ADVANCED POWER ANALYTICS LIMITED Onyx Group - HV installation Test Report Client - Onyx Document Prepared by - Ron Richardson (On behalf of Keysource) Document Date - 02/05/2012

Transcript of Onyx Group Hv Test Report

Page 1: Onyx Group   Hv Test Report

ADVANCED POWER ANALYTICS LIMITEDOnyx Group - HV installation Test Report

Client - OnyxDocument Prepared by - Ron Richardson (On behalf of Keysource)

Document Date - 02/05/2012

Page 2: Onyx Group   Hv Test Report

Table Of Contents! ! 1.0 - Installation Report Overview 3

2.0 - Testing Operation Schedule 6-7

3.0 - HV Testing

3.1 - HV Terminations

3.1.1 - HV Feed to TX1 9

3.1.2 - HV Feed to TX2 10

3.1.3 - Scottish Power Incomer Number 1 11

3.1.4 - Scottish Power Incomer Number 2 12

3.2 - HV Switchboard

3.2.1 - HV Pressure testing of Busbars & Switchgear 13

3.2.2 - Ductor Testing of HV Busbars 14

3.3 - HV Pressure Testing theory

3.3.1 - Pressure testing @ 25KV 15

3.3.2 - Pressure testing @ 18KV 16

3.4 - Transformer Testing

3.4.1 - Transformer No.1 17

3.4.2 - Transformer No.2 18

4.0 - Recommendations 20

Page 3: Onyx Group   Hv Test Report

1 - HV Report Overview

Page 4: Onyx Group   Hv Test Report

The following report has been produced to help give clear indication of the testing procedures and the respective results of the tests that were necessary for

the successful implementation of the new HV Substation which has been installed at the Onyx Group data centre (Edinburgh)

Switchgear & Transformer Testing:

Due to the existing configuration (RMU ‘close-coupled’ to the Transformer) in order to carry out the testing of the Transformer it would be necessary to

disconnect the ‘new’ previously installed HV termination at the RMU and then use the switching ‘on’ positions to test through the switches onto the HV

windings of the Transformer. The HV test voltage values and durations would then have to be considered to ensure no possibility of ‘Over-stressing the HV

Equipment. Functional Switching Checks were also carried out to confirm Switching operation reliability.

Secondary protection tests were also carried out to check that the Switchgear would operate under fault conditions as well as Insulation resistance checks for

the Current Transformers

Method Statements and Risk assessments were constructed prior to the work commencing highlighting the Process and Immediate risk(s) in connection with

the tasks.

The equipment tested was subjected to the following electrical tests consisting of :

1 - Pre and post Insulation resistance testing @ 5KV

2 - Uni-polar HV Testing @ 18 - 25KV (for 1 min & 15min durations)

3 - Secondary Injections Currents (0 - 20 amps) for Trip Testing Simulations

4 - Ductor testing Currents (50 & 100 amps) for testing the HV Busbars

*Important Notes -

1 - Any recorded values lower than 75 Mega Ohms for Transformer tests will need to be reported to the manufacturer prior to any Energization activity as this

may representative of a potential Failure.

2 - Any HV Cables tests with Insulation resistance values lower than 500 Mega Ohms prior to Energization will be subject to further investigation works as this

may again be representative of imminent or possible near future Failure.

Page 5: Onyx Group   Hv Test Report

2 - Testing Operation Sheets

Page 6: Onyx Group   Hv Test Report
Page 7: Onyx Group   Hv Test Report
Page 8: Onyx Group   Hv Test Report

3 - HV Testing (Switchgear & Cables)

Page 9: Onyx Group   Hv Test Report

3.1.1 - HV Cable feed to TX1

Page 10: Onyx Group   Hv Test Report

3.1.2 - HV Cable feed to TX2

Page 11: Onyx Group   Hv Test Report

3.1.3 - Scottish Power Incomer No.1

Page 12: Onyx Group   Hv Test Report

3.1.4 - Scottish Power Incomer No.2

Page 13: Onyx Group   Hv Test Report

3.2.1 - HV Busbar Testing (Insulation Resistance & Pressure Testing)

Page 14: Onyx Group   Hv Test Report

3.2.2 - HV Busbar Testing (Ductor Testing)

Page 15: Onyx Group   Hv Test Report

This figure is 2x the RMS value and is used to theoretically simulate some of the 'in rush currents that are associated at the point of energisation.

Peak Value

11000 √3

Value = 1.732

This figure is used to establish the voltage in any individual 'phase

Root 3

This figure is the system voltage, and is the phase to phase value that the cable/switchgear is subjected to

System Voltage

6351 x 1.414 x 2.55 x 1.1

25185 voltsTest value = 25 KV (Per Phase - DC Test)

x 1.414 x 2.55 x 1.1

11000 1.732

x 1.414 x 2.55 x 1.1

This figure takes is the nominal voltage based on 10% more than the system voltage (11 KV)

Nominal voltage

1 - Insulation resistance test results should be greater than 10 gig ohms when testing each individual core to earth as well as phase to phase testing.2 - Insulation resistance tests that are less than 10 gig Ohms will result in further inspection of the cable installation for any possible causes.3 - If there is a large variation in core test results when carrying out insulation resistance tests then further investigation will be required.

Additional notes (For new cables)This figure takes into consideration the transient voltage at the peak of the sinewave

Transient Voltage

3.3.1 - HV Pressure Testing Theory (25 KV)

Page 16: Onyx Group   Hv Test Report

This figure is 2x the RMS value and is used to theoretically simulate some of the 'in rush currents that are associated at the point of energisation.

Peak Value

11000 √3

Value = 1.732

This figure is used to establish the voltage in any individual 'phase

Root 3

This figure is the system voltage, and is the phase to phase value that the cable/switchgear is subjected to

System Voltage

6351 x 1.414 x 2

17960 volts

Test value = 18 KV (Per Phase - DC Test)

Cable test theoryDue to the nature of the installation it is deemed that the cable under test is an 'old' cable because it would have been subjected to factory tests. The test value used in this instance is a value that takes this into consideration as well as the fact that there will be certain impulse values which can be 2 or 3 times the Peak value. Each phase of the cable will be tested individually with the other phases earthed for a duration of 1 min. This test will be a DC Test.

x 1.414 x 2

11000 1.732 x 1.414 x 2

1 - Insulation resistance test results should be greater than 10 gig ohms when testing each individual core to earth as well as phase to phase testing.2 - Insulation resistance tests that are less than 10 gig Ohms will result in further inspection of the cable installation for any possible causes.3 - If there is a large variation in core test results when carrying out insulation resistance tests then further investigation will be required.

Additional notes (For new cables)

This figure takes into consideration the peak value which can be 2 or 3 x the peak value when the cable is energised

Peak multiple factor

3.3.2 - HV Pressure Testing Theory (18 KV)

Page 17: Onyx Group   Hv Test Report

3.4.1 - Transformer No.1 Testing

Page 18: Onyx Group   Hv Test Report

3.4.2 - Transformer No.2 Testing

Page 19: Onyx Group   Hv Test Report

4 - Recommendations

Page 20: Onyx Group   Hv Test Report

The following items listed below are recommended future works that we feel are necessary to ensure the system resilience for the current and future power

demands the Data centre will be subjected to:

1 - Full HV/LV Protection Study:

It is recommended that a full Protection study including the current and future HV equipment is carried out so that the data centre can run with the maximum

level of safety.

2 - Thermal imaging of new and existing infrastructure:

Thermal imaging will help gauge an understanding of the system performance with respect to system efficiencies and help identify equipment which emit

excessive heat which equate to power losses.

3 - Detailed Power Supply Audit (HV &LV):

APA Ltd can conduct a detailed power audit which differs from the conventional approach in that:

a) We will identify the losses within the system using multiple approaches.

b) We will identify how the problems (if any) came into existence.

c) We will accurately determine what the costs of the inefficiencies are with respect to money.

d) Provide realistic tangible solutions for the client starting with looking at ways to re-managing the existing power infrastructure.

4 - Asset Maintenance:

We recommend that a planned maintenance program is constructed with respect to the HV supply and Heavy current LV equipment which can be factored in at

the most convenient times suitable to the client.

Page 21: Onyx Group   Hv Test Report

No.8 Bank Apartments, Marlow, Buckinghamshire, United Kingdom SL7 3DXMobile - +44 7515 384458

email - [email protected]

Advanced Power Analytics LimitedInstallation Services: HV & LV Cable Jointing up to 33 KV HV & LV Construction Up to 33 KV Protection Testing / Grading Surveys Full HV and LV Commissioning

Maintenance & Analysis (Online & Offline) HV & LV Maintenance Up to 132 KV Power Quality Analysis / Power Auditing Thermal Imaging Ultrasonic Testing Partial Discharge Testing

Additional Services: Technical Consultancy Technical Media Development Asset Management Project Management Training (On site and system specific)

Page 22: Onyx Group   Hv Test Report