Page 2: Offshore Wind Turbine Foundation Monopile CP Retrofit Options

Environmental Variables Internal

• Conditions – Partially filled with Static Seawater – Mixture of atmospheric and submerged – Sealed conditions or are they??

Page 3: Offshore Wind Turbine Foundation Monopile CP Retrofit Options

Design Codes

– DNV (Det Norske Veritas) Certification – DNV OS-J101 Design of Offshore Wind Turbine Structures – Early versions a bit vague on corrosion protection – Later revisions of OS-J101 included improved corrosion

protection/ monitoring – Cathodic Protection refers to DNV-RP-B401

• is this applicable??

Page 4: Offshore Wind Turbine Foundation Monopile CP Retrofit Options

• Need to minimise any retrospective activities • Working inside is very difficult • Need to Consider overall Solution including the

installation • Not just about the material costs

CP Retrofit

Page 5: Offshore Wind Turbine Foundation Monopile CP Retrofit Options

Internal CP Systems - Monopiles

Page 6: Offshore Wind Turbine Foundation Monopile CP Retrofit Options

Sacrificial Anode Retrofit

• RetroLink • Simple suspended anode

solution, • Designed and engineered for

durable service • Can be customised

Page 7: Offshore Wind Turbine Foundation Monopile CP Retrofit Options
Page 8: Offshore Wind Turbine Foundation Monopile CP Retrofit Options

Up the Ladder

Page 9: Offshore Wind Turbine Foundation Monopile CP Retrofit Options

Vessel to Turbine Lift

Page 10: Offshore Wind Turbine Foundation Monopile CP Retrofit Options

Through the Door

Page 11: Offshore Wind Turbine Foundation Monopile CP Retrofit Options

And Down Again

Page 12: Offshore Wind Turbine Foundation Monopile CP Retrofit Options

Assembling Anodes on lower deck

Page 13: Offshore Wind Turbine Foundation Monopile CP Retrofit Options

Ready to Lift Anodes

Page 14: Offshore Wind Turbine Foundation Monopile CP Retrofit Options

Lowering of String

Total Anode Lift

Page 15: Offshore Wind Turbine Foundation Monopile CP Retrofit Options

Insert Rope

• Very Expensive • Stainless rope difficult to cast • Over-potential issues • Does not solve corrosion issue necessarily

Page 16: Offshore Wind Turbine Foundation Monopile CP Retrofit Options

Monitoring

• Current • Current Density • Hydrogen • Oxygen • Temp./RH

Potentials

Hydrogen