Ohio Department of Transportation (ODOT) Rail Transit ......FTA Transportation Safety Program...
Transcript of Ohio Department of Transportation (ODOT) Rail Transit ......FTA Transportation Safety Program...
Page 1 of 18
Ohio Department of Transportation (ODOT)
Rail Transit Safety and Security Oversight (SSO) Program
2015 Annual Program Status Report
Office of Transit
1980 West Broad Street
Columbus, Ohio 43223
April 2016
Page 2 of 18
[This page left intentionally blank]
Page 3 of 18
Executive Summary
This 2015 Annual Program Status Report highlights the changing transit safety program
landscape at the federal, state, and transit agency levels, with a focus on calendar year 2015. This
report generally focuses on activities and accomplishments that are a part of the Ohio
Department of Transportation (ODOT) Rail Transit State Safety and Security Oversight (SSO)
program. In addition, this status report is federally required to be provided annually to the
Federal Transit Administration (FTA), the Governor of the State of Ohio, and the boards of
directors or equivalent for the rail transit agencies (RTAs) in the State of Ohio – Greater
Cleveland Regional Transit Authority (GCRTA), the Southwest Ohio Regional Transit Authority
(SORTA), and the City of Cincinnati.
As background, the ODOT SSO program was originally developed in 1996 in response to an
FTA regulation, 49 Code of Federal Regulation (CFR) Part 659, focused on establishing a state
safety oversight (SSO) program for rail transit systems not already regulated by the Federal
Railroad Administration (FRA). This regulation tasks a state to oversee the safety and security
programs of rail fixed guideway systems through a designated oversight agency, which in Ohio
is ODOT’s Office of Transit. The SSO rule was revised in 2005 to make improvements and
provide additional direction to states with SSO programs. The ODOT SSO program has provided
safety and security oversight for GCRTA since the beginning of the regulation and now for the
Cincinnati Streetcar project since 2012.
Enhanced FTA Safety Program
Since the passage of Moving Ahead for Progress in the 21st Century (MAP-21) in July 2012, the
FTA Office of Safety and Oversight (TSO) has been working to establish all of the regulations
that would implement the new federal safety program requirements for states and public transit
agencies. These FTA rulemaking activities have kept the transit industry extremely busy trying
to understand and provide feedback in order to establish the enhanced, but efficient and effective,
transit safety programs. MAP-21 was also recently replaced by a five-year surface transportation
bill, the Fixing America’s Surface Transportation (FAST) Act, in December 2015, adding a few
updates to and clarifications for the FTA’s safety programs. A summary of FTA’s rulemakings
based on the new safety program requirements from 49 U.S.C. Section 5329 are listed here:
FTA Transportation Safety Program (August 2015) – notice for proposed rulemaking
(NPRM) that described the FTA’s responsibilities for the new transit safety programs, to
be codified at 49 CFR Part 670. This includes requirements for the National Safety Plan
and the use of FTA’s transit-specific safety management system (SMS).
Draft National Safety Plan (February 2016) – a draft National Safety Plan was
released in the Federal Register for public comment. One of the main highlights of this
draft plan are the safety performance criteria for the transit industry, which were chosen
to be fatalities; injuries; specific safety events; and system reliability.
Agency Safety Plan (February 2016) – this is the most recent NPRM and covers the
requirements of this new safety plan that will eventually replace the system safety
program plan (SSPP) and implement the transit-specific SMS at the transit agency and
state levels (for smaller transit bus agencies). This regulation will be codified at 49 CFR
Part 673.
Page 4 of 18
Safety Certification Training Program (April 2014 and December 2015) – this
program currently has an interim final rule (IFR) and an NPRM for a final rule to be
codified at 49 CFR Part 672. This training program has specific training requirements for
state SSO staff and rail transit agency (RTA) safety oversight staff that includes the
Transportation Safety Institute’s (TSI) Transit Safety and Security Program (TSSP)
certificate classes and specific classes for the transit-specific SMS. In addition, there is a
requirement for the state SSO program to have training developed and provided by the
RTAs in regards to rail system and safety program related awareness.
Enhanced State Safety Oversight (SSO, March 2016)) – this new regulation (49 CFR
Part 674) has just been finalized in March 2016 and goes into effect April 2016 with three
years to fully implement at the state level. This regulation will eventually replace the
current SSO rule (49 CFR Part 659) as state SSO programs achieve the FTA’s
Certification requirements.
Transit Asset Management (TAM, September 2015) – this NPRM establishes
requirements for TAM and state of good repair (SGR) for the transit industry and the data
submission requirements for TAM into the National Transit Database (NTD).
Efforts to Enhance the ODOT SSO Program
The ODOT SSO program has been responsive to all of the rulemakings and requirements made
by FTA, requiring enhancements to the ODOT SSO program. These enhancements have been
coordinated with and communicated to the two Ohio RTAs (GCRTA and SORTA/Cincinnati
Streetcar), and are described here:
Self-Assessment – The development of the enhanced ODOT SSO program activities
started with a required self-assessment comparing the new requirements of MAP-21’s
version of FTA’s Safety Program to the current SSO rule implementation, and this self-
assessment was provided to FTA on August 30, 2013. FTA responded with a letter on
October 1, 2013 indicating that the ODOT SSO program was not pre-certified, but was
qualified to develop a certification work plan (CWP) and apply for SSO program grant
funding (referred to as Section 5329 grant funding). Only two states were pre-certified at
that time – California and Massachusetts, based on their established enforcement
authority as part of being a state public utilities commission.
Re-designation of SSO Agency (SSOA) – For the new SSO program, FTA required the
state to re-designate the ODOT Office of Transit as the SSOA for the state. This was
completed through a letter, dated November 12, 2014, from Governor John Kasich to the
FTA Region V Administrator, Ms. Marisol Simon.
ODOT SSO Program Certification Work Plan (CWP) – This CWP was submitted via
letter on May 1, 2014. FTA notified the ODOT SSO program that this CWP was
approved on May 16, 2014. The CWP consists of five sections, and the ODOT SSO
program defined eight deliverables as proof of achieving the requirements of the
enhanced SSO program. To date, all eight deliverables have been provided to the FTA.
FTA has indicated that the ODOT SSO program is expected to be certified in 2016.
Updated Program Standard – The ODOT SSO program completely redesigned its Rail
Transit Safety and Security Oversight Program Standard (SSOPS) to accommodate
Page 5 of 18
adding a second RTA, the Cincinnati Streetcar project, and addressing the new SSO
program requirements from MAP-21 and FTA. This update was posted on the website
November 16, 2015. Additional changes to this SSOPS are expected in 2016.
FTA Safety Advisories (SA) – The ODOT SSO program has worked with GCRTA to
properly respond to requests/requirements from FTA for specific audits and
investigations from existing National Transportation Safety Board (NTSB)
recommendations. These FTA SAs are expected to continue (e.g., SA 16-1 for analysis of
stop signal violations was released in April 2016) as requirements for the ODOT SSO
program and the Ohio RTAs. Responses have been provided for:
o SA 14-1 for Right-of-Way Worker Protection (RWP);
o SA 14-2 Verification of Safe Rail Vehicle Stopping Distances at Terminal
Stations; and
o SA 15-1 Audit of RTA Subway Tunnel Environments
GCRTA Rail Safety Program Status
From the ODOT SSO program perspective, the GCRTA rail system safety and security programs
are being managed properly and all deadlines for annual certification continue to be completed
on time. The working relationship with GCRTA executive management, department
management, and staff continues to be excellent. GCRTA’s challenges from a safety perspective
continue to be properly managing aging infrastructure and rail vehicles, as well as turnover of
middle management and technical staff. GCRTA has been working to fully complete their transit
asset management activities for rail infrastructure and vehicles so that priorities for technical
projects and purchasing of materials can be more effectively prioritized, including from a safety
perspective. GCRTA has also invested significantly into training and capabilities for the
technical staff in rail-related departments. These activities require a tremendous amount of effort
and discipline, and significant progress continues to be made.
Cincinnati Streetcar Rail Safety Program Status
From the ODOT SSO program perspective, the Cincinnati Streetcar project team (City of
Cincinnati, SORTA, and Transdev) and rail system safety and security programs are being
managed properly and all deadlines for developing documentation for the safety and security
programs are being met. The working relationship with the project team management and staff
continues to be excellent. The challenges ahead are completion of safety and security
certification for construction and acceptance of rail vehicles, as well as planned start-up of
revenue service on September 15, 2016.
Highlights for 2016
The 2016 calendar year is expected to be busy with planned (and already completed) activities
for the ODOT SSO program as follows:
FTA Office of Safety and Oversight (TSO) completed their Safety and Security
Readiness Review (SSRR) for the Cincinnati Streetcar project and the ODOT SSO
program in Cincinnati during January 12-14, 2016.
FTA TSO has completed a three-year review of the ODOT SSO program in Cleveland
during March 1-2, 2016.
Page 6 of 18
The ODOT SSO program completed all of the defined CWP deliverables for FTA
certification in April 2016.
Required completion of Annual Reports and Certification from GCRTA by January 31st
and Approval from the ODOT SSO program has been completed. Required annual data
and information submission and annual certification by the ODOT SSO program to FTA
by March 31st has been completed.
Several FTA rulemakings are expected to be completed during 2016 and will require
significant work from the ODOT SSO program to implement the final requirements and
coordinate with the Ohio RTAs.
Quarterly meetings will continue, as scheduled.
o GCRTA – January, April, July, and October
o SORTA/City of Cincinnati – February, May, August, and November
Cincinnati Streetcar safety and security certification, testing, and start-up of revenue
service are to be completed by September 15, 2016. The ODOT SSO program is required
to be a part of the final decision-making for that start-up.
Cleveland is hosting several major events in 2016, including the Republican National
Convention in July 2016, with significant support by the GCRTA transit systems.
ODOT SSO program staff will continue to attend required FTA safety certification
training classes and to implement the technical training plans with both GCRTA and the
Cincinnati Streetcar project.
Both Ohio RTAs (GCRTA and SORTA) Safety and Security staff continue to work
towards completing FTA-required safety certification training.
Page 7 of 18
Introduction
This 2015 Annual Program Status Report highlights the changing transit safety program
landscape at the federal, state, and transit agency levels, with an emphasis on calendar year 2015.
This report generally focuses on activities and accomplishments that are a part of the Ohio
Department of Transportation (ODOT) Rail Transit State Safety and Security Oversight (SSO)
program. As the initial annual report for the ODOT SSO Program, background information from
the past several years’ activities are provided to enhance the context of the report. In addition,
this status report is federally required1 to be provided annually to the Federal Transit
Administration (FTA), the Governor of the State of Ohio, and the boards of directors or
equivalent for the rail transit agencies (RTAs) in the State of Ohio – Greater Cleveland Regional
Transit Authority (GCRTA), the Southwest Ohio Regional Transit Authority (SORTA), and the
City of Cincinnati.
As background, the ODOT SSO program was originally developed in 1996 in response to an
FTA regulation, 49 Code of Federal Regulation (CFR) Part 659, and focused on establishing a
state safety oversight (SSO) program for rail transit systems not already regulated by the Federal
Railroad Administration (FRA). This regulation tasks a state to oversee the safety and security
programs of rail fixed guideway systems through a designated oversight agency. The rule was
revised in 2005 to make improvements and provide additional direction to the states with SSO
programs.
In Ohio, the designated state safety oversight agency (SSOA) has been and continues to be the
ODOT Office of Transit. The ODOT Office of Transit provides financial and technical
assistance to public transit systems, local governments, and human service agencies throughout
the state for the planning, establishment, and operation of those public transit systems. The
ODOT SSO program has provided safety and security oversight for GCRTA since the beginning
of the program and now for the Cincinnati Streetcar project since 2012.
Enhancements to the Federal Transit Safety Program
Starting with the passage of Moving Ahead for Progress in the 21st Century (MAP-21) in July
2012, the SSO authority was changed again with significantly more authority, responsibility, and
funding for the state SSO programs and the FTA SSO program. Previous to MAP-21, the SSO
programs were an unfunded mandate, and states were responsive, but generally only providing
the minimum effort required and specifically only what the FTA SSO program required and
enforced.
Since MAP-21 went into effect, the FTA Office of Safety and Oversight (TSO) has been
working to establish all of the regulations that will implement the new federal expectations of the
safety program for states and public transit agencies. These FTA rulemaking activities have kept
the transit industry extremely busy trying to understand and provide feedback in order to
establish the enhanced, but efficient and effective, transit safety programs. ODOT has provided
feedback for these rulemakings from both the perspective of being a state DOT and for the
1 Federally required in 49 U.S.C. Section 5329(e)(4)(A)(vii) and 49 CFR Part 674.13(a)(7).
Page 8 of 18
ODOT SSO program. FTA safety program rulemaking activities published in the Federal
Register and status are summarized as follows:
Advanced Notice of Proposed Rule Making (ANPRM) on FTA’s Safety Program
Changes, October 3, 2013 – provided an overview of FTA’s vision of the new safety
program, state of good repair, and transit asset management, along with a request for
input from the transit industry with 123 questions. FTA has used this initial ANPRM as
part of their justification for the other rulemakings presented here.
Interim Safety Certification Training Program Provisions, April 30, 2014 – this was
first a notice from FTA for comment, and then was finalized February 27, 2015. The
safety certification training requires both the SSO program staff and rail transit agency
(RTA) staff to complete specific safety-related training requirements from the U.S.
Department of Transportation (DOT) Transportation Safety Institute (TSI). In addition,
the SSO programs must work with the state’s RTAs to develop rail system awareness
training for the SSO program staff, designated Technical Training Plans (TTPs).
State Safety Oversight NPRM, February 27, 2015 – provided FTA’s vision of the
higher expectations for the state SSO programs to be published as 49 CFR Part 674, and
this regulation would eventually replace 49 CFR Part 659. FTA finalized this rule on
March 16, 2016 and it went into effect on April 15, 2016.
Public Transportation Safety Program NPRM, August 14, 2015 – explains FTA’s
policy and requirements for a National Safety Plan and its content, implementation of a
transit-specific Safety Management System (SMS), and FTA leadership and participation
in investigations. This NPRM indicates that FTA has decided to use four safety
performance criteria based on data already collected by transit agencies: fatalities,
injuries, safety-related events, and system reliability. This NPRM will eventually be
regulation as 49 CFR Part 670.
Transit Asset Management (TAM) NPRM, September 30, 2015 – establishes the
requirements for TAM as part of state of good repair (SGR) for transit agencies. This new
requirement will eventually be 49 CFR Part 625, with significant data collection and
reporting required to the National Transit Database (NTD) per 49 CFR Part 630.
Final Rule for Safety Certification Training Program NPRM, December 3, 2015 –
takes the Safety Certification Training Program from an Interim Final Rule to a Final
Rule as 49 CFR Part 672. This draft final rule provides a clearer picture of required safety
training and staff at the state and RTAs that must have the training. Bus transit agencies
continue to have access to the safety training program, as a voluntary participant.
Agency Safety Plan NPRM, February 5, 2016 – describes the requirements for each
transit agency (except those with safety programs regulated by another federal agency) to
develop an agency safety plan in place of the system safety program plan (SSPP), and
based on FTA’s transit-specific SMS. This NPRM will eventually be regulation at 49
CFR Part 673. The first draft National Safety Plan was also released for formal comment
by FTA at the same time as this NPRM.
MAP-21 was originally a two-year (FY2013-FY2014) surface transportation funding
mechanism, but was extended several times until a new five-year bill was passed and signed in
Page 9 of 18
December 2015, the Fixing America’s Surface Transportation (FAST) Act. The FAST Act
provides continued level funding for the SSO programs. There were also clarifications added to
Section 5329 for FTA’s authority to temporarily take over a state’s SSO program and
responsibilities when the SSO program is deemed to be ineffective. This authority is currently
being used by FTA TSO to provide oversight of the Washington Metropolitan Area
Transportation Authority (WMATA) until the replacement for the Tri-state Oversight Committee
(TOC) SSO program is developed and working. Another important clarification is the penalty for
a state not being certified as a compliant MAP-21 SSO program is now capped at up to 25
percent of a state’s Section 5307 (urban transit agencies) grant funding from FTA.
Enhancements to the ODOT SSO Program
The ODOT SSO program has been responsive to all of the rulemakings and requirements made
by FTA. Enhancements to the ODOT SSO program have been coordinated with and
communicated to the two Ohio RTAs (GCRTA and SORTA/Cincinnati Streetcar). These
activities started with a self-assessment of the ODOT SSO program compared to the new
requirements of MAP-21’s version of Section 5329, which was provided to FTA TSO on August
30, 2013. FTA responded with a letter on October 1, 2013 indicating that the ODOT SSO
program was not pre-certified, but was qualified to develop a certification work plan (CWP) and
apply for SSO program grant funding (referred to as Section 5329 grant funding). Only two
states were pre-certified by FTA at that time – California and Massachusetts based on their
established enforcement authority as part of being a public utilities commission in each state.
One of the requirements from the new SSO program was for Ohio to re-designate the ODOT
Office of Transit as the SSOA for the state. This was completed through a letter, dated
November 12, 2014, from Governor John Kasich to the FTA Region V Administrator, Ms.
Marisol Simon. The ODOT SSO program also developed their CWP for becoming certified as
compliant with the new SSO program, via letter on May 1, 2014. FTA notified the ODOT SSO
program that their CWP was approved on May 16, 2014.
ODOT SSO Certification Work Plan (CWP) Status
FTA SSO CWPs include five required sections based on 49 U.S.C. Section 5329(e). The ODOT
SSO program CWP includes tasks and deliverables to provide evidence to FTA of progress
towards certification. The CWP sections and ODOT SSO program letter deliverables to date are
described.
CWP Section 1. Independence from Rail Fixed Guideway Public Transportation
Systems. The ODOT SSO program had one item out of five to be addressed in regards to
assuring financial independence from the Ohio RTAs. A letter report was provided to
FTA on October 9, 2015 showing a new organization chart for the Office of Transit that
separates grant funding and oversight activities within the office. A second attachment
provided an explanation of independent budgets for the oversight activities. The third
attachment provided a conflict of interest policy statement added to the ODOT SSO
program standard to restrict RTAs from providing any funding to the SSOA.
CWP Section 2. Enforcement Authority. The ODOT SSO program had to respond to
issues for each of the four items in this section. A letter report was provided to FTA on
Page 10 of 18
September 8, 2015 with the updated Ohio Revised Code (ORC) in 5501.55 and 5501.56
that addressed state authority for enforcement of the safety program at the Ohio RTAs.
An additional deliverable was added by FTA to provide an enforcement escalation
procedure that was provided to FTA via letter report on April 11, 2016.
CWP Section 3. SSO Program Implementation Activities. This CWP section includes
three items, but is the most involved and requires evidence of improved and enhanced
SSO program activities. Five letter reports have been completed for the following
program activities.
1. Enhanced Management of Corrective Actions delivered on December 18, 2015
2. Enhanced Hazard Management delivered on December 18, 2015
3. Enhanced Triennial Review of Ohio RTAs delivered on December 18, 2015
4. Accident response and investigation simulation (at GCRTA) delivered on
December 31, 2015
5. Procedures for developing this annual program report delivered on April 11, 2016.
CWP Section 4. Staffing and Qualifications of SSO Personnel and Contractors.
ODOT provided another letter report on October 9, 2015 with a work breakdown
structure (WBS) for the new ODOT SSO program, level of effort planned, and addition
of the Safety Certification Training Plan for the ODOT SSO program staff. ODOT has
also added an additional staff member in 2015 and continues planning how to best
implement and support the ODOT SSO program with internal and contractor staff.
CWP Section 5. Grants and Waivers. All three items in this section were certified with
the approval of the ODOT SSO program CWP.
ODOT SSO Program Standard Update
The ODOT SSO program completely redesigned its Safety and Security Oversight Program
Standard (SSOPS) to accommodate adding a second RTA with the Cincinnati Streetcar project
and addressing the new SSO program requirements from MAP-21 and FTA. This update was
completed on November 16, 2015, and the new SSOPS is available on the ODOT website at:
http://www.dot.state.oh.us/Divisions/Planning/Transit/Documents/Programs/Rail%20Safety/SSO
PS.pdf.
FTA Safety Advisories
At the end of 2013, FTA started to issue Safety Advisories (SAs) to the SSO programs and their
RTAs to respond to recommendations from the National Transportation Safety Board (NTSB)
investigations of rail transit accidents. These SAs have required significant time and effort for
both GCRTA and the ODOT SSO program and are expected to continue as FTA determines
additional safety-critical issues that need to be investigated (SA 16-1 on stop signal violations
was released in April 2016).
SA 14-1. Right-of-Way (ROW) Worker Protection (RWP) – issued by letter from
FTA on December 31, 2013. The ODOT SSO program worked with GCRTA to develop
their response and a modified RWP Plan that focused on converting their RWP practice
to follow FRA requirements. This response was originally sent to FTA on May 16, 2014.
Later, GCRTA and the ODOT SSO program worked together to allow a modification to
the GCRTA RWP Plan to follow rail transit standards and best practices. This
Page 11 of 18
modification was completed in October 2015 and made to better address the needs of
GCRTA and controlling RWP costs while maintaining the safety intent. Additional minor
changes were made in March 2016 as the plan was fully implemented. GCRTA’s effort
to develop the RWP Plan was implemented through an internal audit from 2014, and the
corrective actions are being tracked to completion as part of the ODOT SSO program.
The ODOT SSO program has communicated with the Cincinnati Streetcar project on this
topic, and will follow up as the project gets closer to start-up and revenue service.
SA 14-2. Verification of Safe Rail Vehicle Stopping Distances at Terminal Stations –
issued by letter from FTA on June 12, 2014 in response to NTSB investigation of a
Chicago Transit Authority (CTA) rail accident at the Chicago O’Hare airport station. The
ODOT SSO program worked with GCRTA to complete the review and verification as
part of another 2014 internal audit to study the design and implementation of end of line
devices and braking distances for all rail lines. The internal audit report was provided to
FTA as required in July 2014. The corrective actions from this internal audit are being
tracked to completion as part of the ODOT SSO program. The ODOT SSO program has
communicated with the Cincinnati Streetcar project on this topic, and will follow up as
the project gets closer to start-up and revenue service.
SA 15-1. Audit All RFGPTS with Subway Tunnel Environments – issued by letter
from FTA on June 17, 2015 in response to NTSB investigation of a WMATA accident in
a tunnel near L’Enfant Plaza station. The ODOT SSO program worked with GCRTA to
complete the review and verification as part of a 2015 internal audit of the Airport Tunnel
on the Red Line. This station and tunnel had just been refurbished with completion in
2014. A letter response from the ODOT SSO program was provided to FTA on August 7,
2015. The internal audit was completed on August 18, 2015, and the corrective actions
are being tracked to completion as part of the ODOT SSO program. This safety advisory
did not apply to the Cincinnati Streetcar project, because there are no tunnels.
Greater Cleveland Regional Transit Authority (GCRTA)
The ODOT SSO program provides safety and security oversight for the
GCRTA (www.riderta.com) heavy and light rail systems shown in Figure 1,
which include 37 miles of double track and catenary power system. Figure 1
also shows GCRTA’s two bus rapid transit (BRT) lines, but the bus
operations are not a part of the SSO program. Figure 2 shows one of the
light rail vehicles.
Communications with GCRTA occur daily with email or phone calls, usually with the Safety
Department. GCRTA provides monthly status reports for all investigations, internal audits, and
corrective actions. In addition, the ODOT SSO program and GCRTA have quarterly meetings at
GCRTA with executive and department management staff to go over status of corrective actions
and to share presentations about current safety or security activities related to the ODOT SSO
program. Quarterly meetings for 2015 occurred on February 3rd, April 29th, and July 29th.
Page 12 of 18
Figure 1. GCRTA Heavy and Light Rail Service Map
Figure 2. GCRTA Light Rail Vehicle
The October quarterly meeting was canceled due to the 2015 Triennial Review being completed
in September 2015, with the on-site activities completed during September 15-16 and September
21-25. The Triennial Review is conducted every three years by the ODOT SSO program in order
to determine if the RTA is complying with the ODOT SSO Program Standard and following its
Page 13 of 18
own safety and security documentation and methodologies. The draft Triennial report was
provided to GCRTA for comment on November 12, 2015 and a revised final report was provided
on December 7, 2015. Corrective actions were developed by GCRTA and discussed as part of
the January 2016 quarterly meeting. On February 5, 2016, the ODOT SSO program approved 32
corrective actions from GCRTA designed to further improve the safety and security programs in
response to the 2015 Triennial Review.
GCRTA and the ODOT SSO program have actively worked together completing investigations
and internal audits, using these as an opportunity to enhance safety and security capabilities
related to the rail systems. As shown in Figure 3, the number of reportable event investigations
over the last nine years have been an average of 15 per year. The ODOT SSO program has
started to require additional, less severe, events that were already being investigated to also be
included in the ODOT SSO program. Note the significant increase of ODOT reportable events
starting in 2012 is a part of the new requirements for the MAP-21 enhanced SSO program.
Figure 3. Number of FTA and ODOT Required Investigations by Year
The ODOT SSO program assigns GCRTA to complete these investigations, and the ODOT SSO
program adopts and approves all of the investigations and corrective action plans (CAPs). The
ODOT SSO program staff carefully and independently review the investigations and CAPs to
assess whether or not all of the root causes for the events were fully investigated and
appropriately mitigated/controlled. Any changes needed are discussed and negotiated between
the ODOT SSO program and GCRTA staff. Figure 4 shows all CAPs from investigations,
internal audits, and ODOT SSO program Triennial Reviews at GCRTA during the nine-year
period. All of these CAPs have been approved by and included in the ODOT SSO program. The
CAPs represent action items to improve safety or security on the rail system including training,
additional maintenance, or adding/improving new capabilities.
GCRTA’s internal audits are coordinated with the ODOT SSO program and GCRTA’s Safety
and Internal Audit Departments. Each year, approximately one-third of the system safety
Page 14 of 18
program plan (SSPP) elements and system security plan (SSP) sections are audited in order to
cover the entire safety and security programs over a three-year period. For each internal audit,
the ODOT SSO program is included for review of the planned procedures and checklists both for
information and in case the ODOT SSO program staff decide to participate in those internal
audits. Several meetings during the year are completed with Safety and the Internal Audit
Departments to accomplish this coordination and inclusion of the ODOT SSO program.
Figure 4. Number of Corrective Actions for Investigations and Audits by Year
The ODOT SSO program and GCRTA have been working together to ensure that safety
certification training is being planned and completed for both organizations. The ODOT SSO
program developed an FTA-required Safety Certification Training Plan (dated December 2015)
to manage the required safety training activities. In addition, the GCRTA Training Department
has been developing an awareness training agenda for the ODOT SSO program Technical
Training Plan. This training from GCRTA is planned as two two-day training activities to cover
all of the technical aspects of operating and maintaining the rail systems at GCRTA. This activity
is planned to be developed in early 2016, and then the training with the ODOT SSO program
staff will be completed as well, along with the regional/local Transportation Security
Administration (TSA) Surface Transportation Inspectors. In addition, the GCRTA Safety
Department staff have also been active in completing their required FTA Safety Certification
Training.
GCRTA Rail Safety Program Status. From the ODOT SSO program perspective, the GCRTA
rail system safety and security programs are being managed properly and all deadlines for annual
certification continue to be completed on time. The working relationship with GCRTA executive
management, department management, and staff continues to be excellent. GCRTA’s challenges
from a safety perspective continue to be properly managing aging infrastructure and rail vehicles,
as well as turnover of middle management and technical staff. GCRTA has been working to fully
complete their transit asset management activities for rail infrastructure and vehicles so that
priorities for technical projects and purchasing of materials can be more effectively prioritized,
Page 15 of 18
including from a safety perspective. GCRTA has also invested significantly into training and
capabilities for the technical staff in rail-related departments. These activities require a
tremendous amount of effort and discipline, and significant progress continues to be made.
Cincinnati Streetcar Interactions
The ODOT SSO program also provides safety and security
program oversight for the Cincinnati Streetcar project
(http://www.cincinnati-oh.gov/streetcar/), which includes a
route of 3.6 miles of single track and catenary power system.
One of the modern streetcar vehicles is shown in Figure 5 and
the route map is shown in Figure 6. The route runs between the Banks through downtown up to
the Over the Rhine neighborhood. This is a joint project between the City of Cincinnati and the
Southwest Ohio Regional Transit Authority (SORTA). Transdev started in August 2015 as the
operations and maintenance contractor to SORTA for the Cincinnati Streetcar, including
management and staff to operate and maintain the streetcar services. Figure 7 shows one of the
streetcar vehicles at the maintenance and operating facility (MOF).
Figure 5. Cincinnati Streetcar Vehicle
Communications with the project team occurs daily with email or phone calls. SORTA/City of
Cincinnati provide monthly status reports for the project that are required as part of FTA’s
project management oversight (PMO) activity. The ODOT SSO program and SORTA/City of
Cincinnati have recently started quarterly meetings (August 20th and November 20th) in
Cincinnati to go over status of the project, development of procedures, and development of
related safety and security program documents.
The ODOT SSO program staff monitor (usually by phone) the safety and security review
committee and the rail activation and integrated testing activities. The investigation procedure
and plan were formally approved by the ODOT SSO program on November 11, 2015 in order
for the project team to provide any needed investigations for the ODOT SSO program as testing
on the rail system has started. In addition, the ODOT SSO program staff participate with the
FTA Region V and PMO contractor monthly and quarterly meetings with the Cincinnati
Streetcar project team.
Page 16 of 18
The ODOT SSO program will participate in the Cincinnati Streetcar training and work together
to set up awareness training to address the technical training program for the streetcar operation.
A training session for reviewing investigation processes will be planned as part of one of the
event tabletops for the project testing and start-up phase. In addition, SORTA safety and security
staff and Transdev staff have worked towards completing their FTA Safety Certification
Training Program requirements.
Figure 6. Cincinnati Streetcar Route Map
Page 17 of 18
Cincinnati Streetcar Rail Safety Program Status. From the ODOT SSO program perspective,
the Cincinnati Streetcar project team and rail system safety and security programs are being
managed properly and all deadlines for developing documentation for the safety and security
programs are being met. The working relationship with the project team management and staff
continues to be excellent. The challenges ahead are completion of safety and security
certification for construction and acceptance of rail vehicles, as well as planned start-up of
revenue service on September 15, 2016.
Figure 7. Cincinnati Streetcar Maintenance and Operating Facility (MOF)
Page 18 of 18
ODOT SSO Program Plans for 2016
The 2016 calendar year is expected to be busy with planned (and already completed) activities
for the ODOT SSO program as follows:
FTA Office of Safety and Oversight (TSO) completed their Safety and Security
Readiness Review (SSRR) for the Cincinnati Streetcar project and the ODOT SSO
program in Cincinnati during January 12-14, 2016.
FTA TSO has completed a three-year review of the ODOT SSO program in Cleveland
during March 1-2, 2016.
The ODOT SSO program completed all of the defined CWP deliverables for FTA
certification in April 2016.
Required completion of Annual Reports and Certification from GCRTA by January 31st
and Approval from the ODOT SSO program has been completed. Required annual data
and information submission and annual certification by the ODOT SSO program to FTA
by March 31st has been completed.
Several FTA rulemakings are expected to be completed during 2016 and will require
significant work from the ODOT SSO program to implement the final requirements and
coordinate with the Ohio RTAs.
Quarterly meetings will continue, as scheduled.
o GCRTA – January, April, July, and October
o SORTA/City of Cincinnati – February, May, August, and November
Cincinnati Streetcar safety and security certification, testing, and start-up of revenue
service are to be completed by September 15, 2016. The ODOT SSO program is required
to be a part of the final decision-making for that start-up.
Cleveland is hosting several major events in 2016, including the Republican National
Convention in July 2016, with significant support by the GCRTA transit systems.
ODOT SSO program staff will continue to attend required FTA safety certification
training classes and to implement the technical training plans with both GCRTA and the
Cincinnati Streetcar project.
Both Ohio RTAs (GCRTA and SORTA) Safety and Security staff continue to work
towards completing FTA-required safety certification training.