The production of biomass in forestry
will be supported under RDP.
The support for resource efficiency under OPIC is aimed at enterprises and / or groups
of manufacturing enterprises for pilot and demonstration initiatives to increase the
efficient use of resources. Enterprises from food industry for processing and marketing
of product from Annex I to the TFEU are excluded.
The support under OPIC excludes primary production of agricultural products,
including fish and fishery products. In terms of the food industry, processing /
marketing of agricultural products from Annex I to the TFEU, supported under RDP
are excluded by OPIC: milk and milk products, meat and meat products, fruits and
vegetables, including mushrooms, honey, cereals, grain mill and starch products,
vegetable and animal oils and fats, technical and medical plants, including rose oil and
herbs, prepared feeds for farm animals, grape must, wine and vinegar, energy
production through processing plant and animal products with the exception of biomass
of fishery products.
OPIC and Programme for Maritime Affairs and Fisheries (PMAF)
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 134 of 274
PMAF will be financed through the European Maritime and Fisheries Fund and will
include measures in the field of development of research infrastructure and applied
research, technological development and innovation, competitiveness, entrepreneurship,
low-carbon technologies and energy efficiency, environmental protection etc. in the
fisheries and aquaculture sectors.
Considering the nature and scope of the proposed measures under the two programmes,
the main line of demarcation should, as in the current programming period, be sought in
terms of beneficiaries. Eligible beneficiaries of PMAF will be physical persons and
legal entities registered under the Commerce Act or the Cooperatives Act and operating
in the fisheries and/or aquaculture sector, as well as organisations and associations of
organisations of producers in the fisheries or aquaculture sectors and other groupings in
the said sectors that are excluded from the scope of OPIC. With regard to measures to
support ―blue‖ growth PMAF emphasis on marine flora and fauna, and OPIC will fund
projects in case the demand and the potential for the development of "blue" energy is
demonstrated.
Demarcation and complementarity between the Operational Programme
“Innovation and Competitiveness” and other programmes under the Common
Strategic Framework
In order to guarantee the most effective and efficient use of EU resources, it is necessary
to ensure a coordinated approach, cooperation and complementarity of financing tools
in EU programmes and Member States with innovative approaches to tackle global
economic and social challenges. It should therefore be determined which of the
identified funding areas/priorities can be financed through horizontal programmes of the
EU that are relevant to OPIC objectives.
OPIC and Horizon 2020
The framework research and innovation programme Horizon 2020 (2014-2020) will be
the main financial instrument implementing the Innovation Union, a Europe 2020
flagship initiative aimed at securing smart, sustainable and inclusive growth. The
Programme will focus on financing three key priorities:
The first will support Europe‘s position as global leader in research, for example
through the European Research Council, associations and research
infrastructure;
The second will strengthen Europe‘s industrial leadership and make Europe a
more attractive location for investment in research and innovation by providing
major investment in key industrial technologies and offering greater access to
capital and support for SMEs;
The third will address major concerns shared by all citizens in Europe, organised
under six key headlines or Societal Challenges: health, demographic change and
well-being; food security, sustainable agriculture, marine and maritime water
research and bioeconomy; secure, clean and efficient energy; smart, green and
integrated transport; climate action, resource efficiency and raw materials;
inclusive, innovative and secure societies.
OPIC envisages actions to support innovation and increase the competitiveness of
Bulgarian enterprises. This will ensure convergence of the levels of development of
innovation in Bulgaria and the EU, as well as opportunities (increased capacity) for
active and successful participation of Bulgarian enterprises in international initiatives,
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 135 of 274
programmes and projects in the field of innovation and development of key industrial
technologies. Enterprises or other organisations are generally eligible to apply under the
EU horizontal programmes as long as they can submit sustainable and successful
transnational projects which require a certain capacity to prepare and implement.
Securing the necessary investment and working capital is one of the main problems
facing businesses in Bulgaria and the development of entrepreneurship that is addressed
by OPIC, envisaging financial instruments in the field of innovation in accordance with
the ex-ante evaluation of financial instruments.
Horizon 2020 place particular emphasis on the transition to green economy as a driver
of sustainable development. The financial allocation to climate impacts and resource
efficiency will be parallelled with other specific objectives so that at least 60% of the
proposed total budget, amounting to 80 billion euros, will be allocated to sustainable
development and 35% to climate-related issues. The goal will be to provide direct
benefits to citizens, such as safe food, clean cities, green transport and energy-efficient
buildings.
OPIC has a designated priority axis to support the transition to green and efficient
economy whereas eco-innovation falls under PA 1.
OPIC and Programme for the Competitiveness of Enterprises and Small and
Medium-Sized Enterprises (COSME)
The new Programme for the Competitiveness of Enterprises and Small and Medium-
Sized Enterprises has a planned budget of 2.3 billion euros and is aimed at facilitating
SMEs‘ access to funding, creating a favourable environment for business development
and growth of enterprises, fostering entrepreneurial culture in Europe, enhancing
sustainable competitiveness of enterprises in the EU, improving the access of small
businesses to international markets, and supporting the development of the Enterprise
Europe Network.
OPIC envisages actions aimed at promoting entrepreneurship and business development
and supporting the internationalisation of enterprises and the development of business
services. This will increase the capacity of Bulgarian enterprises to participate in
European initiatives and compete internationally.
The envisaged activities like mentoring and attracting international experience will
strenghthen the capacity of enterprises and organizations to apply for financing under
COSME and Horizon 2020...
Complementarity and demarcation of Operational Programme “Innovation and
Competitiveness” with other national instruments
The National Innovation Fund (NIF) at the Ministry of Economy and Energy, which is
managed by BSMEPA, will be assigned BGN 10 million from the central budget,
including also the 7th
round of applications. The identified priority sectors and areas of
industrial research and experimental development to be financed from the NIF under the
seventh round of applications are: mechanical engineering, electronics, food processing,
ICT in enterprises and creative industries.
The main goal of the NIF is to promote research and development in order to enhance
the competitiveness of Bulgarian enterprises, and its specific objective is to promote the
implementation of research and development projects and technical feasibility projects
initiated and implemented by enterprises with best performance in order to acquire new
or improved products, processes or services aimed at enhancing the economic
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 136 of 274
efficiency, innovation potential and technological development of enterprises,
leveraging private investment, and improving the dynamics of innovative processes.
The Fund aims to improve the market outcome for enterprises and society as reflected in
better prices for higher quality, increased production volumes, reduced resource use and
increased investment in efficient businesses.
OPIC and EUREKA
EUREKA is a Europe-wide network for market-driven industrial research and
development. It facilitates the competitiveness of European businesses through
development of international cooperation leading to networking and development of
innovation networks. EUREKA‘s goal is achieving commercialisation of the results of
quality research and development and using the multiplier effect of joint operation to
improve the quality of life.
At present the EUREKA network numbers 39 members, the 40th
being the European
Union. Besides EU States, other members in the initiative are Switzerland, Russia,
Macedonia, Israel, Ukraine, Turkey etc.
The Bulgarian Small and Medium Enterprises Promotion Agency organises and
coordinates the activities related to the country‘s participation in the EUREKA
initiative. The costs of the participation of Bulgarian organisations in projects under
EUREKA are covered from the budget of the National Innovation Fund.
OPIC and EUROSTARS II
EUROSTARS II is successor to EUROSTARS – a joint initiative of EUREKA and the
European Commission under the 7th
Framework Programme for research and
technological development (FP7), and, respectively, Horizon 2020 in the new
programming period. Its aim is to provide funding for market-oriented research and
experimental development with the active participation of small and medium-sized
enterprises in the field of research and development.
EUROSTARS provides opportunities for joint national and European funding of
international research projects, where projects should have partners (legal entities) from
two or more EUROSTARS countries and the lead partner should be a ―small or
medium-sized enterprise working in the area of research and development‖.
The Bulgarian Small and Medium Enterprises Promotion Agency organises and
coordinates the activities related to the country‘s participation in the joint EUROSTARS
initiative. The costs of the participation of Bulgarian organisations in projects under
EUROSTARS are covered from the budget of the National Innovation Fund.
Demarcation and complementarity between the Operational Programme ―Innovation
and Competitiveness‖ and other instruments of the European Economic Area and
Norway
OPIC and Norway Grants
Green industry innovation is one of the support areas of Norway Grants in the financing
period 2009-2014. The total contribution of Norway in the period will amount to over
110 million euros. The overall objective of the grants is increased competitiveness of
green enterprises, including greening of existing industries, green innovation and green
entrepreneurship. The expected results of this particular area of support are: realisation
of business opportunities for greening the European economy – reduced production of
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 137 of 274
waste and reduced air, water and soil pollution – more use of environmentally-friendly
technologies, increased job creation and entrepreneurship.
OPIC and Swiss Programme
Switzerland cooperates with the EC by supporting efforts to reduce economic and social
disparities. The contribution of Bulgaria in the amount of 76 million Swiss francs will
be implemented in the form of projects and programs in the period 2010-2019.
Switzerland participates in areas in which Bulgaria has declared greatest needs and
where Switzerland can provide their expertise. In these areas the support to the private
sector, research and education and the support for building partnerships are included.
The Bulgarian-Swiss Research Programme 2011-2016 encourages joint scientific
cooperation between the two countries.
9. EX-ANTE CONDITIONALITIES
The applicable ex-ante conditionalities are general and thematic:
General ex-ante conditionality 1. The existence of administrative capacity for the
implementation and application of Union anti-discrimination law and policy in the field
of ESI Funds.
General ex-ante conditionality 2. The existence of administrative capacity for the
implementation and application of Union gender equality law and policy in the field of
ESI Funds.
General ex-ante conditionality 3. The existence of administrative capacity for the
implementation and application of the United Nations Convention on the rights of
persons with disabilities (UNCRPD) in the field of ESI Funds in accordance with
Council Decision 2010/48/EC.
General ex-ante conditionality 4. The existence of arrangements for the effective
application of Union public procurement law in the field of the ESI Funds.
General ex-ante conditionality 5. The existence of arrangements for the effective
application of Union State aid rules in the field of the ESI Funds.
General ex-ante conditionality 7. The existence of a statistical basis necessary to
undertake evaluations to assess the effectiveness and impact of the programmes.
The existence of a system of result indicators necessary to select actions, which most
effectively contribute to desired results, to monitor progress towards results and to
undertake impact evaluation
Thematic conditionality 1.1. Research and innovation: The existence of a national or
regional strategy for smart specialisation in line with the National Reform Programme
aimed to raise private funds for research and innovation, in line with the characteristics
of well-performing national or regional systems in research and innovation.
Thematic conditionality 3.1. Specific actions have been carried out to underpin the
promotion of entrepreneurship taking into account the Small Business Act (SBA).
Thematic conditionality 4.1. Actions have been carried out to promote cost-effective
improvements of energy end use efficiency and cost-effective investment in energy
efficiency when constructing or renovating buildings.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 138 of 274
Thematic conditionality 4.3. Actions have been carried out to promote the production
and distribution of renewable energy sources.
Thematic conditionality 6.1. Water sector: The existence of a) a water pricing policy
which provides adequate incentives for users to use water resources efficiently and b) an
adequate contribution of the different water uses to the recovery of the costs of water
services at a rate determined in the approved river basin management plan for
investment supported by the programmes.
Thematic conditionality 6.2. Waste sector: Promoting economically and
environmentally sustainable investments in the waste sector particularly through the
development of waste management plans consistent with Directive 2008/98/EC, and
with the waste hierarchy.
Thematic conditionality 7.4. Development of smart energy distribution, storage and
transmission systems. The existence of comprehensive plans for investments in smart
energy infrastructure, and of regulatory measures, which contribute to improving energy
efficiency and security of supply.
9.1. Description of the actions which will be taken to implement ex-ante
conditionalities, responsible authorities and timeframe of these actions
The actions which will be taken to implement the applicable general ex-ante
conditionalities are presented in the table below.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 139 of 274
Table 9-1 Applicable ex-ante conditionalities and assessment of their fulfilment
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
Thematic ex-ante conditionalities under ESIF
1.1. Research and
innovation: The existence
of a national or regional
smart specialization
strategy in line with the
National Reform
Program, to leverage
private research and
innovation expenditure,
which complies with the
features of well-
performing national or
regional R&I systems.
NO A national or regional smart
specialization strategy is in place that:
— is based on a SWOT or similar
analysis to concentrate resources on a
limited set of research and innovation
priorities;
— outlines measures to stimulate
private RTD investment;
— contains a monitoring mechanism.
NO A working draft of the SSS strategy is
prepared. It is elaborated together with
expert from the WB.
http://www.mi.government.bg/files/userupl
oads/files/innovations/ris3_31_10_2013.pd
f.
National Strategy of Scientific Research to
2020 - adopted by the National Assembly
in 2011.
http://www.strategy.bg/StrategicDocuments
/View.aspx?lang=bg-BG&Id=708
National Strategy of Scientific Research
was adopted by Decision of the National
Assembly in 2011 (State Gazette, issue 62,
dated 12.08.2011). The strategy provides a
stable framework for the development of
research institutions and of the scientific
and innovation activities in Bulgaria for a
period of ten years 2011 - 2020. It contains
all necessary elements required in the ex-
ante conditionalities for the EU Structural
and Investment Funds for 2014-2020 - it is
based on the SWOT analysis and outlines
the measures to improve the research and
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 140 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
technological development and includes
indicators for monitoring the
implementation of objectives, tasks as well
as measures and mechanism for
monitoring. Furthermore, it is accompanied
by a three-year Action Plan for the period
August 2011 - August 2014, and the
effectiveness of the implementation of the
objectives and measures will be evaluated
by independent experts on a three-year
period. The Action Plan is the framework
for the activities, programs and initiatives
that the Government will implement in
connection with the implementation of the
National Research Strategy. The Action
Plan covers the policies, priorities and
programs of line ministries and
departments in the science and innovation
system. The Action Plan proposes a
combination of measures and actions,
supported by various national funds,
European programs, cohesion instruments
and special schemes for support from third
parties.
A framework outlining available
budgetary resources for research and
innovation has been adopted.
NO
1.2 Research and
Innovation infrastructure.
The existence of a multi-
NO An indicative multi-annual plan for
budgeting and prioritization of
investments linked to Union priorities,
NO National Roadmap for Research
Infrastructure
In implementation of the Roadmap,
MES participated in three pan-
European research infrastructures
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 141 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
annual plan for budgeting
and prioritization of
investments.
and, where appropriate, the European
Strategy Forum on Research
Infrastructures (ESFRI) has been
adopted.
http://www.mon.bg/top_menu/science/infr
astructure/
National Roadmap for Research
Infrastructure is adopted by CoM Decree
No. 692 dated 21.09.2010. The National
Roadmap has identified priority
infrastructures as well as possible sources
of funding. In developing the National
Roadmap, experts from the European
Strategy Forum for Research
Infrastructures are attracted and ex ante
assessment is made of the included
infrastructures.
through concluded Memoranda of
Understanding.
As at 2013 Bulgaria is part of the
following international consortium:
1. EURO-ARGO - Global
Monitoring of Oceans - PART OF
THE ADVANTAGES FOR
BULGARIA, Bulgaria has the
potential to be designated as a
Regional Coordinator for the Black
Sea. Our participation in the
EURO-ARGO will improve the
technical installations for
observations of the Black Sea, the
climate change and for better
precision and accuracy of weather
forecasting. Will provide access to
advanced facilities and information
about the countries of the region
and will provide services to the
benefit of society - climate change,
the state - security of maritime
transport and business - aquaculture
and fisheries, and others;
2. BBMRI - BIOBANKING AND
BIOMOLECULAR RESOURCES,
Bulgarian scientists will participate
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 142 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
in the development of new
diagnostic methods and drugs,
including a quick transfer to clinical
trials and development of methods
for individual diagnosis and
subsequent treatment.
3. CLARIN-E-
INFRASTRUCTURE FOR THE
INTEGRATION AND
DEVELOPMENT OF
ELECTRONIC LANGUAGE
RESOURCES WITH UNIQUE
DATABASES AND
KNOWLEDGE BASES FOR
BULGARIAN LANGUAGE
TECHNOLOGY SOFTWARE
MODULES AND COMPUTER
NETWORKS. CLARIN will
preserve Bulgarian linguistic
heritage and will provide wide
access to language resources and
technologies to all potential users
from industry and research to
education.
3.1. Specific actions have
been carried out to
underpin the promotion of
entrepreneurship taking
into account the Small
YES The specific actions are:
— measures have been put in place
with the objective of reducing the time
and cost involved in setting-up a
business taking account of the targets
YES Applications for initial registration of
traders are considered within the statutory
three days. The fee for registration of a
limited liability company is currently well
below the specified amount of 100 €.
Legal acts in effect regulating the measures
Draft amendments and
supplements to the Commercial
Register Act (in implementation of
measure 7 of the package of
measures to reduce the regulatory
burden adopted by Decision No
484/15.08.2013 of the Council of
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 143 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
Business Act (SBA). of the SBA;
are available on the following websites:
http://www.registryagency.bg/downloads/Z
TR.pdf
http://www.registryagency.bg/downloads/t
arifa.pdf
Four plans to reduce the administrative and
regulatory burden on business, containing a
total of 385 measures are currently being
implemented - Plan to reduce the
regulatory burden on the business from
2012 and three new packages to reduce the
administrative and regulatory burden on
the business, adopted in 2013 and 2014.
Most of these measures relate to reducing
the time to establish a business.
http://www.strategy.bg/Publications/View.
aspx?lang=bg-
BG&categoryId=&Id=170&y=&m=&d=
http://www.strategy.bg/StrategicDocument
s/List.aspx?lang=bg-
BG&categoryId=6&typeConsultation=1&t
ypeCategory=6&docType=2
Ministers (CoM) have been
prepared a and provide for a
reduction of the period for initial
registration of traders from 3 days
to one day.
The proposed texts are included in
the
draft legislative amendments to
reduce
the regulatory burden, namely the
transitional provisions of the Draft
Law
amending the Law on Tourism.
Draft
Law amending the Law on Tourism
was
adopted by the Council of Ministers
in
January 2014 and was submitted to
the
National Assembly on February 4,
2014.
Same is considered by the
Committee
on European Affairs and Control of
the
European Funds (February 26,
2014)
and by the Committee on Legal
Affairs
(March 12 2014). Its first reading in
plenary is forthcoming.
On 14.02.2014 in the Official
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 144 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
Gazette No. 13/14.02.2014 was
promulgated and became effective
Decree № 15 of 7 February 2014
amending the Tariff of state fees
collected by the Registry Agency
adopted by Decree № 243 of the
Council of Ministers in 2005. The
adopted amendment reduces the
fees for the registration of traders in
the Commercial Register at the RA.
Information about the amendments
to the Tariff for state fees collected
from the RA can be found on the
website of the Registry Agency:
http://www.registryagency.bg/down
loads/tarifa.pdf
JEREMIE is used to create seed and
start-up funds and accelerators that
fill in the niche in the market to
fund business ideas and start-ups.
The banks do not provide such
funding. The funds operate a little
over a year and are considered one
of the most successful not only in
Bulgaria but also in the wider
Balkan region. As a result, Bulgaria
climbs 12 steps up in the
"Entrepreneurship" by SBA and
now ranks ninth. Bulgaria ranks 6
in the EU in the ranking of the
World Bank with regard to density
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 145 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
of start-ups. Funds are managed by
private companies, using funds
under JEREMIE, awarded through
the program "Competitiveness" of
MEE, and the funds are from the
EIF.
http://doingbusiness.org/data/explor
etopics/entrepreneurship
http://eleven.bg/bulgarian/
http://launchub.com/
— measures have been put in place
with the objective of reducing the time
needed to get licenses and permits to
take up and perform the specific
activity of an enterprise taking
account of the targets of the SBA;
YES There are national plans and programs that
are aimed at reducing the administrative
burden and for better regulation (see
above).
CoM Decision №484 dated August 2013
http://www.strategy.bg/PublicConsultation
s/View.aspx?lang=bg-BG&Id=1043
CoM Decision №484 dated October 2013
See TExAC 11.
— a mechanism is in place to monitor
the implementation of the measures of
the SBA which have been put in place
and assess the impact on SMEs.
YES National Strategy for Promotion
of Small and Medium Enterprises 2014-
2020 National Strategy for Promotion of
Small and Medium Enterprises 2014-2020
was adopted by Decision № 37 of the
Council of Ministers of 23 January 2014.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 146 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
It is entirely adapted to SBA. The criteria
for evaluation of the implementation of the
strategy objectives meet the criteria used
by EC in assessing the implementation of
SBA in the so called Fact Sheets.
http://www.mi.government.bg/bg/themes/n
acionalna-strategiya-za-nasarchavane-na-
msp-v-balgariya-2014-2020-small-
business-act-11-285.html
Internal assessment other than through
SBA Fact Sheets is also carried out by
considering the implementation of the
Annual program for implementation of the
Strategy by the SME under the SME Act,
Article 12, paragraph 1.
• Annex № 1 to Art. 30a, para 2, item 6 of
RPCMA provides that assessment is
required for the administrative and
regulatory burden. Such an assessment is
an element necessary to the performance of
the SME test. Pursuant to the adopted
Concept for implementation of SME-test,
systematic application of the SME test
should be guaranteed by the amendments
to the Act on regulations. that The draft
Law amending the LLA, which includes
the impact assessment and the SME test, is
in the process of interministerial
coordination under Art. 32-34 of RPCMA
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 147 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
4.1. Actions have been
carried out to promote
cost-effective
improvements of energy
end use efficiency and
cost-effective investment
in energy efficiency when
constructing or renovating
buildings.
Partially The actions are:
— measures to ensure minimum
requirements are in place related to the
energy performance of buildings
consistent with Article 3, Article 4 and
Article 5 of Directive 2010/31/EU of
the European Parliament and of the
Council ( 1 );The actions include:
NO
Bulgaria has adopted a methodology for
calculating the energy performance of
buildings, which is regulated in Article 15
of the Energy Efficiency Act (EEA),
promulgated in SG 24, dt 12.03.2013, and
in the provisions of Ordinance No РД-16-
1058 on indicators for energy consumption
and energy performance of buildings of
MEE and MRD and in the provisions of
Ordinance No. 7 on energy efficiency, heat
and energy savings in buildings of MIP and
Appendix No 3 of Ordinance No 7.
http://www.seea.government.bg/index.php
?option=com_content&view=article&id=9
250&Itemid=227&lang=bg
http://www.seea.government.bg/documents
/Naredba%207.pdf
According to the methodology for
calculating the energy performance
of buildings, the latter is determined
on the basis of the calculated or
measured amount of energy needed
to meet the energy needs associated
with typical consumption for the
building which includes heating,
cooling, ventilation, hot water and
lighting. The needs of heating,
cooling, ventilation and hot water
for domestic use and for non-
residential lighting are reflected.
The energy performance of a
building is expressed in a
transparent manner and includes an
indicator of energy use and digital
indicator for primary energy use.
The methodology takes into account
the aspects affecting energy
performance as follows: Features of
the building and energy plants:
heating, hot water supply, air
conditioning, ventilation, lighting,
solar systems and protection, indoor
climatic conditions, etc.; aspects
that positively influence the energy
performance: local solar exposure,
active solar systems, other heating
and electricity systems based on
renewable energy sources,
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 148 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
electricity produced from co-
generation, systems for heating /
cooling of the district or block of
flats, natural lighting and more.
In SG, issue 93, dated 25.10.2013,
an Ordinance supplementing
Ordinance No. 7 of 2004 is
promulgated for energy efficiency,
heat and energy savings in
buildings by the Minister of
Investment Planning. The
supplemented Ordinance includes
explicit reference to Commission
Delegated Ordinance (EU) No
244/2012 of 2012 supplementing
Directive 2010/31/EU by
establishing a comparative
methodology framework for
calculating cost-optimal levels of
minimum requirements energy
performance of buildings and
building components (OJ, L 81/18
of 21 March 2012).
Pursuant to Art. 5, paragraph 2 of
Directive 2010/31/EU on the energy
performance of buildings and art. 6
of Regulation 244/2012 of the
Commission, a report has been
developed and presented to the EC
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 149 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
"Calculation of optimal cost levels
of minimum energy performance
requirements for buildings in the
Republic of Bulgaria".
The report was developed based on
the results of four consecutive and
interrelated systematic analyses of
buildings in Bulgaria. The
legislative acts in the field of energy
efficiency for project, establishment
and renovation of buildings in
conformity of the requirement in he
Directive 2010/31/ЕU and
Regulation 244/2012 of the EC.
Forthcoming is notification in front
of the bodies of the EC.
— measures necessary to establish a
system of certification of the energy
performance of buildings consistent
with Article 11 of Directive
2010/31/EU;
YES
In Section II of the Energy Efficiency Act,
promulgated in SG 24, 12.03.2013 a
system of certification of the energy
performance of buildings is regulated
"Energy efficiency evaluation and
certification of buildings", as well as in
Ordinance No 16-1594 of 13.11.2013 on
energy auditing, certification and
assessment of energy savings in buildings,
with its Appendices.
http://www.seea.government.bg/index.php
?option=com_content&view=article&id=9
250&Itemid=227&lang=bg
Pursuant to the mentioned
regulations governing the
certification system of buildings,
there are in place energy
performance certificates to allow
the owners or tenants of the
building or building part to compare
and assess its energy performance;
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 150 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
— measures to ensure strategic
planning on energy efficiency,
consistent with Article 3 of Directive
2012/27/EU of the European
Parliament and of the Council ( 2 );
YES Strategic planning of energy efficiency is
accomplished with the Energy Strategy of
the Republic of Bulgaria.
http://www.mi.government.bg/bg/themes/e
nergiina-strategiya-na-republika-balgariya-
do-2020-g-147-295.html
http://www.minfin.bg/bg/page/573- - p.36
In terms of residential buildings a National
Housing Strategy and National Program for
Renovation of Residential Buildings in the
Republic of Bulgaria are in effect.
Bulgaria has set national indicative
energy efficiency target of 25%
improvement in energy efficiency
by 2020 in accordance with Art. 3
of Directive 2012/27EU.
— measures consistent with Article 13
of Directive 2006/32/EC of the
European Parliament and of the
Council ( 3 ) on energy end-use
efficiency and energy services to
ensure the provision to final customers
of individual meters in so far as it is
technically possible, financially
reasonable and proportionate in
relation to the potential energy
savings.
YES Regulations related to measures under
Article 13 of Directive 2006/32/EC are:
The Energy Act (EA) and Ordinance No
16-334 for heat supply
http://www.mi.government.bg/bg/library/z
akon-za-energetikata-256-c25-m258-
2.html
http://www.mi.government.bg/bg/library/n
aredba-16-334-ot-6-april-2007-g-za-
toplosnabdyavaneto-404-c78-m260-3.html
For electricity - Art. 120 of EA;
For newly constructed multifamily
buildings - Ordinance № 15 of 28.07.2005
on technical rules and standards for design,
construction and operation of facilities and
Heating systems in multifamily
buildings with central heating in
Bulgaria until 1995. are performed
exclusively as two pipe, vertical
systems. In these installations,
radiators of various properties
located vertically above each other,
join the vertical part of the building
installation. For this type of
prevailing buildings, the only
technical possibility of measuring
the consumed thermal energy in
housing and its distribution is by the
installation of individual valves on
each radiator in the multifamily
buildings.
For newly build buildings, well
before the introduction of the
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 151 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
equipment for the generation, transmission
and distribution of heat
For district heating - Art. 139, para. 1; Art.
140, para. 1; Art. 140а to Art. 145 and Art.
156 of EA; Art. 43; Art. 52, Art. 1 to 5;
Art. 62 and Methodology for distribution
of heat for buildings - condominium,
Appendix to Art. 61 of Ordinance No 16-
334.
http://www.mi.government.bg/bg/library/n
aredba-15-ot-28-07-2005-g-za-tehnicheski-
pravila-i-normativi-za-proektirane-
izgrajdane-i-eksploa-405-c78-m260-3.html
Regulatory framework for billing by
energy distributors is in Art. 38 of the
Energy Efficiency Act (EEA).
http://www.seea.government.bg/index.php
?option=com_content&view=article&id=9
250&Itemid=227&lang=bg
Provisions relating to the general
conditions of the contracts approved by the
State Energy and Water Regulatory
Commission are spelled in Art. 150, para.
1 and Art. 149b of the EA
http://www.mi.government.bg/bg/library/z
akon-za-energetikata-256-c25-m258-
2.html
The rest of the information is contained in
requirements of the Directive, the
national legislation has introduced
the requirement for the design and
construction of horizontal heating
systems (Ordinance No 15 of
28.07.2005). For this type of
heating systems, the radiators for
each plot are with horizontal pipes
for each property and a technical
possibility is available for
individual measuring of the heating
energy consumed by each separate
property.
The requirements laid down in
Directive 2006/32/EC, including the
measuring of individual heat
consumption are further developed
and refined by Directive
2012/27/EU.
In item 12 of the preamble to
Directive 2012/27/EU it is stated
that provisions of Directive
2004/8/EC of November 2004
should be strengthened with regard
to the promotion of cogeneration
based on a useful heat energy
demand in the domestic energy
market and of Directive
2006/32/EC. In this sense, at
present, Bulgaria has introduced in
its legislation precisely those
"enhanced" - precise and detailed
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 152 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
the monthly reports of invoices provided to
customers of heat from the respective
district heating companies.
requirements of Directive
2012/27/EC.
4.3. Actions have been
carried out to promote the
production and
distribution of renewable
energy sources ( 4 ).
YES Transparent support schemes, priority
in grid access or guaranteed access
and priority in dispatching, as well as
standard rules relating to the bearing
and sharing of costs of technical
adaptations which have been made
public are in place consistent with
Article 14(1), Article 16(2) and 16(3)
of Directive 2009/28/EC of the
European Parliament and of the
Council ( 4 ).
YES Art. 52, Art. 54 of the Renewable energy
Sources Act (RESA) (Promulgated SG,
issue 35/03.05.2011, amended and
supplemented SG 109 of 2013, effective
since 1.01.2014,
http://www.mi.government.bg/bg/library/z
akon-za-energiyata-ot-vazobnovyaemi-
iztochnici-167-c25-m258-1.html
Ordinance for gathering and provision of
information through the National
Information System about the potential, the
production and consumption of renewable
energy in Bulgaria (SG 39/22.05.2012)
http://www.seea.government.bg/documents
/NAREDBA_RD16558_ot_8052012.pdf
The state has implemented the
requirements for transparent support
schemes. The requirement to provide
information to all stakeholders on the
support measure was introduced in the
Bulgarian legislation.
Art. 18, Art. 1, Art. 24, item 1, Art. 26,
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 153 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
para. 3, para. 4, para. 5 and Art. 30, Art. 6,
Art. 7 of RESA;
Art. 50, Art. 52 of Ordinance No. 3,
21.03.2013 on licensing of activities in the
energy sector (promulgated, SG. 33 of
5.04.2013)
Rules for Management of the Electricity
System (Promulgated, SG, issue 6 of
21.01.2014) /
Rules on the Electricity Distribution
Networks Management (Promulgated, SG,
issue 66 of 14.08.2007)
http://www.dker.bg/files/DOWNLOAD/P
RAVILA__upr_na_ees.pdf
http://www.dker.bg/files/DOWNLOAD/rul
e_el_16.pdf
The requirement to provide guaranteed grid
access and priority dispatch of electricity
from renewable sources are introduced into
the Bulgarian legislation.
Art. 22, Art. 23, Art. 27, Art. 29, Art. 52 of
RESA;
Art. 30, Art. 31 of the Energy Act
(Promulgated in SG, issue 107 of
9.12.2003, amended and supplemented
SG, issue 66 of 26.07.2013)
Ordinance No 1 of 18.03.2013 on the
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 154 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
adjustment of electricity prices
(Promulgated, SG, issue 33 of 5.04.2013)
http://www.mi.government.bg/bg/library/z
akon-za-energetikata-256-c25-m258-
1.html
Methodology to offset the cost of the
public service and end suppliers resulting
from imposed public service obligations
for the purchase of electricity at
preferential prices from renewable energy
sources and high-efficiency combined heat
and electricity production (promulgated,
SG, issue 62 of 14.08.2012)
http://dker.bg/docsbg.php?d=8&subD=30
State has complied with the requirement of
public accessibility rules for bearing and
sharing of costs associated with grid
connection of power plants for electricity
production from renewable sources.
A Member State has adopted a
national renewable energy action plan
consistent with Article 4 of Directive
2009/28/EC.
YES National Action Plan for Energy from
Renewable Sources (NAPERS) was
adopted by the Council of Ministers of the
Republic of Bulgaria on January 9, 2013.
http://www.mi.government.bg/files/userupl
oads/files/eoos/plan_res_2013.pdf
Bulgaria has prepared and adopted
a National Action Plan for Energy
from Renewable Sources. The plan
was prepared on the model adopted
by Decision No C) 2009) 5174 of
the Commission, presented to the
European Commission and
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 155 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
implemented.
6.1. Water sector: The
existence of a) a water
pricing policy which
provides adequate
incentives for users to use
water resources efficiently
and b) an adequate
contribution of the
different water uses to the
recovery of the costs of
water services at a rate
determined in the
approved river basin
management plan for
investment supported by
the programmes.
NO - In sectors supported by the
ERDF and the Cohesion Fund, a
Member State has ensured a
contribution of the different water
uses to the recovery of the costs of
water services by sector consistent
with the first indent of Article 9(1) of
Directive 2000/60/EC having regard,
where appropriate, to the social,
environmental and economic effects
of the recovery as well as the
geographic and climatic conditions of
the region or regions affected.
NO River basin management plans
http://www3.moew.government.bg/?show=
top&cid=66&lang=bg
I. River Basin Management Plans are
into force and reported to EC on
22.03.2010.
II. Water Act
http://www3.moew.government.bg/files/fil
e/Water/Legislation/Zakoni/ZAKON_za_v
odite.pdf
Fee tariff for water use, use of water object
and pollution
http://www3.moew.government.bg/files/fil
e/Water/Legislation/tarifi/Ttaksi_vodovz_p
olzv_zamyrs.pdf
The Tariff introduced fees for water use for
various purposes, which partly provides
contribution to water users for recovery of
costs for water services and partly - the
"polluter pays" principle.
Legislation in the water sector
http://www.moew.government.bg/?show=t
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 156 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
op&cid=40
- The adoption of a river
basin management plan for the river
basin district consistent with Article
13 of Directive 2000/60/EC
NO River basin management plans
http://www3.moew.government.bg/?show=
top&cid=66&lang=bg
River Basin Management Plans are into
force and reported to EC on 22.03.2010.
6.2. Waste sector:
Promoting economically
and environmentally
sustainable investments in
the waste sector
particularly through the
development of waste
management plans
consistent with Directive
2008/98/EC, and with the
waste hierarchy.6.2.
Partially An implementation report as requested
by Article 11(5) of Directive
2008/98/EC has been submitted to the
Commission on progress towards
meeting the targets set out in Article
11 of Directive 2008/98/EC.
YES The report has been sent to the European
Commission on 30th of September 2013.
The existence of one or more waste
management plans as required under
Article 28 of Directive 2008/98/EC;
NO At present in Bulgaria a National
Programme for Waste Management 2009-
2013 is in place:
http://www.moew.government.bg/?show=t
op&cid=376
The National Waste Management
Plan 2014-2020 is being prepared.
The existence of waste prevention
programmes, as required under Article
29 of Directive 2008/98/EC;
NO At present in Bulgaria the National
Programme for Waste Management 2009-
2013 is in effect.
The programme for prevention of
generating waste is to be a part of
the National Waste Management
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 157 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
http://www.moew.government.bg/?show=t
op&cid=376
Plan 2014-2020.
See TExAC 6.2.2.
Necessary measures to achieve the
targets on preparation for re-use and
recycling by 2020 consistent with
Article 11(2) of Directive 2008/98/EC
have been adopted.
NO Since 13.07.2012 the promulgated Waste
Management Act sets the targets and
responsibilities.
http://www3.moew.government.bg/files/fil
e/Waste/Legislation/Zakoni/ZUO.pdf
Measures for targets achievement
will be included in the new National
Waste Management Plan
See TExAC 6.2.2.
7.4. Development of
smart energy distribution,
storage and transmission
systems. The existence of
comprehensive plans for
investments in smart
energy infrastructure, and
of regulatory measures,
which contribute to
improving energy
efficiency and security of
supply.
NO — Comprehensive plans describing
the national energy infrastructure
priorities are in place that are:
— in accordance with Article 22 of
Directive 2009/72/EC and of Directive
2009/73/EC, where applicable, and
—consistent with the relevant regional
investment plans under Article 12 and
with the Union-wide ten-year network
development plan in accordance with
point (b) of Article 8(3) of Regulation
(EC) No 714/2009 of the European
Parliament and of the Council ( 6 )
and with Regulation (EC) No
715/2009 of the European Parliament
No
No
Yes
There is a national plan laying out the
priorities in gas infrastructure development
in Bulgaria and including the Bulgaria-
Serbia interconnector.
The Ten-year Network Development Plan
(TYNDP) of Bulgartransgaz under Article
22 of Directive 2009/72/EC for the period
2014-2022 can be accessed via the
following link:
http://www.bulgartransgaz.bg/files/userupl
oads/files/financial_reports/tyndp_2014_20
23_bg.pdf
IBS has been included in the Gas Regional
Investment Plans (GRIPs), as well as in the
Union-wide TYNDP in all their versions.
As regards financing, Competitiveness of
the Bulgarian Economy Operational
Programme is pointed out (page 22):
http://publ.com/a4yjmMw#22
The project for gas interconnection
Bulgaria-Serbia (IBS) is included
on p. 49, item 5.2.3, on top of page
39 is foreseen Bulgartransgaz
investment for connection to IBS.
On 23 September 2014 public
discussion with the stakeholders of
the 10-year Network Development
Plan (TYNDP) 2014-2023 of
Bulgartransgaz was held. It was
followed by closed meeting of the
State Energy and Water Regulatory
Commission on 8 October 2014.
After it, a letter requesting the
provision of additional information
was sent to Bulgartransgaz.
Bulgartransgaz have provided the
required additional information.
Approval of the TYNDP is part of
the process of certification of
Bulgartransgaz an an independent
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 158 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
and of the Council ( 7 ), and
— compatible with Article 3(4) of
Regulation (EU) No 347/2013 of the
European Parliament and of the
Council ( 8 );.
— Those plans shall contain:
— a realistic and mature project
pipeline for projects for which support
from the ERDF is envisaged;
— measures to achieve the objectives
of social and economic cohesion and
environmental protection, in line with
Article 3(10) of Directive 2009/72/EC
and Article 3(7) of Directive
2009/73/EC;
— measures to optimise the use of
energy and promote energy
efficiency, in line with Article 3(11)
of Directive 2009/72/EC and Article
3(8) of Directive
Yes
IBS is included in the first list of Projects
of Common Interest (PCI-s) that can be
reached via the following link:
http://ec.europa.eu/energy/infrastructure/p
ci/doc/2013_pci_projects_country.pdf
transmission operatior, which will
be completed by September 2015.
It is envisaged by the end of
January 2015 the project for a
decision for certification of
Bulgartransgaz EAD to be agreed
by SEWRC and notified to the
Comission. Final certification
decision to be adopted by
September 2015.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 159 of 274
General ex-ante conditionalities under ESIF
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
1. The existence of
administrative capacity
for the implementation
and application of Union
anti-discrimination law
and policy in the field of
ESI Funds
YES Arrangements in accordance with the
institutional and legal framework of
Member States for the involvement of
bodies responsible for the promotion
of equal treatment of all persons
throughout the preparation and
implementation of programmes,
including the provision of advice on
equality in ESI fund-related activities;
YES -Protection against Discrimination Act
((http://www.kzd-
nondiscrimination.com/layout/index.php/la
yout-over-40-positions/normativni-
dokumenti/zakon-za-zashtita-ot-
diskriminacia) fully transposes EU
directives on equality: 2000/43/ЕC,
78/200/ЕC, 75/117/ЕEC, 97/80/EC and
76/207/EEC, and ensures the protection of
all citizens of the Republic of Bulgaria
against discrimination, while assisting in
the prevention of discrimination and
establishes measures for equal
opportunities.
- Commission for Protection against
Discrimination
Under the provisions of Article 40 of the
Protection against Discrimination Act, in
2005 the Commission for Protection against
Discrimination is created, which is an
independent specialized state body for
prevention of discrimination, protection
from discrimination and ensuring equal
opportunities. The Commission monitors
the implementation and compliance of
Bulgarian and international anti-
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 160 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
discrimination rules governing equal
treatment and for its activities it is
accountable to the highest authority of the
legislature - the National Assembly of the
Republic of Bulgaria. Commission for
Protection against Discrimination (CPD) is
accredited body for human rights protection
to UN, with status "B" in relation to
responding to the Paris Principles.
-As a platform for consultation and
involvement of the authorities responsible
for anti-discrimination, the Commission
holds annually seminars with senior
officials from the central government - MoI,
MLSP, MoC, etc.., The judicial system -
judges and prosecutors, the territorial
municipal administrations, as well as
representatives of media and NGOs.
-To facilitate the active participation of
CPD in the equitable treatment of all people
in the preparation and implementation of
programs and activities of the EU, Rules of
Proceedings before CPD are adopted and
implemented An amendment of Protection
against Discrimination Act will be made
The Draft was approved by the Council of
Ministers by Decision № 735 of
11.22.2013, and is submitted to the
National Assembly on 25.11.2013, under №
302-01-46. The amendment will set new
minimum requirements for preferential
referral of CPD in order to implement the
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 161 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
principle of equal treatment and prevention
of discrimination.
The shape of the consultation and
involvement is through participation in
various coordination procedures under the
Rules of Procedure of CoM and working
groups such as WG 13 "Social Policy and
Employment", etc.
According to Article 5, para. 4 of the
Decree of CoM No. 5 of January 18, 2012
to develop strategic and program
documents of the Republic of Bulgaria to
manage funds under the Common Strategic
Framework of the European Union for the
programming period 2014-2020, the
composition of the thematic working
groups for program development for the
new programming period must include
representatives of the CPD and national
representative organizations of and for
people with disabilities recognized by the
Council of Ministers under the Integration
of Persons with Disabilities Act;
In all programs in the new programming
period the horizontal principles of gender
equality and non-discrimination will be
observed.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 162 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
Arrangements for training for staff of
the authorities involved in the
management and control of the ESI
Funds in the fields of Union anti-
discrimination law and policy.
YES - This criterion is implemented at several
levels: through the Training Plan of the
Training Centre of MLSP, project activities
of CPD, the activities of the Agency for
People with Disabilities (APD), the
Ombudsman, NGOs, social partners and
other stakeholders, aimed at raising
awareness and capacity in the field of law
and anti-discrimination policy.
- CPD annually conducts training on EU
legislation and anti-discrimination policy
through thematic workshops where as guest
speakers representatives of the EU
institutions are invited.
Implementation of the Convention on the
Elimination of All Forms of Discrimination
against Women and its Additional Protocol
is within the training programmes at the
National Institute of Justice regarding
safeguards against discrimination
A public lecture was held with the
participation of a judge in the EC Court of
Justice in Luxembourg on "The practice of
the Court of Justice on the application of
the Charter of Fundamental Rights of the
EU. Application of the Charter in the
Member States.". The program of the event
included anti-discrimination legislation and
relevant case-law of the EC Court of
Justice. In the public lecture were involved
63 participants /48 judges, 9 prosecutors,
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 163 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
investigators, 2 representatives of the
Commission for Protection against
Discrimination, one representative of the
Sofia University and one representative of
the Union of Jurists in Bulgaria/.
- The workshops cover a wide area of
responsible employees from the central
government authorities - MoI, MLSP, MES,
MoC etc., the territorial municipal
administrations as well as representatives of
the media and NGOs.
- Within the scope of project activities
MLSP conducts training regarding anti-
discrimination policies and relevant
legislation. This includes training for
social partners, employers' organizations,
the structures of the Employment Agency
(EA), the structures of the Agency for
Social Assistance (ASS) , trade unions,
employers, NGOs, etc., aiming at a real
impact and change on the labor market in
the direction of reducing inequality under
all discriminatory signs.
Five workshops were held within the
project "Combating discrimination - of a
just society
(JUST/2012/PROG/AG/AD/3710)
program PROGRESS (2007-2013).
Another area in which the MLSP is
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 164 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
operating is conducting trainings for
prevention of discrimination in homes for
children deprived of parental care.
In March, were prepared the third
roundtable on Central region and training
seminars in Plovdiv and Burgas for the
teams working with children in
institutional care.
In March and April 2014 were held two
roundtables at regional level, with the
participation of employers, young people
leaving institutions for children, local
government, regional structures of the
Employment Agency and the Agency for
social support. Roundtables aimed to
change public attitudes and the realization
of the labor market for young people in
social institutions who are in their final
year of study.
In april 2014 a National Campaign was
held to raise awareness and increase
public sensitivity in relation to Council
Directives 2000/43/EC and 2000/78/EC -
in Kardzhali and Balchik. Project
activities were completed with organizing
the final conference in Sofia during the
month of May 2014.
2. The existence of
administrative capacity
for the implementation
YES Arrangements in accordance with the
institutional and legal framework of
Member States for the involvement of
bodies responsible for gender equality
YES According to Art. 20 Directive 2006/54/EC,
the Commission for Protection against
Discrimination is defined as a national
With Order No РД01-727 of
09.27.2013 of the Minister of
Labour and Social Policy was
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 165 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
and application of Union
gender equality law and
policy in the field of ESI
Funds
throughout the preparation and
implementation of programmes,
including the provision of advice on
gender equality in ESI Fund-related
activities;
equality body.
-Protection against Discrimination Act (in
force since 01.11.2004) fully transposes EU
directives on equality: 2000/43/ЕC,
78/200/ЕC, 75/117/ЕEC, 97/80/EC and
76/207/EEC, and ensures the protection of
all citizens of the Republic of Bulgaria
against discrimination, while assisting in
the prevention of discrimination and
establishes measures for equal
opportunities. Under the provisions of
Article 40 of the Protection against
Discrimination Act, in 2005 the
Commission for Protection against
Discrimination is established, which is an
independent specialized state body for
prevention of discrimination, protection
from discrimination and ensuring equal
opportunities. The Commission monitors
the implementation and compliance of
Bulgarian and international anti-
discrimination rules governing equal
treatment and for its activities it is
accountable to the highest authority of the
legislature - the National Assembly of the
Republic of Bulgaria. Commission for
Protection against Discrimination (CPD) is
accredited body for human rights protection
to UN, with status "B" in relation to
responding to the Paris Principles.
The state policy of the Republic of Bulgaria
established an interdepartmental
working group, which aim is to
prepare a draft law on gender
equality.
The Draft addresses the
commitments of the Republic of
Bulgaria in international and
European treaties to which it is
party.
The draft law defines the
institutions and mechanisms for
the implementation of state policy
on gender equality and regulation
of opportunity, incl. regulates the
institutional mechanism for gender
equality.
Ministers adopted Decree № 104
of 10 May 2014 amending the
Decree № 313 of the Council of
Ministers in 2004 to establish the
National Council on Equality
between women and men, the
Council of Ministers.
The Decree amends the Rules for
the structure and organization of
the National Council on Equality
between women and men to the
Council of Ministers. The Rules
are adopted in the annex to the
Art. 2 of the Decree № 313 of
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 166 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
in the field of gender equality and non-
discrimination on the ground of "sex" is a
horizontal policy which is coordinated by
the Ministry of Labour and Social Policy at
national level. A sustainable model for
cooperation is achieved between the
institutions and the social partners and civil
society through their participation in the
National Council on Equality between
Women and Men at the Council of
Ministers. Chairperson of the Council is the
Minister of Labour and Social Policy. The
strategic document of the Bulgarian
government, defining the policy framework
is the National Strategy for Promotion of
Gender Equality for the period 2009 - 2015,
which was adopted in accordance with the
recommendations of the Council of Europe,
the strategic documents of the European
Union and the principles underlying the UN
conventions on human rights and women's
rights. In fulfillment of this basic strategic
document, each year, the Ministry of
Labour and Social Policy develops annual
national action plans for the promotion of
equality between women and men
involving in the consultation process all
responsible authorities for the
implementation of gender equality.
Through national plans it is aimed to
consolidate the efforts of all institutions for
the implementation of measures and
activities to achieve equality between
2004
Amendments to the Rules relating
to reflect structural changes in the
Council of Ministers and to
strengthen national institutional
mechanism for the implementation
of the policy on equality between
women and men.
According to Article 5, para. 4 of
the Decree of CoM No. 5 of
January 18, 2012 to develop
strategic and program documents
of the Republic of Bulgaria to
manage funds under the Common
Strategic Framework of the
European Union for the
programming period 2014-2020,
the composition of the thematic
working groups for program
development for the new
programming period must include
representatives of the CPD.
In addition to all programs in the
new programming period the
horizontal principles of gender
equality and non-discrimination
will be observed.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 167 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
women and men in all spheres of economic,
political and social life. In fulfillment of the
commitments of the Republic of Bulgaria to
the European and international treaties to
which it is a party, and the adopted by the
Council of Ministers Decision No 438 of 25
July 2013 Action Plan for the
implementation of the final
recommendations to the Republic of
Bulgaria made by the UN Committee for
the Elimination of Discrimination against
Women, a Gender Equality Act will be
developed. The aim is to create legal
guarantees concerning measures to ensure
equal opportunities for women and men and
to strengthen institutional mechanisms /
structures for implementation of the state
policy in this area. The Action Plan is
developed by an interdepartmental working
group with the participation of
representatives of all ministries, agencies,
public authorities, social partners, non-
governmental organizations working in the
field of gender equality and organizations
for protection of human rights. The
following measures are provided for based
on the recommendations made:
- preparation of a Draft Law on
Gender Equality;
- strengthening the National
Mechanism on Gender Equality;
- activities to overcome gender
stereotypes and discriminatory
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 168 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
practices;
- thematic studies and analyses;
- of magistrates, investigating
police officers, teachers and
social workers; activities to
promote the participation of
women in different spheres of
social life, etc.
Arrangements for training for staff of
the authorities involved in the
management and control of the ESI
Funds in the fields of Union gender
equality law and policy as well as on
gender mainstreaming.
YES The Action Plan for the implementation of
the final recommendations to the Republic
of Bulgaria made by the UN Committee on
the Elimination of Discrimination against
Women includes the following measures in
accordance with the recommendations, such
as:
training for capacity building of
civil servants on gender equality,
including laws and policies on
gender equality;
conducting awareness and
information activities, incl.
among women from
disadvantaged groups to promote
the UN Convention on the
Elimination of All Forms of
Discrimination against Women
and others.
In the catalog of the Center for
Human Resource Development
and Regional Initiatives, to MLSP
2014 is set to conduct a two-day
training in July on "Practical
guidelines for the implementation
of the UN Convention on the
Elimination of All Forms of
Discrimination against Women" .
The training is designed for senior
management and expert positions
in MLSP and other central and
local administrations, social
partners and NGOs.
The objectives of the training are:
Understanding the UN Convention
on the Elimination of All Forms of
Discrimination against Women,
with final recommendations to the
Republic of Bulgaria made by the
UN Committee on the Elimination
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 169 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
of All Forms of Discrimination
against Women (CEDAW) and the
resulting obligations of the
Republic of Bulgaria;
Improve the capacity of public
administration to implement the
UN Convention on the Elimination
of All Forms of Discrimination
against Women and related
documents;
Building skills to implement an
integrated approach to the
implementation of the Action
Plan;
Improve administrative
competence.
Yet to be fully developed course
content for training.
3. The existence of
administrative capacity
for the implementation
and application of the
United Nations
Convention on the rights
of persons with
disabilities (UNCRPD) in
the field of ESI Funds in
accordance with Council
Decision 2010/48/EC ( 1 )
YES Arrangements in accordance with the
institutional and legal framework of
Member States for the consultation
and involvement of bodies in charge
of protection of rights of persons with
disabilities or representative
organisations of persons with
disabilities and other relevant
stakeholders throughout the
preparation and implementation of
programmes;
YES On 26.01.2012, the National Assembly of
the Republic of Bulgaria adopted the Law
on ratification of the Convention on the
Rights of Persons with Disabilities, which
is the first major human rights treaty of the
21st century policy for people with
disabilities.
By Decision No 868 of 19 October 2012,
the Council of Ministers adopted an Action
Plan containing measures to bring the
Republic of Bulgaria legislation and
In implementing the Action Plan,
an interdepartmental working
group is established to develop an
independent mechanism under Art.
33.2 of the UN Convention on the
Rights of Persons with
Disabilities, including the
establishment of a body and
implementation of an independent
mechanism.
The working group on
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 170 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
policies for people with disabilities in
accordance with the provisions of the
Convention on the Rights of Persons with
Disabilities (2013 -2014).
The Action Plan aims to take effective steps
for the implementation of the Convention
on the Rights of Persons with Disabilities:
Identify key areas in need of legal
reform and take consistent steps on input
requirements of the Convention;
Define and implement a coordination
mechanism and monitoring mechanism
for the implementation of the
Convention, with clearly defined roles,
tasks and responsibilities of the involved
institutions;
Capacity-building of government
officials and experts from different fields
to correctly apply the provisions of the
Convention;
Widely promote the principles of the
Convention in the public and civil society
involvement in the process of its
implementation;
Provide periodic update of activities to
implement the Convention and monitor
the application of the provisions of the
Convention.
coordination for the
implementation of the Action Plan,
development of a coordination
mechanism for monitoring and
independent monitoring
mechanism under Article 33 of the
Convention, as well as for
determination of implementation
authorities continues its operation.
The Action Plan identifies the
participants from various
institutions, as well as the non-
government sector in the field of
integration of people with
disabilities.
The plan shows the various steps
governing leading institutions and
their partners in the development
of concepts for regulatory changes
in various areas covered by the
Convention.
Currently, a review has been
carried out. Therefore were
developed and adopted Concepts
for legislative changes in relation
to the application of article 11 -
Situations of risk and humanitarian
emergencies, article 12 - Equality
before the law, article 14 -
Freedom and personal security,
article 18 - Freedom of movement
and nationality, article 19 -
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 171 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
Independent living and inclusion
in the community and article 24 -
Education from the UN
Convention on the Rights of
Persons with Disabilities and in
implementation of the Action Plan.
The adoption of a concept in terms
of accessibility to the built
environment (article 9) is
forthcoming.
The plan regulates accordingly the
deadlines for implementation of
the measures set out in it.
By Orders No РД01-186 of
28.02.2013, subsequent Order
РД01-353 of 04.23.2013 on the
cancellation of the first and Order
РД01-602 of 08.02.2013 on the
amendment and supplementation
Order РД01-353 of 23.04.2013 of
the Minister of Labour and Social
Policy, an interdepartmental
working group is established on
coordination of the
implementation of the Action Plan,
containing measures to bring the
legal framework and policies for
people with disabilities, in
accordance with the provisions of
the UN Convention on the Rights
of the Persons with Disabilities in
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 172 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
the Republic of Bulgaria
(hereinafter referred to as the
Coordination Group). The
Coordination Group includes
representatives of all government
institutions and NGOs involved in
the policy for people with
disabilities.
Regarding civil society
representatives, in particular
organizations representing people
with disabilities in the Republic of
Bulgaria to cooperate in the
development and implementation
of policy on the integration of
people with disabilities, a National
Council for the Integration of
People with Disabilities is set up
to the Council of Ministers,
chaired by the Minister of Labour
and Social Policy, and deputy
chairpersons - the Deputy Minister
of Labour and Social Policy and
the Deputy Minister of Health and
a representative of the nationally
represented organizations of
people with disabilities and a
representative of the nationally
representative organizations for
people with disabilities, selected
on a rotating basis for a period of
one year. The National Council for
the Integration of People with
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 173 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
Disabilities is an advisory body to
the Council of Ministers, which
shall consist of : representatives of
the state, nominated by the
Council of Ministers, nationally
representative organizations of and
for people with disabilities,
nationally representative
organizations of employees,
nationally representative
organizations of employers and the
National Association of
Municipalities in Republic of
Bulgaria. National Council for the
Integration of People with
Disabilities opinions on all draft
legislation, strategies, programs
and plans affecting the rights of
people with disabilities and their
integration.
According to Article 5, para. 4 of
the Decree of CoM No. 5 of
January 18, 2012 to develop
strategic and program documents
of the Republic of Bulgaria to
manage funds under the Common
Strategic Framework of the
European Union for the
programming period 2014-2020,
the composition of the thematic
working groups for program
development for the new
programming period must include
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 174 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
mandatory representatives of the
CPD and of the nationally
representative organizations of and
for people with
disabilities, recognized by the
Council of Ministers under the
Integration of People with
Disabilities Act.
In addition, all programs in the
new programming period will
include the horizontal principles of
gender equality and non-
discrimination.
Arrangements for training for staff of
the authorities involved in the
management and control of the ESI
Funds in the fields of applicable
Union and national disability law and
policy, including accessibility and the
practical application of the UNCRPD
as reflected in Union and national
legislation, as appropriate;
YES The Action Plan for the purposes of Art. 8
of the Convention "Raising awareness and
changing attitudes on the rights of people
with disabilities" operational objective is set
"Increasing the capacity of local, regional
and central government and others related
to the provisions of the UN Convention." In
this connection seminars are envisaged for
employees of public administration, the
judiciary, doctors and medical
professionals, seminars for teaching staff,
other forms for people with disabilities, etc.
On 11-12 November 2013 in Sofia, a
seminar was held with international
participation on the Convention on the
Rights of Persons with Disabilities and the
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 175 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
Action Plan for its implementation. It was a
place to exchange experiences and best
practices internationally and to present the
Bulgarian experience in the implementation
of the Convention on the Rights of Persons
with Disabilities. The initiative provided an
opportunity to raise the capacity of the
representatives of the administration on the
trends in the policy for people with
disabilities in the context of the
implementation of the Convention on the
Rights of Persons with Disabilities in
Europe and it will ensure implementation of
the measures in the two-year Action Plan
for Implementation of the Convention.
Expansion of the knowledge for the
national institutional framework for the
implementation of the UN Convention on
the Rights of Persons with Disabilities - a
mechanism for coordination, monitoring
and independent monitoring; Studies and
exchange of foreign experience in reporting
to the UN Committee on the Rights of
Persons with Disabilities - principles,
approaches, sources of information,
methods of data processing, analyses;
comprehensive information was received on
the guidelines for the preparation of the
national reports as well as acquiring
practical knowledge and skills approaches
and techniques for the preparation of the
national reports. On 12 and 13 June 2014,
the Center for Human Resource
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 176 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
Development and Regional Initiatives of
MLSP was held a training of officials from
local, regional and central government and
NGO experts working on issues for people
with disabilities "Application the UN
Convention on the Rights of persons with
Disabilities and the participation of local,
regional and central government.". Purpose
of the training was to increase the capacity
of the staff of local, regional and central
government on the provisions of the
Convention on the Rights of Persons with
Disabilities and update their knowledge
related to integration policies for people
with disabilities.
Arrangements to ensure monitoring of
the implementation of Article 9 of the
UNCRPD in relation to the ESI Funds
throughout the preparation and the
implementation of the programmes.
YES The Action Plan for the purposes of Art. 8
of the Convention "Raising awareness and
changing attitudes on the rights of people
with disabilities" operational objective is set
"Increasing the capacity of local, regional
and central government and others related
to the provisions of the UN Convention." In
this connection seminars are envisaged for
employees of public administration, the
judiciary, doctors and medical
professionals, seminars for teaching staff,
other forms for people with disabilities, etc.
On 11-12 November 2013 in Sofia, a
seminar was held with international
participation on the Convention on the
Rights of Persons with Disabilities and the
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 177 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
Action Plan for its implementation. It was a
place to exchange experiences and good
practices internationally and to present the
Bulgarian experience in the implementation
of the Convention on the Rights of Persons
with Disabilities. The initiative provided an
opportunity to raise the capacity of the
representatives of the administration on the
trends in the policy for people with
disabilities in the context of the
implementation of the Convention on the
Rights of Persons with Disabilities in
Europe and it will ensure implementation of
the measures in the two-year Action Plan
for Implementation of the Convention.
Expansion of the knowledge for the
national institutional framework for the
implementation of the UN Convention on
the Rights of Persons with Disabilities - a
mechanism for coordination, monitoring
and independent monitoring; studies and
exchange of foreign experience in reporting
to the UN Committee on the Rights of
Persons with Disabilities - principles,
approaches, sources of information,
methods of data processing, analyses;
comprehensive information was received on
the guidelines for the preparation of the
national reports as well as acquiring
practical knowledge and skills approaches
and techniques for the preparation of the
national reports.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 178 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
4. The existence of
arrangements for the
effective application of
Union public procurement
law in the field of the ESI
Funds.
Partially Arrangements for the effective
application of Union public
procurement rules through
appropriate mechanisms;
NO National Strategy for the Development of
the Public Procurement Sector in Bulgaria
for the period 2014 – 2020.
http://www.government.bg/cgi-bin/e-
cms/vis/vis.pl?s=001&p=0211&n=99&g
Adopted with CoM Decision
498/11.07.2014.
The strategy forsees measures for
improving effectiveness in awarding of
contracts and establish guarantees of
compliance with EU legislation in the field.
EU legislation on public procurement
(Directives 2004/18/EC, 2004/17/EC,
Directives 89/665/EEC, 92/13/EEC and
2007/66/EC and 2009/81/EC and the
Regulations associated with their
implementation) has been fully
implemented in the PPA. Different from the
PPA, the regulations on public procurement
contain:
• Rules for the Implementation of the PPA;
• Ordinance on competitions
projects in the planning and investment
design, approved by Decree № 75 of 2009
of the Council of Ministers, promulgated
SG. No. 26 of 2009;
• Ordinance under Art. 13, para 3 of the
Measures in this direction will be
further strengthened.
It provides measures to use a
uniform practice among the Public
Procurement Agency, MA of OP,
National Audit Office, SFIA, CPC
and SAC and coordination of their
activities. It will also include
measures to further expand the
scope of the ex-ante control by the
Public Procurement Agency for
effective cooperation between
supervisory authorities in order to
standardize the practices and
streamlining ex-post control.
There will also be measures to
increase the effectiveness of
judicial protection.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 179 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
Public Procurement Act (PPA) for the
criteria and procedures for determining the
presence of vital national interests in
security and defense within the meaning of
Art. 346 of the Treaty on the Functioning of
the European Union (TFEU) and the
procedures to sign contracts, approved by
Decree № 180 of 22.08.2013, promulgated
SG № 75 of 2013.
http://www.aop.bg/fckedit2/user/File/bg/No
rmativna%20baza/ZOP_15_02_2013.pdf
http://www.aop.bg/fckedit2/user/File/bg/No
rmativna%20baza/PPZOP_09032012.pdf
http://www.aop.bg/fckedit2/user/File/bg/No
rmativna%20baza/Naredba_konkursi.pdf
http://www.aop.bg/fckedit2/user/File/bg/No
rmativna%20baza/Naredba_27082013.pdf
In relations to amendments to the public
procurement legislation - the PPA in effect
has been adopted in 2004. Since then five
major amendments are made. Three of them
introduce the applicable European
Directives (Directive 2004/17/EC and
Directive 2004/18/EC, Directive
2007/66/EC and Directive 2009/81/EC),
while the other two - the preliminary
control by the Public Procurement Agency
and the approved government concept
related to changes in public procurement
legislation. Apart from those, a number of
amendments have been made that comprise
specific provisions of the law. The
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 180 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
definition of the public law organization in
the PPA is in full compliance with the
applicable directives. Public law
organizations are specifically regulated in
Art. 7 § 3 of the PPA as the term is defined
in § 1, item 21 of the Additional provisions
to the PPA.
In terms of institutional arrangements -
there are several bodies that operate in the
field of public procurement. These are:
• Public Procurement Agency - a national
body which supports the Minister of
Economy and Energy to implement the
policy in the field of public procurement,
issues methodological guidelines under the
PPA, ex-ante control over certain
procedures, etc.
• OPs Managing Authoritie who also
supervises the public procurement
procedures and gives guidance to
contracting authorities - beneficiaries on the
operational programs.
• Bulgarian National Audit Office and the
Public Financial Inspection Agency -
bodies to carry out further control over the
implementation of the PPA.
• CPC and SAC - appeal bodies that settles
disputes on the legality of the public
procurement procedures.
Although some mechanisms for imposing a
uniform practice, it is necessary to work for
a uniform interpretation of the law by those
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 181 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
bodies.
There have been introduced different forms
of control at all stages of the public
procurements, including at the stage of their
implementation, as well as procedures for
the imposition of a uniform practice.
Since 2009, the Public Procurement Agency
exercises ex-ante control over procedures
for awarding public contracts financed in
full or in part by the EU funds (Art. 19, para
2, item 22 and Art. 20a of the PPA). The
amendments to the Public Procurement Act,
in force since 26.02.2012, this control is
carried out in two phases - before and after
the announcement of the procedure, as there
was introduced a mechanism for feedback
by monitoring the implementation of the
recommendations made.
Pursuant to Art. 19, para 2, item 1 of the
PPA, the Executive Director of the Public
Procurement Agency issues a general
methodological guidance on the application
of the law and its implementing rules.
When these guidelines are agreed with the
controlling authorities under law -
Bulgarian National Audit Office and the
State Financial Inspection Agency (SFIA),
they become mandatory for them in
carrying out their checks.
Methodological guidelines are published on
the Public Procurement Portal.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 182 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
http://rop3-
app1.aop.bg:7778/portal/page?_pageid=93,
1&_dad=portal&_schema=PORTAL
Article 123, para 1 of the PPA provides that
the Bulgarian National Audit Office and the
State Financial Inspection Agency shall
carry out further control over the contracted
public procurements. PPA provides an
administrative penalty part (art. 127 - Art.
133 of PPA). It provides for violations for
which the contracting authorities are
imposed with fines.
http://www.aop.bg/fckedit2/user/File/bg/No
rmativna%20baza/ZOP_15_02_2013.pdf
Every Ops Managing Authority provides a
procedure for ex-ante, ongoing and ex-post
control concerning the public procurement
procedures.
Measures have been taken to address the
main types of errors found in procurement,
as follows:
Decree № 134 of the Council of Ministers
of 5.07.2010 introduces a Methodology for
determining financial corrections to be
applied to expenses associated with the
implementation of operational programs co-
financed by the structural instruments of the
European Union, the European Agricultural
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 183 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
Fund for Rural Development and the
European Fisheries Fund. The authorities
responsible for the implementation of the
methodology are the contracting authorities
(MA/ IB) under the operational programs
financed by SCF RDP OP ―Fisheries ― and
the audit bodies on SCF, EAFD and EFF.
Decree № 18 of the Council of Ministers of
4.02.2003 establishes a Council to
coordinate the fight against infringements
affecting the financial interests of the
European Union.
Decree № 285 of the Council of Ministers
of 30.11.2009 adopts the Ordinance laying
down the procedures for the administration
of irregularities in funds, instruments and
programs financed by the European Union.
http://www.eufunds.bg/bg/page/119
Instructions issued by the Minister of
Finance - ДНФ 7/22.12.2010 regulates the
process associated with the write-off and
recovery of undue payments and
overpayments and unduly or improperly
spent funds on projects co-financed by the
Structural and Cohesion Funds of the
European Union.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 184 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
The guidelines are published at:
http://www.minfin.bg/bg/page/10?q=%D0
%94%D0%9D%D0%A4
OPs Managing Authorities keep records of
financial corrections imposed in the
implementation of public procurement
procedures. Each MA disposes of specific
employees who have in their job
descriptions responsibilities on public
procurement.
The Law Amending and Supplementing the
PPA, promulg. SG, issue 40, 2014, in force
since 01.07.2014, extends of the ex-ante
control carried out by the Public
Procurement Agency regarding procedures
for public works contracts financed with
funds from the national budget and above a
certain threshold.
PPA regulates the two-instance appeal of
the decisions of contracting authorities
issued in relation to procedures for the
award of public contracts. First instance is
the Commission for Protection of
Competition, which is an administrative
body, and the second and final instance is
the Supreme Administrative Court. There is
a two months period for both instances to
take a decision. In terms of the CPC –
there is no delay in hearing the cases. In
terms of SAC – there is some delay, taking
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 185 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
into account that the statutory one month
period to rule is inconsistent with the rules
of procedure for dealing with cases of this
Court.
http://www.aop.bg/fckedit2/user/File/bg/No
rmativna%20baza/ZOP_15_02_2013.pdf
The planned action "Review of the appeal
system and proposals for its optimization
(eg. Safeguards against abuse of the right of
appeal, etc.)" has been completed.
Received were letters from the responsible
authorities (CPC and SAC) with proposals
to streamline the system of appeals. With
the suggestions taken the implementation of
activities 14.1, measure 14 of the
Implementation Plan of the National
Strategy for development of the sector
procurement in Bulgaria for the period
2014-2020 year will be accepted as
completed.
Proposals of CPC and SAC will be
discussed in connection with the
preparation of new legislation on public
procurement.
Arrangements which ensure
transparent contract award
procedures;
YES http://rop3-
app1.aop.bg:7778/portal/page?_pageid=93,
408251&_dad=portal&_schema=PORTAL
Measures in this direction will be
further strengthened. In this
connection, regarding the
introduction of e-procurement – in
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 186 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
http://rop3-
app1.aop.bg:7778/portal/page?_pageid=93,
1488254&_dad=portal&_schema=PORTA
L&url=687474703A2F2F7777772E616F70
2E62672F657365617263685F7070322E70
6870
http://www.aop.bg/fckedit2/user/File/bg/No
rmativna%20baza/ZOP_15_02_2013.pdf
http://www.aop.bg/fckedit2/user/File/bg/No
rmativna%20baza/PPZOP_09032012.pdf
http://rop3-
app1.aop.bg:7778/portal/page?_pageid=93,
1&_dad=portal&_schema=PORTAL
Contracts with a value below the thresholds
for applicable European directives are
awarded under procedure provided for in
the PPA (art. 14, para 1 of the PPA). The
procedure is similar to that set out in the
European Directives, with some
exemptions.
For the award for contracts of very low
values, the PPA provides a procedure that
respects the principle of publicity and
transparency (Article 101a -101 g of the
PPA). According to this procedure, the
contracting authorities are required to
collect bids by publishing public calls on
the Public Procurement Portal, which is
supported by the Public Procurement
the National Strategy for the
Development of the Public
Procurement Sector in Bulgaria for
the period 2014 – 2020 envisages
by the end of 2016 to introduce
entirely electronic communication
to the stage of e-offer, including.
For this purpose, a contract for
services was signed between the
European Bank for Reconstruction
and Development (EBRD) and the
Ministry of Economy and Energy,
which was ratified by the 42th
National Assembly, by law,
adopted on 24 January 2014,
promulgated SG No. 11 2014. As
a result of the implementation of
the contract, it will be proposed a
model for e-procurement based on
European best practices and
consistent with national
specification.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 187 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
Agency. There is a minimum period for
public access to the call, which may not be
shorter than 7 days. Thus, all stakeholders
have the opportunity to see the contracts
which the contracting authorities intend to
award.
Decree № 69 of 11 march 2013 provides
the conditions and procedures for
determining the contractor by candidates for
grants or beneficiaries of contracted grants
from the Structural Funds and the Cohesion
Fund of the European Union, Joint
Operational Programme ―Black Sea Basin
2007 - 2013", financed by the European
Instrument for Neighbourhood and
Partnership, Financial Mechanism of the
European Economic Area and Norwegian
Financial Mechanism.
The principle of publicity and transparency
is also guaranteed by the Public
Procurement Register (PPR), which is
maintained by the Public Procurement
Agency (Article 21 - 22a of the PPA).
The Register is part of the Public
Procurement Portal and is a unified
electronic database, which contains
information about all open public
procurement procedures, the results of their
award and implementation. Besides the
information required under the European
directives and regulations (notice for OP,
contract information, etc.). PPR also
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 188 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
contains information that stems from the
national requirements (information on the
implementation of the contract, the decision
to negotiate without notice, information on
the progress of appeal). http://rop3-
app1.aop.bg:7778/portal/page?_pageid=93,
158263&_dad=portal&_schema=PORTAL
The Public Procurement Portal also
contains public calls based on which
contracting authorities collect bids under
Art. 101a – 101g of PPA.
http://rop3-
app1.aop.bg:7778/portal/page?_pageid=93,
1488254&_dad=portal&_schema=PORTA
L&url=687474703A2F2F7777772E616F70
2E62672F657365617263685F7070322E70
6870
Contracting authorities are able to provide
through the Public Procurement Portal
documentation electronically, to exchange
questions and answers with the participants
electronically and publish clarifications.
Through the Public Procurement Portal is
given the opportunity to fully communicate
in electronic form between the participants
and contracting authorities, through to
preparation and submission of the bid.
http://rop3-
app1.aop.bg:7778/portal/page?_pageid=93,
1&_dad=portal&_schema=PORTAL
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 189 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
PPA regulates a number of additional
measures relating to publicity and
transparency. Some of them are related to:
the ability to attract external persons as
members of the committees who are from a
list maintained by the Public Procurement
Agency, public opening of tenders and
envelopes with the price offered, the
announcement of the evaluation of tenders
by other indicators - under criterion "most
economically advantageous tender",
publication of information on opening
negotiated procedures without notice and
for their awarding, posting opinions on
progress monitoring of negotiated
procedures without notice and information
on the implementation of contracts, etc.
http://rop3-
app1.aop.bg:7778/portal/page?_pageid=93,
1488254&_dad=portal&_schema=PORTA
L&url=687474703A2F2F7777772E616F70
2E62672F657365617263685F7070322E70
6870
According to the recent amendments in the
Public Procurement Act, promulgated. SG.
40 of 2014, contracting authorities are
obliged to publish at its buyer profile all
documents related to the implementation of
these procedures - procurement contracts,
additional agreements thereto, information
about each payment, the public calls, the
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 190 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
opinions of the Executive Director of the
Agency on requests of the contracting
authority and other useful information. The
obligation to publish these documents is set
in Art. 22b of the PPA and enters into force
from 10.01.2014.
Arrangements for training and
dissemination of information for staff
involved in the implementation of the
ESI funds;
NO •According to reports of the Public
Procurement Agency and OPs Managing
Authorities, a number of suitable trainings
for MA experts are provided on the
effective implementation of the public
procurement legislation, avoidance of the
risk of imposing financial corrections and
administrative penalties in the conduct of
award procedures.
•According to information from OPs
Managing Authorities through their
websites they provide to interested parties
the necessary information, incl. via
developed documents, manuals,
instructions, handbooks, etc. in the field of
public procurement.
•In the National Strategy for the
• For all operational
programs financed by the
Structural and Cohesion Fund is
used a unified Management
Information System (MIS). The
system is fully implemented as a
web based application and stores a
complete history of all changes in
the data and enables the generation
of historical references and full
traceability of the chronological
sequence of changed records, each
of which contains evidence of
actions performed.
• Within State Fund
Agriculture was developed and is
currently functioning an Integrated
Administration and Control
System (IACS). The access,
operation and storage of
information in the system is
applied in accordance with the
information policies of State Fund
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 191 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
Development of the Public Procurement
sector it is envisaged to include activities
related to the training of persons involved
in the preparation and conduct of public
procurement procedures, as well as officials
from the Public Procurement Agency and
the OPs Managing Au thorities.
Public Procurement Agency supports
centralized information system (Public
Procurement Portal), which gives access to
all aspects of public procurement. It
provides information on:
• legislation in the field of public
procurement;
• Public Procurement Register (PPR);
• general methodological guidelines
concerning the application of the law;
• issued practical guidance related to
completing the document templates, batch
creation and a unique PPR number, sending
information to the agency, etc.;
• list of the entities to be used as external
experts;
• published public calls;
• opinions of the preliminary control of
negotiated procedures without notice;
Agriculture.
Information and Systems for
Management of EU funds
Directorate to the Administration
of the Council of Ministers
supports a Single Information
Portal through which information
is provided for all operational
programs, sample documents, calls
for project proposals, etc.
Information from the Central
Coordination Unit on the
trainings related to public
procurement in MAs of OPs
(2013):
For MA of OPHRD were
conducted 10 training sessions, the
total number of trained employees
is 115.
For IB – Employment Agency
were conducted 3 trainings, the
total number of trained employees
is 10.
For IB - ASA is conducted 1
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 192 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
• other information.
The National Strategy for the Development
of the Public Procurement Sector in
Bulgaria for the period 2014 – 2020
envisages measures for effective
cooperation between the authorities
responsible for functions related to the
methodology and control of public
procurement with a view to establishing a
uniform practice.
training, the total number of
trained employees is 2.
For IB - MES were conducted 11
training sessions, the total number
of trained employees is 11.
From February to October 2013
were 65 times in Bulgaria or
abroad of experts in the MA and
IB OPHRD participated in
trainings on implementation of the
PPL and introduction to current
developments within the European
procurement rules. For November
no planned training on the topic.
Through official correspondence
and the website of the MA is
submitted required information
through manuals, instructions and
guides. In Handbook of HRD OP
is the declaration of the officers
familiar with the changes;
guidelines have been prepared
with the most common errors in
the award.
In 2012 16 employees of the OPE
MA participated in 45 training
courses on to procurement issues
and from the IB 30 employees
participated in three training
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 193 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
sessions.
Since the beginning of 2013 was
conducted on public procurement
were trained 16 experts from the
MA in 4 courses and 4 experts
from IB in 1 course.
In 2014 5 experts from GD ―OPE‖
at MOEW have participated in 3
trainings on public procurement.
In the matters of PP is engaged
department ―Ex-post control and
procedural representation‖ after
the restructuiring of IB and MA of
OPE into GD ―OPE‖ in the end of
March 2914.
MA OPE has posted on its web
site a number of guidelines and
supporting documents to
beneficiaries related to public
procurement (mainly published in
"Documents / Manuals /
Instructions / Manuals):
1. Most common violations related
to the award and implementation
of contracts:
http://ope.moew.government.bg/fil
es/useruploads/files/documentatio
n/ukazania/narushenia_obshtestve
ni_porachki.pdf
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 194 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
2. Documents relating to errors
and violations and current issues
of the PPA:
http://ope.moew.government.bg/b
g/pages/dopuskani-greshki-i-
narushenia/67 #1
3. In section manuals, guidelines,
manuals / Implementation of
projects financed by the OPE
- Additional section 1
"Procurement" with additional
supplies, incl. model forms
http://ope.moew.government.bg/b
g/pages/narachnitsi-ukazania-
rakovodstva/66#1
As a new measure to help increase
the capacity of beneficiaries in the
field of public procurement,
quarterly Managing Authority will
prepare a newsletter with practical
examples and descriptions of the
different types of violations found
during verification. The newsletter
will be sent by email and will be
posted on the official website of
the program. The first newsletter
was published in July 2014
(http://ope.moew.government.bg/b
g/pages/dopuskani-greshki-i-
narushenia/67#1). The second one
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 195 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
is under preparation.
Various trainings on Public
Procurement Act for the period
from 2007 to present have visited
50 officials from OPT.
In 2012 there were 3 trainings on
procurement, which have trained a
total of 9 employees MA
OPDCBE.
Planned are two trainings which
will train 64 employees of MA
OPDCBE.
Arrangements for training is
regulated by Chapter 18 of the
Manual of Operational Programme
"Competitiveness" and the Internal
Rules on the organization and
conduct of training and
qualification of employees in
MEE.
Earlier this year, the MA approve
annual training plan for employees
which shall be developed based on
their personal learning plans.
Training of the "Public
procurement financed by EU
funds 2013" and in practice of the
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 196 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
application of the Public.
Pending the training on "Tender
procedures PPA regulations on
public procurement."
period 2008-2012 were conducted
7 trainings on procurement of a
total of 23 employees from OPTA
MA. OPTA MA carried out
preliminary control procedures
under the LPP funded OPTA with
a view to identifying any gaps still
at the stage before the start of the
procedure; 2. OPTA MA
maintains constant communication
with beneficiaries and holds
regular meetings with them
regarding the progress of the
projects / implementation of
activities, which includes a
discussion of current and planned
procedures under the PPA.
10 employees of the MA-OPAC
have undergone four courses
related to public procurement.
Ahead are two trainings on
procurement.
In the period 2011 - October 2013
were held 18 trainings for
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 197 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
beneficiaries - municipal, regional,
central administration and the
judiciary, through which
information and practical exercises
are carried out on the application
of the rules governing
Procurement under projects
financed by ESF-OPAC. By the
end of 2013 provides for an
additional 2 pieces trainings for
beneficiaries.
Through its website, the MA
provides information on public
procurement, including in the form
of documents elaborated on:
• Examples of indicators for
assessing the bids using the
criterion of "most economically
advantageous tender" when
awarding service training;
• Procedure for ex-ante control of
procurement funded projects
OPAC;
• Common Errors and
irregularities in the drafting of
documentation and tendering;
• Instructions for completing the
schedule of public procurement;
• Examples of violations;
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 198 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
• Guide for beneficiaries.
Within OPAC taken and
implemented are the following
measures to improve
communications available
between the managing authority
and the beneficiaries in the
implementation of the Public
Procurement Act:
• regular trainings to beneficiaries
after the conclusion of contracts;
• providing advice and
clarification of the beneficiaries;
• maintenance of the special
section "For beneficiaries" on the
website of the program.
Various trainings on Public
Procurement Act for the period
from 2009 have participated 71
employees MA of OPRD. Planned
training on procurement of 28
employees of the MA of OPRD.
Eight experts from the Directorate
General "Programming of
Regional Development" took part
in three training sessions on the
following topics:
• Practice of the Court of Auditors,
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 199 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
APFI, CPC and PPA on
implementing PPL;
• Practice and changes in public
procurement in 2013;
• ABC of public procurement.
Information for 2014
Two experts from DG
"Programming of Regional
Development" took part in training
on "How to assign a lawful and
effective procurement"
Conducted an internal workshop
of experts from DG "Programming
of Regional Development" on
"New approach of the audit
authority on procurement from
beneficiaries of OP" Regional
Development "2007-2013
Six experts from DG
"Programming of Regional
Development" took part in two
training sessions on the following
topics:
- "Practice of Public Procurement"
- Expected changes in the PPA.
Practical problems of procedures
for the award of the OP. Practice
of Public Procurement Agency. "
- "Act amending the Public
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 200 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
Procurement Act (promulgated
SG. 40 2014)" - analysis and
interpretation. Preparation and an
open procedure. New practices of
the CPC and SAC in application
of the law. "
Forty-three experts from the
Directorate General
"Programming of Regional
Development" took part in three
training sessions on the following
topics:
- "Up-to-date amendments to the
Law on Public Procurement"
- Eighteenth national seminar
"Practice of public procurement" -
"Recent amendments to the PPA.
Process management in
procurement under the new rules.
Practice of the Public Procurement
Agency";
- Seminar on "Improvement of the
control systems in MA to ex-ante
and ex-post control procedures for
procurement by the Beneficiary
under the Operational Programme
"Regional Development" 2007-
2013
Eight experts from GD ―PRD‖
participated in three training
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 201 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
sessions on:
- „Act amending the Public
Procurement Act (promulgated
SG. 40 2014)" - analysis and
interpretation. Preparation and an
open procedure. New practices of
the CPC and SAC in application
of the law.";
- „New moments in the
control and appeal of PP‖;
- „Improvement of control
systems in MA in relation to
execute ex-ante and ex-post
control procedures for
procurement by the Beneficiary of
the Operational Programme
"Regional Development" 2007-
2013"
In the period 28-29.07.2014, MA
organized and conducted a
training seminar for MA staff and
practical training of beneficiaries
on lawful public procurement with
participation of representatives of
the audit unit of DG "Regional and
urban policy" and representatives
of DG "Internal Market and
Services" by the EC and of the
Public Procurement Agency.
Seminar participants were
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 202 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
presented best practices and also
errors in the procurement, taking
preventive actions to prevent
violations.
OPRD MA maintains systems to
exchange information to help
participants in the implementation
and monitoring of the program as
follows:
• Issuing guidance to assist the
beneficiaries, such as general and
in relation to specific cases.;
• Maintain an updated summary of
the practice of admitted violations
in awarding obshtestveniporachki
established by the audit authorities
to audit the MA of OPRD and
related recommendations,
preparing updated information
published on the website of
OPRD, and is provided as
indication to the experts MA
performing pre and post-control.
The information is updated
according to the audits;
• Established practice for
continuous exchange of
experience and good practice
between experts from the RE
department "Zorn" and department
«Monitoring» in connection with
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 203 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
implementing the preliminary and
follow-up.
Regarding procurement 4 officers
of MA RDP participated in
trainings.
IB MA of OP Fisheries - In 2010 a
study was conducted in
conjunction with PPL for
employees from the "Fisheries and
aquaculture.''
In 2013, training in connection
with the PPA will involve two
experts from the same department.
In 2012, six employees of MA
RDP trained on PPL that are
organized by "European Training
Center" Ltd.; also in 2012, were
trained 29 employees MA RDP on
PPL training being organized by a
contractor on a project funded
under the measure "Technical
assistance" 'RDP (2007-13);
State Fund "Agriculture" - During
2012 and early 2013, seven people
from the "Control of procurement
and implementation of local
development strategies" have been
trained concerning the PPA. At the
end of 2011, all employees of the
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 204 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
department CPILDS responsible
for processing procedures on
procurement have undergone
training related to the upcoming
changes in the PPA subsequently
entered into force on 26.02.2012.
NAFA
Employees of the Executive
Agency for Fisheries and
Aquaculture have undergone
trainings related to the application
of the procurement rules of the EU
at all relevant levels. In addition,
at the end of November 2013
provided is training on "Public
Procurement Act - a practice of
application".
Measures to improve the
communication channels between
the managing authorities and
beneficiaries in the
implementation of the Public
Procurement Act will be included
in the Programme for Maritime
Affairs and Fisheries from 2014 to
2020.
Public Procurement Agency
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 205 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
During the period 2007 - 2013 the
Public Procurement Agency has
organized and participated in
conducting 85 training of persons
involved in the process of
procurement.
By Decision № 41 from 27.12.
2012 is approved for funding
under the Operational Programme
"Technical Assistance" a project
entitled "Strengthening the
capacity of the Public Procurement
Agency, improving the system of
ex-ante control procedures
financed by EU funds' with
beneficiary the Public
Procurement Agency. The project
aims to increase the efficiency of
the Agency ex-ante control on
procedures financed by the EU.
The project provides 4 courses in
the field of public procurement of
200 employees of the Managing
Authorities, Intermediate Bodies
and the Public Procurement
Agency.
Information for 2014:
Three of the planned project
trainings are held, having trained
128 employees.
In annex to the OPTA project
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 206 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
contract is provided an option for
organizing and conducting two
additional training for 80 people.
Agency‘s employees participated
as lecturers in three trainings
organized by the IPA.
In relation of the latest changes in
PPL, in force since 01.07.2014 г.,
PPA experts participated as
lecturers in 14 trainings as 11 of
them are organized by IPa, 2 by
MRD and 1 from National
Association of Labor-Productive
Cooperatives.
Arrangements to ensure
administrative capacity for
implementation and application of
Union public procurement rules.
NO http://rop3-
app1.aop.bg:7778/portal/page?_pageid=93,
168247&_dad=portal&_schema=PORTAL
The Public Procurement Agency is
established with the Public Procurement
Act (promulgated in SG, issue 28 of 2004,
effective from 01.10.2004). It is a legal
entity with the status of an Executive
Agency to the Minister of Economy and
Energy and assist him in the
implementation of the state policy in the
field of public procurement.
The functions of the Agency are described
in Art. 19, para. 2 of PPA.
The most important of them are:
At present, in order to ensure
personnel for preliminary control,
the Agency implements a project
under OP Technical Assistance
that ensures funds for 10
additional staff positions. It is
envisaged in the draft Partnership
Agreement, the Public
Procurement Agency to be
included as a beneficiary under OP
Good Governance to strengthen
the administrative capacity of the
Agency.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 207 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
• drafting of legislation in
the field of public procurement for the
implementation of European Directives and
Regulations and national rules;
• methodological support
by giving opinions on inquiries of
contracting authorities;
• issuing common
methodological guidance on the application
of PPA and the rules for implementation of
PPA;
• ex-ante control of
procedures for the award of public contracts
financed entirely or partially under the EU
funds;
• opinions of the ex-ante
control of negotiated procedures without
notice;
• maintaining the Public
Procurement Register (PPR) and the Public
Procurement Portal etc.
Each MA has certain employees who have
in their job descriptions responsibilities on
public procurement issues. Adequate
training on various topics are held.
The National Strategy for the Development
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 208 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
of the Public Procurement Sector in
Bulgaria for the period 2014 - 2020
provides measures for strengthening and
stability of the administrative capacity of
the Public Procurement Agency,
According to Art. 19, para. 2, items 1 and 2
of the PPA, the Public Procurement Agency
issues general methodological guidelines to
the unification of practices in the
application of PPA and the rules on the
implementation of PPA and provides
methodological support to contracting
authorities by providing opinions on their
queries. Methodological guidelines are
published on the Public Procurement Portal.
According to the changes in PPA, effective
from 10.01.2014, the contracting authorities
are obliged to provide in the preparation of
technical specification and assessment
methodology the participation of at least
one expert who has the professional
competence related to the subject of the
order. When you do not have such a
specialist, they can provide such a person
from the list of external experts, supported
by the PPA. In this list are included
persons, proposed by the professional
associations and organizations in the
respective sector or by the bodies as per
art.19 of Law on Administration or those
who have submitted an application for self-
Information from the CCU on the
administrative capacity of the MA
OP (2013):
The OPT has 8 employees who
have in their job descriptions
responsibilities on public
procurement.
In MA OPDCBE has 119
employees who have responsibility
on public procurement.
In OPTA MA has 2 employees
who have responsibilities related
to public procurement.
The OPAC MA has six employees
who have responsibilities on pa
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 209 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
registration.
According to information by OPs Managing
Authorities through their websites they
provide to interested parties the necessary
information, incl. under the form of
developed documents, manuals,
instructions, guidance and more in the field
of public procurement.
The National Strategy for the Development
of the Public Procurement Sector in
Bulgaria for the period 2014 – 2020
provides measures to ensure technical
assistance to those who apply the rules on
public procurement.
procurement.
MA RDP - In job descriptions of
employees in "Legal and
information services" has included
responsibilities in relation to
public procurement. Ministry of
MA of OP Fisheries (Directorate
"Fisheries and Aquaculture" State
Fund "Agriculture") - no
employees whose job descriptions
to include responsibilities relating
to public procurement.
In the OP MA - the "Rural
Development" Directorate - has no
employees with responsibilities
concerning the issues of public
procurement;
State Fund "Agriculture" - Paying
Agency: In the job descriptions of
the 49 employees of the SFA-PA,
the "Implement measures to Rural
Development''," Control over the
procurement and implementation
of local development strategies "is
written handling public
procurement procedures.
In MA of OPRD has 89
employees who have responsibility
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 210 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
on public procurement.
In Manual for the management and
implementation of the Operational
Programme "Regional
Development" 2007-2013 Chapter
20 Technical Assistance are
written procedures for the award
of public procurement orders for
the provision of grants for projects
with specific beneficiary
departments DG "RDP" under the
PPA. There are teams for the
development of the documentation
for the award of the OP. Schedules
is how to control the procurement
process conducted by the
departments of DG "RDP" which
takes place on various stages of
conducting the procedure.
As of 04/28/2014, the adopted
amendments to the checklist for
performing the preliminary and
follow-up of open procedures and
negotiated procedures without
notice; checklist to follow when
contracting under Chapter "Eight"
and the PPA / most used / -
Version 9.1. Changes are made to
strengthen control mainly
concerning the legality of the
removal of participants/candidates
in the procedures and the legality
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 211 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
of the assessment methodology
and their application to the work
of Combs for review, evaluation
and ranking of bids. The control of
Expert 2 is strengthened - in terms
of conformity with technical
specifications from the
documentation and requirements
in public procurement to those in
grant contracts and the subsequent
need for compliance of offers with
these requirements.
In connection with the violations
found during routine audit mission
from 04.07.2014 -11.04.2014, in a
letter from DG "Regional and
urban policy", European
Commission, received on
06/03/2014, in OPRD Managing
Authority, having regard to
identified violations committed by
OPRD beneficiaries in
procurement that provides the
basis for determining financial
corrections and in view of the need
to improve the control systems, the
MA of OPRD has taken the
following actions:
- on 20.06.2014 were adopted
amendments to Chapter 13
Monitoring of Handbook on
MIOPRD (effective from
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 212 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
01.07.2014 years), including with
respect to: checklists for
implementing ex-ante and ex-post
control of procedures for the
award of public procurement;
checklist for ex post control in
procurement by public invitation
under Chapter Eight "a" of PPA –
Version.
- conducting internal training of
MA experts responsible for
conducting ex-ante and ex-post
control, work with advanced
checklists of Handbook on
MIOPRD-26-27.06.2014 on;
- Supplement the directives issued
to beneficiaries published on
25.06.2014 on the website of MA
of OPRD, in order to prevent
irregularities in procurement;
- Practical training of beneficiaries
in relation to the new control
mechanisms implemented by the
MA of OPRD.
- In the period 28-29.07.2014, MA
organized and conducted a training
seminar for MA staff and practical
training of beneficiaries on lawful
public procurement with
participation of representatives of
the audit unit of DG "Regional and
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 213 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
urban policy" and representatives
of DG "Internal Market and
Services" by the EC and of the
Public Procurement Agency.
Seminar participants were
presented best practices and also
errors in the procurement, taking
preventive actions to prevent
violations.
- on 28.07.2014 was held technical
meeting at expert level with
participation of Head of MA of
OPRD, EC representatives, the
national audit body and the
certifying authority on which were
discussed the concrete steps that
need to be undertaken for
restarting of payments on the two
axis of the programme,
recommendations were made for
supplementing control sheets for
ex-post control with control
questions regarding risk spheres in
awarding;
- MA of OPRD elaborated an
analysis of statements on
violations in awarding of PP by
beneficiaries with view and
readiness for constant improving
of the management and control
system.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 214 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
- execution of contracts for the
provision of specialized legal
services for MA of OPRD in order
to support the process of ex-ante
and ex-post-control, the
administering of denunciations and
support of the MA in the case of
proceedings under Art. 100 of
Regulation № 1083/2006 by the
Council.
MA OPHRD - 6 employees with
responsibilities relating to issues
of procurement and 32 employees
with responsibilities related to
inspection activities, some of
which are public procurement
procedures;
IB - EA - 15 employees with
responsibilities in matters of
public procurement;
IB - SAA - 34 employees with
responsibilities in matters of
public procurement;
IB - Ministry of Education and
Science- 25 employees with
responsibilities related to public
procurement issues.
In addition to the above control
mechanisms, information entities
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 215 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
as part of the control and the
involvement of external expertise
where such missing in the OP.
In 2012 16 employees of the OPE
MA participated in 45 training
courses on to procurement issues
and from the IB 30 employees
participated in three training
sessions.
Since the beginning of 2013 was
conducted on public procurement
were trained 16 experts from the
MA in 4 courses and 4 experts
from IB in 1 course.
In 2014 5 experts from GD ―OPE‖
at MOEW have participated in 3
trainings on public procurement.
In the matters of PP is engaged
department ―Ex-post control and
procedural representation‖ after
the restructuiring of IB and MA of
OPE into GD ―OPE‖ in the end of
March 2914.
MA OPE has posted on its web
site a number of guidelines and
supporting documents to
beneficiaries related to public
procurement (mainly published in
"Documents / Manuals /
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 216 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
Instructions / Manuals):
1. Most common violations related
to the award and implementation
of contracts:
http://ope.moew.government.bg/fil
es/useruploads/files/documentatio
n/ukazania/narushenia_obshtestve
ni_porachki.pdf
2. Documents relating to errors
and violations and current issues
of the PPA:
http://ope.moew.government.bg/bg
/pages/dopuskani-greshki-i-
narushenia/67 #1
3. In section manuals, guidelines,
manuals / Implementation of
projects financed by the OPE
- Additional section 1
"Procurement" with additional
supplies, incl. model forms
http://ope.moew.government.bg/bg
/pages/narachnitsi-ukazania-
rakovodstva/66#1
As a new measure to help increase
the capacity of beneficiaries in the
field of public procurement,
quarterly Managing Authority will
prepare a newsletter with practical
examples and descriptions of the
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 217 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
different types of violations found
during verification. The newsletter
will be sent by email and will be
posted on the official website of
the program. The first newsletter
was published in July 2014
(http://ope.moew.government.bg/b
g/pages/dopuskani-greshki-i-
narushenia/67#1). The second one
is under preparation.
5. The existence of
arrangements for the
effective application of
Union State aid rules in
the field of the ESI
Funds..
YES Arrangements for the effective
application of Union State aid rules; YES The national legislation on state aid is
available at:
http://stateaid.minfin.bg/
1. State Aid Act (SAA) - Art. 5, 7,
9, 11, 12, 13; (CoM Decree 86/2006 in
effect since 1.1.2007, amended CoM
Decree 16/2008)
2. Rules for the Implementation of
SAA - notification procedures;
(CoM Decree 26/2007, amended CoM
Decree 97/2007, CoM Decree 10/2009,
CoM Decree 3/2010)
3. Procedure to ensure the
• All aid measures -
notifiable or exempt from
notification, except for de
minimis, are subject to mandatory
coordination.
• Cumulation rules are
directly applicable to the
requirements of the aid measures.
National legislation does not
contain specific regulations,
because accumulation is an
element of specific aid measures
and is obligatory checked when
coordinating the measure.
Compliance with the rules for
accumulation are monitored by the
administrator through: -
determining at the programming
phase whether the measures are /
are not eligible for accumulation -
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 218 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
transparency of financial relations
between public authorities and local
governments and state and municipal
enterprises and transparency within
certain undertakings - the transposition of
Directive 2006/111 (EC) (CoM Decree
99/2006, effective from 1.1.2007 )
The current SAA regulates national
procedures for the implementation of Art.
107 and Art. 108 TFEU, as well as the
powers of the Ministry of Finance and the
Minister of Agriculture and Food, the
nature of the procedures, information
exchange and coordination. It establishes
a framework for compliance with the
regime at national level, incl. with respect
to the notifiable aid, aid exempted from
notification and aid de minimis.
check of the maximum amount of
the aid on a specific project - in
ex-ante and ex-post control of the
project.
• Clause "Deggendorf" is
legally regulated in Article 9, para.
3 of the Rules for Implementation
of SAA. It is applicable to all aid
administrators.
• According to § 1, point 5
of the SP of SAA, any amendment
of an aid shall be treated as new
aid and it is subject to the same
rules of coordination and approval.
• Regardless of the way of
management of the financial
instrument, the State aid rules are
applicable to the aid administrator.
Objectives, content and specific
parameters of any new state aid are
developed by the administrator
and submitted to the Ministry of
Finance. In case of doubt or
ambiguity the Ministry of Finance
provides recommendations.
Regardless of the form and the
instrument for support, grant /
financial instruments, state aid
legislation is applicable to each
administrator (MA). In case of
multi-phase schemes, the latter is
applicable to each of the
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 219 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
participants. The aid element may
be missing at a particular level of
the measure but it may appear on
another level. Exceptions and / or
special derogations from the
procedure for notification and
assessment in case of repayable
assistance are not provided for.
• National law governs the
procedure for recovery of illegal
and incompatible aid under the
Tax Insurance Procedure Code
(TIPC) by NRA. NRA acts are
subject to appeal before the
competent national courts.
Effective and timely recovery is
governed by the procedures for the
collection and provision of public
debts. Decisions of the
Commission for recovery of
unlawful State aid shall be
enforceable under the TIPC.
Additional measures are taken to
improve the legal framework to
allow immediate and full
implementation of the decisions of
the Commission for recovery.
• The compliance with
General Block Exemption
Regulation (GBER) is regulated in
SAA. The Minister of Finance
shall consider the information
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 220 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
received and shall issue an
opinion. In the event that there is
uncertainty about the application
of the measure or discrepancy, the
administrator has 14 days to
correct the project. In case where
the administrator does not bring
state aid in alignment within the
prescribed period, the MoF shall
inform the administrator that the
aid does not meet the criteria for
block exemption. A state aid
administrator not accepting the
opinion of MoF and grants the
state aid is responsible for its
legality. The state aid
administrator shall inform the
Ministry within three days of the
delivery of any state aid covered
by GBER and will publish
information on the Internet.
• The exchange of
information on state aid and de
minimis aid at national level are
governed on two levels that are
sufficiently accurate and timely.
Data to the Commission are
provided as follows:
- based on specific
requests from the European
Commission;
- regular data exchange -
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 221 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
annual report, thematic reports etc.
At present, the EU legislation does
not have a requirement for a
central de minimis aid registry,
this is an option only for the aid
under Regulation 1998/2006.
Special separate statement is
included in the new GBER
(Regulation No 651/2014,
17.06.2014). The Bulgarian state
aid legislation empowers MoF to
request information related to the
state aid and provides for sanctions
in case of non-delivery by the
administrator.
The SAA obliges the state aid
administrators to maintain their
own registers of state/de minimis
aid and they bear the
responsibility for the reliability of
the data and upon request allow
access to the registers. To ensure
transparency and reporting, MoF
supports an Internet based
Information system "State Aid
and De Minimis Register"
available at:
http://minimis.minfin.bg. The
Register is completed directly by
the state aid and de minimis
administrators that submit the
same information on hard copy to
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 222 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
the MoF. The register allows for
drawing various types of public
reports. The information for state
aid is only on the basis of the new
GBER requirements. In a
subsequent revision of the
European legislation in the field
of state aid, requiring additional
registers for information, such
will be created.
According to the document
"Procedure for managing user
access to Information system
―Register of state aid", approved
by Order of the Ministry of
Finance ZMF-925 of 15.08.2014,
the system provides access at two
levels - user part (for aid
administrators) and
administrative part (for
employees of the Ministry of
Finance).
User part serves to the
administrators for input and
processing the necessary
information about the types of aid
measures and beneficiaries, and
the administrative one - to
provide access to administrators.
The system has a public module
for (accessible to all), which at
the moment is extended in order
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 223 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
to retrieve data under different
criteria, according to the new
GBER requirements.
A draft for the
amendment of SAA is prepared.
It was preliminaly coordinated
with the relevant administrative
bodies but it will be sent to the
Council of Ministers after the
new cabinet has took place after
the elections on as per the
5.10.2014 In view of the limited
rights of the caretaker
government, before CoM the
draft will again be sent for
consultations. The amendments
seek technical refinement and
updating of the rules so as to
improve the procedures and
interaction between the parties in
the process of state aid since its
planning until the time of its
actual use. The main version of
the State Aid Act is of 2006,
respectively comes into effect on
01.01.2007 and currently does not
reflect the development of the
system at European level.
Substantial changes in the bill
over the status quo are:
The new SAA draft does not
amend conceptually the order and
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 224 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
regime at a national level, but
rather refines texts and procedures.
The novelties are:
1. Introducing a special procedure
for recovery of illegal and
incompatible aid when recipients
and amounts of aid are not
predefined in the EC decision for
recovery. SAA currently does not
regulate this specific case, the
provision defines only that the aid
be recovered pursuant to the
decision of the European
Commission.
2. Provisions are made to ensure
sufficient capacity for planning,
development, notification,
management, reporting and control
of the granting of state and
minimum aid by aid
administrators. The proposal
creates a connection between
previously existing legal
obligation for administrators and
its practical implementation,
ensuring maintenance of
administrative capacity at all
levels, providing state aid.
Currently there are no provisions
for capacity in the SAA.
3. The functions of the MF to
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 225 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
provide methodological guidance
to administrators and to take
measures to improve the regime
are expanded. In the current SAA
functions of MF do not allow
issuing of guidelines, only
opinions to help administrators.
4. Improved is the coordination
and monitoring of state aid by
suggesting compilation of acts for
establishing violations be carried
out by officials of the Agency for
State Financial Inspection. Under
the current SAA policy violations
are established by acts issued by
officials authorized by the MF.
With the proposed change the
existing control mechanism is
improved which ensures the
applicable enforcement of the
regime and clearly separates
control from the methodological
functions. Control is delegated to a
subject with control functions.
To improve control, a change is
suggested in the Public Financial
Inspection Act in terms of
functions. Until now Art. 5 of
PFIA regulates control over the
utilization of state aid and
spending of expedient subsidies,
after the change control should
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 226 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
cover the provision, utilization and
spending.
5. Terminological and practical
refinement of the law:
- introduction of basic
principles that must comply when
providing aid. This is in the
context of European legislation on
state aid, as it requires provision of
aid to be necessary, appropriate,
efficient and transparent, also to
have an incentive effect in certain
cases. These are defined according
to the criteria laid down in the
relevant act by the law of the
European Union, on which aid is
granted.
- moving the requirement to
comply with the Degdendorf
criteria from the regulation to the
Act;
- creating a framework regulating
the establishment and maintenance
of an IT system for monitoring and
coordination of state aid held at
central, regional and municipal
level. The current SAA does not
have such provisions. Currently,
the system of coordination takes
place in Working Group 6 to
Decree 85/2007 or through
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 227 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
targeted initiatives on specific
problem. The purpose of this
change is not to significantly
change the existing system but to
improve its performance by
regularity and raising awareness.
- refined are aid exempt from
notification on grounds other than
the block exemption by Regulation
1370/2007 and EC decision SGEI
2012.
- introducing the obligation for
aid administrators to inform
recipients about the type, size and
compatibility of the aid, as well
as obligations arising from the
arrangement. Until now, the
current SAA does not regulate
particular order.
Arrangements for training and
dissemination of information for staff
involved in the implementation of the
ESI funds;
YES Sources of specialized information
1. http://stateaid.minfin.bg/
2. http://minimis.minfin.bg/
3. http://www.minfin.bg/en/page/12
• All MA have undergone trainings on
state aid in the School of Public Finance at
the Ministry of Finance, and some of them
within the framework of OPs technical
assistance.
MoF supports specialized web
page for information related to
State aid, where the Bulgarian
and the legislation of EU, the
procedures and initiatives of EC
are available.
Information system "State aid and
de minimis register― is
maintained by MoF. It is
completed by the administrators
of state aid.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 228 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
School of Public Finance at the Ministry of
Finance
(http://www.minfin.bg/bg/page/12)
organizes trainings in state aid on requests
several times a year. Any training program
is formed according to the objectives and
needs of the trainees. The trainings are
free-of-charge.
• Maintenance of information and
publicity of state aid is implemented
through two information channels:
o general - specialized Internet
page on State Aid legislation
http://stateaid.minfin.bg/ and within
WG 6 to the Council of European
Affairs (CEA).
o thematically by the MoF, as
appropriate and in accordance with
different cases, such notification shall
be made by official correspondence
or e-mail and via the FAQ page of the
State Aid;
• The system of exchange of
information on state aid at the level of each
administrator (MA) is carried out
according to the specifics of its activities -
for example by internal rules.
• MoF may issue thematic
guidance on various topics aimed to clarify
specific issues.
The Institute of Public
Administration/School on Public
Finance provide training for each
administrator and/or public
authority under issues related to
state aid.
In order to strengthen the regime
the proposal for amending SAA
provides for additional
obligations for state aid
administrator, which are
developed, in order to build and
maintain sufficient administrative
capacity to plan, develop, inform,
manage, report and control state
aid and grant de minimis aid.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 229 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
Each relevant MA (OPHRD, OPE,
OPRD, OPCBE) has certain employees
who are responsible for public
procurement issues which responsibilities
are included in their job descriptions.
Arrangements to ensure
administrative capacity for
implementation and application of
Union State aid rules.
YES The national and European legislation on
state aid is available at:
http://stateaid.minfin.bg/
• According to the national legal
framework, MoF is the national body
responsible for the monitoring,
transparency and coordination of state aid at
national, regional and local level, with the
exception of aid schemes or individual aid
in the agriculture and fisheries, where the
competent body is MAF.
• The competences of the Ministry
of Finance regulate the issuance of specific
opinions and prior coordination of aid
measures.
• In the draft new SAA refining of
the functions of the coordination unit are
planned by preparing methodological
guidelines and taking measures for the
development of the regime in the field of
state aid.
• MoF has experience in issuing
publications, manuals and instructions for
Since 01.09.2014 is in force new
functional characteristics of Real
Sector Finance Directorate at
MoF, as part of the State Aid
Department functions are
transferred to the other
departments of RSFD with which
they are entitled competences and
specific functions from the state
aid field. This is aimed at creating
additional capacity. State Aid
Department is renamed to
―Methodology, monitoring and
coordination of state aid‖.
Prepared changes in SAA
explicitly require any aid
administrator, as OPMA, to build
and maintain sufficient capacity
for planning, development,
notification, management,
reporting and control of the
granting of state and de minimis
aid.
Provisions are envisaged for each
aid administrator to individually
determine the measures for the
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 230 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
the benefit of aid administrators, including
MA. Beyond regular opinions of the State
Aid Department in the MoF, since 2007
thematic guidelines in favor of MA are
issued / updated as well. All current
national guidelines and EU publications
that would be useful for administrators are
publish on a specialized website.
• In the draft amendment to the
SAA an introduction of a specific
obligation for aid administrators is
envisaged (including OPMA) to build,
maintain, and provide sufficient capacity
for the planning, development, notification,
management, reporting and control of
granted state and de minimis aid. Measures
for the implementation of the latter are
determined individually by each aid
administrator.
Each relevant MA (OPHRD, OPE,
OPRD, OPCBE) has certain employees
who are responsible for public procurement
issues which responsibilities are included in
their job descriptions.
implementation of these activities,
according to the volume and
specifics of the administered aid,
including at least technical
security and staffing and measures
for data protection.
The draft provides for each state
aid and de minimis aid, the
administrator to determine the
persons responsible for carrying
out the planning, development,
notification, management,
reporting and control of the
granting of state aid and de
minimis aid.
The bill contains a change in the
functions of MoF. New functions
are envisaged:
- on the preparation of
methodological guidelines for the
implementation of this Act and the
legislation on state aid;
- on the measures for the
development and improvement of
the system in the field of state aid
and to ensure transparency.
- on building and maintaining of
information system for monitoring
and coordination of state aid at
central, regional and municipal
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 231 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
level; the system will represent a
set of measures for exchange of
information, building and
maintaining administrative
capacity in order to improve the
transparency of state aid at all
levels.
These functions are intended to
clarify the legal framework in
which MoF shall provide specific
recommendations and guidance to
help administrators.
Until now, such recommendations
are provided on the basis of the
general powers of the Minister of
Finance as a national coordinating
body for monitoring and ensuring
transparency and does not have a
unified and binding nature for the
administrators.
With the adoption of the proposed
regulatory changes MoF will be
able to issue thematic instructions
to the administrators. The
amendments in the SAA will not
change the obligatory character of
the issued instructions. The current
model is being kept – the
administrator of aid to carry
responsibility of the legal
conformity of the aid given. The
instructions of the MoF regarding
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 232 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
the aid, subject to notification as
per art.108/3/TFEU and regarding
de minimis aid are
methodological, not obligatory.
Obligatory are the standpoints
regarding the aid exempted from
notification.
• The change in the legal
framework will allow the MoF to
provide thematic and practical
instructions, for example:
- preparation of Internal Rules for
the preliminary assessment of the
aid and the phases in which the
support measures are coordinated;
- development of internal rules for
assessing the eligibility of
cumulation of aid and for effective
control of the same.
- development of individual
mechanism by which to check the
compliance of the provision of
Art. 9, para. 3 of the Implementing
Rules ("Deggendorf");
- Description of a specific
procedure by steps of the
modification of already published /
approved aid measure and
arrangements for coordination
with the Ministry of Finance, and
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 233 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
if necessary - to notify the
European Commission (eg
pursuant to Art. 4 of Regulation
794/2004 and Regulation
800/2008).
- for inclusion in MA procedural
manuals of specific provisions
(steps) to ensure awareness and
dissemination of information on
the rules on state aid at all levels.
In the context of the new
operational programmes, the need
for specific actions related to the
capacity of the MA is evaluated
after the Ministry of Finance starts
the coordination of specific
procedures, the measures for
assistance and/or other relevant
information, and where PFIA
provide information about the
inspections / checks, in which
there are findings and
recommendations in the field of
state aid.
6. The existence of
arrangements for the
effective application of
Union environmental
legislation related to EIA
and SEA.6.
YES
Arrangements for the effective
application of Directive 2011/92/EU
of the European Parliament and of the
Council ( 2 ) (EIA) and of Directive
2001/42/EC of the European
Parliament and of the Council ( 3 )
(SEA);
YES Environmental Protection Act
(promulgated, SG, issue 91 of 25.09.2002,
amended and supplemented)
http://www3.moew.government.bg/files/file
/Industry/Legislation/Zakoni/ZOOS.pdf
A legislation is in place to
implement the Directives on EIA
and SEA, including in terms of
clear regulations the method of
assessing the quality of EIA
reports and reports on the EA and
the opportunities for access to
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 234 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
Ordinance on the conditions and procedures
for environmental impact assessment
(subsequent amendment SG, issue 94 of
30.11.2012)
http://www3.moew.government.bg/files/file
/Legislation/Naredbi/NAREDBA_za_uslovi
qta_i_reda_za_izvyrsvane_na_ocenka_na_v
yzdejstvieto_vyrhu_okolnata_sreda_Zagl_i
zm_D.pdf
Ordinance on the conditions and procedures
for environmental impact assessment
(subsequent amendment (SG, issue 94 of
30.11.2012)
http://www3.moew.government.bg/files/file
/Industry/Legislation/Naredbi/NAREDBA_
za_usloviqta_i_reda_za_izvyrsvane_na_eko
logicna_ocenka_na_planove_i_programi_Z
agl_izm_DV_br_.pdf
documents and public participation
at various stages of the EIA and
EA procedures and clear
regulation of the right of interested
parties for access to justice.
Arrangements for training and
dissemination of information for staff
involved in the implementation of the
EIA and SEA Directives;
YES http://www.moew.government.bg/?show=to
p&cid=233
Letter № 05-08-7258/13.11.2013 of MEW,
containing information about the experts
Implemented JASPERS project No
2012 155 BG MSE MSU,
‖Support for Preventive Activities
Directorate and Natura 2000‖
Department within the Ministry of
Environment and Waters (MEW),
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 235 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
responsible for EIA and SEA for
development of electronic network.
Guidelines elaborated under the JASPERS
project are published at the internet page of
the Ministry of Environment and Water:
http://www.moew.government.bg/?show=to
p&cid=233
http://www.moew.government.bg/?show=to
p&cid=233&lang=en
Trainings, workshops and seminars are
held. Guidelines are developed. Access is
ensured to the guidelines and the issued
manuals electronically and by regular mail.
An electronic network of the EIA and EA
experts is created, including at regional
level, for exchange of information,
experience and for the electronic
dissemination of information and
documents.
E-mail address of all EIA and SEA experts
at MOEW for exchange of information,
experience and dissemination of
information and documentation by e-mail.
given the implementation of the
common ex-ante conditionalities.
A seminar was held in March 2013
with the participation of EIA and
EA experts from the 16 RIEWs,
representatives of JASPERS and
the EC. Six manuals are issued
under the project: for roads,
railway projects, waste, waste
waters, application of Art. 7 of the
EIA Directive and practical
handbook for EIA and EA training
- key elements, including a list of
rulings of the EU Court of Justice
on EIA.
Letter № 26-00-3425/13.01.2014
of the MEW with guidance for the
implementation of the Regulation
on conditions and procedures for
assessing the environmental
impact and Chapter VI of the Law
on Environmental Protection.
Guidelines have been prepared
under ref. No. No. 05-08-
857/20.02.2014, 05-08-
858/20.02.2014 and 02-00-
11/24.02.2014 on the legal effect
of the EIA decision and
application of the provisions of
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 236 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
At the page of the MEW is published
guidance on the application of the
provisions of Art. 2a of the Ordinance on
the arrangements and procedures for EIA,
art. 7 of the Ordinance on the arrangements
and procedures for conducting SEA on
plans and programs, and art. 13 , para . 3 of
the Ordinance on the arrangements and
procedures for assessing the compatibility
of plans, programs, projects and investment
proposals with the subject and the
objectives of the conservation of protected
areas to determine the eligibility of
investment proposals, plans , programs and
projects according to the restrictions in the
National Action Plan for renewable energy
by 2020, arising from the environmental
assessment Opinion № 1-2/2012 of the
Minister of Environment and Water .
http://www.moew.government.bg/?show=to
p&cid=233
article 93, para 7 and article 99,
para. 8 of the EPA.
Instruction sent to the RIEWs
through the electronic network of
experts on EIA and SEA to fill the
information in the records in EIA
and SEA registers. Instruction sent
on defining the scope and content
of the reports of assessing the
environmental impact assessment
(EIA) and Environmental
Assessment (EA), sent through
formal mail to the directors of
RIEWs by letter ref. № 05-08-
2757/28.04.2014, as well as
through the electronic network of
experts in EIA and SEA. The same
is also published on the website of
Ministry:
http://www.moew.government.bg/
?show=top&cid=233
Instruction prepared № 05-08-
3097/30.05.2014 of MOEW
regarding the scope of p. 2, ―g― of
Annex № 2 of the Law on
Environmental Protection, which
is distributed by e-network experts
in EIA and SEA and published at
http://www.moew.government.bg/
files/file/Industry/EIA/2014/Ukaza
nia_pravno_deistvie_reshenia_OV
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 237 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
OS.pdf.
Instruction prepared № 91-00-
78/15.07.2014 of MOEW rearding
legal application of decision under
FIA and decisions for judgement
of the necessity of having FIA,
which is sent through the e-
network experts on FA and SEA
as well as by official mail to the 16
RIEWs, 4 basins directorated,
MEE, MRD and MAF.
Instruction letter prepared 04-00-
1379/22.07.2014 г. regarding
application of the environmental
legislation in deciding on
contruction under LSP, which is
sent through the e-network experts
on FA and SEA.
Update of information at MOEW
page with instructions on
application of EIA and SEA
procedures:
http://www.moew.government.bg/
?show=top&cid=233
Guidance letter ref. № 15-00-71 /
03.10.2014 from MoEW on the
application of Art. 93, para. 6 of
the EPA was issued. The letter was
sent by mail to the official
"Bulgarian Association of
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 238 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
Recycling" as an interested party
and to the Directors of Regional
Inspectorates, as well as the
electronic network of experts in
EIA and SEA.
Arrangements to ensure sufficient
administrative capacity. YES In the 16 RIEWs, as competent
environmental authorities in the EIA and
EA procedure, structural EIA and EA units
exist with appointed experts whose job
descriptions include the coordination of the
procedures under EIA and EA.
http://www.moew.government.bg/?show=1
64
Trainings, workshops and
seminars are held. Guidelines are
developed. Access is ensured to
the guidelines and the issued
manuals electronically and by
regular mail. Methodological
guidelines and manuals are
promptly disclosed on the websites
of MEW and RIEW. Guidelines
and manuals are distributed both in
paper and electronically via the
created network of the experts on
EIA and SEA at national and
regional level.
Prepared under project of
JASPERS guidelines are
distributed to all experts in EIA
and SEA in the system of the
Ministry and 16 RIEWs in the
created electronic network.
Guideline on determining the
eligibility of investment proposals,
plans, programs and projects
according to the restrictions in the
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 239 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
National Action Plan for
Renewable Energy by 2020,
arising from the environmental
assessment Opinion № 1-2/2012
of the Minister of Environment
and water is circulated to all
experts on EIA and SEA in the
system of the Ministry and 16
RIEWs via the created electronic
network.
Letter № 26-00-3425/13.01.2014
of the MEW with guidance for the
implementation of the Regulation
on conditions and procedures for
assessing the environmental
impact and Chapter VI of the Law
on Environmental Protection was
distributed among all experts in
AEI and SEA in the system of the
Ministry and the 16 RIEWs
through the established electronic
network.
On 02.07.2014 г. At MOEW is hel
a working meeting with AEI and
SEA at MOEW system incl the 11
RIEWs.
7. The existence of a
statistical basis necessary
to undertake evaluations
Partially Arrangements for timely collection
and aggregation of statistical data
with the following elements are in
YES European statistics Code of Practice
http://www.nsi.bg/files/Quality/1.1.%20Co
To ensure the quality of results,
harmonized national statistics are
developed, produced and
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 240 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
to assess the effectiveness
and impact of the
programmes. The
existence of a system of
result indicators necessary
to select actions, which
most effectively
contribute to desired
results, to monitor
progress towards results
and to undertake impact
evaluation.
place:
— the identification of sources and
mechanisms to ensure statistical
validation;
— arrangements for publication and
public availability of aggregated data;
P_ALL_BG.pdf
Declaration on the quality of the national
statistical system of the Republic of
Bulgaria:
http://www.nsi.bg/files/Quality/QUALITY_
NSI_Declaration.pdf
Statistics Act:
http://www.nsi.bg/dokument.php?P=64&SP
=102&NSP=1#cont
National Statistical Program for 2013:
http://www.nsi.bg/dokument.php?P=64&SP
=102&NSP=36#cont
Rules for the dissemination of statistical
products and services:
http://www.nsi.bg/dokument.php?P=64&SP
=102&NSP=20#cont
disseminated on the basis of
harmonized standards and
methods. The following quality
criteria are applied:
a) "relevance", which refers to the
degree to which statistics meet
current and potential needs of the
users;
b) "Accuracy", which refers to the
closeness of estimates to the
unknown true values;
c) "Timeliness": refers to the
period between the availability of
the information and the event or
phenomenon it describes;
d) "Punctuality", which refers to
the period of time between the date
of the release of the data and the
target date (the date by which the
data should have been delivered);
e) "Accessibility" and "clarity":
refer to the conditions and
modalities by which users can
obtain, use and interpret data;
f) "comparability", which refers to
the measurement of the impact of
differences in applied statistical
concepts, measurement tools and
procedures where statistics are
compared between geographical
areas, sectoral domains or over
time;
j) "coherence", which refers to the
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 241 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
adequacy of the data to be reliably
combined in different ways and for
various uses.
NSI - leading to the provision of
general for the programs
performance indicators and
mechanisms to ensure statistical
validation.
OPs Managing Authorities -
leading to the development and
maintenance of an effective system
of indicators.
For the systems developed to date,
the information concerning
indicators of individual programs
will be available in the public
UMIS, on the websites of the
Managing Authorities of the
respective programs.
An effective system of result
indicators including:
— the selection of result indicators
for each programme providing
information on what motivates the
selection of policy actions financed
by the programme;
— the establishment of targets for
these indicators;
— the consistency of each indicator
NO List of standard statistical indicators:
http://www.nsi.bg/img/uplf/StdInd2013.pdf
http://www.nsi.bg/img/uplf_e/StdInd2013_
en.pdf
Performance of the criterion is
linked to the complete
development of the OPs.
Indicators that will be developed
during the implementation of OPs
by MA or the beneficiaries will
have to undergo statistical
validation in accordance with the
following procedures:
1. When the indicators are based
on administrative data, the
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 242 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
with the following requisites:
robustness and statistical validation,
clarity of normative interpretation,
responsiveness to policy, timely
collection of data;
definitions and concepts used for
administrative purposes should be
close enough to those required for
statistical purposes.
2. Sampling and assessment
methods should be well justified.
3. Methods of data collection
should be coordinated with NSI,
and their application is observed in
terms of compliance with the
methodology.
4. Beneficiaries and MA cooperate
with NSI to ensure data quality.
Defined are quantity and quality
goals for result indicators, which
content is coordinated between the
EU programmes and other donors.
For the indicators are are defined
quantity and quality goals that are
in conformity with Europe 2020.
–
- Procedures to ensure that all
operations financed by the program
adopt an effective system of
indicators.
NO For the ESF is provided collecting
information on an individual level
for each participant in accordance
with the provisions of Regulation
1304/2013 as well as at project
level and priority level. Reporting
will be accomplished through
performance and result indicators
set at the appropriate level of the
operational programme for which
the reporting and impact
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 243 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
assessment are held.
Monitoring data will be presented
at each meeting of the Monitoring
Committee (MC) so that MC
members can discuss issues that
could hinder the proper
implementation of the programme.
Activities carried out in relation to
the timely collection of microdata
for participants will be reported in
the annual implementation reports,
as well as in the progress reports
submitted to the MC.
The data itself reflects all
participants that directly used or
benefit of ESF support, as in case
of doubled participation in the
same operation, the individual
participant is counted only once.
For reporting purposes (despite the
fact that to the EC will be provided
only aggregated data) personal
data will be used for each
participant (eg, gender, status on
the labor market, education level,
etc) including "sensitive" one (eg,
disability, minority status,
disability, etc.). Under the
provisions of the Directive on the
protection of personal data, each
participant may refuse to give
"sensitive" information, in which
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 244 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
case the relevant management
bodies of documentary
programmes must establish that
they have attempted to collect such
data, and that was refused.
Much like the common indicators
in Regulation 1304/2013, the
Managing Authorities will provide
clear and understandable
definitions of specific indicators of
individual programs with which to
achieve a common understanding
of them and to facilitate their
subsequent reporting.
Managing authorities build their
systems for storage and reporting
data on individual participants in
electronic form, with regard not
only to the formal implementation
of the provisions of Article 56 of
Regulation 1303/2013 and Article
5 and Article 19 of Regulation
1304/2013, but in order to
effectively fulfill the obligations of
the monitored and evaluation. For
this purpose, they were built on the
systems and procedures for
monitoring the ESF in the 2007-
2013 programming period, which,
however, need additional settings
and clarification as to comply with
the requirements applicable to the
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 245 of 274
Applicable ex-ante
conditionality for which
national authorities are
responsible
Applicable
ex-ante
conditionality
fulfilled:
Yes/No/Parti
ally
Criteria: Criterion
fulfilled:
Yes/No
Reference (if fulfilled)
(reference to the strategies, legal acts or
other relevant documents articles or
paragraphs, accompanied by a
hyperlink or other access to the full text)
Explanation (where appropriate)
programming period 2014-2020
and also to reporting indicators for
immediate and long-term result,
incl. on a sample basis.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 246 of 274
Table 9-2 Actions to fulfil applicable general ex-ante conditionalities
Applicable general ex-ante
conditionalities for which
national authorities are
responsible and which are
unfulfilled or partially
fulfilled
Criteria not fulfilled Actions to be taken Deadline (date)
Responsible
authorities for
fulfillment
4. The existence of arrangements
for the effective application of
Union public procurement law in
the field of the ESI Funds.
Arrangements for the effective
application of Union public
procurement rules through appropriate
mechanisms;
Action 1.
Adoption of National Strategy for the Development of the Public
Procurement Sector in Bulgaria for the period 2014 – 2020
The draft Strategy envisages measures to raise effectiveness in public
procurement and creation of guarantees for conformity with EU law
in the field.
Deadline for Action 1:
July 2014
MEE
PPA
Action 2.
Adoption of a codified, sustainable and simplified legislation on
public procurement through adoption of new PPA and secondary
legislation acts on its application.
Deadline for Action 2:
January 2016
MEE
PPA
Action 3.
Design of reinforced management and control systems for ESIF, incl.
effective cooperation in order to ensure consistency between the
actions in the ex-ante and ex-post control
Deadline for Action 3:
January 2016
MA
CCU
EA AEUF
PPA
Court of Auditors
PFIA
Action 4.
Review of the appeal system and proposals for its optimization (ie
safeguards against abuse of the right to appeal, etc.)
Deadline for Action 4:
October 2014
CPC
SAC
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 247 of 274
Applicable general ex-ante
conditionalities for which
national authorities are
responsible and which are
unfulfilled or partially
fulfilled
Criteria not fulfilled Actions to be taken Deadline (date)
Responsible
authorities for
fulfillment
Arrangements for training and
dissemination of information for staff
involved in the implementation of the
ESI funds.
Action 1.
Design and implementation of training and development programme
for staff involved in the management of ESIF (trainings on public
procurement incl. by the Training academy on ESIF (IPA)
Deadline for Action 1:
December 2016
IPA
MA
PPA
Action 2
Revision and update of existing systems of dissemination and
exchange of information between practitioners from Managing
authorities and beneficiaries and other stakeholders on public
procurement with a view to establishing a uniform practice.
Deadline for Action 2:
December 2016
MA
CCU
EA AEUF
PPA
Court of Auditors
PFIA
Arrangements to ensure administrative
capacity for implementation and
application of Union public
procurement rules.
Action 1.
Strengthening and stability of the administrative capacity of the
Public Procurement Agency through increase in personnel and
conducting specialized trainings
Deadline for Action 1:
December 2015
MEE
PAA
Action 2
Providing improved technical assistance to those who apply the rules
of public procurement through organization and conduction of
trainings and other needs identified from consultation of target
groups
Deadline for Action 1:
December 2016
IPA
MA
PAA
7. The existence of a statistical — An effective system of result Action 1 Deadline for Action 1: NSI together with OP
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 248 of 274
Applicable general ex-ante
conditionalities for which
national authorities are
responsible and which are
unfulfilled or partially
fulfilled
Criteria not fulfilled Actions to be taken Deadline (date)
Responsible
authorities for
fulfillment
basis necessary to undertake
evaluations to assess the
effectiveness and impact of the
programmes. The existence of a
system of result indicators
necessary to select actions, which
most effectively contribute to
desired results, to monitor
progress towards results and to
undertake impact evaluation
indicators including:
— the selection of result
indicators for each programme
providing information on what
motivates the selection of policy
actions financed by the
programme;
— the establishment of targets
for these indicators;
— the consistency of each
indicator with the following
requisites: robustness and
statistical validation, clarity of
normative interpretation,
responsiveness to policy, timely
collection of data;
Selection of performance indicators for each operational program.
Performance and result indicators are relevant and linked to the
thematic axes, objectives and measures of an OP.
For statistical validation will apply an unified system for
requirements of collection of microdata, for applicable
methodologies and definitions of their scope and for the applicable
procedure for processing and aggregating data. The framework for
statistical validation will be developed in accordance with the
European Code of Practice and methodological requirements of the
statistical regulations of the European Commission and the
Parliament.
Within two months after
the adoption of each OP
MAs
Action 2
Check on compliance for each indicator in terms of its sustainability,
clarity of interpretation, timeliness of data collection and responsive
to policy.
Deadline for Action 2:
September 2014
NSI together with OP
MAs
— Procedures in place to ensure that all
operations financed by the programme
adopt an effective system of indicators.
Action 1
Development of procedures to collect and process the microdata
necessary to assess the contribution of operations to specific
objectives of each OP.
Deadline for Action 1:
Within two months after
the adoption of each OP
NSI together with OP
MAs
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 249 of 274
Table 9-3 Actions to fulfil applicable thematic ex-ante conditionalities
Applicable thematic ex-ante
conditionalities for which
national bodies are responsible
and which are unfulfilled or
partially fulfilled
Criteria not fulfilled Actions to be taken Deadline (date) Bodies
responsible for
fulfillment
1.1. Research and innovation:
The existence of a national or
regional smart specialization
strategy in line with the National
Reform Program, to leverage
private research and innovation
expenditure, which complies with
the features of well-performing
national or regional R&I systems.
A national or regional smart
specialization strategy is in place
that:
Smart Specialisation Strategy of R. of Bulgaria has been developed and adopted by
CM, Decision № 761/06.11.2014 as a precondition for fulfillment of ex-ante
conditionality 1.1 and 1.2 as per Annex XI of Regulation (EC) 1303/2013.
The actions to be taken are described in the detailed Action plan (Annex 6). The
actions aim at:
1. Improving the organizational structure for the governance of implementation of
IS3 and coordination with the OPs.
2. Promotion of private investments in R&D.
3. Ensuring synergy to solve national and regional challenges – identifying the
mechanism of implementation of horizontal and vertical links in the implementation
of IS3.
4. Intensifying the Entrepreneurial Discovery process, activating the links between
science and business by identifying the specific challenges and the ways to overcome
them.
June 2015
June 2015
June 2015
October 2015
October 2015
Ministry of
Economy
— is based on a SWOT or similar
analysis to concentrate resources on
a limited set of research
Based on SWOT analysis, quantative, qualitative and cross analyses, considering the
market demand, world trends and the results from several discussions (described in
the strategy) the thematic areas where Bulgaria has competitive advantages have
been defined and in which the interventions of the new programming period will be
implemented.
Defining the product and technology niches in which Bulgaria successfully competes
on the European and international markets is forthcoming (p.24-30 of the Action
Plan).
October 2015
Ministry of
Economy
Ministry of
Education and
Science
— outlines measures to stimulate
private RTD investment;
Elaboration of multiannual plan with indicative budget of the measures for IS3
implementation, including measures for stimulating the private investments in R§D
(p.10 of the Action Plan).
Support of innovative companies for development of new products and technologies
with the resources of the National Innovation Fund (p.11 of the Action Plan).
June 2015 Ministry of
Economy
MES, MTITC,
MAF
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 250 of 274
Applicable thematic ex-ante
conditionalities for which
national bodies are responsible
and which are unfulfilled or
partially fulfilled
Criteria not fulfilled Actions to be taken Deadline (date) Bodies
responsible for
fulfillment
— contains a monitoring
mechanism.
Developing detailed structure of the monitoring and evaluation process (p.7 of the
Action Plan)
June 2015 ME, MES
A framework outlining available
budgetary resources for research and
innovation has been adopted.
Elaboration of multiannual plan with indicative budget of the measures for IS3
implementation (p.10 of the Action Plan).
June 2015 ME, MES,
MTITC, MAF
1.2 Research and Innovation
infrastructure. The existence of a
multi- annual plan for budgeting
and prioritization of investments.
An indicative multi-annual plan for
budgeting and prioritization of
investments linked to Union
priorities, and, where appropriate,
the European Strategy Forum on
Research Infrastructures (ESFRI)
has been adopted.
Aligning research infrastructure and scientific priorities with economic priority areas
identified in IS3, including:
− Mapping of the research infrastructure capacity in Bulgaria;
− Update of Research Infrastructure roadmap;
− Update of the National Strategy of Scientific Research.
http://www.mon.bg/?go=page&pageId=74&subpageId=143
July 2015 MES
6.1. Water sector: The existence
of a) a water pricing policy which
provides adequate incentives for
users to use water resources
efficiently and b) an adequate
contribution of the different
water uses to the recovery of the
costs of water services at a rate
determined in the approved river
basin management plan for
investment supported by the
programmes.
In sectors supported by the ERDF
and the Cohesion Fund, a Member
State has ensured a contribution of
the different water uses to the
recovery of the costs of water
services by sector consistent with the
first indent of Article 9(1) of
Directive 2000/60/EC having regard,
where appropriate, to the social,
environmental and economic effects
of the recovery as well as the
geographic and climatic conditions
of the region or regions affected.
The economic analysis as described in Annex III to Directive 2000/60/EC has been
made for the purpose of the first River Basin Management Plan. This analysis
identifies what is the contribution of all three sectors (households, agriculture, and
industry) to the refunding of water service costs by taking into consideration any
possible cross subsidising.
This economic analysis was estimated by the European Commission as quite detailed
and well structured, in accordance with WATECO guidelines.
http://ec.europa.eu/environment/water/participation/map_mc/map.htm
The European Commission has exposed its notes on the assessment of River Basin
Management Plans: ―The climate change aspects are not considered directly in the
economic analysis‖.
To meet the requirements, two actions will be implemented.
Public procurements are announced and consultants will be selected to carry them
out.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 251 of 274
Applicable thematic ex-ante
conditionalities for which
national bodies are responsible
and which are unfulfilled or
partially fulfilled
Criteria not fulfilled Actions to be taken Deadline (date) Bodies
responsible for
fulfillment
Action 1.
Implementation of a national survey to ensure the needed data on climate change and
its impact on waters
The project was approved for funding from the Fund for Sustainable Development of
the Regions.
The public procurement under the PPA is announced and it is expected a consultant
to be selected.
Deadline for Action 1:
December 2015
MOEW
Action 2.
Drawing up the water use economic analysis for the period 2007-2013, which would
be the basis of the measures and pricing policy in the second River Basin
Management Plans
The project was approved for funding from the Fund for Sustainable Development of
the Regions. The public procurement is announced and it is expected a consultant to
be selected.
Deadline for Action 2:
December 2015
MOEW
Applying the pricing policy as referred to in Art. 9, paragraph 1, first subparagraph
of Directive 2000/60/EC, including:
Action 3.
Adoption of an Ordinance on the water use standards as referred to in Art. 117а,
paragraph 2 of the Water Act
Actions were initiated by the Minister of Environment and Water to the Ministers of
Regional Development, Agriculture and Food Economy, Energy and Health to
determine the experts and deadlines for providing suggestions related to the
definition of standards for water consumption. The updating of the standards for
irrigation started.
MRD is preparing Report on the implementation of the Action Plan of the WSS,
including an analysis of international experience and practice in the development and
implementation of legislative and strategic documents in the area of standards for
water consumption in the water sector, with a deadline for submission March 31,
Deadline for Action 3:
December 2015
MOEW
MRD
MAF
MEE
MH
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 252 of 274
Applicable thematic ex-ante
conditionalities for which
national bodies are responsible
and which are unfulfilled or
partially fulfilled
Criteria not fulfilled Actions to be taken Deadline (date) Bodies
responsible for
fulfillment
2015.
Action 4.
Adoption of legislative changes in the regulatory framework in the WSS sector
Additional agreement for consultancy services between the MRD and the World
Bank is signed to provide technical assistance to the State Energy and Water
Regulatory Commission in the part regulating the WSS sector. As a result from the
implementation of the contract the necessary legislative changes in the WSS sector
will be specified. •
The ratification from the National Assembly is forthcoming.
Deadline for Action 4:
December 2015
MRD
SEWRC
MEW
Action 5.
Introduction of different prices of the service water supply for subscribed users using
within water consumption standards, and users exceeding such standards.
This commitment will be completed upon the adoption of the Ordinance on the water
consumption standards under article 117а, paragraph 2 of the Water Act.
MRD is preparing a report on the implementation of the Action Plan of the Strategy
for WSS, including study of international experience and practices for determining
the price of water (icl. two-stage / preferential prices) - Deadline for submission
January 31, 2015
Deadline for Action 5:
December 2015
MEW
SEWRC
MRD
Action 6.
Drafting an amendment to the Tariff for water intake fees, water facility use fees and
pollution fees, whereby:
- higher fees are to be put in place where the water consumption standards are
exceeded (except for Water and Sewerage operators);
- different fees should be determined for pollution of purified and for non-purified
water;
- the Tariff should be brought in accordance with the amendments made to the Water
Deadline for Action 6:
December 2014
MOEW
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 253 of 274
Applicable thematic ex-ante
conditionalities for which
national bodies are responsible
and which are unfulfilled or
partially fulfilled
Criteria not fulfilled Actions to be taken Deadline (date) Bodies
responsible for
fulfillment
Act (Action 8)
A proposal was drafted concerning the methods of fee definition, for fees provided
for in the draft developed of the Law on the Amendment and Supplement of the
Water Act. The public tender for the development of a cost-recovery analysis
provides for fee grading and the respective economic reasoning thereto. The
pollution fee is planned to be determined in most cases based on the load of
pollutants (pollutant quantity and pollutant concentration measured).
In justification of the fees will be considered the motivating function of prices for
water use and whether the current water prices and charges for water leads to
efficient use of water, including water for irrigation. Under Bulgarian legislation in
all cases of abstraction for business purposes requires measuring draw amounts,
which is the main factor for sensitivity of prices and reducing inefficient and
wasteful use of water.
For the purposes of the implementation of subcriterion, the implementation of action
2, action 7 and action 8 will be needed.
The first River Basin Management Plans introduced the principle of cost-recovery if
water services in the Water and Sewerage sector are concerned.
The European Commission forwarded a remark on the assessment of River Basin
Management Plans:
―15. The cost-recovery should address a broad range of water services, including
impoundments, abstraction, storage, treatment and distribution of surface waters, and
collection, treatment and discharge of waste water, also when they are "self-
services", for instance self-abstraction for agriculture. The cost recovery should be
transparently presented for all relevant user sectors, and environment and resource
costs should be included in the costs recovered. Information should also be provided
on the incentive function of water pricing for all water services, with the aim of
ensuring an efficient use of water. Information on how the pollutant pays principle
has been taken into account should be provided in the RBMPs …‖.
Action 7. Deadline for Action 7:
December 2014
MEW
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 254 of 274
Applicable thematic ex-ante
conditionalities for which
national bodies are responsible
and which are unfulfilled or
partially fulfilled
Criteria not fulfilled Actions to be taken Deadline (date) Bodies
responsible for
fulfillment
Drawing up a cost-recovery analysis, using the available statistics.
The first phase of the contract is under implementation.
• The analysis will include as many water services as possible, including
water dams, water intake for different purposes, surface water storage, purification
and distribution, waste water collection, purification and discharge, individual
independent drinking water supply, individual independent water supply in
agriculture and industry, etc. The analysis foresees the inclusion of water collection
for the purposes of energy production and for other purposes (industrial, agricultural,
drinking). As regards guaranteeing the contribution of agriculture to diffuse pollution
environmental expenses, it is provided that cost-recovery include plant-growing and
cattle-breeding. The analysis of cost recovery foresee navigation to be included as a
service - element of the environmental costs calculated on the basis of bilge and
ballast water of ships collected waste port sea and ships, collected oil and petroleum
from spills in tons annually. , The Bulgarian legislation requires obligatorily
measuring of extracted and discharged water volumes (Water Act, Art. 194,
paragraph 2 and Art. 194а), which helps identify the contribution of different water
users to cost-recovery.
Action 8.
Adoption of Law on the Amendment and Supplement of the Water Act, whereby
simple and applicable mechanisms for determining pollution fees should be
introduced.
A draft of a Law on the Amendment and Supplement of Water Act was drawn up
including the implementation of the needed amendments related to applying the
‗pollutant is the one to charge‘ and ensuring the resource expenses and the
environment expenses. Furthermore, the draft includes the introduction of fees for all
water services (activities which lead to significant impact on waters) as identified in
the first River Basin Management Plans and the introduction of a resource expenses
and environment expenses identification mechanism, where all said expenses need to
be taken into consideration upon the evaluation of cost-recovery.
Deadline for Action 8:
July 2014
MOEW
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 255 of 274
Applicable thematic ex-ante
conditionalities for which
national bodies are responsible
and which are unfulfilled or
partially fulfilled
Criteria not fulfilled Actions to be taken Deadline (date) Bodies
responsible for
fulfillment
The draft law is approved by internal coordination within the Ministry of
Environment and Water and is under preparation for inter-institutional consultation
before adoption of the Council of Ministers.
The adoption of a river basin
management plan for the river basin
district consistent with Article 13 of
Directive 2000/60/EC
Adoption of river basin management plans covering the territories included in
Operational Programmes, which include priorities for water investments, including:
Action 1.
Adoption of the second River Basin Management Plans.
The second River Basin Management Plans must fill in the gaps and meet the
recommendations of the European Commission.
A call for proposals for the selection of a consultant is forthcoming.
Deadline for Action 1:
December 2015 г.
MOEW
Ensuring a Map of the monitoring networks installed for the purposes of Article 8
and Annex V, and presentation on a map of the results from the programmes carried
out according to these provisions for monitoring the status of surface waters
(environmental and chemical), underground waters (chemical and quantitative) and
the protected territories.
There are monitoring maps and networks, however these are further developed in
terms of binding to specific sources of pressure, ensuring the information needed
both for the assessment of the status of the water bodies and for clear and precise
planning of the measures and evaluation of their effect.
http://www3.moew.government.bg/?show=top&cid=66&lang=bg
The European Commission has forwarded its remarks in the assessment of the first
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 256 of 274
Applicable thematic ex-ante
conditionalities for which
national bodies are responsible
and which are unfulfilled or
partially fulfilled
Criteria not fulfilled Actions to be taken Deadline (date) Bodies
responsible for
fulfillment
River Basin Management Plans:
http://ec.europa.eu/environment/water/participation/map_mc/map.htm
―2. Monitoring should be strengthened as there is not enough monitoring data related
to biological and chemical elements and this is also a reason for low confidence in
the assessment of their status .
4. There is a significant gap in the intercalibration and the development of
methodologies, the expert judgement approach is often used. There is no fully
developed and formally adopted classification system for the assessment of the
ecological status. These gaps should be filled.
6. The identification of river basin specific pollutants needs to be more transparent,
with clear information on how pollutants were selected, how and where they were
monitored, where there are transcendences and how such transcendences have been
taken into account in the assessment of ecological status. It is important that there is
an ambitious approach to combating chemical pollution and those adequate measures
are put in place.
9. Mercury, hexachlorobenzene and hexachlorobutadiene should be monitored in
biota for comparison with the biota standards in the EQSD, unless water EQS
providing an equivalent level of protection are derived. Biota EQS should also be
considered for other substances where analysis in water is problematic. Trend
monitoring in sediment or biota is specified for several priority substances in
Directive 2008/105/EC Article 3(3) and will need to be reflected in the next River
Basin Management Plan.
10. Groundwater trend assessments should be carried out at all RBDs.‖
The following three actions will be carried out to cover the requirements.
Action 2.
Implementation of a three-year programme for completion of intercalibration of the
methods for analysis and values of quality of biological elements (QBE) applicable
to the types of surface waters in Bulgaria corresponding to certain common EU
types.
Deadline for Action 2:
December 2016
MOEW
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 257 of 274
Applicable thematic ex-ante
conditionalities for which
national bodies are responsible
and which are unfulfilled or
partially fulfilled
Criteria not fulfilled Actions to be taken Deadline (date) Bodies
responsible for
fulfillment
A program for development and intercalibration of analysis methods by categories of
surface waters is under implementation.
Action 3.
National studies to be carried out to overcome specified deficiencies.
1. Updating the typology and the classification system for assessment of surface
water bodies of the categories ―river‖, ―lake‖ and ―transitional waters‖.
2. Assessment of hydromorphological status water bodies of the categories ―river‖,
―lake‖ and ―transitional waters‖ and definition of the impact over the ecological
status caused by hydromorphological changes
3. Study and assessment of quantitative status of underground water bodies
4. Study and assessment of chemical status of underground water bodies
5. Study and assessment of the impact of diffuse sources of pollution over the status
of surface waters
6. Study and assessment of the chemical condition of the surface water.
The projects were approved for funding from the Fund for Sustainable Development
of the Regions. One of the suspended for appeal tenders is re-announced(4). The
documentation under the PPA is currently being reviewed and the second appealed
public procurement(3) is planned to be re-announced. Four public procurements
are announced(1,2,5,6)
For biological and hydromorphological elements - the second RBMP will have all
the assessment methods that will be developed and validated with projects on points
1 and 2 and action 2. Bulgaria currently monitor and provide data for all QBE, in the
case of the Danube the monitoring will start in 2014 .
Regarding hydromorphological elements it is envisaged to carry out a pilot
monitoring to validate the method. The full monitoring is expected to start with the
second RBMP.
The supplying of equipment (GC / MS / MS, HPLC / MS / MS, GC / MS and other
ancillary equipment), should be completed by the end of 2013. This will create
Deadline for Action 3:
December 2015
MOEW
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 258 of 274
Applicable thematic ex-ante
conditionalities for which
national bodies are responsible
and which are unfulfilled or
partially fulfilled
Criteria not fulfilled Actions to be taken Deadline (date) Bodies
responsible for
fulfillment
technical possibility to analyze specific pollutants.
With the implementation of planned project in p.6 is expected to gather information
and to develop methods for monitoring Hg, HCB, HCBD, to select appropriate
indicator species, categories of surface water and concrete posts, selection of
monitoring trends of accumulative matrices and output of background concentrations
and determination of bioavailability of metals.
Currently a study is conducted and the organization of work in the laboratories of the
EEA is on-going in order to shorten time to analysis of PBDE, TBT, C10- 13
Chloroalkanes, after the publication of improved methods for their analysis of the
results (CEN 424 - by the end of 2014), as well as to provide a clean laboratory
environment for analysis of DEHP in Bulgaria.
Action 4.
Investments for further building of monitoring networks were planned in OPE 2014-
2020.
Planned in the OPE 2014-2020 draft. At the implementation of the national studies
(under action 4) it was provided for to reason the needed the locations and the
number of the additional monitoring points and of the optimization of monitoring
programmes according to the identified specific pressure and impact owed to human
activity.
Upon the start of OPE 2014-2020 and upon the implementation of action 4, the
network further building projects may be drafted.
There is a list of ecologic targets identified according to Article 4 for surface
waters, underground waters and protected areas, and the exclusions thereof but they
will be further developed.
http://www3.moew.government.bg/?show=top&cid=66&lang=bg
The European Commission has forwarded its remarks on the assessment of the first
Deadline for Action 4:
December 2016
MOEW
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 259 of 274
Applicable thematic ex-ante
conditionalities for which
national bodies are responsible
and which are unfulfilled or
partially fulfilled
Criteria not fulfilled Actions to be taken Deadline (date) Bodies
responsible for
fulfillment
River Basin Management Plans:
http://ec.europa.eu/environment/water/participation/map_mc/map.htm
―7. The ecological objectives defined are of a very general nature, there are no
quantitative dimensions and easily measurable and verifiable criteria for monitoring
their achievement. Ecological objectives should be better specified.
3. The existing pressures are not being sufficiently detected, particularly where
complex pressure factors exist, e.g. combined pollution from diffuse and point
sources, or combined pressures from pollution and hydromorphological alterations.
Pressures should be sufficiently detected;
5. Where there are currently high uncertainties in the characterization of the RBDs,
identification of pressures, and in the assessment of status, these need to be
addressed in the current cycle, to ensure that adequate measures can be put in place
before the next cycle
12. The identification of exemptions is incomplete and should be completed in the
next RBMP cycle. While the WFD does provide for exemptions, there are specific
criteria that must be fulfilled for their use to be justified. The application of
exemptions needs to be more transparent and the reasons for the exemptions should
be clearly justified in the plans. ―
The recommendations will be completed by the specified national studies in
conformity with Action 4.
As regards the summary of the measures undertaken under Article 11,
paragraph 5 for the water facilities, which fail to achieve the targets as identified
under Article 4, measures are planned such as specified in the report under Art.15 of
the Framework Water Directive (presented by Bulgaria to the European Commission
in 2010)
http://www3.moew.government.bg/?show=top&cid=66&lang=bg
The planned measures are to be announced for financing under the Norwegian
programme (if proposals for the relevant projects are received).
6.2. Waste sector: Promoting
economically and
environmentally sustainable
The existence of one or more waste
management plans as required under
Action 1 Deadline for Action 1.
August 2014
MOEW
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 260 of 274
Applicable thematic ex-ante
conditionalities for which
national bodies are responsible
and which are unfulfilled or
partially fulfilled
Criteria not fulfilled Actions to be taken Deadline (date) Bodies
responsible for
fulfillment
investments in the waste sector
particularly through the
development of waste
management plans consistent
with Directive 2008/98/EC, and
with the waste hierarchy.
Article 28 of Directive 2008/98/EC; Adoption of a National Waste Management Plan for the period 2014-2020 г.
The Plan will be in accordance with the requirements of Art.28 of the Framework
Waste Directive.
On 22.08.13, a contract was signed with a contractor for the development of the Plan
(and the Programme thereto).
A draft National Plan for Waste Management (NPWM) for the period 2014-2020 is
presented. On the website of the MOEW are published the analyzes, prepared by
consultants, being the first part of publication of the Programme for public
consultation. Forthcoming steps:
1) Publication of the draft plan or program on the website of the Ministry, as the
second part of public discussion and public consultation on the draft plan and
programs in the context of the environmental assessment.
2) Submission of the plan to Council of Ministers - August 2014
In developing the 2014-2020 NPWM into account are taken all recommendations
and examples of measures set out in the Roadmap for Bulgaria. In developing 2014-
2020 NPWM also was considered the methodological guidance of the European
Commission, DG "Environment" to develop plans for waste management.
The existence of waste prevention
programmes, as required under
Article 29 of Directive 2008/98/EC;
Action 1
Preparation of Waste Generation Prevention Programme – as part of the National
Waste Management Plan for the period 2014-2020 г.
A draft of the National Waste Generation Prevention Programme is prepared and it is
part of the National Waste Management Plan.
The National Waste Generation Prevention Programme includes objectives,
measures and key indicators and is oriented towards highest level in the hierarchy of
waste management.
Deadline for Action 1.
August 2014
MOEW
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 261 of 274
Applicable thematic ex-ante
conditionalities for which
national bodies are responsible
and which are unfulfilled or
partially fulfilled
Criteria not fulfilled Actions to be taken Deadline (date) Bodies
responsible for
fulfillment
See TExAC 6.2.1
Necessary measures to achieve the
targets on preparation for re-use and
recycling by 2020 consistent with
Article 11(2) of Directive
2008/98/EC have been adopted.
Action 1
Adoption of National Waste Management Plan for the period 2014-2020 г.
The measures for implementation of the targets will also be included in the new
National Waste Management Plan.
See TExAC 6.2.1
The application of the principle ‗polluter has to pay‘, which requires the waste
disposal expenses to be paid by the waste generator, is set in the Waste Management
Act. The producers of waste and the owners of waste should manage it in a way,
which guarantees high degree of protection for the environment and for human
health, by taking into account the real expenses on environment derived from waste
generation and waste management. The application of the principle will also be laid
down in the new National Waste Management Plan for the period 2014-2020. The
principle of ―extended responsibility of the producer‖ was imposed to strengthen
waste prevention, re-use, recycling and other kind of utilization and to reduce
household waste management expenses the responsibility whereof, according to the
Bulgarian Waste Management Act lies on the mayor of the municipality. The Waste
Management Act and the implementing regulations stipulate measures to guarantee
that each natural person or legal entity, which develops, produces, processes, treats,
sells or imports products (producer of the product) where wide spread waste is
formed, shall bear extended producers responsibility. These measures include
obligations for subsequent collection and treatment, here included recycling of waste
and the financial liability for carrying out these activities.
In 2010 economic instruments were introduced for the municipalities, responsible for
management of waste, for fulfillment of the objectives: waste depositing deductions
(deposition fee) which purpose is to reduce the quantity of waste received for
deposition, encouragement of separated collection of recyclable waste, an increase in
the quantities of recycled and utilized waste and acceleration of building of regional
systems for treatment of household waste and establishment of technical
infrastructure for waste recycling and utilization as provided in the National Waste
Management Plan. The introduction of the amendment to the 2013 Local Taxes and
Deadline for Action 1.
August 2014
MOEW
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 262 of 274
Applicable thematic ex-ante
conditionalities for which
national bodies are responsible
and which are unfulfilled or
partially fulfilled
Criteria not fulfilled Actions to be taken Deadline (date) Bodies
responsible for
fulfillment
Fees Act encourages the municipalities to introduce a household waste management
fee based on the quantities of generated waste. The amendment shall be enforced as
of 2015.
According to the Waste Management Act, the construction waste treatment systems
shall ensure by 1 January 2020 the latest their re-use, recycling or other utilization of
materials composed of non-hazardous construction waste, including those in the case
of embankment activities by means of replacement of other materials by waste by a
quantity not less than 70 per cent of their total weight excluding unpolluted soils, soil
or rock bulk masses excavated in natural condition.
In NPWM are set binding targets for municipal recycling and use of household waste
and the reduction of biodegradable waste. The programs of measures to achieve the
objectives of NPWM provide a number of activities to improve the administrative
capacity at the municipal level to improve waste management, including control
activities, information on waste data, methodological support from the MOEW and
others.
To achieve the National target for re-use, recycling or other utilization of materials
the persons in charge will be the entities which were assigned for the construction
works and which ensure selective division and utilization of materials.
The analysis on which the objectives of NPWM 2014 - 2020 are based, and the
measures to achieve them, extensively is presented in the application of the
Bulgarian scheme for producer responsibility. The conclusion is that as an approach
and as results achieved the scheme was successful and achieves targets for recycling
and recovery of these waste streams. Deficiencies are identified and for their
overcoming it is proposed an individual program of measures to improve the scheme,
such as the expansion and improvement of audits to the recovery organizations and
others.
7.4. Development of smart
energy distribution, storage and
transmission systems. The
existence of comprehensive plans
for investments in smart energy
infrastructure, and of regulatory
measures, which contribute to
Comprehensive plans describing the
national energy infrastructure
priorities are in place
Approval of the Ten-year Network Development Plan (TYNDP) of Bulgartransgaz
under Article 22 of Directive 2009/72/EC for the period 2014-2023, including:
1. Preparing a project for a decision for certification of the Operator (BTG)
2. Notifying the EC
3. Receiving the EC Statement
2015-01-31
2015-02-02
2015-06-02
SEWRC
SEWRC
EC
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 263 of 274
Applicable thematic ex-ante
conditionalities for which
national bodies are responsible
and which are unfulfilled or
partially fulfilled
Criteria not fulfilled Actions to be taken Deadline (date) Bodies
responsible for
fulfillment
improving energy efficiency and
security of supply.
4. Issuing Final Certification Decision
5. Publishing the final decision in the Official Gazette of the Community
2015-08-02
2015-09-02
SEWRC
SEWRC
— in accordance with Article 22 of
Directive 2009/72/EC and of
Directive 2009/73/EC, where
applicable, and
See actions for 7.4.1 criteria 2015-09-02 SEWRC
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 264 of 274
10. REDUCTION OF THE ADMINISTRATIVE BURDEN FOR THE BENEFICIARIES
ULessons learned from the programming period 2007-2013 г.
(The data used are from a study of ESTAT OOD, carried out in the period December
2012 – January 2013.)
The main lesson learned from the period 2007-2013 is that the administrative burden is
one of the biggest impediments preventing the initiation of more interest for
participation in OPC procedures, as well as their effective implementation. Therefore
using the learning-by-doing principle, activities have been undertaken to relieve
candidates/beneficiaries, such as:
In May 2012 an institutional reform was carried out aiming to create a more
simplified and efficient management structure of OPC. The Intermediate Body
of the OP was closed to avoid duplication of responsibilities and monitoring and
control functions, and to reduce time for document review and decision taking.
The volume of documents to be submitted with the application has been
reduced; the content of some declarations has been simplified; the contracting
procedure has been streamlined; an option for introducing functional corrections
to the project budget in the event of errors/inconsistencies admitted by
candidates has been adopted; monthly reporting on the implementation has been
dropped; the number of requests for clarification by beneficiaries during the
verification of project implementation reports has been reduced.
An electronic submission under the procedure BG161PO003-1.2.04
―Development of applied research in the research organisations in Bulgaria‖ has
been introduced as a pilot project.
Since April 2013 a new Decree of the Council of Ministers (Nr. 69 dated 11th
March 2013) on the conditions and procedure for determination of contractor on
the part of beneficiaries of contracted grant financial aid from the structural
funds and the Cohesion Fund of the European Union, the Black Sea Basin Joint
Operational Programme 2007-2013, and the EEA and Norway Grants has been
enforced. This act repeals previous Decree Nr. 55 dated 12th
March 2007 of the
Council of Ministers and lays out a new procedure to simplify the system for
selection of contractor and accelerate the project implementation.
The MA recognises the positive results achieved so far in connection with reducing the
administrative burden and, at the same time, plans to take further action in this regard in
the new programming period.
UMeasures planned for the programming period 2014-2020
The common vision to reduce the administrative burden within the overall process of
coordination, management, implementation, monitoring and control of EU funds is to be
achieved by creating a stable and predictable environment for the implementation of
ESI-funded programmes, introducing maximum electronisation in the communication
between beneficiaries and the MA, optimising administrative procedures, dropping
unnecessary obligations for beneficiaries and synchronising rules. To this end, the
following specific measures have been envisaged:
UDocuments and document processing
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 265 of 274
Standardised application, evaluation and reporting forms will be introduced, as this
process is expected to be finalized in the 3rd
trimester of 2015 with the introduction of
UMIS 2020:
On the one hand – significant reduction of the burden for beneficiaries and
expected reduction of problems and queries related to the completion of the
application form, respectively a lower number of inaccurately completed forms
submitted, hence also a lower number of proposals rejected on such grounds;
On the other hand – standardisation is a prerequisite for successful introduction
of full electronisation of processes as per the Regulation. Although electronic
systems should allow for some flexibility according to the specifics of the
procedure, a limited number of standardised forms should be used, e.g. forms for
infrastructure projects, soft-measure projects etc.
UWith a view to optimising the document processing, the following measures will be
initiated:
Enlarging the scope of electronic submission of project proposals and electronic
project reporting – indicative deadline for implementation is the 3rd trimester of
2015 with the introduction of UMIS 2020 ;
Exploring the possibility of suspending the submission of the same documents
more than once, and precising/reducing the cases in which these documents have
to be submitted in original or notarized and additional copies - indicative
implementation deadline the end of 2015;
Introducing technical provisions to conduct the entire communication between
applicants/beneficiaries and the MAs of the programmes co-funded from the
ESIF, as well as between the separate units within the management system of
EU funds via UMIS 2020- indicative deadline for implementation is the 3rd
trimester of 2015 with the expected introduction of the fully operational version
of UMIS 2020
Dropping the requirement to submit administrative and other documents issued
by public institutions in hard copies in cases of availability of publicly accessible
electronic registers or in cases of provisions for regulated access through official
channels (automated data submission under the E-Government Act) for access to
such documents – implemented with the adoption of the legal documents for the
implementation of the programmes funded under ESIF .
Preparation of project proposals
The following specific measures have been envisaged to reduce the administrative
burden related to the preparation of project proposals:
Unification of the rules and requirements for investment projects under the
different programmes related to preliminary preparation, preparation of detailed
justification, objectives, indicators, budget and timetable for the implementation
of project activities, pre-feasibility studies, cost-benefit analyses etc. – indicative
deadline for implementation the middle of 2015;;
Synchronisation of the timeframe for implementation of complementary
schemes under different operational programmes – implemented with the
adoption of Decree № 107 of 10.05.2014, section III;
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 266 of 274
Seeking opportunities to introduce vouchers and voucher schemes (eg. for
cooperation, specialized corporate services and trainings) with reduced deadlines
for receiving of the support and start of the implementation – the vouchers are
among the planned support approaches (with grant and financial instruments)
under OPIC and similar measures are envisaged for the whole programming
period.
UEvaluation of project proposals, award of grants and implementation of projects
The following specific measures have been envisaged to reduce the administrative
burden related to the evaluation of project proposals:
Improving the quality of the evaluation process by setting minimum quality
requirements for submitted proposals, whereby no funding will be awarded to
projects below the established quality threshold - implemented with the adoption
of Decree № 107 of 10.05.2014;
Transparent evaluation procedure with electronisation of the projects to be
evaluated and enabling involvement of high-quality external expertise, including
international participation, especially in areas such as innovation – indicative
deadline for implementation the middle of 2015 with the introduction of the E-
evaluation within UMIS 2020;
When evaluating projects in procedures for direct grant award shall be included
the opportunity for communication between the MA and the applicants for
correction of project proposals – implemented with the adoption of Decree №
107 of 10.05.2014;
Allowing a simplified approach to grant funding to direct beneficiaries -
administrative structures via "Budget lines" - implemented with the adoption of
the Decree № 107 of 10.05.2014, Article 29, paragraph 1.
UProcedures for selection of contractors
The following specific measures have been envisaged to reduce the administrative
burden related to contractor selection procedures under projects co-financed by the EU:
Creating clearly structured and standardised rules to introduce a unified
approach to the requirements for beneficiaries, and public and private entities
concerning contractor selection. The existence of straightforward rules should
eliminate any possibility for free interpretation on the part of the MA and
supervisory bodies. In cases when the adopted statutory rules decree that the
contractor selection should follow a certain procedure based on contract value or
type of beneficiary, the latter should be administered accordingly, without
inclusion of further requirements – implemented with the adoption of Decree
№118 of 20.05.2014;
Using a simplified contractor selection procedure in accordance with the
statutory requirements to ensure observance of the principles of sound financial
management, openness and transparency, equality and free competition -
implemented with the adoption of Decree №118 of 20.05.2014;
Electronization of the processes related to the selection of a contractor, incl.
enabling e-tendering - indicative deadline for implementation is the third
trimester of 2015, when UMIS 2020 is expected to be finalized and fully
operational.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 267 of 274
UVerification and payment
Similar to the submission stage, the volume of administrative documents at the
verification stage should be reduced to a minimum. In this regard the following has
been foreseen:
Exploring the possibilities to approve not only bank guarantees for advance
payments but also guarantees provided by another financial institution or
coverage by instrument provided as a guarantee by a public entity – indicative
implementation deadline the end of 2015;
Standardised reporting forms should set a limit on the volume of details
provided to guarantee that just the most essential information has been included
in order to establish the compliance between the implementation and initial
intentions – establishment of unifed models for all programmes included in the
UMIS 2020 of the following documents is envisaged: application form, request
for payment; financial report, technical report and the indicative deadline for the
implementation of this mesure is the 3rd
trimester of 2015;
Application of accounting rules for simplified costs to cover all ESI-funded
programmes. Given the failed application of simplified costs in the present
programming period, an adoption of a relevant national methodology has been
foreseen for the period 2014-2020 – indicative deadline for implementation is
the middle of 2015;
Maximum standardisation of verification and reimbursement procedures for all
programmes with clear specification of rules, functions and responsibilities in
order to avoid duplication of activities and checks of identical documents and
information at several stages; clear identification of responsible persons at each
stage of the verification process – implemented with the adopton of Decree 119
frim 20.05.2014 for the adoption of national rules for elegibility of the costs
under the operational programmes;
As regards payment, the lack of resources available to the MA will be excluded
as a reason for delayed reimbursement of funds to beneficiaries. Establishing
such a condition, beyond the control of the beneficiaries, will transfer the risk of
delayed reimbursement on the part of the MA to the beneficiary. In addition to
which, the right of the beneficiary to claim interest for the period of delay will
be retained – this issued has already been solved.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 268 of 274
11. HORIZONTAL PRINCIPLES
USustainable development
Sustainable development is one of the key priorities of the National Development
Programme: Bulgaria 2020, which outlines the main applicable challenges and
opportunities for the country over the next few years.
The key legislation and sectoral strategic documents in the field of sustainable
development and environmental protection include:
Environmental Protection Act;
Disaster Protection Act;
Energy Act;
National Strategy for Regional Development for the period 2012-2022; National
Regional Development Strategy (NRDS) for the period 2012-2022
Water Act;
Waste Management Act;
National Strategy for Management and Development of the Water Sector in the
Republic of Bulgaria; National Strategy for Water Sector Management and
Development in the Republic of Bulgaria.
Maritime Strategy of the Republic of Bulgaria;
Strategic Action Plan for the Environmental Protection and Rehabilitation of the
Black Sea;
National Programme for the Requisite Measures in Conditions of Drought;
National Strategy for Biodiversity Conservation;
National Programme for Waste Management for the period 2009-2013;
National Programme for Waste Management for the period 2014-2020 (to be
developed by end 2013);
National Action Programme for Sustainable Land Management and Combat to
Desertification (2007-2013);
National Programme for Action on Environment and Health 2008-2013;
National Programme for Disaster Protection 2009-2013;
Third National Action Plan on Climate Change 2013-2020;
National Plan for Protection from Natural Disasters
National Long-Term Programme for Promoting the Use of Renewable Energy
Sources 2005-2015;
National Action Plan on Renewable Energy Sources, valid until 2020
Energy Strategy of the Republic of Bulgaria until 2020, which includes goals
connected with improving security of gas supplies, increasing energy efficiency
and the use of renewable energy;
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 269 of 274
Second National Action Plan on Energy Efficiency 2011-2013 and its respective
report.
The documents take into account the main priorities and objectives of the European
policy on sustainable development and are integral part of all policies related to the
development of the country.
The necessary provisions to ensure the application of the principle of sustainable
development in the management of ESI funds were established during the programming
of the different measures and interventions. The OPIC working group includes
representatives of the main institutions responsible for the implementation of policies on
environmental protection and sustainable development and representatives of non-
governmental organisations.
At the same time, the Council of Ministers has adopted Guidelines on Mainstreaming of
Environmental Policy and Climate Change Policy in Cohesion Policy, Common
Agricultural Policy and Common Fisheries Policy Funds 2014-2020. The Guidelines set
out specific measures and types of actions for the environmental policy and the climate
change policy to be mainstreamed by the respective national responsible authorities in
the Partnership Agreement and the programmes to be supported by the ESI Funds in the
period 2014-2020. The purpose of the Guidelines is to ensure the implementation of a
single, systematic and coordinated approach in the mainstreaming of the environmental
policy and the climate change policy in the main programming documents for the period
2014-2020, as well as reporting and monitoring of results and achievement of specific
and measurable national targets consistent with the targets of the EU.
The document ―Guidelines on Mainstreaming of Environmental Policy and Climate
Change Policy in Cohesion Policy, Common Agricultural Policy and Common Fisheries
Policy Funds 2014-2020. Phase: Implementation of Operational Programmes and the
Partnership Agreement‖ forms part of the Guidelines. It envisages developing a system
of criteria to ensure that in the period 2014-2020 the allocation of ESI funds will
prioritise projects that contribute to a higher degree to the implementation of
environmental policies and climate change policies. Also particularly important in the
preparation and implementation of the operational programmes will be to take account
of the requirements for protection and improvement of the environment, principally
through application of the precautionary principle, the principle of preventive action and
the polluter pays principle.
The effective implementation of the Guidelines, Phase 1 and Phase 2 and the integration
of the envisaged measures in the programmes to be supported from the ESI Funds will
be ensured through continuous dialogue and coordination by all stakeholders. In this
regard, it has been envisaged to establish a national network with representation of the
competent environmental authorities, MAs, and the non-governmental and business
sectors in the country.
In accordance with the specific provisions of the CPR and other applicable European
legislation, the polluter pays principle will be systematically applied across the
Programme and projects. Prevention and recovery costs will be borne by the agent of
potential or actual pollution to the environment. In practice, the principle will be applied
through:
Ensuring the enforcement of the national and European legislation in the field of
environmental licenses, assessments and sustainable development for all
investment under the programmes;
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 270 of 274
Promoting the introduction of quality management systems in the field of the
environment in enterprises and organisations;
Supporting the development of environmentally-friendly activities (work
without using paper, green public procurement);
Preparing an environmental impact assessment for each investment, when
required by the European and/or national legislation;
Preparing full cost-benefit analysis for major investment projects, particularly
with regard to public infrastructure and municipal environmental facilities;
Making support conditional on the presence of full compliance of the actions to
be funded with the national legislation in the field of the environment, as well as
on the full payment of all taxes and tolls for activities with environmental
impacts.
Considering the importance of green procurement as one of the factors contributing to
sustainable development, adopted is National Strategy for the Development of the
Public Procurement Sector in Bulgaria for 2014 - 202064
, which supports the policy of
public procurement and provides for the development of green public procurement, i.e.
―green public procurement‖( GPP). GPP is an important tool to facilitate the
implementation of measures in the field of sustainable development, as a tool for this is
public contracts. Through them may impose conditions for the imposition of green
practices such as reducing the use of paper, the use of "green products" in the object of
orders disclosure of green jobs certification of sustainable buildings criteria for
environmental quality / eco-balance the construction site, optimal use of resources and
water application requirements for energy efficiency and energy savings in the supply of
equipment and vehicles, and others who are provided for in the upcoming practical
guide for preparing for the such contracts.
UPromotion of equality between men and women, non-discrimination and
accessibility
The principles of gender equality, non-discrimination and accessibility are embedded in
the Bulgarian legislative and institutional system and apply to all spheres of social life,
including property status, economic activities, etc. The overall framework ensuring
compliance with these horizontal principles includes: Constitution of the Republic of
Bulgaria (Article 6); Act on Protection Against Discrimination; Integration of People
with Disabilities Act; National Strategy for Equal Opportunities for People with
Disabilities 2008-2015; National Strategy for Promotion of Gender Equality 2009-2015;
Long-term Strategy for the Employment of People with Disabilities 2011–2020.
The application of these principles to the management of ESI funds is similarly ensured
at the various stages of preparation and implementation of OPIC 2014-2020.
The necessary requirements for the programming stage have been ensured through:
Determining the composition of the working group for the preparation of OPIC
to include a wide range of organisations in the field of equal opportunities and
non-discrimination, including the Commission for Protection against
Discrimination and the National Council for Cooperation on Ethnic and
Integration Issues, NGOs in the field of gender equality and non-discrimination,
64
Approved by CoM Decree № 498/11.07.2014
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 271 of 274
the Ministry of Labour and Social Policy, which has horizontal competences
related to the coordination and control of the national policy on equal
opportunities;
Designating a core function of the working group to ensure compliance with the
horizontal principles during the process;
Including a requirement to review and, respectively, advise on issues relating to
non-discrimination in the requirements for the technical assistance and the ex-
ante evaluation.
During the implementation of OPIC the application of the principles of gender equality,
non-discrimination and accessibility will be ensured through the following measures:
The MA will fulfil the horizontal guidelines on the application of these
principles at the various stages of the programme implementation to be issued by
the Central Coordination Unit. Based on these guidelines, beneficiaries‘
contracts will include specific requirements on the application of the principles
in the project implementation;
As part of the evaluation of project proposals, the compatibility with the
principles of gender equality, non-discrimination and accessibility will be
assessed;
Ensuring compliance with the horizontal principles will be an integral part of
project monitoring. Project implementation reports will include a description of
the contribution to the principles of equality, non-discrimination and
accessibility;
The violation of the principles during implementation, as well as the failure to
fulfil the commitments described in the project proposal, related to those
principles, will lead to imposing financial corrections, which will be based on
the extent and impact of the non-fulfillment;
During the preparation of each OPIC annual implementation report or progress
report, the MA will provide information on the current state of fulfillment of the
horizontal principles under each axis;
During the programming period at least one evaluation of the fulfillment of the
principles of equality, non-discrimination and accessibility will be carried out,
either separately or as part of an overall evaluation of the implementation of
OPIC;
Representatives of non-governmental organizations in the field of equal
opportunities, non-discrimination and accessibility will be included in the
Monitoring Committee of OPIC;
This mechanism will build upon the approach used during the programming
period 2007-2013 and reinforce some of its elements with a view to achieving
higher efficiency.
UAccessibility
Based on the guidelines to be prepared by the Central Coordination Unit for all
applicable interventions, the MA should include the criterion compliance with the the
principle of accessibility in the evaluation of project proposals. The same principle
should be included in the contracts of beneficiaries with approved projects.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 272 of 274
On the other hand, with the help of transparency, publicity and information tools,
related to the funding opportunities to be provided by the ESI Funds, access to
investment for all potential beneficiaries and the general public will be facilitated. This
will enable both efficient participation in the implementation of EU-funded projects and
effective use of the development incentives offered by them.
12. SEPARATE ELEMENTS
12.1. Relevant partners involved in preparation of programme
Ministry of Economy and Energy:
General Directorate ―European Funds for Competitiveness‖
Directorate ―Business environment and SME policy‖;
Directorate ―Investments, innovations and entrepreneurship‖;
Directorate ―Energy Strategy and Sustainable Energy Development Policies;
Directorate ―Tourist Policy‖;
Directorate ―Tourism Marketing, Advertising and Information‖;
Ministry of Finance:
Directorate ―Economic and Financial Policy‖;
Directorate ―National Fund‖;
Directorate ―Operational Programme Administrative Capacity‖
Ministry of Transport, Information Technologies and Communications;
Ministry of Education and Science;
Ministry of Environment and Waters;
Ministry of Agriculture and Foods;
Ministry of Regional Development;
Ministry of Labour and Social Policy;
Ministry of Health
Central Coordination Unit;
Administration of the Council of Ministers;
Directorate ―Strategic development and coordination‖
Directorate ―Operational Programme Technical Assistance‖.
Agency for Sustainable Energy Development;
Executive Agency for Promotion of Small and Medium Enterprises;
Invest Bulgaria Agency;
Executive Agency “Audit of EU Funds”
Patent Office
National Statistical Institute
State Fund “Agriculture”:
Department „Authorization of Payments for Implementation of Measures for
Development of Rural Regions‖;
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 273 of 274
Department „Contracting for Implementation of Measures for Development of
Rural Regions‖;
Department ―Certification of Expenses under RDP‖.
Executive Agency for Fisheries and Aquaculture;
Representatives of academia;
Anti-Discrimination Commission;
National Association of the Municipalities in the Republic of Bulgaria;
Regional Development Council of the South-West Region;
Regional Development Council of the North-West Region;
Regional Development Council of the South-East Region;
Regional Development Council of the North-East Region;
Regional Development Council of the South-Central Region;
Regional Development Council of the North-Central Region;
Confederation of Employers and Industrialists in Bulgaria;
Association of Industrial Capital in Bulgaria;
Bulgarian Trade and Commerce Chamber;
Bulgarian Industrial Association;
Confederation of the Independent Syndicates in Bulgaria;
Confederation of Labour “Podkrepa”;
Nationally Representative Organizations of and for People with Disabilities;
Non-governmental Organizations from Thematic Group “Social Organizations”;
Non-governmental Organizations from Thematic Group “Organizations
operating in the Sphere of Education, Science and Culture”;
Non-governmental Organizations from Thematic Group “Environmental
Organizations”;
Non-governmental Organizations from Thematic Group “Development Policies”.
OPIC 2014-2020, 2014 BG16RFOP002 – March 2015
Page 274 of 274
LIST OF ANNEXES
ANNEX 1: REPORT ON THE EX-ANTE EVALUATION
ANNEX 2: REPORT ON THE ENVIRONMENTAL ASSESSMENT
ANNEX 3: EX-ANTE ASSESSMENT AND INVESTMENT STRATEGY FOR THE EFFECTIVE USE
OF FINANCIAL INSTRUMENTS UNDER OPIC
ANNEX 4: CITIZENS‘ SUMMARY
ANNEX 5: RIS3 GOVERNANCE STRUCTURE
ANNEX 6: ACTION PLAN FOR COMPLIANCE WITH EX ANTE CONDITIONALITIES 1.1 AND 1.2