Operation of the C1 Modular Coil in the Coil Test Facility Peer Review

28
NCSX Operation of the C1 Modular Coil in the Coil Test Facility Peer Review June1, 2006 NCSX

description

NCSX. Operation of the C1 Modular Coil in the Coil Test Facility Peer Review. June1, 2006. The objectives of this review are to consider: Installation of the C1 in the CTF Instrumentation and Data Acquisition Test Plan. C1 Operation Review Objective. Close Quarters. - PowerPoint PPT Presentation

Transcript of Operation of the C1 Modular Coil in the Coil Test Facility Peer Review

NCSX

Operation of the C1 Modular Coil in the Coil Test Facility

Peer Review

June1, 2006

NCSX

June 1,2006 2

NCSX

C1 Operation Review Objective

• The objectives of this review are to consider:

– Installation of the C1 in the CTF

– Instrumentation and Data Acquisition

– Test Plan

June 1,2006 3

NCSXClose Quarters

The New Cryostat Mostly Fills The Test Enclosure

June 1,2006 4

NCSXES&H Changes

• Magnetic field exposure for personnel is slightly higher for the C1 test. The barrier distance increases from 15 feet to 23 feet.

• The C1 cryostat is large enough to impede access to and egress from the test enclosure. Three access doors allow entrance to the enclosure with necessary procedure changes (RLM: von Halle).– May become classified as a Confined Space

June 1,2006 5

NCSX

C1 Installation

• 304 stainless steel legs (SE144-030)for strength– One leg fixed in

X&Y, three on roller supports

• EM loads on baseplate for boil-off reservoir require tie-downs

June 1,2006 6

NCSXCoil Flow Diagram

The C1 Coil Has Been Plumbed As 9 Separate Single-Phase Flow Paths

and

One Two-Phase Supply For The Lead Block Bleeds

June 1,2006 7

NCSXThe Plumbing B-Plan

• Teflon tubing with Swagelok joints and custom backing inserts were not reliable– 40 psig was the best pressure achieved– The previous style of insulating G-10 pipe

nipples will be used in the plumbing

June 1,2006 8

NCSXBus Conductor

500 MCM Welding Cable Insulated with Teflon FEP Shrink Tubing Has Successfully Been Tested to 58 kV

June 1,2006 9

NCSXBus Bracing

A Robust Support Has Been Fabricated To Both Partially Relieve The Leads From Load And To React Bus-Bus Forces

Clamping force of 11300 N/m or 65 lbf/in is required on close conductors

D. Williamson has asserted that the coil leads are not particularly fragile

June 1,2006 10

NCSXLead Insulation

• Maximum voltage across coil is expected to be approximately 499 volts – The G11CR lead sleeves designed and

machined for the production coils are being used for this test set-up

June 1,2006 11

NCSX

June 1,2006 12

NCSX

June 1,2006 13

NCSX

June 1,2006 14

NCSX

June 1,2006 15

NCSX

June 1,2006 16

NCSX

June 1,2006 17

NCSX

June 1,2006 18

NCSXTest Objectives

• Main purpose – calibrate FE models with actual data– Improves confidence with which models can

be used for future what-if inquiries.

• Secondary purpose – assess cooldown/recovery performance from ambient temperature and after pulses

June 1,2006 19

NCSXDimensional/Deflection Measurements

• 3 measurement approaches

– Extensive strain gauge array

– Mechanical displacement measurement

– Manual measurement of total width of both winding packs before and after

June 1,2006 20

NCSXStrain Gauge Locations

• 15 of K. Freudenberg’s 20 requested locations are instrumented

June 1,2006 21

NCSXMechanical Measurement

Box Dimensions are 94” X 116.5” ID with wall thickness of 6”

Three tubes needed

1. 9.5 foot outer tube ss tube, .875 OD, .675” ID. (purchased)

2. 8 inch ss tube (box entrance) .75” OD, .6875” ID

3. 10 foot inner ss tube ¼ diameter

Three angles needed (2” X 3”) (.1875 thick). These may be from local boat supply store. (Tentatively purchased two anchors.)

June 1,2006 22

NCSXThermal Measurements

• Extensive strain gauge and t/c data collection system

• V/I resistance inference– This is a key feature as it is prototypical of the

first-plasma machine protection scheme– ADMINISTRATIVE control of coil temperature

through resistance value (wait for next pulse until cool)

June 1,2006 23

NCSXTemperature Differentials

• Fiberglass convection insulation will be installed on coil with fiberglass rope

• Only outer aspect of coil will be exposed to cooling

• Two T/C’s will be installed near the winding packs on coolant tubes. The resulting temperatures will be used to monitor the deltaT between the windings and the MCWF.

• A 50C difference has been recommended.

June 1,2006 24

NCSXTest Sequence

– Lift the both ends of the cable bus assembly and megger pole-pole to 3 kV

– Restore the bus at the coil end and megger the warm coil to ground to 7.5 kV

– Completely restore the bus and measure the warm circuit resistance from the rectifier room

– Collect winding pack width data prior to cool-down– Cool the coil to ~80K with proper data collection

June 1,2006 25

NCSXTest Sequence (cont.)

– Measure the cold circuit resistance from the rectifier room

– Perform basic shot sequence with T/C, strain archival and V/I cooldown checks

– Warm up to install mechanical measurement rig– 5 kA room temperature pulse for K.F. – Cool down, repeat shot sequence, collect previous

data plus displacements– Warm up facility– Measure final winding pack dimensions

June 1,2006 26

NCSXCurrent Waveforms for Test

C1 Waveforms

0

5000

10000

15000

20000

25000

30000

35000

40000

-1 -0.5 0 0.5 1 1.5

Time (seconds)

Cu

rren

t (a

mp

eres

)

Series1

Series2

Series3

Series4

The 2T Scenario from the Rev. 4 GRD offers 36.5 kA with

an I**2t of 1.15e9 a**2sec.

June 1,2006 27

NCSXProtective Circuitry

• Protective Settings– Maximum “On” time – 2.3 seconds - no

change from TRC– Tau (thermal) – 200 seconds – no change– Minimum cycle time – 900 seconds – no

change– I**2t max – 1.6e9 a**2sec – no change– Imax – 38.5 kA up from 33 kA

June 1,2006 28

NCSX