Page 1 of 13
CUSTOMER:
PROJECT:
SUBMITTED BY:
PH AR M A EN G I N EER S
PLOT NO. 113/A/1 , LANE 8, PHASE II,
IDA CHERLAPALLI, HYDERABAD- 500051 .
Tel No.91-40 27261113 , 27261114
OPERATION QUALIFICATION PROTOCOL FOR HVAC SYSTEM OF
AHU-01
Page 2 of 13
OPERATION QUALIFICATION PROTOCOL APPROVAL
This document is prepared by the documentation team of M/S. PHARMA ENGINEERS
for
AHU TAG Number : ____________________________
PLANT /PROJECT :
CLIENT :
Hence this document before being effective shall be approved by Client / Customer
M/s. PHARMA ENGINEERS:
Name Designation Signature Date
Prepared By
Reviewed By
CLIENT / CUSTOMER:
Name Designation Signature Date
Reviewed By
Approved By
Client: Supplier/ Manufacturer: PHARMA ENGINEERS, HYDERABAD
Equipment: HVAC SYSTEM FOR AHU-01
Page 3 of 13
OPERATION QUALIFICATION (OQ)
TABLE OF CONTENT
1. OBJECTIVE ............................................................................................................................... 4
2. TEST OF ALARMS & INTERLOCKS: ................................................................................. 4
3. CONTROL LOGIC VERIFICATION: .................................................................................. 6
4. UTILITY VERIFICATION: .................................................................................................... 7
5. VERIFICATION OF WATER BALANCING: ..................................................................... 8
Client: Supplier/ Manufacturer: PHARMA ENGINEERS, HYDERABAD
Equipment: HVAC SYSTEM FOR AHU-01
Page 4 of 13
OPERATION QUALIFICATION (OQ)
1. OBJECTIVE
The objective of this document is to qualify and certify the functionality of
HVAC system (TAG NO) with due considerations as specified in DQ of HVAC
System (TAG NO).
2. TEST OF ALARMS & INTERLOCKS:
Sr.no Method of testing Acceptance criteria Observations
1. Switch ON the AHU and observe functionality
The fan & motor of both AHU Supply, Return, Exhaust, Bed rotor and heaters shall start.
2. Switch OFF the AHU and observe functionality
The fan & motor of both AHU Supply, Return, Exhaust, Bed rotor and heaters shall stop.
3. Switch OFF the process blower
Bed Rotor & Heaters shall stop. However, Reactivation Blower Remains ON
4. Switch OFF the reactivation blower
Process Blower, Bed Rotor & Heaters shall stop.
5. Switch OFF the bed rotor while AHU is ON
Heaters shall stop. However, Reactivation Blower, Process Blower Remains ON
6.
While the system is in operation, open any access door of blower
The fan & motor of both AHU Supply, Return, Exhaust, Bed rotor and heaters shall stop.
Client: Supplier/ Manufacturer: PHARMA ENGINEERS, HYDERABAD
Equipment: HVAC SYSTEM FOR AHU-01
Page 5 of 13
OPERATION QUALIFICATION (OQ)
7. Press the Fire Damper Limit Switch
Dampers will close and the fan & motor of both AHU Supply, Return, Exhaust, Bed rotor and heaters shall stop.
8. Manually manipulate the smoke sensor thermostat
Dampers will close and the fan & motor of both AHU Supply, Return, Exhaust, Bed rotor and heaters shall stop.
9.
Emergency Stop: While the machine is in operation, press Emergency Stop button
The fan & motor of both AHU Supply, Return, Exhaust, Bed rotor and heaters shall stop
10. Manually manipulate electrical relay for any motor
The fan & motor of both AHU Supply, Return, Exhaust, Bed rotor and heaters shall stop showing trip indication with alarm
11. Manually remove the pressure switch tubes
Bed Rotor & Heaters shall stop with alarm However, Reactivation Blower, Process Blower Remains on
12. Abnormal noise & Vibration
No abnormal noise& vibration should be observed.
REMARKS (IF ANY): Test Conducted By Test Witnessed By
Client: Supplier/ Manufacturer: PHARMA ENGINEERS, HYDERABAD
Equipment: HVAC SYSTEM FOR AHU-01
Page 6 of 13
OPERATION QUALIFICATION (OQ)
3. CONTROL LOGIC VERIFICATION:
(SENSOR LOCATED IN RETURN DUCT)
CHILLED WATER
ACTUATOR
HOT WATER ACTUATOR
RESULT
TEMPERATURE
HIGH √ X
LOW X √
RELATIVE HUMIDITY
HIGH √ √
LOW X X
REMARKS (IF ANY): Test Conducted By Test Witnessed By
Client: Supplier/ Manufacturer: PHARMA ENGINEERS, HYDERABAD
Equipment: HVAC SYSTEM FOR AHU-01
Page 7 of 13
OPERATION QUALIFICATION (OQ)
4. UTILITY VERIFICATION:
Sr. No.
Component Method of Testing Acceptance Criteria Result
1. Chilled water inlet temperature
Place temperature gauge in inlet chilled water port
NMT 7 deg C
2. Chilled water inlet pressure
Place pressure gauge in inlet chilled water port
NLT 1.5 kg/cm2
3. Hot water inlet temperature
Place temperature gauge in inlet hot water port
NLT 50 deg C
4. Hot water inlet pressure
Place pressure gauge in inlet hot water port
NLT 1 kg/cm2
5. Steam inlet pressure
Place pressure gauge in inlet steam port
NLT 3 kg/cm2
6. Current drawn in AHU Supply Unit
Check through Multi Meter / Clamp meter
The current drawn shall be less than the rated amperage
7. Current drawn in AHU Return Unit
Check through Multi Meter / Clamp meter
The current drawn shall be less than the rated amperage
8. Current drawn in Exhaust Unit
Check through Multi Meter / Clamp meter
The current drawn shall be less than the rated amperage
9. Current drawn in Dehumidifier Unit
Check through Multi Meter / Clamp meter
The current drawn shall be less than the rated amperage
REMARKS (IF ANY): Test Conducted By Test Witnessed By
Client: Supplier/ Manufacturer: PHARMA ENGINEERS, HYDERABAD
Equipment: HVAC SYSTEM FOR AHU-01
Page 8 of 13
OPERATION QUALIFICATION (OQ)
5. VERIFICATION OF WATER BALANCING: PURPOSE: To ensure that the water balancing is performed as per the flow rates mentioned in the room data sheet. PRE-REQUISITES: 1. Duly calibrated pressure meter / gauge. 2. Ensure Manifold header is connected to the main header and water is
circulating. 3. 19mm and 7mm Screw Spanners. 4. 8mm silicon tube. 5. Bucket to collect water.
TEST PROCEDURE: 1. Connect the silicone tubes to the two pressure ports of the balancing valve. 2. Open the ports using the specified spanners and drain the water into the
bucket. 3. Make sure that the supply and return valves were 100% open before taking the
reading. 4. Connect the silicone tubes to the pressure meter and note down the readings. 5. Calculate the flow using the below formula.
Q in M3/Hr = Square root (∆ Pressure in cmHg) × K value
6. Turn the balancing valve wheel as per the K Value until the required flow GPM is achieved.
7. Graph between the K value and flow rate for various sizes are enclosed here. 8. To convert the flow in Cu.mt/hr to GPM, multiply the flow value in Cu.mt/hr
with 4.4 to get the value in GPM. 9. Test results are enclosed with this document.
ACCEPTANCE CRITERIA:
Balancing valve shall be adjusted to flow (GPM) as per designed flow.
However, the acceptance is up to the judgment of experts if any deviation in the readings.
Client: Supplier/ Manufacturer: PHARMA ENGINEERS, HYDERABAD
Equipment: HVAC SYSTEM FOR AHU-01
Page 9 of 13
OPERATION QUALIFICATION (OQ)
REPRINTED ADVANCE MAKE BALANCING VALVE CURVES FOR VARIOUS PIPE SIZES.
Client: Supplier/ Manufacturer: PHARMA ENGINEERS, HYDERABAD
Equipment: HVAC SYSTEM FOR AHU-01
Page 10 of 13
OPERATION QUALIFICATION (OQ)
Client: Supplier/ Manufacturer: PHARMA ENGINEERS, HYDERABAD
Equipment: HVAC SYSTEM FOR AHU-01
Page 11 of 13
OPERATION QUALIFICATION (OQ)
Client: Supplier/ Manufacturer: PHARMA ENGINEERS, HYDERABAD
Equipment: HVAC SYSTEM FOR AHU-01
Page 12 of 13
OPERATION QUALIFICATION (OQ)
Client: Supplier/ Manufacturer: PHARMA ENGINEERS, HYDERABAD
Equipment: HVAC SYSTEM FOR AHU-01
Page 13 of 13
OPERATION QUALIFICATION (OQ)
TEST REPORT FOR WATER BALANCING
Purpose: To determine the flow rate of chilled water and hot water are as per designed flow rate
Status of test At rest Date of Test
INSTRUMENT / EQUIPMENT USED
Name of instrument / equipment
Make
Serial number
Calibrated on Calibration Due
TEST RESULTS
Sr.no Type of
manifold Pipe size
Designed Flow
(USGPM)
Differential pressure
(∆ P in cmHg)
Actual flow (M3 / Hr)
Square root (∆P in cm Hg) × K value
Actual flow (USGPM)
(M3 / Hr * 4.4)
REMARKS (IF ANY): Performed By Checked By