OFFICE OF THE EXECUTIVE DIRECTORpubdocs.worldbank.org/en/848511523914108135/FY2017...ANNUAL REPORT...
Transcript of OFFICE OF THE EXECUTIVE DIRECTORpubdocs.worldbank.org/en/848511523914108135/FY2017...ANNUAL REPORT...
THE WORLD BANK GROUP
Mongolia
Korea
Cambodia
Palau Micronesia
Marshall Islands
Papua New Solomon
Islands
Vanuatu
Samoa
Kiribati
Australia
New Zealand
FISCAL YEAR
2016-2017
ANNUAL REPORT
OFFICE OF THE EXECUTIVE DIRECTOR
Tuvalu
Australia │Cambodia │Kiribati │Korea │RMI│ FSM │Mongolia │Nauru │New Zealand │Palau │PNG│Samoa │Solomon Islands │Tuvalu │Vanuatu
Nauru
WBG – EAST ASIA / PACIFIC CONSTITUENCY OFFICE ANNUAL REPORT FY17
CONTENTS
EXECUTIVE SUMMARY
ABBREVIATIONS AND ACRONYMS
CONSTITUENCY OFFICE
Governors and Alternate Governors for the Constituency…………………………………………………. 1
Executive Director, Alternate Executive Director and Staff.................................................... 2
Voice Secondment Program... ................................................................................................ 3
POLICY AND ANALYTICAL WORK OF INTEREST TO OUR
CONSTITUENCY
Small States Roadmap ………………………………………………………………………………………………………. 4
Pacific Possible ........................................................................................................................ 5
Ocean (Pacific Regional Oceanscape Program) ..................................................................... 5
Climate Change Action Plan ............................................................................................ ....... 6
Doing Business Report ....................................................................................................... ..... 6
Gender Strategy ..................................................................................................................... 7
OPERATIONS POLICY OF INTEREST
Forward Look ......................................................................................................................... 8
IDA18 Update .......................................................................................................................... 9
Crisis Response ....................................................................................................................... 10
HR Update ………………………………………………………………………………………………………… ................ 11
Debt Sustainability Framework .................................................................................................. 12
SHAREHOLDING REVIEW AND FINANCIAL RESULTS
Shareholder Review …………..……………………………………………………………………………………………………. 12
IBRD......... ...................................................................................................................................... 13
IDA ................................................................................................................................................. 14
IFC .................................................................................................................................................. 15
MIGA .............................................................................................................................................. 15
ANNEXES
Annex 1. List of FY17 Constituency Country Developments and Approved Projects..... ........ 16
Annex 2. Governors’ Resolutions ............................................................................................ 27
Annex 3. Consultations with Constituents in FY17..... ............................................................ 28
Annex 4. WBG Organizational Structures ……………………………………………………………………….. .. 30
ANNUAL REPORT FY2017: WBG EDS09 CONSITUENCY OFFICE
EXECUTIVE SUMMARY
The past year provided a number of opportunities and challenges for the World Bank Group (WBG), while
also delivering $42.1 billion in commitments to IBRD and IDA member countries, and IFC providing and
mobilizing financing of $19.3 billion.
With regard the opportunities, two highlights stand out for our constituency: the Pacific Possible and the
IDA18 replenishment.
The Pacific Possible, launched during 2017 along with the Small States Roadmap, provides a framework
for realizing the potential of many of our members. It illustrates what can be achieved when the WBG
works closely with country partners, leveraging their collective development knowledge and expertise and,
as importantly, building the regional opportunities (the “Pacific Possible”) from country-level insights. The
value of this work is evident by the actions of some countries who are already looking at how to develop
the insights and approach into a country “Possible” setting.
The successful replenishment of IDA18 was the largest in IDA’s history, with the $75 billion lending
envelope a significant 50% increase over IDA17. It also introduces a number of new innovations in how it
is financed, with the intent to issue bonds for the first time and so get better leverage from the IDA balance
sheet, and how it will support IDA-eligible countries such as the use of an IFC-MIGA Private Sector
Window and a regional sub-window for refugees.
The Pacific Possible and IDA18, with its substantial increase in allocations for many of our constituency
members, provide a great base for turning the “Possible” into a reality. They also pose an enviable challenge,
requiring concerted effort and investment by the WBG and by constituency members to ensure that effective
and meaningful projects are developed and supported during the three-year window of IDA18. This
includes ongoing support and advocacy through our Constituency Office for increased WBG budget and
staff resources for the East Asia and Pacific region, as evidenced by the recent increase in presence in the
WBG’s Fiji-based office.
Other creative and innovative successes, that help WBG to be more effective, include establishing the
Global Crisis Response Window, launching the Cascade approach to leverage private sector involvement
in helping governments to pursue their development goals, and continued financial innovation, notably the
successful launch issue of a pandemic bond.
It has done so while largely continuing delivering on its intent in relation to being a “World Bank”; one that
supports all its members. While IBRD commitments were lower than expected last year, commitments for
FY18 are expected to be higher, with IFC and MIGA commitments and projects continuing to perform
strongly. However, a notable omission in its “support for all members” is the WBG not having the flexibility
to provide support to Palau, who does not have access to finance from capital markets. Our constituency
office continues to engage with the WBG on addressing this anomaly, as it is not only inconsistent with the
WBG’s Forward Look strategy, it is also inconsistent with the WBG’s drive to be more agile.
With regard the challenges, there has been considerable debate and discussion in the past year regarding
the role of regional and international agreements, institutions and organizations. The WBG is not immune
from these issues, and these discussions are occurring as the international financial architecture continues
to be increasingly complex, the WBG seeks to expand the level of its activities in order to deliver on its
twin goals of reducing poverty and raising prosperity, and its financial capacity to support such expansion
is being debated.
As we look towards the next year, a key focus will be ensuring the vision, resources and tools for an
effective and well run Bank are aligned and reflect shareholder expectations. Some elements are already in
place, with the “Forward Look”, which is the WBG’s vision to meet the challenges of development through
to 2030, endorsed at last year’s Annual Meetings.
However, decisions on realigning shareholdings and strengthening IBRD and IFC’s balance sheets have
not progressed as quickly as envisioned in the Lima Roadmap. These decisions will be critical for the
constituency over the next year. They will influence how the WBG gives effect to its vision, including
where it focuses its administrative and financial resources, and ultimately influence the WBG’s role in the
global development environment.
In reflecting on the many successes and developments during a very busy FY17, we are also very mindful
that WBG’s goals of reducing poverty and increasing prosperity are ambitious yet also critical to the lives
of many of our citizens. We expect FY18 to be as busy, engaging and challenging (if not more so) and we
look forward to working with you in order to address these challenges, realize the opportunities, and make
a difference in reducing poverty and increasing prosperity.
ABBREVIATIONS AND ACRONYMS
AF Additional Financing
AIMM Anticipated Impact Measurement and Monitoring
BSEDN Baganuur Southeastern Region Electricity Distribution Network
CCK Communication Commission of Kiribati
CER Contingency Emergency Response
CERC Contingency Emergency Response Component
CES Central Energy System
CLS Cable Landing Station
CODB Cost of Doing Business
CPF Country Partnership Framework
DDO Deferred Draw-Down Option
DPO Development Policy Operation
DSF Debt Sustainability Framework
DTC Developing and Transitions Countries
DTF Distance To Frontier
EBEDN Edernet-Bulgan Electricity Distribution Network
E/L Equity to Loan
EMC East Micronesia Cable
ERM Emergency Response Manual
FCV Fragility, Conflict and Violence
FFA Forum Fisheries Agencies
FIF Financial Intermediary Fund
FSM Federated States of Micronesia
GDP Gross Domestic Product
GEF Global Environment Facility
GFC Global Financial Crisis
GoT Government of Tuvalu
HPF Hydro Power Facility
HR Human Resources
IBRD International WBG for Reconstruction and Development
ICAO International Civil Aviation Organization
ICT Information and Communication Technology
IDA International Development Association
IDA17 International Development Association/17th Replenishment by IDA Donors
IDA18 International Development Association/17th Replenishment by IDA Donors
IFC International Finance Corporation
IFI International Financial Institution
IMF International Monetary Fund
LICs Low Income Countries
MDBs Multilateral Development WBGs
MCPP Managed Co-Lending Portfolio Program
MEF Ministry of Economy and Finance
MENA Middle East and North Africa
MIGA Multilateral Investment Guarantee Agency
MOE Ministry of Energy
MRD Ministry of Rural Development
NGOs Non-Government Organization
NPTG National Power Transmission Grid
OBA Output Based Aid
PDO Project Development Objective
PFM Public Financial Management
PICs Pacific Islands Countries
PIU Project Management Unit
PNG Papua New Guinea
PREP Pacific Resilience Program
PROP Pacific Islands Regional Oceanscape Program
PSW Private Sector Window
PV Photo Voltaic
RMI Republic of the Marshall Islands
RPF Regional Partnership Framework
SAR South Asia Region
SCD Strategic Country Diagnostic
SCI Selective Capital Increase
SDG Service Delivery Grant
SISRI Small Islands States Resilience Initiative
SME Small and Medium Enterprises
SSF Small States Forum
SUF Scale-up Facility
TA Technical Assistance
TC Tropical Cyclone
TRHDP Tina River Hydro Development Project
VSP Voice Secondment Program
WBG World Bank Group
We-Fi Women Entrepreneurs Finance Initiative
All monies expressed in USUS$ unless indicated otherwise
FY17 – refers to 1 July 2016-30 June 2017
1
CONSTITUENCY OFFICE
GOVERNORS AND ALTERNATE GOVERNORS FOR THE CONSTITUENCY*
Member Countries Governor Alternate Governor
Australia Hon. Scott Morrison, MP Hon. Kelly O’Dwyer, MP
Cambodia H.E. Aun Pornmoniroth H.E. Vongsey Vissoth
Kiribati Hon. Teuea Toatu Mr. Tukabu Tauati
Korea Hon. Dong Yeon Kim Mr. Ju Yeol Lee
Marshall Islands Hon. Brenson S. Wase Mr. David Paul
Federated States of
Micronesia
Hon. Sihna N. Lawrence Mrs. Senny Phillip
Mongolia Hon. Choijilsuren Battogtokh Mr. Nadmid Bayartsaikhan
Nauru
Hon. David Adeang, MP
Mr. Martin Hunt
New Zealand Hon. Steven Joyce Mr. Gabriel Makhlouf
Palau Hon. Elbuchel Sadang Mr. Casmir Remengesau
Papua New Guinea Hon. Charles Abel, MP Mr. Dairi Vele
Samoa Hon. Sili Epa Tuioti Mr. Lavea Iulai Lavea
Solomon Islands Hon. Snyder Rini Mr. Harry Degruit
Tuvalu Hon. Maatia Toafa Mr. Vavau Fatuuga
Vanuatu Hon. Gaetan Pikioune Mr. Simeon Malachi Athy
* As of August, 2017.
2
EXECUTIVE DIRECTOR, ALTERNATE EXECUTIVE DIRECTOR AND STAFF
Executive Director Jason Allford (Australia)
Alternate Executive Director Hoe Jeong Kim (Korea)
Senior Advisor Eriati Manaima (Kiribati)
Senior Advisor Warwick White (New Zealand)
Advisor David Higgins (Australia)
Advisor Kyung-Yun Yeom (Korea)
Advisor Napae Hurim (Papua New Guinea)
Advisor Rhinehart Silas (Palau)
Advisor Henry Ah Ching (Samoa)
Program Assistant Beatrice Nguerekata
Program Assistant Monica Eun Jong Chang
Program Assistant Elsa Warouw
3
VOICE SECONDMENT PROGRAM
The capacity building Voice Secondment Program (VSP) created by the WBG Executive Directors in 2005 is
now entering its 14th series. The program is a great opportunity to enhance the capacities of officials from
Developing and Transition Countries (DTC), including members of our constituency, as well as provide them
with insights to how the WBG operates and develop deeper networks with WBG staff. It is a great opportunity
for all who are involved with the program, which is why our office continues to support this program.
The program runs from January to July every year. Participants are selected from DTCs following a competitive
selection process. They are placed in selected units of the WBG, with a mentor coaching them throughout their
six-months assignment. During their time at the WBG, participants also spend two weeks, usually one at the
beginning of their assignment and one at the end, in our Executive Director’s (ED) office to learn, among other
things, the important role the office executes in the WBG.
For the VSP concluded in July 2017, we had the pleasure
of working with Mrs. Letauilomalo Polataivao Malaga
from Samoa, who was our constituency’s participant in
the 13th cohort. Her primary placement while she was here
was at the Center of Expertise Unit of the WBG’s Budget
Performance Review and Strategic Planning Division.
We congratulate Ms Malaga for successfully completing
the program and wish her well and success as she
commences her work for the Government of Samoa.
The WBG will increase the number of participants from
17 to 25 for the 14th series, commencing in January 2018,
in response to increasing demand from DTCs especially
in the context of IDA’s 18th replenishment.
This 14th series will include two participants from our
constituency: Mr. Damien Horiambe, First Assistant
Secretary at the Department of Treasury in Papua New
Guinea; and Mr. Henderson Tagaro, Senior Economist
from the Department of Finance and Treasury in Vanuatu.
We look forward to welcoming them and working with
them at the WBG.
Unfortunately, a third successful candidate from our
constituency, Ms. Raatu Aretaake, Senior Economist at
the Ministry of Finance in Kiribati, had to withdraw for
personal reasons.
We encourage you to take full advantage of this program and actively consider likely VSP candidates so that you
are well positioned to submit applications when submissions are requested for the next (15th) series. We will
notify you when these submissions are due. All applications are forwarded to the WBG’s Corporate Secretariat
who will undertake the selection process. With the increase in participants to 25 likely to continue, we hope to
have more applicants from our constituency chosen to participate in the VSP in future.
Figure 1: ED J. Allford & VSP LP Malaga at farewell reception 2017
4
Table 1 provides an overview of the VSP applications received from our members since 2013. We were very
pleased that all three applications for 2018 were successful in being chosen for the program.
Table 1: EDS09 Voice Secondment Applications & Outcomes
Year
(Cohort)
FY18
(14th)
FY17
(13th)
FY16
(12th)
FY15
(11th)
FY14
(10th)
2013
(9th)
Applications received 3 4 5 2 3 4
Countries PNG,
Vanuatu,
Kiribati
Cambodia,
Mongolia,
PNG, Samoa
Cambodia,
Kiribati,
Solomon Is,
Vanuatu
Cambodia,
Mongolia
Cambodia,
Mongolia,
PNG
Cambodia,
Mongolia,
Tuvalu,
Vanuatu
# Successful
Applicant(s)
3 1 1 0 1 1
Successful
Applicant(s)’ Country
PNG,
Vanuatu,
Kiribati*
Samoa Kiribati NA Cambodia Tuvalu
*applicant from Kiribati withdrew
POLICY AND ANALYTICAL WORK OF INTEREST TO OUR CONSTITUENCY
SMALL STATES ROADMAP
The WBG is actively engaged in addressing small states’ development interests following its establishment of
the Small States Advisory Group and a WBG Small States Secretariat that organizes the annual Small States
Forum (SSF). These two entities serve to promote a consistent WBG-wide approach on small states.
Prior to the Spring Meetings this year, the Small States Secretariat produced a report, the “World Bank Group
Engagement with Small States: Taking Stock”, and made a commitment last year to develop a Roadmap of
engagement with Small States. The Roadmap was designed according to the seven (7) priority actions adopted
at the 2016 SSF. The report was finalized in May 2017 and will be formally presented at this year’s SSF during
the October 2018 Annual Meetings. The Roadmap sets the agenda on how the WBG will address the priority
concerns for small states clients.
The SSF is currently chaired by the Prime Minister of Grenada, H.E. Keith Mitchell, and the Pacific region is
scheduled to assume the Chairmanship of the Forum in mid-2018. The outgoing Chairman of the Forum
proposed to establish the SSF as a platform that would pull and mix finance from various sources like IDA,
IBRD, multilaterals, climate funds, donors, the private sector, and NGOs. The proposal also envisioned the SSF
as a platform for knowledge sharing and learning, as well as an avenue for various partnerships with key fora
such as G20, V20 and the World Economic Forum. The Pacific chairmanship will come in at a critical time
when the Roadmap’s implementation of several actions in three broad areas of engagement is expected to take
course. The areas of engagement are 1) enhancing concessional financing; 2) attracting private sector financing;
and 3) building client capacity.
The WBG, guided by its “Forward Look”, recognizes the special challenges faced by small states and is
committed, in collaboration with other partners, to address the specific development needs of the small states.
5
For the Pacific small state members, this commitment is well demonstrated in the WBG’s FY17-21 Pacific
Regional Partnership Framework that was adopted earlier this year.
PACIFIC POSSIBLE
The WBG’s flagship report for the region – Pacific Possible – was launched by the Chairman of the Pacific
Leaders Forum meeting, Hon. Tuilaepa Dr. Sailele Malielegaoi, Prime Minister of Samoa and Victoria Kwakwa,
Vice President, WBG, East Asia & Pacific Region on Thursday 7th September 2017 in Apia, Samoa during the
Pacific Islands Forum Leaders meeting. Amongst those who attended were all the Pacific Leaders and high level
observers from the regional organizations and development partners.
The report was a result of a joint effort lead by the WBG and the Pacific Island governments, development
partners, civil society and formal public consultations across the Pacific including the draft overview report
discussed at the Forum Economic Minister’s meeting in April 2017. Seven key themes were identified, five of
them were opportunities that will create a significant boost in employment, income and government economy:
• Tourism
• Knowledge Economy
• Fisheries
• Deep Sea Mining
• Labor Mobility
while two were risks that could undermine development
gains if they are not managed well:
• Climate Change and Disasters
• Non-communicable diseases
The Pacific Possible report carefully provides clear and measurable analysis for the region by 2040 and will also
offer another avenue to assist the region in progressing and implementing proper actions in priority areas outlined
by the Framework for the Pacific Regionalism which includes fisheries, climate change, labor mobility and ICT.
OCEAN (PACIFIC ISLANDS REGIONAL OCEANSCAPE PROGRAM - PROP)
Since the inception of PROP, four of our member countries, namely Federated State of Micronesia, Republic of
the Marshall Islands, Solomon Islands, and Tuvalu, have participated in it. However, most recently some of our
other constituency members have expressed a keen interest in the program.
The PROP emerged out of the “WBG’s Fisheries Engagement Strategy” developed with countries and WBG
partners and stakeholders in the Pacific and released in 2011. The Pacific Ocean ecosystems play a very critical
role in the future socio-economic development and shared prosperity of Pacific Island Countries (PIC). Our
recently approved Regional Partnership Framework (PRPF) for the nine PICs could not attest more to this than
when it identified the Fisheries Sector, which is harmonious with the oceanic focus of PROP, as one of the key
areas of economic opportunities that PICs will pursue under the framework.
The three key aims of the PROP program are; (1) strengthening the national and regional institutions responsible
for the management of the oceanic fisheries; (2) strengthening the local and national institutions responsible for
Figure 2: Prime Minister of Samoa - Hon, Tuilaepa Dr Sailele
Malielegaoi and WBG East Asia and Pacific Region Vice President -
Victoria Kwakwa
6
the management of the coastal fisheries; and (3) the strengthening of institutions responsible for the conservation
of the natural habitats that support them. These aims are incorporated in the program’s three components of,
Sustainable Management of Oceanic Fisheries; Sustainable Management of Coastal Fisheries; and the
Sustainable financing of the conservation of critical fishery habitats.
Since the PROP began in 2011, the total costs of PROP related projects undertaken by our four participating
member countries is US$30.5 million (Solomon Islands US$11.22 million, Marshall Islands US$6.75 million,
Fed. State of Micronesia US$5.5 million, and Tuvalu US$7 million). In addition to this, the Forum Fisheries
Agency (FFA) receives financing of around USUS$4 million to help coordinate, provide technical support and
conduct regional analysis supportive of the countries. The financing/funding of these projects are from IDA and
GEF, except for FSM’s project which fully IDA funding.
With more interest now coming from other PIC members, particularly Kiribati and Tonga1, and with additional
space under the new and unprecedented IDA18 scale up, we may be seeing more PROP related projects going
forward.
CLIMATE CHANGE ACTION PLAN
Climate change will continue to be a threat in achieving the twin goals of the WBG of reducing poverty and
increasing prosperity. With the Pacific region one of the most vulnerable to climate change and natural disasters,
it is understandable that the WBG continues to identify climate change as one of the five focus areas for its
strategy in the region.
The Climate Change Action Plan sets out how the WBG is intending to overcome this threat by addressing the
challenges and optimizing opportunities through its comparative advantage, scaling up climate action, integrating
climate change across its operation and more effective coordination with its partners. The commitment to the
Plan and comprehensive climate reform by the WBG and the Pacific region is further demonstrated in the work
done on the Strategy for Climate and Disaster Resilient Development in the Pacific; the Pacific Resilience
Program (PREP); the Pacific Catastrophe Risk Assessment & Financing Initiative (PCRAFI); and the Small
Island State Resilient Initiative (SISRI).
The Regional Partnership Framework, the Systematic Country Diagnostics and Country Partnership Frameworks
will continue to pave the pathway for the WBG’s future commitment to each country’s development including
the Pacific Island Countries and climate and disaster risk will continue to be a vital part of the analysis of each
country’s challenges and priorities.
DOING BUSINESS REPORT
The theme for the 2017 Doing Business Report (14th edition) is Equal Participation for All.
The Doing Business Report measures and compares aspects of regulations that enable or prevent private sector
businesses from starting, operating and expanding in 190 economies.
It uses 11 indicators sets: starting a business, dealing with construction permits, getting electricity, registering
property, getting credit, protecting minority investors, paying taxes trading across borders, enforcing contracts,
resolving insolvency and labor market regulation.
1 Tonga is not in our EDS09 constituency; it is in EDS16 constituency along with Indonesia and others
7
The Doing Business 2017 expanded the paying taxes indicators set by adding post filing processes on tax audits,
refunds and appeals and presents data on selling to the government to measure public procurement regulations.
Further, for the first time, the report added a gender component to three indicators – starting business, registering
property and enforcing contracts.
The Doing Business scores economies based on how business friendly their regulatory systems are using the
Distance to the Frontier (DTF) and the ease of doing business ranking. The DTF ‘measures the distance of each
economy to the ‘’frontier’’, which represents the best performance observed on each of the indicators across all
economies in Doing Businesses sample since 2005’.
All countries in our constituency that participated in the survey, except the Mongolia, Cambodia, Federated
States of Micronesia and Kiribati, showed improvements from 2016 in their Distance to Frontier Scores (DTF).
Two of our constituents rank in the top five, with New Zealand taking over from Singapore by moving into the
first spot with the highest DTF score, and the Republic of Korea ranking 5th.
The overall conclusion for this edition of Doing Business is that more economies are reforming and implementing
reforms to make it easier to start and conduct business.
The Doing Business 2018 Report is expected to be launched end of October 2017. This edition is expected to
include changes to the publication of data which will affect some of our constituency members.
Economies with a population below 1 million will have their data updated bi-annually. 34 out of the 190
economies fall into this category. Further, the data for 17 out of the 34 economies will be frozen in each report
cycle while data for the other 17 economies will be updated. The two groups will alternate bi-annually. And
during the frozen cycle, the DTF score will be computed using the previous year’s data.
This affects 7 countries in our constituency - Kiribati, Republic of Marshalls, Federated States of Micronesia,
Palau, Samoa, Solomon Islands and Vanuatu. For these countries, there will be no data update in the Doing
Business 2018 Report but this data will be updated in Doing Business 2019. Their DTF scores for 2018 will be
computed using the 2017 data.
Another change that will affect the 2019 Doing Business Report is the Reform Cut-off Date, which will be
brought forward to 1 May 2018 (previously the cut-off date was June of each year). This means any reforms
completed or undertaken after 1 May 2018 will not be considered for ranking or DTF scores in the Doing
Business 2019 report.
GENDER STRATEGY
The new Gender Strategy, launched in FY16, has four key objectives - improving human endowments, removing
constraints for more and better Jobs, removing barriers to women’s ownership and control of assets, enhancing
women’s voice & agency and engaging men and boys. These objectives position the WBG to be a more effective
actor in tackling specific gender gaps. The Strategy has generated higher ambition for policies and operations
and helped set the stage for robust, results-oriented commitments under IDA18. However, FY17 is a transitional
year as changes work their way through WBG systems.
Early progress has been made in a number of key areas including:
• Undertaking deeper analytical work on gender equality;
8
• Increase in the number of operations in fragile contexts that include gender-based violence
prevention/response and linkages to economic/livelihood activities;
• Introduced a new monitoring system and more outcome-oriented IDA18 policy commitments;
• more integrated approaches to close gaps between women and men that engage both the public and
private sectors in countries and at the global level;
• New country engagement tools and innovations;
• Increase in the availability and quality of sex-disaggregated data, a more systematic approach to
understanding what works, and bringing the evidence to task teams.
However, a range of challenges remain. Some of these are country specific and including entrenched norms that
can be difficult to shift, uneven capacity, and inconsistent demand from client countries. Within the WBG itself,
transitioning to new systems and shifting to a results focus will take time before becoming part of standard
practice. And operational staff with gender skills are diffused across the decentralized WBG which results in
expertise gaps that will take time to address.
Women Entrepreneurs Finance Initiative
Women entrepreneurs play a critical role in economic development by boosting growth and creating jobs,
particularly for the poorest forty percent of the population. Yet, women entrepreneurs face numerous challenges
to financing, owning, and growing a business, including limited access to capital and technology, a lack of
networks and knowledge resources, and legal and policy obstacles to business ownership and development. Lack
of networks and knowledge also constrain female entrepreneurship. Studies show that men have more social
connections that enable them to access business opportunities, information, and contacts than do women.
To help unlock the potential of women entrepreneurs, a new Women Entrepreneurs Finance Initiative (We-Fi)
will enable more than US$1 billion in financing to improve access to capital, provide technical assistance, and
invest in projects and programs that support women and women-led SMEs in WBG client countries. The goal of
the facility is to leverage donor grant funding of over US$340 million and mobilize more than US$1 billion in
international financial institution and commercial financing, by working with financial intermediaries, funds, and
other market actors.
We-Fi is a Financial Intermediary Fund (FIF) housed at the WBG, drawing on the WBG’s strong track record in
designing and managing such Funds to ensure best practice in terms of governance and efficiency. The WBG
acts as the Trustee for the facility and will also serve as the Secretariat. Multilateral development WBGs,
including the WBG and IFC, are eligible as implementing partners to propose private and public sector activities
to be supported by the facility. A Governing Committee, composed of the 15 founding contributors to the Facility
will make allocation decisions. Founding contributors include Australia and South Korea.
OPERATIONS POLICY OF INTEREST
FORWARD LOOK
The Forward Look was endorsed by the Development Committee during the 2016 Annual Meetings. It describes
how the WBG will deliver on the Twin Goals and its three priorities of sustainable and inclusive growth,
investment in human capital, and strengthening resilience. The Forward look calls on the WBG to provide
services to all clients; to scale up mobilization, while expanding use of private sector solutions; to take stronger
leadership on global issues; and to build a more efficient and effective business model.
9
Since the Forward Look was endorsed last year, some key WBG outcomes achieved in line with its objectives
include:
• Scaled up IDA18 by nearly 50 percent to promote growth, resilience, and opportunity in the world’s
poorest countries. IDA18 more than triples the base allocations to small states.
• Launched the IDA18 IFC-MIGA Private Sector Window (PSW) to encourage investment in the world’s
most challenging country settings.
• Scaled up support for countries facing fragility, conflict and violence (FCV)1 by increasing resources
and collaboration with external partners, built on a recognition that peace, security, and development go
hand in hand.
• Begun to implement the Cascade, or “maximizing finance for development”, an approach building on
and expanding the MDB Principles on Crowding-in Private Financing that were endorsed at the G20
Hamburg Summit.
• Put in place implementation mechanisms for the IFC 3.0 strategy. These include IFC’s Creating Markets
Advisory Window, the new Anticipated Impact Measurement and Monitoring Framework (AIMM),
Country Private Sector Diagnostics, the Managed Co-Lending Portfolio Programs (MCPP) for
Infrastructure and Financial Markets, and Sector Deep Dives.
• Made progress on the Climate Action Plan, including toward the goal of 28 percent of WBG financing
for projects with climate co-benefits by 2020, to help countries meet their Nationally Determined
Contributions to the Paris Agreement.
• Launched the Global Crisis Response Platform to support countries facing natural disasters, pandemics,
economic shocks, or refugee crises.
• Launched a new Women Entrepreneurs Finance Initiative (We-Fi) with US$341 million in donor funds
from 13 countries, which will enable more than US$1 billion in financing to support women-led small
and medium enterprises (SMEs)
• Introduced a Cost-of-Doing-Business (CODB) analysis for budget purposes at IFC.
• Optimized the use of capital, including by enabling IDA to raise resources in capital markets.
On small states, the WBG established a Small States Advisory Group and Secretariat to facilitate coordination
and support from across the WBG. IDA18 quadrupled the minimum base allocations for small states and assured
highly concessional financing terms and adjusted eligibility criteria for small states to access regional resources.
In April 2017, the WBG hosted a Small States Engagement Update where a new roadmap was presented. The
roadmap outlines actions in three broad areas of engagement: enhancing concessional financing; attracting
private sector financing; and building client capacity. An update on actions taken in the roadmap will be discussed
at the next Small States Forum during the WBG/IMF Annual Meetings in October 2017.
IDA18 UPDATE
IDA18 was finalized in December 2016 and will finance projects over the three-year period from July 1, 2017 to
June 30, 2020. The IDA18 replenishment is the largest in IDA’s 56-year history and marks a significant step
change in its policy and financing framework.
IDA clients face a myriad of complex and interrelated challenges in the new global economy, calling for
innovative approaches to development. The IDA18 package responds to the calls from the G20 and international community for the WBG to innovate and do everything it can to underpin the delivery of the 2030 Agenda.
Key features of the IDA18 package include:
• Quadruple allocations to small states, including small island developing states;
10
• Double financial support in aggregate for countries facing current or rising risks of fragility;
• Increase support to strong performing countries and non-fragile or conflict states, who would continue to
receive the bulk of IDA financing (nearly 65% of core IDA);
• Significantly increase financing for the regional program, where demand for resources to expand regional
integration and infrastructure has consistently outstripped supply;
• Establish a regional sub-window for refugees to provide a dedicated source of funding for host governments
struggling to meet the needs of both refugees and their host communities;
• Expand financing to promote resilience through crisis preparedness and response, through an enhanced Crisis
Response Window, including aligning governance arrangements for responding to economic shocks with the
process in place for natural disasters and health emergencies.
• Expand instruments available for crisis preparedness and response, by introducing the Catastrophe Deferred
Draw-Down Option (Cat DDO) for IDA countries in response to the demand for contingent financing
mechanisms;
• Introduce an IFC-MIGA Private Sector Window to mobilize increased private sector investment in IDA
countries, especially in fragile and conflict states, through unprecedented collaboration among IDA, IFC and
MIGA to scale up their work in the most challenging markets;
• Increase non-concessional financing available for transformational projects, through the IDA18 Scale-up
Facility (SUF), to meet the very strong client demand; and
• Provide transitional support for IDA18 graduates (Bolivia, Sri Lanka and Vietnam), which still have
significant poverty and lingering vulnerabilities, while facing a drop in WBG financing.
IDA18 Implementation
While the IDA18 period only began July 2017, early indications in relation to implementation are positive. The
WBG leadership is closely engaged and efforts are being made to deploy staffing resources to manage the shift
in resources.
The project pipeline for FY18 is strong FY18 pipeline and interest in the Scale Up Facility and Private Sector
Window has been strong. There has also been early need for the Crisis Response Window and there has been
considerable demand for the Refugee Sub-Window from Africa, MENA and SAR countries.
Preparation for first bond issuance is on track with the aim of issuing in the second half of FY18, subject to
market conditions.
The Private Sector Window’s first four projects are well advanced and are expected to be submitted to the Board
later this year. Of these, two are East Asia Pacific region investments in renewables and energy efficiency.
CRISIS RESPONSE
The WBG’s Global Crisis Response Platform (GCRP) brings together the full suite of WBG crisis-related funding
mechanisms, instruments, and knowledge-based products. The GCRP addresses a variety of global threats,
including crises resulting from pandemics, macroeconomic and financial market shocks, fragility and conflict,
and natural disasters. It has also provided an important interface with external partners such as the UN and the
Red Cross. Looking ahead, the GCRP work program will include: (a) strengthening and streamlining crisis risk
monitoring and analytical capacities, with a focus on multi-dimensional and compound risks; (b) aligning crisis
risk programming at the global, regional, and country levels; (c) enhancing existing financial solutions and seeking
new market-based products; and (d) improving operational effectiveness by promoting greater crisis risk
management flexibility and delivery mechanisms.
A key element of the GCRP is the Global Concessional Finance Facility (GCFF), which has received pledges of
11
over US$370 million in its first year. The GCFF has approved US$200 million in grants which unlocked US$1
billion in concessional financing to support refugees and host communities in Jordan and Lebanon. The seven
projects supported so far by the GCFF promote job creation and economic opportunities, provide basic services
in health and social protection, and fund the delivery of critical infrastructure.
HR UPDATE
In October 2016, the WBG established the new three year (FY 2017-2019) WBG People Strategy. This people
strategy is a key initiative in support of the WBG’s Forward Look.
The new strategy has five strategic areas of focus: talent acquisition, leadership capacity, performance and
rewards, well-being of staff, and WBG’s organizational effectiveness.
Talent acquisition will focus on (i) “building” our internal talent through a more proactive and deliberate process,
and (ii) “buying” fresh talent into the organization when skills are not readily available in-house.
For leadership capacity, the strategy involves identifying the future cohort of leaders and equipping them with the
skills and behaviors required to lead teams for high impact.
Performance and rewards will focus on reinforcing a culture of high performance underpinned by a robust
framework of rewards and incentives.
The well-being of staff element of the strategy emphasizes wellness, flexible work solutions, and a family-friendly
environment supported by modern policies and practices.
In the fifth area of WBG’s organizational effectiveness, the focus is to have a “fit-for-purpose” organizational
structure and appropriate processes to manage and deploy the talent with agility.
In addition to these five focus areas, the People Strategy has three cross-cutting themes that will support (and be
supported by) the focus areas. The first theme is fixing the HR fundamentals – policies, processes, platforms, and
support, which underpin overall activities of the HR. The second theme is to ensure that staff working in the
challenging environments that most need help – the Fragile, Conflict and Violent situations – are given the utmost
priority. The third theme is to operationalize commitment to “Diversity and Inclusion”, for which the WBG is
already regularly tracking and reporting on progress.
Our Office has strongly supported the Diversity and Inclusion work given is importance for good performing
organizations and urged management to address the issues surrounding the recruitment of underrepresented
nationalities. The Office has also stressed the importance of competitive processes, especially when positions are
filled by promotion and for high level positions. Our Office argued that rather than non-transparent internal
processes, competitive process should be required for such cases. The WBG uses competitive processes for entry-
level staffs and GH+ level positions.
This year’s staff Engagement Survey showed a continuing improvement in overall results. Only one (‘my job
makes good use of my skills’) out of 75 questions had a score lower than in FY16. However, the positive responses
from staff remained relatively low (below 50%) in area of senior leadership and performance rewards, and while
there is an improving trend there is still considerable room for further improvement.
In the Board discussion on salary increases for FY18, many Executive directors including our office argued that
the compensation methodology needed to be reviewed considering the difficult financial condition of the WBG.
12
Management agreed to conduct the review of WBG compensation methodology and is now developing the new
compensation approach in time to inform salary decisions for FY19.
DEBT SUSTAINABILITY FRAMEWORK
The framework for debt sustainability analysis for low-income countries (LICs) underwent a comprehensive
review in FY17. This review is important for many countries in our constituency as the analysis produced from
this Debt Sustainability Framework (DSF) provides an assessment of a country’s risk of external debt distress
(low, moderate, high or in debt distress). This analysis is used by LICs and creditors to inform financing decisions,
such as the mix of IDA loans and grants that the WBG may provide.
The review identified a number of changes aimed at:
• Encouraging closer engagement with country authorities on key assumptions and better incorporating
country-specific information and risks into the framework. This includes tailored stress tests to better
reflect risks such as natural disasters and volatile export prices, improving the realism of baseline
projections, and continued use of judgements (such as climate change implications and concerns about
exposure to external market-financing pressures) in finalizing the assessment.
• Making the framework less complex and more transparent. This includes embedding remittances into the
model, shortening the forecast horizon to 10 years (from 20 years), removing an indicator and some
standardized stress tests as they added little value to the analysis, and disclosing the underlying reasons
for using judgment when it is used to modify a rating.
• Making the framework stronger in its ability to predict debt distress, and to reduce the high rate of “false
alarms” when considered over the history of debt distress episodes. This includes an expanded set of
measures to better capture countries’ capacity to handle debt (i.e. recent and expected growth
performance, reserve coverage, remittances, and world economic growth, in addition to the Country
Policy and Institutional Assessment rating currently used).
In September 2017, the WBG and IMF Boards approved the proposed changes, with the revised DSF to apply
from 1 July 2018. The focus now switches to developing guidance and training, these will be critical in shaping
how judgements will be applied, and engaging with countries in preparing for the updated analyses. Debt
sustainability analyses using the new framework are expected to be completed for all LICs by 1 July 2019, in time
to inform IDA18 allocations for fiscal year 2020 and IDA19 projections.
It is not possible to tell with any certainty how the revised DSF will affect a country’s risk rating, particularly in
light of the potential for judgements to modify a risk rating. But elements of the proposals that would tend to
downgrade a risk rating include building the impact of natural disasters into baseline projections and stress tests,
as well factoring in additional fiscal costs, such as those for climate change. when reality checking the projections.
Conversely, elements of the proposals that would tend to upgrade a risk risking are shortening the forecast horizon
to 10 years and use of the expanded measures to better capture a countries’ capacity to handle debt.
SHAREHOLDING REVIEW AND FINANCIAL RESULTS
SHAREHOLDER REVIEW
13
Executive Directors completed their work on the Dynamic Formula which was subsequently endorsed by
Governors at the Annual meetings in 2016. The Dynamic Formula is based on two key variables: a measure of
Economic Weight, with a weight of 80 per cent, and a measure of contributions to IDA, with a weight of 20 per
cent. Economic Weight is measured by a five-year average of GDP, using a blend of Market Exchange Rates (60
per cent) and Purchasing Power Parity (40 per cent). IDA contributions are measured by a variable that combines
the most recent three IDA replenishments with a weight of 80 per cent and earlier replenishments with a weight
of 20 per cent. Donors contributing to IDA for the first time are provided with a booster to ensure that their
contribution receives the full weight of the recent component of the IDA variable. A compression factor of 0.95
is applied to the overall formula results. As previously reported to Governors, the formula is intended as an
important input for a realignment, not as the final outcome for such realignment.
The subsequent discussions on rebalancing shareholding have built on these three pillars which provide both
context and guidance: the agreement on the Dynamic Formula and accompanying package of commitments; and
the previously agreed shareholding review principles and formula guidance. While Shareholding discussions in
both IBRD and IFC advanced since the 2016 Annual meetings, it will take further time to complete the work than
was envisaged when the Roadmap was agreed two years ago. There has been some convergence of views on
certain topics.
Discussions have continued to reflect the collaborative spirit that has characterized the implementation of the
Roadmap and have developed and refined the options for a Selective Capital Increase in line with agreed principles
and commitments that meets the declared objective of “a balanced outcome in the upcoming SCI that addresses
under-representation of individual countries while avoiding excessive dilution.” Nevertheless, further work,
analysis, and discussion on the wider capital package is necessary before a comprehensive set of proposals, as
envisaged in the Lima agreement, can be put to Governors for decision. This includes the time needed to complete
the independent review of capital adequacy that will be presented to Governors at the Annual meetings in 2017.
The elements of the shareholding package to be agreed, including the size of the potential SCI and the allocation
rules, are connected and will need to be settled together.
The next opportunity to report to Governors with proposals on shareholding for consideration will be at the Spring
Meetings of 2018. In the interim, Executive Directors will continue their discussions on shareholding with a view
to reaching agreement on a balanced set of proposals as part of a wider package.
IBRD
14
Total IBRD commitments in FY 17 were US$22.6 billion. This is less than the US$29.7 billion in FY16, but in
line with commitment volumes in recent years.
From a balance sheet perspective, the equity-to-loan (E/L) ratio remains a key indicator of capital adequacy. The
ratio of 22.8% for FY17 was almost the same as at FY16 (22.7%), and above the Board approved minimum of
20%. While it is well down from the 38% E/L ratio that the WBG had at the beginning of the global financial
crisis in 2008, the lower ratio reflects the WBG getting significantly more leverage (i.e. total loan exposure) from
its equity than it did a decade ago. However, the headroom for further increasing total loan exposure continues to
remain tight with an E/L ratio forecast for FY18 of 21.7%.
Net income to be allocated by the Board is based on the WBG’s Allocable Income (net income adjusted for items
such as pension fund accounting and unrealised gains and losses). Of the US$765 million in Allocable Income
for FY17 of (FY16 US$593million), US$672 million was assigned to General Reserves and US$123 million
transferred to IDA. The amount transferred to IDA is based on a formula agreed by the Board in FY17, which
assigns the majority of allocable income to reserves in order to grow these reserves from earnings while still
providing support to IDA.
IDA
FY17 was the third and final year of IDA17, with the US$58 billion IDA17 lending envelope fully committed
over this three-year period. Fully committing the IDA17 envelope was a strong focus for the Board and
Management during FY17, with commitments during the year totalling US$19.5 billion (FY16 US$16.2 billion).
In March 2017, an IDA18 lending envelope of US$75 billion was approved for the three-year starting on 1 July
2018; a significant increase on IDA17. This increase was enabled through greater use of the IDA balance sheet;
that is, leveraging the IDA equity of US$158 billion to raise market debt of up to US$22 billion to contribute to
IDA18.
15
IFC
Stronger growth in emerging markets flowed through to a stronger FY17 performance for IFC; a turnaround from
the difficult conditions and results experienced in FY16.
Total long-term financing and core mobilisation commitments for the year increased US$0.4 billion to US$19.3
billion (FY16 US$18.9 billion). The increase resulted from an increase in long-term finance to US$11.9 billion
(FY16 US$11.1 billion) partially offset by a US$0.3 billion decrease in core mobilisation2 to US$7.5 billion (FY16
US$7.7 billion)
IFC’s headline indicator of capital adequacy (Deployable Strategic Capital as a percentage of Total Resources
Available) increased to 7.8% in FY17 (4.4% in FY16). This indicator addresses how much capital is available to
support new business and increasing risk, with FY17 the strongest result in the past few years but still well below
the high of 32% prior to 2008. Some of the volatility in this indicator in recent years is due to remeasurement of
the actuarial liability for pension plans, contributing to the ratio decrease in FY16 and subsequent increase in
FY17.
Allocable income increased to US$1.2 billion in FY17 (FY16 US$0.8 billion), with lower provisions and
impairments for loan losses contributing most of this increase. Based on the application of a set of Board-approved
principles, this would allow IFC to designate up to US$205 million for other purposes. Executive Directors
decided to recommend that the Board of Governors transfer US$80 million to IDA (FY16 US$101 million),
US$85 million to the Creating Markets Advisory Window (a new vehicle that focuses on market creation in IDA-
eligible and fragile countries), and US$40 million to replenish the Funding Mechanism for Technical Assistance
and Advisory Services for 2 years.
MIGA
MIGA had another strong year, following a strong performance in FY16.
The adoption of a new Economic Capital model used for provisioning purposes significantly affected some key
indicators; notably increasing Net Income by US$164.3 million to US$200.2 million (FY16 US$56.8 million) and
decreasing the capital utilisation ratio (Total Economic Capital/Operating Capital) to 42% (FY16 50%).
But looking through these accounting estimate changes, the guarantee portfolio reached record highs with new
guarantees increasing 25% to US$4.8 billion (FY16 US$4.3 billion) and the gross guarantee exposure also
increasing by 25% to US$17.8 billion (FY16 US$14.2 billion). These results helped contribute to operating
income reaching US$42 million (FY16 US$38 million), the strongest result since at least 2013. Although lower
investment income resulted in a drop in FY17 net income to US$35.9 million (excluding the accounting estimate
change) compared with the FY16 result of US$57 million.
2 Core mobilization is financing from other entities available to clients due to IFC’s direct involvement in raising resources
16
ANNEXES
ANNEX 1 - LIST OF FY17 CONSTITUENCY COUNTRY DEVELOPMENTS AND
APPROVED PROJECTS
Country/Document/Project Name
Agency
Amount
(USUS$
millions)
Date of
Approval
CAMBODIA
❖ KH-Livelihood Enhancement and Association of the Poor Project
(LEAP)
The development objectives of Livelihood Enhancement and
Association of the Poor Project for Cambodia are to improve access of
poor and vulnerable households in selected communities to financial
services, opportunities for generating income, and small-scale
infrastructure, and to provide immediate and effective response in case
of an eligible crisis or emergency. This project has four components. 1)
The first component, Improving Livelihoods for Rural Poor and
Vulnerable Households, aims to address the needs of the IDPoor and
vulnerable households in the 47 communes in Siem Reap Province
through a demand driven approach. It has the following three
subcomponents: (i) Building and Strengthening Institutions of the Rural
Poor; (ii) Enhancing Skills and Employment Opportunities for the Rural
Poor; and (iii) Improving Basic Services and Community Infrastructure
for the Rural Poor. 3) The second component, Improving Livelihoods
for Urban Poor and Vulnerable Households, aims to address the needs
of the Poverty Identification Process (IDPoor) and vulnerable
households in 13 Sangkats in Phnom Penh Capital through a demand
driven approach. It has the following two subcomponents: (i) Enhancing
Skills and Employment Opportunities for the Urban Poor; and (ii)
Improving Basic Services and Community Infrastructure for the Urban
Poor. 3) The third component, Project Management, would support the
overall implementation, supervision and coordination of the project at
the national, provincial, district or Khan, commune or sangkat, and
village or community levels, including: (a) social and environmental
safeguard risk management; (b) procurement planning and contracts
management; (c) financial management, disbursement and audit; and (d)
monitoring and evaluation (M and E), and communication. 4) The fourth
component, Contingent Emergency Response, would allow the
reallocation of a portion.
IDA Credit 20.17 02/24/2017
❖ Cambodia Southeast Asia Disaster Risk Management Project
The development objective of the Southeast Asia Disaster Risk
Management Project for Cambodia is to improve climate resilient rural
road connectivity in select provinces. The project comprises of four
components. The first component, resilient rural corridors consists of
two sub-components: (i) resilient rural roads rehabilitation and
maintenance; and (ii) institutional strengthening for disaster resilience.
The second component, financial planning for disaster resilience will
provide technical assistance to strengthen Ministry of Economy and
Finance (MEF’s) capacity for financial planning for disaster resilience.
The third component, project management will provide technical and
operational assistance to strengthen the institutional, organizational, and
IDA Credit 60.0 4/14/2017
17
Country/Document/Project Name
Agency
Amount
(USUS$
millions)
Date of
Approval
technical capacity of Ministry of Rural Development (MRD) to support
day-to-day project implementation, including coordination, technical
matters, procurement, financial management, social and environmental
safeguards, monitoring and evaluation, and reporting. The fourth
component, contingent emergency response component will provide
immediate and effective response to an eligible crisis or emergency, as
needed
❖ Secondary Education Improvement Project
The objective of the Secondary Education Improvement Project (SEIP)
is to expand lower secondary education to achieve minimum standards
in target areas, and to provide immediate and effective response in case
of an eligible crisis or emergency. There are three components to the
project, the first component being improving lower secondary education
to meet minimum standards. This component aims to support the goals
of the ESP and TPAP through the establishment of 130 effective lower
secondary schools (i.e., schools that meet LSSES) in efforts to provide
lessons for replication to MoEYS as it increases expenditures in the sub-
sector. This component targets approximately 8 percent of total lower
secondary schools nationwide. This component will be implemented
using a holistic approach, targeting national, sub-national, and school
levels, improving school-based management, teacher performance, and
school environments. The second component is the strengthening
project management and monitoring and evaluation. This component
provides technical and operational assistance for the coordination,
administration, monitoring, evaluation, and audit of the project. It will
also include activities to support the PISA for Development (PfD) to
strengthen the assessment capacity of MoEYS in preparation for PISA
2021. Finally, the third component is the contingent emergency
response. The objective of the contingent emergency response
component, with a provisional zero allocation, is to allow for the
reallocation of financing in accordance with the IDA Immediate
Response Mechanism in order to provide an immediate response to an
eligible crisis or emergency, as needed. An Emergency Response
Manual (ERM) will be developed for activities under this component,
detailing streamlined FM, procurement, safeguard, and any other
necessary implementation arrangements.
IDA Credit 40.0 4/14/2017
FEDERATED STATE OF MICRONESIA
❖ P2: Palau-FSM Connectivity Project: AF Kosrae Connectivity
The development objective of the Second Phase of Pacific Regional
Connectivity Program Project for Micronesia is to reduce the cost, and
increase the availability of, information and communication technology
services needed to support social and economic development in the
recipient’s country. The additional grant will help finance the costs
associated with the restructuring and scaling up of the project as follows:
(a) modification of Component one C of the project to finance the costs
to the FSM of its share of the proposed East Micronesia Cable (EMC)
system that will connect Kiribati (Tarawa), Nauru and FSM (Kosrae) to
Guam via the existing HANTRU-one cable system and landing point in
FSM (Pohnpei), including ancillary works, equipment and facilities; (b)
scaling up of component two of the project to provide additional
technical assistance to FSM for Project advisory services; and (c)
scaling up of component three of the project to support additional project
management and administrative support services to strengthen the
IDA Grant 16.2 5/31/2017
18
Country/Document/Project Name
Agency
Amount
(USUS$
millions)
Date of
Approval
capacity of the Government of FSM to deliver these new and additional
activities.
KIRIBATI
❖ Third Economic Reform Development Policy
The development objective of Third Economic Reform Development
Policy Operation Project for Kiribati is to (i) strengthen public financial
management, through greater transparency in managing fisheries
revenue, improved governance of the sovereign wealth fund, and better
reporting and monitoring of public debt and contingent liabilities; and
(ii) create an environment for inclusive and private sector led growth,
through reducing the costs, improving the quality, and expanding the
coverage of essential public utilities services (electricity, water, sewage,
and telecommunications). The operations supported the government
actions in three main policy areas: (i) improving the management of
fisheries revenues; (ii) improving the management of public assets and
liabilities; and (iii) expanding private sector opportunities. This
operation is aligned with the priorities identified in the existing Country
Assistance Strategy and the new Systematic Country Diagnostic for the
Eight Pacific Island Countries
IDA Grant 2.0 9/13/2016
❖ Pacific Regional Connectivity Program Phase 4: KI: Connectivity
Project
The development objective of the Fourth Phase of the Pacific Regional
Connectivity Program Project for Kiribati is to reduce the cost and
increase the availability of Internet services in Kiribati. The project
comprises of three components. The first component, submarine cable
system consists of following sub-components: (i) submarine cable
system; and (ii) cable landing station (CLS) and ancillary equipment.
The second component, technical assistance (TA) consists of following
sub-components: (i) provision of legal, financial, technical, and
transactional assistance in connection with the drafting and negotiation
of an arrangement for the construction, ownership, and management of
the East Micronesia cable (EMC) to be entered into, between Kiribati,
Nauru, and Federated States of Micronesia (FSM), each acting through
its respective national cable operator on the one hand and the constructor
and other parties (as the case may be) on the other hand; (ii) provision
of legal advisory assistance for the establishment of a Kiribati national
cable service operator, with capacity and resources for the purpose of
operating the EMC and managing all national aspects of the provision
of services to users of the EMC’s capacity in the Recipient’s territory;
(iii) provision of TA to the Communications Commission of Kiribati
(CCK) in the areas of licensing, interconnection and access, and landing
party agreements, including any implementing or ancillary regulatory
instruments ensuring cost‐based, non‐discriminatory, and open access
to capacity; and (iv) provision of information and communication
technologies (ICT) policy and legal technical assistance in connection
with electronic transactions (such as e‐government and e‐commerce) to
facilitate citizens access to and use of broadband services, including for
the development of the legal and regulatory framework to support safe
electricity.
IDA
Grant
20.0 5/31/2017
MARSHALL ISLANDS
19
Country/Document/Project Name
Agency
Amount
(USUS$
millions)
Date of
Approval
❖ Pacific Resilience Project II under the Pacific Resilience Program
The objective of the Second Phase of Pacific Resilience Projects in the
Republic of the Marshall Islands (RMI) is to strengthen early warning
systems, climate resilient investments in shoreline protection, and to
provide immediate and effective response to an eligible crisis or
emergency. There are four components to the project, the first
component being institutional strengthening, early warning and
preparedness. Component one has two sub‐components: (i) institutional
strengthening, central agency capacity building in risk governance, early
warning, and modernization of the NDMO’s facilities (which will be
implemented by RMI); and (ii) NDMO capacity building, and post
disaster needs assessment (which will be implemented by the SPC). The
second component is the strengthening coastal resilience. Component
two is divided into two sub‐components: (a) coastal vulnerability
assessment and protection investments (which will be implemented by
RMI); and (b) strengthening coastal risk planning (which will be
implemented by SPC). The third component is the contingency
emergency response. This government‐led component will include
carrying out a program of activities designed to provide rapid response
to an eligible crisis or emergency, as needed. This Contingency
Emergency Response Component (CERC) may be used following the
declaration of a disaster event. The CERC will complement the PCRAFI
disaster insurance mechanism financed under PREP Phase I and will
strengthen the emergency preparedness and immediate response
capacity of RMI for low‐ and medium‐scale disasters or disasters that
are not covered by the PCRAFI insurance scheme (e.g. flood, drought).
Finally, the fourth component is the project and program management.
Component 4 is divided into two sub‐components: (1) project
Management (which will be implemented by RMI); and (2) program
management (which will be implemented by SPC)
IDA Grant 19.63 05/09/2017
MONGOLIA
❖ Mongolia Export Development Project
The development objective of Export Development Project for
Mongolia is to support Mongolian small and medium size firms (SMEs)
in the non-mining sectors to strengthen their export capabilities and
expand access to export markets. This project has three components as
follows: 1) The firs component, Development of a new line of export
finance products, will provide financial, technical, and institutional
development support to the Agricultural Reinsurance Joint Stock
Company (AgRe) in building a new line of export finance products. It
has the following two subcomponents: (i) knowledge transfer and
capacity building for the Agricultural Reinsurance Joint Stock Company
(AgRe); and (ii) equity injection to AgRe’s Export Insurance
Subsidiary. The second component, Export competitiveness
enhancement, will provide funding for (i) export-related training
programs and (ii) matching grants which would support various
expenditures by exporters directed at enhancing competitiveness of
individual SMEs in global markets. It has two subcomponents as
follows: (i) training and research on foreign trade; and (ii) matching
grants to promote export competitiveness. 3) The third component,
IDA Credit 20.0 7/7/2016
20
Country/Document/Project Name
Agency
Amount
(USUS$
millions)
Date of
Approval
Project Implementation Support, will provide its services for all three
components of the project
❖ Mongolia Employment Support Project
The development objective of Employment Support Project for
Mongolia is to provide jobseekers and micro-entrepreneurs in Mongolia
with improved access to labor market opportunities. This project has
three components. 1) The first component, supporting client-centric
public employment services, aims to address job-search constraints
related to incomplete information and poor labor market transparency
by supporting client-centric public employment services. 2) The second
component, strengthening select active labor market programs, aims to
strengthen the design, relevance, and demand orientation of select active
labor market programs. It has three subcomponents as follows: a)
Integrated employment training program; b) Support for micro-
entrepreneurs; and c) Employment promotion piloting program. 3) The
third component, facilitating labor market monitoring and analysis and
project management, aims to enhance the scope, quality, and availability
of labor market information for institutional and individual users, to
allow them to make informed decisions. It has two subcomponents as
follows: a) Labor market monitoring and analysis; and b) Project
management and monitoring
IDA Credit 25.0 4/27/2017
❖ Strengthening Fiscal and Financial Stability Project
The development objective of Strengthening Fiscal and Financial
Stability Project for Mongolia is to contribute to the government of
Mongolia’s efforts to strengthen fiscal and financial stability and
improve the quality of expenditure management. This project has five
components. 1) The first component, Strengthening Macroeconomic
and Fiscal Management, aims to strengthen fiscal responsibility and
support the implementation of relevant policy measures toward (a)
improving the quality of expenditure management, (b) strengthening
macroeconomic and budget policy-making capacity, and (c) improving
regulatory processes. It has the following three subcomponents: (i)
Improving macroeconomic policy tools and enhancing research
capacity; (ii) Strengthening fiscal policy and planning; and (iii)
Strengthening capacity for debt management and external development
financing operations. 2) The second component, Improving the
Efficiency of Public Financial Management, aims to improve fiscal
discipline by strengthening the country’s PFM and enhance the quality
of expenditures by revamping PIM and fostering activities aimed at
increasing transparency and accountability. It has the following four
subcomponents: (i) Improving budget credibility, predictability, and
execution for better delivery of services; (ii) Increasing budget
comprehensiveness and transparency through better control, reporting,
and expansion of the recipient’s Integrated Financial Management
Information System capabilities; (iii) Strengthening the public financial
management institutional capacity; and (iv) Strengthening Public
Investment Management. 3) The third component, Enhancing Financial
Sector Stability, aims to support the MOF, BOM, FRC, DBM, and
DICOM to strengthen the resiliency of the Banking system. It has the
following five subcomponents: (i) Developing and implementing a
financial sector development.
IDA Credit 12.0 6/9/2017
WBG
IDA Credit 42.0 6/15/2017
21
Country/Document/Project Name
Agency
Amount
(USUS$
millions)
Date of
Approval
PAPUA NEW GUINEA
❖ Water Supply and Sanitation Development Project
The development objective of Water Supply and Sanitation
Development Project for Papua New Guinea is to support the
development and strengthening of the planning and implementation
capacity of water sector institutions, and to increase access to water
supply services in selected urban towns and rural districts. There are
four components for this project. 1) The first component, Institutional
structures for the implementation of the National WaSH Policy, focuses
on supporting the development of the key sector institution i.e., the
WaSH Project Management Unit (PMU), and key sector tools
(strategies, plans and sector instruments) that will form the management
framework of the sector as envisaged in the National WaSH Policy. It
has the following two subcomponents: (a) Support to the establishment,
operationalization and strengthening of the WaSH PMU; and (b)
Support to the development and/or implementation of key sector tools.
2) The second component, Rural and Peri-urban Water and Sanitation,
will support the WaSH PMU to develop a framework for the
coordination, planning and implementation of rural and peri-urban WSS
in districts and in peri-urban areas. It has the following two
subcomponents: (a) Investment planning, design, and financing
structures for rural and peri-urban WSS; and (b) Infrastructure
investment in water and sanitation systems in rural and peri-urban areas.
3) The third component, Urban Water and Sanitation, focuses on
supporting the expansion of WSS services to urban areas, specifically in
district and provincial towns where Water PNG has the mandate to
provide these services. It has the following two subcomponents: (a)
Operational improvement and capacity building of Water PNG; and (b)
Infrastructure investment in water and sanitation systems in selected
District and or Provincial Towns. 4) The fourth component, Contingent
Emergency Response (CER).
IDA Credit 70.0 02/09/2017
❖ Emergency Tuberculosis Project
The objective of the Emergency Tuberculosis Project is to improve the
quality and expand the coverage and utilization of health services to
control the spread of tuberculosis in targeted areas of Papua New Guinea
by strengthening programmatic management of tuberculosis. There are
three components to the project, the first component being early
detection of active tuberculosis patients. The IDA credit will finance the
implementation of ACF strategies, which have been developed for
Western Province and are also included in the NCD TB plan. Financing
will be provided for procurement of diagnostic medical devices and
consumables, technical assistance, and other eligible expenditures
deemed necessary for the early detection of active TB patients. The
second component is the effective treatment of drug-susceptible and
drug-resistant tuberculosis patients. The project will support the
effective treatment of both DS and DR TB patients, including the new
short regimen for DR TB patients, through three subcomponents:
improving clinical management of DS TB and DR TB; strengthening
the directly observed treatment implementation and reduce the loss of
follow up of patients in the BMUs; and supporting social mobilization
IDA Credit 15.0 5/31/2017
22
Country/Document/Project Name
Agency
Amount
(USUS$
millions)
Date of
Approval
in targeted areas. Finally, the third component is the strengthen the
recipient’s systems for managing its health services delivery and
tuberculosis response.
❖ Rural Services Delivery Project
The development objective of the Rural Service Delivery Project for
Papua New Guinea is to improve communities' access to basic
infrastructure and services in targeted rural areas using inclusive,
participatory planning, and implementation. The project comprises of
three components. The first component, preparation and implementation
of sub‐projects consists of following sub-components: (i) ward
development grants; and (ii) subproject preparation and implementation
support grants. The second component, capacity building of national
and sub‐national entities will support the strengthening of capacities of
national and sub‐national government entities as well as community
members to manage and implement subprojects, and to improve local
governance as it relates to basic service delivery. The third component,
project management will finance incremental costs of the implementing
agency for project management, specifically coordination and
supervision of implementation activities, financial management, annual
audits, and monitoring and evaluation.
IDA Credit 23.0 6/09/2017
❖ PNG Tourism Sector Development Project
The objective of the Tourism Sector Development Project for Papua
New Guinea is to improve tourism services in targeted destinations.
There are three components to the project, the first component being
institutional and policy frameworks. This component will seek to raise
the standard of government entities integral to establishing and growing
an effective tourism sector. Institutional strengthening and integrated
planning at the national level, the provincial level (in East New Britain
and Milne Bay), and the local level (in Kokopo, Rabaul and Alotau),
will enable entities to carry out key priorities such as: improved
destination planning and management; marketing and promotion;
skilled workforce development and capacity building; product
development; sustainable site management of tourism assets; and
performance monitoring and evaluation activities. Support will ensure
that all planning, design, implementation and monitoring activities are
done in an inclusive and gender-sensitive manner. The second
component is the infrastructure and community/product development.
This component will support the development of integrated tourism
destinations in Milne Bay and East New Britain, as identified in the
provincial tourism strategies. The implementation of the vision laid out
in the tourism strategies will require small-scale/site-specific
improvements or rehabilitations that do not affect areas broader than the
sites, and direct support to community led enterprises. Finally, the third
component is the project management. This component will support the
project implementation, including procurement, financial management,
safeguards compliance, preparation of feasibility studies and details
design and construction supervision. In doing so, this component will
support the establishment of a project implementing entity in TPA,
headed by a project manager, together with two provincial coordinators.
IDA Credit 20.0 6/09/2017
23
Country/Document/Project Name
Agency
Amount
(USUS$
millions)
Date of
Approval
SAMOA
❖ Second Fiscal and Economic Reform Operation
The development objectives of Second Fiscal and Economic Reform
Operation Project for Samoa (i) to improve fiscal management in the
areas of debt, procurement and revenue; (ii) to strengthen the payments
system, tourism sector policy and private sector development
opportunities as foundations for more robust economic growth over the
medium term, and (iii) to strengthen the monitoring, reporting, and
coordination of climate resilience activities in Samoa, as an important
step toward increasing its resilience to the effects of climate change. The
first development objective of the proposed operation is to strengthen
public financial management in the areas of debt, procurement and
revenue. The three reform areas that contribute to this objective are
strengthening debt policy and management, strengthening public
procurement processes to improve value for money in expenditure, and
strengthening revenue collection. These reforms should assist the
government to consolidate its public finances and rebuild the fiscal
buffers it needs to respond to future external shocks. The second
development objective of the proposed operation is to strengthen the
payments system, tourism sector policy and private sector development
opportunities as foundations for more robust economic growth over the
medium term. The three areas that contribute to this objective are
reforms to modernize the payments system, strengthen the sector policy
for the critical tourism industry, and increase opportunities for private
participation in the large state-owned enterprise sector. The third
development objective of the proposed operation, which is new to the
programmatic series, is to strengthen the monitoring, reporting, and
coordination of climate resilience activities in Samoa, as an important
step toward increasing its resilience to the effects of climate change.
IDA Credit 5.0 9/13/2016
SOLOMON ISLANDS
❖ Rapid Employment Project Additional Financing
The objective of the Rapid Employment Project for Solomon Islands
was to assist targeted vulnerable urban populations in the Recipient’s
territory to: (i) increase their incomes through the provision of short term
employment; and (ii) improve their knowledge, experience and basic
employment skills that are valued in the workplace and society. The
Additional Financing (AF), which will be the Second Additional IDA
Grant, will be used to support an ongoing, well-performing project. It
will support the continuation of project activities for a further 24
months, scale up certain components of the project, and help to improve
its overall development effectiveness and the sustainability of project
impacts. The AF will help to scale up the project’s components one and
two, which will help to improve developmental effectiveness and
sustainability. Specifically, the AF will generate additional short-term
employment and extend mentoring and referral services for job seekers
and vulnerable urban groups, including women and youth; and maintain
improved public service provision and access to services and markets
through the rehabilitation of tertiary roads. In addition, and in
IDA Grant 1.90 11/18/2016
24
Country/Document/Project Name
Agency
Amount
(USUS$
millions)
Date of
Approval
accordance with the existing Project Development Objective (PDO), the
AF will provide a small amount of financing to facilitate preparatory
activities, including carrying out pilot activities in Guadalcanal, which
will help to generate lessons on the provision of urban services and labor
-intensive sub-projects in a low capacity environment with community
participation, and to support preparatory work for such pilot activities in
one other high growth urban location outside of Honiara. The
information and experience is expected to inform the preparation of a
REP Phase II operation, currently under discussion with the SIG.
❖ Tina River Hydropower Development Project
The development objective of the Tina River Hydro Development
Project (TRHDP) is to increase the share of renewable energy through
hydropower in Solomon Islands. The WBG has mobilized a range of
resources and instruments to enable the Government to attract an
experienced international hydropower developer to construct and
operate the hydropower facility (HPF), and to enhance the quality and
viability of the Project. The TRHDP will consist of four components: (i)
HPF; (ii) access road; (iii) transmission lines; and (iv) technical
assistance (TA). In terms of timing, the TA component is expected to
begin first in order to maintain continuity of the TRHDP Project Office
(PO) with the preparation phase and to support the other project
components.
IDA Credit 23.4 6/20/2017
❖ Electricity Access Expansion Project
The objective of the Electricity Access Expansion Project is to increase
access to electricity services in low-income areas of Solomon Islands. A
summary of the project components follows: USUS$2.125 million to
cover a portion of the upfront cost of electricity service connections for
2,565 households to the Honiara grid and outstations through pre-paid
metered connections. This includes materials and installation of the
service line and auxiliary pole, when needed; a pre-paid meter; and in-
house wiring including protection, earthling, and two LED light bulbs.
USUS$100,000 for implementation support for project management
throughout the Output Based Aid (OBA) program to manage its
implementation, including: (a) procuring materials for service lines and
in-house wiring; (b) hiring licensed electrical contractors to perform in-
house wiring; (c) managing distribution of materials; (d) administering
or managing payments to suppliers and electrical contractors; (e)
reporting to IVA and the bank; and (f) other related activities.
Component three: USUS$75,000 for independent verification of outputs
to verify and recommend payment of OBA subsidies to Solomon Power
for electricity service connections delivered. This component will be
WBG-executed
GPOBA
Grant
2.22 7/20/2016
TUVALU
❖ Third Development Policy Operation (DPO)
The operation is aimed at supporting the reform agenda of the
Government of Tuvalu (GoT) in the critical areas of: (a) improving
social service delivery and (b) building macroeconomic sustainability.
Building human capital is a key pillar to the national development
strategy and fostering access to economic opportunities and public
services has been identified by the Systematic Country Diagnostic
IDA Grant 3.3 12/09/2016
25
Country/Document/Project Name
Agency
Amount
(USUS$
millions)
Date of
Approval
(SCD) as an area of priority action for reducing poverty and boosting
shared prosperity. The reforms in this area are in turn focused on
enhancing inclusiveness and equity of secondary education and
supporting improved health sector outcomes and its financing
sustainability. The national development strategy and SCD also
reiterated that exogenous shocks create poverty traps, which are
amplified by weaknesses in macroeconomic management. Building
resilience to shocks and sustainability is particularly important to
Tuvalu, in light of the Global Financial Crisis (GFC) and the recent
Tropical Cyclone (TC) Pam, which resulted in losses exceeding 15
percent of gross domestic product (GDP) in the Tuvalu Trust Fund
(TTF) and damage and losses exceeding 30 percent of GDP. To mitigate
against this, the reforms under the second pillar of the operation are
focused on improving macroeconomic sustainability by strengthening
investment management of reserve assets, which will be complemented
by reforms to improve the effectiveness of payroll controls, and
increasing oversight on the Banking sector. Financing provided through
this proposed operation will not only support the maintenance of buffers
and meet long-term financing needs, but more importantly focus on the
reform agenda while sustaining the reform momentum built through the
previous operations.
VANUATU
❖ Vanuatu Aviation Investment Project Additional Financing
The development objective of the Aviation Investment Project for
Vanuatu is to improve operational safety and oversight of international
air transport and associated infrastructure in Vanuatu. The additional
financing will be used for additional activities in two components: (i)
international airport infrastructure investments to invest in international
aviation infrastructure to meet and maintain minimum International
Civil Aviation Organization (ICAO) safety and security standards at
Vanuatu’s three international airports: Bauerfield, Whitegrass, and
Pekoa airports; and (ii) project implementation support finance to the
complexity and intensified urgency of the project resulting from recent
delays.
IDA
Grant/Credit
14.1 1/10/2017
❖ Rural Electrification Project Stage II
The objective of the Second Rural Electrification Project Stage Project
is to support increased penetration of renewable energy and increased
access to electricity services in the dispersed off-grid areas of Vanuatu.
There are three components to the project, the first component being
provision of solar home systems and micro grids systems in rural areas
of Vanuatu. This component will support expansion of access to reliable
electricity service in rural Vanuatu through SHS and micro grid
configurations where mini grid configurations are unlikely to be
economically viable and which are not earmarked for mini grids under
this or other donor or government projects or are the least cost solution.
SHS and micro grids will be available to rural households and public
institutions. This component will target approximately 37 public
institutions and 8,400 rural households, which equates to approximately
42,000 people. The second component is the Construction of Mini Grids
systems in rural areas of Vanuatu. This component will support the
expansion of access to reliable electricity services for rural communities
IDA
Grant/Credit
4.0 5/31/2017
26
Country/Document/Project Name
Agency
Amount
(USUS$
millions)
Date of
Approval
through support for the design, supply, installation and commissioning
of mini grid systems. The project will finance the construction of five
mini grids, based on initial cost estimates. Finally, the third component
is the technical assistance and project management. This component
addresses three key areas of the project, the first focusing on the vendor
registration model for Component one, the second focusing on owners’
engineer for component two and the third focusing on project
management. In addition, there is an allowance for Government
contribution (USUS$1.5 million ‘in kin’”) that will cover the
Government of Vanuatu’s direct project related
27
ANNEX 2 – GOVERNORS’ RESOLUTIONS
No. RESOLUTION TITLE DATE
IBRD
649 2016 Regular Election of Executive Directors July 28, 2016
650 Direct Remuneration of Executive Directors and their Alternates July 28, 2016
651 Parental Leave for Executive Directors and their Alternates July 28, 2016
652 Financial Statements, Accountants’ Report and Administrative Budget October 7, 2016
653 Allocation of FY16 Net Income October 7, 2016
654 Forthcoming Annual Meetings of the Boards of Governors – Proposed
Dates for the 2019 and 2020 Annual Meetings in Washington D.C. April 28, 2017
655 Transfer from Surplus to Replenish the Trust Fund for Gaza and the West
Bank September 8, 2017
656 Direct Remuneration of Executive Directors and their Alternates September 13, 2017
657 Child Planning Benefit for Executive Directors and their Alternates September 13, 2017
IDA
238 Financial Statements, Accountants’ Report and Administrative Budget October 7, 2016
239 Additions to Resources: Eighteenth Replenishment March 31, 2017
IFC
263 Financial Statements, Accountant’s Report, Administrative Budget and
Designations of Retained Earnings October 7, 2016
MIGA
99 2016 Regular Election of Directors July 28, 2016
100 Financial Statements and the Report of Independent Accountants October 7, 2016
101 Increase in Overall Limit on Guarantee Capacity November 11, 2016
102 Periodic Review of MIGA FY11-FY16Q3 January 27, 2017
* While most Constituency members are quick to respond to a request for a vote from Governors, our office continues to be concerned about a
number of Constituency members who have difficulty in returning their vote and /or do not take the opportunity to vote.
28
ANNEX 3 – CONSULTATIONS WITH CONSTITUENTS IN FY17
Annual
Meetings
DC
Spring
Meeting
DC
Country
Visits
FY17
(Dates)
EDs’ Group
Trip to ECA
Region
(Serbia,
Kosovo and
Albania)
JEMFAC
(Joint
Economic
Management
and
Financial
Acco.)
IDA Deputy
EU ++
Meeting
(Slovakia)
IDA18
Meeting
(Indonesia)
Australia x x
x
Mar 25-Apr 2,
2017
x
Apr 4-8,
2016
x
Sep 28-29,
2016
x
Dec 13-15,
2016
Cambodia x x
x
May 8-11,
2017
Kiribati x x
Korea x x
x
Jul 23-27,
2016; Aug
30, Sep 3,
11-12; Nov
13-19, 2016
Marshall
Islands x x
x
Mar 8-10,
2017
Micronesia
(FSM) x
x
Sep 7-10,
2016; Mar
3-6, 2017
Mongolia x x
x
Aug 31-Sep
2, 2016;
May 1-3,
2017
Nauru x x
New Zealand x x
Palau x
x
(Sep 4-6,
2016)
Papua New
Guinea x x
29
Annual
Meetings
DC
Spring
Meeting
DC
Country
Visits
FY17
(Dates)
EDs’ Group
Trip to ECA
Region
(Serbia,
Kosovo and
Albania)
JEMFAC
(Joint
Economic
Management
and
Financial
Acco.)
IDA Deputy
EU ++
Meeting
(Slovakia)
IDA18
Meeting
(Indonesia)
Samoa x x
Solomon
Islands x x
Tuvalu x
Vanuatu x x
30
ANNEX 4 – WBG ORGANIZATIONAL STRUCTURES