OPERATION RESEARCH PLANNING AND SCHEDULING OF A MULTI-STOREY RESIDENTIAL BUILDING Project by:- SHAIK KHAZAMOHIDDIN -11BCL1012 Name of Guide: -Prof. Uma maheswari

Transcript of Operation Research Final Project

OPERATION RESEARCH

PLANNING AND SCHEDULING OF A

MULTI-STOREY RESIDENTIAL BUILDING

Project by:-

SHAIK KHAZAMOHIDDIN -11BCL1012 Name of Guide: -Prof. Uma maheswari

Introduction:

The feasibility studies stage considers the options for satisfying the client's needs, enabling

the client to prepare a business case for the preferred option and deciding whether to proceed with

the project. It is possible to make an outline planning application during this stage if the risk to the

project of not receiving planning permission is high, or if delays in receiving planning

permission would be problematic.

MS project is designed to assist a project manager in developing a plan, assigning resources to

tasks, tracking progress, managing the budget, and analyzing workloads, Cost Estimation can be

done in feasibility report.

Objective:-

• To prepare feasibility report.

• Planning, design and financial services for Multi-Storey Commercial Building

• Sub Activities:

• Survey and soil investigation

• Preparation of Feasibility Report and financial viability of Project.

• Master Plan and Conceptual Plan

• Design Development & tender Documents

• Invitation of Tenders and evaluation of Bids

• Detailed design & Construction drawings

• Top Supervision

• TIME SCHEDULE

• CONSULTANTS FEE STRUCTURE

• REMUNERATION OF SERVICES

• Complete Final Inspections

Methodology

SEQUENCE of MS Project:-

1. Set overall project information: goals, scope, assumptions, start date, manager

2. Create a Base Calendar, assign it to the project and to the Gantt chart.

3. List tasks and milestones, estimate durations

4. Outline the project (create Summary Tasks)

5. Link the tasks

6. Assign resources

7. Evaluate and refine the project

8. Save a Baseline

9. Track and update the project—Actuals

10. Communicate progress—Reports

11. Close the project

TASK Allocation:

1. Commercial Construction 11.General Conditions

2. Long Lead Procurement 12.Mobilize on Site

3. Grading and Utilities 13. Foundations

4. Steel Erection 14.Form and Pour Concrete Floors and Roof

5. Carpentry Work 15. Masonry Work

6. Roofing 16. Window wall and

7. Store front closure 17.Building Finishes

8. Elevators 18.Plumbing

9. Electrical 19.Heating and Ventilating - AC

10. Final Clean-up and Occupancy 20.Complete Final Inspections

Task Mode Task Name Duration Start Finish Predecessors Resource Names

Auto Scheduled

Commercial Construction

344 days Mon 1/3/00

Thu 4/26/01

Auto Scheduled

General Conditions

17 days Mon 1/3/00

Tue 1/25/00

Auto Scheduled

Receive notice to proceed and sign contract

3 days Mon 1/3/00 Wed 1/5/00

G.C. General Management

Auto Scheduled

Submit bond and insurance documents

2 days Thu 1/6/00 Fri 1/7/00 2

G.C. Project Management,G.C. General Management[25%]

Auto Scheduled

Prepare and submit project schedule

2 days Mon 1/10/00

Tue 1/11/00

3 G.C. Project Management[25%],G.C. Scheduler

Auto Scheduled

Prepare and submit schedule of values

2 days Wed 1/12/00

Thu 1/13/00

4 G.C. General Management[10%],G.C. Project Management

Auto Scheduled

Obtain building permits

4 days Thu 1/6/00 Tue 1/11/00

2 G.C. Project Management[50%],G.C. Procurement[50%]

Auto Scheduled

Submit preliminary shop drawings

2 wks Wed 1/12/00

Tue 1/25/00

6 G.C. Project Management[50%],G.C. Procurement[50%]

Auto Scheduled

Submit monthly requests for payment

1 day Thu 1/6/00 Thu 1/6/00 2

Auto Scheduled

Long Lead Procurement

70 days Fri 1/7/00 Thu 4/13/00

Auto Scheduled

Submit shop drawings and order long lead items - steel

2 wks Fri 1/7/00 Thu 1/20/00

8 Steel Erection Contractor Management

Auto Scheduled

Submit shop drawings and order long lead items - roofing

2 wks Wed 1/26/00

Tue 2/8/00 7 Roofing Contractor Management

Auto Scheduled

Submit shop drawings and order long lead items - elevator

2 wks Wed 1/26/00

Tue 2/8/00 7 Elevator Contractor Management

Auto Scheduled

Submit shop drawings and order long lead items - plumbing

2 wks Wed 1/26/00

Tue 2/8/00 7 Plumbing Contractor Management

Auto Scheduled

Submit shop drawings and order long lead items - electric

2 wks Wed 1/26/00

Tue 2/8/00 7 Electric Contractor Management

Auto Scheduled

Submit shop drawings and order long lead items - HVAC

2 wks Wed 1/26/00

Tue 2/8/00 7 HVAC Contractor Management

Auto Scheduled

Detail, fabricate and deliver steel

12 wks Fri 1/21/00 Thu 4/13/00

10 Steel Erection Contractor Management[50%],Steel Erection Contractor[50%]

Auto Scheduled

Mobilize on Site 10 days Thu 1/6/00 Wed 1/19/00

Auto Scheduled

Install temporary power

2 days Thu 1/6/00 Fri 1/7/00 2 Electric Contractor

Auto Scheduled

Install temporary water service

2 days Thu 1/6/00 Fri 1/7/00 2 Plumbing Contractor

Auto Scheduled

Set up site office

3 days Mon 1/10/00

Wed 1/12/00

18,19 G.C. Superintendent,G.C. Labor Crew[10%]

Auto Scheduled

Set line and grade benchmarks

3 days Thu 1/13/00

Mon 1/17/00

20 G.C. Survey Crew

Auto Scheduled

Prepare site - lay down yard and temporary fencing

2 days Tue 1/18/00

Wed 1/19/00

21 Site Grading Contractor,G.C. Labor Crew[10%]

Auto Scheduled

Site Grading and Utilities

35 days Thu 1/20/00

Wed 3/8/00

Auto Scheduled

Clear and grub site

3 days Thu 1/20/00

Mon 1/24/00

20,22 Site Grading Contractor

Auto Scheduled

Stone site access and temporary parking area

2 days Tue 1/25/00

Wed 1/26/00

24,22 Site Grading Contractor

Auto Scheduled

Rough grade site (cut and fill)

1 wk Thu 1/27/00

Wed 2/2/00

25 Site Grading Contractor

Auto Scheduled

Install storm drainage

2 wks Thu 2/3/00 Wed 2/16/00

26 Site Grading Contractor

Auto Scheduled

Install exterior fire line and building fire riser

2 wks Thu 2/3/00 Wed 2/16/00

26 Plumbing Contractor

Auto Scheduled

Perform final site grading

2 wks Thu 2/17/00

Wed 3/1/00

27FF+1 day,28 Site Grading Contractor

Auto Scheduled

Erect building batter boards and layout building

1 wk Thu 3/2/00 Wed 3/8/00

29 G.C. Survey Crew

Auto Scheduled

Foundations 33 days Thu 3/9/00 Mon 4/24/00

Auto Scheduled

Excavate foundations

2 wks Thu 3/9/00 Wed 3/22/00

30 Site Grading Contractor[50%]

Auto Scheduled

Excavate elevator pit

2 days Thu 3/9/00 Fri 3/10/00 30 Site Grading Contractor

Auto Scheduled

Form column piers and spread foundations

4 days Thu 3/23/00

Tue 3/28/00

32 G.C. Rough Carpenter Crew

Auto Scheduled

Rough-in electric and plumbing in elevator

4 days Mon 3/13/00

Thu 3/16/00

33 Plumbing Contractor, Electric Contractor

Auto Scheduled

Form elevator pit walls

4 days Fri 3/17/00 Wed 3/22/00

35 G.C. Rough Carpenter Crew

Auto Scheduled

Set reinforcing and anchor bolts

4 days Wed 3/29/00

Mon 4/3/00

34 G.C. Rough Carpenter Crew

Auto Scheduled

Pour column piers and foundations

5 days Tue 4/4/00 Mon 4/10/00

37 G.C. Concrete Crew

Auto Scheduled

Pour concrete elevator walls

1 day Thu 3/23/00

Thu 3/23/00

36 G.C. Concrete Crew

Auto Scheduled

Cure elevator wall concrete

7 days Fri 3/24/00 Mon 4/3/00

39 G.C. Labor Crew[10%]

Auto Scheduled

Cure piers and foundations

7 days Tue 4/11/00

Wed 4/19/00

38 G.C. Labor Crew[10%]

Auto Scheduled

Strip wall forms

1 day Tue 4/4/00 Tue 4/4/00 40 G.C. Labor Crew[10%]

Auto Scheduled

Strip column piers and foundation forms

3 days Thu 4/20/00

Mon 4/24/00

41 G.C. Labor Crew

Auto Scheduled

Install pneumatic tube in elevator pit

3 days Wed 4/5/00 Fri 4/7/00 42 Elevator Contractor

Auto Scheduled

Prepare and pour concrete floor in elevator pit

1 day Mon 4/10/00

Mon 4/10/00

44 G.C. Concrete Crew

Auto Scheduled

Steel Erection 45 days Tue 4/25/00

Mon 6/26/00

Auto Scheduled

Erect steel columns, beams and joist - 1st and 2nd floors

2 wks Tue 4/25/00

Mon 5/8/00

43,16 Steel Erection Contractor

Auto Scheduled

Erect steel columns, beams and joist - 3rd floor and roof

2 wks Tue 5/9/00 Mon 5/22/00

47 Steel Erection Contractor

Auto Scheduled

Install miscellaneous iron and bracing - 1st and 2nd floors

2 wks Tue 5/9/00 Mon 5/22/00

47 Steel Erection Contractor[75%]

Auto Scheduled

Install miscellaneous iron and bracing - 3rd floor and roof

2 wks Tue 5/23/00

Mon 6/5/00

48 Steel Erection Contractor[75%]

Auto Scheduled

Install stairs and miscellaneous iron railing

2 wks Tue 6/6/00 Mon 6/19/00

50 Steel Erection Contractor[50%]

Auto Scheduled

Touch-up paint on steel

1 wk Tue 6/20/00

Mon 6/26/00

51 Steel Erection Contractor[20%]

Auto Scheduled

Form and Pour Concrete - Floors and Roof

85 days Tue 5/9/00 Mon 9/4/00

Auto Scheduled

Form 2nd floor including all floor openings

5 days Tue 6/27/00

Mon 7/3/00

52,13,14,15,47 G.C. Rough Carpenter Crew,G.C. Labor Crew[20%]

Auto Scheduled

Install rebar and in-floor utilities (including mechanical, electrical, plumbing)

5 days Tue 5/9/00 Mon 5/15/00

47

G.C. Labor Crew[33%],Plumbing Contractor[33%],Electric Contractor[33%]

Auto Scheduled

Pour 2nd floor slab

4 days Tue 7/4/00 Fri 7/7/00 55,54 G.C. Concrete Crew

Auto Scheduled

Cure 2nd floor slab

7 days Mon 7/10/00

Tue 7/18/00

56 G.C. Labor Crew[10%]

Auto Scheduled

Strip forms from 2nd floor slab

2 days Wed 7/19/00

Thu 7/20/00

57 G.C. Labor Crew

Auto Scheduled

Form 3rd floor including all floor openings

5 days Wed 7/19/00

Tue 7/25/00

57 G.C. Rough Carpenter Crew[50%],G.C. Labor Crew[20%]

Auto Scheduled

Install rebar and in-floor utilities (including mechanical, electrical, plumbing)

5 days Wed 7/19/00

Tue 7/25/00

57

G.C. Labor Crew[33%],Plumbing Contractor[33%],Electric Contractor[33%]

Auto Scheduled

Pour 3rd floor slab

4 days Wed 7/26/00

Mon 7/31/00

60,59 G.C. Concrete Crew

Auto Scheduled

Cure 3rd floor slab

7 days Tue 8/1/00 Wed 8/9/00

61 G.C. Labor Crew[10%]

Auto Scheduled

Strip forms from 3rd floor slab

2 days Thu 8/10/00

Fri 8/11/00 62 G.C. Labor Crew

Auto Scheduled

Form roof slab including all floor openings

5 days Thu 8/10/00

Wed 8/16/00

62 G.C. Rough Carpenter Crew,G.C. Labor Crew[20%]

Auto Scheduled

Install rebar and in-floor utilities (including mechanical, electrical, plumbing)

5 days Thu 8/10/00

Wed 8/16/00

62

G.C. Labor Crew[33%],Plumbing Contractor[33%],Electric Contractor[33%]

Auto Scheduled

Pour roof slab 4 days Thu 8/17/00

Tue 8/22/00

65,64 G.C. Concrete Crew

Auto Scheduled

Cure roof slab 7 days Wed 8/23/00

Thu 8/31/00

66 G.C. Labor Crew[10%]

Auto Scheduled

Strip forms from roof slab

2 days Fri 9/1/00 Mon 9/4/00

67 G.C. Labor Crew

Auto Scheduled

Form 1st floor 4 days Fri 7/21/00 Wed 7/26/00

58 G.C. Rough Carpenter Crew

Auto Scheduled

Install electrical underground

1 wk Fri 7/21/00 Thu 7/27/00

58 Electric Contractor

Auto Scheduled

Install plumbing underground

1 wk Fri 7/21/00 Thu 7/27/00

58 Plumbing Contractor

Auto Scheduled

Install rebar and in-floor utilities

4 days Fri 7/21/00 Wed 7/26/00

58

G.C. Labor Crew[33%],Plumbing Contractor[33%],Electric Contractor[33%]

Auto Scheduled

Pour 1st floor slab

4 days Fri 7/28/00 Wed 8/2/00

69,72,70,71 G.C. Concrete Crew

Auto Scheduled

Cure 1st floor slab

7 days Thu 8/3/00 Fri 8/11/00 73 G.C. Labor Crew[10%]

Auto Scheduled

Strip forms from 1st floor slab

2 days Mon 8/14/00

Tue 8/15/00

74 G.C. Labor Crew

Auto Scheduled

Carpentry Work 15 days Tue 9/5/00 Mon 9/25/00

Auto Scheduled

Install exterior sheathing and metal studs

3 wks Tue 9/5/00 Mon 9/25/00

63,68 Drywall Contractor

Auto Scheduled

Masonry Work 110 days Tue 6/6/00 Mon 11/6/00

Auto Scheduled

Rough-in plumbing at toilets and masonry walls

4 wks Wed 8/16/00

Tue 9/12/00

75,13 Plumbing Contractor

Auto Scheduled

Lay masonry at core, mechanical, and toilets

4 wks Tue 6/6/00 Mon 7/3/00

49,50 Masonry Contractor

Auto Scheduled

Install exterior masonry work

5 wks Tue 9/26/00

Mon 10/30/00

77 Masonry Contractor

Auto Scheduled

Install roof drains

2 days Tue 10/31/00

Wed 11/1/00

81 Roofing Contractor

Auto Scheduled

Install tile in toilet rooms

2 wks Wed 9/13/00

Tue 9/26/00

79 Tile Contractor

Auto Scheduled

Clean masonry 1 wk Tue 10/31/00

Mon 11/6/00

81 Masonry Contractor[50%]

Auto Scheduled

Clean toilet room tile

1 wk Wed 9/27/00

Tue 10/3/00

83 Tile Contractor[50%]

Auto Scheduled

Roofing 31 days Tue 10/31/00

Tue 12/12/00

Auto Scheduled

Install flashing at parapet walls

4 days Tue 10/31/00

Fri 11/3/00 81 Roofing Contractor

Auto Scheduled

Pour lightweight concrete roof fill

2 days Mon 11/6/00

Tue 11/7/00

11,82,87 Roofing Contractor

Auto Scheduled

Install seamless roofing material

5 days Wed 11/15/00

Tue 11/21/00

88FS+5 days Roofing Contractor

Auto Scheduled

Spread stone ballast on seamless roof

5 days Wed 11/22/00

Tue 11/28/00

89 Roofing Contractor

Auto Scheduled

Set rooftop equipment

2 wks Wed 11/29/00

Tue 12/12/00

90 HVAC Contractor

Auto Scheduled

Window wall and store front closures

60 days Tue 10/31/00

Mon 1/22/01

Auto Scheduled

Install window wall aluminum and glass

5 wks Tue 10/31/00

Mon 12/4/00

81 Window Contractor

Auto Scheduled

Install interior stud walls and drywall

5 wks Tue 12/5/00

Mon 1/8/01

93 Drywall Contractor

Auto Scheduled

Install interior doors and hardware

2 wks Tue 1/9/01 Mon 1/22/01

94 G.C. Finish Carpenter Crew

Auto Scheduled

Install store front doors and hardware

3 wks Tue 10/31/00

Mon 11/20/00

81 Window Contractor

Auto Scheduled

Building Finishes 80 days Tue 12/5/00

Mon 3/26/01

Auto Scheduled

Install millwork and wood trim

3 wks Tue 1/9/01 Mon 1/29/01

96,94 G.C. Finish Carpenter Crew

Auto Scheduled

Paint walls and woodwork

4 wks Tue 1/30/01

Mon 2/26/01

98,95 Painting Contractor

Auto Scheduled

Install conduit at ceiling plenum space

3 wks Tue 12/5/00

Mon 12/25/00

93 Electric Contractor

Auto Scheduled

Install duct in ceiling plenum space

3 wks Tue 1/9/01 Mon 1/29/01

94,100 HVAC Contractor

Auto Scheduled

Install ceiling grid

2 wks Tue 1/30/01

Mon 2/12/01

94,101 Drywall Contractor

Auto Scheduled

Install ceiling tile

2 wks Tue 2/13/01

Mon 2/26/01

102 Drywall Contractor

Auto Scheduled

Hang wallpaper

2 wks Tue 2/13/01

Mon 2/26/01

102 Painting Contractor

Auto Scheduled

Install building carpet

4 wks Tue 2/27/01

Mon 3/26/01

99 Carpet Contractor

Auto Scheduled

Install hardware and accessories

3 wks Tue 2/27/01

Mon 3/19/01

99 G.C. Finish Carpenter Crew

Auto Scheduled

Complete interior and exterior sod and plantings

2 wks Tue 2/27/01

Mon 3/12/01

99 Landscape Contractor

Auto Scheduled

Pave, curb, and stripe parking lot

2 wks Tue 3/13/01

Mon 3/26/01

107 Paving Contractor

Auto Scheduled

Elevators 40 days Tue 7/4/00 Mon 8/28/00

Auto Scheduled

Set elevator equipment in shafts

4 wks Tue 7/4/00 Mon 7/31/00

80,45,12 Elevator Contractor

Auto Scheduled

Set equipment in mechanical room

2 wks Tue 8/1/00 Mon 8/14/00

110 Elevator Contractor

Auto Scheduled

Test and align doors and equipment

2 wks Tue 8/15/00

Mon 8/28/00

111 Elevator Contractor

Auto Scheduled

Plumbing 90 days Tue 11/7/00

Mon 3/12/01

Auto Scheduled

Rough-in plumbing in drywall walls

4 wks Tue 12/5/00

Mon 1/1/01

93 Plumbing Contractor

Auto Scheduled

Tie-in fire line riser and set valves

2 wks Tue 11/7/00

Mon 11/20/00

84 Plumbing Contractor

Auto Scheduled

Set plumbing fixtures and trim

3 wks Tue 1/2/01 Mon 1/22/01

85,114,79 Plumbing Contractor

Auto Scheduled

Flush, test, and clean piping and fixtures

2 wks Tue 2/27/01

Mon 3/12/01

99,115,116 Plumbing Contractor

Auto Scheduled

Electrical 139 days Wed 8/16/00

Mon 2/26/01

Auto Scheduled

Rough-in electrical in masonry walls

4 wks Wed 8/16/00

Tue 9/12/00

75,14 Electric Contractor

Auto Scheduled

Rough-in electrical in drywall walls

4 wks Tue 12/5/00

Mon 1/1/01

93 Electric Contractor

Auto Scheduled

Pull wire in conduit and set area transformers

3 wks Tue 12/26/00

Mon 1/15/01

119,100 Electric Contractor

Auto Scheduled

Install and terminate electrical devices

3 wks Tue 1/16/01

Mon 2/5/01

121,120 Electric Contractor

Auto Scheduled

Make electrical terminations for HVAC equipment

2 days Tue 1/16/01

Wed 1/17/01

121,91 Electric Contractor

Auto Scheduled

Install light fixtures - test and clean

2 wks Tue 2/13/01

Mon 2/26/01

102,122 Electric Contractor

Auto Scheduled

Heating and Ventilating - AC

180 days Tue 7/4/00 Mon 3/12/01

Auto Scheduled

Set equipment in mechanical room

2 wks Tue 7/4/00 Mon 7/17/00

80,15 HVAC Contractor

Auto Scheduled

Rough-in mechanical in masonry walls

4 wks Wed 8/16/00

Tue 9/12/00

75 HVAC Contractor

Auto Scheduled

Rough-in mechanical in drywall walls

2 wks Tue 12/5/00

Mon 12/18/00

93 HVAC Contractor

Auto Scheduled

Install duct in building chase

3 wks Tue 12/5/00

Mon 12/25/00

126,127,93 HVAC Contractor

Auto Scheduled

Set HVAC trim and test and balance system

4 wks Tue 2/13/01

Mon 3/12/01

102,129,123 HVAC Contractor

Auto Scheduled

Final Clean-up and Occupancy

60 days Tue 1/9/01 Mon 4/2/01

Auto Scheduled

Install hard tile flooring in common areas

1 wk Tue 1/9/01 Mon 1/15/01

94 Tile Contractor

Auto Scheduled

Clean hard tile floors

4 days Tue 1/16/01

Fri 1/19/01 132 Tile Contractor[50%]

Auto Scheduled

Remove debris from building and do final clean-up

4 days Tue 3/27/01

Fri 3/30/01 ########## G.C. Labor Crew

Auto Scheduled

Substantial completion date

1 day Mon 4/2/01 Mon 4/2/01

134 G.C. Superintendent

Auto Scheduled

Complete Final Inspections

6 days Mon 4/2/01

Mon 4/9/01

Auto Scheduled

Complete elevator inspection and certification

3 days Mon 4/2/01 Wed 4/4/01

134,112 Elevator Contractor

Auto Scheduled

Perform architect's inspection

1 day Thu 4/5/01 Thu 4/5/01 134,108,137

G.C. Superintendent[50%],G.C. Project Management[50%]

Auto Scheduled

Perform local building agency inspection

1 day Fri 4/6/01 Fri 4/6/01 138 G.C. Project Management[50%],G.C. Superintendent[50%]

Auto Scheduled

Perform Fire Marshal's inspection

1 day Mon 4/9/01 Mon 4/9/01

139

G.C. Superintendent[50%],G.C. Project Management[50%]

Auto Scheduled

Complete punch list items from all inspections

2 wks Tue 4/10/01

Mon 4/23/01

140

G.C. Superintendent[11%],G.C. Labor Crew[11%],Plumbing Contractor[11%],Electric Contractor[11%],HVAC Contractor[11%],Drywall Contractor[11%],Carpet Contractor[11%],Paving Contractor[11%],Painting Contractor[11%]

Auto Scheduled

Obtain certificate of occupancy

2 days Tue 4/24/01

Wed 4/25/01

141 G.C. Project Management

Auto Scheduled

Issue final completion documents including warranties

1 day Tue 4/24/01

Tue 4/24/01

141 G.C. Project Management

Auto Scheduled

Issue final request for payment

1 day Thu 4/26/01

Thu 4/26/01

142,143

G.C. Project Management[33%],G.C. Accounting[33%],G.C. General Management[33%]