OPERATION MANAGEMENT (CASE: MRP AT A-CAT CORP.)

44
18 th of May 2015 Operations Management For Competitive Advantage Group 4 Azis Rizky Prawira 1406513344 Camelia Indah Murniwati 1406513376 Jejen Nugraha 1406589114 Muhammad Yuriansyah Putra 1406514100 Nasrul Nabil Sangadji 1406589303

description

Tugas Kelompok Analisis Kasus Mata Kuliah Manajemen Operasi MM UI Tahun 2015.

Transcript of OPERATION MANAGEMENT (CASE: MRP AT A-CAT CORP.)

  • 18th of May 2015

    Operations Management For Competitive Advantage

    Group 4

    Azis Rizky Prawira 1406513344

    Camelia Indah Murniwati 1406513376

    Jejen Nugraha 1406589114

    Muhammad Yuriansyah Putra 1406514100

    Nasrul Nabil Sangadji 1406589303

  • Company Background of A-CAT Corp.

    Problem Identification

    Theory of MRP

    Analysis

    Conclusion & Lesson Learned

    OUTLINE

  • Mid-sized manufacturer and distributor of domestic electrical

    appliances.

    Operated two medium-sized facilities in Vidarbha region of Maharashtra states of India.

    Focus on the rural segment (low-income customers).

    A-CATs manufacturing units had been in operation since 1986.

    Annual sales of Rs6,000,000 US$120,000.

    Had about 35 employees.

    Manufactured electrical appliances for household use: television signal boosters, transformers, FM radio kits, electronic ballasts, battery chargers, voltage regulators, etc.

    Company Background: A-CAT Corp.

  • Sunita Menon was assigned the task of preparing

    the operation plan for the next eight weeks for the product P0110.

    The basic problem Menon Faced was deciding how to produce economically.

    After collecting the data (Bill of Materials, Product Structure Diagram, Master Schedule, On Hand Inventory, Costs Associated), Menon reached a different answer for every lot-sizing technique that she applied.

    Problem Identification

  • MRP is a planning approach to material / material

    that ignoring the past, but look to the demands or needs of future production.

    MRP can be applied for planning materials / parts / components or sub-assemblies that depend on the product or inventory.

    MRP is a computerized information system is built specifically to help manufacturers manage inventory and schedule of reservations / reception material / materials.

    Theory of MRP

  • MRP Input

    Inventory

    transactions

    Inventory

    records

    Other

    sources

    of demand

    Authorized

    master production

    schedule

    Bills of

    materials

    Engineering

    and process

    designs

    Material

    requirements

    plan

    MRP

    explosion

  • Information for MRP

    Bill of Materials (BOM) of all products for certain that consists of several levels (level).

    Number parts / components are unique and permanent. The existence of Master Production Schedule (MPS) of production. The

    final result contains the time and amount. The amount of material requirements / Notes Inventory (Inventory Record)

    for each part / component products. Stock code number. Lead time for each part / component in an exact figure. The required amount equal to that of the production schedule.

    BOM Sample

  • Master Production Scheduling

    Master production schedule (MPS): Total aggregate production for all types of "family" seats

  • Inventory Record

    Supply Notes : A record that shows an items lot-size policy, lead time, and various time-phased data.

    Gross requirements : The total demand derived from all parent production plans.

    Scheduled receipts are orders that have been placed but not yet completed.

    projected on-hand inventory: An estimate of the amount of inventory available each week after gross requirements have been satisfied.

    planned receipts : Orders that are not yet released to the shop or supplier.

    planned order releases : An indication of when an order for a specified quantity of an item is to be issued.

  • Lot Sizing in MRP Systems

    Lot sizes the part quantities issued in the planned order receipt and planned order release sections of an MRP schedule.

  • Based on the data (Bill of Materials, Product

    Structure Diagram, Master Schedule, On Hand Inventory, Costs Associated), Lot Sizes will be determined by using Lot Sizing Strategies below:

    1. Lot for Lot (L4L)

    2. Economic Order Quantity (EOQ)

    3. Least Total Cost (LTC)

    4. Least Unit Cost (LUC)

    Analysis

  • Bill of Material (BOM)

    Level

    0

    1

    2

    (1)

    (2)(2)

    (4) (3)

    (Quantity)

    Dependent Demand

    Independent Demand

  • Master Production ScheduleThe End Item: P0110

  • On Hand Inventory

  • Cost

  • Lot-for-Lot (L4L) is the most commont technique. It

    Sets planned orders to exactly match the net requirements

    Produces exactly what is needed each week with no inventory carroed over into future periods.

    Minimizes carrying cost.

    Does not take into account setup costs or capacity limitations.

    1. Lot for Lot (L4L)

  • MRP Explosion Calculations

    Item -4 -3 -2 -1 1 2 3 4 5 6 7 8

    P0110 Gross requirement 400 350 300 450 300 450 225 525

    Q L4L Scheduled receipts

    LT 2 Projected available balance 240 240 240 240 0 0 0 0 0 0 0 0

    OH 240 Net requirements 160 350 300 450 300 450 225 525

    SS 0 Planned order receipts 160 350 300 450 300 450 225 525

    Planned order release 160 350 300 450 300 450 225 525

    Week

    MRP Explosion Calculations

    Item -4 -3 -2 -1 1 2 3 4 5 6 7 8

    POX Gross requirement 320 700 600 900 600 900 450 1050

    Q L4L Scheduled receipts

    LT 1 Projected available balance 500 500 180 0 0 0 0 0 0 0

    OH 500 Net requirements 0 520 600 900 600 900 450 1050

    SS 0 Planned order receipts 0 520 600 900 600 900 450 1050

    Planned order release 0 520 600 900 600 900 450 1050

    Week

    Step 1: MRP Explosion Calculations

  • MRP Explosion Calculations

    Item -4 -3 -2 -1 1 2 3 4 5 6 7 8

    POY Gross requirement 320 700 600 900 600 900 450 1050

    Q L4L Scheduled receipts

    LT 1 Projected available balance 340 340 20 0 0 0 0 0 0 0

    OH 340 Net requirements 0 680 600 900 600 900 450 1050

    SS 0 Planned order receipts 0 680 600 900 600 900 450 1050

    Planned order release 0 680 600 900 600 900 450 1050

    Week

    MRP Explosion Calculations

    Item -4 -3 -2 -1 1 2 3 4 5 6 7 8

    P1X1 Gross requirement 2080 2400 3600 2400 3600 1800 4200

    Q L4L Scheduled receipts

    LT 1 Projected available balance 500 500 0 0 0 0 0 0 0

    OH 500 Net requirements 1580 2400 3600 2400 3600 1800 4200

    SS 0 Planned order receipts 1580 2400 3600 2400 3600 1800 4200

    Planned order release 1580 2400 3600 2400 3600 1800 4200

    Week

    MRP Explosion Calculations

    Item -4 -3 -2 -1 1 2 3 4 5 6 7 8

    P1X2 Gross requirement 1560 1800 2700 1800 2700 1350 3150

    Q L4L Scheduled receipts

    LT 1 Projected available balance 600 600 0 0 0 0 0 0 0

    OH 600 Net requirements 960 1800 2700 1800 2700 1350 3150

    SS 0 Planned order receipts 960 1800 2700 1800 2700 1350 3150

    Planned order release 960 1800 2700 1800 2700 1350 3150

    Week

  • Step 2: Lot-for-Lot Run Size for an MRP Schedule

    P0110

    Week Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost

    1 160 160 0 0 500 500

    2 350 350 0 0 500 1000

    3 300 300 0 0 500 1500

    4 450 450 0 0 500 2000

    5 300 300 0 0 500 2500

    6 450 450 0 0 500 3000

    7 225 225 0 0 500 3500

    8 525 525 0 0 500 4000

    P0X

    Week Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost

    -1 520 520 0 0 400 400

    1 600 600 0 0 400 800

    2 900 900 0 0 400 1200

    3 600 600 0 0 400 1600

    4 900 900 0 0 400 2000

    5 450 450 0 0 400 2400

    6 1050 1050 0 0 400 2800

    POY

    Week Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost

    -1 680 680 0 0 350 350

    1 600 600 0 0 350 700

    2 900 900 0 0 350 1050

    3 600 600 0 0 350 1400

    4 900 900 0 0 350 1750

    5 450 450 0 0 350 2100

    6 1050 1050 0 0 350 2450

  • P1X1

    Week Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost

    -2 1580 1580 0 0 430 430

    -1 2400 2400 0 0 430 860

    1 3600 3600 0 0 430 1290

    2 2400 2400 0 0 430 1720

    3 3600 3600 0 0 430 2150

    4 1800 1800 0 0 430 2580

    5 4200 4200 0 0 430 3010

    P1X2

    Week Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost

    -2 960 960 0 0 400 400

    -1 1800 1800 0 0 400 800

    1 2700 2700 0 0 400 1200

    2 1800 1800 0 0 400 1600

    3 2700 2700 0 0 400 2000

    4 1350 1350 0 0 400 2400

    5 3150 3150 0 0 400 2800

    Step 3: Total Cost Calculation for L4L

    Item Cost

    P0110 4,000

    P0X 2,800

    P0Y 2,450

    P1X1 3,010

    P1X2 2,800

    Total Cost L4L 15,060

  • 2. Economic Order Quantity (EOQ)

    Step 1: EOQ Calculations

    D = Annual DemandH = Annual Holding CostS = Setup Cost

    Economic order quantity (EOQ) is the order quantity that minimizes total inventory holding costs and ordering costs. It is one of the oldest classical production scheduling models.

  • Step 2: MRP Explosion Calculations

    Lv 0 (P0110)

    LT :2 -2 -1 1 2 3 4 5 6 7 8

    Gross requirement 400 350 300 450 300 450 225 525 D = 17940

    schedule receipts H = 52

    projected on hand 240 S = 500

    net requirements 160 350 300 450 300 450 225 525 2DS/H = 345000

    Planned order receipts 588 588 588 588 588 EOQ = 588

    Planned Ending Inventory 428 78 366 504 204 342 117 180

    Planned order releases 588 588 588 588 588 Total Cost : 4719

    EOQ = 588

    Lv 1 (POX)

    LT :1 -3 -2 -1 1 2 3 4 5 6 7 8

    Gross requirement 1176 0 1176 1176 0 1176 0 1176 D = 34970

    schedule receipts H = 16.9

    projected on hand 500 S = 400

    net requirements 676 1176 1176 1176 1176 2DS/H = 1655385

    Planned order receipts 1287 1287 1287 1287 1287 EOQ = 1287

    Planned Ending Inventory 611 722 833 944 1055

    Planned order releases 1287 1287 1287 1287 1287 Total Cost : 3354

    EOQ = 1287

    Lv 1 (POY)

    LT :1 -3 -2 -1 1 2 3 4 5 6 7 8

    Gross requirement 1176 0 1176 1176 0 1176 0 1176 D = 36010

    schedule receipts H = 9.1

    projected on hand 340 S = 350

    net requirements 836 0 1176 1176 0 1176 0 1176 2DS/H = 2770000

    Planned order receipts 1665 1665 1665 1665 EOQ = 1665

    Planned Ending Inventory 829 1318 142 631 1120

    Planned order releases 1665 1665 1665 1665 Total Cost : 2107

    EOQ = 1665

  • Lv 2 (P1X1)

    LT :1 -4 -3 -2 -1 1 2 3 4 5 6 7 8

    Gross requirement 5148 0 5148 5148 0 5148 0 5148 D = 164060

    schedule receipts H = 1.3

    projected on hand 500 S = 430

    net requirements 4648 0 5148 5148 0 5148 0 5148 2DS/H = 108532000

    Planned order receipts 10418 10418 10418 EOQ = 10418

    Planned Ending Inventory 5770 622 5892 744 6014

    Planned order releases 10418 10418 10418 Total Cost : 1766

    EOQ = 10418

    Lv 2 (P1X2)

    LT :1 -4 -3 -2 -1 1 2 3 4 5 6 7 8

    Gross requirement 3861 0 3861 3861 0 3861 0 3861 D = 121582.5

    schedule receipts H = 3.9

    projected on hand 600 S = 400

    net requirements 3261 0 3861 3861 0 3861 0 3861 2DS/H = 24940000

    Planned order receipts 4994 4994 4994 4994 EOQ = 4994

    Planned Ending Inventory 1733 2866 3999 138 1271

    Planned order releases 4994 4994 4994 4994 Total Cost : 2351

    EOQ = 4994

  • Step 3: EOQ Run Size for an MRP ScheduleP0110

    Week Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost

    1 160 588 428 428 500 928

    2 350 0 78 78 0 1006

    3 300 588 366 366 500 1872

    4 450 588 504 504 500 2876

    5 300 0 204 204 0 3080

    6 450 588 342 342 500 3922

    7 225 0 117 117 0 4039

    8 525 588 180 180 500 4719

    P0X

    Week Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost

    -2 676 1287 611 199 400 599

    -1 0 0 0 0 0 599

    1 1176 1287 722 235 400 1233

    2 1176 1287 833 271 400 1904

    3 0 0 0 0 0 1904

    4 1176 1287 944 307 400 2611

    5 0 0 0 0 0 2611

    6 1176 1287 1055 343 400 3354

    POY

    Week Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost

    -2 836 1665 829 145 350 495

    -1 0 0 0 0 0 495

    1 1176 1665 1318 231 350 1076

    2 1176 0 142 25 0 1101

    3 0 0 0 0 0 1101

    4 1176 1665 631 110 350 1561

    5 0 0 0 0 0 1561

    6 1176 1665 1120 196 350 2107

  • P1X1

    Week Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost

    -3 4648 10418 5770 144 430 574

    -2 0 0 0 0 0 574

    -1 5148 0 622 16 0 590

    1 5148 10418 5892 147 430 1167

    2 0 0 0 0 0 1167

    3 5148 0 744 19 0 1186

    4 0 0 0 0 0 1186

    5 3861 10418 6014 150 430 1766

    P1X2

    Week Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost

    -3 3261 4994 1733 130 400 530

    -2 0 0 0 0 0 530

    -1 3861 4994 2866 215 400 1145

    1 3861 4994 3999 300 400 1845

    2 0 0 0 0 0 1845

    3 3861 0 138 10 0 1855

    4 0 0 0 0 0 1855

    5 3861 4994 1271 95 400 2351

    Step 4: Total Cost Calculation for EOQ

    ITEM COST (In Rs)

    P0110 4719

    POX 3354

    POY 2107

    P1X1 1766

    P1X2 2351

    TOTAL 14296

    Total EOQ Cost

  • 3. Least Total Cost (LTC)

    Least Total Cost (LTC) is a dynamic lot-sizing technique that calculates the order quantity by comparing the carrying cost and the setup (or ordering) cost for various lot sizes and then selects the lot in which these are most nearly equal.

  • Step 1

    Step 2

    Level 0P0110

    Week

    1

    2

    3

    4

    5

    6

    7

    8

    300

    450

    225

    525

    Net Requirement

    400

    350

    300

    450

    LTCWeek Quantity Ordered Carrying Cost Setup Cost Total Cost Different1 160 0 500 500 500

    1-2 510 350 500 850 150

    1-3 810 950 500 1450 450

    1-4 1260 2300 500 2800 1800

    1-5 1560 3500 500 4000 3000

    1-6 2010 5750 500 6250 5250

    1-7 2235 7100 500 7600 6600

    1-8 2760 10775 500 11275 10275

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Different

    3 300 0 500 500 500

    3-4 750 450 500 950 50

    3-5 1050 1050 500 1550 550

    3-6 1500 2400 500 2900 1900

    3-7 1725 3300 500 3800 2800

    3-8 2250 5925 500 6425 5425

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Different

    5 300 0 500 500 500

    5-6 750 450 500 950 50

    5-7 975 900 500 1400 400

    5-8 1500 2475 500 2975 1975

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Different

    7 225 0 500 500 500

    7-8 750 525 500 1025 25

    Week Net Requirement Prod. Qty Ending Inv. Holding Cost Setup Cost Total Cost

    1 160 510 350 350 500 850

    2 350 0 0 0 0 850

    3 300 750 450 450 500 1800

    4 450 0 0 0 0 1800

    5 300 750 450 450 500 2750

    6 450 0 0 0 0 2750

    7 225 750 525 525 500 3775

    8 525 0 0 0 0 3775

    Item Inventory

    P0110 240

    POX 500

    POY 340

    P1X1 500

    P1X2 600

    Item Cost/Unit Set Up Cost

    P0110 200 500

    POX 65 400

    POY 35 350

    P1X1 5 430

    PIX2 15 400

  • Level 1P0X

    LTCStep 1

    Step 2

    Item Inventory Qty

    P0110 240 1

    POX 500 2

    POY 340 2

    P1X1 500 4

    P1X2 600 3

    Week Tot. Req

    1 1020

    2 0

    3 1500

    4 0

    5 1500

    6 0

    7 1500

    8 0

    750

    0

    750

    0

    Net Requirement

    510

    0

    750

    0

    Item Cost/Unit Set Up Cost

    P0110 200 500

    POX 65 400

    POY 35 350

    P1X1 5 430

    PIX2 15 400

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Different

    1 520 0 400 400 400

    1-2 520 0 400 400 400

    1-3 2020 975 400 1375 575

    1-4 2020 975 400 1375 575

    1-5 3520 2925 400 3325 2525

    1-6 3520 2925 400 3325 2525

    1-7 5020 5850 400 6250 5450

    1-8 5020 5850 400 6250 5450

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Different

    3 1500 0 400 400 400

    3-4 1500 0 400 400 400

    3-5 3000 975 400 1375 575

    3-6 3000 975 400 1375 575

    3-7 4500 2925 400 3325 2525

    3-8 4500 2925 400 3325 2525

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Different

    5 1500 0 400 400 400

    5-6 1500 0 400 400 400

    5-7 3000 975 400 1375 575

    5-8 3000 975 400 1375 575

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Different

    7 1500 0 400 400 400

    7-8 1500 0 400 400 400

    Week Net Requirement Prod. Qty Ending Inv. Holding Cost Setup Cost Total Cost

    1 520 520 0 0 400 400

    2 0 0 0 0 0 400

    3 1500 1500 0 0 400 800

    4 0 0 0 0 0 800

    5 1500 1500 0 0 400 1200

    6 0 0 0 0 0 1200

    7 1500 1500 0 0 400 1600

    8 0 0 0 0 0 1600

  • Level 1P0Y

    LTC

    Item Inventory Qty

    P0110 240 1

    POX 500 2

    POY 340 2

    P1X1 500 4

    P1X2 600 3

    Week Tot. Req

    1 1020

    2 0

    3 1500

    4 0

    5 1500

    6 0

    7 1500

    8 0

    750

    0

    750

    0

    Net Requirement

    510

    0

    750

    0

    Item Cost/Unit Set Up Cost

    P0110 200 500

    POX 65 400

    POY 35 350

    P1X1 5 430

    PIX2 15 400

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Different

    1 680 0 350 350 350

    1-2 680 0 350 350 350

    1-3 2180 525 350 875 175

    1-4 2180 525 350 875 175

    1-5 3680 1575 350 1925 1225

    1-6 3680 1575 350 1925 1225

    1-7 5180 3150 350 3500 2800

    1-8 5180 3150 350 3500 2800

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Different

    5 1500 0 350 350 350

    5-6 1500 0 350 350 350

    5-7 3000 525 350 875 175

    5-8 3000 525 350 875 175

    Step 1

    Step 2

    Week Net Requirement Prod. Qty Ending Inv. Holding Cost Setup Cost Total Cost

    1 680 2180 1500 263 350 613

    2 0 0 1500 263 0 875

    3 1500 0 0 0 0 875

    4 0 0 0 0 0 875

    5 1500 3000 1500 263 350 1487.5

    6 0 0 1500 263 0 1750

    7 1500 0 0 0 0 1750

    8 0 0 0 0 0 1750

  • Level 2P1X1

    LTC

    Item Inventory Qty

    P0110 240 1

    POX 500 2

    POY 340 2

    P1X1 500 4

    P1X2 600 3

    Week Tot. Req

    1 2080

    2 0

    3 6000

    4 0

    5 6000

    6 0

    7 6000

    8 0

    1500

    0

    1500

    0

    Net Requirement

    520

    0

    1500

    0

    Item Cost/Unit Set Up Cost

    P0110 200 500

    POX 65 400

    POY 35 350

    P1X1 5 430

    PIX2 15 400

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Different

    1 1580 0 430 430 430

    1-2 1580 0 430 430 430

    1-3 7580 300 430 730 130

    1-4 7580 300 430 730 130

    1-5 13580 900 430 1330 470

    1-6 13580 900 430 1330 470

    1-7 19580 1800 430 2230 1370

    1-8 19580 1800 430 2230 1370

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Different

    5 6000 0 430 430 430

    5-6 6000 0 430 430 430

    5-7 12000 300 430 730 130

    5-8 12000 300 430 730 130

    Step 1

    Step 2Week Net Requirement Prod. Qty Ending Inv. Holding Cost Setup Cost Total Cost

    1 1580 7580 6000 150 430 580

    2 0 0 6000 150 0 730

    3 6000 0 0 0 0 730

    4 0 0 0 0 0 730

    5 6000 12000 6000 150 430 1310

    6 0 0 6000 150 0 1460

    7 6000 0 0 0 0 1460

    8 0 0 0 0 0 1460

  • Level 2P1X2

    LTC

    Item Inventory Qty

    P0110 240 1

    POX 500 2

    POY 340 2

    P1X1 500 4

    P1X2 600 3

    Week Tot. Req

    1 1560

    2 0

    3 4500

    4 0

    5 4500

    6 0

    7 4500

    8 0

    1500

    0

    1500

    0

    Net Requirement

    520

    0

    1500

    0

    Item Cost/Unit Set Up Cost

    P0110 200 500

    POX 65 400

    POY 35 350

    P1X1 5 430

    PIX2 15 400

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Different

    1 960 0 400 400 400

    1-2 960 0 400 400 400

    1-3 5460 675 400 1075 275

    1-4 5460 675 400 1075 275

    1-5 9960 2025 400 2425 1625

    1-6 9960 2025 400 2425 1625

    1-7 14460 4050 400 4450 3650

    1-8 14460 4050 400 4450 3650

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Different

    5 4500 0 400 400 400

    5-6 4500 0 400 400 400

    5-7 9000 675 400 1075 275

    5-8 9000 675 400 1075 275

    Step 1

    Step 2Week Net Requirement Prod. Qty Ending Inv. Holding Cost Setup Cost Total Cost

    1 960 5460 4500 338 400 738

    2 0 0 4500 338 0 1075

    3 4500 0 0 0 0 1075

    4 0 0 0 0 0 1075

    5 4500 9000 4500 338 400 1813

    6 0 0 4500 338 0 2150

    7 4500 0 0 0 0 2150

    8 0 0 0 0 0 2150

  • Step 3: Total Cost Calculation for LTC

    Item Cost

    P0110 3,775

    P0X 1,600

    P0Y 1,750

    P1X1 1,460

    P1X2 2,150

    Total Cost 10,735

  • Least unit cost method a dynamic lot-sizing

    technique that adds ordering and inventory carryingcost for each trial lot size and divides by the numberof units in each lot size, picking the lot size with thelowest unit cost.

    4. Least Unit Cost (LUC)

  • Step 1

    Step 2

    Level 0P0110

    LUCWeek Quantity Ordered Carrying Cost Setup Cost Total Cost Unit Cost

    1 160 0 500 500 3.13

    1-2 510 350 500 850 1.67

    1-3 810 950 500 1450 1.79

    1-4 1260 2300 500 2800 2.22

    1-5 1560 3500 500 4000 2.56

    1-6 1200 5750 500 6250 5.21

    1-7 2235 7100 500 7600 3.40

    1-8 2760 10775 500 11275 4.09

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Unit Cost

    3 300 0 500 500 1.7

    3-4 750 450 500 950 1.3

    3-5 1050 1050 500 1550 1.5

    3-6 1500 2400 500 2900 1.9

    3-7 1725 3300 500 3800 2.2

    3-8 2250 5925 500 6425 2.9

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Unit Cost

    5 300 0 500 500 1.7

    5-6 750 450 500 950 1.3

    5-7 975 900 500 1400 1.4

    5-8 1500 2475 500 2975 2.0

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Unit Cost

    7 225 0 500 500 2.2

    7-8 750 525 500 1025 1.4

    Week Net Requirement Prod. Qty Ending Inv. Holding Cost Setup Cost Total Cost

    1 160 510 350 350 500 850

    2 350 0 0 0 0 850

    3 300 750 450 450 500 1800

    4 450 0 0 0 0 1800

    5 300 750 450 450 500 2750

    6 450 0 0 0 0 2750

    7 225 750 525 525 500 3775

    8 525 0 0 0 0 3775

  • Step 1

    Step 2

    Level 1P0X

    LUCWeek Quantity Ordered Carrying Cost Setup Cost Total Cost Unit Cost

    -1 0 0 0 0 0

    -1-0 520 0 400 400 0.77

    -1-1 1120 195 400 595 0.53

    -1-2 2020 780 400 1180 0.58

    -1-3 2620 1365 400 1765 0.67

    -1-4 3520 2535 400 2935 0.83

    -1-5 3970 3266.25 400 3666.25 0.92

    -1-6 5020 5313.75 400 5713.75 1.14

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Unit Cost

    2 900 0 400 400 0.44

    2-3 1500 195 400 595 0.40

    2-4 2400 780 400 1180 0.49

    2-5 2850 1218.75 400 1618.75 0.57

    2-6 3900 2583.75 400 2983.75 0.77

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Unit Cost

    4 900 0 400 400 0.44

    4-5 1350 146.25 400 546.25 0.40

    4-6 2400 828.75 400 1228.75 0.51

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Unit Cost

    6 1050 0 400 400 0.38

    Week Net Requirement Prod. Qty Ending Inv. Holding Cost Setup Cost Total Cost

    -1 0 0 180 58.5 0 58.5

    0 520 1120 600 195 400 653.5

    1 600 0 0 0 0 653.5

    2 900 1500 600 195 400 1248.5

    3 600 0 0 0 0 1248.5

    4 900 1350 450 146.25 400 1794.75

    5 450 0 0 0 0 1794.75

    6 1050 1050 0 0 400 2194.75

  • Step 1

    Step 2

    Level 1P0Y

    LUCWeek Quantity Ordered Carrying Cost Setup Cost Total Cost Unit Cost

    -1 0 0 0 0 0

    -1-0 680 0 350 350 0.51

    -1-1 1280 105 350 455 0.36

    -1-2 2180 420 350 770 0.35

    -1-3 2780 735 350 1085 0.39

    -1-4 3680 1365 350 1715 0.47

    -1-5 4130 1758.75 350 2108.75 0.51

    -1-6 5180 2861.25 350 3211.25 0.62

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Unit Cost

    3 600 0 350 350 0.58

    3-4 1500 157.5 350 507.5 0.338

    3-5 1950 315 350 665 0.341

    3-6 3000 866.25 350 1216.25 0.41

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Unit Cost

    5 450 0 350 350 0.78

    5-6 1500 183.75 350 533.75 0.36

    Week Net Requirement Prod. Qty Ending Inv. Holding Cost Setup Cost Total Cost

    -1 0 0 20 3.5 0 3.5

    0 680 2180 1500 262.5 350 616

    1 600 0 900 157.5 0 773.5

    2 900 0 0 0 0 773.5

    3 600 1500 900 157.5 350 1281

    4 900 0 0 0 0 1281

    5 450 1500 1050 183.75 350 1814.75

    6 1050 0 0 0 0 1814.75

  • Step 1

    Step 2

    Level 2P1X1

    LUC

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Unit Cost

    -1 780 0 430 430 0.55

    -1-0 3580 70 430 500 0.14

    -1-1 5980 190 430 620 0.10

    -1-2 9580 460 430 890 0.093

    -1-3 11980 700 430 1130 0.094

    -1-4 15580 1150 430 1580 0.10

    -1-5 17380 1420 430 1850 0.11

    -1-6 21580 2155 430 2585 0.12

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Unit Cost

    3 2400 0 430 430 0.18

    3-4 3600 90 430 520 0.14

    3-5 7800 180 430 610 0.078

    3-6 11400 495 430 925 0.081

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Unit Cost

    6 4200 0 430 430 0.10

    Week Net Requirement Prod. Qty Ending Inv. Holding Cost Setup Cost Total Cost

    -1 780 9580 8800 220 430 220

    0 2800 0 6000 150 0 370

    1 2400 0 3600 90 0 460

    2 3600 0 0 0 0 460

    3 2400 7800 5400 135 430 1025

    4 3600 0 1800 45 0 1070

    5 1800 0 0 0 0 1070

    6 4200 4200 0 0 430 1500

  • Step 1

    Step 2

    Level 2P1X2

    LUC

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Unit Cost

    -1 360 0 400 400 1.11

    -1-0 2460 157.5 400 557.5 0.23

    -1-1 4260 427.5 400 827.5 0.19

    -1-2 6960 1035 400 1435 0.21

    -1-3 8760 1575 400 1975 0.23

    -1-4 11460 2587.5 400 2987.5 0.26

    -1-5 12810 3195 400 3595 0.28

    -1-6 15960 4848.75 400 5248.75 0.33

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Unit Cost

    2 2700 0 400 400 0.15

    2-3 4500 135 400 535 0.12

    2-4 7200 540 400 940 0.13

    2-5 8550 843.75 400 1243.75 0.15

    2-6 11700 1788.75 400 2188.75 0.19

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Unit Cost

    4 2700 0 400 400 0.15

    4-5 4050 101.25 400 501.25 0.12

    4-6 7200 573.75 400 973.75 0.14

    Week Quantity Ordered Carrying Cost Setup Cost Total Cost Unit Cost

    6 3150 0 400 400 0.13

    Week Net Requirement Prod. Qty Ending Inv. Holding Cost Setup Cost Total Cost

    -1 360 4260 3900 97.5 400 97.5

    0 2100 0 1800 45 0 142.5

    1 1800 0 0 0 0 142.5

    2 2700 4500 1800 45 400 587.5

    3 1800 0 0 0 0 587.5

    4 2700 4050 1350 33.75 400 1021.25

    5 1350 0 0 0 0 1021.25

    6 3150 3150 0 0 400 1421.25

  • Step 3: Total Cost Calculation for LUC

    Item Cost (Rs)

    P0110 3,775

    P0X 2,195

    P0Y 1,815

    P1X1 1,500

    P1X2 1,421

    TOTAL 10,706

  • Conclusion

    Based on calculations, Total Cost for every lot-sizing Method as follows

    Lot-Sizing Method Total Cost (Rs)

    Lot-for-Lot (L4L) 15,060

    Economic Order Quantity (EOQ) 14,296

    Least Total Cost (LTC) 10,735

    Least Unit Cost (LUC) 10,706

    The lowest cost was obtained using the Least Unit Cost Method of Rs10,706.

    Sunita Menon should choose the Least Unit Cost Method as Lot Sizing Strategy at A-Cat Corp.

  • MRP system determines detailed schedules that show exactly what

    is needed over time. MRP is most useful in industries where standard products are

    made in batches from common components and parts. The systems effectiveness depended on the inventory position and

    policies, the bill of materials and the demand requirements for finished goods and components.

    Lot sizes are the production (or purchasing quantities) that are used by the MRP system. The simplest case is when the system schedules exactly what is needed each period (known as lot-for-lot), but when there are significant cost (set up cost & carrying cost) lot-for-lot might not be the least costly method.

    The advantage of the least unit cost method is that it is more complete analysis and would take into account ordering or setup costs that might change as the order sizes increases.

    The lowest cost from the alternatives method of Lot Sizing can be a consideration for Lot Sizing.

    Lesson Learned

  • Jacobs, F. Robert, and Richard B. Chase. Operations

    and Supply Chain Management. 14th. Global Ed. New York: McGraw-Hill Companies Inc. 2014.

    Material Requirements Planning at A-Cat Corp. 2012. Richard Ivey School of Business Foundation.

    References